The Cost Benefit of Solar for Small and Medium Enterprises Dr Tadhg S. O’Donovan Overview Scottish Institute for Solar Energy Research (SISER) Assessing the economic viability of Renewable Energy The Feed-In Tariff (FIT) and the Renewable Heat Incentive Thermal Storage Funding Opportunities on the Horizon (2020) Levelised Cost of Energy (LCOE) Techno-Economic Modelling of Energy Conversion Devices Total Lifecycle Cost (Currency) LCOE Total Lifetime Energy Production (Whrs) Levelised Cost of Energy (LCOE) Expanding the LCOE equation in basic categories gives: 𝐿𝐶𝑂𝐸 = 𝐼𝑐 + 𝑁 𝑛=1(𝑂 + 𝑀)𝑛 + 𝑁 𝑛=1(𝐸𝑝 )𝑛 Where: N = The life of the project n = Year n 𝐼𝑐 = Initial Costs 𝑂 + 𝑀 = Operation and Maintenance Costs F = Financing 𝐸𝑝 = Energy Produced 𝑁 𝑛=1(𝐹)𝑛 Initial Costs Important Factors to consider: 𝐿𝐶𝑂𝐸 = System Components Cost Installation Costs Labour Cost Overheads Permitting and Commissioning Land Cost Site Preparation Connection and Transmission Fees Storage Costs 𝐼𝑐 + 𝑁 𝑛=1(𝑂 + 𝑀)𝑛 + 𝑁 𝑛=1(𝐸𝑝 )𝑛 𝑁 𝑛=1(𝐹)𝑛 Operation and Maintenance Cost Important Factors to consider: Field repairs Part Cleaning Failure Rates Storage Costs Running Costs Fuel Costs 𝐿𝐶𝑂𝐸 = 𝐼𝑐 + 𝑁 𝑛=1(𝑂 + 𝑀)𝑛 + 𝑁 𝑛=1(𝐸𝑝 )𝑛 𝑁 𝑛=1(𝐹)𝑛 Operation and Maintenance Costs are often taken as percentage of the Initial Cost and treated as an assumption. Financing Important costs to consider: Insurance Loan Payments Taxes Important benefits to consider: • Depreciation • Investment Tax credit • Feed in tariffs • Government Incentives 𝐿𝐶𝑂𝐸 = 𝐼𝑐 + 𝑁 𝑛=1(𝑂 + 𝑀)𝑛 + 𝑁 𝑛=1(𝐸𝑝 )𝑛 𝑁 𝑛=1(𝐹)𝑛 A key consideration in LCOE calculations is the discount rate. Energy Produced Important Factors to consider: Rated Output Capacity Factor Geographical Location Degradation Rate Failure rates Other losses 𝐿𝐶𝑂𝐸 = 𝐼𝑐 + 𝑁 𝑛=1(𝑂 + 𝑀)𝑛 + 𝑁 𝑛=1(𝐸𝑝 )𝑛 𝑁 𝑛=1(𝐹)𝑛 Decommissioning The cost to decommission a project is rarely considered in LCOE calculations. The costs can be high depending on the project. The amount that can be salvaged at the end of the project (land sale etc) should also be considered. LCOE A more realistic model for LCOE calculation would be: 𝐿𝐶𝑂𝐸 = (𝐼𝑐 − 𝐿𝑜 ) + 𝑂+𝑀 𝑛 𝐿𝑃 𝑁 + 𝑛=1 1 + 𝑟 𝑛 + + 𝑟)𝑛 𝑛 𝑁 𝐼𝑛𝑖𝑡𝑎𝑙 𝑂𝑢𝑡𝑝𝑢𝑡 × (1 − 𝑆𝐷𝑅) 𝑛=1 (1 + 𝑟)𝑛 𝑁 𝑛=1 (1 Where: Lo= Loan Amount LP = Loan Payments (D-S) = Decommissioning cost – Salvage potential r = Discount rate SDR= System degradation rate (𝐷 − 𝑆) 𝑁 𝑛=1 (1 + 𝑟)𝑁 To install Photovoltaic Panels...? A case study for a simple home installation of PV panels: Located in the East of Edinburgh, Polysun software was used to simulate energy output for the TMY (Typical Metrological Year). 8 Sharp ND-R250A5 0.25 kWp panels were used with quotes from local installation company EvoEnergy. Equation Inputs Section Value Initial Cost £4262 Decommissioning £997.50 Operation and Maintenance £582 (every replacement) Energy Produced 1760 kWh System Degradation Rate 0.5% Discount rate 3.5% Project Life 25 years Losses 7% Results LCOEWithout With Loan LCOE Loan £3.00 £0.45 (£/kWh) LCOE(£/kWh) LCOE £0.40 £2.50 £0.35 £0.30 £2.00 £0.25 £1.50 £0.20 LCOE LCOE £0.15 £1.00 £0.10 £0.50 £0.05 £0.00 £0.00 Grid Parity Grid Parity 0 0 5 5 10 10 15 15 Year Year 20 20 25 25 30 30 The loan considered is a 10 year loan with an interest rate of 5.7% for the whole Initial Cost amount Sensitivity Analysis-Assumptions System Degradation LCOE With Loan Rate Discount rate Operation and Maintenance £0.50 £0.60 £0.45 £0.45 £0.40 £0.50 £0.40 £0.35 LCOE (£/kWh) LCOE LCOE(£/kWh) (£/kWh) £0.35 £0.30 £0.40 0.25% 2% 0% 0.50% LCOE 3.50% 0.50% 0.75% 4% 1% Grid Parity 1% 6% 1.50% 1.25% 8% 2% 1.50% £0.30 £0.25 £0.30 £0.25 £0.20 £0.20 £0.15 £0.20 £0.15 £0.10 £0.10 £0.10 £0.05 £0.05 £0.00 £0.05 £0.00 0 £0.00 £0.00 0 00 5 5 55 10 10 10 10 15 15 Year 15 15 Year Year Year 20 20 20 20 25 25 25 25 30 30 30 30 A 2% in