2016-2021 Transportation Improvement Program

DENVER REGIONAL COUNCIL OF GOVERNMENTS
We make life better!
2016-2021
Transportation Improvement Program
(As Adopted April 15, 2015 )
2016-2021
TRANSPORTATION IMPROVEMENT PROGRAM
April 15, 2015
Denver Regional Council of Governments
1290 Broadway, Suite 700
Denver, Colorado 80203
Preparation of this report has been financed in part through grants from the
U.S. Department of Transportation, Federal Transit Administration
and Federal Highway Administration
ABSTRACT
TITLE:
2016-2021 Transportation Improvement Program
AUTHOR:
Denver Regional Council of Governments
SUBJECT:
Six-year multimodal transportation program
DATE:
Adopted $SULO, 2015
TIP AMENDMENTS:
This document describes the 2016-2021 Transportation
Improvement Program as adopted on $SULO, 2015.
SOURCE OF COPIES:
Public Information and Communications
DRCOG
1290 Broadway
Suite 700
Denver, Colorado 80203
(303) 455-1000
NUMBER OF PAGES: ̀
21
ABSTRACT:
The Transportation Improvement Program identifies all
federally funded surface transportation projects
anticipated for funding in the Denver metropolitan area
during fiscal years 2016-2021. This multimodal program
includes highway, high-occupancy vehicle, transit, travel
demand management, and non-motorized facilities and
services.
ii
TABLE OF CONTENTS
Introduction
................................................................................................................... 1
Regional Needs ....................................................................................................... 2
Federal Requirements ............................................................................................. 4
Investment Decision Process .................................................................................. 6
The 2016-2021 Program ................................................................................................. 13
Project Descriptions ...................................................................................................... 19
APPENDIX A TIP Project Funding Summary ............................................................ 137
APPENDIX B Major Projects in the 2012-2017 Transportation Improvement
Program Not Yet Completed ............................................................. 189
Rollover List ....................................................................................... 189
APPENDIX C Lookup List of Projects ................................................................... . 193
APPENDIX D Regionally Significant Projects Not Supported by Federal Funds .. 209
APPENDIX E Waiting List ........................................................................................... 215
APPENDIX F Governor’s Approval ........................................................................... 219
iii
LIST OF TABLES
Table 1. Estimated 2012-2017 Revenues for DRCOG TIP Region ................................... 5
Table 2. 2016-2021 Transportation Improvement Program Project List ........................... 15
Table 3. Regionally Significant Projects Included in the 2016-2021 TIP .......................... 18
Table 4. Eligible Projects for Waiting List(s) for the 2016-2021 TIP .............................. 198
(To be completed at a later date)
LIST OF EXHIBITS
Exhibit 1
Project Descriptions ........................................................................................ 19
LIST OF FIGURES
Figure 1 Geographic Area of the Transportation Improvement Program..........................1
Figure 2 RTP and TIP Relationship ..................................................................................3
Figure 3 Denver Region Transportation Investment Decision Process ............................8
Figure 4 2016-2021 Transportation Improvement Program Project Locations ............... 14
iv
Introduction
This Transportation Improvement Program (TIP) identifies federally-funded surface
transportation projects to be implemented in the Denver region from fiscal years 2016
through 2021.
The Denver Regional Council of Governments (DRCOG), the region’s Metropolitan
Planning Organization (MPO), is responsible for the preparation of the TIP in
cooperation with local governments, the Colorado Department of Transportation
(CDOT), and the Regional Transportation District (RTD). The geographic area covered
by the TIP includes all or portions of Adams, Arapahoe, Boulder, Broomfield, Denver,
Jefferson, Douglas, and Weld counties as shown in Figure 1.
Figure 1 Geographic Area of the Transportation Improvement Program
1
Projects are selected through a cooperative process, considering submittals from local
governments, CDOT, and RTD. A further description of how TIP projects are selected
is presented later, in the Investment Decision Process section. Regional policy 1
provides the basis for the evaluation and ranking of DRCOG-selected projects. The
2016-2021 TIP was approved by the DRCOG Board of Directors on $SULO.
The TIP is intended to fulfill the following purposes:

To serve as a short-range implementation tool to address the goals of the regional
long-range transportation plan.

To provide continuity of current transportation improvement projects with those
identified in previous TIPs.

To identify transportation projects recommended for implementation by
transportation mode, type of improvement, funding source(s), and geographic area.

To estimate the costs of projects proposed for federal funding. The project
allocations are to be consistent with the federal funds reasonably anticipated to be
available for such projects in the area.

To establish a prioritization of projects to effectively utilize federal funds as they
become available.

To identify and implement transportation improvements which will maintain the system;
improve safety; improve air quality and reduce greenhouse gas emissions; reduce
vehicle miles traveled (VMT) and congestion; and enhance the transportation system.
Regional Needs
Transportation projects support the currently-adopted Metro Vision 2035 Plan (Metro
Vision), the regional vision to address future growth. Metro Vision defines a balanced
multimodal transportation system that provides mobility and accessibility for people and
goods, and contains three key goals for 2035:

Reduce the percent of trips made to work by single occupant vehicle to 65%

Reduce the regional per capita VMT by 10%

Reduce annual per capita greenhouse gas emissions from the transportation sector
by 60%
1
Policy on Transportation Improvement Program Preparation, Adopted July 16, 2014 by the Denver Regional Council
of Governments Board of Directors.
2
This TIP is also based on the policy direction received to date for the Metro Vision 2040
Plan and the 2040 Metro Vision Regional Transportation Plan (2040 MVRTP) which will
be adopted in mid-2015. It is consistent with the Fiscally Constrained 2040 Regional
Transportation Plan (RTP) and identifies the regionally significant projects in the RTP
scheduled to receive federal surface transportation revenues over the next six years.
Figure 2 graphically shows the relationship between the Metro Vision Regional
Transportation Plan (MVRTP), the Fiscally Constrained RTP, and the Transportation
Improvement Program.
Transportation projects in the 2016-2021 TIP support all the elements of Metro Vision,
and address other transportation issues including congestion management, safety,
multimodal transportation options, regional sustainability, and asset management.
Figure 2 RTP and TIP Relationship
3
Federal Requirements
Conformity Finding
The impact of transportation on the Denver region’s air quality is a component of
DRCOG’s regional planning efforts. Under Section 176(c) of the Clean Air Act, as
amended in 1990, MPOs are required to show conformity of its TIP with the State
Implementation Plan (SIP) for air quality before it can be adopted.
The 2016-2021 TIP is consistent with air quality conformity requirements by assuring all
regionally significant capacity projects are contained within the applicable stage of the
adopted 2040 RTP. The following technical documents which present the conformity
findings can be found on DRCOG’s website:

DRCOG CO and PM-10 February 2015 Conformity Determination

Denver Southern Subarea 8-Hour Ozone February 2015 Conformity Determination
Financial Constraint
The 2016-2021 TIP is financially constrained and demonstrates, as summarized in
Table 1, that projects listed from 2016 to 2019 can be implemented using anticipated
revenues (i.e., projects are within committed or reasonably expected funding levels).
Most of the funds for the last two years of the TIP (2020-2021) remain unprogrammed
for specific projects. The funds will be fully programmed in the next TIP.
Appendix A expands this table by presenting funding information by individual project.
It shows TIP projects by funding category over the six years of the TIP (collectively for
2020-2021). Prior (before 2016), future (after 2021), and total funding is also displayed
in most instances. The totals for each funding source are shown for comparison with
available resources. Additional information on the projects is available later in this
section, which includes project descriptions.
As these funds are programmed by the respective agencies, DRCOG is responsible for
assuring the projects meet Metro Vision objectives, are consistent with the RTP, and
that the program is fiscally constrained. The DRCOG Board of Directors then adopts
the TIP document and the projects are implemented.
4
Table 1
FY2016-2019 Programmed Funding for DRCOG TIP Region
(dollars in thousands)
Funding Sources
2016
CDOT Programmatic Categories (2)
Bridge Off-System
Bridge On-System
Federal Emergency
FASTER Bridge Enterprise
FASTER Safety
Intelligent Transportation Systems
RAMP
Safety
Surface Treatment
Regional Priority Program (RPP)
Transportation Alternatives Program (TAP)
Sub-Totals
DRCOG Federal Allocation Categories (1) (2)
STP-Metro
Transportation Alternatives Program (TAP)
Congestion Mitigation/Air Quality (CMAQ)
Sub-Totals
Federal and Local Transit Categories (2)
Section 5307 Urban Formula
Section 5309 New Start
Section 5337 State of Good Repair
Section 5339 Capital Improvements
Innovative Transit Workforce Development Program
RTD Funds Only
Sub-Totals
Additional Match (i.e., local)
Grand Total Programmed
TIP Programmed
2017
2018
0
14,802
37,603
19,080
36,880
0
64,772
21,098
69,580
19,135
2,366
285,316
0
19,220
11,161
756,324
13,770
9,494
40,875
12,913
67,380
25,351
2,032
958,520
624
9,472
2,444
17,000
19,869
7,400
40,000
5,413
54,180
25,893
0
182,295
36,347
2,282
29,626
68,255
28,789
1,949
26,502
57,240
29,909
2,814
33,252
65,975
56,221
257,000
11,000
5,209
487
446,287
776,204
56,793
192,706
11,000
5,261
0
286,507
552,267
57,372
71,892
11,000
5,314
0
76,308
221,886
39,660
41,133
39,888
1,169,435 1,609,160
510,044
Notes:
1) Based on CDOT OFMB 2040 Revenue Forecast and Resource Allocation (August 2014).
Includes rollover funds from previous TIP.
2) Excludes matching funds
5
2019
Total
2016-2019
0
624
0
43,494
0
51,208
54,773
847,177
20,149
90,668
0
16,894
0
145,647
413
39,837
55,400
246,540
13,425
83,804
0
4,398
144,160 1,570,291
36,162
3,359
36,038
75,559
131,207
10,404
125,418
267,029
57,956
228,342
1,141
522,739
11,000
44,000
5,367
21,151
0
487
1,315
810,417
76,779 1,627,136
62,000
182,681
358,498 3,647,137
Project Management
The implementation status of major projects funded in the previous 2012-2017 TIP, but
not yet completed, is presented in Appendix B. It shows major projects (total cost
greater than $5 million) anticipated in the 2012-2017 TIP to be completed by 2015, for
which funds have been obligated but construction is not yet substantially complete (in
other words, the project is still under construction). It also lists major projects from the
2012-2017 TIP that have been substantially delayed, such that major elements have
been moved into the 2016-2021 TIP horizon.
Appendix B also lists all projects from previous TIPs that were originally scheduled to be
obligated in fiscal year 2015 or earlier, but did not meet that timeline. While these
projects were not obligated, CDOT will reserve past obligation authority for them. The
other projects from the 2012-2017 TIP not listed have been implemented or are
currently being implemented.
Public Involvement
Public involvement is a continuous process for DRCOG. The TIP project selection
considers the concerns of affected citizens at both local and regional levels. Citizen
involvement is most significant at the local level as projects are developed for submittal
to DRCOG for regional review. Local governments and agencies such as CDOT and
RTD, work directly with citizens in the development of transportation projects. In
shaping public involvement programs, local governments often consider the size of their
community, level of public awareness about transportation issues, and involvement of
community based organizations. Setting realistic goals and ensuring accountability
between local officials and community organizations promotes successful public
involvement activities.
Public notice of public involvement activities and time established for public review and
comment on the TIP will satisfy the Program of Projects requirements of the FTA
Section 5307 Program for RTD’s Program of Projects.
A public hearing was conducted on TIP project selection at the DRCOG Board meeting
on March 18, 2015. Members of the public had the opportunity to testify verbally at the
hearing or in writing during the preceding 30-day comment period.
Investment Decision Process
Investment decisions for selecting transportation projects to be funded are made by
6
DRCOG, CDOT, RTD, and local agencies through the MPO planning process. Figure 3
illustrates the process that results in a TIP. Decisions begin by identifying federal, state,
and local revenue sources available in specific funding categories. DRCOG, RTD, and
CDOT follow their own specific project selection procedures and federal guidelines for
selecting projects to be included in the regional TIP.
The Federal Highway Trust Fund and General Revenue funds are appropriated by
Congress and distributed to either the Federal Highway Administration (FHWA) or the
Federal Transit Administration (FTA).
By law, Colorado Highway Users Tax fund revenues flow annually to CDOT and local
governments. State general fund revenues have been forecast to flow to CDOT per the
triggers of SB 09-228. The CDOT Transportation Commission combines state and
federal revenue sources into different investment categories. CDOT submits selected
projects to DRCOG for inclusion in the TIP in several program areas such as: Strategic
Projects, Regional Priority Program, Congestion Relief Program, Bridge, Responsible
Acceleration of Maintenance and Partnerships (RAMP), Transportation Alternatives
Program (TAP), Funding Advancements for Surface Transportation and Economic
Recovery Act of 2009 (FASTER), and Safety. Surface Treatment is listed in the TIP as
a pool. SB09-108 (FASTER) created the Colorado Bridge Enterprise and the High
Performance Transportation Enterprise. Projects from those enterprises are listed
under appropriate CDOT program areas.
Most FTA funds are allocated to the Regional Transportation District (RTD) through
formula grants and discretionary new starts, new bus, and fixed guideway categories.
Other sources of RTD funds are sales and use taxes, fare box collection, and
miscellaneous revenues. The RTD Board of Directors, through the adoption of the
annual six-year Strategic Business Plan, sets priorities for RTD capital improvements.
RTD submits the selected projects to DRCOG for inclusion in the TIP.
DRCOG selects projects through its MPO committee process for Transportation
Alternatives Program (TAP), Surface Transportation Program-Metro (STP-Metro), and
Congestion Mitigation/Air Quality (CMAQ) federal funding categories. DRCOG also lists
in the TIP local government-funded projects that require a federal approval. DRCOG
only allocates a maximum of four years of funding for projects it selects.
7
Figure 3 Denver Region Transportation Investment Decision Process
8
DRCOG TIP Selection Process
In selecting projects, DRCOG committees follow eligibility and evaluation criteria
defined in the Policy on Transportation Improvement Program Preparation, originally
adopted by the Board of Directors on July 16, 2014 (Preparation Policy). The
Preparation Policy is amended as needed. It is available here.
In August 2014, DRCOG issued a call for projects for the 2016-2021 TIP. Application
instructions and details were available through the DRCOG website, and DRCOG staff
provided data and assistance to local governments. Project sponsors submitted
applications to DRCOG in September 2014. Projects for which DRCOG has selection
responsibility (CMAQ, STP-Metro, and TAP) were reviewed for eligibility, scored, and
then ranked based on the Preparation Policy.
DRCOG selected TIP projects in two phases. In the first phase, new projects were
selected directly from ranked lists of projects by score. A maximum of 75 percent of
available funding was allocated to projects based on funding targets set for each project
type category.
In the second phase, the DRCOG Board approved a policy to place additional emphasis
during deliberations on projects from Very Small Communities 2 and in “under-equity”
counties as defined by the County Funding Equity Status and Ratio criterion. Other
criteria considered included TIP Score, Multi-jurisdictional projects, Projects Not Eligible
in First Phase, Number of Projects Selected in First Phase, First-Last Mile Connection.
Projects selected in second phase were funded with the remaining amount.
The following is a description of the allocation of funding types as part of the DRCOG
project selection process:
STP-Metro
The available STP-Metro federal funding for the DRCOG area is estimated to be $131.2
million for both previous and new TIP commitments, as well as new projects in 20162019. This amount includes $10 million of funding carried over from FY 2015.
While $17.5 million of the STP-Metro was allocated to previous commitments and setasides, the remaining $113.7 million in STP-Metro funds were directed to new projects
in six project types: roadway reconstruction, roadway operational improvements,
roadway capacity, transportation-related studies, transit (operational and passenger
facilities), and bicycle/pedestrian. Twenty-five “new” projects were selected for the
2016-2021 TIP:
2
Very Small Communities is defined as communities with less than $10 million in annual net sales tax value (based
on the most recent data from the CO Dept. of Revenue).
9
 5 roadway capacity
 2 roadway operational improvements
 4 roadway reconstruction
 9 transportation studies
 4 bicycle/pedestrian
 1 transit passenger facility
Congestion Mitigation/Air Quality (CMAQ)
The available CMAQ federal funding for the DRCOG area is estimated to be about
$125.4 million for TIP commitments and new projects in 2016-2019. This amount
includes $8.8 million of funding carried over from FY 2015.
$48.4 million was allocated to previous commitments and set-asides. The remaining
$77 million in CMAQ funds were directed to new projects in four project types: Transit,
Bicycle/Pedestrian, Roadway Operational, and air quality. Seventeen “new” projects
were selected for the 2016-2021 TIP:
 1 air quality
 8 bus service projects
 5 bicycle/pedestrian
 1 roadway reconstruction (to be used on eligible portions of the project only)
 2 roadway operational improvements
Transportation Alternatives Program (TAP)
The available TAP federal funding sub-allocated to the DRCOG area is estimated to be
about $10.4 million for new projects in 2016-2019. DRCOG used its allocation to select
eight new bicycle/pedestrian projects in the 2016-2021 TIP.
Potential Additional Funds
Additional STP-Metro, CMAQ, or TAP funds may become available to DRCOG for
programming in fiscal years 2016 through 2019, for example through project close-outs or
year-end funding reconciliations. In that event, funding for projects identified in the TIP will
be advanced, with the concurrence of the sponsor. The project evaluation score for new
2016-2021 projects will be used as the priority basis for advancing project funding.
If additional funds still remain, “new” projects may be selected from among those on
10
waiting lists. The waiting lists will be prepared following adoption of the TIP.
CDOT TIP Selection Process
CDOT has primary responsibility for selecting projects that use federal National
Highway System, Bridge, Interstate Maintenance, Safety, TAP (that are not MPO
allocated), Transit Small Urban and Rural, and Elderly/Disabled funding. CDOT also
has primary responsibility for selecting projects to be funded through the Colorado
Transportation Commission’s “Regional Priority Programs”, “Congestion Relief
Program”, and “FASTER Programs”, which include state funds and some of Colorado’s
share of federal surface transportation funds. The Transportation Commission also
selects projects in the Strategic Projects Implementation Program and the Bridge
Enterprise Board selects projects using FASTER bridge funds. CDOT held county
meetings per their Project Priority Programming Process to receive comments and
suggestions, prior to selecting projects.
For projects that are not regionally significant from an air quality modeling perspective,
CDOT has adopted a philosophy for the Statewide TIP of displaying such funds in
pools. For small pools such as Hot Spots, Safety Enhancements, and Traffic Signals,
CDOT will not identify the specific projects to use those pool funds. For pools allocated
entirely to CDOT (such as bridge on-system, FASTER safety, and surface treatment),
the 2016-2021 TIP simply lists the projects CDOT intends to fund, at such a time as
those decisions are made. For pools such as hazard elimination or bridge off-system,
where sponsors may be entities other than CDOT, the 2016-2021 TIP will identify
specific projects at such a time as the decisions are made.
RTD TIP Selection Process
In November 2004, voters in the RTD service area endorsed a multi-billion dollar transit
implementation program called FasTracks by approving a 4/10 cent sales tax increase.
The current FasTracks financial plan approved in 2014 assumes a variety of funding
sources beyond the regional sales tax, including federal funds (new starts, earmarks,
and CMAQ/STP-Metro funds) and local contributions. While federal law does not
mandate that RTD include non-federally-funded projects “in” the TIP (such projects are
required to be included in the air quality conformity finding), RTD is including the
FasTracks corridor projects in the 2016-2021 TIP, as with previous TIP’s, recognizing
that the eventual mix of corridor implementation funds may ultimately include some
federal funding.
RTD has primary responsibility for selecting projects in the Transit Formula and
Discretionary Grants (Fixed Guideway, New Bus, and New Starts) federal funding
categories. RTD ensures that all projects are in one of its two Strategic Business Plans
11
(SBP) and have fiscal support. The SBPs are six-year overviews of the operating and
capital improvement programs for RTD. One is specific to FasTracks, the other to the
non-FasTracks RTD services. They are updated and published annually and are
fiscally constrained.
RTD includes projects in the SBP by considering current and future service needs and
the capital improvements required to sustain those needs, and the revenue resources
available. The SBPs are developed with input from RTD departments and local
governments. In the final stage of adoption, the SBPs are approved by the RTD Board
in an open meeting process.
Besides the FasTracks projects, the TIP reflects other SBP projects using federal funds.
To identify the projects to be included in the TIP, RTD considers both SBP project
priority and estimates of historical federal funding levels. Except for FasTracks, RTD
does not submit for inclusion in the TIP other construction or operational projects, that
are funded solely with regionally-derived revenues. As such, the reader is encouraged
to contact RTD directly for a copy of its SBP in order to gain a complete picture of public
transit expenditures.
Interagency Coordination
While the three agencies’ selection processes are independent, the three agencies take
appropriate steps to ensure coordination:
•
•
RTD and DRCOG actively participated in CDOT’s county hearings.
RTD’s SBP development is a public process.
•
DRCOG’s Preparation Policy is reviewed by MPO committees (on which RTD
and CDOT serve) before adoption by the DRCOG Board.
•
DRCOG, RTD, and CDOT staffs discuss the potential relationships (synergies
or conflicts) between their respective projects.
•
The entire DRCOG selection process is transparent, with briefings at MPO
committees on progress and tentative decisions.
•
RTD and CDOT are represented on the DRCOG Board as non-voting
members and provide comment and advice to the Board.
12
The 2016-2021 Program
The remaining pages of this document are dedicated to providing a detailed synopsis of
the projects proposed for implementation within the DRCOG area during the timeframe
of this TIP. In order to aid the reader, 2016-2021 TIP projects are presented in following
formats:

2016-2021 TIP Projects Map (Figure 4) – Presents the geographic location of
programmed projects by project type

2016-2021 TIP Project List (Table 2) - A simple look-up table sorted by project name
to compliment the projects map and descriptions

Regionally Significant Projects Included in the 2016-2021 TIP (Table 3) – Includes
roadway and rapid transit projects recognized in the air quality conformity
determination documents. All projects are part of the conformity network and are in
the applicable staging periods of the 2040 Fiscally Constrained RTP.

