ICC STANDARDS - PUBLIC COMMENT FORM
PLEASE SEE INSTRUCTIONS (SUBMITTAL RULES OF PROCEDURES). ALL SUBMITTALS MUST BE IN COMPLIANCE WITH THESE PROCEDURES.
CLOSING DATE: All Comments Must Be Received by the Announced Closing Date
1)
Indicate the format in which you would like to receive your Public Comments Report (PCR):
Paper
* CD
X
*Download
(*Note: A paper copy will not be sent to you if you have chosen a CD or to download the PCR from the ICC Web Site.)
2)
PLEASE TYPE OR PRINT CLEARLY: FORMS WILL BE RETURNED if they contain unreadable information.
Name:
Oscar Scott, Chief Compliance Officer
Date:
Jurisdiction/Company:
National Storm Shelter Association
Submitted on Behalf of:
National Storm Shelter Association
Address:
Box 43155
City:
Lubbock
Phone:
806-679-9163
e-mail:
[email protected]
State:
TX
Zip +4:
Ext:
8/26/13
79409-3155
Fax:
Signature on File
3)
*Signature:
* I hereby grant and assign to the ICC all rights in copyright I may have in any authorship contributions in any proposal or comment I make to the ICC. I
understand that I will have no rights in any ICC publications that use such contributions in the form submitted by me or another similar form and certify
that such contributions are not protected by the copyright of any other person or entity.
IS-STM
4)
Indicate appropriate ICC Standard associated with this Public Proposal – Please use Acronym:
(See bottom of this form or the instructions for list of Names and Acronyms for the ICC Standards)
5)
Indicate the Standard Proposal Number that is being addressed by this Public Comment (if applicable): IS-STM10- 11/12
6)
Revision to:
7)
COMMENT
X
X
Section 106.3.1
Table
Figure
Revise as follows (check BOX and state proposed change):
Revise as follows:
Add new text as follows
Delete and substitute as follows:
Delete without Substitution:
Show the proposed NEW or REVISED or DELETED TEXT in legislative format: Line through text to be deleted. Underline text to be added.
Proposed Revisions to ICC Section 106.3 are as follows:
106.3.1 Special Cases. Special Inspectors shall be provided for proposed work comprised of :
1. Construction materials and systems that are alternatives to traditional materials and systems prescribed by the
applicable code
2. Unusual design and construction applications
3. Anchors post-installed in hardened concrete for shelter anchorage in accordance with Section 106.3.1.
106.3.1 Special Inspections to Verify Anchorage Installation. Special inspection to verify the anchor installation, capacity and
foundation adequacy according to the anchor manufacturer and shelter anchorage and foundation requirements provided in
the shelter design information required in Section 107.25.1, qualify assurance plans required in Section 107.3.2, and
foundation anchorage criteria required in Section 309.
ADD to end of 106.3.1
As an alternative to this special inspection, the AHJ (Authority Having Jurisdiction) may accept a process from a qualified
producer, design professional and a third party reviewer which can assure proper installation.
X
8)
COMMENT Continued (Attach additional sheets as necessary)
SUPPORTING INFORMATION (State purpose and reason, and provide substantiation to support proposed change):
Section 106.3.1 of ICC/NSSA Standard for the Design and Construction of Storm Shelters (ICC 500-213 Edition) as proposed
would add a costly inspection. The National Storm Shelter Association (NSSA) has established a “saferoom qualified status”
which requires a design engineer of record to design the shelter/saferoom, work with the shelter manufacturer to develop a
Quality Assurance Plan (QAP) and a very comprehensive installation checklist that would include all scenarios to ensure a
ICC Standards Public Comment e-form
Revised: 02-13
quality installation. The shelter/saferoom design, QAP and installation checklist are then to be submitted to an independent
approved third party reviewer. The third party reviewer mush have submitted their qualifications and experience to the NSSA
for approval. The third party reviewer is not to be part of the same firm as the design engineer of record.
NSSA believes the manufacturer can train their personnel to comprehend the entire installation checklist. The installer is by
far the person best able to perform an informed sign off to assure the anchorage and other requirements are met.
Many shelters/saferooms go into remote areas and special inspections are difficult to obtain and extremely costly. Adding
the cost of a special inspection could easily prevent hundreds from purchasing/installing a shelter/saferoom.
X
SUPPORTING INFORMATION Continued (Attach additional sheets as necessary)
PLEASE USE SEPARATE FORM FOR EACH COMMENT
SUBMITTAL AS A DOCUMENT ATTACHMENT TO AN E-MAIL IS PREFERRED
e-mail: [email protected] Phone: (708) 799-2300 x4317 Fax:
(708) 799-0320
If E-MAIL is not available, mail form and disk to: International Code Council, 4051 W. Flossmoor Rd. Country Club Hills, IL 60478
Name of ICC Standard: The following acronyms should be used when designating the name of a
Standard.
Acronym ICC Standard Name
IS-BLE
IS-RHW
IS-IEDC
IS-LOG
IS-MAN
IS-STM
A117.1
Standard on Bleachers, Folding and Telescopic Seating, and Grandstands
Standard for Residential Construction in High Wind Regions
Landscape Irrigation Sprinkler and Emitter Standard
Standard on Design, Construction and Performance of Log Structures
Manufactured Housing Construction & Safety Standards
Standard on Design, Construction and Performance of Storm Shelters
Standard on Accessible and Usable Buildings and Facilities