Page 1/2 Oil Platforms for the Offshore Oil Field “Schwedeneck-See”, Baltic Sea, Germany OFFSHORE WIND Schwedeneck-See, Platform A The first two German offshore oil platforms were erected in the oil field “SchwedeneckSee” within the bight of Kiel in 1983. These two structures are reinforced concrete constructions, having been built in a dry dock and afterwards floated to their working positions. Client: Consortium Deutsche Texaco Aktiengesellschaft/ Wintershall AG, Germany The reinforced concrete constructions were laid out for the specific hydrographical conditions of this Baltic Sea area. The local water depth at position of platform A is 25 m and 17 m at platform B. Construction Costs: about 300 mill. DM Below inner and outer wall a sheet pile wall is bound into the base slab. These sheet piles penetrate the ground while lowering the platform into the seabed and transfer the horizontal forces into deeper bearing soil layers. Foundation joints are closed by high pressure injections. Services: Site supervision Period: 1983 Only 8 months lay between site mobilisation and the sinking of the platform at its final position at the Schwedeneck-See. The construction is laid out for a gentle removal when its task will be finished. For the construction, the sea transport and the sinking of rig A, the following working sequence was applied: • • • • dry dock 8a at HDW in Kiel construction of reinforced concrete structure up to the wall tops floating completion within the harbour of Kiel and partially ballasting up to a draught of 12 m sea transport to the Eckernförder Bay for further ballasting sea transport to the final sinking location Project-No. 1935 Sellhorn Ingenieurgesellschaft mbH, Teilfeld 5, 20459 Hamburg, Germany, Phone+49 (0)40 36 12 01-0, Fax +49 (0)40 36 12 01-28 [email protected], www.sellhorn-hamburg.de LKP 20110930 Page 2/2 Parallel to these activities the outfitting of pipeline systems and steel construction elements was carried out. Because of the limited construction period it was not acceptable to allow for any leeway. Therefore it was necessary to clarify any potential design conflicts between the involved parties on site and immediately. Aside from quality control of concrete works intensive checks on steel construction elements, pipeline systems and especially on welding works and corrosion protection systems were carried out. Because of the remarkable stress of the structure in the offshore position the quality of welded joints and the corrosion protection system was of decisive importance for stability, lifetime and maintenance as well as for tightness and reliability of pipeline systems. Of further priority was the check of structure geometry, because the floating stability was depending from exact load distribution. After flooding the dry dock nearly 300 m long joints at the bottom proved to be as tight as concrete walls, base and pipe breakthroughs. Site supervision was performed by up to seven engineers at the same time being on daily duty for 24 hours, seven days a week. All correspondence and supervision was held in English. Project-No. 1935 Sellhorn Ingenieurgesellschaft mbH, Teilfeld 5, 20459 Hamburg, Germany, Phone+49 (0)40 36 12 01-0, Fax +49 (0)40 36 12 01-28 [email protected], www.sellhorn-hamburg.de LKP 20110930 OFFSHORE WIND
© Copyright 2025 Paperzz