2016-2021 TIP Project Descriptions – Provides details of each transportation project
proposed for implementation within the DRCOG area during this TIP timeframe. The
descriptions are in order by TIP project number. The upper portion of each
description sheet includes the project title, TIP and State TIP identification numbers,
sponsor, project type, project scope, and location map, as appropriate. The title is a
brief descriptor of the project location.
For DRCOG-selected projects, the scope identifies all elements for which points
were awarded, and what the project must do at a minimum. The center of each
project description page indicates the anticipated opening date, affected counties
and municipalities, and funding sources.
The total project funding is the sum of funds previously programmed before fiscal
2016, funds shown for fiscal 2016 through 2021 in this TIP and projected future
funding (allocated or unallocated) beyond that shown in this TIP. The most likely
federal funding source for each project is identified. The bottom of the sheet
displays the amendment history for projects initiated in previous TIPs.
Appendix C contains projects sorted by county, city and project type.
13
Figure 4: 2016-2021 TIP Projects
}
I
Â
K
2016-053
ú
M
ú
M
2016-015
O
¤
O
¤
`
!
WELD
2012-051
IBOULDER
}
O
¤
2016-050
2016-010
2008-081
í
M
2016-011
í
M
2016-030
2016-026
Â
K
2016-052
2016-048
§
I
2016-054
2016-008
Í
M
2016-007
O
Ì
Í
M
2016-035
O
¤
2016-045
2016-054
}
I
2016-029
r
^
2016-033
b
!
Í
M
2016-055!
`
2016-034
q
^
ADAMS
BROOMFIELD
2016-013
2016-014
Â
K
O
¼
O
¼
2008-114
p
M
§
I
2012-079
é
M
Â
K
Ê
M
ÿ
M
e
M
2012-063
}
I
O
¹
b
!
r
M
2016-037
a
!
2016-047
d
%
2007-050
2007-055
a
!
2016-003
2016-020
2008-111
2007-053 2016-028
2016-012
2016-023 2016-022
2016-018
2016-009 1999-052
2016-062
2012-062
ò
M
a
!
s
I
2012-080
2016-039
`
!
2016-025
¢
I
2016-032
2016-006 2016-061
s
I
2016-060
r
M
ó
Q
DENVER
2016-019
k
M
2007-158
2016-021
2016-017
2007-044
`
!
Ï
M
²
I
O
¹
2016-040
k
M
O
Ò
a
M
²
I
ARAPAHOE
c
%
2016-038
2016-059
Þ
M
2016-005
Þ
M
2016-024
2016-049
÷
Q
2016-016
Ê
M
Û
M
Ï
M
M̀
2016-044
a
!
¢
I
2016-046
§
I
k
M
2007-058
q
^
2016-031
2016-042
JEFFERSON
2016-043
2016-036
2007-059
DOUGLAS
`
!
h
M
2001-154
§
I
LEGEND
O
x
2016-027
2016-041
j
M
Project Type
Bike/Ped
Studies
Transit
Roadway
Bike/Ped
This data is intended for informational
purposes only. DRCOG provides this information
on an "as is" basis and makes no guarantee,
representation or warranty, either express or implied,
that the data will be error free. DRCOG further makes
no guarantees, representations or warranties, either
express or implied, as to the completeness, accuracy or
correctness of the data, or as to merchantability or
fitness of the data for a particular use or purpose. DRCOG
is not responsible to any user for any costs, expenses,
liabilities or damages arising from inconsistencies in its
data or from any use of the information.
Projection: State Plane Colorado Central, NAD 83 (feet)
±
Studies
Transit
0
2
Miles
4
Initials of map creator & date map made
location of map. Example:
Kennedy\CRS\GIS\Basemaps\Website_Maps\
MapGallery_Maps\2010_census_urbanized_area
Table 2. 2016-2021 Transportation Improvement Program Project List
TIPID
2016-028
2016-018
2016-035
2016-030
2016-002
2016-012
2016-046
2016-054
2016-008
2016-026
2016-014
2016-059
2016-031
2016-019
2012-010
2016-029
2016-048
2007-053
2008-111
2007-056
2007-055
2007-050
2007-044
2007-059
2007-058
2016-011
2016-041
2016-040
2016-038
2016-044
2016-021
2012-063
2016-055
2007-158
2016-003
2016-060
2012-062
2016-024
2016-047
2016-049
2016-022
2016-053
2016-027
2016-005
2016-009
2016-006
2008-081
2012-079
2012-080
Project Name
16th St Mall Reconstruction: Arapahoe St to Lawrence St
23rd Ave. Bike/Ped Path at Fitzsimons Station
30th St and Colorado Ave Bike/Ped Underpass
71st St Multimodal Pathway Connection: Winchester to Idylwild Trail
Air Quality Improvements Pool
Anschutz Medical Campus Shuttle
Arapahoe Rd: I-25 to Parker Rd Next Steps Operations Study
Boulder County Bus-then-Bike Shelters
Boulder Slough Multiuse Path: 30th St to 3100 Pearl
Broadway Reconstruction: Violet Ave to US-36
Broomfield Call-n-Ride
C-470 Managed Toll Express Lanes: Kipling to I-25
C-470 Multi-use Trail: Grade Separation at Yosemite St
Colfax 15L Transit Improvements: I-225 to I-25
DRCOG Second Commitment to FasTracks Pool
East Lafayette Multimodal Path Connection: Commerce Ct to Lafayette Park-n-Ride
Erie Pkwy Study: SH-287 to I-25
FasTracks Central Corridor: 30th Ave & Downing St to 38th Ave & Blake St
FasTracks Eagle P-3 Corridors (Gold and East Line)
FasTracks I-225 LRT Corridor: Parker Rd to East Corridor Commuter Rail
FasTracks North Metro: Denver Union Station to 72nd Ave
FasTracks Northwest Rail Corridor
FasTracks Projects: DRCOG First Commitment Pool
FasTracks Southeast Corridor Extension: Lincoln Ave to RidgeGate Pkwy
FasTracks Southwest Corridor Extension: Mineral Station to C-470
FLEX Route Extension: Boulder to Longmont
Founders Pkwy and Allen Way Intersection Improvements
Gun Club Rd and Quincy Ave Operational Improvements
High Line Canal Trail Underpass
Hwy 79 and Hwy 36 Grade Separation: FA and Design Study
I-25 & Broadway Interchange Reconstruction
I-25 North PEL Action Items
I-25: 120th Ave to E-470 Managed Lanes
I-25: Santa Fe Dr to Alameda Ave Interchange Improvements (Valley Hwy Phases I and II)
I-70 East Reconstruction
I-70/Genesee Bike Path
I-70/Kipling: NEPA Study
Iliff Ave Operational Improvements: Parker Rd to Quebec St
Industrial Area Transportation Study: I-25 to I-270 to 40th Ave/Smith Rd
Jeffco Bike Wayfinding Study
Martin Luther King Jr. Blvd Extension: Havana St to Peoria St
Mead School to School Trail Project
Meadows Pkwy Reconstruction: US-85 to Meadows Blvd
Metro Center Station Area Bike/Ped Connector Facility
MetroRide Service Expansion: DUS to Civic Center
Multi-use path on the D10: Wadsworth Blvd to Zephyr St and Kipling St to Oak St
North I-25: Front Range EIS
North Metro Rail 112th Ave Corridor Improvements
North Metro Rail 72nd Ave and Colorado Blvd Station Sidewalks
15
2016-058
2016-036
2016-023
2016-025
2007-078
2008-103
2008-076
2007-073
2007-074
2016-056
2012-112
2012-115
2016-057
2007-096
2007-075
2012-116
2008-028
2007-133
2008-077
2008-106
2007-094
2007-092
2012-109
2007-095
2007-091
2016-051
2012-064
1999-097
2016-004
2016-043
2016-039
2012-108
2007-169
2016-010
1997-084
2012-068
2016-015
2016-050
2012-051
2016-045
2016-062
2016-061
1999-052
2007-089
2016-013
2016-033
2016-034
2016-016
2016-007
2016-042
2008-114
2016-032
Ozone State Implementation Plan (SIP) Modeling Study
Parker Rd Sidewalk Connection: Plaza Dr to Sulphur Gulch Trail
Quebec St Operational Improvements: 13th Ave to 26th Ave
Ralston Rd Reconstruction: Yukon St to Upham St
Region 1 Bridge On-System Pool
Region 1 FASTER Bridge Enterprise Pool
Region 1 FASTER Pool
Region 1 Hazard Elimination Pool
Region 1 Hot Spot Pool
Region 1 ITS Pool
Region 1 RAMP Project Pool
Region 1 Rockfall Mitigation
Region 1 RPP Pool
Region 1 Surface Treatment Pool
Region 1 Traffic Signals Pool
Region 4 2013 Flood-Related Projects Pool
Region 4 Bridge Off-System Pool
Region 4 Bridge On-System Pool
Region 4 FASTER Pool
Region 4 FASTER Transit Pool
Region 4 Hazard Elimination Pool
Region 4 Hot Spot Pool
Region 4 RAMP Project Pool
Region 4 Surface Treatment Pool
Region 4 Traffic Signals Pool
Regional BRT Feasibility Study
Regional TDM Program: Way to Go
Regional Transportation Demand Management (TDM) Program Pool
Regional Transportation Operations Pool
RidgeGate Pkwy Widening: Havana St to Lone Tree City Limits
Route 73 Extension: Smith Rd Station to 60th Ave and Dahlia St
RTD Capital Improvements: Bus and Facilities Funding
RTD Enhancements - ADA/Ped/Bus Shelter
RTD L Route Service Enhancement
RTD Preventive Maintenance: Transit Vehicle Overhaul and Maintenance
RTD Regional Workforce Initiative Now (WIN)
RTD Route #324 Frequency Improvements
SH 119 BRT NEPA Analysis: Boulder to Longmont
SH-119: South of Hover Bike/Ped Underpass
SH-7 BRT Study: Boulder to Brighton
Sheridan Blvd Sidewalks: Colfax Ave to 17th
Sheridan Blvd Sidewalks: W. 6th Ave to W. 10th Ave
State of Good Repair
Station Area Master Plan/Urban Center Studies Pool
Superior Call-n-Ride
Superior Trail: McCaslin BRT Station to Coal Creek
Superior Trail: McCaslin BRT to Davidson Mesa Underpass
Toll Gate Creek Trail: Chambers Rd to Montview Blvd
University of Colorado Boulder East Campus Pedestrian Bridge & Trail Connection
US 85: Highlands Ranch Pkwy to Blakeland Dr Capacity Improvements
US-36: Boulder to I-25 Managed Lanes/BRT
US-6 Shared-Use Path: Colfax Ave to Johnson Rd
16
2001-154
2016-020
2016-037
2016-017
2016-052
US-85: Cook Ranch Rd to Meadows Pkwy Widening
Wadsworth Blvd Widening: 35th Ave to 48th Ave
Washington Ave Complete Streets
Westerly Creek Trail to Toll Gate Creek Trail Connector
Williams Fork Trail Multi-use Path: 63rd St to Twin Lakes Rd
17
Table 3. Regionally Significant Projects Included in the 2016-2021 TIP
2001-154
US-85: Cook Ranch Rd to Meadows Pkwy Widening
2007-050
Northwest Rail: Denver Union Station to Westminster; rail, stations, parking
2007-053
Central Corridor; 30 Ave & Downing St to 38 Ave and Blake St; rail, stations
2007-055
North Metro: Denver Union Station to 72
2007-056
I-225 Corridor: Parker Rd to East Corridor Commuter Rail; rail, stations, parking
2007-058
Southwest Corridor Extension: Mineral Station to C-470; rail, stations, parking
2007-059
Southeast Corridor Extension: Lincoln Ave to Ridgegate Pkwy; rail, stations, parking
2007-158
I-25: Santa Fe Dr to Alameda Ave Interchange Improvements
2008-111
Eagle P-3 FasTracks Corridors (Gold and East Line)
2008-114
US-36: Boulder to I-25 Managed Lanes/BRT
2016-003
I-70 East Reconstruction
2016-020
Wadsworth Blvd Widening: 35 Ave to 48 Ave
2016-021
I-25 & Broadway Interchange Reconstruction
2016-022
Martin Luther King Jr. Blvd Extension: Havana St to Peoria St
2016-042
US85: Highlands Ranch Pkwy to Blakeland Dr Capacity Improvements
2016-043
RidgeGate Pkwy Widening: Havana St to Lone Tree City Limits
2016-055
I-25: 120 Ave to E-470 Managed Lanes
2016-059
C-470 Managed Toll Express Lanes: Kipling to I-25
th
th
nd
th
Ave; rail, stations parking
th
th
18
Project Descriptions
19
20
2016-2021 Transportation Improvement Program (Approved TIP)
Title: RTD Preventive Maintenance: Transit Vehicle Overhaul and
Maintenance
TIP-ID: 1997-084
STIP-ID: N/A
Project Type: Transit Vehicles
Open to Public:
Sponsor: R T D
Project Scope
Ongoing program: Overhaul and maintenance for transit vehicles. A portion of
these 5307 funds will be applied to capital cost of contracting. RTD has
privatized service on fixed-routes and private carriers provide capital
maintenance in addition to fixed-route bus service. In addition to routine capital
maintenance, RTD will apply 5307 capital maintenance funds to bus fuel cost
and utility cost for LRT vehicles as a result of the Federal Transit Administration
expanded definition of allowable cost.
Affected County(ies)
Regional
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$55,691
$56,248
$56,810
$57,378
$114,756
State
$0
$0
$0
$0
$0
Local
$11,195
$11,250
$11,365
$11,475
$22,955
$66,886
$67,498
$68,175
$68,853
$137,711
Federal (5307)
$0
Total
Total
Funding
$0
$409,123
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
05/16/2013
Amended
Add $3,140,000 in FY2013, $140,000 in FY2014, and $140,000 in FY2015 of federal Section 5307 funds and $28,000 in FY2013, $28,000 in
FY2014, and $28,000 in FY2015 of local match to correct a previous mistake. Increase total project funds.
07/17/2012
Amended
Update project scope to include “In addition to routine capital maintenance, RTD will apply 5307 capital maintenance funds to bus fuel cost and
utility cost for LRT vehicles as a result of the Federal Transit Administration expanded definition of allowable cost.” Total project funding remains
unchanged.
03/13/2012
Amended
Reallocate $5,000,000 of federal Section 5307 funding from FY2013 to FY2012 and add $2,500,000 of local funding in FY2012. Increase total
project funding.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
03/19/2008
Approved
Adopted into the 2008-2013 TIP
06/22/2007
Amended
Add the following to Federal funds; $2,388,000 to FY 2007, $1,457,000 to FY 2008, and $651,000 to FY 2009. Add local match funds in the
amounts of $597,000 to FY 2007, $364,000 to FY 2008, and $163,000 to FY 2009. Total project costs increase by $5,620,000 ($4,496,000 in
Section 5307 funds and $1,124,000 in local funds).
06/14/2006
Approved
Adopted into the 2007-2012 TIP
03/17/2004
Approved
Adopted into the 2005-2010 TIP
05/15/2002
Approved
Adopted into the 2003-2008 TIP
03/21/2001
Amended
Decrease in local funding to reflect actual apportionment
11/15/2000
Approved
Adopted into the 2001-2006 TIP
21
2016-2021 Transportation Improvement Program (Approved TIP)
Title: State of Good Repair
Project Type: Transit Operational
Improvements
TIP-ID: 1999-052
STIP-ID: SDR3440
Open to Public:
Sponsor: R T D
Project Scope
Funds will be used for upgrades and maintenance of the 16th St Mall from
Broadway to Market St. Funds will also be used for RTD's transfer facilities at
each end of the 16th St Mall, and other fixed guideway assets. Funds will also
go toward on-going maintenance of rail guideways, and preventative
maintenance of the Fixed Guideway Rail and assets, including maintenance of
the LRT Rolling stock and LRT maintenance support. Includes funds for State of
Good Repair funding and high-intensity motor bus.
Affected Municipality(ies)
Affected County(ies)
Denver
Denver
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$11,000
$11,000
$11,000
$11,000
$22,000
State
$0
$0
$0
$0
$0
Local
$2,500
$2,500
$2,500
$2,500
$5,000
$13,500
$13,500
$13,500
$13,500
$27,000
Federal (5337)
$0
Total
Total
Funding
$0
$81,000
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
05/16/2013
Amended
Change project title from "RTD Fixed Guideway Improvements, Upgrades, and Maintenance" to "State of Good Repair." Update project scope,
adding "Includes funds for State of Good Repair funding and high-intensity motor bus." Change all funding from Section 5309 Fixed Guideway to
Section 5337 State of Good Repair. Total project funding remains unchanged.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
02/17/2010
Amended
Increase Section 5309 Fixed Guideway funds by $10,314,000 and adjust the fiscal years as follows; increase FY 2010 by $8,589,000, FY 2011 by
$3,295,000, and decrease FYs 2012-2013 by $1,570,000. Increase local funds by $4,878,000 and adjust the fiscal years as follows; increase FY
2010 by $2,147,000, FY 2011 by $824,000 and FYs 2012-2013 by $1,907,000. Increase total project funding.
12/07/2009
Amended
Transfer federal 5309 Fixed Guideway funds in the amounts of $4,935,000 from FY 2008 and $5,453,000 from FY 2009, to FY 2010, and local
funds in the amounts of $1,234,000 in FY 2008 and $1,363,000 in FY 2009, to FY 2010. Total funding remains unchanged.
06/23/2009
Amended
Add the following language to the existing scope; "preventative maintenance of the Fixed Guideway Rail and assets, including maintenance of the
LRT Rolling stock and LRT maintenance support." No changes to funding.
03/19/2008
Approved
Adopted into the 2008-2013 TIP
06/14/2006
Approved
Adopted into the 2007-2012 TIP
03/17/2004
Approved
Adopted into the 2005-2010 TIP
01/08/2004
Amended
Specify the following in the scope: constructing central corridor passing trackage and upgrades to fiber optic system, power distribution system,
public address message system, and ticket vending machine software.
07/25/2003
Amended
Reduce FTA 5309 Guideway funds by $32k and local by $8k in FY03. Change the first part of the project name from "16th Street Mall" to "RTD
Fixed Guideway"
05/15/2002
Approved
Adopted into the 2003-2008 TIP
03/21/2001
Amended
Fund reduction to reflect actual apportionment
11/15/2000
Approved
Adopted into the 2001-2006 TIP
22
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Regional Transportation Demand Management (TDM) Program Pool
TIP-ID: 1999-097
STIP-ID:
Project Type: Congestion Management
Open to Public:
Sponsor: DRCOG
Project Scope
The Regional TDM Program funds projects that promote alternative
transportation mode use, with the intent to reduce mobile source emissions.
This pool includes funds for seven TMA regional partnerships and other TDM
projects selected through a call for projects.
Affected County(ies)
Regional
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$3,200
$0
$3,200
$0
$0
State
$0
$0
$0
$0
$0
Local
$800
$0
$800
$0
$0
$4,000
$0
$4,000
$0
$0
Federal (CMAQ)
$0
Total
Total
Funding
$0
$8,000
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
02/19/2014
Amended
Remove pool project Downtown Denver Partnership: Let's Go LODO for $145,000 of Federal CMAQ funds in FY2014 and add Community Cycles:
Bus-Bike Shelters/BikeStation: Promotion and Services [Boulder] for $80,000 of Federal CMAQ in FY2014.
12/11/2013
Amended
Transfer $450,000 of federal STP Metro funds in FY2014 to TIPID #2007-044 and receive $450,000 of federal CAMQ funds in FY2014 from TIPID
#2007-044. Total project funding remains unchanged.
09/20/2013
Amended
Add $337,000 of federal CMAQ funds and $84,000 of local match in FY2014. Add 11 new pool projects in FY2014 and increase funding to the six
Regional TDM Program projects by $160,000 each and add one new Regional TDM Program for $80,000 in FY2015. Increase total project funding.
10/04/2012
Amended
Reallocate $1,203,000 of federal CMAQ funds, $225,000 of federal STP Metro funds, and $357,000 of local match from FY2015 to FY2014. Total
project funding remains unchanged.
10/18/2011
Amended
Reallocate $225,000 in federal STP-Metro funds, $1,203,000 in federal CMAQ funds and $357,000 in local match from FY2013 to FY2012. Total
project funding remains unchanged.
10/13/2011
Amended
Add the following new projects for FY2012-13:
•eGo CarShare- SHIFT Your Mode, Shift Your Mood ($218,566)
•Boulder East- Community Investment Program ($150,000)
•RTD- Marketing of RTD Region-Wide FlexPass Program ($194,076)
•Groundwork Denver- NW Denver Community-based Social Marketing VMT Reduction Program ($145,710)
•South I-25 Urban Corridor TMA- Million Mile Challenge ($138,349)
•Transportation Solutions- Parker/Leetsdale Corridor Campaign ($64,000)
•36 Commuting Solutions- US-36 Transit Incentive Program ($119,218)
•Boulder County- Nederland Monthly Pass Program ($108,799)
•Community Cycles- Employee Bike Ambassadors ($50,000)
•RAQC (Wadsworth Corridor)- Every Trip Counts ($226,082)
•Boulder County- Diagonal Highway Vehicle Trip Reduction Program ($51,200)
•Stapleton TMA- Building an Active Stapleton ($50,000)
•Bike Denver- Denver Special Event Bike Parking ($50,000)
•B-cycle (Denver)- Denver B-cycle Winter Warriors Campaign and Marketing ($50,000)
•NATA (Thornton)- NATA Transportation Management Organization Start Up ($156,000)
Correct previous pool project funding levels to reflect federal only, instead of federal and local match. Total project funding remains unchanged.
06/20/2011
Amended
Add the following pool projects: 36 Commuting Solutions Regional TDM Program (FY12-13) ($193,000), Boulder East Community Regional TDM
Program (FY12-13) ($193,000), Downtown Denver Partnership Regional TDM Program (FY12-13) ($193,000), Southeast Business Partnership
Regional TDM Program (FY12-13) ($193,000), Stapleton Area TMA Regional TDM Program (FY12-13) ($193,000), Transportation Solutions Regional
TDM Program (FY12-13) ($193,000), Unallocated FY2012-2013 ($2,257,000), and Unallocated FY2014-2015 ($3,570,000). Total pool funding
remains unchanged.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
07/23/2009
Amended
Add the following projects and corresponding amounts to the pool; eGo Carshare for $195,000, Groundwork Denver for $160,000, Transportation
Solutions for $144,000, Boulder East: E-Marketing Campaign for $180,000, 36 Commuting Solutions: Commute Optimization Program for $154,000,
RAQC-Pilot TDM for $200,000, Go Boulder Drive Less for $105,000, South I-25 Pledge Against Pollution Program for $50,000, I-70 Coalition Rec.
Trip Planner for $68,000, Boulder County Final Mile for $115,000, DDP-Bicycle Parking Improvements for $61,000, and Transit Alliance: 10 Toes
Express for $153,000. Modify two existing projects; delete Skicarpool.com and reduce Stapleton TMA by $135,000 to $15,000. Reduce federal
CMAQ funds by $700,000 and local funds by $175,000 in both FY's 2010 and 2011 and transfer to FY 2009. Total funding remains unchanged.
23
Date
Status
Description
03/19/2008
Approved
Adopted into the 2008-2013 TIP
06/08/2007
Amended
Add 14 new projects to the pool.
06/14/2006
Approved
Adopted into the 2007-2012 TIP
03/17/2004
Approved
Adopted into the 2005-2010 TIP
12/17/2002
Amended
$300K in CM/AQ funding advanced into FY03 with reductions of $107K in FY04 and $193K in FY05; zero net change in federal funding. Local
match amounts redistributed to be 20% of total by year.
05/15/2002
Approved
Adopted into the 2003-2008 TIP
11/15/2000
Approved
Adopted into the 2001-2006 TIP
24
2016-2021 Transportation Improvement Program (Approved TIP)
Title: US-85: Cook Ranch Rd to Meadows Pkwy Widening
TIP-ID: 2001-154
STIP-ID: SDR5055
Project Type: Roadway Capacity
Open to Public: 2020
Sponsor: CDOT Region 1
Project Scope
Design and construct capacity improvements determined by the I-25 / US-85
Corridor EIS Record of Decision (see also TIP-ID 1999-002 in the 2001-2006
TIP). Widen from Cook Ranch Rd to Meadows Pkwy from 2 to 4 lanes.
Affected Municipality(ies)
Affected County(ies)
Castle Rock
Douglas
Littleton
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal
$0
$0
$0
$0
$0
State (R P P)
$0
$6,500
$8,900
$3,500
$0
Local
$0
$0
$0
$0
$0
$0
$6,500
$8,900
$3,500
$0
$65,298
Total
$37,300
Total
Funding
$121,498
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
01/17/2012
Amended
Reallocate $4,000,000 of state RPP funds from FY2013 to FY2012. Add $1,000,000 of state Regional Priority Projects (RPP) funding in FY2012.
Increase total project funding.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
12/22/2010
Amended
Add $700,000 of state Regional Priority Project (RPP) funds to FY 2011. Increase total project funding.
05/19/2010
Amended
Add $350,000 of state Regional Priority Project (RPP) funds in FY 2010. Increase total project funding.
04/06/2009
Amended
Add $451,000 of Section 1117 Transportation, Community and System Preservation (TCSP) funds to FY 2009. Increase total project funding.
03/23/2009
Amended
Add $5,400,000 of ARRA (ES9-CDOT) funds, $1,800,000 of Regional Priority Project (RPP) funds, and $1,750,000 of state Surface Treatment Funds
to FY 2009
04/21/2008
Amended
Add $358,000 of HB-1310 Regional Priority Projects (RPP) funds in FY 2008. Increase total project funding.
03/19/2008
Approved
Adopted into the 2008-2013 TIP
11/29/2007
Amended
Add $8,000,000 of HB-1310 Regional Priority Projects (RPP) funds to FY 2008 and reduce future funding by $8,000,000. Total funding remains
unchanged.
12/19/2006
Approved
Decrease prior funds by $7,225,000 and FY2008 RPP by $6,250,000. Add $5,000,000 in FY2007 RPP (Source HB 1310). Total project cost to
remain the same.
06/14/2006
Approved
Adopted into the 2007-2012 TIP
05/24/2006
Amended
Add $194,000 of federal earmark to the $661,000 that was already TIPed. Increase total cost.
03/27/2006
Amended
Add $9,625,000 of Regional Priority Program funds (source: $2,400,000 in HB-1310 funds and $7,225,000 in State General Fund dollars) in FY 2006
and delete $500,000 in RPP funds in FY 2007, and $9,125,000 in future. Total project cost remains the same.
04/26/2005
Amended
Add $661,000 of federal discretionary funds in FY05. Increase total project cost.
12/21/2004
Amended
Add $2,800,000 of Regional Priority Projects funds (source: HB 1310) in FY05. Add $1,300,000 of local match in FY05. Increase total project
funding.
10/18/2004
Amended
Decrease FY05 Regional Priority Projects funds by $1,275,000 as a result of bid savings. Decrease total funding.
03/17/2004
Approved
Adopted into the 2005-2010 TIP
06/04/2002
Amended
Transferred $1.983M from Titan Rd (TIPID # 99-002) project to this project due to a TCSP grant for the Titan Rd project.
03/14/2002
Amended
Reduce planned funding in FY03 from $8M to 1M. Project will continue with design and delay construction.
11/06/2001
Amended
Borrowed $7.2 million from Intermountain TRP to be paid back in FY04.
03/21/2001
Amended
Deferment of $3.0M required in order to transfer to Titan Road
11/15/2000
Approved
Adopted into the 2001-2006 TIP
25
2016-2021 Transportation Improvement Program (Approved TIP)
Title: FasTracks Projects: DRCOG First Commitment Pool
TIP-ID: 2007-044
STIP-ID: ST6803
Project Type: Transit Operational
Improvements
Open to Public: 2017
Sponsor: R T D
Project Scope
Funding allocated to RTD by DRCOG Board to be used on FasTracks-related
projects.
2016-2021 TIP projects provide funding for the following FasTracks projects:
• Southeast Corridor (FY2016 & FY2017)
• North Metro Corridor (FY2016)
2012-2017 TIP projects provided funding for the following FasTracks projects:
• Gold Line - Pecos Station (FY2012)
• East/I-225 Corridors- Smith/Peoria Station (FY2012)
• Northwest Corridor- 41st and Fox Station (FY2012 & FY2014)
• Commuter Rail Vehicles (FY2014)
Affected County(ies)
Regional
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal (CMAQ)
$4,000
$0
$0
$0
$0
Federal (STP-M)
$4,000
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$2,000
$0
$0
$0
$0
$10,000
$0
$0
$0
$0
$65,000
Total
Total
Funding
$0
$75,000
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
07/15/2014
Amended
Update project scope to include 'North Metro Corridor (FY2016)' and 'Southeast Corridor (FY2016 & FY2017).' Total project funding remains
unchanged.
04/10/2014
Amended
Update the project scope to replace 'Gold Line - 41st and Fox Station (FY2012)' with 'Gold Line - Pecos Station (FY2012).'
02/19/2014
Amended
Update the project scope to replace 'Gold Line - Ward Road Station (FY2012)' and 'Denver Union Station - (FY2014)' with 'Gold Line - 41st and Fox
Station (FY2012)' and 'Commuter Rail Vehicles - (2014).'
01/07/2014
Amended
Move $450,000 of Federal CMAQ funds from FY2015 to FY2014. Move $450,000 of Federal STP-M funds from FY2014 to FY2015. Total project
funding remains unchanged.
12/11/2013
Amended
Transfer $450,000 of federal CMAQ funds in FY2014 to TIPID #1999-097 and receive $450,000 of federal STP Metro funds in FY2014 from TIPID
#1997-097. Total project funding remains unchanged.
05/16/2013
Amended
Update project scope to change the use of East Corridor funds in FY2009 and switch the FY2014 use of North Metro federal funds to Denver Union
Station, replacing the North Metro corridor’s First Commitment Funds with local RTD. Total project funding remains unchanged.
08/16/2012
Amended
Update project scope to read “Project will provide funding for the following FasTracks projects:
• Gold Line –Ward Road Station (FY2012)
• East/I-225 Corridors- Smith/Peoria Station (FY2012)
• Northwest Corridor- 41st and Fox Station (FY2012 & FY2014)
• North Metro Corridor- TBD (FY2014)”
Total project funding remains unchanged.
12/05/2011
Amended
Reallocate $6,000,000 of federal CMAQ funds and $1,500,000 of local match from FY2013 to FY2012. Total project funding remains unchanged.
10/13/2011
Amended
Update scope to read:‘2012 funds for the Gold Line will be used for construction of the 41st Ave Station (2011 funds from previous TIP were also
used for Gold Line). Remaining 2012 funds and 2013 funds will for the I-225 Corridor's Iliff Station.’Total project funding remains unchanged.
09/15/2011
Amended
Update scope to read:‘2012 funds for the Gold Line will be used for construction of the Ward Road Station (2011 funds from previous TIP were also
used for Gold Line). Remaining 2012 funds and 2013 funds will for the I-225 Corridor's Iliff Station.’Total project funding remains unchanged.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
12/22/2010
Amended
Add specific location (Table Mesa) for one pedestrian crossing. Total funding remains unchanged.
12/07/2009
Amended
Adding language to the scope indicating the specific use and expenditure timeframe of CMAQ funds to satisfy federal requirements. Total funding
remains unchanged.
03/19/2008
Approved
Adopted into the 2008-2013 TIP
03/19/2008
Approved
Adopted into the 2008-2013 TIP
26
Date
Status
Description
02/13/2008
Amended
Reduce CMAQ funds in FY 2008 by $200,000 and allocate to prior funding. Total funding remains unchanged.
06/14/2006
Approved
Adopted into the 2007-2012 TIP
27
2016-2021 Transportation Improvement Program (Approved TIP)
Title: FasTracks Northwest Rail Corridor
TIP-ID: 2007-050
Project Type: Rapid Transit
STIP-ID: SST7015.007
Open to Public: 2018
Sponsor: R T D
Project Scope
Completion of Phase I rail to Westminster, and completion of the Longmont
Station Transfer Center, which will include a bus transfer facility, 240-space Park
-n-Ride, and passenger waiting area.
Affected Municipality(ies)
Affected County(ies)
Denver
Adams
Westminster
Denver
Unincorporated
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal
$0
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
$5,362
$1,494
$0
$0
$0
$5,362
$1,494
$0
$0
$0
Local (RTD)
$125,640
Total
Total
Funding
$0
$132,496
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
02/21/2013
Amended
Reduce local funding by $218,574,000 in Previous Funding, $18,506,000 in FY2012, $110,098,000 in FY2013, $197,015,000 in FY2014,
$178,009,000 in FY2015, and $96,119,000 in FY2016-17. Update project scope and title to reflect the change in project termini from Longmont
(1st Ave and Terry St) to Westminster (71st Ave). Decrease total project funding.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
10/27/2008
Amended
Reduce prior funding and local funds in FY 2008 and FY 2009 to $0, and increase local funds in FY 2010 by $111,208,000, FY 2011 by $80,671,000
and future funding by $27,801,000. Reduce FY's 2012-2013 by $73,083,000. Increase total project funding.
03/19/2008
Approved
Adopted into the 2008-2013 TIP
06/14/2006
Approved
Adopted into the 2007-2012 TIP
28
2016-2021 Transportation Improvement Program (Approved TIP)
Title: FasTracks Central Corridor: 30th Ave & Downing St to 38th Ave &
Blake St
TIP-ID: 2007-053
STIP-ID: SST7015
Project Type: Rapid Transit
Open to Public:
Sponsor: R T D
Project Scope
The Central Corridor Extension begins at the 30th Ave and Downing Station and
extends north approximately 0.8 miles to the 38th/Blake Station, which will serve
as a transfer station to the East Corridor. The alignment will operate within a
traffic lane in each direction along Downing St from 30th Ave and Downing St to
36th Ave. The alignment will continue along 36th Ave from Downing St to the
38th Ave and Blake St station.
Affected Municipality(ies)
Affected County(ies)
Denver
Denver
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal
$0
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
$14
$15
$0
$0
$0
$14
$15
$0
$0
$0
Local (RTD)
$10,702
Total
Total
Funding
$0
$10,731
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
02/21/2013
Amended
Remove all funding for the current TIP and add $10,702,000 to Previous Funding. Decrease total project funding.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
10/27/2008
Amended
Reduce local funds from prior funding through FY 2011 to $0, increase fiscal years 2012-2013 by $9,012,000, and reduce future funding by
$1,442,000. Decrease total project funding.
03/19/2008
Approved
Adopted into the 2008-2013 TIP
06/14/2006
Approved
Adopted into the 2007-2012 TIP
29
2016-2021 Transportation Improvement Program (Approved TIP)
Title: FasTracks North Metro: Denver Union Station to 72nd Ave
TIP-ID: 2007-055
STIP-ID: SST7015.008
Project Type: Rapid Transit
Open to Public: 2020
Sponsor: R T D
Project Scope
Commuter rail corridor from Denver Union Station to 72nd Ave. Alignment
generally follows the BNSF rail alignment to near 54th Ave, then further north it
joins the UPRR Boulder Branch ROW. Future funds are anticipated
expenditures from 2018-2035, and may not represent total build out costs.
Affected Municipality(ies)
Affected County(ies)
Commerce City
Adams
Denver
Denver
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal
$0
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
$172,484
$84,690
$4,740
$0
$0
$172,484
$84,690
$4,740
$0
$0
Local (RTD)
$157,680
Total
Total
Funding
$0
$419,594
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
02/21/2013
Amended
Increase Previous Funds by $5,456,000. Reduce local funding by $18,000,000 in FY2012, $23,913,000 in FY2013, $29,431,000 in FY2014,
$45,432,000 in FY2015, $361,640,000 in FY2016-17, and $64,869,000 in Future Funds. Update project scope and title to reflect the change in
project termini from 160th Ave to 72nd Ave. Decrease total project funding.
11/17/2011
Amended
Increase total project funds by $7,175,000 and reallocate project funds between fiscal years resulting in local funding of $75,000,000 in Previously
Programmed, $18,000,000 in FY2012, $47,000,000 in FY2013, $83,000,000 in FY2014, $83,000,000 in FY2015, $397,000,000 in FY2016-2017 and
$239,000,000 in Future Funding. Increase total project funding consistent with the 2011 FasTracks Financial Plan.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
10/27/2008
Amended
Reduce prior funding and local funds through FY 2011 to $0. Increase funding in FY 2012-2013 by $145,184,000 and future funding by
$145,157,000. Increase total project funding.
03/19/2008
Approved
Adopted into the 2008-2013 TIP
06/14/2006
Approved
Adopted into the 2007-2012 TIP
30
2016-2021 Transportation Improvement Program (Approved TIP)
Title: FasTracks I-225 LRT Corridor: Parker Rd to East Corridor Commuter
Rail
TIP-ID: 2007-056
STIP-ID: SST7015
Project Type: Rapid Transit
Open to Public: 2016
Sponsor: R T D
Project Scope
Extend double-track light rail train from the Southeast Corridor Nine Mile Station
to Smith/Peoria and intersect the East Corridor.
Affected Municipality(ies)
Affected County(ies)
Aurora
Adams
Arapahoe
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal
$0
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
$76,508
$0
$0
$0
$0
$76,508
$0
$0
$0
$0
Local (RTD)
$684,248
Total
Total
Funding
$0
$760,756
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
02/21/2013
Amended
Reduce total project funding by $36,021,000 in local funds and advance funds from FY2015, FY2016-17, and Future Funds resulting in
$208,047,000 in Previous Funding, $0 in FY2012, $211,896,000 in FY2013, $168,800,000 in FY2014, $95,505,000 in FY2015, and $2,731,000 in
FY16-17 of local funds. Decrease total project funding.
11/17/2011
Amended
Increase total project funds by $41,055,000 and reallocate project funds between fiscal years resulting in local funding of $151,000,000 in
Previously Programmed, $27,000,000 in FY2012, $27,000,000 in FY2013, $80,000,000 in FY2014, $158,000,000 in FY2015, $280,000,000 in
FY2016-2017 and $27,000,000 in Future Funding. Increase total project funding consistent with the 2011 FasTracks Financial Plan.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
10/27/2008
Amended
Reduce prior funding and local funds through FY 2010 to $0. Increase local funds in FY 2011 by $49,155,000, FY 2012-2013 by $59,195,000 and
future funding by $93,145,000. Increase total project funding.
03/19/2008
Approved
Adopted into the 2008-2013 TIP
06/14/2006
Approved
Adopted into the 2007-2012 TIP
31
2016-2021 Transportation Improvement Program (Approved TIP)
Title: FasTracks Southwest Corridor Extension: Mineral Station to C-470
TIP-ID: 2007-058
STIP-ID: SST7015
Project Type: Rapid Transit
Open to Public:
Sponsor: R T D
Project Scope
Extend the Southwest Corridor light rail from the Mineral Station to C-470/Lucent
Blvd in Highlands Ranch.
Affected Municipality(ies)
Affected County(ies)
Littleton
Arapahoe
Douglas
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal
$0
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local (RTD)
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$23,150
Total
Total
Funding
$0
$23,150
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
02/21/2013
Amended
Remove all funding for the current TIP and reduce Previous Funding to $23,150,000. Decrease total project funding.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
10/27/2008
Amended
Reduce local funds through FY 2010 to $0 and future funding by $74,101,000. Increase local funds in FY 2011 by $44,418,000 and FY's 2012-2013
by $75,162,000. Increase total project funding.
03/19/2008
Approved
Adopted into the 2008-2013 TIP
06/14/2006
Approved
Adopted into the 2007-2012 TIP
32
2016-2021 Transportation Improvement Program (Approved TIP)
Title: FasTracks Southeast Corridor Extension: Lincoln Ave to RidgeGate
Pkwy
TIP-ID: 2007-059
STIP-ID: SST7015
Project Type: Rapid Transit
Open to Public: 2019
Sponsor: R T D
Project Scope
Extend Southeast Corridor LRT from Lincoln Ave to RidgeGate Pwy in the City
of Lone Tree.
Affected Municipality(ies)
Affected County(ies)
Lone Tree
Douglas
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$0
$0
$0
$0
$0
$92,000
$42,706
$25,942
$1,141
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$43,190
$58,614
$29,872
$1,315
$0
$135,190
$101,320
$55,814
$2,456
$0
Federal
Federal (5309S)
Local (RTD)
$39,379
Total
Total
Funding
$0
$334,159
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
02/21/2013
Amended
Increase total project funds by $29,129,000 in local funds and reallocate funding between fiscal years resulting in $32,606,000 in Previous Funding,
$0 in FY2012, $2,216,000 in FY2013, $3,058,000 in FY2014, $1,499,000 in FY2015, $0 in FY2016-17, and $182,041,000 in Future Funds. Increase
total project funding.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
10/27/2008
Amended
Reduce local funds from FY 2008 through FY 2010 to $0, increase FY 2011 by $39,082,000, FY's 12-13 by $73,736,000, and reduce future funding
by $89,453,000. Increase total project funding.
03/19/2008
Approved
Adopted into the 2008-2013 TIP
06/14/2006
Approved
Adopted into the 2007-2012 TIP
33
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 1 Hazard Elimination Pool
TIP-ID: 2007-073
Project Type: Safety
STIP-ID: SR16682
Open to Public:
Sponsor: CDOT Region 1
Project Scope
CDOT Region 1 Hazard Elimination pool. Specific projects will not be listed.
Affected County(ies)
Adams
Arapahoe
Broomfield
Denver
Douglas
Jefferson
Amounts in $1,000s
Prior
Funding
FY16
$0
FY19
FY20-21
Future
Funding
$0
$0
$0
$0
$16,635
$5,850
$0
$0
$0
$0
$0
$0
$0
$0
$16,635
$5,850
$0
$0
$0
Local
Total
FY18
$0
Federal
State (Safety)
FY17
Total
Funding
$0
$22,485
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
09/18/2014
Amended
Add $4,504,080 of State Safety funds in FY2015 for US 6 bridges design/build. Increase total project funding.
08/21/2013
Amended
Add $8,208,000 in FY2014 and $8,954,000 in FY2015 of state Safety funds transferred from project TIPID #2007-081. Increase total project
funding.
05/16/2013
