5-Year Capital Improvements Water Supply, Treatment and Distribution • Water Treatment Plant #1 – 2013 - 2014 Wells and Wellfields – 2015 - 2017 Electrical Improvements – Wells and Wellfields $ $ $ 500,000 500,000 750,000 • Water Treatment Plant #2 – 2013 - 2014 Zero Liquid Discharge – Wells and Wellfields – 2015 – 2017 Wells and Wellfields $10,000,000 $ 1,500,000 $ 3,000,000 • Water Treatment Plant #3 – 2013 - 2014 Wells and Wellfields – Color/Iron Reduction – 2015 - 2017 Wells and Wellfields – Membrane Replacement – Plant Expansion Design $ 1,600,000 $ 625,000 $ 1,850,000 $ 275,000 $ 1,500,000 5-Year Capital Improvements Water Supply, Treatment and Distribution • Water Distribution – 2013 - 2014 Palm Coast Pkwy. 6-laning related – Pine Lakes Pkwy. Related – Distribution System Improvements – 2015 - 2017 Citation/Old Kings/S.R. 100 loop – Old Kings Road phase 2 Related/misc. – Distribution System Improvements $ 1,000,000 $ 200,000 $ 150,000 $ 900,000 $ 150,000 $ 225,000 • General Plant R & R – 2013 - 2014 Renewal and Replacements – Miscellaneous Small Capital Projects – 2015 – 2017 Renewal and Replacements – Miscellaneous Small Capital Projects $ 1,000,000 $ 244,000 $ 1,500,000 $ 151,000 5-Year Capital Improvements Wastewater Collection, Treatment and Disposal • Wastewater Treatment Plant #1 – 2013 - 2014 Misc. Improvements – Rapid Infiltration Basins Slope Rehab – 2015 - 2017 Advanced Waste Treatment – Clarifiers 7 & 8 Rehab. $ 350,000 $ 230,000 $ 7,200,000 $ 500,000 • Wastewater Treatment Plant #2 – 2013 - 2014 – 2015 – 2017 Plant Construction incl. Discharge $ -0$ 20,540,000 • Reclaimed Water – 2013 - 2014 Holland Park – 2015 – 2017 Matanzas Woods Pkwy. – Seminole Woods Pkwy. Start Project – Old Kings Road Phase 2 Design $ 100,000 $ 2,300,000 $ 250,000 $ 100,000 5-Year Capital Improvements Wastewater Collection, Treatment and Disposal • Pump Stations – 2013 - 2014 Pump Station 4-2 Upgrade – Misc. Pump Station Upgrades – Generators – Odor Control Systems – Beachside Sewer – 2015 - 2017 Matanzas Woods Master Pump Station – Old Kings Road Master Pump Station – Misc. Pump Station Upgrades – Generators – Odor Control Systems $ 500,000 $ 150,000 $ 60,000 $ 100,000 $ 2,500,000 $ 2,000,000 $ 1,250,000 $ 225,000 $ 90,000 $ 150,000 • Force Mains – 2013 - 2014 – 2015 – 2017 Force Mains – Old Kings Road Phase 2 -0$ 1,250,000 5-Year Capital Improvements Wastewater Collection, Treatment and Disposal • Collection System – 2013 - 2014 PEP System Upgrades and Tanks – 2015 – 2017 PEP System Upgrades and Tanks $ 750,000 $1,200,000 • General Plant R & R – 2013 - 2014 General Plant Repair and Rehabilitation – Miscellaneous Small Capital Projects – 2015 – 2017 General Plant Repair and Rehabilitation – Miscellaneous Small Capital Projects $1,000,000 $ 24,000 $1,500,000 $ 21,000
© Copyright 2025 Paperzz