This The LCOE is achange major will topic the discount rate of increase debate by within 5% the roughly industry. forwill each 0.5%lead to a 10% change in increment LCOE value. However the LCOE will only change by 2% each increment Sensitivity Analysis-Loan Loan Year £0.70 £0.60 LCOE (£/kWh) £0.50 5 yr 10 yr £0.40 There is a 11% rise in the LCOE value for each 5 year increment 15yr £0.30 20 yr £0.20 25 yr £0.10 £0.00 0 5 10 15 Year 20 25 30 A 1% increase in the interest rate will lead to a 4% increase in the LCOE value Sensitivity Analysis-Energy Produced Tilt Angle 1800 Energy Produced (kWh) £0.50 £0.45 1750 £0.40 1700 LCOE (£/kWh) Energy Prodcued (kWh) 1800 Orientation Losses 1650 1600 1550 0 £0.35 £0.30 £0.25 £0.20 £0.15 £0.10 20 £0.05 40 60 80 This means that every time the energy produced 7% 1600 drops by 20 kWh 9% 1550 12% the LCOE will -20 0 20 40 60 80 15% drop by 1% Orientation (0) 3% 1650 6% -60 -40 East £0.00 5 1700 0% -80 Tilt Angle (0) 0 1750 10 The tilt angle makes little difference to the LCOE as long as it is with the 200 to 600 region 15 Year 20 Each 3% increment changes the LCOE by 3.2% West 25 30 The orientation will have little impact to the LCOE if the system is 400 East or West of South Sensitivity Analysis-Project Inverter Life Initial Cost £0.50 £0.60 £0.45 £0.50 £0.40 £3500 LCOE (£/kWh) LCOE (£/kWh) £0.35 £0.40 £0.30 £4000 5 year £4262 10 year £4500 15 year £0.30 £0.25 £0.20 £0.20 £0.15 £5000 20 year 25 year £5500 £0.10 £0.10 £0.05 £0.00 £0.00 0 0 5 5 10 10 15 15 Year Year 20 20 25 25 30 As expected, the The life of thethe solar Changing Initial cost can make panel can also Inverter Life a largea difference on make down large to 5 years the LCOE, around difference will each increase the 12% increment by outlives 12% If LCOE the panel the 25 year However warranty by 5 increasing years then the LCOE will life inverter decrease 7.5% will onlyby lead to a 5% drop 30 Input Worst Case Best Case Initial Cost £4262 £4262 Decommissioning £997.50 £997.50 £0.70 Inverter Life 10 years 15 years £0.60 Inverter Cost £582 £582 £0.50 Operation and Maintenance 1% 0% System Degradation Rate 0.67% 0.25% Other Losses 12% 2% Discount Rate 3.5% 3.5% Panel Life 25 years 35 years Loan Year 10 years 5 years Loan Rate 8% 4% Findings LCOE (£/kWh) LCOE £0.40 Best Case Worst Case Grid Parity £0.30 £0.20 £0.10 £0.00 0 5 10 15 20 Year 25 30 35 40 Feed-In Tariff Government Incentive for Micro-generation (decreasing) Extra Incentive to Sell to Grid (increasing) Dates Tariff p/kWh Tariff (p/kWh) Scale Type / Rate 1 Apr 2010 - 31 Mar 2011 3 > 1/10/14 1 Apr 2011 ≤4 kW- 31 Mar 2012 Higher rate 1 Apr 2012 ≤4 kW- 31 July 2012 Medium rate 3.1 3.2 14.38 1 Aug - 31 Mar 2013 >42012 - 10kW Higher rate 1 Apr>42013 - 31 Mar 2014 - 10kW Medium rate 1 Apr 2014 - 31 Mar 2015 >10 - 50kW Higher rate 4.5 4.64 4.77 13.03 12.94 11.73 12.13 >10 - 50kW Medium rate 10.92 >50 - 150kW Higher rate 10.34 >50 - 150kW Medium rate 9.31 >150 - 250kW Higher rate 9.81 >150 - 250kW Medium rate 8.9 ≤250kW Lower rate 6.38 >250kW - 5MW ≤5MW 6.38 Standalone 6.38 Thermal Energy Storage Renewable Heat Incentive Case Study Conclusions The length of loan, discount rate and initial cost have a large effect on the LCOE value for a solar PV system. The much debated topic of system degradation rate does not greatly effect the LCOE value. If the system ran as well as it could then it would reach close to grid parity. Overall Conclusion Using the standardised equation with the factors discusses, a reasonable LCOE value can be calculated. The assumptions used in the equation can vary location to location, however there is a range they should be inside. All assumptions must be clearly stated on any LCOE value in order to make a fair comparison between projects.
© Copyright 2026 Paperzz