Amended
Add $63,000 of state Safety funds in FY2013. Increase total project funding.
03/15/2013
Amended
Add $327,000 of state Safety funds in FY2013. Increase total project funding.
07/17/2012
Amended
Add $229,000 in FY2012 and $337,000 in FY2013 of state Safety funds. Increase total project funding.
03/13/2012
Amended
Add $305,000 of state Safety funding in FY2012. Increase total project funding.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
01/27/2011
Amended
Add $290,000 of state Safety funds to FY2011 and program to US285 west of Conifer for new VMS Installation. Increase total project funding.
09/07/2010
Amended
Add $517,000 of state Safety funds in FY 2011. Increase total project funding.
11/12/2008
Amended
Add $625,000 of state Safety funds and $77,000 of state Regional Priority Project (RPP) funds in FY 2009. Increase total project funding.
08/15/2008
Amended
Reduce state Safety funds in FY 2009 by $177,000. Decrease total project funding.
07/14/2008
Amended
Add $201,000 of state Safety funds in FY 2009. Increase total project funding.
06/30/2008
Amended
Add $46,000 of State Regional Priority Projects (RPP) funds in FY 2008. Increase total project funding.
03/19/2008
Approved
Adopted into the 2008-2013 TIP
11/29/2007
Amended
Add $135,000 of RPP funds in FY 2008, and increase line item; Upper Bear Creek Rd. Intersection Project by same amount. Increase total project
funding.
09/30/2006
Amended
Add $1,785,000 state (safety) in FY07.
07/21/2006
Amended
Decrease $800,000 from this pool’s reserves in FY07 in order to fund new project. Total funding remains the same.
06/14/2006
Approved
Adopted into the 2007-2012 TIP
34
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 1 Hot Spot Pool
TIP-ID: 2007-074
Project Type: Safety
STIP-ID: SR16683
Open to Public:
Sponsor: CDOT Region 1
Project Scope
CDOT Region 1 Hot Spot Pool. Specific projects will not be listed.
Affected County(ies)
Adams
Arapahoe
Broomfield
Denver
Douglas
Jefferson
Amounts in $1,000s
Prior
Funding
FY16
FY17
$0
FY20-21
Future
Funding
$0
$0
$0
$0
$413
$413
$413
$413
$0
$0
$0
$0
$0
$0
$413
$413
$413
$413
$0
Local
Total
FY19
$0
Federal
State (Safety)
FY18
Total
Funding
$0
$1,652
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
08/21/2013
Amended
Add $164,000 of state Safety funds in FY2014. Add $360,000 in FY2014 and $376,000 in FY2015 of state Safety funds transferred from TIPID
#2001-225. Increase total project funding.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
06/23/2009
Amended
Reduce state Safety funds in FY 2010 by $54,000. Decrease total project funding.
08/15/2008
Amended
Reduce state Safety funds by $85,000 in FY 2009. Decrease total project funding.
03/19/2008
Approved
Adopted into the 2008-2013 TIP
06/14/2006
Approved
Adopted into the 2007-2012 TIP
35
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 1 Traffic Signals Pool
TIP-ID: 2007-075
Project Type: Safety
STIP-ID: SR16684
Open to Public:
Sponsor: CDOT Region 1
Project Scope
CDOT Region 1 Traffic Signal Pool. Specific projects will not be listed.
Affected County(ies)
Adams
Arapahoe
Broomfield
Denver
Douglas
Jefferson
Amounts in $1,000s
Prior
Funding
FY16
FY17
$2,341
FY20-21
Future
Funding
$0
$0
$0
$0
$1,050
$6,650
$5,000
$0
$0
$0
$0
$0
$0
$0
$1,050
$6,650
$5,000
$0
$0
Local
Total
FY19
$0
Federal
State (Safety)
FY18
Total
Funding
$0
$15,041
Date
Status
Description
05/04/2015
Proposed
Add the following projects and corresponding amounts to the pool for FY2016; SH-224 (E 74th Ave) at Dahlia St for $350,000; SH-287 (W 120th
Ave) at Greenway Dr/Lamar St for $350,000; and SH-287 at W 10th Ave $350,000.
04/16/2015
Approved
Proposed for adoption into 2016-2021
08/21/2013
Amended
Add $245,000 in FY2014 and $255,000 in FY2015 of state Safety funds transferred from TIPID #1999-063. Increase total project funding.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
01/27/2011
Amended
Add $146,000 of state Safety funds to FY2011 and program to signal replacements at SH-74 and County Road 65. Increase total project funding.
02/23/2010
Amended
Add $122,000 of state Safety funds to FY 2010. Increase total project funding.
06/23/2009
Amended
Reduce state Safety funds in FY 2010 by $36,000. Decrease total project funding.
04/06/2009
Amended
Add $331,000 of state Safety funds to FY 2009. Increase total project funding.
08/15/2008
Amended
Reduce state Safety funds in FY 2009 by $58,000. Decrease total project funding.
03/19/2008
Approved
Adopted into the 2008-2013 TIP
06/14/2006
Approved
Adopted into the 2007-2012 TIP
36
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 1 Bridge On-System Pool
TIP-ID: 2007-078
Project Type: Bridge
STIP-ID: SR16712
Open to Public:
Sponsor: CDOT Region 1
Project Scope
The Bridge On-System Pool funds various bridge projects throughout CDOT
Region 1.
Affected County(ies)
Adams
Arapahoe
Broomfield
Denver
Douglas
Jefferson
All pool project funding depicts federal and/or state funding only.
Cost
(1,000s)
I-70 Bridge
Replacement
@Havana
BNSF Replacement
Study
SH-265
$250
I-70 WB Deck Rehab
US-40 to DITCH
$330
State Highway Repairs
$750
SH-105 Bridge
Removal Study
DRAW
$250
US-40 Deck
Rehab/Replacement
Beaver Brook
$100
US Highway Repairs
$750
$250
I-70 and I-270 Repairs
Ramp to I-25 NB
Pedestrian Overpass
Removal Study
SH-95 Fiber Wrap
$2,000
Start-At and End-At
I-70 WB to I-225 SB
Flyover
$3,695
I-25 Repairs
I-25
County Line Rd to Bellevue
$1,400
I-225
I-25 to Parker Rd
I-70 Bridge
Replacement
Havana St
US-6
I-70 to SH-119
$498
Santa Fe
Florida to I-25
I-76
96th to US-85
$280
6th Ave
Potomac to Airport
$263
Colfax
I-70 to Kipling
$31
C-470
Morrison to Bowles
$3,508
Sheridan
Hampden to Arizona
$178
I-25
Hampden to Evans
Federal
92nd to 120th
$327
US-85
Hampden to Florida
University
Arapahoe to Hampden
$845
US-85
I-76 to 136th
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
$56
FY19
FY20-21
$0
$0
$0
State
$14,692
$15,920
$9,472
$0
$0
Local
$0
$0
$0
$0
$0
$14,692
$15,920
$9,472
$0
$0
$0
$727
$63
I-25 T-Rex Narrows
$5,396
I-70 and I-25
$5,381
I-70/I-25 Ramps
$10,336
$25
Essential Culvert
Repairs (FY16)
$2,085
$3,328
Essential Culvert
Repairs (FY17)
$2,669
$92
Essential Culvert
Repairs (FY18)
$2,669
Future
Funding
$0
Total
$1,500
$4,110
$0
Federal (BR)
$5,894
$1,500
$241
I-25/I-70/I-76
I-70 and I-25
I-76 Repairs
US-6 to Beaver Brook
$2,207
Start-At and End-At
$1,500
US-40
Douglas County Scour
Repairs
Facility Name
(Cont)
Cost
(1,000s)
Start-At and End-At
$1,800
Facility Name
(Cont)
Cost
(1,000s)
Facility Name
Total
Funding
$0
$40,084
Date
Status
Description
05/05/2015
Proposed
Change "I-70 Bridge Replacement Havana" to "I-70 Bridge Replacement @Havana St (FY16)"; change "I-70 Bridge Replacement @Havana" to "I70 Bridge Replacement @Havana St (FY17)" and adjust funding to $800,000. Total project funding remains unchanged.
04/16/2015
Approved
Proposed for adoption into 2016-2021
09/02/2014
Amended
Add the following project and corresponding amount to the pool; I-225 Bridge Preventative Maintenance for $2,500,000 in state Bridge On-System
funds in FY2015. Increase total project funding.
37
Date
Status
Description
07/15/2014
Amended
Add the following projects and corresponding amounts to the pool in State Bridge On-System funds; 40th Ave (SH33) Bridge Devolution for
$1,000,000 in FY2015 and $1,000,000 in FY2016; Hudson Road over Coyote Run for $92,800 in FY2015. Increase total project funding.
01/07/2014
Amended
Add 1 new pool project for region-wide preventative maintenance ($8,400,000), using available pool funds. Total project funding remains
unchanged.
10/16/2013
Amended
Add 1 new pool project in FY2014, US40/Colfax: Federal to Speer ($1,200,000), using available pool funds. Total project funding remains
unchanged.
09/20/2013
Amended
Add $9,727,000 in FY2014 and $10,121,000 in FY2015 of federal Bridge On-System funds, as well as pool project Bridge Deck Replacement
($9,225,000), transferred from TIPID #2007-080. Add new pool project I-70 East: Smith Rd Structures Replacement ($644,000). Increase total
project funding.
05/16/2013
Amended
Add $5,255,000 of state Bridge On-System funds in FY2013 allocating to: I-70 East: Frontage Road over Middle Bijou Creek ($3,500,000) and US40: Byers to Deer Trail Overlay & Bridge Rehabilitation ($755,000), and I-25 SB: Surrey Ridge Roud & SH-86 at Founders Pkwy ($1,000,000).
Increase total project funding.
01/15/2013
Amended
Add $7,900,000 of state Bridge On-System funds in FY2013 allocating to I-70 East: Smith Rd and UPRR ($12,900,000). Increase total project
funding.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
09/07/2010
Amended
Add $471,000 of state Bridge On-System funds to FY 2011. Increase total project funding.
08/18/2010
Amended
Add state Bridge On-System funds in the amount of $2,309,000 in FY 2010 and $2,073,000 in FY 2011. Increase total project funding.
04/06/2009
Amended
Add state Bridge On-System funds in the amount of $500,000 to FY 2009. Increase total project funding.
08/15/2008
Amended
Reduce state Bridge On-System funds in FY 2009 by $806,000. Decrease total project funding.
03/19/2008
Approved
Adopted into the 2008-2013 TIP
06/14/2006
Approved
Adopted into the 2007-2012 TIP
38
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 1 Bridge Off-System Pool
TIP-ID: 2007-079
Project Type: Bridge
STIP-ID: SR17001
Open to Public:
Sponsor: CDOT Region 1
Project Scope
The Bridge Off-System Pool funds off-system bridge projects throughout CDOT
Region 1.
Affected County(ies)
Adams
Arapahoe
Broomfield
Denver
Douglas
Jefferson
All pool project funding depicts federal and/or state funding only.
Facility Name
Start-At and End-At
Dartmouth Ave (FY18)
@ S Platte River
Amounts in $1,000s
Prior
Funding
Cost
(1,000s)
$524
FY16
Facility Name
(Cont)
Start-At and End-At
88th Ave (FY18)
@ Wolf Creek
FY17
FY18
FY19
Cost
(1,000s)
FY20-21
Future
Funding
$0
$0
$0
$0
$0
State
$0
$0
$624
$0
$0
Local
$0
$0
$0
$0
$0
$0
$0
$624
$0
$0
$0
Start-At and End-At
Cost
(1,000s)
$100
Federal (BRO)
Total
Facility Name
(Cont)
Total
Funding
$0
$624
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
07/15/2014
Amended
Add the following project and corresponding amount to the pool in State Bridge Off-System funds; Evergreen Road over Bear Lake for $632,000 in
FY2015. Increase total project funding.
08/21/2013
Amended
Add $544,000 of state Bridge-Off System funds and $169,000 of local match in FY2014 allocating to new pool project: Plum Creek Pkwy over
Seller's Gulch ($544,000). Add $1,844,000 of state Bridge-Off System funds and $461,000 of local match in FY2013 of state Bridge-Off System
funds transferred from TIPID #2007-097 for transferred pool project: 72nd Ave and Raleigh St- Little Dry Creek ($1,844,000). Increase total
project funding.
05/16/2013
Amended
Add $132,000 of state Bridge funds in FY2014 allocating to new pool project: Hudson Rd Bridge over Box Elder Creek ($132,000). Increase total
project funding.
05/16/2013
Amended
Add $132,000 of state Bridge funds in FY2014 allocating to new pool project: Hudson Rd Bridge over Box Elder Creek ($132,000). Increase total
project funding.
05/16/2013
Amended
Add $132,000 of state Bridge funds in FY2014 allocating to new pool project: Hudson Rd Bridge over Box Elder Creek ($132,000). Increase total
project funding.
05/16/2013
Amended
Add $132,000 of state Bridge funds in FY2014 allocating to new pool project: Hudson Rd Bridge over Box Elder Creek ($132,000). Increase total
project funding.
05/16/2013
Amended
Add $132,000 of state Bridge funds in FY2014 allocating to new pool project: Hudson Rd Bridge over Box Elder Creek ($132,000). Increase total
project funding.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
03/15/2011
Amended
Add $2,406,000 of state Bridge Off-System funds and $603,000 local match to FY2011 and $59,000 of state Bridge Off-System funds and $15,000
local match in FY2012 allocating to Arapahoe County Structure #ARA-30-26.8 ($501,000), Douglas County Structure #DOU-016-00.55
($1,700,000), Jefferson County Structure #D-27-MP-010 ($808,000) and Structure #Morr-Park Ave ($74,000). Increase total project funding.
03/19/2008
Approved
Adopted into the 2008-2013 TIP
06/14/2006
Approved
Adopted into the 2007-2012 TIP
39
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Station Area Master Plan/Urban Center Studies Pool
TIP-ID: 2007-089
STIP-ID: N/A
Project Type: Station Area/Urban Center
Studies
Open to Public:
Sponsor: DRCOG
Project Scope
Pool funds for future station area master plans and/or urban center planning
studies.
Affected County(ies)
Regional
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$600
$600
$600
$600
$0
State
$0
$0
$0
$0
$0
Local
$150
$150
$150
$150
$0
$750
$750
$750
$750
$0
Federal (CMAQ)
$0
Total
Total
Funding
$0
$3,000
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
09/02/2014
Amended
Switch Littleton Downtown Light Rail Station Area Study from FY2014 to FY2015 and Mineral Light Rail Station Area Study from FY2015 to FY2014.
09/20/2013
Amended
Add 11 new pool projects in FY2014 and FY2015 using unallocated funds; increase local funds to match adopted projects. Increase total project
funding.
05/16/2013
Amended
Update project title from "Station Area Master Plan Studies Reserve" to "Station Area Master Plan/Urban Center Studies Pool." Update project scope
to "Pool funds station area master plans and/or urban center planning studies. Pool projects will be depicted individually." Change project type from
"Funding Reserves" to "Station Area Master Plan/Urban Studies." Total project funding remains unchanged.
12/05/2011
Amended
Add $1,000,000 of federal CMAQ funds and $250,000 of local match in FY2015. Increase total project funding.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
03/19/2008
Approved
Adopted into the 2008-2013 TIP
06/08/2007
Amended
Remove $100,000 of CMAQ and $25,000 of Local funds from these reserves.
01/24/2007
Amended
Defer $185,000 of CMAQ and $47,000 of local funds from FY2007 to FY2008. Remove $400,000 of CMAQ and $100,000 of local funds from these
reserves.
08/28/2006
Amended
Advance $330,000 of CMAQ and $83,000 of local from FY08 to FY07
06/14/2006
Approved
Adopted into the 2007-2012 TIP
40
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 4 Traffic Signals Pool
TIP-ID: 2007-091
Project Type: Safety
STIP-ID: SR46668
Open to Public:
Sponsor: CDOT Region 4
Project Scope
Pool funds traffic signal projects in CDOT Region 4 (Boulder and SW Weld
Counties). Specific projects will not be listed.
Affected County(ies)
Boulder
Weld
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal
$0
$0
$0
$0
$0
State (Safety)
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$637
Total
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
03/19/2008
Approved
Adopted into the 2008-2013 TIP
06/08/2007
Amended
Reduce State Safety funds by $3,000 in FY 2008 and $6,000 in FY 2009.
06/14/2006
Approved
Adopted into the 2007-2012 TIP
41
Total
Funding
$0
$637
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 4 Hot Spot Pool
TIP-ID: 2007-092
Project Type: Safety
STIP-ID: SR46667
Open to Public:
Sponsor: CDOT Region 4
Project Scope
Pool funds hot spot projects in CDOT Region 4 (Boulder and SW Weld
Counties). Specific projects will not be listed.
Affected County(ies)
Boulder
Weld
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal
$0
$0
$0
$0
$0
State (Safety)
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$854
Total
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
03/19/2008
Approved
Adopted into the 2008-2013 TIP
06/08/2007
Amended
Reduce State Safety funds in FY 2008 by $4,000 and FY 2009 by $8,000
06/14/2006
Approved
Adopted into the 2007-2012 TIP
42
Total
Funding
$0
$854
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 4 Hazard Elimination Pool
TIP-ID: 2007-094
Project Type: Safety
STIP-ID: SR46666
Open to Public:
Sponsor: CDOT Region 4
Project Scope
Pool funds hazard elimination projects in CDOT Region 4 (Boulder and SW
Weld Counties).
Affected County(ies)
Boulder
Weld
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal
$0
$0
$0
$0
$0
State (Safety)
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$15,785
Total
Total
Funding
$0
$15,785
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
05/16/2013
Amended
Add $407,000 of local funds in FY2015. Add new pool projects using unallocated funds: SH-119: Ken Pratt Blvd & South Pratt Pkwy ($550,000),
Valmont Rd & 29th St ($2,713,000), and 95th St: Isabelle Rd to Valmont Rd ($950,000). Increase total project funds.
11/14/2011
Amended
Move SH-66 at East County Line Rd from the 2008-2013 TIP into the 2012-2017 TIP and add $488,000 from existing state Safety funds. Total
funding remains unchanged.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
03/02/2011
Amended
Add the following new projects: US85 Cable Rail- Brighton North of SH66 for $1,200,000, and East County Line Rd Auxiliary Lanes and signal
upgrade for $350,000 from existing funding levels. Total funding remains unchanged.
07/26/2010
Amended
Add line item; WCR 34 and WCR 17 Intersection Improvements in the amount of $172,000. Total funding remains unchanged.
10/15/2009
Amended
Add line item; SH-287 (Main St. Longmont) and Pike Rd. in the amount of $300,000. Total funding remains unchanged.
06/30/2008
Amended
Add SH-42: S. Boulder Rd. to the pool and allocate $400,000 of unallocated Hazard Elimination funds from FY 2008. (Project is also listed in the R4
Congestion Relief Pool.) Total project funding remains unchanged.
03/19/2008
Approved
Adopted into the 2008-2013 TIP
06/08/2007
Amended
Reduce State Safety funds in FY 2008 by $46,000 and FY 2009 by $107,000.
06/14/2006
Approved
Adopted into the 2007-2012 TIP
43
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 4 Surface Treatment Pool
TIP-ID: 2007-095
Project Type: Roadway Reconstruction
STIP-ID: SR45218
Open to Public:
Sponsor: CDOT Region 4
Project Scope
Projects in CDOT Region 4 (Boulder and SW Weld Counties) to be approved for
pool funding by Region 4 Director.
Affected County(ies)
Boulder
Weld
All pool project funding depicts federal and/or state funding only.
Facility Name
Start-At and End-At
SH-119
Monarch Rd to Fordham St
Amounts in $1,000s
Prior
Funding
$6,817
FY16
State (Surface)
Start-At and End-At
SH-119
MM 22.8 to 37.4
FY17
FY18
FY19
Cost
(1,000s)
$11,000
FY20-21
Facility Name
(Cont)
Start-At and End-At
SH-119
47th St to Monarch Rd
Future
Funding
$0
$0
$0
$0
$14,580
$14,580
$14,580
$0
$0
$0
$0
$0
$0
$0
$14,580
$14,580
$14,580
$0
$0
Local
$0
Facility Name
(Cont)
$0
Federal
Total
Cost
(1,000s)
Cost
(1,000s)
$11,100
Total
Funding
$0
$43,740
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
02/06/2015
Amended
Add the following projects and corresponding amounts to the pool: SH-119 Boulder East Monarch Rd to Fordham St for $6,817,000; and US-85
Brighton to Ft Lupton NB Only for $8,160,000. Remove $1,873,000 of State Surface Treatment funds from FY2012. Add $3,803,000 of State
Surface Treatment funds in FY2016-17. Increase total project funding.
02/21/2013
Amended
Remove $1,873,000 of state Surface funds in FY2012. Add $2,308,000 to SH-66: MP 39-43 ($5,200,000). Add new pool project: SH-119: MP 5964 ($12,000,000). Remove pool project SH-119: Boulder East MP44.24 ($10,300,000). Reduce total project funding.
05/04/2012
Amended
Add pool project SH-172 Chip Seal- SH-119 to SH-17 ($2,000,000) using unallocated pool funding. Total project funding remains unchanged.
12/15/2011
Amended
Add $1,500,000 of state Surface funding in FY2012. Increase total project funding.
07/28/2011
Amended
Reduce state Surface Treatment funding in FY2012 by $1,873,000 per the adopted budget allocation. Add three new projects to the pool: SH-66:
St Vrain Bridge MP 45-48 ($1,000,000), US-85: Ft Lupton to Brighton MP 236-242 ($1,492,000), and SH-66: Boulder/Weld County Line East MP
38.92-42.74 ($2,892,000). Decrease total pool funding.)
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
07/26/2010
Amended
Remove and transfer the following two projects to the Region 4 FASTER Pool; SH-119 at Jay Rd in the amount of $1,500,000 and SH-119 at Niwot
Rd. in the amount of $1,200,000, and reduce SH-119 at Boulder East by $4,200,000. Total funding remains unchanged.
02/17/2010
Amended
Add $7,000,000 of state Surface Treatment funds in FY 2010 and allocate to a new project: I-25, mile marker 243.5 to 249. Increase total project
funding.
10/15/2009
Amended
Remove line item SH-287C (Main St. Longmont) and Pike Rd. in the amount of $300,000 and transfer to the Region 4 Hazard Elimination Pool (TIP
ID #2007-094). Total funding remains unchanged.
09/10/2009
Amended
Add line item; SH-287C (Main St. Longmont) and Pike Rd. in the amount of $300,000. Total funding remains unchanged.
08/12/2009
Amended
Allocate $2,700,000 of unallocated state Surface Treatment funds to new pool projects in the following amounts; $1,500,000 to SH-119: Jay Rd.
Concrete Intersection and $1,200,000 to SH-119: Niwot Rd. Concrete Intersection. Total funding remains unchanged.
07/23/2009
Amended
Allocate $1,500,000 of unallocated state Surface Treatment funds from FY 2010 to existing pool project; SH-119: Resurfacing [MP46 to MP55], and
add the following new projects; SH-157: Boulder South, SH-36 [MP 0 to MP 2.83] for $2,800,000, SH-36: Boulder East [MP 44.3 to 48.1] for
$5,200,000, SH-52 and SH-119 East [MP 0 to MP 4.6] for $3,400,000, SH-7: Lyons to Raymond [MP 19.3 to MP 33.47] for $1,500,000, and SH-119:
Boulder East [MP44.24 to 54.42] for $14,500,000. Total funding remains unchanged.
06/23/2009
Amended
Allocate $3,000,000 of state Surface Treatment funds in FY 2010 to the following new project; SH-119: Resurfacing [MP46 to MP55]. Total funding
remains unchanged.
03/23/2009
Amended
Add $1,000,000 of ARRA (ES9-CDOT) funds to FY 2009 and allocate to the US-36: Estes Park to Lyons (DRCOG portion) project, replacing
$633,000 of Surface Treatment funds allocated to the project. Increase total project funding.
44
Date
Status
Description
08/15/2008
Amended
Reduce SH-93: Boulder by $31,000 to $2,976,000 and add the following projects and corresponding amounts; 1) SH-42 at Boulder Rd. for
$100,000, 2) SH-119 at 63rd St. (Louisville) for $147,000, 3) SH-66 Lyons (US-36 to Longmont) for $5,000,000, and 4) US-36: Estes Park to Lyons
(DRCOG portion) for $633,000. Total funding remains unchanged.
03/19/2008
Approved
Adopted into the 2008-2013 TIP
11/29/2007
Amended
Add $215,000 of state Surface Treatment funds to FY 2008. Increase line item, IGA Boulder: US-36 at Arapahoe and Iris by $50,000, and add line
item, SH-119 and County Line Rd in the amount of $165,000. Increase total project funding.
07/18/2007
Amended
Delete one project; SH-157/Boulder South. Modify funding for SH-170/IGA with Boulder, SH-7 (Lyons), SH-7 at SH-157, SH-93: Boulder, and US36/Boulder North. Add four new projects; IGA-Boulder: US-36 at Arapahoe and Iris, US-36: North St. Vrain Creek Bridge, IGA-Longmont: US-287
Quebec to Ken Pratt, and IGA-Lyons: US-36 downtown.
Total funding (control totals) remains the same.
06/08/2007
Amended
Reduce State Surface Treatment funds by $180,000 in FY 2008 and $215,000 in FY 2009, reducing overall funding.
06/14/2006
Approved
Adopted into the 2007-2012 TIP
45
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 1 Surface Treatment Pool
TIP-ID: 2007-096
Project Type: Roadway Reconstruction
STIP-ID: SR15215
Open to Public:
Sponsor: CDOT Region 1
Project Scope
Projects in CDOT Region 1 to be approved for Pool Funding by Region 1
Director.
Affected County(ies)
Adams
Arapahoe
Broomfield
Denver
Douglas
Jefferson
All pool project funding depicts federal and/or state funding only.
Facility Name
Start-At and End-At
I-25
@ I-225
I-76
96th to US-85
Colfax
Cost
(1,000s)
Facility Name
(Cont)
Start-At and End-At
US-6
I-70 to SH-119
$6,500
Wadsworth
I-70 to Kipling
$3,000
Federal
92nd to 120th
Kipling
SH-128
Cost
(1,000s)
Cost
(1,000s)
Facility Name
(Cont)
Start-At and End-At
$2,500
C-470
SH-8 to Bowles
Highland to 10th
$2,500
I-25
County Line Rd to Belleview
I-25
Hampden to Evans
$5,000
I-225
I-25 to Parker Rd
$7,500
$6,000
6th
Potomac to Airport
$4,500
Colfax
Peoria to Sable
$2,500
Jewell to 6th
$4,000
Colfax
Speer to Clarkson
$4,000
Hampden
Dahlia to Yosemite
$4,000
Eldorado to Wadsworth
$3,500
US-85
Hampden to Florida
$2,500
US-287
@ 120th Ave Intersection
SH-72
SH-93 to Coal Creek Canyon
$1,500
Santa Fe
Florida to I-25
$3,500
Preventative
Maintenance
Sheridan
Hampden to Arizona
$3,500
US-85
I-76 to 136th
$8,000
University
Arapahoe to Hampden
$5,000
Wadsworth
Bear Creek to 4th
$5,500
Amounts in $1,000s
$500
Prior
Funding
FY16
$0
FY19
FY20-21
Future
Funding
$0
$0
$0
$0
$55,000
$52,800
$39,600
$43,400
$0
$0
$0
$0
$0
$0
$55,000
$52,800
$39,600
$43,400
$0
Local
Total
FY18
$0
Federal
State (Surface)
FY17
$7,500
$12,000
$250
$0
Total
Funding
$0
$190,800
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
01/23/2015
Amended
Add $12,037,000 of state Surface Treatment funds in FY2015. Add the following projects and corresponding amounts to the pool; I-70 Havana St
to I-225 for $3,500,000; Preventative Maintenance at Various Locations for $2,000,000; SH-58 from US-6/SH-93 to I-70 for $10,000,000; US-40
from Clarkson St to Colorado Blvd for $4,500,000; US-85 from Blakeland Dr to Crestline Ave for $8,200,000; SH-95 from 25th Ave to 58th Ave for
$4,000,000; SH-74 from I-70 to CR-73 for $5,200,000; and SH-86 from I-25 to Woodlands Blvd for $8,000,000. Increase total project funding.
09/18/2014
Amended
Add $47,000,000 of state Surface Treatment funds in FY2016. Add the following projects and corresponding amounts to the pool; I-76, 96th to
US-85 for $6,500,000; Wadsworth, Highland to 10th for $2,500,000; I-25 @ I-225 for $500,000; SH-72, SH-93 to Coal Creek Canyon for
$1,500,000; US-40, Berthoud Pass East for $1,500,000; I-70, EMJT East for $3,000,000, Sheridan, Hampden to Arizona for $3,500,000; Federal,
92nd to 120th for $6,000,000; Kipling, Jewell to 6th for $4,000,000; University, Arapahoe to Hampden for $5,000,000; Colfax, I-70 to Kipling for
$3,000,000; SH-128, Eldorado to Wadsworth for $3,500,000; US6 I-70 to SH-119 for $2,500,000; US-40, US-6 to Beaver Brook for $2,000,000; and
US-36, Strasburg to Byers for $2,000,000. Increase total project funding.
10/16/2013
Amended
Add the following two pool projects transferred from TIPID #2001-214: US 285: Federal to Marion ($4,500,000) and SH 83/Parker: Jewell to
Mississippi ($2,000,000). Add $194,000 to pool project US 285: Federal to Marion ($4,694,000 total), $304,000 to SH 83/Parker: Jewell to
Mississippi ($2,304,000 total), and remove $1,200,000 from US 40/Colfax: Federal to Speer ($2,200,000 total) from unallocated FY2014 state
Surface Treatment funds. Total project funding remains unchanged.
46
Date
Status
Description
09/20/2013
Amended
Add the following two pool projects transferred from TIPID #2001-214: US-40 (Colfax Ave): Federal Blvd to Speer Blvd ($2,000,000) and Federal
Blvd & 120th Ave ($550,000). Add $1,400,000 to pool project US-40 (Colfax Ave): Federal Blvd to Speer Blvd ($3,400,000) from unallocated funds.
Total project funding remains unchanged.
08/21/2013
Amended
Add $2,442,000 of state Surface Treatment funds in FY2014 allocating to pool project: SH-86- Franktown-East (+$2,442,000 = $3,642,000 total).
Add $34,813,000 in FY2014 and $35,563,000 in FY2015 of state Surface Treatment funds transferred from project TIPID #2001-214 adding pool
project: SH-121 (Wadsworth Blvd)- 10th Ave to Colfax Ave ($2,400,000). Increase total project funding.
06/07/2013
Amended
Add $2,000,000 of federal Highways for Life funds in FY2013 allocating to pool project: I-70 East: Tower Rd to Colfax Ave ($18,524,000). Increase
total project funding.
05/16/2013
Amended
Add $1,200,000 of state Surface Treatment funds in FY2013 allocating to new project: SH-86 Preventative Maintenance: Franktown-East
($1,200,000). Increase total project funding.
04/09/2013
Amended
Add $453,000 of state Surface Treatment funds in FY2013 allocating to pool project: US-40: Byers to Deer Trail ($1,953,000). Increase total
project funding.
01/15/2013
Amended
Add $7,500,000 of state Surface Treatment funds in FY2013 allocating to pool project: I-70 East: Tower Rd to Colfax Ave ($16,524). Increase total
project funding.
08/16/2012
Amended
Reallocate $4,139,000 of state Surface Treatment funds from FY2013 to FY2012. Reduce state Surface Treatment funds by $3,652,000 in FY2013,
$10,371,000 in FY2014, and $5,480,000 in FY2015 based on the revised and updated Region 1 Surface Treatment Program. Add the following new
projects: SH-83: Antelope Creek to Castlewood Canyon ($4,139,000), US-36: Kiowa Creek to East of Byers ($4,000,000), US-40: Byers to Deer Trail
($1,500,000), SH-67 at Rampart Range Rd ($2,500,000), US-36 east of Cabin Creek ($500,000), SH-74: Evergreen to Morrison ($3,500,000), SH-79
north of Bennett ($3,000,000), and SH-30/E 6th Ave: S Picadilly Road to N Airport Blvd ($2,000,000). Decrease total project funding.
07/17/2012
Amended
Add $350,000 of state Regional Priority Project (RPP) funds in FY2012 allocating to I-70 East: Tower Rd to Colfax Ave ($9,024,000). Increase total
project funding.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
04/20/2011
Amended
Add $150,000 in FY2010 and $50,000 in FY2011 of state Rockfall Mitigation (RFM) funds, allocating to US-285: Turkey Creek Canyon. Increase
total project funding.
03/02/2011
Amended
Add $2,617,000 of Surface Treatment funds and $2,983,000 of Regional Priority Project (RPP) funds to FY2011 and allocate to SH-83 (Parker Rd):
Cottonwood Dr S project ($5,000,000) and US-36: Watkins to Bennett Rehabilitation project ($600,000). Increase total project funding.
12/22/2010
Amended
Add $500,000 of state Surface Treatment funds to SH36: West of Watkins to Bennett project in FY2011 and move $6,000,000 to FY2012-13.
Increase total project funding.
06/21/2010
Amended
Add $200,000 of state Surface Treatment funds to FY 2010 and increase SH-72 Junction @ SH-93 North by corresponding amount. Increase total
project funding.
01/15/2010
Amended
Add $100,000 of state Regional Priority Project (RPP) funds to FY 2010 and allocate to I-70 East Tower Rd. to Colfax Ave. Increase total project
funding.
08/12/2009
Amended
Add $2,574,000 of HB-1310 Regional Priority Project (RPP) funds in FY 2010 and increase line item; I-70 East Tower Rd. at Colfax Ave. by the
corresponding amount. Increase total project funding.
06/23/2009
Amended
Add the following new projects; US-285: Turkey Creek Canyon for $1,250,000, SH-72: Junction of SH-93 North for $900,000, US-285: Pine Junction
to Richmond Hill for $4,000,000, SH-36: West of Watkins-Bennett for $3,000,000, and I-70 East: Tower Rd. to Colfax Avenue for $6,000,000.
Reduce Pavement Preservation Jobs to $1,701,000 and the Unallocated 08-10 to $0. From 2009, reduce by $95,000 and transfer $8,331,000 to FY
2010 and $100,000 to FY 2011. Decrease total project funding.
04/06/2009
Amended
Shift $1,750,000 of state Surface Treatment funds from FY 2010 to FY 2009 and adding a new line item to the pool for the corresponding amount;
SH-85 (Louviers to C-470), and reduce the Unallocated balance by this same amount. Add $651,000 of state Surface Treatment funds to FY 2009
(allocating $325,000 to South I-25: Tomah Rd. to Douglas Lane and $326,000 to SH-86: Founders Parkway). Increase total project funding.
01/15/2009
Amended
Decrease state Surface Treatment funds in FY 2009 by $554,000 and reduce the Pavement Preservation Jobs project by the corresponding amount
to a total of $2,046,000. Decrease total project funding.
12/09/2008
Amended
Add $436,000 of HB-1310 Regional Priority Projects (RPP) funds in FY 2009 and increase line item; SH-86: Founders Parkway by the corresponding
amount to $8,213,000. Increase total project funding.
11/20/2008
Amended
Increase state Surface Treatment funds by $4,039,000 in FY 2009, $2,169,000 in FY 2010, and by $3,061,000 in FY 2011. Increase line item I-25:
Tomah Rd to Douglas Lane from $5,541,000 to $5,562,000. Add the following new line items: I-70: Tower Rd to Colfax Ave for $6,000,000; US285: Turkey Creek Canyon East for $1,250,000; SH83/Parker Rd: pavement preservation for $1,008,000; SH-72: Junction of SH-93-North for
$900,000; US-285: Deer Creek to Richmond Hill for $5,000,000; US-85: Louviers to C-470 (various locations) for $1,750,000; and I-25 South: El
Paso County Line-North for $3,000,000. Increase total project funding.
10/15/2008
Amended
Add state Surface Treatment funds in the amounts of $6,119,000 in FY 2008 and $2,298,000 in FY 2009, and add state Regional Priority Projects
(RPP) funds in the amount of $837,000 in FY 2008. Modify line items as follows; PE & Design from $1,600,000 to $600,000, SH-79: North of
Bennett from $500,000 to $3,200,000, SH-86: Founders Parkway from $7,000,000 to $7,777,000, South I-25: Tomah Rd. from $5,500,000 to
$5,541,000, and Unallocated 08-10 from $941,000 to $12,831,000. Add the following line items; US-6: Golden-West for $1,629,000 and I-70:
Hogback West for $282,000. Increase total project funding.
09/29/2008
Amended
Add $351,000 of state Surface Treatment funds to FY 2009 and increase the US-285: Foxton-Richmond Hill project by the corresponding amount to
total $1,791,000. Increase total project funding.
06/30/2008
Amended
Reduce state RPP funds in FY 2008 in the amount of $381,000 and return to the state pool and add $381,000 of state Surface Treatment funds in
FY 2009. Total project funding remains unchanged.
04/21/2008
Amended
Add $381,000 of HB-1310 Regional Priority Projects (RPP) funds and $181,000 of Surface Treatment funds in FY 2008. Increase total project
funding.
03/19/2008
Approved
Adopted into the 2008-2013 TIP
02/13/2008
Amended
Add $296,000 of Regional Priority Projects (RPP) funds to FY 2008 and allocate same amount to new line item; SH 86: Founders Parkway.
Increase total project funding.
12/19/2007
Amended
Add $273,000 of RPP funds to FY 2008 and increase line items; SH-79: North of Bennett by $100,000, and the I-70 Hogback West project by
$173,000. Total funding increases by $273,000.
11/29/2007
Amended
Add $29,000 of RPP funds to FY 2008 and increase line item, I-70 Hogback West project by the same amount. Transfer $41,000 from I-25:
Larkspur-North to Tomah Rd/Douglas Lane. Total funding increases by $29,000.
09/12/2007
Amended
Add $80,000 of state Regional Priority Project (RPP) funds to FY 2008 from Region 1 Safety TSM Pool. Increase line item project I-70 Hogback
West by this amount.
47
Date
Status
Description
08/10/2007
Amended
Add $41,000 of state Surface Treatment funds in FY 2008. Increase line item project, South I-25: Larkspur-North by this amount.
07/18/2007
Amended
Reduce funding for US-6: Golden West Overlay project. Add funding to the SH-79 Pavement Preservation: North of Bennett project. Add two new
projects; Foxton Road to Richmond Hill Road, and Tomah Road to Douglas Lane. Delay the SH-86: Founders Parkway project until FY 2010.
Unallocated funding amount will change respectively. Total project costs remain unchanged.
06/21/2007
Amended
Delete two projects; I-25: Tomah Rd to Douglas and I-70: Tower Rd. to Colfax. Add one new project US-6: Golden-West Overlay. Modify funding
for Pavement Preservation, I-25 Larkspur-North, I-70 Hogback West and the Unallocated 2007-2009. Total funding is unchanged.
04/13/2007
Amended
Add $492,000 to State Surface Treatment funds and add $107,000 of Maintenance Level of Service (MLOS) /System Quality funds to Federal/State
(80/20 split) in FY 2007.
03/07/2007
Amended
1) Additional $4,790,000 awarded to the pool comprised of HB1310 "RSL=0" funds ($4,200,000), Safety funds ($450,000 state), and Maintenance
Level of Service (MLOS) funds ($140,000). This funding is to be allocated to 3 existing projects: $730,000 to the I-70 Hogback West project,
$660,000 to the SH-86 Franktown East project, and $1,500,000 to the SH 86: Founders Parkway project, and one new project: SH-83: El Paso
County Line-North Resurfacing project, $1,900,000.
06/14/2006
Approved
Adopted into the 2007-2012 TIP
48
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 4 Bridge On-System Pool
TIP-ID: 2007-133
Project Type: Bridge
STIP-ID: SR46598
Open to Public:
Sponsor: CDOT Region 4
Project Scope
Pool funds Region 4 On-System bridge projects.
Affected County(ies)
Boulder
Weld
All pool project funding depicts federal and/or state funding only.
Facility Name
Start-At and End-At
Bridge Asset
Management
I-25, US-157, US-287
Amounts in $1,000s
Prior
Funding
Cost
(1,000s)
Facility Name
(Cont)
Cost
(1,000s)
Start-At and End-At
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$0
$0
$0
$0
$0
State
$110
$3,300
$0
$0
$0
Local
$0
$0
$0
$0
$0
$110
$3,300
$0
$0
$0
$0
Start-At and End-At
Cost
(1,000s)
$3,410
Federal (BR)
Total
Facility Name
(Cont)
Total
Funding
$0
$3,410
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
03/19/2015
Amended
Add the following project and corresponding amount to the pool: I-25, SH-157 and US-287 bridge overlay and repair for $1,442,000. Add
$1,442,000 of State Bridge funds in FY2015. Increase total project funding.
02/09/2015
Amended
Add the following project and corresponding amount to the pool; I-25, US-157 and US-287 bridge overlay maintenance for $1,442,000. Add
$1,442,000 of state Bridge funds in FY2015.
12/11/2013
Amended
Remove $1,187,000 of state Bridge-On funds in FY2014 replacing with state RPP funds in the same amount. Add $158,000 of state Regional
Priority Projects (RPP) funds in FY2014 allocating to new pool project: I-25, SH-157, and US-287- Bridge Maintenance ($158,000). Increase total
project funding.
05/04/2012
Amended
Add pool project SH-7- CBC between Ferncliff and Allenspark ($250,000) using unallocated pool funding. Total project funding remains unchanged.
03/13/2012
Amended
Add $470,000 to SH-157 at US-36. Total project funding remains unchanged.
10/13/2011
Amended
Add the following new project: SH-157 at US-36 (E-16-W) Bridge Deck Replacement ($1,710,000) from existing unallocated pool funds. Total
project funding remains unchanged.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
03/02/2011
Amended
Add the following new project: Design of bridge deck replacement for structure E-16-HW for $200,000 from existing funding levels. Total funding
remains unchanged.
11/12/2010
Amended
Add I-25 North: Mead Structures D-17-DA and D-14-DB with $500,000 of existing FY2011 funds to the project and increase the SH-93: Critical
Culvert Repair project by $250,000 with existing FY2011 funding. Total funding remains unchanged.
06/21/2010
Amended
Add SH-93 Critical Culvert Repair and allocate $100,000 of existing state Bridge On-System funds to project. Total funding remains unchanged.
07/23/2009
Amended
Increase state Bridge On-System funds in FY 2010 by $210,000 and add line item; SH-66: St. Vrain Bridge by the corresponding amount.
05/22/2008
Amended
$3,793,000 of State Bridge On-System funds are allocated in FY 2008. Total project funding increases.
03/19/2008
Approved
Adopted into the 2008-2013 TIP
11/29/2007
Amended
Add $5,181,000 of new Regional Priority Projects (RPP) funds and $200,000 of Region 4 Bridge On-System funds in FY 2008. Total funding
