Management Accounting 2nd Year Examination Additional Sample Questions and Solutions - Variance Additional Question 1 The following information relates to product X which is produced by STADIUM Ltd. during December: Variances Materials price Materials usage Labour rate Labour efficiency Actual data Materials costs Labour costs Production volume €/£ 28,500 10,500 24,980 40,000 Favourable Adverse Adverse Favourable € / £600,000 for 40,000kg € / £784,000 for 55,000 hrs. 10,000 units Actual and standard production volumes are the same. Required: (a) Prepare a standard cost sheet for Product Z. 10 Marks (b) Outline two possible reasons for each of the material price and labour efficiency variances. 4 Marks (c) Briefly list and explain three benefits and three limitations of a standard costing system. 6 Marks Total: 20 Marks Solution to Additional Question 1 Standard cost per kg of material Material price variance 40,000kg should have cost (40,000 x C) 40,000kg did cost Variance €/£ 40,000C 600,000 28,500 40,000kg should have cost 40,000kg did cost Variance € 628,500 600,000 28,500 F (Bal. Fig) F Therefore 40,000 x Cost = € / £628,500 Standard cost per kg of material = € / £628,500/40,000 = € / £15.7125 (round off to €15.71) Standard kg of material used per unit of product Material usage variance Kg 10,000K 40,000 Variance in kg 10,000 units should have used (10,000 x kg) 10,000 units did use x standard cost per kg € / £15.71 Variance € / £10,500 A Therefore the variance in kg is € /£10,500/€ /£15.71 = 668kg Kg 39,332 40,000 668 10,000 units should have used (10,000 x kg) 10,000 units did use x standard cost per kg € / £15.71 Variance € /£10,500 Therefore 10,000 x K = 39,332 Standard kg per unit of product is 39,332/10,000 = 3.93Kg 3 (Bal. Fig.) A A Standard cost per labour hour Labour rate variance 55,000 hours should have cost (55,000 x C) 55,000 hours did cost Variance €/£ 55,000C 784,000 24,980 55,000 hours should have cost (55,000 x C) 55,000 hours did cost Variance €/£ 759,020 784,000 24,980 A (Bal. Fig.) A Therefore 55,000 x Cost = € /£759,020 Standard cost per labour hour = € /£759,020/55,000 = € /£13.80 Labour hours per unit of product Labour efficiency variance Hrs. 10,000H 55,000 Variance in hrs 10,000 units should have used (10,000 x hrs.) 10,000 units did use x standard cost per hr. € / £13.80 Variance €40,000 F Therefore the variance in hours is € /£40,000/€ /£13.80 = 2,898 hrs. Hrs. 57,898 55,000 2,898 10,000 units should have used (10,000 x hrs.) 10,000 units did use x standard cost per hr € /£13.80 Variance €40,000 Therefore 10,000 x hrs = 57,898 Standard hours per unit of product is 57,898/10,000 = 5.79hrs 4 F Standard cost card per unit Materials cost Labour cost 3.93kg @ € / £ 15.71 per kg 5.79 hours @ € / £ 13.80 per hour Total cost €/£ 61.74 79.90 141.64 5 Additional Question 2 The standard cost card (per unit) for the Visual, one of the products produced by THOMOND Ltd is as follows. € /£ 192 144 168 504 Direct material 32kg @ € / £6 per kg Direct labour 12 hrs. @ € / £12 per hr. Fixed production overhead 12 hrs. @ € / £14 per hr. During August 2013 Thomond Ltd reported the following variances for the Visual Material price Material usage Labour rate Labour efficiency Fixed production overhead expenditure Fixed production overhead volume 37,680 favourable 960 adverse 21,196 adverse 16,956 favourable 20,000 favourable 25,200 favourable Actual data Fixed production overhead Direct labour cost Direct material cost per kg 400,000 342,640 9 Required: a) Calculate the following i. ii. iii. iv. v. Budgeted output Actual hours worked Actual labour rate per hour Actual output Actual number of kg of materials used 12 Marks b) Outline the key factors that should be considered before deciding whether or not a variance should be investigated. 4 Marks c) Outline two possible reasons for each of the fixed production overhead expenditure and fixed production overhead volume variances calculated. 4 Marks Total: 20 Marks 6 Solution to Additional Question 2 i. Budgeted output Fixed overhead expenditure variance Budgeted fixed overhead expenditure (€ /£168 x budgeted output) Actual fixed overhead expenditure Variance € /£ 168 x BO 400,000 20,000 €/£ 420,000 400,000 20,000 Budgeted fixed overhead expenditure (€ /£168 x units) Actual fixed overhead expenditure Variance F (Bal. Fig) F Therefore € / £ 168 x BO = € / £420,000 Budgeted output = € / £420,000/€ / £168 = 2,500 units ii. Actual labour hours worked Labour rate variance Actual hours should have cost (AH x € / £ 12) Actual hours did cost €/£ 12 AH 342,640 Variance €21,196 Actual hours should have cost (AH x € / £ 12) Actual hours did cost €/£ 321,444 342,640 Variance €21,196 Therefore actual hours € /£ 321,444/12 = 26,787 hours iii. Actual labour rate per hour Actual cost € / £342,640/26,787 = € / £12.8 7 A A iv. Actual output Labour efficiency variance €/£ 12AO 26,787 Variance in hours F 16,956 F Actual output should have taken (12 x AO) Actual output did take Variance €/£ 28,200 26,787 1,413 F x standard rate per hour € / £12 16,956 F 2,500 2,350 150 F 25,200 F Actual outputs should have taken (12 x AO) Actual output did take Variance x standard rate per hour € / £12 Therefore the variance in hours is € /£16,956/€ /£12 = 1,413 hrs. Therefore actual output € / £28,200/12 = 2,350 units or Production overhead volume variance Budgeted output Actual output Variance x standard rate per unit € / £168 v. Actual kg of material used Material usage variance Kg 75,200 ______ Variance in kg 2,350 units should have used (2,350 x 32kg) 2,350 units did use x standard cost per kg € / £6 Variance € / £960 Therefore the variance in kg is € /£960/€ /£6 = 160kg 8 A Kg 75,200 75,360 2,350 units should have used (2,350 x 32kg) 2,350 units did use 160 € / £960 x standard cost per kg € / £6 Variance Therefore actual kg of material used is 75,360kg. 9 (Bal. Fig) A A
© Copyright 2026 Paperzz