HSE ALERT ☒ Initial issuance Title: Region/ Project: HSE Alert Category: (Synergi 1.0 Incident Categorisation) ☐ N°05/2016 Final Issuance Reversal of J-Tube section Synergi Case No: 440096 Region A (Subsea) – Moho Nord Project Incident Date: 17/03/2016 SIF Near Miss Alert Issue Date: 22/03/2016 DESCRIPTION OF THE INCIDENT J-tube sections have been locally constructed on a Fabrication Yard (Ponticelli) located a few kilometers from ILOGS quay were the mobilization of the Orelia (Technip Construction vessel in charge of the setup of the J-Tube) was taking place. J-Tube sections were transferred on 2 flat trailers from the Fabrication yard to the ILOGS quay. As the construction vessel was not ready to reception them, they have been temporarily stored alongside the quay on top of two foam blocks to comply with the vessel storage scheme in the afternoon of the 16th March. The 17th march at around 14.30 it was discovered that one of the J-tube assemblies (2T) had overturned on the quayside. 2.0 SUMMARY OF FINDINGS & PICTURES Accident scene: TECHNIP Group. This document and the information it contains are property of TECHNIP France SAS. It shall not be used for any purpose other than those for which it was supplied. Copyright TECHNIP France – All rights reserved. CR 08.E – Rev.0 – Sept. 2015 HSE ALERT ☒ Initial issuance Title: Region/ Project: HSE Alert Category: (Synergi Incident Categorisation) ☐ N°05/2016 Final Issuance Reversal of J-Tube section Synergi Case No: 440096 Region A (Subsea) – Moho Nord Project Incident Date: 17/03/2016 SIF Near Miss Alert Issue Date: 22/03/2016 Findings: Procedure to transfer the J-Tube from the fabrication yard to ILOGS quay on flat trailer on two foam blocks. Foreman in charge of the loading of the J-Tube on flat trailer at the fabrication yard decided to load them on one foam block as truck stanchions were too low (Good HSE practice) Upon arrival of the truck transporting J-Tube on the ILOGS quay side, construction vessel could not reception them directly aboard their vessel (Tidal issue + welding operation being performed on the side of the vessel) Only 2 trucks were available to transfer the 12 J-Tube sections from the fabrication yard to Ilogs quay. TECHNIP Group. This document and the information it contains are property of TECHNIP France SAS. It shall not be used for any purpose other than those for which it was supplied. Copyright TECHNIP France – All rights reserved. CR 08.E – Rev.0 – Sept. 2015 HSE ALERT ☒ Initial issuance Title: Region/ Project: HSE Alert Category: (Synergi Incident Categorisation) Final Issuance Reversal of J-Tube section Synergi Case No: 440096 Region A (Subsea) – Moho Nord Project Incident Date: 17/03/2016 SIF Near Miss Alert Issue Date: 22/03/2016 It was finally decided to temporarily store the J-Tube sections on the quayside In order to comply with the offshore installation procedure and to gain time on the mobilization of the construction vessel. J-tubes sections were installed on top of 2 foam blocks on the quay side. There was a deviation in the mobilisation procedure: J-tube were temporarily stored on quayside whereas they should have been directly loaded from truck to construction vessel No MOC and risk assessment performed following the deviation of the procedure Temporarily storage on 2 foam blocks along the quay was identified as not good HSE practice nevertheless no action was taken Foam blocks used for the storage of the J-Tube did not have all the same characteristics (Low density and High density). Wind gusts were observed along quayside prior the incidents 3.0 ☐ N°05/2016 IMMEDIATE ACTIONS All J-tube sections temporarily stored on the quayside on 2 foam blocks have been stored on 1 foam block Temporarily storage area was barriered off J-Tube were then transferred to Orelia and sea fastened as per procedure TECHNIP Group. This document and the information it contains are property of TECHNIP France SAS. It shall not be used for any purpose other than those for which it was supplied. Copyright TECHNIP France – All rights reserved. CR 08.E – Rev.0 – Sept. 2015 HSE ALERT ☒ Initial issuance Title: Region/ Project: HSE Alert Category: (Synergi Incident Categorisation) Reversal of J-Tube section Synergi Case No: 440096 Region A (Subsea) – Moho Nord Project Incident Date: 17/03/2016 SIF Near Miss Alert Issue Date: 22/03/2016 RECOMMENDATIONS Everyone is empowered to Stop the Work whenever an unsafe situation is observed: Stop Work authority should be reinforced Any deviation to procedure should be submitted to a Management of Change and risk assessment Procedure to be thoroughly reviewed prior each operation to ensure that all steps are properly defined and risk assessed Ensure storage area even temporary is barried off 5.0 Final Issuance The remaining J-Tube sections coming from the fabrication yard were transferred directly from truck to construction vessel without temporarily storage along quayside as per initial procedure TOFS were held to review main findings of the incident Initial investigation process started (ToR, Witness statement, storyboard…) 4.0 ☐ N°05/2016 12 SAFETY ACTIONS ALWAYS intervene when you see an unsafe act or condition ALWAYS perform a HSE Toolbox Talk and work with a permit or safe system to work ALWAYS use the correct tools safely to carry out the job. NEVER expose yourself or others to the risk of dropped or falling objects. TECHNIP Group. This document and the information it contains are property of TECHNIP France SAS. It shall not be used for any purpose other than those for which it was supplied. Copyright TECHNIP France – All rights reserved. CR 08.E – Rev.0 – Sept. 2015
© Copyright 2026 Paperzz