increases by $5,381,000.
06/08/2007
Amended
Reduce State Bridge On-System funding by $335,000 in FY 2008 and by $384,000 in FY 2009.
06/14/2006
Approved
Adopted into the 2007-2012 TIP
49
2016-2021 Transportation Improvement Program (Approved TIP)
Title: I-25: Santa Fe Dr to Alameda Ave Interchange Improvements (Valley
Hwy Phases I and II)
TIP-ID: 2007-158
STIP-ID: SDR7047
Project Type: Interchange Reconstruction
Open to Public: 2016
Sponsor: CDOT Region 1
Project Scope
Reconstruct interchanges at I-25/Santa Fe Dr and I-25/Alameda Ave as Phases
1 and 2 of the Valley Highway ROD (TIPID 1999-009).
Affected Municipality(ies)
Affected County(ies)
Denver
Denver
Amounts in $1,000s
Prior
Funding
FY16
$119,724
FY19
FY20-21
Future
Funding
$0
$0
$0
$0
$11,156
$11,346
$2,000
$0
$0
$0
$0
$0
$0
$0
$11,156
$11,346
$2,000
$0
$0
Local
Total
FY18
$0
Federal
State (Faster-S)
FY17
Total
Funding
$0
$144,226
Date
Status
Description
04/16/2015
Approved
Adopted into 2016-2021 TIP
09/20/2013
Amended
Add $4,350,000 in FY2014, $2,275,000 in FY2015, and $7,375,000 in FY2016-17 of state FASTER Safety funds (Also show in TIPID #2008-076)
and add $2,000,000 of state Bridge On-System funds in FY2014. Reduce state Regional Priority Project (RPP) funds by $8,250,000 in FY2014 and
$5,850,000 in FY2015. Increase total project funding.
10/13/2011
Amended
Add $3,300,000 of state Regional Priority Project (RPP) funding and remove $1,925,000 of state Congestion Relief funding in FY2012. Increase
total project funding.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
08/18/2010
Amended
Add $39,000,000 of state Regional Priority Project (RPP) funds in FY 2011 and reduce future funding by the corresponding amount. Total funding
remains unchanged.
06/21/2010
Amended
In FY 2010, reduce ARRA (ES9-CDOT) funds by $1,000,000, increase state Regional Priority Project (RPP) funds by $1,000,000, and decrease state
Congestion Relief funds by $681,000. In FY 2011, reduce state Regional Priority Project funds by $10,178,000 and increase state Congestion Relief
funds by $20,000. Reduce total project funding.
02/17/2010
Amended
Add $500,000 of state Regional Priority Project (RPP) funds in FY 2010. Increase total project funding.
10/15/2009
Amended
Add $2,000,000 of state Regional Priority Project (RPP) funds in FY 2010. Increase total project funding.
08/28/2009
Amended
Decrease Surface Treatment funds by $3,900,000 in FY 2010. Decrease total project funding.
08/19/2009
Amended
Reduce state Congestion Relief funds by $681,000 in FY 2010 and add $20,000 in FY 2011, and reduce state Regional Priority Project (RPP) funds
by $10,072,000 in FY 2010 and add $235,000 in FY 2011. Decrease total project funding.
08/12/2009
Amended
Add $14,300,000 of ARRA (ES9-CDOT) funds in FY 2010. Increase total project funding.
07/15/2009
Amended
Add $4,900,000 of state Surface Treatment funds in FY 2010 from Surface Treatment Pool (TIP ID # 2001-214). Increase total project funding.
07/06/2009
Amended
Reduce state Congestion Relief funds by $681,000 in FY 2010 and add $20,000 in FY 2011, and reduce state Regional Priority Project (RPP) funds
by $10,072,000 in FY 2010 and add $235,000 in FY 2011. Decrease total project funding.
03/23/2009
Amended
Add $22,100,000 of ARRA (ES9-CDOT) funds to FY 2009. Increase total project funding.
06/30/2008
Amended
Transfer $1,925,000 of state Congestion Relief funds from FY 2009 to FY's 2012-2013. Total project funding remains unchanged.
03/19/2008
Approved
Adopted into the 2008-2013 TIP
11/29/2007
Amended
Add $11,000,000 of HB-1310 Regional Priority Project (RPP) funds to FY 2008 and reduce future funding by $11,000,000. Total funding remains
unchanged.
01/31/2007
Amended
Add $8,000,000 in Regional Priorities Program funds (Source HB 1310) in FY2007 and set total costs at amount defined from 1999-009.
50
2016-2021 Transportation Improvement Program (Approved TIP)
Title: RTD Enhancements - ADA/Ped/Bus Shelter
TIP-ID: 2007-169
Project Type: Transit Passenger Facilities
STIP-ID: SST6741.018
Open to Public:
Sponsor: R T D
Project Scope
ADA upgrades and pedestrian improvements at the LRT stations; shelter kits
including canopies, bike accessory upgrades, and landscaping upgrades at the
Transit Centers and Park-n-Rides; digital signage installations along the LRT
corridors; ADA bus announcement upgrades at station boarding areas, and
public art projects at the stations.
Affected County(ies)
Regional
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$530
$545
$562
$578
$1,156
State
$0
$0
$0
$0
$0
Local
$106
$109
$113
$116
$232
$636
$654
$675
$694
$1,388
Federal (5307)
$0
Total
Total
Funding
$0
$4,047
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
04/10/2014
Amended
Add $360,000 in federal Section 5307 funds and $97,000 in local match in FY2013, $375,000 federal and $101,000 in local match in FY2014,
$390,000 federal and $105,000 in local match in FY2015 and $1,093,000 federal and $273,000 in local match in FY2016-17. Increase total project
funding.
06/12/2012
Amended
Update project scope to include “ADA bus announcement upgrades at station boarding areas.” Total project funding remains unchanged.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
03/15/2011
Amended
Add $364,000 of federal Section 5307 funds and $91,000 local match to FY2011 and modify project scope to add ‘New enhancement funds will be
used for fixed-route ADA automatic annuciators, shelter enhancements and bicycle upgrades.’ Increase total project funding.)
03/19/2008
Approved
Adopted into the 2008-2013 TIP
06/08/2007
Amended
Allocate Section 5307 funds as follows; $1,409,000 to FY 2007, $400,000 to FY 2008, $404,000 to FY 2009 and $408,000 to FY 2010-2012; and
local match of $352,000 to FY 2007, $100,000 to FY 2008, $101,000 to FY 2009 and $102,000 to FY 2010-2012.
51
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 4 Bridge Off-System Pool
TIP-ID: 2008-028
Project Type: Bridge
STIP-ID: SR46601
Open to Public:
Sponsor: CDOT Region 4
Project Scope
Bridge Off-System Pool funds off-system bridge projects throughout CDOT
Region 4 (Boulder and SW Weld Counties).
Affected County(ies)
Boulder
Weld
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal (BRO)
$0
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
Total
Funding
$0
$0
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
08/21/2013
Amended
Add $159,000 of federal Bridge Off-System funds and $40,000 of local match in FY2014 allocating to: County Rd 5 Over Sullivan Ditch ($159,000).
Increase total project funding.
02/15/2012
Amended
Add $830,000 of federal Bridge-off System funding and $207,000 of local match in FY2012 allocating to Boulder County Rd 49 over St. Vrain Canal.
Increase total project funding.
12/15/2011
Amended
Add $261,000 of state Regional Priority Project (RPP) funding in FY2012 allocating to Lefthand Creek Bridge- 63rd St ($221,000) and Weld County
Bridge ($40,000). Increase total project funding.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
07/26/2010
Amended
Add $320,000 of state Bridge Off-System funds and $80,000 of local funds in FY 2010 and allocate to the Bridge Rehabilitation Project: Weld
County Road (WCR) 6 and US-85. Increase total project funding.
52
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 1 FASTER Pool
TIP-ID: 2008-076
Project Type: Safety
STIP-ID: SR17002
Open to Public:
Sponsor: CDOT Region 1
Project Scope
Pool contains safety-related improvements and upgrades based on the new
FASTER funding program (Colorado Senate Bill 108) in CDOT Region 1.
Affected County(ies)
Adams
Arapahoe
Broomfield
Denver
Douglas
Jefferson
All pool project funding depicts federal and/or state funding only.
Facility Name
Start-At and End-At
Cost
(1,000s)
Facility Name
(Cont)
Start-At and End-At
Cost
(1,000s)
Facility Name
(Cont)
Start-At and End-At
Cost
(1,000s)
I-76 and C-470 Cable
Barrier
$1,224
SH-95 Intersection
Improvements
64th Ave
$851
High Line Canal Trail
Underpass
Parker/Mississippi
$3,201
I-70 PPSL
$3,000
SH-121/72nd Ave
Right turn accel lanes
$961
Cable Median Barrier
104th to 168th Ave
$2,000
C-470 Path Separations
$1,572
SH-121 Intersection
Improvements
Waterton Rd
$2,050
US-85 and Kuner Rd
Barrier Replacement
Bromley to Bridge
Founders Pkwy
Intersection
Reconstruct
Crowfoot Valley Rd
Girton, Eastman and Yale
I-70 at 32nd Ave and C- Chain Station Lighting
470
$594
SH-177 Sidewalks
Mineral Ave to Orchard Rd
SH-391
$570
I-70/US-6
Chain station lighting
improvements
$1,000
Wadsworth TOD left
turn protection
$440
I-76 Curve
Reconstruction and
Lane Balancing
US-85
$6,150
Region 1 TSM Study
Outcomes
$5,000
$200
I-76 Roundabouts at
ramp terminals
Bromley Ln
$2,164
FASTER Safety Design
$4,000
Jefferson County Schools
Access
SH-2 Traffic Signal
Upgrades
SH-75 and Mineral Ave
Amounts in $1,000s
Curb ramp and B/P crossing
improvements
Prior
Funding
FY16
$86,453
FY19
FY20-21
Future
Funding
$0
$0
$0
$0
$20,724
$2,424
$17,869
$19,869
$0
$0
$0
$0
$0
$0
$20,724
$2,424
$17,869
$19,869
$0
Local
Total
FY18
$0
Federal
State (Faster-S)
FY17
$521
$560
$1,602
$200
Total
Funding
$0
$147,339
Date
Status
Description
05/05/2015
Proposed
Increase US-85 and Kuner Rd Barrier Replacement cost from $560,000 to $700,000 to reflect sponsor"s original request. Total project funding
remains unchanged.
04/16/2015
Approved
Proposed for adoption into 2016-2021
09/20/2013
Amended
Transfer pool project I-25/Santa Fe (#2007-158) and add $13,000,000 from unallocated (total=$29,500,000) and transfer US-85: Santa Fe Dr and
Oxford UPRR Crossing Surface Replacement and add $230,000 from unallocated (total=$730,000) from TIPID #2008-078. Add new pool project:
US-285: Shaffers Crossing Interchange ($500,000) using unallocated funds. Total project funding remains unchanged.
08/21/2013
Amended
Add $260,000 of state Bridge On-System funds in FY2014 substituting out the FASTER Safety funds to pool project: I-25 SB at Surry Ridge RdConcrete Approach Slab Replacements ($260,000). Add $24,315,000 in FY2014 and $25,204,000 in FY2015 of state FASTER Safety funds and pool
project "Signal Upgrades- Various Locations (+$150,000 = $3,400,000 total)" transferred from project TIPID #2008-078. Increase total project
funding.
08/21/2013
Amended
Add $260,000 of state Bridge On-System funds in FY2014 substituting out the FASTER Safety funds to pool project: I-25 SB at Surry Ridge RdConcrete Approach Slab Replacements ($260,000). Add $24,315,000 in FY2014 and $25,204,000 in FY2015 of state FASTER Safety funds and pool
project "Signal Upgrades- Various Locations (+$150,000 = $3,400,000 total)" transferred from project TIPID #2008-078. Increase total project
funding.
07/24/2013
Amended
Add $917,000 of state FASTER Safety funds, allocating to: I-25 SB at Surrey Ridge Rd: Concrete Approach Slab Replacements ($1,460,000) and US
-40: Byers to Deer Trail- Asphalt and Bridge Repair ($657,000). Increase total project funding.
53
Date
Status
Description
04/09/2013
Amended
Add $300,000 of state FASTER Safety funds in FY2013 allocating to: I-25: US-85/SH-86 Interchange Improvements ($1,500,000). Increase total
project funding.
12/05/2012
Amended
Add $4,000 of state FASTER Safety funds in FY2013 allocating to: SH-83: Access Improvements in Franktown ($504,000). Increase total project
funding.
11/07/2012
Amended
Reallocate $3,900,000 of state FASTER Safety funds from FY2012 to FY2013. Add $2,000,000 of state FASTER Safety funds in FY2013 allocating to
new pool project: US-40: Type 3 W-Beam Guardrail Replacement. Increase total project funding.
10/15/2012
Amended
Delete the I-70 East: Tower-Colfax pool project and reduce state FASTER Safety funds in FY2013 by $3,900,000. Decrease total project funding.
09/18/2012
Amended
Add $200,000 of state FASTER Safety funds in FY2013 allocating to I-25: Allen Way Intersection/I-25 intersection improvements and rename the
project I-25: US-85/SH-86 Interchange Improvements. Increase total project funding.
08/13/2012
Amended
Add $600,000 of state FASTER Safety funds in FY2013 allocating to: SH-74: Culverts Relining & Repairs ($400,000) and US-285: Windy Point
Underdrain Removal & Replacement ($200,000). Increase total project funding.
05/04/2012
Amended
Project awarded additional funding and adds a new pool project. Add $187,000 in FY2012 of additional state FASTER funds to SH-83 (Parker Rd)N. Russelville Rd ($687,000) and $1,200,000 in FY2013 of state FASTER funds allocating to a new project: I-25 SB at Surrey Ridge Road
12/15/2011
Amended
Add $28,000 of state FASTER Saftey funds in FY2012 allocating to pool project US-285: Truck Warning System Aspen Park to Morrison ($28,000).
Increase total project funding.
11/14/2011
Amended
Project awarded $121,000 of state FASTER funds in FY2012, allocating to pool project SH-86 at Deerpath Road, and $500,000 of state FASTER
funds in FY2013, allocating to the new pool project I-70 West: Floyd Hill Wildlife Mitigation. Increase total project funding.
08/15/2011
Amended
Shift $1,522,000 of state FASTER funding from FY2012 to FY2013 and reduce state FASTER funding in FY2012 by $1,255,000. Add $200,000 to SH
-83: North Russelville Rd Intersection improvements. Add the following new projects: SH 83 Access Improvements in Franktown ($500,000), US85/ North Meadows Extension: New Interchange ($4,600,000), US-285 Truck Warning System: Aspen Park to Morrison ($400,000), I-70 West:
Recreational Path/Non-motorized Highway Bypass from El Rancho to Genesee ($700,000), I-25 & SH 86: Allen Way Intersection/I-25 Interchange
Improvements ($1,000,000), I-70 West: Active Traffic Management - Mt.Vernon Canyon-East ($2,500,000). Decrease total project funding.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
06/20/2011
Amended
Add $62,000 of state FASTER safety funding to FY2011 allocating to South I-25 Frontage Road Cable Rail Installation ($887,000). Increase total
project funding.
04/20/2011
Amended
Add $95,000 of FASTER Safety funds in FY2011, allocating to SH-86 at Deerpath Rd. Increase total project funding.
03/15/2011
Amended
Reallocate $322,000 of state FASTER Safety funds from US-285: Bailey to Richmond Hill in FY2010 to FY2011 allocating to US-285: Turkey Creek
Canyon. Total funding remains unchanged.
12/22/2010
Amended
Add $13,000 to I-70 West: Delineator Upgrades project in FY2011 and move $4,200,000 to FY2012-13. Increase total project funding.
11/10/2010
Amended
Remove $500,000 from US-285: Turkey Creek Canyon project and $275,000 from I-25 South: near Tomah Road project, and reduce FY2011
amount by corresponding amounts. Decrease total project funding.
05/21/2010
Amended
Add $620,000 to the US-285: Turkey Creek Median Rockfall project from US-285 Overlay: Bailey-Richmond Hill project. Total funding remains
unchanged.
02/23/2010
Amended
Add $7,075,000 of Faster Safety funds to FY 2011 and allocate to new projects as follows; SH-83 (Parker Road): North Russelville Rd Intersection
Improvements ($300,000), SH-83 (Parker Road): Indian Pipe Decel Lane NB ($400,000), SH-86 and Deerpath Rd: Widening EB Left Turn Lane
($400,000), I-70 West (Jeff Co): Delineator Lanes ($175,000), US-285: Turkey Creek- Median Updgrades/Rockfall Mitigation ($500,000), I-70 East:
Tower to Colfax- Shoulder Improve. ($3,900,000), I-70 East (near Bennett): VMS Install. ($300,000), I-25 South (near Tomah Rd): Cable Rail
Maintenance ($1,100,000). Increase total project funding.
54
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 4 FASTER Pool
TIP-ID: 2008-077
Project Type: Safety
STIP-ID: SR460606
Open to Public:
Sponsor: CDOT Region 4
Project Scope
Pool contains safety-related improvements and upgrades based on the FASTER
funding program (Colorado Senate Bill 108) in CDOT Region 4.
Affected County(ies)
Boulder
Weld
All pool project funding depicts federal and/or state funding only.
Cost
(1,000s)
Facility Name
Start-At and End-At
SH-7
Shoulder Gaps and Safety
(Flood)
Amounts in $1,000s
Prior
Funding
FY16
State (Faster-S)
SH-119
Gilpin CL to Boulder City
Limits
FY18
FY19
Cost
(1,000s)
Facility Name
(Cont)
Start-At and End-At
Cost
(1,000s)
$2,000
FY20-21
Future
Funding
$0
$0
$0
$0
$0
$5,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$5,000
$0
$0
$0
$0
Local
$0
Start-At and End-At
FY17
Federal
Total
$3,000
Facility Name
(Cont)
Total
Funding
$0
$5,000
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
11/07/2012
Amended
Reduce funding for SH-119 at Jay Rd and SH-119 at Niwot Rd by $700, returning funds to unallocated. Total project funding remains unchanged.
02/15/2012
Amended
Add the following pool project using existing pool funds: SH-93: SH-170 to SH-128 Shoulders Project ($2,100,000). Total project funding remains
unchanged.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
05/19/2011
Amended
Add the following new project: design and Right-of-way for SH93 shoulders from Hwy 170 to Hwy 128 for $400,000 from existing state FASTER
safety funding. Total funding remains unchanged.
08/17/2010
Amended
Decrease SH-7 Lengthen Culverts project by $300,000 in FY 2011. Decrease total project funding.
07/26/2010
Amended
Add $8,000,000 of FASTER Safety funds in FY's 2012-2013 and allocate as follows; New projects: SH-119 at WCR 5.5 (signal improvements) for
$350,000, Baseline at US-36: Bike/Ped Underpass for $500,000, SH-42 at Paschal Underpass for $650,000, and US-287 at SH-119 (Longmont
intersection improvements) for $1,250,000. Allocate the following amounts to existing projects; SH-119 at Jay Rd. for $1,500,000, SH-119 at Niwot
Rd. for $1,500,000, and SH-66 WCR 17-19 for $2,250,000. Increase total project funding.
03/16/2010
Amended
Add $4,600,000 of FASTER Safety funds in FY 2011, allocating $2,250,000 to SH-52 at WCR 11 Intersection, and adding the following projects: SH119 at WCR 7.5 Signal for $350,000, SH-7: Lengthen Culverts for $1,000,000, and SH-66, WCR 17-09 surface treatment, shoulders, and turn lanes
for $1,000,000. Increase total project funding.
55
2016-2021 Transportation Improvement Program (Approved TIP)
Title: North I-25: Front Range EIS
TIP-ID: 2008-081
Project Type: Roadway/Transit Studies
STIP-ID: SSP4028
Open to Public:
Sponsor: CDOT Region 4
Project Scope
Funds will be used to complete the Final Environmental Impact Statement, the
Record of Decision for Phase I of North I-25 (MP 214 - 269), and for design and
Right of Way for phase I elements. Project funding shown is for DRCOG portion
only.
Affected County(ies)
Weld
Amounts in $1,000s
Prior
Funding
FY16
FY17
$21,317
FY20-21
Future
Funding
$0
$0
$0
$0
$465
$451
$438
$425
$0
$0
$0
$0
$0
$0
$465
$451
$438
$425
$0
Local
Total
FY19
$0
Federal
State (R P P)
FY18
Total
Funding
$0
$23,096
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
03/19/2015
Amended
Add $60,000 of state RPP funds in FY2015 for additional evaluation at SH-7. Increase total project funding.
03/19/2015
Amended
Add State RAMP funding type. Add $10,000,000 of State RAMP funds in FY2015 for preconstruction activities. Increase total project funds.
01/07/2014
Amended
Add $1,200,000 in state Regional Priority Program (RPP) funds in FY2014. Increase total project funding.
12/11/2013
Amended
Add $1,200,000 of state Regional Priority Project (RPP) funds in FY2014. Increase total project funds.
05/16/2013
Amended
Add $150,000 of state 7th Pot funds in FY2013. Increase total project funding.
05/09/2013
Amended
Add $2,303,000 in FY2014, $2,303,000 in FY2015, and $5,852,000 in FY2016-17 of state RPP funds. Increase total project funding.
10/15/2012
Amended
Reduce state Regional Priority Projects (RPP) funding by $450,000 in FY2013 and add $450,000 of 7th Pot funds in FY2013. Total project funding
remains unchanged.
02/15/2012
Amended
Add $1,035,000 of state Regional Priority Project (RPP) funding in FY2015. Increase total project funding.
12/15/2011
Amended
Add $1,900,000 in FY2012, $1,035,000 in FY2013, and $1,035,000 in FY2014 of state Regional Priority Project (RPP) funding. Increase total
project funding.
10/13/2011
Amended
Update scope to read:‘Funds will be used to complete Final Environmental Impact Statement, the Record of Decision for Phase I of North I-25 (MP
214 - 269), and design and Right of Way for Phase I elements. Project funding shown is for DRCOG portion only.’Total project funding remains
unchanged.)
04/20/2011
Amended
Add $1,000,000 in state Regional Priority Project (RPP) funds to FY2012. Increase total project funding.
04/12/2011
Adopted
Adopted into the 2012-2017 TIP
03/16/2010
Amended
Add $1,200,000 of Regional Priority Project (RPP) funds to FY 2010.
56
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 1 FASTER Bridge Enterprise Pool
TIP-ID: 2008-103
Project Type: Bridge
STIP-ID: SST8102
Open to Public:
Sponsor: CDOT Region 1
Project Scope
Pool contains bridge-related improvements and repairs based on the new
FASTER Bridge Enterprise funding program (Colorado Senate Bill 108) in CDOT
Region 1.
Affected County(ies)
Adams
Arapahoe
Broomfield
Denver
Douglas
Jefferson
All pool project funding depicts federal and/or state funding only.
Facility Name
Start-At and End-At
I-70
Over UPRR
York St
Cost
(1,000s)
Cost
(1,000s)
Facility Name
(Cont)
Start-At and End-At
$11,934
US-287 (Federal)
Over BNFN at 69th Ave
Over I-270
$17,380
County Rd
Over I-70
$7,296
I-70 WB
Over US 6, Clear Creek
$30,000
US-36
Over Draw
$3,379
I-70 Frontage Rd
Over Clear Creek
$3,910
SH-9
Over Platte Gulch
Amounts in $1,000s
Prior
Funding
FY16
$113
FY19
FY20-21
I-70 Viaduct
(see TIP ID-2016-003)
US-85
Sand Creek
Future
Funding
$0
$0
$0
$0
$11,000
$4,154
$17,000
$54,773
$0
$0
$0
$0
$0
$0
$11,000
$4,154
$17,000
$54,773
$0
Local
Total
FY18
Start-At and End-At
Cost
(1,000s)
$113
$874
$0
Federal
State (FASTER-B)
FY17
$12,154
Facility Name
(Cont)
Total
Funding
$0
$87,040
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
02/21/2013
Amended
Add $113,000 of state FASTER Bridge funds in FY2013 allocating to new project: US-85 over Sand Creek ($113,000). Increase total project
funding.
03/13/2012
Amended
Add $3,600,000 of state FASTER Bridge Enterprise funding in FY2012 allocating to: US-85 over Oxide Draw ($1,500,000) and US-85 over Highlands
Gulch ($2,100,000). Increase total project funding.
12/15/2011
Amended
Add $1,617,000 of state FASTER Bridge funding in FY2012 allocating to pool project SH-36 Bridge over Comanche Creek. Increase total project
funding.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
03/15/2011
Amended
Add $240,000 of state FASTER Bridge Enterprise funds to FY2011 allocating to SH-36 Bridge over Comanche Creek. Increase total project funding.
09/14/2010
Amended
Add one project to the pool under state Bridge Enterprise funds in FY 2011; SH-36 over Comanche Creek (Design) for $216,000.
57
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 1 FASTER Transit Pool
TIP-ID: 2008-105
Project Type: Transit Operational
Improvements
STIP-ID: SR17004
Open to Public:
Sponsor: CDOT Region 1
Project Scope
Pool contains transit-related projects based on the new FASTER Transit
program (Colorado Senate Bill 108) in CDOT Region 1 (DRCOG TIP-area only).
Affected County(ies)
Adams
Arapahoe
Douglas
Jefferson
All pool project funding depicts federal and/or state funding only.
Facility Name
Start-At and End-At
Seniors Resource
Center
purchase vehicles (FY12)
RTD
US-285/Pine Junction park-nRide (FY12)
Castle Rock
Senior Center Shuttle Bus
Replacement (FY13)
Seniors Resource
Center
Cost
(1,000s)
Cost
(1,000s)
Facility Name
(Cont)
Start-At and End-At
Seniors Resource
Center
Evergreen Vehicle Purchase
(FY14)
Arvada
Olde Towne Arvada Bus
Transfer phase 2
$50
RTD
Civic Center Station Phase II
$595
“Fix it First” Improvements to
Evergreen Transit Facility
(FY13)
$41
Seniors Resource
Center
Vehicle Replacements - SRC
Urban and A-Lift
$48
Douglas County Transit To the Rescue (TTR) Transit
Solutions
(FY14)
$227
RTD
Thornton Park-n-Ride
Expansion
Amounts in $1,000s
Prior
Funding
$26
$960
FY16
FY17
FY18
FY19
$1,339
FY20-21
Superior/Louisville
DDI Transit Improvements
$464
Thornton
SH 7 at I-25 Carpool Lot
$522
RTD
Church Ranch P-n-R Boarding
Platforms Relocation
Future
Funding
$0
$0
$0
$0
$0
State (Faster-T)
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$8,493
Start-At and End-At
$1,266
$997
Federal
Total
$26
Cost
(1,000s)
Facility Name
(Cont)
Total
Funding
$0
$8,493
Date
Status
Description
05/05/2015
Proposed
Add $1,240,000 of state FASTER Transit funds in FY2016. Add the following projects in FY2016 and corresponding amounts; East Colfax/15L
Transit Enhancements Project (RTD) for $770,000 and Speer Blvd Light Rail Crossing Repair and Replacement (RTD) for 470,000. Increase total
project funding.
05/05/2015
Amended
Proposed for adoption into 2016-2021
06/26/2014
Amended
Add $5,660,277 of state FASTER Transit funds in FY2015 and $1,132,055 in local safety funds in FY2015. Add the following projects and
corresponding state funding amounts to the pool; Arvada Olde Towne Arvada Bus Transfer Facility phase 2 for $1,338,521; RTD Civic Center
Station Phase II for $594,879; Seniors Resource Center Vehicle Replacements – SRC Urban and A-Lift for $48,000; RTD Thornton Park-n-Ride
Expansion for $997,404; Superior/Louisville DDI Transit Improvements for $463,610; Thornton SH 7 at I-25 Carpool Lot for $521,988; and RTD
Church Ranch P-n-R Boarding Platforms Relocation for $1,265,863. Increase total project funding.
03/15/2013
Amended
Add $253,000 of state FASTER Transit funds and $63,000 of local match in FY2014 allocating to the following new pool projects: Seniors' Resource
Center- Evergreen Vehicle Purchase ($26,000), and Douglas County Transit Solutions- To the Rescue (TTR) Transit ($227,000). Increase total
project funding.
03/13/2012
Amended
Add $91,000 of state FASTER Transit funding and $22,000 of local match in FY2013 allocating to: Castle Rock Senior Center Shuttle Bus
Replacement ($50,000) and Seniors’ Resource Center (SRC) “Fix it First” Improvements to Evergreen Transit Facility ($41,000). Increase total
project funding.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
12/22/2010
Amended
Add 3 projects to the pool under FASTER Transit funds in FY2011 and FY2012 totaling $1,272,000, including local match. Specific projects listed in
the scope. Increase total project funding.
58
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 4 FASTER Transit Pool
TIP-ID: 2008-106
Project Type: Transit Operational
Improvements
STIP-ID: SR47005
Open to Public:
Sponsor: CDOT Region 4
Project Scope
Pool contains transit-related projects based on the FASTER Transit program
(Colorado Senate Bill 108) in CDOT Region 4 (DRCOG-TIP area only).
Affected County(ies)
Boulder
Weld
All pool project funding depicts federal and/or state funding only.
Facility Name
Start-At and End-At
Boulder
14th/Walnut Tran. Center
Improv. (Prior Funding)
Boulder
Transit Stop Enhancements
(Prior Funding)
Boulder County
Bus Stop Improvements (Prior
Funding)
RTD
US-287 and Niwot pnR
Expansion (Prior Funding)
Amounts in $1,000s
Prior
Funding
Cost
(1,000s)
FY16
Cost
(1,000s)
Facility Name
(Cont)
Start-At and End-At
$370
RTD
Tantra Dr pnR upgrades (Prior
Funding)
$230
Boulder County
Special Transit Mountain
Service (Prior Funding)
$84
eGO Car Share
$280
36 Commuting
Solutions
FY17
FY18
Start-At and End-At
City of Boulder
Broadway Euclid Transit Stop
Improvements (Prior Funding)
$350
$54
CDOT DTR
Service Development Plan for
Front Range Commuter Rail
(Prior Funding)
$352
“SHIFT” (Shared Hubs
Integrated for Transp CMAQ
Match (Prior Funding)
$18
CDOT Region 4
DDI Transit Improvements
(Prior Funding)
$964
Prepaid Pass Kiosks for US36 BRT (Prior Funding)
$781
FY19
FY20-21
$0
$0
$0
$0
$0
State (Faster-T)
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$5,374
$284
Future
Funding
Federal
Total
Cost
(1,000s)
Facility Name
(Cont)
Total
Funding
$0
$5,374
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
03/15/2013
Amended
Add $1,017,000 in FY2014 and $579,000 in FY2015 of state FASTER Transit funds and $255,000 in FY2014 and $144,000 in FY2015 of local match,
allocating to the following new projects: CDOT DTR - Service Development Plan for Front Range Commuter Rail ($352,000), CDOT Region 4- DDI
Transit Improvements (statewide funds) ($964,000); as well as additional funding for the following existing projects: Boulder- 14th/Walnut Tran.
Center Improvements (statewide funds) ($370,000- removing $200,000 of FY11 funds and adding $170,000 of FY14 funds), and Boulder- Transit
Stop Enhancements ($230,000- removing $120,000 of FY11 funds and adding $110,000 of FY14 & 15 funds). Reduce state FASTER Transit funds
by $16,000 and local match by $4,000 in FY2012 to reconcile with pool project totals. Transfer $240,000 of state FASTER Transit funds and
$60,000 of local match in FY2012 to TIPID #2012-051 and remove pool project Boulder County- SH119 Ped Underpass. Increase total project
funding.
03/13/2012
Amended
Add $1,767,000 of state FASTER Transit funding and $355,000 of local match in FY2013 allocating to: US-287 and Niwot pnR Expansion (statewide
funds) ($280,000), Tantra Dr pnR upgrades (statewide funds) ($284,000), Boulder County Special Transit Mountain Service ($54,000), eGO Car
Share “SHIFT” CMAQ Match TIP-ID #1997-097 ($18,000), 36 Commuting Solutions Prepaid Pass Kiosks for US-36 BRT (statewide funds)
($781,000), and Boulder Broadway Euclid Transit Stop Improvements ($350,000). Increase total project funding.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
12/22/2010
Amended
Add 6 projects to the pool under FASTER Transit funds in FY2011 and FY2012 totaling $1,577,000, including local match. Specific projects listed in
the scope. Increase total project funding.
59
2016-2021 Transportation Improvement Program (Approved TIP)
Title: FasTracks Eagle P-3 Corridors (Gold and East Line)
TIP-ID: 2008-111
STIP-ID:
Project Type: Rapid Transit
Open to Public: 2016
Sponsor: R T D
Project Scope
Build electrified commuter rail line running from Denver Union Station to Denver
International Airport (East Line) and Denver Union Station to Ward Rd (Gold
Line). Projects being combined at the request of FTA due to outcome of P-3
process. Former East Corridor TIP-ID 2007-052 and Gold Line Corridor TIP-ID
2007-054.
FasTracks Second Commitment in Principal STP-Metro funding for I-225 in
FY16 will support double tracking in portions of the East Corridor.
Affected Municipality(ies)
Affected County(ies)
Arvada
Adams
Aurora
Denver
Denver
Jefferson
Wheat Ridge
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$0
$0
$0
$0
$0
Federal (5309S)
$165,000
$150,000
$45,950
$0
$0
Federal (STP-M)
$3,650
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$913
$0
$0
$0
$0
$140,729
$140,856
$41,696
$0
$0
$310,292
$290,856
$87,646
$0
$0
Federal
Local (RTD)
Total
$1,224,211
Total
Funding
$0 $1,913,005
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
09/18/2014
Amended
Add language to scope and add $984,000 in federal STP-Metro funds transferred from TIP ID 2012-084 in FY2014 for the North Metro Corridor's
FasTracks Second Commitment in Principle funding, which will support Gold Line 60th Avenue improvements. Increase total project funding.
06/26/2014
Amended
Revise 8/16/2012 amendment to move the I-225 Second Commitment in Principal project location from the Peoria/Smith station to double tracking
in portions of the East Corridor. Add additional language to the scope to reflect this. Total project funding remains unchanged.
10/15/2012
Amended
Reduce local match by $8,951,000 in FY2013, $3,650,000 in FY2014, and $3,600,000 in FY2015 which should have been removed previously with
the addition of new federal funds. Decrease total project funding.
08/16/2012
Amended
Add $3,600,000 in FY2015 and $3,650,000 in FY2016-17 of federal CMAQ funds for the I-225 Corridor's FasTracks Second Commitment in Principle
funding, which will support the Peoria/Smith Station. Increase total project funding.
08/06/2012
Amended
Add $7,161,000 of federal CMAQ funds and $1,790,000 of local match in FY2013 representing $700,000 of the North West Corridor's federal funds
and all ($6,461,000) of the Gold Corridor's federal funds from FasTracks: DRCOG Second Commitment in Principle Pool (TIP ID 2012-010).
Increase total project funding.
12/05/2011
Amended
Reallocate $2,000,000 of federal CMAQ funds and $500,000 of local match from FY2014 to FY2012 and $2,000,000 of federal CMAQ funds,
$3,000,000 of STP Metro and $1,250,000 of local match from FY2013 to FY2012. Total project funding remains unchanged.
11/17/2011
Amended
Add $2,000,000 in FY2012, $2,000,000 in FY2013, and $2,000,000 in FY2014 of federal Congestion Mitigation / Air Quality (CMAQ) funds and
$3,000,000 in FY2012, $3,000,000 in FY2013, and $1,350,000 in FY2014 of federal STP Metro funds. Increase total project funding.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
12/22/2010
Amended
Transfer prior Gold Line (2007-054) and East Line (2007-052) federal Section 5309 New Starts and RTD local funding into single project.
60
2016-2021 Transportation Improvement Program (Approved TIP)
Title: US-36: Boulder to I-25 Managed Lanes/BRT
TIP-ID: 2008-114
Project Type: Roadway Capacity
STIP-ID: SDR2073
Open to Public: 2016
Sponsor: HPTE
Project Scope
Construction of managed lanes/BRT on US-36 from Table Mesa Dr to I-25
Express Lanes.
2016-2021 TIP funding will construct ancillary enhancements.
2012-2017 TIP funding constructed an extension of the Managed Lane/BRT
Facilities/US-36 Bikeway from the current terminus west to Table Mesa.
Affected Municipality(ies)
Affected County(ies)
Broomfield
Adams
Westminster
Boulder
Broomfield
Jefferson
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal
$0
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
$8,000
$838
$0
$0
$0
$8,000
$838
$0
$0
$0
Local (RTD)
$452,278
Total
$264,184
Total
Funding
$725,300
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
12/20/2013
Amended
Add $71,800,000 of local Private funds in FY2014. Increase total project funding.
08/21/2013
Amended
Add $3,000,000 of State Transportation Committee (STC) Discretionary funds in FY2014. Increase total project funding.
12/05/2012
Amended
Transfer $1,500,000 of state Regional Priority Project (RPP) funds from Future Funds to FY2013. Total project funding remains unchanged.
10/04/2012
Amended
Add $3,805,000 of federal STP Metro funds, $9,742,000 of federal CMAQ funds, and $67,637,000 of local match in FY2013 and $1,453,000 of
federal STP Metro funds and $363,000 of local match in FY2015. Increase total project funding.
09/18/2012
Amended
Reallocate $4,000,000 of state STC Discretionary funds from Future Funds to FY2013. Update project scope by changing the project terminus from
Interlocken to Table Mesa. Total project funding remains unchanged.
05/04/2012
Amended
Reallocate $2,000,000 of state Regional Priority Project (RPP) funding from Future Funding to FY2012. Total project funding remains unchanged.
04/10/2012
Amended
Reallocate $2,500,000 of state Regional Priority Project (RPP) funding from Future Funding to FY2012. Total project funding remains unchanged.
03/13/2012
Amended
Reallocate $2,000,000 of state Regional Priority Project (RPP) funding from Future Funding to FY2012. Total project funding remains unchanged.
10/18/2011
Amended
Reallocate $410,000 in federal STP-Metro funds and $1,467,000 in federal CMAQ funds from FY2013 to FY2012 and $9,408,000 in federal STPMetro and $730,000 in federal CMAQ funds from FY2014 to FY2012. Total project funding remains unchanged.
08/18/2011
Amended
Advance $60,000,000 from future funding to FY2012 per FHWA request and show $6,000,000 as federal TIGER funds and $54,000,000 as federal
TIFIA funds. Total funding remains unchanged.
04/20/2011
Amended
1) Advance project funds. Decrease future funding by $90,000,000 and allocate $30,000,000 to FY2012, $30,000,000 to FY2013, and $30,000,000
to FY2014 as RTD local funds. 2) Change scope from “…west of Wadsworth Blvd to E. Flatirons Cir.” to “…from the current terminus west to
Interlocken or further, if funding allows.” 3) Shift project funds. Shift $3,125,000 of Prior Funding to FY2012 and distribute $2,500,000 in state
FASTER Transit funds and $625,000 in local match (RTD). 4) Correct previous mistake by removing local match for CMAQ and STP Metro funding.
FASTER Transit and RTD funds will be used for matching these two federal funds. Total funding remains unchanged.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
04/20/2011
Amended
Shift $2,500,000 in state FASTER Transit funds and $625,000 in local match from FY2011 to FY2012-13. Total funding remains unchanged.
03/02/2011
Amended
61
2016-2021 Transportation Improvement Program (Approved TIP)
Title: DRCOG Second Commitment to FasTracks Pool
TIP-ID: 2012-010
STIP-ID:
Project Type: Transit Operational
Improvements
Open to Public:
Sponsor: DRCOG
Project Scope
Set aside to fund second commitment in principle to FasTracks corridors not yet
allocated. Individual projects will be TIP’d upon approval of Policy Amendments
per the process and requirements of DRCOG Resolution 20-2008 (July, 2008).
Corridor projects previously approved using second commitment funds include:
- West Corridor (TIP ID 2007-042)- July 2010, $7,422,000
- US-36 Corridor (TIP ID 2008-114)- Feb 2011, $2,755,000
- Denver Union Station (TIP ID 2007-057)- July 2010, $2,519,000
- East Corridor (TIP ID 2008-111)- Nov 2011, $13,350,000.
- Gold Corridor (TIP ID 2008-111)- May 2012, $6,461,000.
- Northwest Corridor (TIP ID 2007-050)- May 2012, $1,200,000.
- North Metro Corridor (TIP ID 2007-055)- May 2012, $7,451,000.
- I-225 Corridor (TIP ID 2007-056)- July 2012, $7,250,000.
Remaining allocations include:
- Northwest Corridor $6,803,000
- Southeast Extension $1,928,000
- Southwest Extension $2,089,000
- Central Corridor $771,000
Affected County(ies)
Regional
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal (CMAQ)
$4,073
$0
$0
$0
$0
Federal (STP-M)
$6,518
$1,000
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$2,648
$250
$0
$0
$0
$13,239
$1,250
$0
$0
$0
$0
Total
Total
Funding
$0
$14,489
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
11/07/2012
Amended
Transfer funds to new TIP Projects TIP ID 2012-100 and 2012-101. Remove all funds in FY2016-17 and reduce Future Funding to $16,165,000 to
reflect amount remaining after Board Action on July 27, 2012. Update project scope, increasing North Metro Corridor's approved funding to
$7,451,000. Decrease total project funding.
08/06/2012
Amended
Transfer $600,000 from FY2013, $200,000 from FY2014, $1,200,000 from FY2015 and $3,650,000 from FY2016-17 of federal CMAQ funds,
$1,650,000 from FY2014 and $3,000,000 from FY2015 of federal STP-Metro funds, and $150,000 from FY2013, $463,000 from FY2014 ,
$1,050,000 from FY2015, and $913,000 from FY2016-17 of local match to projects receiving Second Commitment in Principal funds for the Gold,
Northwest, North Metro, and I-225 Corridors. Decrease total project funding.
12/05/2011
Amended
Reallocate $600,000 of federal CMAQ funds and $150,000 of local match from FY2015 to FY2013 and $200,000 of federal CMAQ funds and $50,000
of local match from FY2015 to FY2014. Total project funding remains unchanged.
11/17/2011
Amended
Transfer $2,000,000 in FY2012, $2,000,000 in FY2013, and $2,000,000 in FY2014 of federal Congestion Mitigation / Air Quality (CMAQ) funds, and
$3,000,000 in FY2012, $3,000,000 in FY2013, and $1,350,000 in FY2014 of federal STP Metro funds to TIP ID #2008-111 and remove $1,250,000
in FY2012, $1,250,000 in FY2013, and $837,500 in FY2014 of local match. Update title, scope, and funding to reflect pool as only showing
remaining unallocated funds. Decrease total project funding
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
62
2016-2021 Transportation Improvement Program (Approved TIP)
Title: SH-119: South of Hover Bike/Ped Underpass
TIP-ID: 2012-051
Project Type: Bicycle and Pedestrian
Projects (New)
STIP-ID: SDR7007.009
Open to Public: 2017
Sponsor: Longmont
Project Scope
Project constructs a new multi-use underpass at least 8 ft wide and sidewalk
connection under SH-119 south of the Hover St intersection. Additionally
includes easements for a walkway, access to transit stops, and a midblock
crossing of Hover south of SH-119, completing a gap between the multi-use trail
along Hover with a similar trail on SH-119. The project will provide 20 bicycle
parking spaces (10 of the spaces covered) as well as new ADA/AASHTO
compliant lighting.
Affected Municipality(ies)
Affected County(ies)
Longmont
Boulder
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$955
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$746
$0
$0
$0
$0
$1,701
$0
$0
$0
$0
Federal (CMAQ)
$295
Total
Total
Funding
$0
$1,996
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
12/11/2013
Amended
Transfer $955,000 of federal CMAQ funds and $746,000 of local match from FY2015 to FY2016. Total project funding remains unchanged.
04/09/2013
Amended
Transfer $120,000 in FY2012 and $490,000 in FY2014 of state FASTER Transit funds and $30,000 in FY2012 and $123,000 in FY2014 of local
match to TIPID #2012-058. Decrease total project funding.
03/15/2013
Amended
Add $490,000 of state FASTER Transit funds and $123,000 of local match in FY2014. Receives $240,000 of state FASTER funds and $60,000 of
local match in FY2012 transferred from TIPID #2008-106. Increase total project funding
10/18/2011
Amended
Reallocate $10,000 in federal CMAQ funds and $100,000 in local match from FY2013 to FY2012. Total project funding remains unchanged.
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
63
2016-2021 Transportation Improvement Program (Approved TIP)
Title: I-70/Kipling: NEPA Study
TIP-ID: 2012-062
Project Type: Roadway/Transit Studies
STIP-ID:
Open to Public:
Sponsor: CDOT Region 1
Project Scope
Funding for activities post PEL.
Affected Municipality(ies)
Affected County(ies)
Wheat Ridge
Jefferson
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal
$0
$0
$0
$0
$0
State (R P P)
$0
$1,600
$500
$0
$0
Local
$0
$0
$0
$0
$0
$0
$1,600
$500
$0
$0
$1,000
Total
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
04/06/2011
Adopted
Adopted into the 2012-2017 TIP
64
Total
Funding
$0
$3,100
2016-2021 Transportation Improvement Program (Approved TIP)
Title: I-25 North PEL Action Items
TIP-ID: 2012-063
Project Type: Roadway Operational
Improvements
STIP-ID: SDR7067.999
Open to Public:
Sponsor: CDOT Region 1
Project Scope
The PEL Study will look at operational and safety improvements on I-25 from US
-36 to SH-7 to provide relief to the existing general purpose lanes.
Affected County(ies)
Adams
Amounts in $1,000s
Prior
Funding
FY16
FY17
$15,500
FY20-21
Future
Funding
$0
$0
$0
$0
$900
$1,100
$0
$0
$0
$0
$0
$0
$0
$0
$900
$1,100
$0
$0
$0
Local
Total
FY19
$0
Federal
State (R P P)
FY18
Total
Funding
$0
$17,500
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
06/20/2011
Amended
Project receives transfer of $2,000,000 in FY2013, $1,400,000 in FY2014, and $5,500,000 in FY2015 of state FASTER Safety funds from TIP ID
#2008-078, $1,100,000 in state Congestion Relief funds in FY2014 from TIP ID #2007-093, and $5,500,000 in state Surface Treatment funds in
FY2013 from TIP ID #2001-214 ($2,300,000 of which was previously unprogrammed). Increase total project funding.
65
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Regional TDM Program: Way to Go
TIP-ID: 2012-064
Project Type: Congestion Management
STIP-ID: SST6803.069
Open to Public:
Sponsor: DRCOG
Project Scope
DRCOG will partner with transportation management agencies in the region to
cooperatively carry out a comprehensive and coordinated program to mitigate
traffic congestion and poor air quality through reducing travel demand. As part of
The Program, DRCOG will offer:
(a) Web-accessible CarPool matching programs for individuals and employers
(b) SchoolPool programs with web-accessible matching software
(c) Vanpool Services with web-accessible matching software
(d) Telework programs
(e) Regional Bike to Work Day Coordination
(f) Guaranteed Ride Home programs
(g) Support, Assistance, Materials, and Collateral for DRCOG services
(h) Regional TDM web-page, portal, and web-applications supportive of The
Program
(i) Regional TDM services telephone numbers
(j) Customer service staff for written, telephone, or email referrals, inquiries or
issues
(k) Developing and maintaining a marketing program to efficiently and effectively
meet Program goals
(l) Conducting surveys to determine the benefits of The Program
(m) Reporting Program outcomes
(n) Business Outreach
(o) Maintaining an employer outreach database for shared use
(p) Providing training and facilitating professional development opportunities
Affected County(ies)
Regional
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$3,600
$0
$3,600
$0
$0
State
$0
$0
$0
$0
$0
Local
$226
$0
$226
$0
$0
$3,826
$0
$3,826
$0
$0
Federal (CMAQ)
$0
Total
Total
Funding
$0
$7,652
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
10/04/2012
Amended
Reallocate $1,800,000 of federal CMAQ funds, and $113,000 of local match from FY2015 to FY2014. Total project funding remains unchanged.
10/18/2011
Amended
Reallocate $1,800,000 in federal CMAQ funds and $113,000 in local match from FY2013 to FY2012. Total project funding remains unchanged.
06/20/2011
Amended
Project receives transfer of $1,800,000 in FY2012, $1,800,000 in FY2013, $1,800,000 in FY2014, and $1,800,000 in FY2015 of federal CMAQ funds
and $113,000 in FY2012, $113,000 in FY2013, $113,000 in FY2014, and $113,000 in FY2015 of local match from TIP ID #1997-044. Increase total
project funding.
66
2016-2021 Transportation Improvement Program (Approved TIP)
Title: RTD Regional Workforce Initiative Now (WIN)
TIP-ID: 2012-068
Project Type: Rapid Transit
STIP-ID: SST7041.001
Open to Public:
Sponsor: R T D
Project Scope
The Workforce Initiative Now (WIN) program is a sector-based workforce
partnership that leverages existing training providers to assess, train and place
community members into careers in transportation and transit construction. WIN
helps businesses attain qualified local workers, supports regional job creation by
connecting Colorado contractors with federally funded transit infrastructure
projects and provides local residents with skills development training, jobs, and
career pathways related to occupations within transportation and transitconstruction.
Affected County(ies)
Regional
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$487
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$487
$0
$0
$0
$0
$974
$0
$0
$0
$0
Federal (WIN)
$584
Total
Total
Funding
$0
$1,558
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
01/23/2012
Amended
Add $487,000 of federal Workforce Initiative Now (WIN) funds and $97,000 of local match to Previous Funds.
67
2016-2021 Transportation Improvement Program (Approved TIP)
Title: North Metro Rail 112th Ave Corridor Improvements
TIP-ID: 2012-079
STIP-ID:
Project Type: Bicycle and Pedestrian
Projects (New)
Open to Public: 2018
Sponsor: Northglenn
Project Scope
Project constructs a new 10 ft multi-use trail on the north side of 112th Ave from
Washington St to York St, a new 10 ft multi-use trail from 112th Ave, north along
the west side of York St leading to the 112th Ave FasTracks Station, and ADA
compliant access at all road crossings. Additionally, project widens 112th Ave
including the installation of box-culverts to direct the existing drainage into
“underground” facilities, allowing the trail system to pass unobstructed on the
surface at 112th Ave/Larson Dr and 112th Ave/Irma Dr. Also includes all right of
way, easements, design and environmental clearance.
Affected Municipality(ies)
Affected County(ies)
Northglenn
Adams
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$99
$728
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$25
$207
$0
$0
$0
$124
$935
$0
$0
$0
Federal (STP-M)
$0
Total
Total
Funding
$0
$1,059
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
08/06/2012
Amended
Add $99,000 of STP-Metro and $25,000 of local match in FY2016-17 and $728,000 of STP-Metro and $207,000 of local match in Future Funds.
68
2016-2021 Transportation Improvement Program (Approved TIP)
Title: North Metro Rail 72nd Ave and Colorado Blvd Station Sidewalks
TIP-ID: 2012-080
STIP-ID:
Project Type: Bicycle and Pedestrian
Projects (New)
Open to Public: 2018
Sponsor: Commerce City
Project Scope
Project constructs the following facilities on Colorado Blvd from East 68th Ave to
East 72nd Ave:
1. Curb, gutter, and a 5-foot wide (minimum) sidewalk along both sides of the
street.
2. Drainage improvements, including inlets, manholes and RCP piping
3. Street lighting spaced at 300 foot intervals on both sides of the street.
Affected Municipality(ies)
Affected County(ies)
Unincorporated
Adams
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$185
$1,357
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$46
$339
$0
$0
$0
$231
$1,696
$0
$0
$0
Federal (STP-M)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
08/06/2012
Amended
Add $1,542,000 of federal STP-Metro funds and $385,000 of local match in FY2016-17.
69
Total
Funding
$0
$1,927
2016-2021 Transportation Improvement Program (Approved TIP)
Title: RTD Capital Improvements: Bus and Facilities Funding
TIP-ID: 2012-108
STIP-ID:
Project Type: Transit Vehicles
Open to Public:
Sponsor: R T D
Project Scope
Funds will be directed to capital improvements including the following:
1 - Civic Center Station infrastructure improvements including improvements to
the building, access areas, boarding areas, shelters, and overall accessibility
through reconfiguration of adjacent park area;
2 - Funds will also be used to purchase fuel efficient buses and vans equipped
with ADA-compliant lifts.
Affected County(ies)
Regional
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$5,209
$5,261
$5,314
$5,367
$10,743
State
$0
$0
$0
$0
$0
Local
$1,042
$1,053
$1,063
$1,074
$2,147
$6,251
$6,314
$6,377
$6,441
$12,890
Federal (5339)
$0
Total
Total
Funding
$0
$38,273
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
12/19/2013
Amended
Add federal Section 5339 funding of $5,106,000 in both FY2013 and FY2014, $5,158,000 in FY2015, and $10,470,000 in FY2016-2017. Add
corresponding local match of $1,277,000 in both FY2013 and FY2014, $1,289,000 in FY2015, and $2,617,000 in FY2016-2017.
70
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 4 RAMP Project Pool
TIP-ID: 2012-109
Project Type: Other
STIP-ID:
Open to Public:
Sponsor: CDOT Region 4
Project Scope
Pool contains projects selected under the RAMP program in CDOT Region 4
(DRCOG-TIP area only).
Projects selected under RAMP that are Regionally Significant will be depicted
individually.
Affected Municipality(ies)
Affected County(ies)
Boulder
Boulder
Longmont
Weld
All pool project funding depicts federal and/or state funding only.
Cost
(1,000s)
Facility Name
Start-At and End-At
SH-119: Boulder
Canyon
Trail Extension (MP 39.1-37.8)
Amounts in $1,000s
Prior
Funding
FY16
$3,498
Facility Name
(Cont)
Start-At and End-At
US-287 (Main St.
Longmont) Adaptive
Signals
MP 313.8-318.7
FY17
FY18
FY19
Cost
(1,000s)
FY20-21
Future
Funding
$0
$0
$0
$0
State (RMP)
$3,723
$875
$0
$0
$0
Local
$1,316
$219
$0
$0
$0
$5,039
$1,094
$0
$0
$0
$8,513
Total
Start-At and End-At
Cost
(1,000s)
$1,100
$0
Federal
Facility Name
(Cont)
Total
Funding
$0
$14,646
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021
03/19/2015
Amended
Change funding source from State RPP funds to State RAMP funds.
12/19/2013
Amended
Add 4 new projects selected from the RAMP program in FY2014-2017 totaling $14,646,000, including local match. Specific projects are listed in the
pool.
71
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 1 RAMP Project Pool
TIP-ID: 2012-112
Project Type: Other
STIP-ID:
Open to Public:
Sponsor: CDOT Region 1
Project Scope
Pool contains projects selected under the RAMP program in CDOT Region 1.
Projects selected under RAMP that are Regionally Significant will be depicted
individually.
Affected County(ies)
Adams
Arapahoe
Broomfield
Denver
Douglas
Jefferson
All pool project funding depicts federal and/or state funding only.
Facility Name
Cost
(1,000s)
Start-At and End-At
New ramp meters and
upgrades
Amounts in $1,000s
Facility Name
(Cont)
Cost
(1,000s)
Start-At and End-At
Facility Name
(Cont)
Start-At and End-At
Cost
(1,000s)
$999
Prior
Funding
FY16
FY17
$2,745
FY20-21
Future
Funding
$0
$0
$0
$0
$999
$0
$0
$0
$0
$0
$0
$0
$0
$0
$999
$0
$0
$0
$0
Local
Total
FY19
$0
Federal
State (RMP)
FY18
Total
Funding
$0
$3,744
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into 2016-2021 TIP
12/19/2013
Amended
Add 9 new projects selected from the RAMP program in FY2014-2017 totaling $5,680,000, including local match. Specific projects are listed in the
pool.
72
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 1 Rockfall Mitigation
TIP-ID: 2012-115
Project Type: Safety
STIP-ID: SDN6678
Open to Public:
Sponsor: CDOT Region 1
Project Scope
Rockfall mitigation in multiple locations within CDOT Region 1.
Affected County(ies)
Jefferson
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal
$0
$0
$0
$0
$0
State (Safety)
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$1,500
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
03/10/2014
Amended
Allocate $1,500,000 in state Safety funds in FY2015.
73
Total
Funding
$0
$1,500
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 4 2013 Flood-Related Projects Pool
TIP-ID: 2012-116
Project Type: Roadway Reconstruction
STIP-ID:
Open to Public:
Sponsor: CDOT Region 4
Project Scope
Pool contains flood-related repair projects from the fall of 2013 flood event.
Affected County(ies)
Boulder
Weld
All pool project funding depicts federal and/or state funding only.
Facility Name
Start-At and End-At
ERLA 47th St
Cost
(1,000s)
Facility Name
(Cont)
Start-At and End-At
@ Fourmile Canyon Creek
ERLA Sunset Bridge
ERLA 55th St/Cypress
Ave
@ Big Dry Creek
ERLA Table Mesa Dr
ERLA Lehigh
Cost
(1,000s)
Facility Name
(Cont)
Start-At and End-At
@ St. Vrain Creek T19
ER SH 7 St. Malo
MP 11
ERLA Boston Bridge
@ St Vrain Creek T17
ER US36
MP21
Lehigh To Broadway
ERLA 57th St
@ Fourmile Canyon Creek
T22
PR US36
D-15-X D-15-I
Table Mesa to Cragmoor
ERLA 75th Ave St
Repairs T24
PR SH7 Flood Repair
MP 19-33
$0
ERLA Violet Ave Bridge @ Fourmile Canyon Creek
$0
ERLA Kenosha Rd T25
in Erie
PR SH 119A
Boulder Canyon
19th St
@ Fourmile Canyon Creek
$0
ERLA Valmont Rd
Bridge
@ S. Boulder Creek
PR SH 119B
MP 52.9 to 60.0
26th St
@ Fourmile Canyon Creek
$0
ERLA 95th St
@ Left Hand Creek
PR SH 170
MP 1.08 to 3.64
ERLA Baseline Rd
@ S Boulder Creek Path
$0
ERLA Airport Rd
@ Left Hand Creek
PR SH 72B Resurfacing
ERLA Pike Rd
@ Lefthand Creek Longmont
PR SH 52 Flood Repair MP 6.9 to 7.2
ERLA Airport Rd
@ BNSF RR
ERLA Bella Rosa
Pkwy/WCR 20 Repairs
ERLA WCR 7 Repairs
ERLA Lefthand Canyon
Drive T01
ERLA 63rd St
@ Lefthand Creek
$0
ERLA 73rd St
@ Lefthand Creek T11
ERLA 9th Ave (Ss)
E Hayden Ct
ERLA Dillon Rd
Over Rock Creek T28
ERLA 95th St
Over Coal Creek Bridge Repl
$0
ERLA Godding Hollow
Parkway/WCR 18
ERLA Sunshine
Canyon Drive Detour
T29
ERLA Dillon Rd
Underpass Repairs
ERLA Ecl/WCR1 Bridge @ Bldr Creek T20
ERLA Left Hand
Canyon Dr.
MP 16.2 - 16.8
ER SH119 DelCamino
D-16-CG
ERLA 95th St
ER SH 7 Lyons to
Raymond
MDB
ER SH66
@ CR17
ERLA 71st St Pipe T23
ER SH119
MP 26-41
PR SH 119
MP 61.5-63.9
ERLA Valmont At Dry
Creek T09
ER US36
Just South of SH66
PR SH66B Permanent
Flood Repairs
ERLA South Boulder
Road Repair T27
ER US36
MP 28 D-15-X
@ Boulder Creek T14
ERLA Ecl Rd/WCR 1
Amounts in $1,000s
@ St Vrain Creek T19
Prior
Funding
ERLA WCR 13 CR 26A Over St Vrain
Bridge
ER CROOK FLOOD
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$37,603
$11,161
$2,444
$0
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$37,603
$11,161
$2,444
$0
$0
Federal (EMR)
$78,304
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
74
Total
Funding
$0
$129,512
Cost
(1,000s)
Date
Status
Description
09/18/2014
Amended
Create a new pool for permanent repair projects related to the 2013 floods. Transfer $20,098,000 in federal Emergency funds from TIP ID 2012114 in FY2014. Allocate $11,020,000 of federal Emergency funds in FY2014; $47,186,000 in FY2015; $48,764,000 in FY2016-17; and $2,444,000 in
future years. Add 55 projects to the pool.
75
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Air Quality Improvements Pool
TIP-ID: 2016-002
Project Type: Air Quality Improvement
Projects
STIP-ID:
Open to Public: 2016
Sponsor: R A Q C
Project Scope
Funding for three specialized air quality improvement activities:
1 - Conduct a Call for Projects for local agency air quality projects, as allocated
and administered by RAQC
2 - Advance Fleet Technology. Implements a large vehicle retrofit, repair, and
replacement program targeting older, higher polluting vehicles.
3 - Ozone Aware. A public outreach program to increases awareness of groundlevel ozone pollution.
Amounts in $1,000s
Affected County(ies)
Project Phases
Regional
Year
Phase
2016
Initiate Study
2017
Initiate Study
2018
Initiate Study
2019
Initiate Study
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$1,320
$1,800
$1,800
$1,800
$0
State
$0
$0
$0
$0
$0
Local
$330
$450
$450
$450
$0
$1,650
$2,250
$2,250
$2,250
$0
Federal (CMAQ)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
76
Total
Funding
$0
$8,400
2016-2021 Transportation Improvement Program (Approved TIP)
Title: I-70 East Reconstruction
TIP-ID: 2016-003
Project Type: Roadway Reconstruction
STIP-ID:
Open to Public:
Sponsor: CDOT Region 1
Project Scope
Project reconstructs portions of I-70 East in Denver.
Affected Municipality(ies)
Affected County(ies)
Denver
Denver
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal
$0
$0
$0
$0
$0
Federal (CMAQ)
$0
$6,000
$3,000
$16,000
$0
State
$0
$0
$0
$0
$0
$8,080
$752,170
$0
$0
$0
$0
$1,500
$750
$4,000
$0
$8,080
$759,670
$3,750
$20,000
$0
State (FASTER-B)
Local
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
77
Total
Funding
$0
$791,500
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Regional Transportation Operations Pool
TIP-ID: 2016-004
Project Type: Congestion Management
STIP-ID:
Open to Public:
Sponsor: DRCOG
Project Scope
A pool to fund capital improvements to traffic signal systems, traffic signal timing
and coordination work, traffic signal system engineering and design, and
intelligent transportation systems projects.
Affected County(ies)
Regional
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$4,839
$4,200
$4,200
$4,200
$0
State
$0
$0
$0
$0
$0
Local
$1,210
$1,050
$1,050
$1,050
$0
$6,049
$5,250
$5,250
$5,250
$0
Federal (CMAQ)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
78
Total
Funding
$0
$21,799
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Metro Center Station Area Bike/Ped Connector Facility
TIP-ID: 2016-005
STIP-ID:
Project Type: Bicycle and Pedestrian
Projects (New)
Open to Public: 2017
Sponsor: Aurora
Project Scope
This project constructs a new 10 ft wide multi-use bi-directional path near the
Aurora Municipal Center Complex for the following segments:
1) from the south end of the pond to Alameda Pkwy.
2) from Alameda Pkwy southwestwardly to the Metro Center Bus/Light Rail
Station located at Sable Blvd and Centrepoint Dr.
3) from the pond and the Aurora Municipal Center Complex; and
4) replaces an existing 6-ft. wide concrete sidewalk that extends along the east
side of a pond from the base of the High Line Canal embankment near the north
end of the pond to a point near the south end of the pond.
The project will also construct an underpass at Alameda Pkwy, modify existing
pavement striping and traffic signals as needed, install pedestrian-scale
ADA/AASHTO compliant lighting, way-finding signage with destination and
distance information, and 20 or more bicycle parking spaces within 1/2 mile of
the project.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Aurora
Arapahoe
Year
Phase
2016
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$1,832
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$459
$0
$0
$0
$0
$2,291
$0
$0
$0
$0
Federal (STP-M)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
79
Total
Funding
$0
$2,291
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Multi-use path on the D10: Wadsworth Blvd to Zephyr St and Kipling
St to Oak St
TIP-ID: 2016-006
STIP-ID:
Project Type: Bicycle and Pedestrian
Projects (New)
Open to Public: 2019
Sponsor: Lakewood
Project Scope
The project will construct two segments of the D10 bike path.
• a 10 ft multi-use path from Kipling St to Oak St, with MSE retaining walls.
Relocation of the existing sound wall and fences at the rear and side property
lines will be required.
• a 10 ft multi-use path from Zephyr St to Wadsworth Blvd. This segment will be
at grade with a 6" curb to separate the path and the apartment parking lot.
There will be down cast light wall packs attached to the retaining wall.
• land acquisitions will be required in both segments, and include
signage/wayfinding with destinations and distances.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Lakewood
Jefferson
Year
Phase
2016
Initiate Environmental
2016
Initiate Design
2017
Initiate ROW
2018
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$320
$536
$1,064
$0
$0
State
$0
$0
$0
$0
$0
Local
$80
$134
$266
$0
$0
$400
$670
$1,330
$0
$0
Federal (TAP)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
80
Total
Funding
$0
$2,400
2016-2021 Transportation Improvement Program (Approved TIP)
Title: University of Colorado Boulder East Campus Pedestrian Bridge &
Trail Connection
TIP-ID: 2016-007
STIP-ID:
Project Type: Bicycle and Pedestrian
Projects (New)
Open to Public: 2018
Sponsor: University of ColoradoBoulder
Project Scope
Project constructs a 10 ft wide multi-use path and pedestrian/bike bridge from
parking lot 560 on East Campus across Boulder Creek to connect to the existing
Boulder Creek multi-use path.
ADA/AASHTO compliant lighting, signage/wayfinding with destinations and
distances, and 70 bicycle parking spaces within 1/2 mile of the project will also
be constructed as part of the project.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Boulder
Boulder
Year
Phase
2016
Initiate Environmental
2016
Initiate Design
2017
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$132
$254
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$33
$64
$0
$0
$0
$165
$318
$0
$0
$0
Federal (TAP)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
81
Total
Funding
$0
$483
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Boulder Slough Multiuse Path: 30th St to 3100 Pearl
TIP-ID: 2016-008
STIP-ID:
Project Type: Bicycle and Pedestrian
Projects (New)
Open to Public: 2019
Sponsor: Boulder
Project Scope
Project constructs a 10 ft wide multi-use path along the Boulder Slough from
30th St to 3100 Pearl, including a bicycle/pedestrian bridge crossing the Boulder
Slough. Signage and wayfinding with destinations and distances, along with 20
bicycle parking spaces within 1/2 mile of the project will also be constructed as
part of the project.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Boulder
Boulder
Year
Phase
2016
Initiate Environmental
2016
Initiate Design
2017
Initiate ROW
2018
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$96
$96
$288
$0
$0
State
$0
$0
$0
$0
$0
Local
$24
$24
$72
$0
$0
$120
$120
$360
$0
$0
Federal (STP-M)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
82
Total
Funding
$0
$600
2016-2021 Transportation Improvement Program (Approved TIP)
Title: MetroRide Service Expansion: DUS to Civic Center
TIP-ID: 2016-009
STIP-ID:
Project Type: Bus Service Projects
(Expanded)
Open to Public: 2016
Sponsor: R T D
Project Scope
This project will expand the existing service hours and frequencies for the Free
MetroRide. Hours will be extended by approximately four hours (2 hours in the
morning and 2 hours in the afternoon) and the frequency will be increased to
approximately 4.5 to 6-minute intervals.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Denver
Denver
Year
Phase
2016
Initiate Bus Service - Year 1
2017
Initiate Bus Service - Year 2
2018
Initiate Bus Service - Year 3
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$400
$400
$400
$0
$0
State
$0
$0
$0
$0
$0
Local
$100
$100
$100
$0
$0
$500
$500
$500
$0
$0
Federal (CMAQ)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
83
Total
Funding
$0
$1,500
2016-2021 Transportation Improvement Program (Approved TIP)
Title: RTD L Route Service Enhancement
TIP-ID: 2016-010
Project Type: Bus Service Projects
(Expanded)
STIP-ID:
Open to Public: 2016
Sponsor: Boulder County
Project Scope
This project will expand the existing service on RTD’s L Route between
Longmont and Denver. Service frequency on the route will be enhanced from
two-hour to one-hour headways during the mid-day on weekdays. One
additional late-night trip will be added on weekdays. Saturday service frequency
will be enhanced from three-hour to ninety-minute headways.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Broomfield
Adams
Year
Phase
Denver
Boulder
2016
Initiate Bus Service - Year 1
Erie
Broomfield
2017
Initiate Bus Service - Year 2
Lafayette
Denver
2018
Initiate Bus Service - Year 3
Longmont
Jefferson
Westminster
Unincorporated
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$536
$548
$580
$0
$0
State
$0
$0
$0
$0
$0
Local
$134
$137
$145
$0
$0
$670
$685
$725
$0
$0
Federal (CMAQ)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
84
Total
Funding
$0
$2,080
2016-2021 Transportation Improvement Program (Approved TIP)
Title: FLEX Route Extension: Boulder to Longmont
TIP-ID: 2016-011
Project Type: Bus Service Projects
(Expanded)
STIP-ID:
Open to Public: 2016
Sponsor: Boulder County
Project Scope
This project will extend the existing FLEX route by providing service from
Longmont to Boulder. This extension will create up to five, round-trip, weekday
trips. These trips will run as a complement to the existing FLEX trips between
Ft. Collins and Longmont, which will remain with their existing run times and with
the same destinations.
Destinations for the route within Boulder include: Boulder Junction (30th &
Pearl), Boulder Transit Center/ downtown Boulder (14th & Walnut), and the
University of Colorado at Boulder campus.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Boulder
Boulder
Year
Phase
Longmont
2016
Initiate Bus Service - Year 1
Unincorporated
2017
Initiate Bus Service - Year 2
2018
Initiate Bus Service - Year 3
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$380
$384
$392
$0
$0
State
$0
$0
$0
$0
$0
Local
$95
$96
$98
$0
$0
$475
$480
$490
$0
$0
Federal (CMAQ)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
85
Total
Funding
$0
$1,445
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Anschutz Medical Campus Shuttle
TIP-ID: 2016-012
Project Type: Bus Service Projects (New)
STIP-ID:
Open to Public: 2016
Sponsor: University of ColoradoDenver
Project Scope
This project will create new bus service from the Fitzsimons Pkwy Light Rail
Station into the Anschutz Medical Campus. Stops will be at key locations on
campus near University Hospital, Children's Hospital of Colorado, and the
University of Colorado Anschutz Medical Campus. Operating hours for the bus
service will include:
• BUS 1: early AM to late PM, 7 days per week
• BUS 2: early AM to late PM, Monday through Friday
• BUS 3: AM peak and PM peak, Monday through Friday
Affected Municipality(ies)
Affected County(ies)
Project Phases
Aurora
Adams
Year
Phase
2016
Initiate Bus Service - Year 1
2017
Initiate Bus Service - Year 2
2018
Initiate Bus Service - Year 3
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$867
$316
$326
$0
$0
State
$0
$0
$0
$0
$0
Local
$372
$136
$140
$0
$0
$1,239
$452
$466
$0
$0
Federal (CMAQ)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
86
Total
Funding
$0
$2,157
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Superior Call-n-Ride
TIP-ID: 2016-013
Project Type: Bus Service Projects (New)
STIP-ID:
Open to Public: 2016
Sponsor: Superior
Project Scope
This project adds a new Call-n-Ride servicing an area generally from McCaslin
Blvd to 96th St, and US 36 to south of Interlocken Loop. Service hours will be
approximately 5:30am to 7pm Monday through Friday.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Superior
Boulder
Year
Phase
2016
Initiate Bus Service - Year 1
2017
Initiate Bus Service - Year 2
2018
Initiate Bus Service - Year 3
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$215
$102
$106
$0
$0
State
$0
$0
$0
$0
$0
Local
$54
$26
$27
$0
$0
$269
$128
$133
$0
$0
Federal (CMAQ)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
87
Total
Funding
$0
$530
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Broomfield Call-n-Ride
TIP-ID: 2016-014
Project Type: Bus Service Projects
(Expanded)
STIP-ID:
Open to Public: 2016
Sponsor: Broomfield
Project Scope
This project expands the geographic area served by the existing Broomfield Calln-Ride to include an area generally from Sheridan to Zuni, and 120th to
144th/Dillon, with the same service hours, Monday through Friday, from 5:30 AM
until 7:00 PM. The project includes the purchase of two additional buses.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Broomfield
Broomfield
Year
Phase
2016
Initiate Bus Service - Year 1
2017
Initiate Bus Service - Year 2
2018
Initiate Bus Service - Year 3
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$188
$89
$92
$0
$0
State
$0
$0
$0
$0
$0
Local
$80
$38
$40
$0
$0
$268
$127
$132
$0
$0
Federal (CMAQ)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
88
Total
Funding
$0
$527
2016-2021 Transportation Improvement Program (Approved TIP)
Title: RTD Route #324 Frequency Improvements
TIP-ID: 2016-015
Project Type: Bus Service Projects
(Expanded)
STIP-ID:
Open to Public: 2016
Sponsor: Longmont
Project Scope
This project will increase the weekday frequency on RTD route #324 from 30
minutes to 15 minutes during peak operating times.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Longmont
Boulder
Year
Phase
2016
Initiate Bus Service - Year 1
2017
Initiate Bus Service - Year 2
2018
Initiate Bus Service - Year 3
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$392
$392
$392
$0
$0
State
$0
$0
$0
$0
$0
Local
$98
$98
$98
$0
$0
$490
$490
$490
$0
$0
Federal (CMAQ)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
89
Total
Funding
$0
$1,470
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Toll Gate Creek Trail: Chambers Rd to Montview Blvd
TIP-ID: 2016-016
STIP-ID:
Project Type: Bicycle and Pedestrian
Projects (New)
Open to Public: 2018
Sponsor: Aurora
Project Scope
This project constructs a 10 ft wide concrete multi-use bi-directional trail along
Toll Gate Creek between Montview Blvd/Fitzsimons Pkwy and Chambers Rd.
Retaining walls, bike railing, pedestrian-scale ADA/AASHTO compliant lighting,
way-finding signage with destination and distance information, and 20 or more
bicycle parking spaces within 1/2 mile of the project will be included. A new 10'
wide bicycle and pedestrian bridge at East 13th Ave across Toll Gate Creek will
also be constructed.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Aurora
Adams
Year
Phase
Arapahoe
2016
Initiate Environmental
2016
Initiate Design
2016
Initiate ROW
2017
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$1,136
$4,547
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$285
$1,137
$0
$0
$0
$1,421
$5,684
$0
$0
$0
Federal (CMAQ)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
90
Total
Funding
$0
$7,105
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Westerly Creek Trail to Toll Gate Creek Trail Connector
TIP-ID: 2016-017
STIP-ID:
Project Type: Bicycle and Pedestrian
Projects (New)
Open to Public: 2019
Sponsor: Aurora
Project Scope
This project provides bike/pedestrian inter-connections between Westerly Creek
trail, Toll Gate Creek trail, and the Florida LRT Station. The project includes two
major segments:
East of the Florida Station:
• A Florida LRT Station 3-car kiss-n-ride area on both the north and south sides
of Abilene St.
• A diagonal bike/pedestrian crossing at Florida Ave. and Abilene St.
• Reconfigure Florida Ave. to include an 11ft barrier separated (with candle stick
delineators), bi-directional cycle track between the Florida LRT Station and
Chambers Rd. Bulb-outs will also be constructed at the intersections.
• East of Chambers Rd, the cycle track will transition to sharrows on Helena Cir
to Idalia Ct.
• From there, a 12 ft wide concrete path will be constructed along the west bank
of Toll Gate Creek southward to Mexico Ave.
• The existing Mexico Ave. overpass over Toll Gate Creek will be upgraded to
include a 12 ft concrete path, connecting to the existing Toll Gate Creek trail with
a pedestrian/cyclist activated signal.
• Replacement of sidewalks less than 6 ft to 6 ft.
West of the Florida Station:
• Construction a 12 ft wide multi-use bi-directional bike/pedestrian path between
the Florida Station west landing and Potomac St.
• Consolidation of two existing crossings to one controlled HAWK signal crossing
of Potomac St.
• Construction of a new elevated 12 ft wide two-way cycle track on the west side
of Potomac St between the HAWK signal south to the northeast corner of the
Jewell Wetlands and on the north side of Jewell Ave between the west end of
the Jewell Wetlands and Tucson St.
• Install on-street bicycle lanes between the HAWK signal and Louisiana Ave.
• Way finding signage with distance and destination information and bike racks
for at least 20 bikes within 1/2 mile of the project.
• Potomac St will be converted from four lanes to two, with a two-way left turn
lane (TWLTL).
• Traffic signal improvements and pedestrian-scale ADA/AASHTO compliant
lighting will also be constructed as part of the project.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Aurora
Arapahoe
Year
Phase
2017
Initiate Environmental
2017
Initiate Design
2017
Initiate ROW
2018
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal (CMAQ)
$0
$2,501
$6,006
$0
$0
State
$0
$0
$0
$0
$0
Local
$0
$626
$2,502
$0
$0
$0
$3,127
$8,508
$0
$0
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
91
Total
Funding
$0
$11,635
2016-2021 Transportation Improvement Program (Approved TIP)
Title: 23rd Ave. Bike/Ped Path at Fitzsimons Station
TIP-ID: 2016-018
Project Type: Bicycle and Pedestrian
Projects (New)
STIP-ID:
Open to Public: 2017
Sponsor: Aurora
Project Scope
The project constructs a new 12 ft wide concrete multi-use, bi-directional,
physically-protected bicycle/pedestrian facility (use of curbs) along the south
side of Fitzsimons Pkwy extending from the Light Rail Station to Ursula St and
then south to East 23rd Ave. A HAWK signal and crosswalk with ADA ramps
will also be provided at the station.
The project will also install pedestrian-scale ADA/AASHTO compliant lighting,
way-finding signage with destination and distance information, and 20 or more
bicycle parking spaces within 1/2 mile of the project.
Project Phases
Amounts in $1,000s
Prior
Funding
FY16
FY17
Year
Phase
2016
Initiate Construction
FY18
FY19
FY20-21
Future
Funding
$1,492
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$374
$0
$0
$0
$0
$1,866
$0
$0
$0
$0
Federal (STP-M)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
92
Total
Funding
$0
$1,866
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Colfax 15L Transit Improvements: I-225 to I-25
TIP-ID: 2016-019
Project Type: Transit Passenger Facilities
STIP-ID:
Open to Public: 2018
Sponsor: R T D
Project Scope
Project will replace or add existing bus stop amenities for stops along the 15L
bus route servicing Colfax Ave, from I-225 to I-25. Improvements include new
shelters, station furniture, lighting, and security cameras.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Aurora
Adams
Year
Phase
Denver
Arapahoe
2018
Initiate Construction
Denver
2019
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal (STP-M)
$0
$0
$1,300
$1,300
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$325
$325
$0
$0
$0
$1,625
$1,625
$0
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
93
Total
Funding
$0
$3,250
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Wadsworth Blvd Widening: 35th Ave to 48th Ave
TIP-ID: 2016-020
Project Type: Roadway Capacity
STIP-ID:
Open to Public: 2020
Sponsor: Wheat Ridge
Project Scope
This project will widen Wadsworth Blvd from W 35th Ave to W 48th Ave from 4
to 6 lanes. Features include:
• 10 ft wide sidewalks along both sides of the corridor separated from the street
with 10 ft wide tree lawns
• An 11 ft wide two-way cycle track on the east side of Wadsworth Blvd between
35th and 44th
• Street and pedestrian-level lighting
• Landscaped center medians, raised crosswalks, and access consolidation
• Double left turns at 38th and 44th; additional left turn lanes will also be
constructed at up to four additional signalized intersections
• Traffic signals upgrades and bicycle detection
• Transit stop enhancements including shelters, benches, and kiosks
Affected Municipality(ies)
Affected County(ies)
Project Phases
Wheat Ridge
Jefferson
Year
Phase
2016
Initiate Environmental
2017
Initiate Design
2018
Initiate ROW
2019
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$2,000
$4,000
$8,000
$11,280
$0
State
$0
$0
$0
$0
$0
Local
$500
$1,000
$2,000
$2,820
$0
$2,500
$5,000
$10,000
$14,100
$0
Federal (STP-M)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
94
Total
Funding
$0
$31,600
2016-2021 Transportation Improvement Program (Approved TIP)
Title: I-25 & Broadway Interchange Reconstruction
TIP-ID: 2016-021
Project Type: Roadway Capacity
STIP-ID:
Open to Public: 2020
Sponsor: Denver
Project Scope
This project modifies the S. Broadway/I-25 interchange and will include the
following features:
• Reconstructs E. Exposition Ave, from S. Lincoln St to S. Broadway
• Reconstructs S. Broadway, from E. Exposition Ave to south of E. Ohio Ave. in
concrete pavement
• Constructs a new southbound I-25 on-ramp from the Broadway/Ohio
intersection, travel under the existing I-25 viaduct, and extends over Broadway
before it gains vertical elevation to connect to SB I-25
• Adds paved parking at the RTD I-25/Broadway Station; a water quality pond
adjacent to the paved parking
• Adds new or modified traffic signals, with new or improved signal interconnect
and ITS infrastructure
• Adds new 8 ft. minimum width sidewalks, a detached multi-use trail extending
from the Lincoln /Ohio intersection directly into the RTD I-25/Broadway Station
area, bicycle racks, streetscaping, and pedestrian and street lighting
Affected Municipality(ies)
Affected County(ies)
Project Phases
Denver
Denver
Year
Phase
2016
Initiate Design
2016
Initiate ROW
2017
Initiate Environmental
2018
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$6,540
$4,000
$6,833
$0
$0
State
$0
$0
$0
$0
$0
Local
$2,971
$1,000
$6,624
$0
$0
$9,511
$5,000
$13,457
$0
$0
Federal (STP-M)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
95
Total
Funding
$0
$27,968
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Martin Luther King Jr. Blvd Extension: Havana St to Peoria St
TIP-ID: 2016-022
STIP-ID:
Project Type: Roadway Capacity
Open to Public: 2018
Sponsor: Denver
Project Scope
This project adds two additional lanes to Martin Luther King Jr. Blvd. (MLK) from
Havana St/Iola St, and a new 4-lane roadway from where MLK turns south into
Moline St to the Fitzsimons Pkwy/Peoria St intersection. The project will also
include:
• 18 ft landscaped medians, turn lanes, and a 16.5 ft landscaped tree lawn
• A detached 10 ft wide multi-use concrete path on each side, and a 10 ft wide
multi-use concrete and 5 ft parallel soft trail outside of a 30 ft buffer from the
Bluff Lake Nature Center area
• Several existing access consolidations, bus pads, new or improved traffic
signal interconnection, bicycle detection, and a median pedestrian refuge at
Peoria St.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Denver
Denver
Year
Phase
2016
Initiate Environmental
2016
Initiate Design
2017
Initiate ROW
2017
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$1,793
$5,379
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$1,957
$5,871
$0
$0
$0
$3,750
$11,250
$0
$0
$0
Federal (STP-M)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
96
Total
Funding
$0
$15,000
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Quebec St Operational Improvements: 13th Ave to 26th Ave
TIP-ID: 2016-023
STIP-ID:
Project Type: Roadway Operational
Improvements
Open to Public: 2020
Sponsor: Denver
Project Scope
This project constructs additional lanes and other operational improvements on
Quebec St from south of 13th Ave to 26th Ave and will include the following:
• One additional lane in each direction from 13th Ave to Montview Blvd
• One additional northbound lane from Montview Blvd to 23rd Ave
• Receiving and/or turning lanes at intersections of 13th Ave, 14th Ave, Colfax
Ave, 17th Ave, Montview, and E. 23rd Ave
• A continuous 5 ft sidewalk facility with a 3 ft buffer
• New concrete bus pads, transit amenities, and bike parking
• New or improved traffic signal interconnection and ITS infrastructure
Affected Municipality(ies)
Affected County(ies)
Project Phases
Denver
Denver
Year
Phase
2016
Initiate Environmental
2017
Initiate Design
2018
Initiate ROW
2019
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$820
$3,560
$3,810
$3,310
$0
State
$0
$0
$0
$0
$0
Local
$820
$3,560
$3,810
$3,310
$0
$1,640
$7,120
$7,620
$6,620
$0
Federal (STP-M)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
97
Total
Funding
$0
$23,000
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Iliff Ave Operational Improvements: Parker Rd to Quebec St
TIP-ID: 2016-024
STIP-ID:
Project Type: Roadway Operational
Improvements
Open to Public: 2020
Sponsor: Arapahoe County
Project Scope
This project constructs operational and multimodal improvements on Iliff Ave
from Parker Rd to Quebec St and will include the following:
• Separate 8 ft minimum wide pedestrian and bike paths
• Add turn and accelerations lanes at several intersections, with some also
serving as queue jumps
• Widening the bridge over Cherry Creek to accommodate bike lanes and a turn
lane
• Drainage upgrades through the corridor, water quality ponds on S. Cherry
Creek Dr and Valentia St, and burial of utilities
• Medians, protected roadway crossings, access consolidation, new or improved
traffic signal interconnection, bus pads, and bicycle counters and amenities
(racks/lockers)
Affected Municipality(ies)
Affected County(ies)
Project Phases
Denver
Arapahoe
Year
Phase
Unincorporated
Denver
2016
Initiate Environmental
2017
Initiate Design
2018
Initiate ROW
2019
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$1,500
$3,000
$6,000
$6,846
$0
State
$0
$0
$0
$0
$0
Local
$500
$1,000
$2,000
$2,673
$0
$2,000
$4,000
$8,000
$9,519
$0
Federal (CMAQ)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
98
Total
Funding
$0
$23,519
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Ralston Rd Reconstruction: Yukon St to Upham St
TIP-ID: 2016-025
STIP-ID:
Project Type: Roadway Reconstruction
Open to Public: 2019
Sponsor: Arvada
Project Scope
This project reconstructs Ralston Rd from Upham St to Yukon St. The project
will also include the following:
• Widening the existing sidewalks to a minimum width of 8 ft with a landscaped
buffer where feasible
• protected roadway crossings, new or improved traffic signal interconnections,
ITS infrastructure, and bicycle detection and racks/lockers
• Transit amenities and bus pads
Affected Municipality(ies)
Affected County(ies)
Project Phases
Arvada
Jefferson
Year
Phase
2016
Initiate Environmental
2016
Initiate Design
2018
Initiate ROW
2018
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$286
$0
$1,617
$0
$0
State
$0
$0
$0
$0
$0
Local
$72
$0
$404
$0
$0
$358
$0
$2,021
$0
$0
Federal (STP-M)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
99
Total
Funding
$0
$2,379
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Broadway Reconstruction: Violet Ave to US-36
TIP-ID: 2016-026
Project Type: Roadway Reconstruction
STIP-ID:
Open to Public: 2020
Sponsor: Boulder
Project Scope
Project will reconstruct Broadway St, from Violet Ave to US 36. New curb and
gutter, underground utility upgrades, including new or improved traffic signal
interconnection and bicycle detection, and bicycle, pedestrian, and transit stop
facilities and amenities will also be included as part of the project.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Boulder
Boulder
Year
Phase
2016
Initiate Design
2017
Initiate Environmental
2018
Initiate ROW
2019
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$1,000
$400
$1,000
$3,825
$0
State
$0
$0
$0
$0
$0
Local
$250
$100
$250
$1,475
$0
$1,250
$500
$1,250
$5,300
$0
Federal (STP-M)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
100
Total
Funding
$0
$8,300
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Meadows Pkwy Reconstruction: US-85 to Meadows Blvd
TIP-ID: 2016-027
STIP-ID:
Project Type: Roadway Reconstruction
Open to Public: 2018
Sponsor: Castle Rock
Project Scope
Project will reconstruct Meadows Pkwy from US 85 to Meadows Blvd in asphalt,
along with repairing or replacing any damaged curb/gutter along the center
median, roadway edge, and sidewalk. Bike lanes will be added to the outside of
the roadway.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Castle Rock
Douglas
Year
Phase
2017
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal (STP-M)
$0
$1,333
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$0
$334
$0
$0
$0
$0
$1,667
$0
$0
$0
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
101
Total
Funding
$0
$1,667
2016-2021 Transportation Improvement Program (Approved TIP)
Title: 16th St Mall Reconstruction: Arapahoe St to Lawrence St
TIP-ID: 2016-028
STIP-ID:
Project Type: Roadway Reconstruction
Open to Public: 2017
Sponsor: R T D
Project Scope
Project will reconstruct one block of the 16th Street Mall between Lawrence St
and Arapahoe St. The project will reconstruct the sub –base and rehab the
existing pavers, along with improvements to intersection bulb-outs, utilities, and
amenities, including fountains and tree pits/tree replacement, and urban design
upgrades to existing furnishings (e.g., fresh paint, powdercoating, and
wayfinding upgrades).
Affected Municipality(ies)
Affected County(ies)
Project Phases
Denver
Denver
Year
Phase
2016
Initiate Design
2017
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$2,399
$2,400
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$600
$600
$0
$0
$0
$2,999
$3,000
$0
$0
$0
Federal (STP-M)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
102
Total
Funding
$0
$5,999
2016-2021 Transportation Improvement Program (Approved TIP)
Title: East Lafayette Multimodal Path Connection: Commerce Ct to
Lafayette Park-n-Ride
TIP-ID: 2016-029
STIP-ID:
Project Type: Bicycle and Pedestrian
Projects (New)
Open to Public: 2020
Sponsor: Lafayette
Project Scope
This project widens existing sidewalks and constructs new 10 ft wide concrete
multi-use paths along South Boulder Rd from City Center Dr east to 120th St,
and then continuing south along 120th St, connecting to existing sidewalks at
Commerce Ct. Two additional connections will be made to the north from South
Boulder Rd; one on Merlin Dr to Sanchez Elementary School, and another on
City Center Dr to west of Strathmore Ln.
A physically-protected crossing at Avalon St, 20 bicycle parking spaces,
AASHTO compliant lighting, and way-finding signage with destination and
distance information will also be included.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Lafayette
Boulder
Year
Phase
2019
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal (TAP)
$0
$0
$0
$999
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$0
$250
$0
$0
$0
$0
$1,249
$0
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
103
Total
Funding
$0
$1,249
2016-2021 Transportation Improvement Program (Approved TIP)
Title: 71st St Multimodal Pathway Connection: Winchester to Idylwild Trail
TIP-ID: 2016-030
STIP-ID:
Project Type: Bicycle and Pedestrian
Projects (New)
Open to Public: 2020
Sponsor: Boulder County
Project Scope
This project constructs a new 10-foot wide concrete multi-use path from the
existing sidewalk in the Winchester Business Park to the Longmont-to-Boulder
Trail crossing of 71st St, and to the transit services along Lookout Rd. A new
physically-protected crossing for the Lobo Trail across 71st St will be built and
the multiuse path along Lookout Rd will be widened. The project will provide two
grade-separated crossings over the Boulder and Lefthand Ditch and over the
Boulder and Whiterock Ditch.
At least 10 uncovered bike racks with a capacity for 20 bicycles, ADA/AASHTO
compliant lighting, and way-finding signage with destination and distance
information will be included.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Boulder
Boulder
Year
Phase
2019
Initiate Construction
Unincorporated
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal (TAP)
$0
$0
$0
$860
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$0
$215
$0
$0
$0
$0
$1,075
$0
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
104
Total
Funding
$0
$1,075
2016-2021 Transportation Improvement Program (Approved TIP)
Title: C-470 Multi-use Trail: Grade Separation at Yosemite St
TIP-ID: 2016-031
STIP-ID:
Project Type: Bicycle and Pedestrian
Projects (New)
Open to Public: 2020
Sponsor: Douglas County
Project Scope
This project constructs two bike/ped bridges: one over Yosemite St and another
over the C-470 WB On-Ramp. Twenty or more bicycle parking spaces, at least
10 of which will be covered, ADA/AASHTO compliant lighting, landscaping, and
way-finding signage with destination and distance information will also be
included.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Lone Tree
Douglas
Year
Phase
2018
Initiate ROW
2019
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal (TAP)
$0
$0
$500
$1,500
$0
State
$0
$0
$0
$0
$0
Local
$300
$300
$350
$1,050
$0
$300
$300
$850
$2,550
$0
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
105
Total
Funding
$0
$4,000
2016-2021 Transportation Improvement Program (Approved TIP)
Title: US-6 Shared-Use Path: Colfax Ave to Johnson Rd
TIP-ID: 2016-032
STIP-ID:
Project Type: Bicycle and Pedestrian
Projects (New)
Open to Public: 2018
Sponsor: Jefferson County
Project Scope
This project will construct an 8 ft wide detached multi-use path along the north
side of US-6 between Colfax Ave and Johnson Rd. ADA/AASHTO compliant
lighting and way-finding signage with destination and distance information will be
included.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Golden
Jefferson
Year
Phase
2016
Initiate Design
2017
Initiate Construction
Unincorporated
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$50
$539
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$13
$135
$0
$0
$0
$63
$674
$0
$0
$0
Federal (TAP)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
106
Total
Funding
$0
$737
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Superior Trail: McCaslin BRT Station to Coal Creek
TIP-ID: 2016-033
STIP-ID:
Project Type: Bicycle and Pedestrian
Projects (New)
Open to Public: 2018
Sponsor: Superior
Project Scope
This project constructs a 10 ft wide concrete multi-use trail from the McCaslin
BRT/Park-n-Ride Station to the existing McCaslin Blvd pedestrian underpass,
continuing east to the Coal Creek Regional Trail/US-36 Bikeway intersection.
A Bus-then-Bike Shelter with 31 covered bicycle parking spaces, lighting,
landscaping, and way-finding signage with destination and distance information
will also be included.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Superior
Boulder
Year
Phase
2016
Initiate Design
2017
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$280
$320
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$70
$80
$0
$0
$0
$350
$400
$0
$0
$0
Federal (TAP)
$0
Total
Total
Funding
$0
$750
Date
Status
Description
05/07/2015
Proposed
Transfer $320,000 of federal TAP funds and associated local match from FY2017 to FY2016. Total project funding remains unchanged
04/16/2015
Approved
Adopted into the 2016-2021 TIP
107
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Superior Trail: McCaslin BRT to Davidson Mesa Underpass
TIP-ID: 2016-034
STIP-ID:
Project Type: Bicycle and Pedestrian
Projects (New)
Open to Public: 2020
Sponsor: Superior
Project Scope
This project constructs a 10 ft wide concrete multi-use trail between US 36 and
Marshall Rd, from the McCaslin BRT Station to the US 36 pedestrian and bicycle
underpass at Davidson Mesa.
A Bus-then-Bike Shelter with 31 covered bicycle parking spaces, lighting,
landscaping, and way-finding signage with destination and distance information
will also be included.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Superior
Boulder
Year
Phase
2017
Initiate Design
2018
Initiate ROW
2019
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal (CMAQ)
$0
$200
$147
$350
$0
State
$0
$0
$0
$0
$0
Local
$0
$50
$37
$191
$0
$0
$250
$184
$541
$0
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
108
Total
Funding
$0
$975
2016-2021 Transportation Improvement Program (Approved TIP)
Title: 30th St and Colorado Ave Bike/Ped Underpass
TIP-ID: 2016-035
Project Type: Bicycle and Pedestrian
Projects (New)
STIP-ID:
Open to Public: 2020
Sponsor: Boulder
Project Scope
This project constructs an underpass at 30th St and Colorado Ave. Additional
items as part of the project include 10 ft wide multi-use path connections,
ADA/AASHTO compliant lighting, way-finding signage with destination and
distance information, and 20 bicycle parking spaces.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Boulder
Boulder
Year
Phase
2016
Initiate Design
2017
Initiate Environmental
2018
Initiate ROW
2019
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$400
$400
$600
$3,350
$0
State
$0
$0
$0
$0
$0
Local
$100
$100
$700
$2,350
$0
$500
$500
$1,300
$5,700
$0
Federal (CMAQ)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
109
Total
Funding
$0
$8,000
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Parker Rd Sidewalk Connection: Plaza Dr to Sulphur Gulch Trail
TIP-ID: 2016-036
STIP-ID:
Project Type: Bicycle and Pedestrian
Projects (New)
Open to Public: 2019
Sponsor: Parker
Project Scope
This project constructs a new 10 ft-wide sidewalk along the east side of Parker
Rd between the Sulphur Gulch Trail and north of Plaza Dr. Way-finding signage
with destination and distance information will be included.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Parker
Douglas
Year
Phase
2016
Initiate Design
2017
Initiate ROW
2018
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$72
$72
$360
$0
$0
State
$0
$0
$0
$0
$0
Local
$24
$24
$120
$0
$0
$96
$96
$480
$0
$0
Federal (CMAQ)
$0
Total
Total
Funding
$0
$672
Date
Status
Description
05/04/2015
Proposed
Add $26,000 of local CMAQ funds in FY2016 and FY2017 and add $6,000 of local CMAQ funds in FY2018. Transfer $72,000 of federal CMAQ funds
from FY2016 and FY2017 to FY2018. Increase total project funding.
04/16/2015
Approved
Adopted into the 2016-2021 TIP
110
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Washington Ave Complete Streets
TIP-ID: 2016-037
Project Type: Bicycle and Pedestrian
Projects (New)
STIP-ID:
Open to Public: 2018
Sponsor: Golden
Project Scope
This project reconstructs Washington Ave from CO 93 to 10th St to include a
curb-separated 4 ft wide bike facility and 8 ft wide sidewalk, where permitted.
Intersection safety improvements, ADA/AASHTO compliant lighting, transit
supporting amenities, and way-finding signage with destination and distance
information will be included.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Golden
Jefferson
Year
Phase
2016
Initiate Environmental
2016
Initiate Design
2017
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$345
$2,700
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$90
$686
$0
$0
$0
$435
$3,386
$0
$0
$0
Federal (STP-M)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
111
Total
Funding
$0
$3,821
2016-2021 Transportation Improvement Program (Approved TIP)
Title: High Line Canal Trail Underpass at Hampden and Colorado
TIP-ID: 2016-038
STIP-ID:
Project Type: Bicycle and Pedestrian
Projects (New)
Open to Public: 2019
Sponsor: Cherry Hills Village
Project Scope
This project constructs two multi-use underpasses: one under Hampden Ave
1,500’ west of Colorado Blvd, and another under Colorado Blvd 200’ north of
Hampden Ave. The 14’ box culverts will accommodate new 10 ft multi-use trails
from the existing pedestrian bridge at Monroe St to the underpass, along the
north side of Hampden Ave to the other underpass and to the existing multi-use
path on the east side of Colorado Blvd.
At least 10 covered bicycle parking spaces, ADA/AASHTO compliant lighting,
and way-finding signage with destination and distance information will be
included.
CDOT awarded TAP funding of $1,000,000 in FY17.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Cherry Hills Village
Arapahoe
Year
Phase
Denver
Denver
2016
Initiate Environmental
2016
Initiate Design
2017
Initiate ROW
2018
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$1,500
$1,300
$1,250
$0
$0
State
$0
$0
$0
$0
$0
Local
$500
$350
$500
$0
$0
$2,000
$1,650
$1,750
$0
$0
Federal (TAP)
$0
Total
Total
Funding
$0
$5,400
Date
Status
Description
05/07/2015
Proposed
Transfer $37,000 of federal TAP funds and associated local match from FY2016 to FY2017. Total project funding remains unchanged.
04/16/2015
Approved
Adopted into the 2016-2021 TIP
112
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Route 73 Extension: Smith Rd Station to 60th Ave and Dahlia St
TIP-ID: 2016-039
STIP-ID:
Project Type: Bus Service Projects
(Expanded)
Open to Public: 2016
Sponsor: Commerce City
Project Scope
This project will extend RTD Route 73 north from Central Park Station to the
60th/Dahlia Transfer Station, generally along Central Park Blvd, Prairie Pkwy
Ave, E. 60th Ave, Holly St, 62nd Ave, and Parkway Dr.
The extension will be for 12 service hours Monday through Saturday
(approximately 6:30 a.m. to 6:30 p.m.), with 30 minute weekday headways and
hourly headways on Saturday. The extension also will provide special event
service at Dicks Sporting Goods Park.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Commerce City
Adams
Year
Phase
Denver
Denver
2016
Initiate Bus Service - Year 1
2017
Initiate Bus Service - Year 2
2018
Initiate Bus Service - Year 3
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$453
$451
$451
$0
$0
State
$0
$0
$0
$0
$0
Local
$114
$113
$113
$0
$0
$567
$564
$564
$0
$0
Federal (CMAQ)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
113
Total
Funding
$0
$1,695
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Gun Club Rd and Quincy Ave Operational Improvements
TIP-ID: 2016-040
STIP-ID:
Project Type: Roadway Operational
Improvements
Open to Public: 2020
Sponsor: Arapahoe County
Project Scope
This project constructs a four through lane Partial Continuous Flow Intersection
(PCFI), with legs extending 1,200 feet in each direction.
Features include:
• A box culvert crossing that will accommodate the Quincy Avenue Trail
• New and improved signal interconnection, and ITS infrastructure
• Bike amenities and bike counters
• Street trees and/or a landscaped buffer
• A new bike lane or shoulders
• Depressed medians on all legs of the intersection
Affected Municipality(ies)
Affected County(ies)
Project Phases
Aurora
Arapahoe
Year
Phase
2016
Initiate Design
2017
Initiate Environmental
2018
Initiate ROW
2019
Initiate Construction
Unincorporated
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$500
$500
$1,000
$2,892
$0
State
$0
$0
$0
$0
$0
Local
$500
$500
$1,000
$6,475
$0
$1,000
$1,000
$2,000
$9,367
$0
Federal (CMAQ)
$0
Total
Total
Funding
$0
$13,367
Date
Status
Description
05/04/2015
Proposed
Add $500,000 of local CMAQ funds in FY2017, add $1,000,000 of local CMAQ funds in FY2018 and remove $2,167,000 of local CMAQ funds in
FY2019. Decrease total project funding to reflect sponsor"s original funding request.
04/16/2015
Approved
Adopted into the 2016-2021 TIP
114
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Founders Pkwy and Allen Way Intersection Improvements
TIP-ID: 2016-041
STIP-ID:
Project Type: Roadway Operational
Improvements
Open to Public: 2020
Sponsor: Castle Rock
Project Scope
Project will widen Founders Pkwy (SH-86) to accommodate a second eastbound
left turn lane, and a dedicated westbound right turn lane. The new left turn lane
will extend to the I-25 / Founders northbound ramp intersection. Project will also
add a second southbound right turn lane at Founders and a second through lane
at the Allen Way and Allen St intersection. The existing roadside trail will be
replaced with a new 8-ft trail.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Castle Rock
Douglas
Year
Phase
2017
Initiate Environmental
2017
Initiate Design
2018
Initiate ROW
2019
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal
$0
$0
$0
$0
$0
Federal (STP-M)
$0
$284
$269
$1,447
$0
State
$0
$0
$0
$0
$0
State (Faster-S)
$0
$0
$0
$280
$0
Local
$0
$71
$68
$905
$0
$0
$355
$337
$2,632
$0
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
115
Total
Funding
$0
$3,324
2016-2021 Transportation Improvement Program (Approved TIP)
Title: US 85: Highlands Ranch Pkwy to Blakeland Dr Capacity
Improvements
TIP-ID: 2016-042
STIP-ID:
Project Type: Roadway Capacity
Open to Public: 2020
Sponsor: Douglas County
Project Scope
This project will widen Santa Fe Blvd (US-85) from 4 to 6 lanes. Features
include:
• Intersection improvements at Blakeland Dr, Norwood Dr, Carder Ct, Town
Center Dr, and Branden Dr, including adding or improving left turn lanes and
auxiliary lanes, where warranted
• Reconstructing and/or repaving existing lanes, adding shoulders, where
feasible
• New and improved signal interconnection, and ITS infrastructure
• 10 ft wide detached multi-use path, bike amenities, and bike counters
• Transit stop enhancements including bus pads, shelters, benches, and
sidewalk connections
• Landscaped center medians, and access consolidation
Affected Municipality(ies)
Affected County(ies)
Project Phases
Unincorporated
Douglas
Year
Phase
2018
Initiate ROW
2019
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal
$0
$0
$0
$0
$0
Federal (STP-M)
$0
$0
$5,000
$10,000
$0
State
$0
$0
$0
$0
$0
State (R P P)
$0
$0
$2,000
$1,000
$0
$2,500
$2,500
$1,250
$5,750
$0
$2,500
$2,500
$8,250
$16,750
$0
Local
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
116
Total
Funding
$0
$30,000
2016-2021 Transportation Improvement Program (Approved TIP)
Title: RidgeGate Pkwy Widening: Havana St to Lone Tree City Limits
TIP-ID: 2016-043
STIP-ID:
Project Type: Roadway Capacity
Open to Public: 2020
Sponsor: Lone Tree
Project Scope
This project will widen Ridgegate Pkwy from Havana St to the Lone Tree city
limits from 2 to 4 lanes. Features include:
• Raised medians
• Left turn lanes at signalized intersections
• A separated cycle track bike detection
• Bike and transit amenities
• New sidewalks of a minimum width of 8 ft
Affected Municipality(ies)
Affected County(ies)
Project Phases
Lone Tree
Douglas
Year
Phase
2018
Initiate Design
2019
Initiate Construction
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal (STP-M)
$0
$0
$1,400
$5,000
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$3,400
$12,200
$0
$0
$0
$4,800
$17,200
$0
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
117
Total
Funding
$0
$22,000
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Hwy 79 and Hwy 36 Grade Separation: FA and Design Study
TIP-ID: 2016-044
STIP-ID:
Project Type: Roadway/Transit Studies
Open to Public: 2019
Sponsor: Bennett
Project Scope
This study undertakes environmental clearances and Final Design for grade
separating Hwy 79 and the Union Pacific Railroad north of Bennett at Old Victory
Rd.
Phase 1 will conduct the necessary NEPA analysis and preliminary design.
Phase 2 will develop a final design.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Bennett
Adams
Year
Phase
2016
Initiate Study
2018
Initiate Design
Unincorporated
Amounts in $1,000s
Prior
Funding
FY16
FY17
$0
Future
Funding
$0
$0
$0
$392
$392
$392
$0
$0
$0
$0
$0
$0
$0
$108
$108
$108
$0
$0
$0
$0
$0
$0
$0
$500
$500
$500
$0
$0
Local
Total
FY20-21
$0
State
State (R P P)
FY19
$0
Federal
Federal (STP-M)
FY18
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
118
Total
Funding
$0
$1,500
2016-2021 Transportation Improvement Program (Approved TIP)
Title: SH-7 BRT Study: Boulder to Brighton
TIP-ID: 2016-045
Project Type: Roadway/Transit Studies
STIP-ID:
Open to Public: 2017
Sponsor: Boulder County
Project Scope
This project will continue PEL analysis and recommendations for SH-7 between
75th Street in Boulder County and SH 287, as well as develop a cohesive plan
for Bus Rapid Transit operations on SH 7 from downtown Boulder to the
terminus of RTD’s North Metro Rail Line at 162nd in the City of Thornton.
The study will:
• Identify traffic operation and safety problems
• Perform a passenger demand analysis for BRT
• Develop level of transit service scenarios and vehicle procurement needed for
the new service
• Identify capital needs and improvements, including queue jump lanes, TSP,
stop enhancements, buses, etc
• Define any possible revenue opportunities to support capital, operations, and
maintenance
• Identify First and Final mile opportunities in the corridor
Affected Municipality(ies)
Affected County(ies)
Project Phases
Boulder
Adams
Year
Phase
Brighton
Boulder
2016
Initiate Study
Broomfield
Broomfield
2017
Initiate Study
Erie
Weld
Lafayette
Thornton
Unincorporated
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$80
$120
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$20
$30
$0
$0
$0
$100
$150
$0
$0
$0
Federal (STP-M)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
119
Total
Funding
$0
$250
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Arapahoe Rd: I-25 to Parker Rd Next Steps Operations Study
TIP-ID: 2016-046
STIP-ID:
Project Type: Roadway/Transit Studies
Open to Public: 2017
Sponsor: Centennial
Project Scope
This study will reevaluate and prioritize operational improvements at major
intersections on Arapahoe Rd between I-25 and Parker Rd. This study will also
incorporate context sensitive solutions that consider development and
redevelopment potential; perceptible corridor width due to the wide paved
median, landscaping, beautification, and other urban design considerations.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Aurora
Arapahoe
Year
Phase
2016
Initiate Study
Centennial
Greenwood Village
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$400
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$100
$0
$0
$0
$0
$500
$0
$0
$0
$0
Federal (STP-M)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
120
Total
Funding
$0
$500
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Industrial Area Transportation Study: I-25 to I-270 to 40th Ave/Smith
Rd
TIP-ID: 2016-047
STIP-ID:
Project Type: Roadway/Transit Studies
Open to Public: 2017
Sponsor: Commerce City
Project Scope
This project will conduct a planning level connectivity study to identify critical
travel sheds on the local arterial and major collector street system west-to-east
from I-25 to Quebec, and then south-to-north from Smith Road/40th to I270/U.S. 85 & 60th. The study will emphasize key connections to I-70 and I-270
and include specific feasibility/ alternatives analysis /concept design for the
following elements:
• BNSF Bridge over SH 265 (conceptual design)
• 60th Ave & US 85 (feasibility/alternatives analysis)
• Union Pacific Railroad grade separation in the vicinity of 47th Ave/49th Ave
(feasibility/alternatives analysis)
Affected Municipality(ies)
Affected County(ies)
Project Phases
Commerce City
Adams
Year
Phase
Denver
Denver
2016
Initiate Study
Unincorporated
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$700
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$300
$0
$0
$0
$0
$1,000
$0
$0
$0
$0
Federal (STP-M)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
121
Total
Funding
$0
$1,000
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Erie Pkwy Study: SH-287 to I-25
TIP-ID: 2016-048
Project Type: Roadway/Transit Studies
STIP-ID:
Open to Public: 2017
Sponsor: Erie
Project Scope
This project will evaluate the improvements needed to Erie Parkway from SH287 to I-25. Components of this study include the following:
• Utilizing existing topography and supplement with field survey.
• Review traffic studies for existing developments, obtain additional traffic counts
and prepare updated traffic study.
• Review drainage reports for existing developments and existing outfall plans.
Prepare conceptual hydraulic design and preliminary drainage memorandum.
• Prepare conceptual roadway design report, plan set, and cost estimate. The
design report will include timing for improvements based on existing and
projected traffic volume.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Erie
Boulder
Year
Phase
Unincorporated
Weld
2016
Initiate Study
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$160
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$40
$0
$0
$0
$0
$200
$0
$0
$0
$0
Federal (STP-M)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
122
Total
Funding
$0
$200
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Jeffco Bike Wayfinding Study
TIP-ID: 2016-049
Project Type: Roadway/Transit Studies
STIP-ID:
Open to Public: 2018
Sponsor: Lakewood
Project Scope
This project will study and make recommendations for a unified county bike/ped
wayfinding signage program. Specific tasks include:
• Public involvement
• Development of a wayfinding brand/signage design and a standards manual
and placement guidelines
• Review of current signage, plans and best practices
• Network mapping
Amounts in $1,000s
Affected County(ies)
Project Phases
Jefferson
Year
Phase
2016
Initiate Study
2017
Initiate Study
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$80
$40
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$20
$10
$0
$0
$0
$100
$50
$0
$0
$0
Federal (STP-M)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
123
Total
Funding
$0
$150
2016-2021 Transportation Improvement Program (Approved TIP)
Title: SH 119 BRT NEPA Analysis: Boulder to Longmont
TIP-ID: 2016-050
STIP-ID:
Project Type: Roadway/Transit Studies
Open to Public: 2018
Sponsor: R T D
Project Scope
This project will conduct the next level of NEPA clearances, route planning, and
preliminary engineering necessary to implement BRT in the SH 119 Corridor.
Affected Municipality(ies)
Affected County(ies)
Project Phases
Boulder
Boulder
Year
Phase
2016
Initiate Study
Longmont
Unincorporated
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$1,000
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$250
$0
$0
$0
$0
$1,250
$0
$0
$0
$0
Federal (STP-M)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
124
Total
Funding
$0
$1,250
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Regional BRT Feasibility Study
TIP-ID: 2016-051
Project Type: Roadway/Transit Studies
STIP-ID:
Open to Public: 2018
Sponsor: R T D
Project Scope
This project will analyze arterial corridors region-wide to determine those that
could be suitable for establishing a regional arterial BRT network and establish a
prioritization for implementation.
Amounts in $1,000s
Affected County(ies)
Project Phases
Regional
Year
Phase
2017
Initiate Study
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal (STP-M)
$0
$1,000
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$0
$500
$0
$0
$0
$0
$1,500
$0
$0
$0
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
125
Total
Funding
$0
$1,500
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Williams Fork Trail Multi-use Path: 63rd St to Twin Lakes Rd
TIP-ID: 2016-052
STIP-ID:
Project Type: Bicycle and Pedestrian
Projects (New)
Open to Public: 2018
Sponsor: Boulder County
Project Scope
This project will construct a 10 ft wide concrete multi use path for 3,800 ft along
Williams Fork Trail between N 63rd St and Twin Lakes Rd. The project will install
pedestrian-scale ADA/AASHTO compliant lighting, way-finding signage with
destination and distance information and 20 or more bike parking spaces within
1/2 miles of the project.
Selected using CDOT TAP funds.
Affected Municipality(ies)
Affected County(ies)
Boulder
Boulder
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal (TAP)
$0
$632
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$0
$158
$0
$0
$0
$0
$790
$0
$0
$0
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
126
Total
Funding
$0
$790
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Mead School to School Trail Project
TIP-ID: 2016-053
Project Type: Bicycle and Pedestrian
Projects (New)
STIP-ID:
Open to Public: 2016
Sponsor: Mead
Project Scope
This project will construct an 8 ft wide trail from Mead Middle School to Mead
High School.
Selected using CDOT TAP funds.
Affected Municipality(ies)
Affected County(ies)
Mead
Weld
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$400
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$100
$0
$0
$0
$0
$500
$0
$0
$0
$0
Federal (TAP)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
127
Total
Funding
$0
$500
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Boulder County Bus-then-Bike Shelters
TIP-ID: 2016-054
Project Type: Bicycle and Pedestrian
Projects (New)
STIP-ID:
Open to Public: 2016
Sponsor: Boulder County
Project Scope
This project will construct Bus-then-Bike shelters at four transit stops.
Selected using CDOT TAP funds.
Affected County(ies)
Boulder
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$226
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$57
$0
$0
$0
$0
$283
$0
$0
$0
$0
Federal (TAP)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
128
Total
Funding
$0
$283
2016-2021 Transportation Improvement Program (Approved TIP)
Title: I-25: 120th Ave to E-470 Managed Lanes
TIP-ID: 2016-055
Project Type: Roadway Capacity
STIP-ID:
Open to Public: 2020
Sponsor: CDOT Region 4
Project Scope
This project will extend the existing and under construction managed lanes
project (TIPID 2012-073), utilizing existing and new ROW. The project will result
in one new managed lane in each direction from the current project's northern
terminus near 120th Ave to E-470. Project will resurface the entire stretch, add
traffic management, sound wall, and tolling/ITS equipment.
Affected Municipality(ies)
Affected County(ies)
Broomfield
Adams
Thornton
Broomfield
Westminster
Unincorporated
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$0
$0
$0
$0
$0
$40,000
$0
$0
$0
$0
$3,000
$0
$0
$0
$0
State (Surface)
$0
$0
$0
$12,000
$0
Local
$0
$0
$0
$0
$0
$43,000
$0
$0
$12,000
$0
Federal
State (RMP)
State (Safety)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
129
Total
Funding
$0
$55,000
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 1 ITS Pool
Project Type: Congestion Management
TIP-ID: 2016-056
STIP-ID:
Open to Public:
Sponsor: CDOT Region 1
Project Scope
CDOT Region 1 ITS Pool. Specific projects will not be listed.
Affected County(ies)
Adams
Arapahoe
Broomfield
Denver
Douglas
Jefferson
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
Federal
$0
$0
$0
$0
$0
State (ITS)
$0
$9,494
$7,400
$0
$0
Local
$0
$0
$0
$0
$0
$0
$9,494
$7,400
$0
$0
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
130
Total
Funding
$0
$16,894
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Region 1 RPP Pool
Project Type: Other
TIP-ID: 2016-057
STIP-ID:
Open to Public: 2016
Sponsor: CDOT Region 1
Project Scope
CDOT Region 1 RPP Pool. Funds projects with RPP funds.
Affected County(ies)
Adams
Arapahoe
Broomfield
Denver
Douglas
Jefferson
All pool project funding depicts federal and/or state funding only.
Facility Name
Start-At and End-At
Cost
(1,000s)
Facility Name
(Cont)
Start-At and End-At
1-70
PPSL
Cost
(1,000s)
Start-At and End-At
$4,000
US 85 design
Sedalia to Meadows
$2,900
$16,000
Small
projects/consultants/clo
seouts
$20,000
Montgomery settlement
$200
I-25 S
PEL
$1,500
US 85
Louviers to Sedalia
I-25 N
Post-PEL
I-70
Tower to Colfax
$2,600
C470
Study
$1,000
C470 West
PEL
$2,100
I-270
Interchange Study (TIP ID
2016-047)
$1,000
120th Ave Connection
Broomfield TIP ID 2007-029
$1,400
I-25
Operational Study
$1,000
Amounts in $1,000s
Prior
Funding
FY16
$0
FY19
FY20-21
Future
Funding
$0
$0
$0
$0
$17,600
$15,700
$13,900
$8,500
$0
$0
$0
$0
$0
$0
$17,600
$15,700
$13,900
$8,500
$0
Local
Total
FY18
$0
Federal
State (R P P)
FY17
Date
Status
Description
04/16/2015
Approved
Proposed for adoption into the 2016-2021 TIP
131
Cost
(1,000s)
Facility Name
(Cont)
Total
Funding
$0
$55,700
$2,000
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Ozone State Implementation Plan (SIP) Modeling Study
TIP-ID: 2016-058
STIP-ID:
Project Type: Air Quality Improvement
Projects
Open to Public: 2018
Sponsor: R A Q C
Project Scope
Conduct modeling and strategy analysis to ensure that the region will be able to
meet anticipated new standards by the mandated deadlines for tighter standards
for ozone.
Amounts in $1,000s
Affected County(ies)
Project Phases
Regional
Year
Phase
2016
Initiate Study
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$480
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$120
$0
$0
$0
$0
$600
$0
$0
$0
$0
Federal (STP-M)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
132
Total
Funding
$0
$600
2016-2021 Transportation Improvement Program (Approved TIP)
Title: C-470 Managed Toll Express Lanes: Kipling to I-25
TIP-ID: 2016-059
STIP-ID:
Project Type: Roadway Capacity
Open to Public:
Sponsor: CDOT Region 1
Project Scope
Adds one managed lane in each direction on C-470, from Kipling to I-25.
Affected County(ies)
Arapahoe
Douglas
Amounts in $1,000s
Prior
Funding
FY16
$0
FY19
FY20-21
Future
Funding
$0
$0
$0
$0
$20,000
$40,000
$40,000
$0
$0
$0
$0
$0
$0
$0
$20,000
$40,000
$40,000
$0
$0
Local
Total
FY18
$0
Federal
State (RMP)
FY17
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
133
Total
Funding
$0
$100,000
2016-2021 Transportation Improvement Program (Approved TIP)
Title: I-70/Genesee Bike Path
TIP-ID: 2016-060
Project Type: Bicycle and Pedestrian
Projects (New)
STIP-ID:
Open to Public:
Sponsor: CDOT
Project Scope
Project constructs a 10 ft wide concrete multi-use path on the northerly side of I70 between the Genesee Exit and Evergreen Pkwy Exit (Exit 251 and 254). The
project will also construct a pedestrian bridge over the buffalo herd culvert
crossing at approximate milepost 253.5. This project will be constructed in
CDOT and Denver Parks Right-of-Way.
Affected County(ies)
Jefferson
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$700
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$175
$0
$0
$0
$0
$875
$0
$0
$0
$0
Federal (TAP)
$88
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
134
Total
Funding
$0
$963
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Sheridan Blvd Multiuse Path: W. 6th Ave to W. 10th Ave
TIP-ID: 2016-061
STIP-ID:
Project Type: Bicycle and Pedestrian
Projects (New)
Open to Public: 2017
Sponsor: Lakewood
Project Scope
Construct multiuse path on the west side of Sheridan Blvd from north of W. 6th
Ave to W. 10th Ave.
Awarded with CDOT Region 1 TAP funds.
Affected Municipality(ies)
Affected County(ies)
Lakewood
Jefferson
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$400
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$100
$0
$0
$0
$0
$500
$0
$0
$0
$0
Federal (TAP)
$500
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
135
Total
Funding
$0
$1,000
2016-2021 Transportation Improvement Program (Approved TIP)
Title: Sheridan Blvd Sidewalks: W. 8th Ave to W. 10th Ave and Colfax Ave
to W. 17th Ave
TIP-ID: 2016-062
STIP-ID:
Project Type: Bicycle and Pedestrian
Projects (New)
Open to Public: 2018
Sponsor: Denver
Project Scope
Complete planning, design, and environmental phases for detached sidewalks
on the east side of Sheridan Blvd (5 ft wide landscaping and 5 ft wide sidewalk)
from W. 8th Ave to W. 10th Ave and north of Colfax Ave to W. 17th Ave.
Awarded with CDOT Region 1 TAP funds.
Affected Municipality(ies)
Affected County(ies)
Denver
Denver
Amounts in $1,000s
Prior
Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Funding
$400
$400
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$100
$100
$0
$0
$0
$500
$500
$0
$0
$0
Federal (TAP)
$0
Total
Date
Status
Description
04/16/2015
Approved
Adopted into the 2016-2021 TIP
136
Total
Funding
$0
$1,000
APPENDIX A
TIP Project Funding Summary
13
138
Appendix A: 2016-2021 Transportation Improvement Program - Project
Funding Summary
STP Metro
TIP-ID
Sponsor
Project Name
Funding
Amounts in $1,000s
Prior Funding
FY16
Federal
2007-044
RTD
FasTracks Projects: DRCOG First
Commitment Pool
$0
State
$0
$0
$0
$0
$0
Local
$1,000
$0
$0
$0
$0
$5,000
$0
$0
$0
$0
$65,000
Prior Funding
FY16
FY18
FY20-21
FY19
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$913
$0
$0
$0
$0
$4,563
$0
$0
$0
$0
$1,224,211
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$1,000
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$1,630
$250
$0
$0
$0
$8,148
$1,250
$0
$0
$0
$0
139
$0
$70,000
Total Funding
$0
Future
$6,518
Total
Total Funding
Future
$0
Federal
DRCOG Second Commitment to
FasTracks Pool
FY17
$3,650
Amounts in $1,000s
DRCOG
Future
$0
Total
2012-010
FY20-21
$0
Federal
FasTracks Eagle P-3 Corridors
(Gold and East Line)
FY19
$0
Amounts in $1,000s
RTD
FY18
$4,000
Total
2008-111
FY17
$1,228,774
Total Funding
$0
$9,398
Amounts in $1,000s
Prior Funding
FY16
Federal
2012-079
Northglenn
North Metro Rail 112th Ave Corridor
Improvements
State
$0
$0
$0
$0
$0
Local
$25
$207
$0
$0
$0
$124
$935
$0
$0
$0
$0
Prior Funding
FY16
FY18
FY19
FY20-21
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$46
$339
$0
$0
$0
$231
$1,696
$0
$0
$0
$0
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$459
$0
$0
$0
$0
$2,291
$0
$0
$0
$0
$0
140
$0
$1,059
Total Funding
$0
Future
$1,832
Total
Total Funding
Future
$1,357
Federal
Metro Center Station Area Bike/Ped
Connector Facility
FY17
$185
Amounts in $1,000s
Aurora
Future
$0
Total
2016-005
FY20-21
$0
Federal
North Metro Rail 72nd Ave and
Colorado Blvd Station Sidewalks
FY19
$0
Amounts in $1,000s
Commerce City
FY18
$728
Total
2012-080
FY17
$99
$1,927
Total Funding
$0
$2,291
Amounts in $1,000s
Prior Funding
FY16
Federal
2016-008
Boulder
Boulder Slough Multiuse Path: 30th
St to 3100 Pearl
State
$0
$0
$0
$0
$0
Local
$24
$24
$72
$0
$0
$120
$120
$360
$0
$0
$0
Prior Funding
FY16
Colfax 15L Transit Improvements: I225 to I-25
FY17
FY18
FY19
FY20-21
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$374
$0
$0
$0
$0
$1,866
$0
$0
$0
$0
$0
Prior Funding
FY16
FY17
FY19
FY18
FY20-21
$0
$0
$1,300
$1,300
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$325
$325
$0
$0
$0
$1,625
$1,625
$0
$0
141
$0
$600
Total Funding
$0
Future
Federal
Total
Total Funding
Future
$1,492
Amounts in $1,000s
RTD
Future
$0
Total
2016-019
FY20-21
$0
Federal
23rd Ave. Bike/Ped Path at
Fitzsimons Station
FY19
$288
Amounts in $1,000s
Aurora
FY18
$96
Total
2016-018
FY17
$96
$1,866
Total Funding
$0
$3,250
Amounts in $1,000s
Prior Funding
FY16
Federal
2016-020
Wheat Ridge
Wadsworth Blvd Widening: 35th
Ave to 48th Ave
State
$0
$0
$0
$0
$0
Local
$500
$1,000
$2,000
$2,820
$0
$2,500
$5,000
$10,000
$14,100
$0
$0
Prior Funding
FY16
FY18
FY19
FY20-21
$6,833
$0
$0
State
$0
$0
$0
$0
$0
Local
$2,971
$1,000
$6,624
$0
$0
$9,511
$5,000
$13,457
$0
$0
$0
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$5,379
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$1,957
$5,871
$0
$0
$0
$3,750
$11,250
$0
$0
$0
$0
142
$0
$31,600
Total Funding
$0
Future
$1,793
Total
Total Funding
Future
$4,000
Federal
Martin Luther King Jr. Blvd
Extension: Havana St to Peoria St
FY17
$6,540
Amounts in $1,000s
Denver
Future
$0
Total
2016-022
FY20-21
$11,280
Federal
I-25 & Broadway Interchange
Reconstruction
FY19
$8,000
Amounts in $1,000s
Denver
FY18
$4,000
Total
2016-021
FY17
$2,000
$27,968
Total Funding
$0
$15,000
Amounts in $1,000s
Prior Funding
FY16
Federal
2016-023
Denver
Quebec St Operational
Improvements: 13th Ave to 26th
State
$0
$0
$0
$0
$0
Local
$820
$3,560
$3,810
$3,310
$0
$1,640
$7,120
$7,620
$6,620
$0
$0
Prior Funding
FY16
FY18
FY19
FY20-21
$1,617
$0
$0
State
$0
$0
$0
$0
$0
Local
$72
$0
$404
$0
$0
$358
$0
$2,021
$0
$0
$0
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$400
$1,000
$3,825
$0
State
$0
$0
$0
$0
$0
Local
$250
$100
$250
$1,475
$0
$1,250
$500
$1,250
$5,300
$0
$0
143
$0
$23,000
Total Funding
$0
Future
$1,000
Total
Total Funding
Future
$0
Federal
Broadway Reconstruction: Violet
Ave to US-36
FY17
$286
Amounts in $1,000s
Boulder
Future
$0
Total
2016-026
FY20-21
$3,310
Federal
Ralston Rd Reconstruction: Yukon
St to Upham St
FY19
$3,810
Amounts in $1,000s
Arvada
FY18
$3,560
Total
2016-025
FY17
$820
$2,379
Total Funding
$0
$8,300
Amounts in $1,000s
2016-027
Castle Rock
Meadows Pkwy Reconstruction: US85 to Meadows Blvd
Prior Funding
FY16
$0
State
$0
$0
$0
$0
$0
Local
$0
$334
$0
$0
$0
$0
$1,667
$0
$0
$0
$0
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$2,400
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$600
$600
$0
$0
$0
$2,999
$3,000
$0
$0
$0
$0
Prior Funding
Federal
FY16
FY17
FY18
FY19
Total Funding
$0
Future
$2,399
Amounts in $1,000s
Golden
Future
$0
Total
2016-037
FY20-21
$0
Federal
16th St Mall Reconstruction:
Arapahoe St to Lawrence St
FY19
$1,333
Amounts in $1,000s
RTD
FY18
$0
Total
2016-028
FY17
Federal
FY20-21
Total Funding
$0
Future
$345
$2,700
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$90
$686
$0
$0
$0
$435
$3,386
$0
$0
$0
$1,667
$5,999
Total Funding
Washington Ave Complete Streets
$0
Total
144
$0
$3,821
Amounts in $1,000s
2016-041
Castle Rock
Founders Pkwy and Allen Way
Intersection Improvements
Prior Funding
US 85: Highlands Ranch Pkwy to
Blakeland Dr Capacity
RidgeGate Pkwy Widening: Havana
St to Lone Tree City Limits
FY20-21
Future
$1,447
$0
State
$0
$0
$0
$0
$0
Local
$0
$71
$68
$905
$0
$0
$355
$337
$2,352
$0
$0
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$0
$0
$5,000
$10,000
$0
State
$0
$0
$0
$0
$0
Local
$2,500
$2,500
$1,250
$5,750
$0
$2,500
$2,500
$6,250
$15,750
$0
$0
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$0
$0
$1,400
$5,000
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$3,400
$12,200
$0
$0
$0
$4,800
$17,200
$0
$0
145
$0
$3,044
Total Funding
$0
Future
Federal
Total
Total Funding
Future
Federal
Amounts in $1,000s
Lone Tree
FY19
$269
Total
2016-043
FY18
$284
Amounts in $1,000s
Douglas County
FY17
$0
Total
2016-042
FY16
Federal
$27,000
Total Funding
$0
$22,000
Amounts in $1,000s
Prior Funding
FY16
Federal
2016-044
Bennett
Hwy 79 and Hwy 36 Grade
Separation: FA and Design Study
State
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$392
$392
$392
$0
$0
$0
Prior Funding
FY16
FY18
FY19
FY20-21
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$20
$30
$0
$0
$0
$100
$150
$0
$0
$0
$0
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$100
$0
$0
$0
$0
$500
$0
$0
$0
$0
$0
146
$0
$1,176
Total Funding
$0
Future
$400
Total
Total Funding
Future
$120
Federal
Arapahoe Rd: I-25 to Parker Rd
Next Steps Operations Study
FY17
$80
Amounts in $1,000s
Centennial
Future
$0
Total
2016-046
FY20-21
$0
Federal
SH-7 BRT Study: Boulder to
Brighton
FY19
$392
Amounts in $1,000s
Boulder County
FY18
$392
Total
2016-045
FY17
$392
$250
Total Funding
$0
$500
Amounts in $1,000s
Prior Funding
FY16
Federal
2016-047
Commerce City
Industrial Area Transportation
Study: I-25 to I-270 to 40th
Future
$0
State
$0
$0
$0
$0
$0
Local
$300
$0
$0
$0
$0
$1,000
$0
$0
$0
$0
$0
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
Total Funding
$0
Future
$160
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$40
$0
$0
$0
$0
$200
$0
$0
$0
$0
$1,000
Total Funding
Erie Pkwy Study: SH-287 to I-25
$0
Total
Amounts in $1,000s
Prior Funding
Federal
Lakewood
FY20-21
$0
Federal
2016-049
FY19
$0
Amounts in $1,000s
Erie
FY18
$0
Total
2016-048
FY17
$700
FY16
FY17
FY18
FY19
FY20-21
$0
Future
$80
$40
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$20
$10
$0
$0
$0
$100
$50
$0
$0
$0
$200
Total Funding
Jeffco Bike Wayfinding Study
$0
Total
147
$0
$150
Amounts in $1,000s
Prior Funding
FY16
Federal
2016-050
RTD
SH 119 BRT NEPA Analysis:
Boulder to Longmont
Future
$0
State
$0
$0
$0
$0
$0
Local
$250
$0
$0
$0
$0
$1,250
$0
$0
$0
$0
$0
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
Total Funding
$0
Future
Federal
$0
$1,000
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$0
$500
$0
$0
$0
$0
$1,500
$0
$0
$0
$1,250
Total Funding
Regional BRT Feasibility Study
$0
Amounts in $1,000s
Prior Funding
FY16
Federal
RAQC
Ozone State Implementation Plan
(SIP) Modeling Study
Prior Funding
Federal
FY17
FY18
FY19
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$120
$0
$0
$0
$0
$600
$0
$0
$0
$0
FY16
$0
FY17
FY18
FY19
FY20-21
Future Funding
$29,591
$30,013
$36,162
$0
State
$0
$0
$0
$0
$0
Local
$13,273
$12,855
$15,435
$30,553
$0
$48,714
$42,446
$46,876
$69,287
$0
$1,289,211
148
$0
$0
Future
$0
$35,441
Total
FY20-21
$480
Total
STP Metro Project
Allocation Totals
FY20-21
$0
Total
2016-058
FY19
$0
Amounts in $1,000s
RTD
FY18
$0
Total
2016-051
FY17
$1,000
Total Funding
$1,496,534
$1,500
Total Funding
$0
$600
Congestion Mitigation / Air Quality
TIP-ID
Sponsor
Project Name
Funding
Amounts in $1,000s
Prior Funding
FY16
Federal
1999-097
DRCOG
Regional Transportation Demand
Management (TDM) Program Pool
State
$0
$0
$0
$0
$0
Local
$800
$0
$800
$0
$0
$4,000
$0
$4,000
$0
$0
$0
Prior Funding
FY16
FY19
FY18
FY20-21
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$1,000
$0
$0
$0
$0
$5,000
$0
$0
$0
$0
$65,000
Prior Funding
FY16
FY17
FY19
FY18
FY20-21
$600
$600
$600
$0
State
$0
$0
$0
$0
$0
Local
$150
$150
$150
$150
$0
$750
$750
$750
$750
$0
$0
149
$0
$8,000
Total Funding
$0
Future
$600
Total
Total Funding
Future
$0
Federal
Station Area Master Plan/Urban
Center Studies Pool
FY17
$4,000
Amounts in $1,000s
DRCOG
Future
$0
Total
2007-089
FY20-21
$0
Federal
FasTracks Projects: DRCOG First
Commitment Pool
FY19
$3,200
Amounts in $1,000s
RTD
FY18
$0
Total
2007-044
FY17
$3,200
$70,000
Total Funding
$0
$3,000
Amounts in $1,000s
Prior Funding
FY16
Federal
2012-010
DRCOG
DRCOG Second Commitment to
FasTracks Pool
State
$0
$0
$0
$0
$0
Local
$1,018
$0
$0
$0
$0
$5,091
$0
$0
$0
$0
$0
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$746
$0
$0
$0
$0
$1,701
$0
$0
$0
$0
$295
Prior Funding
Federal
FY16
FY17
FY18
FY19
Total Funding
$0
Future
$955
Amounts in $1,000s
DRCOG
Future
$0
Total
2012-064
FY20-21
$0
Federal
SH-119: South of Hover Bike/Ped
Underpass
FY19
$0
Amounts in $1,000s
Longmont
FY18
$0
Total
2012-051
FY17
$4,073
FY20-21
Total Funding
$0
Future
$3,600
$0
$3,600
$0
$0
State
$0
$0
$0
$0
$0
Local
$226
$0
$226
$0
$0
$3,826
$0
$3,826
$0
$0
$5,091
$1,996
Total Funding
Regional TDM Program: Way to Go
Total
$0
150
$0
$7,652
Amounts in $1,000s
Prior Funding
FY16
Federal
2016-002
RAQC
Future
$0
State
$0
$0
$0
$0
$0
Local
$330
$450
$450
$450
$0
$1,650
$2,250
$2,250
$2,250
$0
Total Funding
Air Quality Improvements Pool
$0
Prior Funding
FY16
FY17
FY18
FY20-21
FY19
$0
Future
Federal
$0
$6,000
$3,000
$16,000
$0
State
$0
$0
$0
$0
$0
Local
$0
$1,500
$750
$4,000
$0
$0
$7,500
$3,750
$20,000
$0
$8,400
Total Funding
I-70 East Reconstruction
Amounts in $1,000s
$0
Prior Funding
Federal
DRCOG
FY20-21
$1,800
Total
2016-004
FY19
$1,800
Amounts in $1,000s
CDOT Region 1
FY18
$1,800
Total
2016-003
FY17
$1,320
Regional Transportation Operations
Pool
FY16
FY17
FY18
FY20-21
FY19
Future
$4,839
$4,200
$4,200
$4,200
$0
State
$0
$0
$0
$0
$0
Local
$1,210
$1,050
$1,050
$1,050
$0
$6,049
$5,250
$5,250
$5,250
$0
Total
$0
151
$0
$31,250
Total Funding
$0
$21,799
Amounts in $1,000s
Prior Funding
FY16
Federal
2016-009
RTD
MetroRide Service Expansion: DUS
to Civic Center
Future
$0
State
$0
$0
$0
$0
$0
Local
$100
$100
$100
$0
$0
$500
$500
$500
$0
$0
$0
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
Total Funding
$0
Future
$536
$548
$580
$0
$0
State
$0
$0
$0
$0
$0
Local
$134
$137
$145
$0
$0
$670
$685
$725
$0
$0
$1,500
Total Funding
RTD L Route Service Enhancement
$0
Total
Amounts in $1,000s
Prior Funding
Federal
Boulder County
FY20-21
$0
Federal
2016-011
FY19
$400
Amounts in $1,000s
Boulder County
FY18
$400
Total
2016-010
FY17
$400
FLEX Route Extension: Boulder to
Longmont
FY16
FY17
FY18
FY19
FY20-21
Future
$380
$384
$392
$0
$0
State
$0
$0
$0
$0
$0
Local
$95
$96
$98
$0
$0
$475
$480
$490
$0
$0
Total
$0
152
$0
$2,080
Total Funding
$0
$1,445
Amounts in $1,000s
Prior Funding
FY16
Federal
2016-012
University of
Anschutz Medical Campus Shuttle
Colorado-Denver
Future
$0
State
$0
$0
$0
$0
$0
Local
$372
$136
$140
$0
$0
$1,239
$452
$466
$0
$0
$0
Prior Funding
FY16
FY17
FY18
FY20-21
FY19
Total Funding
$0
Future
$215
$102
$106
$0
$0
State
$0
$0
$0
$0
$0
Local
$54
$26
$27
$0
$0
$269
$128
$133
$0
$0
$2,157
Total Funding
Superior Call-n-Ride
Total
Amounts in $1,000s
$0
Prior Funding
Federal
Broomfield
FY20-21
$0
Federal
2016-014
FY19
$326
Amounts in $1,000s
Superior
FY18
$316
Total
2016-013
FY17
$867
FY16
FY17
FY18
FY20-21
FY19
$0
Future
$188
$89
$92
$0
$0
State
$0
$0
$0
$0
$0
Local
$80
$38
$40
$0
$0
$268
$127
$132
$0
$0
$530
Total Funding
Broomfield Call-n-Ride
Total
$0
153
$0
$527
Amounts in $1,000s
Prior Funding
FY16
Federal
2016-015
Longmont
RTD Route #324 Frequency
Improvements
State
$0
$0
$0
$0
$0
Local
$98
$98
$98
$0
$0
$490
$490
$490
$0
$0
$0
Prior Funding
FY16
Westerly Creek Trail to Toll Gate
Creek Trail Connector
FY17
FY18
FY20-21
FY19
$4,547
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$285
$1,137
$0
$0
$0
$1,421
$5,684
$0
$0
$0
$0
Prior Funding
FY16
FY17
FY18
FY20-21
FY19
$0
$2,501
$6,006
$0
$0
State
$0
$0
$0
$0
$0
Local
$0
$626
$2,502
$0
$0
$0
$3,127
$8,508
$0
$0
$0
154
$0
$1,470
Total Funding
$0
Future
Federal
Total
Total Funding
Future
$1,136
Amounts in $1,000s
Aurora
Future
$0
Total
2016-017
FY20-21
$0
Federal
Toll Gate Creek Trail: Chambers Rd
to Montview Blvd
FY19
$392
Amounts in $1,000s
Aurora
FY18
$392
Total
2016-016
FY17
$392
$7,105
Total Funding
$0
$11,635
Amounts in $1,000s
Prior Funding
FY16
Federal
2016-024
Arapahoe County Iliff Ave Operational Improvements:
Parker Rd to Quebec St
Superior Trail: McCaslin BRT to
Davidson Mesa Underpass
State
$0
$0
$0
$0
$0
Local
$500
$1,000
$2,000
$2,673
$0
$2,000
$4,000
$8,000
$9,519
$0
$0
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$0
$200
$147
$350
$0
State
$0
$0
$0
$0
$0
Local
$0
$50
$37
$191
$0
$0
$250
$184
$541
$0
$0
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$400
$600
$3,350
$0
State
$0
$0
$0
$0
$0
Local
$100
$100
$700
$2,350
$0
$500
$500
$1,300
$5,700
$0
$0
155
$0
$23,519
Total Funding
$0
Future
$400
Total
Total Funding
Future
Federal
Federal
30th St and Colorado Ave Bike/Ped
Underpass
Future
$0
Amounts in $1,000s
Boulder
FY20-21
$6,846
Total
2016-035
FY19
$6,000
Amounts in $1,000s
Superior
FY18
$3,000
Total
2016-034
FY17
$1,500
$975
Total Funding
$0
$8,000
Amounts in $1,000s
Prior Funding
FY16
FY17
Federal
2016-036
Parker
Parker Rd Sidewalk Connection:
Plaza Dr to Sulphur Gulch Trail
$0
State
$0
$0
$0
$0
$0
Local
$24
$24
$120
$0
$0
$96
$96
$480
$0
$0
$0
Prior Funding
FY16
FY17
$0
State
$0
$0
$0
$0
$0
Local
$114
$113
$113
$0
$0
$567
$564
$564
$0
$0
$0
Prior Funding
FY16
FY17
Federal
FY18
FY19
$1,000
$2,892
$0
State
$0
$0
$0
$0
$0
Local
$500
$500
$1,000
$6,475
$0
$1,000
$1,000
$2,000
$9,367
$0
FY16
FY17
FY18
FY19
FY20-21
Future Funding
$26,502
$33,252
$36,038
$0
State
$0
$0
$0
$0
$0
Local
$7,936
$7,331
$10,546
$17,339
$0
$37,562
$33,833
$43,798
$53,377
$0
$65,295
156
$0
$0
$0
Total Funding
$233,865
$672
Total Funding
Future
$500
$29,626
Total
FY20-21
$500
$0
Total Funding
Future
$0
Total
Prior Funding
FY20-21
$451
Federal
Congestion Mitigation / Air
Quality Project Allocation
Totals
FY19
$451
Amounts in $1,000s
Arapahoe County Gun Club Rd and Quincy Ave
Operational Improvements
FY18
$453
Total
2016-040
Future
$0
Federal
Route 73 Extension: Smith Rd
Station to 60th Ave and Dahlia St
FY20-21
$360
Amounts in $1,000s
Commerce City
FY19
$72
Total
2016-039
FY18
$72
$1,695
Total Funding
$0
$13,367
Bridge On-System
TIP-ID
Sponsor
Project Name
Funding
Amounts in $1,000s
Prior Funding
FY16
Federal
2007-078
CDOT Region 1
FY17
FY18
FY19
FY20-21
Future
$0
$0
$0
$0
$0
State
$14,692
$15,920
$9,472
$0
$0
Local
$0
$0
$0
$0
$0
$14,692
$15,920
$9,472
$0
$0
Total Funding
Region 1 Bridge On-System Pool
$0
Total
Facility Name
Start-At and End-At
6th Ave
Potomac to Airport
BNSF Replacement
Study
C-470
SH-265
Colfax
I-70 to Kipling
Morrison to Bowles
Cost (1,000s)
Facility Name
Start-At and EndAt
$263
I-70 Bridge Replacement
@Havana
$1,800
$250
I-70 Bridge Replacement
Havana St
$1,400
I-70 WB Deck Rehab
US-40 to DITCH
$3,508
$31
Cost (1,000s)
$330
I-70 WB to I-225 SB Flyover
$3,695
$10,336
Douglas County Scour
Repairs
Essential Culvert
Repairs (FY16)
$2,207
I-70/I-25 Ramps
$2,085
I-76
Essential Culvert
Repairs (FY17)
$2,669
I-76 Repairs
Essential Culvert
Repairs (FY18)
$2,669
Ramp to I-25 NB Pedestrian Overpass Removal
Study
96th to US-85
$280
$1,500
$250
Federal
92nd to 120th
$327
Santa Fe
Florida to I-25
$56
I-225
I-25 to Parker Rd
$63
SH-105 Bridge Removal Study
DRAW
$250
I-25
Hampden to Evans
$25
SH-95 Fiber Wrap
I-25
County Line Rd to Bellevue
$727
Sheridan
I-25 Repairs
$1,500
State Highway Repairs
I-25 T-Rex Narrows
$5,396
University
I-25/I-70/I-76
$4,110
US Highway Repairs
I-70 and I-225
$5,894
US-40
I-70 and I-25
$5,381
I-70 and I-270 Repairs
$1,500
$2,000
Hampden to
Arizona
$178
$750
Arapahoe to
Hampden
$845
$750
$241
US-40 Deck Rehab/Replacement
US-6 to Beaver
Brook
Beaver Brook
US-6
I-70 to SH-119
$498
US-85
Hampden to
Florida
$3,328
US-85
I-76 to 136th
$92
157
$100
$0
$40,084
Amounts in $1,000s
Prior Funding
FY16
Federal
2007-133
CDOT Region 4
FY18
FY19
Future
$0
$0
$0
State
$110
$3,300
$0
$0
$0
Local
$0
$0
$0
$0
$0
$110
$3,300
$0
$0
$0
Total Funding
Region 4 Bridge On-System Pool
Facility Name
Start-At and End-At
Cost (1,000s)
Bridge Asset
Management
I-25, US-157, US-287
$3,410
Prior Funding
FY16
Federal
$0
FY17
FY18
FY19
FY20-21
Future Funding
$0
$0
$0
$0
$0
State
$14,802
$19,220
$9,472
$0
$0
Local
$0
$0
$0
$0
$0
$14,802
$19,220
$9,472
$0
$0
Total
FY20-21
$0
Total
Bridge On-System Project
Allocation Totals
FY17
$0
$0
158
$0
Total Funding
$43,494
$0
$3,410
Bridge Off-System
TIP-ID
Sponsor
Project Name
Funding
Amounts in $1,000s
2008-028
CDOT Region 4
Prior Funding
Sponsor
FY19
FY20-21
Future
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total Funding
Region 4 Bridge Off-System Pool
Project Name
CDOT Region 1
FY18
$0
$0
$0
$0
Funding
Amounts in $1,000s
2007-079
FY17
$0
Total
TIP-ID
FY16
Federal
Prior Funding
FY16
FY17
FY19
FY18
FY20-21
Future
Federal
$0
$0
$0
$0
$0
State
$0
$0
$624
$0
$0
Local
$0
$0
$0
$0
$0
$0
$0
$624
$0
$0
Total Funding
Region 1 Bridge Off-System Pool
Total
$0
159
$0
$624
Safety
TIP-ID
Sponsor
Project Name
Funding
Amounts in $1,000s
Prior Funding
FY16
Federal
2007-073
CDOT Region 1
Future
$0
State
$16,635
$5,850
$0
$0
$0
Local
$0
$0
$0
$0
$0
$16,635
$5,850
$0
$0
$0
Total Funding
Region 1 Hazard Elimination Pool
$0
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$0
Future
$0
$0
$0
$0
$0
State
$413
$413
$413
$413
$0
Local
$0
$0
$0
$0
$0
$413
$413
$413
$413
$0
$22,485
Total Funding
Region 1 Hot Spot Pool
$0
Total
Amounts in $1,000s
Prior Funding
Federal
CDOT Region 1
FY20-21
$0
Federal
2007-075
FY19
$0
Amounts in $1,000s
CDOT Region 1
FY18
$0
Total
2007-074
FY17
$0
FY16
FY17
FY18
FY19
FY20-21
$0
Future
$0
$0
$0
$0
$0
State
$1,050
$6,650
$5,000
$0
$0
Local
$0
$0
$0
$0
$0
$1,050
$6,650
$5,000
$0
$0
$1,652
Total Funding
Region 1 Traffic Signals Pool
Total
$2,341
160
$0
$15,041
Amounts in $1,000s
2007-091
CDOT Region 4
Prior Funding
FY20-21
Future
$0
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total Funding
Region 4 Traffic Signals Pool
$637
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$0
Future
Federal
$0
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$637
Total Funding
Region 4 Hot Spot Pool
Amounts in $1,000s
CDOT Region 4
FY19
$0
$854
Total
2007-094
FY18
$0
Amounts in $1,000s
CDOT Region 4
FY17
$0
Total
2007-092
FY16
Federal
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$0
Future
Federal
$0
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$854
Total Funding
Region 4 Hazard Elimination Pool
Total
$15,785
161
$0
$15,785
Amounts in $1,000s
2012-115
CDOT Region 1
Prior Funding
FY16
FY17
Future
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total Funding
Region 1 Rockfall Mitigation
$1,500
Prior Funding
FY16
FY17
Federal
I-25: 120th Ave to E-470 Managed
Lanes
Prior Funding
Safety Project Allocation
Totals
FY18
FY19
$0
$0
$0
State
$3,000
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$3,000
$0
$0
$0
$0
FY16
$0
FY17
FY18
FY19
FY20-21
Future Funding
$0
$0
$0
$0
State
$21,098
$12,913
$5,413
$413
$0
Local
$0
$0
$0
$0
$0
$21,098
$12,913
$5,413
$413
$0
$2,341
162
$0
$0
Future
Funding
$0
$0
Federal
FY20-21
$0
Total
Total
FY20-21
$0
Amounts in $1,000s
CDOT Region 4
FY19
$0
Total
2016-055
FY18
Federal
Total Funding
$42,178
$1,500
Total Funding
$0
$3,000
Regional Priority Projects
TIP-ID
Sponsor
Project Name
Funding
Amounts in $1,000s
2001-154
CDOT Region 1
US-85: Cook Ranch Rd to Meadows
Pkwy Widening
Prior Funding
FY16
Future
$0
$0
State
$0
$6,500
$8,900
$3,500
$0
Local
$0
$0
$0
$0
$0
$0
$6,500
$8,900
$3,500
$0
$65,298
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
Total Funding
$37,300
Future
$0
$0
$0
$0
$0
State
$465
$451
$438
$425
$0
Local
$0
$0
$0
$0
$0
$465
$451
$438
$425
$0
$121,498
Total Funding
North I-25: Front Range EIS
Total
Amounts in $1,000s
CDOT Region 6
FY20-21
$0
Federal
2012-062
FY19
$0
Amounts in $1,000s
CDOT Region 4
FY18
$0
Total
2008-081
FY17
Federal
$21,317
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$0
Future
Federal
$0
$0
$0
$0
$0
State
$0
$1,600
$500
$0
$0
Local
$0
$0
$0
$0
$0
$0
$1,600
$500
$0
$0
$23,096
Total Funding
I-70/Kipling: NEPA Study
Total
$1,000
163
$0
$3,100
Amounts in $1,000s
Prior Funding
FY16
Federal
2012-063
CDOT Region 6
Future
$0
State
$900
$1,100
$0
$0
$0
Local
$0
$0
$0
$0
$0
$900
$1,100
$0
$0
$0
Total Funding
I-25 North PEL Action Items
US 85: Highlands Ranch Pkwy to
Blakeland Dr Capacity
$15,500
Prior Funding
FY17
FY18
FY19
FY20-21
$0
$0
$0
$0
State
$0
$0
$2,000
$1,000
$0
Local
$0
$0
$0
$0
$0
$0
$0
$2,000
$1,000
$0
$0
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$0
$0
$0
$0
State
$108
$108
$108
$0
$0
Local
$0
$0
$0
$0
$0
$108
$108
$108
$0
$0
$0
164
$17,500
Total Funding
$0
Future
$0
Total
$0
Future
$0
Federal
Hwy 79 and Hwy 36 Grade
Separation: FA and Design Study
FY16
Federal
Amounts in $1,000s
Bennett
FY20-21
$0
Total
2016-044
FY19
$0
Amounts in $1,000s
Douglas County
FY18
$0
Total
2016-042
FY17
$0
$3,000
Total Funding
$0
$324
Amounts in $1,000s
Prior Funding
FY16
Federal
2016-057
CDOT Region 1
FY18
FY19
Future
$0
$0
$0
State
$17,600
$15,700
$13,900
$8,500
$0
Local
$0
$0
$0
$0
$0
$17,600
$15,700
$13,900
$8,500
$0
Total Funding
Region 1 RPP Pool
Prior Funding
Federal
FY16
$0
FY18
FY17
FY19
FY20-21
Future Funding
$0
$0
$0
$0
$0
State
$19,135
$25,351
$25,893
$13,425
$0
Local
$0
$0
$0
$0
$0
$19,135
$25,351
$25,893
$13,425
$0
Total
FY20-21
$0
Total
Regional Priority Projects
Project Allocation Totals
FY17
$0
$96,159
165
$37,300
Total Funding
$217,263
$0
$55,700
Surface Treatment
TIP-ID
Sponsor
Project Name
Funding
Amounts in $1,000s
Prior Funding
FY16
Federal
2007-095
CDOT Region 4
FY19
FY20-21
Future
$0
$0
$0
State
$14,580
$14,580
$14,580
$0
$0
Local
$0
$0
$0
$0
$0
$14,580
$14,580
$14,580
$0
$0
Total Funding
Region 4 Surface Treatment Pool
Facility Name
Start-At and End-At
SH-119
Monarch Rd to Fordham St
$6,817
SH-119
MM 22.8 to 37.4
$11,000
SH-119
47th St to Monarch Rd
$11,100
$0
$0
$43,740
Cost (1,000s)
Amounts in $1,000s
Prior Funding
Federal
CDOT Region 1
FY18
$0
Total
2007-096
FY17
$0
FY16
FY17
FY18
FY19
FY20-21
Future
$0
$0
$0
$0
$0
State
$55,000
$52,800
$39,600
$43,400
$0
Local
$0
$0
$0
$0
$0
$55,000
$52,800
$39,600
$43,400
$0
Total Funding
Region 1 Surface Treatment Pool
$0
Total
Facility Name
Start-At and End-At
Cost (1,000s)
Facility Name
Start-At and End- Cost (1,000s)
At
6th
Potomac to Airport
$4,500
Preventative Maintenance
C-470
SH-8 to Bowles
$7,500
Santa Fe
Florida to I-25
$3,500
Colfax
I-70 to Kipling
$3,000
SH-128
$3,500
Colfax
Speer to Clarkson
$4,000
SH-72
Colfax
Peoria to Sable
$2,500
Sheridan
Federal
92nd to 120th
$6,000
University
Hampden
Dahlia to Yosemite
$4,000
US-287
I-225
I-25 to Parker Rd
$7,500
US-6
Eldorado to
Wadsworth
SH-93 to Coal
Creek Canyon
Hampden to
Arizona
Arapahoe to
Hampden
@ 120th Ave
Intersection
I-70 to SH-119
I-25
Hampden to Evans
$5,000
US-85
Hampden to
Florida
$2,500
I-25
County Line Rd to Belleview
$12,000
US-85
I-76 to 136th
$8,000
I-25
@ I-225
$500
Wadsworth
Highland to 10th
$2,500
I-76
96th to US-85
$6,500
Wadsworth
Bear Creek to 4th
$5,500
Kipling
Jewell to 6th
$4,000
166
$0
$1,500
$3,500
$5,000
$250
$2,500
$0
$190,800
Amounts in $1,000s
2016-055
CDOT Region 4
I-25: 120th Ave to E-470 Managed
Lanes
Prior Funding
Prior Funding
FY18
FY19
$0
$0
State
$0
$0
$0
$12,000
$0
Local
$0
$0
$0
$0
$0
$0
$0
$0
$12,000
$0
$0
FY17
FY18
FY19
FY20-21
Future Funding
$0
$0
$0
$0
State
$69,580
$67,380
$54,180
$55,400
$0
Local
$0
$0
$0
$0
$0
$69,580
$67,380
$54,180
$55,400
$0
$0
Future
$0
$0
Total
FY20-21
$0
FY16
Federal
FY17
$0
Total
Surface Treatment Project
Allocation Totals
FY16
Federal
167
$0
Total Funding
$246,540
Total Funding
$0
$12,000
Intelligent Transportation System
TIP-ID
Sponsor
Project Name
Funding
Amounts in $1,000s
2016-056
CDOT Region 1
Prior Funding
FY17
FY18
FY19
Future
$0
$0
$0
$0
State
$0
$9,494
$7,400
$0
$0
Local
$0
$0
$0
$0
$0
$0
$9,494
$7,400
$0
$0
Total Funding
Region 1 ITS Pool
Prior Funding
$0
FY16
FY17
FY18
FY19
FY20-21
Future Funding
Federal
$0
$0
$0
$0
$0
State
$0
$9,494
$7,400
$0
$0
Local
$0
$0
$0
$0
$0
$0
$9,494
$7,400
$0
$0
Total
FY20-21
$0
Total
Intelligent Transportation
System Project Allocation
Totals
FY16
Federal
$0
168
$0
Total Funding
$16,894
$0
$16,894
Section 5307
TIP-ID
Sponsor
Project Name
Funding
Amounts in $1,000s
Prior Funding
FY16
Federal
1997-084
RTD
RTD Preventive Maintenance:
Transit Vehicle Overhaul and
Maintenance
Prior Funding
State
$0
$0
$0
$0
$0
Local
$11,195
$11,250
$11,365
$11,475
$22,955
$66,886
$67,498
$68,175
$68,853
$137,711
$0
Prior Funding
FY16
FY17
FY18
FY19
$562
$578
$1,156
State
$0
$0
$0
$0
$0
Local
$106
$109
$113
$116
$232
$636
$654
$675
$694
$1,388
$0
FY17
FY18
FY19
FY20-21
Future Funding
$56,793
$57,372
$57,956
$115,912
State
$0
$0
$0
$0
$0
Local
$11,301
$11,359
$11,478
$11,591
$23,187
$67,522
$68,152
$68,850
$69,547
$139,099
$0
169
$0
Total Funding
$0
Future
Funding
$545
$56,221
Total
FY20-21
$530
FY16
Federal
Future
$114,756
Total
Section 5307 Project
Allocation Totals
FY20-21
$57,378
Federal
RTD Enhancements - ADA/Ped/Bus
Shelter
FY19
$56,810
Amounts in $1,000s
RTD
FY18
$56,248
Total
2007-169
FY17
$55,691
Total Funding
$413,170
$409,123
Total Funding
$0
$4,047
Section 5309 New Start
TIP-ID
Sponsor
Project Name
Funding
Amounts in $1,000s
Prior Funding
FY16
Federal
2007-059
RTD
FasTracks Southeast Corridor
Extension: Lincoln Ave to
RidgeGate Pkwy
Prior Funding
Federal
State
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$92,000
$42,706
$25,942
$1,141
$0
$39,379
FY16
Prior Funding
FY17
FY18
$45,950
$0
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$165,000
$150,000
$45,950
$0
$0
$1,224,211
FY16
FY18
FY17
FY19
FY20-21
Future Funding
$71,892
$1,141
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$150,000
$192,706
$71,892
$1,141
$0
170
$0
Total Funding
$0
Future
$150,000
$192,706
$1,263,590
FY20-21
FY19
$165,000
$150,000
Total
Future
$0
Total
Section 5309 New Start
Project Allocation Totals
FY20-21
$1,141
Federal
FasTracks Eagle P-3 Corridors
(Gold and East Line)
FY19
$25,942
Amounts in $1,000s
RTD
FY18
$42,706
Total
2008-111
FY17
$92,000
Total Funding
$1,679,329
$201,171
Total Funding
$0
$1,585,161
RTD Funds Only
TIP-ID
Sponsor
Project Name
Funding
Amounts in $1,000s
2007-050
RTD
FY19
FY20-21
Future
$0
$0
State
$0
$0
$0
$0
$0
Local
$5,362
$1,494
$0
$0
$0
$5,362
$1,494
$0
$0
$0
Total Funding
FasTracks Northwest Rail Corridor
FasTracks Central Corridor: 30th
Ave & Downing St to 38th Ave &
FasTracks North Metro: Denver
Union Station to 72nd Ave
$125,640
Prior Funding
FY16
FY17
FY19
FY18
FY20-21
$0
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$14
$15
$0
$0
$0
$14
$15
$0
$0
$0
$10,702
Prior Funding
FY16
FY17
FY19
FY18
FY20-21
$0
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$172,484
$84,690
$4,740
$0
$0
$172,484
$84,690
$4,740
$0
$0
$157,680
171
$132,496
Total Funding
$0
Future
Federal
Total
$0
Future
Federal
Amounts in $1,000s
RTD
FY18
$0
Total
2007-055
FY17
$0
Amounts in $1,000s
RTD
FY16
$0
Total
2007-053
Prior Funding
Federal
$10,731
Total Funding
$0
$419,594
Amounts in $1,000s
2007-056
RTD
FasTracks I-225 LRT Corridor:
Parker Rd to East Corridor
FasTracks Southwest Corridor
Extension: Mineral Station to C-470
FasTracks Southeast Corridor
Extension: Lincoln Ave to
FY19
FY20-21
Future
$0
$0
State
$0
$0
$0
$0
$0
Local
$76,508
$0
$0
$0
$0
$76,508
$0
$0
$0
$0
$684,248
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$0
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$23,150
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$0
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$43,190
$58,614
$29,872
$1,315
$0
$43,190
$58,614
$29,872
$1,315
$0
$39,379
172
$0
$760,756
Total Funding
$0
Future
Federal
Total
Total Funding
Future
Federal
Amounts in $1,000s
RTD
FY18
$0
Total
2007-059
FY17
$0
Amounts in $1,000s
RTD
FY16
$0
Total
2007-058
Prior Funding
Federal
$23,150
Total Funding
$0
$172,370
Amounts in $1,000s
2008-111
RTD
FasTracks Eagle P-3 Corridors
(Gold and East Line)
Prior Funding
US-36: Boulder to I-25 Managed
Lanes/BRT
Prior Funding
FY19
$0
State
$0
$0
$0
$0
$0
Local
$140,729
$140,856
$41,696
$0
$0
$140,729
$140,856
$41,696
$0
$0
$1,224,211
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$0
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$8,000
$838
$0
$0
$0
$8,000
$838
$0
$0
$0
FY16
$452,278
FY17
FY18
FY19
FY20-21
Future Funding
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$446,287
$286,507
$76,308
$1,315
$0
$446,287
$286,507
$76,308
$1,315
$0
173
$264,184
Total Funding
$0
Future
Federal
$0
$2,694,138
Future
$0
Federal
Total
FY20-21
$0
Total
RTD Funds Only Project
Allocation Totals
FY18
$0
Amounts in $1,000s
HPTE
FY17
$0
Total
2008-114
FY16
Federal
$264,184
Total Funding
$3,768,739
$1,547,492
Total Funding
$725,300
Faster Safety
TIP-ID
Sponsor
Project Name
Funding
Amounts in $1,000s
Prior Funding
FY16
CDOT Region 1
I-25: Santa Fe Dr to Alameda Ave
Interchange Improvements (Valley
Future
$0
$0
State
$11,156
$11,346
$2,000
$0
$0
Local
$0
$0
$0
$0
$0
$11,156
$11,346
$2,000
$0
$0
$119,724
Prior Funding
FY16
Federal
FY17
FY18
FY20-21
FY19
$0
$0
$0
$0
$0
State
$20,724
$2,424
$17,869
$19,869
$0
Local
$0
$0
$0
$0
$0
$20,724
$2,424
$17,869
$19,869
$0
$144,226
Total Funding
Region 1 FASTER Pool
Start-At and End-At
C-470 Path Separations
Cost (1,000s)
$1,572
Cable Median Barrier
$0
$86,453
Facility Name
I-76 Curve Reconstruction and Lane Balancing
Start-At and EndAt
US-85
I-76 Roundabouts at ramp terminals
Bromley Ln
FASTER Safety Design
$4,000
Region 1 TSM Study Outcomes
Founders Pkwy
Crowfoot Valley Rd
Intersection Reconstruct
$1,602
SH-121 Intersection Improvements
Waterton Rd
$0
SH-121/72nd Ave
$594
SH-177 Sidewalks
Right turn accel
lanes
Mineral Ave to
Orchard Rd
Cost (1,000s)
$6,150
$2,164
$5,000
$2,050
Highline Canal Trail
Underpass
I-70 at 32nd Ave and C- Chain Station Lighting
470
I-70 PPSL
$3,000
SH-2 Traffic Signal Upgrades
I-70/US-6
$1,000
SH-391
Jefferson County
Schools Access
$570
$1,224
SH-75 and Mineral Ave
$200
SH-95 Intersection Improvements
Curb ramp and
B/P crossing
64th Ave
US-85 and Kuner Rd Barrier Replacement
Bromley to Bridge
$560
Wadsworth TOD left turn protection
Girton, Eastman
and Yale
$200
I-76 and C-470 Cable
Barrier
Total Funding
Future
$0
Total
Facility Name
FY20-21
$0
Amounts in $1,000s
CDOT Region 1
FY19
$0
Total
2008-076
FY18
$0
Federal
2007-158
FY17
Chain station lighting
improvements
174
$961
$521
$440
$851
$0
$147,339
Amounts in $1,000s
Prior Funding
FY16
FY17
Federal
2008-077
CDOT Region 4
Start-At and End-At
SH-119
Gilpin CL to Boulder City
Limits
Shoulder Gaps and Safety
(Flood)
$0
State
$5,000
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$5,000
$0
$0
$0
$0
$0
$0
$5,000
$2,000
$3,000
Founders Pkwy and Allen Way
Intersection Improvements
Prior Funding
Prior Funding
FY16
FY17
FY18
FY19
Future
$0
$0
$0
$0
$0
State
$0
$0
$0
$280
$0
Local
$0
$0
$0
$0
$0
$0
$0
$0
$280
$0
FY16
$0
FY17
FY19
FY18
FY20-21
Future Funding
$0
$0
$0
$0
State
$36,880
$13,770
$19,869
$20,149
$0
Local
$0
$0
$0
$0
$0
$36,880
$13,770
$19,869
$20,149
$0
$206,177
FY20-21
Federal
$0
Federal
Total
Total Funding
Cost (1,000s)
Total
Faster Safety Project
Allocation Totals
Future
$0
Amounts in $1,000s
Castle Rock
FY20-21
$0
Region 4 FASTER Pool
Facility Name
2016-041
FY19
$0
Total
SH-7
FY18
$0
175
$0
Total Funding
$296,845
Total Funding
$0
$280
FASTER Br. Enterprise
TIP-ID
Sponsor
Project Name
Funding
Amounts in $1,000s
Prior Funding
FY16
FY17
Federal
2008-103
CDOT Region 1
Region 1 FASTER Bridge
Enterprise Pool
Start-At and End-At
County Rd
Over I-70
$7,296
I-70
Over UPRR
$11,934
I-70 Frontage Rd
Over Clear Creek
$3,910
I-70 Viaduct
(see TIP ID-2016-003)
I-70 WB
Over US 6, Clear Creek
SH-9
Over Platte Gulch
US-287 (Federal)
Over BNFN at 69th Ave
$12,154
US-36
Over Draw
$3,379
US-85
Sand Creek
$113
York St
Over I-270
$17,380
$0
State
$11,000
$4,154
$17,000
$54,773
$0
Local
$0
$0
$0
$0
$0
$11,000
$4,154
$17,000
$54,773
$0
$113
Total Funding
$0
$87,040
Cost (1,000s)
$30,000
$874
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
Future
$0
$0
$0
$0
$0
State
$8,080
$752,170
$0
$0
$0
Local
$0
$0
$0
$0
$0
$8,080
$752,170
$0
$0
$0
Total Funding
I-70 East Reconstruction
Total
Prior Funding
FASTER Br. Enterprise
Project Allocation Totals
Federal
FY16
$0
FY17
FY18
FY19
FY20-21
Future Funding
$0
$0
$0
$0
$0
State
$19,080
$756,324
$17,000
$54,773
$0
Local
$0
$0
$0
$0
$0
$19,080
$756,324
$17,000
$54,773
$0
Total
Future
$0
Federal
CDOT Region 1
FY20-21
$0
Amounts in $1,000s
2016-003
FY19
$0
Total
Facility Name
FY18
$0
$113
176
$0
Total Funding
$847,290
$0
$760,250
Section 5337 State of Good Repair
TIP-ID
Sponsor
Project Name
Funding
Amounts in $1,000s
Prior Funding
FY16
Federal
1999-052
RTD
FY19
FY18
FY20-21
Future
$11,000
$11,000
$11,000
$22,000
State
$0
$0
$0
$0
$0
Local
$2,500
$2,500
$2,500
$2,500
$5,000
$13,500
$13,500
$13,500
$13,500
$27,000
Total Funding
State of Good Repair
Total
Section 5337 State of
Good Repair Project
Allocation Totals
FY17
$11,000
Prior Funding
FY16
Federal
$0
FY17
FY18
FY19
FY20-21
Future Funding
$11,000
$11,000
$11,000
$11,000
$22,000
State
$0
$0
$0
$0
$0
Local
$2,500
$2,500
$2,500
$2,500
$5,000
$13,500
$13,500
$13,500
$13,500
$27,000
Total
$0
177
$0
Total Funding
$81,000
$0
$81,000
Faster Transit
TIP-ID
Sponsor
Project Name
Funding
Amounts in $1,000s
2008-106
CDOT Region 4
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
Future
Federal
$0
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total Funding
Region 4 FASTER Transit Pool
Total
$5,374
178
$0
$5,374
Workforce Initiative Now
TIP-ID
Sponsor
Project Name
Funding
Amounts in $1,000s
Prior Funding
FY16
Federal
2012-068
RTD
RTD Regional Workforce Initiative
Now (WIN)
Prior Funding
Federal
FY18
FY19
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$487
$0
$0
$0
$0
$974
$0
$0
$0
$0
FY16
$584
FY17
FY18
FY19
FY20-21
Future Funding
$487
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$487
$0
$0
$0
$0
$974
$0
$0
$0
$0
Total
$584
Future
FY20-21
$0
Total
Workforce Initiative Now
Project Allocation Totals
FY17
$487
179
$0
Total Funding
$0
Total Funding
$1,558
$1,558
Section 5339
TIP-ID
Sponsor
Project Name
Funding
Amounts in $1,000s
Prior Funding
FY16
Federal
2012-108
RTD
RTD Capital Improvements: Bus
and Facilities Funding
Prior Funding
FY19
$10,743
State
$0
$0
$0
$0
$0
Local
$1,042
$1,053
$1,063
$1,074
$2,147
$6,251
$6,314
$6,377
$6,441
$12,890
$0
FY17
FY18
FY19
FY20-21
Future Funding
$5,261
$5,314
$5,367
$10,743
State
$0
$0
$0
$0
$0
Local
$1,042
$1,053
$1,063
$1,074
$2,147
$6,251
$6,314
$6,377
$6,441
$12,890
$0
Future
$5,367
$5,209
Total
FY20-21
$5,314
FY16
Federal
FY18
$5,261
Total
Section 5339 Project
Allocation Totals
FY17
$5,209
180
$0
Total Funding
$38,273
Total Funding
$0
$38,273
RAMP
TIP-ID
Sponsor
Project Name
Funding
Amounts in $1,000s
Prior Funding
FY16
Federal
2012-109
CDOT Region 4
Future
$0
State
$3,723
$875
$0
$0
$0
Local
$1,316
$219
$0
$0
$0
$5,039
$1,094
$0
$0
$0
Total Funding
Region 4 RAMP Project Pool
$8,513
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$0
$0
$0
$0
$0
State
$999
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$999
$0
$0
$0
$0
$0
Future
Funding
$14,646
Total Funding
Region 1 RAMP Project Pool
Total
Amounts in $1,000s
$2,745
Prior Funding
Federal
CDOT Region 4
FY20-21
$0
Federal
2016-055
FY19
$0
Amounts in $1,000s
CDOT Region 1
FY18
$0
Total
2012-112
FY17
$0
I-25: 120th Ave to E-470 Managed
Lanes
FY16
FY17
FY18
FY19
FY20-21
Future
$0
$0
$0
$0
$0
State
$40,000
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$40,000
$0
$0
$0
$0
Total
$0
181
$0
$3,744
Total Funding
$0
$40,000
Amounts in $1,000s
Prior Funding
FY16
Federal
2016-059
CDOT Region 1
C-470 Managed Toll Express Lanes:
Kipling to I-25
Prior Funding
Federal
FY18
FY19
$0
$0
State
$20,000
$40,000
$40,000
$0
$0
Local
$0
$0
$0
$0
$0
$20,000
$40,000
$40,000
$0
$0
FY16
$0
FY17
FY18
FY19
FY20-21
Future Funding
$0
$0
$0
$0
State
$64,722
$40,875
$40,000
$0
$0
Local
$1,316
$219
$0
$0
$0
$66,038
$41,094
$40,000
$0
$0
$11,258
Future
$0
$0
Total
FY20-21
$0
Total
RAMP Project Allocation
Totals
FY17
$0
182
$0
Total Funding
$158,390
Total Funding
$0
$100,000
Federal Emergency
TIP-ID
Sponsor
Project Name
Funding
Amounts in $1,000s
Prior Funding
FY16
Federal
2012-116
CDOT Region 4
Region 4 2013 Flood-Related
Projects Pool
Prior Funding
Federal
FY18
FY19
$0
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$37,603
$11,161
$2,444
$0
$0
$78,304
FY17
FY16
FY18
FY19
FY20-21
Future Funding
$11,161
$2,444
$0
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$0
$0
$0
$37,603
$11,161
$2,444
$0
$0
$78,304
Future
$2,444
$37,603
Total
FY20-21
$11,161
Total
Federal Emergency
Project Allocation Totals
FY17
$37,603
183
$0
Total Funding
$129,512
Total Funding
$0
$129,512
Transportation Alternatives
TIP-ID
Sponsor
Project Name
Funding
Amounts in $1,000s
Prior Funding
FY16
Federal
2016-006
Lakewood
Multi-use path on the D10:
Wadworth Blvd to Zephyr St and
Kipling St to Oak St
State
$0
$0
$0
$0
$0
Local
$80
$134
$266
$0
$0
$400
$670
$1,330
$0
$0
$0
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$254
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$33
$64
$0
$0
$0
$165
$318
$0
$0
$0
$0
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$0
$0
$0
$999
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$0
$250
$0
$0
$0
$0
$1,249
$0
$0
184
$0
$2,400
Total Funding
$0
Future
Federal
Total
Total Funding
Future
$132
Amounts in $1,000s
East Lafayette Multimodal Path
Connection: Commerce Ct to
Lafayette Park-n-Ride
Future
$0
Total
Lafayette
FY20-21
$0
Federal
2016-029
FY19
$1,064
Amounts in $1,000s
University of
University of Colorado Boulder East
Colorado-Boulder Campus Pedestrian Bridge & Trail
FY18
$536
Total
2016-007
FY17
$320
$483
Total Funding
$0
$1,249
Amounts in $1,000s
2016-030
Boulder County
71st St Multimodal Pathway
Connection: Winchester to Idylwild
Trail
Prior Funding
C-470 Multi-use Trail: Grade
Separation at Yosemite St
FY20-21
Future
$860
$0
State
$0
$0
$0
$0
$0
Local
$0
$0
$0
$215
$0
$0
$0
$0
$1,075
$0
$0
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$0
$0
$500
$1,500
$0
State
$0
$0
$0
$0
$0
Local
$300
$300
$350
$1,050
$0
$300
$300
$850
$2,550
$0
$0
Prior Funding
Federal
FY16
FY17
FY18
FY20-21
FY19
$539
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$13
$135
$0
$0
$0
$63
$674
$0
$0
$0
$0
185
$0
$1,075
Total Funding
$0
Future
$50
Total
Total Funding
Future
Federal
Amounts in $1,000s
Jefferson County US-6 Shared-Use Path: Colfax Ave
to Johnson Rd
FY19
$0
Total
2016-032
FY18
$0
Amounts in $1,000s
Douglas County
FY17
$0
Total
2016-031
FY16
Federal
$4,000
Total Funding
$0
$737
Amounts in $1,000s
Prior Funding
FY16
Federal
2016-033
Superior
Superior Trail: McCaslin BRT
Station to Coal Creek
State
$0
$0
$0
$0
$0
Local
$70
$80
$0
$0
$0
$350
$400
$0
$0
$0
$0
Prior Funding
FY16
Williams Fork Trail Multi-use Path:
63rd St to Twin Lakes Rd
FY17
FY18
FY19
FY20-21
$1,300
$1,250
$0
$0
State
$0
$0
$0
$0
$0
Local
$500
$350
$500
$0
$0
$2,000
$1,650
$1,750
$0
$0
$0
Prior Funding
FY16
FY17
FY18
FY19
FY20-21
$0
$632
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$0
$158
$0
$0
$0
$0
$790
$0
$0
$0
$0
186
$0
$750
Total Funding
$0
Future
Federal
Total
Total Funding
Future
$1,500
Amounts in $1,000s
Boulder County
Future
$0
Total
2016-052
FY20-21
$0
Federal
High Line Canal Trail Underpass at
Hampden and Colorado
FY19
$0
Amounts in $1,000s
Cherry Hills
Village
FY18
$320
Total
2016-038
FY17
$280
$5,400
Total Funding
$0
$790
Amounts in $1,000s
Prior Funding
FY16
Federal
2016-053
Mead
Future
$0
State
$0
$0
$0
$0
$0
Local
$100
$0
$0
$0
$0
$500
$0
$0
$0
$0
Total Funding
Mead School to School Trail Project
$0
Prior Funding
FY16
Boulder County Bus-then-Bike
Shelters
FY17
FY18
FY19
FY20-21
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$57
$0
$0
$0
$0
$283
$0
$0
$0
$0
$0
Amounts in $1,000s
Prior Funding
Federal
FY16
FY17
FY18
FY19
$0
Future
$226
Total
CDOT
FY20-21
$0
Federal
2016-060
FY19
$0
Amounts in $1,000s
Boulder County
FY18
$0
Total
2016-054
FY17
$400
FY20-21
Total Funding
$0
Future
$700
$0
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$175
$0
$0
$0
$0
$875
$0
$0
$0
$0
$500
$283
Total Funding
I-70/Genesee Bike Path
Total
$88
187
$0
$963
Amounts in $1,000s
Prior Funding
FY16
Federal
2016-061
Lakewood
Sheridan Blvd Sidewalks: W. 8th
Ave to W. 10th Ave
Prior Funding
State
$0
$0
$0
$0
$0
Local
$100
$0
$0
$0
$0
$500
$0
$0
$0
$0
$500
Prior Funding
FY16
FY17
FY18
FY19
$0
$0
$0
State
$0
$0
$0
$0
$0
Local
$100
$100
$0
$0
$0
$500
$500
$0
$0
$0
$0
FY17
FY18
FY19
FY20-21
Future Funding
$3,981
$2,814
$3,359
$0
State
$0
$0
$0
$0
$0
Local
$1,528
$1,321
$1,116
$1,515
$0
$5,936
$5,302
$3,930
$4,874
$0
$588
Prior Funding
Grand Total of Revenues
FY16
FY17
FY18
FY19
FY20-21
Future Funding
Federal
$329,995
$336,995
$214,101
$151,023
$148,655
State
$245,297
$945,327
$179,851
$144,160
$0
Local
$485,670
$323,145
$118,446
$65,887
$30,334
$1,060,962
$1,605,467
$512,398
$361,070
$178,989
Total
$5,713,132
188
$0
$301,484
Total Funding
$0
Future
Funding
$400
$4,408
Total
FY20-21
$400
FY16
Federal
Future
$0
Total
Transportation
Alternatives Project
Allocation Totals
FY20-21
$0
Federal
Sheridan Blvd Sidewalks: Colfax
Ave to 17th
FY19
$0
Amounts in $1,000s
Denver
FY18
$0
Total
2016-062
FY17
$400
Total Funding
$20,630
Total Funding
$9,733,502
$1,000
Total Funding
$0
$1,000
APPENDIX B
Major Projects in the 2012-2017 Transportation Improvement Program
Not Yet Completed
and
Rollover List
189
190
Major Projects with Completion Funds Obligated, but Construction
Not Substantially Completed Before 2016-2021 TIP
TIP ID
2001-214
Project Description
Project Title
C-470: Wadsworth to Santa Fe
th
Sponsor
Roadway Resurfacing
CDOT Region 1
2001-214
I-25: US-36 to 120 Managed Lanes
Roadway Recon/Capacity
CDOT Region 1
2001-214
I-70: Havana to I-225
Roadway Resurfacing
CDOT Region 1
2001-214
I-76: Federal to I-70
Roadway Resurfacing
CDOT Region 1
2001-214
Wadsworth: Parkhill to Florida
Roadway Resurfacing
CDOT Region 1
2001-214
SH-58: US-6 to I-70
Roadway Resurfacing
CDOT Region 1
2001-214
US-6: Sheridan to Simms
Roadway Resurfacing
CDOT Region 1
Roadway Resurfacing
CDOT Region 1
Roadway Resurfacing
CDOT Region 1
th
2001-214
US-6: I-70 to I-76 and 60
2001-214
US-85: Blakeland to Crestline
th
2007-029
120 Connection: Wadsworth to US-287
New Roadway
Broomfield
2007-078
I-70 East: Smith and UPRR Bridge
Bridge Replacement
CDOT Region 1
2007-096
Federal: 92
Roadway Resurfacing
CDOT Region 1
2007-095
SH-66: MP 39-43
Roadway Resurfacing
CDOT Region 4
2007-096
I-70 East: Tower to Colfax
Roadway Resurfacing
CDOT Region 1
nd
to 120
th
th
2007-096
I-76: 96 to US-85
Roadway Resurfacing
CDOT Region 1
2007-096
SH-86 (Founders Pkwy): MP 100.2-104.3
Roadway Resurfacing
CDOT Region 1
2007-096
University: Arapahoe to Hampden
Roadway Resurfacing
CDOT Region 1
2007-171
US-6 Bridges
Bridge Replacement
CDOT Region 1
2008-078
I-270 Resurfacing
Roadway Resurfacing
CDOT Region 1
2008-078
SH-93 Shoulders: SH-72, SH-128
Roadway Operational
CDOT Region 1
2008-078
SH-95 Intersection Improvements
Roadway Operational
CDOT Region 1
2008-104
County Rd (Design): Old Wadsworth @ US-36
Bridge Replacement
CDOT Region 1
Bridge Replacement
CDOT Region 1
th
2008-104
Federal at 69
2008-104
I-70 at Sand Creek
Bridge Replacement
CDOT Region 1
2008-104
I-70 East Preconstruction Activities
Bridge Replacement
CDOT Region 1
2008-104
I-76 at S. Platte
Bridge Replacement
CDOT Region 1
2008-104
I-76 at UPRR
Bridge Replacement
CDOT Region 1
2008-104
Peoria at I-76
Bridge Replacement
CDOT Region 1
2008-104
Wadsworth at Bear Creek
Bridge Replacement
CDOT Region 1
2008-104
Wadsworth at US-36
Bridge Replacement
CDOT Region 1
2008-104
SH-30: Havana at Cherry Creek
Bridge Replacement
CDOT Region 1
2008-104
SH-30: Havana at I-70
Bridge Replacement
CDOT Region 1
2008-104
SH-40 at Sand Creek
Bridge Replacement
CDOT Region 1
th
2008-104
SH-44: 104 at Bull Seep
Bridge Replacement
CDOT Region 1
2008-104
SH-58 at Ford
Bridge Replacement
CDOT Region 1
2008-104
SH-88 at Cherry Creek
Bridge Replacement
CDOT Region 1
2008-104
Sheridan (Design) at UPRR
Bridge Replacement
CDOT Region 1
2008-104
US-6 (design) at Sheridan
Bridge Replacement
CDOT Region 1
th
2012-041
120 and Federal Operational Improvements
Roadway Operational
Westminster
2012-063
I-25 North PEL Action Items
Roadway Operational
CDOT Region 1
191
Major Projects with Completion Funds Obligated, but Construction
Not Substantially Completed Before 2016-2021 TIP
2012-065
2012-072
2012-089
2012-110
2012-111
2012-113
I-70/Pecos Bridge
Federal and 92
nd
Operational Improvements
Wadsworth: Highlands to 10
th
th
US-6/19 Grade Separation
th
Federal: 6 to Howard Widening
nd
SH-2: 72 to I-76 Widening and Devolution
Bridge Replacement
CDOT Region 1
Roadway Operational
Federal Heights
Roadway Capacity
Lakewood
Roadway Capacity
CDOT Region 1
Roadway Capacity
CDOT Region 1
Roadway Capacity
CDOT Region 1
Major Projects Delayed; Major Elements Included in 2016-2021 TIP
(including Rollover List)
2001-154
US-85: Cook Ranch to Meadows Widening
Project
Description
Roadway Capacity
2005-072
US-6: Wadsworth Interchange Reconstruction
Interchange Recon
CDOT Region 1
2007-080
US-40 and Tollgate Creek Bridge Replacement
Bridge Replacement
CDOT Region 1
2007-095
SH-119: MP 59-64
Roadway Resurfacing
CDOT Region 4
TIP ID
Project Title
th
Sponsor
CDOT Region 1
2012-036
2012-043
2012-073
Wadsworth: Highlands to 10
I-25/Arapahoe Interchange Reconstruction
th
North I-25 Managed Lanes: US-36 to 120
Roadway Capacity
Interchange Recon
Roadway Capacity
Lakewood
Arapahoe County
CDOT Region 1
2012-096
I-25: Ridgegate to County Line Lane Balancing
Roadway Capacity
Douglas County
Note: Major projects reported have a total cost greater than $5 million.
Rollover list will be added at a later time.
192
APPENDIX C
Lookup List of Projects
By:
1. County
2. City
3. Project Type
193
194
2016-2021 TIP Projects by County
County
TIP ID
Project Name
2016-012
Anschutz Medical Campus Shuttle
2016-019
Colfax 15L Transit Improvements: I-225 to I-25
2008-111
FasTracks Eagle P-3 Corridors (Gold and East Line)
2007-056
FasTracks I-225 LRT Corridor: Parker Rd to East Corridor Commuter Rail
2007-055
FasTracks North Metro: Denver Union Station to 72nd Ave
2007-050
FasTracks Northwest Rail Corridor
2016-044
Hwy 79 and Hwy 36 Grade Separation: FA and Design Study
2012-063
I-25 North PEL Action Items
2016-055
I-25: 120th Ave to E-470 Managed Lanes
2016-047
Industrial Area Transportation Study: I-25 to I-270 to 40th Ave/Smith Rd
2012-079
North Metro Rail 112th Ave Corridor Improvements
2012-080
North Metro Rail 72nd Ave and Colorado Blvd Station Sidewalks
2007-078
Region 1 Bridge On-System Pool
2008-103
Region 1 FASTER Bridge Enterprise Pool
2008-076
Region 1 FASTER Pool
2007-073
Region 1 Hazard Elimination Pool
2007-074
Region 1 Hot Spot Pool
2016-056
Region 1 ITS Pool
2012-112
Region 1 RAMP Project Pool
2016-057
Region 1 RPP Pool
2007-096
Region 1 Surface Treatment Pool
2007-075
Region 1 Traffic Signals Pool
2016-039
Route 73 Extension: Smith Rd Station to 60th Ave and Dahlia St
2016-010
RTD L Route Service Enhancement
2016-045
SH-7 BRT Study: Boulder to Brighton
2016-016
Toll Gate Creek Trail: Chambers Rd to Montview Blvd
2008-114
US-36: Boulder to I-25 Managed Lanes/BRT
TIP ID
Project Name
2016-046
Arapahoe Rd: I-25 to Parker Rd Next Steps Operations Study
2016-059
C-470 Managed Toll Express Lanes: Kipling to I-25
2016-019
Colfax 15L Transit Improvements: I-225 to I-25
2007-056
FasTracks I-225 LRT Corridor: Parker Rd to East Corridor Commuter Rail
2007-058
FasTracks Southwest Corridor Extension: Mineral Station to C-470
2016-040
Gun Club Rd and Quincy Ave Operational Improvements
2016-038
High Line Canal Trail Underpass
2016-024
Iliff Ave Operational Improvements: Parker Rd to Quebec St
2016-005
Metro Center Station Area Bike/Ped Connector Facility
2007-078
Region 1 Bridge On-System Pool
2008-103
Region 1 FASTER Bridge Enterprise Pool
Adams
County
Arapahoe
195
2016-2021 TIP Projects by County
County
2008-076
Region 1 FASTER Pool
2007-073
Region 1 Hazard Elimination Pool
2007-074
Region 1 Hot Spot Pool
2016-056
Region 1 ITS Pool
2012-112
Region 1 RAMP Project Pool
2016-057
Region 1 RPP Pool
2007-096
Region 1 Surface Treatment Pool
2007-075
Region 1 Traffic Signals Pool
2016-016
Toll Gate Creek Trail: Chambers Rd to Montview Blvd
2016-017
Westerly Creek Trail to Toll Gate Creek Trail Connector
TIP ID
Project Name
2016-035
30th St and Colorado Ave Bike/Ped Underpass
2016-030
71st St Multimodal Pathway Connection: Winchester to Idylwild Trail
2016-054
Boulder County Bus-then-Bike Shelters
2016-008
Boulder Slough Multiuse Path: 30th St to 3100 Pearl
2016-026
Broadway Reconstruction: Violet Ave to US-36
2016-029
East Lafayette Multimodal Path Connection: Commerce Ct to Lafayette Park-n-Ride
2016-048
Erie Pkwy Study: SH-287 to I-25
2016-011
FLEX Route Extension: Boulder to Longmont
2012-116
Region 4 2013 Flood-Related Projects Pool
2008-028
Region 4 Bridge Off-System Pool
2007-133
Region 4 Bridge On-System Pool
2008-077
Region 4 FASTER Pool
2008-106
Region 4 FASTER Transit Pool
2007-094
Region 4 Hazard Elimination Pool
2007-092
Region 4 Hot Spot Pool
2012-109
Region 4 RAMP Project Pool
2007-095
Region 4 Surface Treatment Pool
2007-091
Region 4 Traffic Signals Pool
2016-010
RTD L Route Service Enhancement
2016-015
RTD Route #324 Frequency Improvements
2016-050
SH 119 BRT NEPA Analysis: Boulder to Longmont
2012-051
SH-119: South of Hover Bike/Ped Underpass
2016-045
SH-7 BRT Study: Boulder to Brighton
2016-013
Superior Call-n-Ride
2016-033
Superior Trail: McCaslin BRT Station to Coal Creek
2016-034
Superior Trail: McCaslin BRT to Davidson Mesa Underpass
2016-007
University of Colorado Boulder East Campus Pedestrian Bridge & Trail Connection
2008-114
US-36: Boulder to I-25 Managed Lanes/BRT
2016-052
Williams Fork Trail Multi-use Path: 63rd St to Twin Lakes Rd
Boulder
196
2016-2021 TIP Projects by County
County
TIP ID
Project Name
2016-014
Broomfield Call-n-Ride
2016-055
I-25: 120th Ave to E-470 Managed Lanes
2007-078
Region 1 Bridge On-System Pool
2008-103
Region 1 FASTER Bridge Enterprise Pool
2008-076
Region 1 FASTER Pool
2007-073
Region 1 Hazard Elimination Pool
2007-074
Region 1 Hot Spot Pool
2016-056
Region 1 ITS Pool
2012-112
Region 1 RAMP Project Pool
2016-057
Region 1 RPP Pool
2007-096
Region 1 Surface Treatment Pool
2007-075
Region 1 Traffic Signals Pool
2016-010
RTD L Route Service Enhancement
2016-045
SH-7 BRT Study: Boulder to Brighton
2008-114
US-36: Boulder to I-25 Managed Lanes/BRT
TIP ID
Project Name
2016-028
16th St Mall Reconstruction: Arapahoe St to Lawrence St
2016-019
Colfax 15L Transit Improvements: I-225 to I-25
2007-053
FasTracks Central Corridor: 30th Ave & Downing St to 38th Ave & Blake St
2008-111
FasTracks Eagle P-3 Corridors (Gold and East Line)
2007-055
FasTracks North Metro: Denver Union Station to 72nd Ave
2007-050
FasTracks Northwest Rail Corridor
2016-038
High Line Canal Trail Underpass
2016-021
I-25 & Broadway Interchange Reconstruction
2007-158
I-25: Santa Fe Dr to Alameda Ave Interchange Improvements (Valley Hwy Phases I and II)
2016-003
I-70 East Reconstruction
2016-024
Iliff Ave Operational Improvements: Parker Rd to Quebec St
2016-047
Industrial Area Transportation Study: I-25 to I-270 to 40th Ave/Smith Rd
2016-022
Martin Luther King Jr. Blvd Extension: Havana St to Peoria St
2016-009
MetroRide Service Expansion: DUS to Civic Center
2016-023
Quebec St Operational Improvements: 13th Ave to 26th Ave
2007-078
Region 1 Bridge On-System Pool
2008-103
Region 1 FASTER Bridge Enterprise Pool
2008-076
Region 1 FASTER Pool
2007-073
Region 1 Hazard Elimination Pool
2007-074
Region 1 Hot Spot Pool
2016-056
Region 1 ITS Pool
2012-112
Region 1 RAMP Project Pool
2016-057
Region 1 RPP Pool
Broomfield
County
Denver
197
2016-2021 TIP Projects by County
County
2007-096
Region 1 Surface Treatment Pool
2007-075
Region 1 Traffic Signals Pool
2016-039
Route 73 Extension: Smith Rd Station to 60th Ave and Dahlia St
2016-010
RTD L Route Service Enhancement
2016-062
Sheridan Blvd Sidewalks: Colfax Ave to 17th
1999-052
State of Good Repair
TIP ID
Project Name
2016-059
C-470 Managed Toll Express Lanes: Kipling to I-25
2016-031
C-470 Multi-use Trail: Grade Separation at Yosemite St
2007-059
FasTracks Southeast Corridor Extension: Lincoln Ave to RidgeGate Pkwy
2007-058
FasTracks Southwest Corridor Extension: Mineral Station to C-470
2016-041
Founders Pkwy and Allen Way Intersection Improvements
2016-027
Meadows Pkwy Reconstruction: US-85 to Meadows Blvd
2016-036
Parker Rd Sidewalk Connection: Plaza Dr to Sulphur Gulch Trail
2007-078
Region 1 Bridge On-System Pool
2008-103
Region 1 FASTER Bridge Enterprise Pool
2008-076
Region 1 FASTER Pool
2007-073
Region 1 Hazard Elimination Pool
2007-074
Region 1 Hot Spot Pool
2016-056
Region 1 ITS Pool
2012-112
Region 1 RAMP Project Pool
2016-057
Region 1 RPP Pool
2007-096
Region 1 Surface Treatment Pool
2007-075
Region 1 Traffic Signals Pool
2016-043
RidgeGate Pkwy Widening: Havana St to Lone Tree City Limits
2016-042
US 85: Highlands Ranch Pkwy to Blakeland Dr Capacity Improvements
2001-154
US-85: Cook Ranch Rd to Meadows Pkwy Widening
TIP ID
Project Name
2008-111
FasTracks Eagle P-3 Corridors (Gold and East Line)
2007-050
FasTracks Northwest Rail Corridor
2016-060
I-70/Genesee Bike Path
2012-062
I-70/Kipling: NEPA Study
2016-049
Jeffco Bike Wayfinding Study
2016-006
Multi-use path on the D10: Wadworth Blvd to Zephyr St and Kipling St to Oak St
2016-025
Ralston Rd Reconstruction: Yukon St to Upham St
2007-078
Region 1 Bridge On-System Pool
2008-103
Region 1 FASTER Bridge Enterprise Pool
2008-076
Region 1 FASTER Pool
2007-073
Region 1 Hazard Elimination Pool
2007-074
Region 1 Hot Spot Pool
Douglas
County
Jefferson
198
2016-2021 TIP Projects by County
County
2016-056
Region 1 ITS Pool
2012-112
Region 1 RAMP Project Pool
2012-115
Region 1 Rockfall Mitigation
2016-057
Region 1 RPP Pool
2007-096
Region 1 Surface Treatment Pool
2007-075
Region 1 Traffic Signals Pool
2016-010
RTD L Route Service Enhancement
2016-061
Sheridan Blvd Sidewalks: W. 8th Ave to W. 10th Ave
2008-114
US-36: Boulder to I-25 Managed Lanes/BRT
2016-032
US-6 Shared-Use Path: Colfax Ave to Johnson Rd
2016-020
Wadsworth Blvd Widening: 35th Ave to 48th Ave
2016-037
Washington Ave Complete Streets
TIP ID
Project Name
2016-002
Air Quality Improvements Pool
2012-010
DRCOG Second Commitment to FasTracks Pool
2007-044
FasTracks Projects: DRCOG First Commitment Pool
2016-058
Ozone State Implementation Plan (SIP) Modeling Study
2016-051
Regional BRT Feasibility Study
2012-064
Regional TDM Program: Way to Go
1999-097
Regional Transportation Demand Management (TDM) Program Pool
2016-004
Regional Transportation Operations Pool
2012-108
RTD Capital Improvements: Bus and Facilities Funding
2007-169
RTD Enhancements - ADA/Ped/Bus Shelter
1997-084
RTD Preventive Maintenance: Transit Vehicle Overhaul and Maintenance
2012-068
RTD Regional Workforce Initiative Now (WIN)
2007-089
Station Area Master Plan/Urban Center Studies Pool
TIP ID
Project Name
2016-048
Erie Pkwy Study: SH-287 to I-25
2016-053
Mead School to School Trail Project
2008-081
North I-25: Front Range EIS
2012-116
Region 4 2013 Flood-Related Projects Pool
2008-028
Region 4 Bridge Off-System Pool
2007-133
Region 4 Bridge On-System Pool
2008-077
Region 4 FASTER Pool
2008-106
Region 4 FASTER Transit Pool
2007-094
Region 4 Hazard Elimination Pool
2007-092
Region 4 Hot Spot Pool
2012-109
Region 4 RAMP Project Pool
2007-095
Region 4 Surface Treatment Pool
2007-091
Region 4 Traffic Signals Pool
Regional
County
Weld
199
2016-2021 TIP Projects by County
2016-045
SH-7 BRT Study: Boulder to Brighton
200
2016-2021 TIP Projects by City
City
TIPID
Project Name
2008-111
FasTracks Eagle P-3 Corridors (Gold and East Line)
2016-025
Ralston Rd Reconstruction: Yukon St to Upham St
2016-012
Anschutz Medical Campus Shuttle
2016-046
Arapahoe Rd: I-25 to Parker Rd Next Steps Operations Study
2016-019
Colfax 15L Transit Improvements: I-225 to I-25
2008-111
FasTracks Eagle P-3 Corridors (Gold and East Line)
2007-056
FasTracks I-225 LRT Corridor: Parker Rd to East Corridor Commuter Rail
2016-040
Gun Club Rd and Quincy Ave Operational Improvements
2016-005
Metro Center Station Area Bike/Ped Connector Facility
2016-016
Toll Gate Creek Trail: Chambers Rd to Montview Blvd
2016-017
Westerly Creek Trail to Toll Gate Creek Trail Connector
2016-044
Hwy 79 and Hwy 36 Grade Separation: FA and Design Study
2016-035
30th St and Colorado Ave Bike/Ped Underpass
2016-030
71st St Multimodal Pathway Connection: Winchester to Idylwild Trail
2016-008
Boulder Slough Multiuse Path: 30th St to 3100 Pearl
2016-026
Broadway Reconstruction: Violet Ave to US-36
2016-011
FLEX Route Extension: Boulder to Longmont
2012-109
Region 4 RAMP Project Pool
2016-050
SH 119 BRT NEPA Analysis: Boulder to Longmont
2016-045
SH-7 BRT Study: Boulder to Brighton
2016-007
University of Colorado Boulder East Campus Pedestrian Bridge & Trail Connection
2016-052
Williams Fork Trail Multi-use Path: 63rd St to Twin Lakes Rd
2016-045
SH-7 BRT Study: Boulder to Brighton
2016-014
Broomfield Call-n-Ride
2016-055
I-25: 120th Ave to E-470 Managed Lanes
2016-010
RTD L Route Service Enhancement
2016-045
SH-7 BRT Study: Boulder to Brighton
2008-114
US-36: Boulder to I-25 Managed Lanes/BRT
2016-041
Founders Pkwy and Allen Way Intersection Improvements
2016-027
Meadows Pkwy Reconstruction: US-85 to Meadows Blvd
2001-154
US-85: Cook Ranch Rd to Meadows Pkwy Widening
2016-046
Arapahoe Rd: I-25 to Parker Rd Next Steps Operations Study
City of Arvada
City of Aurora
City of Bennett
City of Boulder
City of Brighton
City of
Broomfield
City of Castle
Rock
City of
Centennial
201
2016-2021 TIP Projects by City
City
TIPID
Project Name
2016-038
High Line Canal Trail Underpass
2007-055
FasTracks North Metro: Denver Union Station to 72nd Ave
2016-047
Industrial Area Transportation Study: I-25 to I-270 to 40th Ave/Smith Rd
2016-039
Route 73 Extension: Smith Rd Station to 60th Ave and Dahlia St
2016-028
16th St Mall Reconstruction: Arapahoe St to Lawrence St
2016-019
Colfax 15L Transit Improvements: I-225 to I-25
2007-053
FasTracks Central Corridor: 30th Ave & Downing St to 38th Ave & Blake St
2008-111
FasTracks Eagle P-3 Corridors (Gold and East Line)
2007-055
FasTracks North Metro: Denver Union Station to 72nd Ave
2007-050
FasTracks Northwest Rail Corridor
2016-038
High Line Canal Trail Underpass
2016-021
I-25 & Broadway Interchange Reconstruction
2007-158
I-25: Santa Fe Dr to Alameda Ave Interchange Improvements (Valley Hwy Phases I and II)
2016-003
I-70 East Reconstruction
2016-024
Iliff Ave Operational Improvements: Parker Rd to Quebec St
2016-047
Industrial Area Transportation Study: I-25 to I-270 to 40th Ave/Smith Rd
2016-022
Martin Luther King Jr. Blvd Extension: Havana St to Peoria St
2016-009
MetroRide Service Expansion: DUS to Civic Center
2016-023
Quebec St Operational Improvements: 13th Ave to 26th Ave
2016-039
Route 73 Extension: Smith Rd Station to 60th Ave and Dahlia St
2016-010
RTD L Route Service Enhancement
2016-062
Sheridan Blvd Sidewalks: Colfax Ave to 17th
1999-052
State of Good Repair
2016-048
Erie Pkwy Study: SH-287 to I-25
2016-010
RTD L Route Service Enhancement
2016-045
SH-7 BRT Study: Boulder to Brighton
2016-032
US-6 Shared-Use Path: Colfax Ave to Johnson Rd
2016-037
Washington Ave Complete Streets
2016-046
Arapahoe Rd: I-25 to Parker Rd Next Steps Operations Study
2016-029
East Lafayette Multimodal Path Connection: Commerce Ct to Lafayette Park-n-Ride
2016-010
RTD L Route Service Enhancement
2016-045
SH-7 BRT Study: Boulder to Brighton
City of Cherry
Hills Village
City of
Commerce City
City of Denver
City of Erie
City of Golden
City of
Greenwood
Village
City of Lafayette
202
2016-2021 TIP Projects by City
City
TIPID
Project Name
2016-006
Multi-use path on the D10: Wadworth Blvd to Zephyr St and Kipling St to Oak St
2016-061
Sheridan Blvd Sidewalks: W. 8th Ave to W. 10th Ave
2007-058
FasTracks Southwest Corridor Extension: Mineral Station to C-470
2001-154
US-85: Cook Ranch Rd to Meadows Pkwy Widening
2016-031
C-470 Multi-use Trail: Grade Separation at Yosemite St
2007-059
FasTracks Southeast Corridor Extension: Lincoln Ave to RidgeGate Pkwy
2016-043
RidgeGate Pkwy Widening: Havana St to Lone Tree City Limits
2016-011
FLEX Route Extension: Boulder to Longmont
2012-109
Region 4 RAMP Project Pool
2016-010
RTD L Route Service Enhancement
2016-015
RTD Route #324 Frequency Improvements
2016-050
SH 119 BRT NEPA Analysis: Boulder to Longmont
2012-051
SH-119: South of Hover Bike/Ped Underpass
2016-053
Mead School to School Trail Project
2012-079
North Metro Rail 112th Ave Corridor Improvements
2016-036
Parker Rd Sidewalk Connection: Plaza Dr to Sulphur Gulch Trail
2016-013
Superior Call-n-Ride
2016-033
Superior Trail: McCaslin BRT Station to Coal Creek
2016-034
Superior Trail: McCaslin BRT to Davidson Mesa Underpass
2016-055
I-25: 120th Ave to E-470 Managed Lanes
2016-045
SH-7 BRT Study: Boulder to Brighton
2007-050
FasTracks Northwest Rail Corridor
2016-055
I-25: 120th Ave to E-470 Managed Lanes
2016-010
RTD L Route Service Enhancement
2008-114
US-36: Boulder to I-25 Managed Lanes/BRT
2008-111
FasTracks Eagle P-3 Corridors (Gold and East Line)
2012-062
I-70/Kipling: NEPA Study
2016-020
Wadsworth Blvd Widening: 35th Ave to 48th Ave
City of
Lakewood
City of Littleton
City of Lone
Tree
City of
Longmont
City of Mead
City of
Northglenn
City of Parker
City of Superior
City of Thornton
City of
Westminster
City of Wheat
Ridge
203
2016-2021 TIP Projects by Project Type
Project Type
TIP ID
Project Name
Air Quality Improvement Projects
Project Type
2016-002
Air Quality Improvements Pool
2016-058
Ozone State Implementation Plan (SIP) Modeling Study
TIP ID
Project Name
Bicycle and Pedestrian Projects (New)
2016-018
23rd Ave. Bike/Ped Path at Fitzsimons Station
2016-035
30th St and Colorado Ave Bike/Ped Underpass
2016-030
71st St Multimodal Pathway Connection: Winchester to Idylwild Trail
2016-054
Boulder County Bus-then-Bike Shelters
2016-008
Boulder Slough Multiuse Path: 30th St to 3100 Pearl
2016-031
C-470 Multi-use Trail: Grade Separation at Yosemite St
2016-029
East Lafayette Multimodal Path Connection: Commerce Ct to Lafayette Park-n-Ride
2016-038
High Line Canal Trail Underpass
2016-060
I-70/Genesee Bike Path
2016-053
Mead School to School Trail Project
2016-005
Metro Center Station Area Bike/Ped Connector Facility
2016-006
Multi-use path on the D10: Wadworth Blvd to Zephyr St and Kipling St to Oak St
2012-079
North Metro Rail 112th Ave Corridor Improvements
2012-080
North Metro Rail 72nd Ave and Colorado Blvd Station Sidewalks
2016-036
Parker Rd Sidewalk Connection: Plaza Dr to Sulphur Gulch Trail
2012-051
SH-119: South of Hover Bike/Ped Underpass
2016-062
Sheridan Blvd Sidewalks: Colfax Ave to 17th
2016-061
Sheridan Blvd Sidewalks: W. 8th Ave to W. 10th Ave
2016-033
Superior Trail: McCaslin BRT Station to Coal Creek
2016-034
Superior Trail: McCaslin BRT to Davidson Mesa Underpass
2016-016
Toll Gate Creek Trail: Chambers Rd to Montview Blvd
2016-007
University of Colorado Boulder East Campus Pedestrian Bridge & Trail Connection
2016-032
US-6 Shared-Use Path: Colfax Ave to Johnson Rd
2016-037
Washington Ave Complete Streets
2016-017
Westerly Creek Trail to Toll Gate Creek Trail Connector
2016-052
Williams Fork Trail Multi-use Path: 63rd St to Twin Lakes Rd
204
2016-2021 TIP Projects by Project Type
Project Type
TIP ID
Project Name
2007-078
Region 1 Bridge On-System Pool
2008-103
Region 1 FASTER Bridge Enterprise Pool
2008-028
Region 4 Bridge Off-System Pool
2007-133
Region 4 Bridge On-System Pool
TIP ID
Project Name
Bridge
Project Type
Bus Service Projects (Expanded)
Project Type
2016-014
Broomfield Call-n-Ride
2016-011
FLEX Route Extension: Boulder to Longmont
2016-009
MetroRide Service Expansion: DUS to Civic Center
2016-039
Route 73 Extension: Smith Rd Station to 60th Ave and Dahlia St
2016-010
RTD L Route Service Enhancement
2016-015
RTD Route #324 Frequency Improvements
TIP ID
Project Name
Bus Service Projects (New)
Project Type
2016-012
Anschutz Medical Campus Shuttle
2016-013
Superior Call-n-Ride
TIP ID
Project Name
2016-056
Region 1 ITS Pool
2012-064
Regional TDM Program: Way to Go
1999-097
Regional Transportation Demand Management (TDM) Program Pool
TIP ID
Project Name
Congestion Management
Project Type
Interchange Reconstruction
Project Type
2007-158
I-25: Santa Fe Dr to Alameda Ave Interchange Improvements (Valley Hwy Phases I and II)
TIP ID
Project Name
2012-112
Region 1 RAMP Project Pool
2016-057
Region 1 RPP Pool
2012-109
Region 4 RAMP Project Pool
Other
205
2016-2021 TIP Projects by Project Type
Project Type
TIP ID
Project Name
2007-053
FasTracks Central Corridor: 30th Ave & Downing St to 38th Ave & Blake St
2008-111
FasTracks Eagle P-3 Corridors (Gold and East Line)
2007-056
FasTracks I-225 LRT Corridor: Parker Rd to East Corridor Commuter Rail
2007-055
FasTracks North Metro: Denver Union Station to 72nd Ave
2007-050
FasTracks Northwest Rail Corridor
2007-059
FasTracks Southeast Corridor Extension: Lincoln Ave to RidgeGate Pkwy
2007-058
FasTracks Southwest Corridor Extension: Mineral Station to C-470
2012-068
RTD Regional Workforce Initiative Now (WIN)
TIP ID
Project Name
2016-059
C-470 Managed Toll Express Lanes: Kipling to I-25
2016-021
I-25 & Broadway Interchange Reconstruction
2016-055
I-25: 120th Ave to E-470 Managed Lanes
2016-022
Martin Luther King Jr. Blvd Extension: Havana St to Peoria St
2016-043
RidgeGate Pkwy Widening: Havana St to Lone Tree City Limits
2016-042
US 85: Highlands Ranch Pkwy to Blakeland Dr Capacity Improvements
2008-114
US-36: Boulder to I-25 Managed Lanes/BRT
2001-154
US-85: Cook Ranch Rd to Meadows Pkwy Widening
2016-020
Wadsworth Blvd Widening: 35th Ave to 48th Ave
TIP ID
Project Name
Rapid Transit
Project Type
Roadway Capacity
Project Type
Roadway Operational Improvements
Project Type
2016-041
Founders Pkwy and Allen Way Intersection Improvements
2016-040
Gun Club Rd and Quincy Ave Operational Improvements
2012-063
I-25 North PEL Action Items
2016-024
Iliff Ave Operational Improvements: Parker Rd to Quebec St
2016-023
Quebec St Operational Improvements: 13th Ave to 26th Ave
TIP ID
Project Name
2016-028
16th St Mall Reconstruction: Arapahoe St to Lawrence St
2016-026
Broadway Reconstruction: Violet Ave to US-36
Roadway Reconstruction
206
2016-2021 TIP Projects by Project Type
Project Type
2016-003
I-70 East Reconstruction
2016-027
Meadows Pkwy Reconstruction: US-85 to Meadows Blvd
2016-025
Ralston Rd Reconstruction: Yukon St to Upham St
2007-096
Region 1 Surface Treatment Pool
2012-116
Region 4 2013 Flood-Related Projects Pool
2007-095
Region 4 Surface Treatment Pool
TIP ID
Project Name
2016-046
Arapahoe Rd: I-25 to Parker Rd Next Steps Operations Study
2016-048
Erie Pkwy Study: SH-287 to I-25
2016-044
Hwy 79 and Hwy 36 Grade Separation: FA and Design Study
2012-062
I-70/Kipling: NEPA Study
2016-047
Industrial Area Transportation Study: I-25 to I-270 to 40th Ave/Smith Rd
2016-049
Jeffco Bike Wayfinding Study
2008-081
North I-25: Front Range EIS
2016-051
Regional BRT Feasibility Study
2016-050
SH 119 BRT NEPA Analysis: Boulder to Longmont
2016-045
SH-7 BRT Study: Boulder to Brighton
TIP ID
Project Name
2008-076
Region 1 FASTER Pool
2007-073
Region 1 Hazard Elimination Pool
2007-074
Region 1 Hot Spot Pool
2012-115
Region 1 Rockfall Mitigation
2007-075
Region 1 Traffic Signals Pool
2008-077
Region 4 FASTER Pool
2007-094
Region 4 Hazard Elimination Pool
2007-092
Region 4 Hot Spot Pool
2007-091
Region 4 Traffic Signals Pool
TIP ID
Project Name
Roadway/Transit Studies
Project Type
Safety
Project Type
Station Area/Urban Center Studies
2007-089
Station Area Master Plan/Urban Center Studies Pool
207
2016-2021 TIP Projects by Project Type
Project Type
TIP ID
Project Name
Transit Operational Improvements
Project Type
2012-010
DRCOG Second Commitment to FasTracks Pool
2007-044
FasTracks Projects: DRCOG First Commitment Pool
2008-106
Region 4 FASTER Transit Pool
1999-052
State of Good Repair
TIP ID
Project Name
Transit Passenger Facilities
Project Type
2016-019
Colfax 15L Transit Improvements: I-225 to I-25
2007-169
RTD Enhancements - ADA/Ped/Bus Shelter
TIP ID
Project Name
2012-108
RTD Capital Improvements: Bus and Facilities Funding
1997-084
RTD Preventive Maintenance: Transit Vehicle Overhaul and Maintenance
Transit Vehicles
208
APPENDIX D
Regionally Significant Projects Not Supported by Federal Funds
209
Locally funded regionally significant projects that are included in the 2015 and 2025
conformity networks (Appendix A of the Conformity document) are listed below for
information purposes. These projects have not been adopted as part of this 2016-2021
TIP, no funding has been assigned, and they are not supported by federal
transportation funds. An FHWA approval is required however for new interchange
projects on the Interstate Highway System.
Locally-Funded Capacity Projects – New Roads
2015-2024
48th Ave.: Picadilly Rd to Powhaton Rd
64th Ave.: Harvest Mile Rd to Powhaton Rd
64th Ave.: Powhaton Rd to Monaghan Rd
160th Ave: Lowell Blvd to Sheridan Pkwy
Canyons Pkwy: Crowfoot Valley Rd to Hess Rd
Central Park Blvd: 47th Ave to 56th Ave
Chambers Rd.: Parker south Town Limit to Crowfoot Valley
Chambers Rd: Crowfoot Valley Rd. to Hess Rd.
Harvest Mile Rd: 6th Ave to I-70
Harvest Mile Rd: I-70 to 56th Ave
Harvest Mile Rd: 56th Ave to 64th Ave
Harvest Mile Rd: Mississippi Ave to Alameda Ave
Jefferson Pkwy Initial Phase: SH-93 to SH-128
Picadilly Rd.: Jewell Ave to 6th Pkwy
Picadilly Rd.: Colfax Ave to I-70
Picadilly Rd.: 56th Ave to 70th Ave./Aurora City Limits
Picadilly Rd.: 70th Ave to 82nd Ave
Quincy Ave: Irving St to Federal Blvd
Stroh Rd: Chambers Rd to Crowfoot Valley Rd
Tower Rd: 6th Ave. to Colfax Ave.
Tower Rd/Buckley Rd: 105th Ave to 118th Ave
210
Locally-Funded Capacity Projects – Roadway Widening
2015-2024
6th Ave.: 6th Pkwy to Harvest Mile Rd
6th Ave/SH30: Tower Rd to 6th Pkwy
6th Ave: Airport Blvd to Tower Rd
6th Pkwy: E-470 to Gun Club Rd
17th Ave: Alpine St to Ute Creek Dr
56th Ave.: E-470 to Imboden Rd
56th Ave.: Pena Blvd to Tower Rd
56th Ave.: Dunkirk St. to Himalaya St.
56th Ave.: Himalaya Rd to Picadilly Rd
56th Ave.: Picadilly Rd to E-470
58th Ave.: Washington St to York St
64th Ave.: Denver/Aurora City Limit to Himalaya
64th Ave.: Himalaya Rd to Harvest Mile Rd
64th Ave.: Terry St to Kendrick Dr
64th Ave.: Tower Rd to Denver/Aurora City Limits
104th Ave.: US-85 to SH-2
144th Ave.: Washington St. to York St.
144th Ave.: York St to Colorado Blvd
144th Ave: US 287 to Zuni St.
Alameda Pkwy: C-470 to Bear Creek Blvd
Arapahoe Rd: Waco St to Himalaya St
Broadway - Exposition Ave to Arizona Ave.
Broncos Pkwy: Jordan Rd to Parker Rd
Buckley Rd.: 118th Ave to Cameron Dr
Buckley Rd.: 136th Ave to Bromley Ln
Chambers Rd: Hess Rd. to Mainstreet
Chambers Rd: Mainstreet to Lincoln Ave
Crowfoot Valley Rd.: Chambers Rd to Stroh Rd
E. Bromley Lane: SH-85 to Sable Blvd
E. Bromley Lane: Tower Rd to I-76
Easter Ave: Havana St to Peoria St
Green Valley Ranch Blvd: Chambers Rd to Telluride St.
Green Valley Ranch Blvd: Telluride St. to Tower Rd.
Green Valley Ranch Blvd: Pena Blvd to Chambers Rd
Gun Club Rd: 1.5 miles s/o Quincy Ave to Quincy Ave.
Hampden Ave: Picadilly Rd to Gun Club Rd
Harvest Rd: Alameda Ave to 6th Ave
Hess Rd.: Motsenbocker Rd to Nate Dr.
Huron St: 150th Ave to 160th Ave
Huron St: 160th Ave to SH-7
Jewell Ave: Himalaya Rd to E-470
Jewell Ave: E-470 to Gun Club Rd
Jewell Ave: Gun Club Rd to Harvest Mile Rd
Jordan Rd.: Bradbury Ranch Rd to Hess Rd
Leon A. Wurl Pkwy: US-287 to 119th St.
211
Locally-Funded Capacity Projects – Roadway Widening
Lincoln Ave: Keystone Blvd to Parker Rd
Lincoln Ave: Peoria St to 1st Ave
Nelson Rd: 75th St to Affolter Dr. Rd
Pace St: 5th Ave to SH-66
Pecos St.: 52nd Ave. to I-76
Pena Blvd: Jackson Gap St to DIA Terminal
Peoria St: E-470 to 0.75 mile south of Lincoln Ave.
Picadilly Rd.: 6th Pkwy to Colfax Ave
Picadilly Rd.: Smith Rd. to 48th Ave
Picadilly Rd.: 48th Ave to 56th Ave
Picadilly Rd.: I-70 to Smith Rd (realignment)
Plum Creek Pkwy: Gilbert St to Ridge Rd
Quebec St: 120th Ave to 128th Ave
Quebec St: 132nd Ave to 160th Ave (SH-7)
Quincy Ave.: Kipling St to Carr St
Quincy Ave.: Plains Pkwy to Gun Club Rd
Quincy Ave.: Simms St. to Kipling Pkwy
Ridge Rd: Plum Creek Pkwy to SH-86
SH-30/Gun Club Rd: Mississippi Ave to Yale Ave
SH-7: Boulder County Line to Sheridan Pkwy
SH-7: Sheridan Pkwy to I-25
Sheridan Pkwy: Lowell Blvd to NW Pkwy
Sheridan Pkwy: Northwest Pkwy to SH 7
Coachline Rd: Wolfensberger Rd to I-25
Stroh Rd: Crowfoot Valley to J. Morgan Blvd
Tower Rd: 38th/40th Ave. to Green Valley Ranch Blvd.
Tower Rd: 56th Ave to Pena Blvd
Tower Rd: Colfax Ave to Smith Rd
Tower Rd: Green Valley Ranch Blvd to 56th Ave
Tower Rd: Pena Blvd to 105th Ave
Washington St.: 144th Ave to 152nd Ave
Washington St.: Elk Pl to 52nd Ave
Washington St.-Phase IV: 52nd Ave. to 58th Ave.
Washington St: 152nd Ave to 160th Ave
York St.: 160th Ave (SH-7) to 168th Ave
York St: E-470 to SH-7
212
Locally-Funded Interchanges
2015-2024
E-470: 48th Ave., New Interchange
E-470: Potomac New Interchange
Jefferson Pkwy: SH-72 New Interchange
Jefferson Pkwy: Candelas Pkwy New Interchange
Jefferson Pkwy: Indiana St. New Interchange
I-25: Castlegate Dr., New Interchange
I-70: 32nd Ave Interchange Reconstruction
I-70: Harvest Rd. New Interchange
I-70: Picadilly Rd New Interchange
I-76: Bridge St. New Interchange
SH-58: Cabela Drive, New Interchange
US-86: North Meadows Dr., New Interchange
213
214
APPENDIX E
Waiting List
215
216
Waiting List Protocol
To be determined at a later date.
217
Table 4. Eligible Projects for Waiting List(s) for the 2016-2021 TIP
(To be completed at a later date)
Wait
Sponsor
List
Order*
COG-ID
Project Title
Project Type
218
Requested
Federal $
($000)
Local $
($000)
APPENDIX F
Governor’s Approval
219
220
221
DENVER REGIONAL COUNCIL OF GOVERNMENTS
We make life better!
2016-2021 Transportation Improvement Program
Denver Regional Council of Governments
1290 Broadway, Suite 700
Denver, CO 80203-5606
www.drcog.org - 303-455-1000