EYETS_LHC_2016-2017 _Travaux EN-EL

EYETS LHC 2016/2017
Works EN/EL/CF
A. Gonzalez & G. Girardot
11 octobre 2016
Agenda
1. Copper cabling
2. Optical fibers
3. Support needed
4. Conclusion
20/10/2015
Coordination meeting
1. Cabling campaigns
Intervention overview
1.
LHC1G-YEB1
2.
LHC1D-YEB1
3.
LHC1S-YEB1
4.
LHC2G-YEB1
5.
LHC2D-YEB1
6.
LHC3P-YEB1
7.
LHC3S-YEB1
8.
LHC4S-YEB1
9.
LHC5G-YEB1
18 cabling campaigns
275 cables / 21 km
10. LHC5D-YEB1
11. LHC5S-YEB1
12. LHC6S-YEB1
13. LHC7G-YEB1
14. LHC7D-YEB1
15. LHC7P-YEB1
16. LHC7S-YEB1
17. LHC8G-YEB1
18. LHC8D-YEB1
11/10/2016
EYETS 2016-2017 – Works EN-EL-FC
1. Cabling campaigns – Pt1 (Underground)
• Constraints:
•
•
•
•
•
Liquid Helium in QRL => authorization for the access to the cable trays needed
Electrical lockout
Installation of scaffolding over the magnets in UJ14
Opening cable passages in UJ14 / UJ16
Pulling fragile cables for AFP activity
Affaire
Code
Building
N°
PLAN
Title
Group
User
Nb.
cables
Length
(m)
Cabling
campaign
C213AHA173001
UL16
??
EYETS - SEISMIC NETWORK
EN-MME
M. CABON
4
120
LHC1D-YEB1
C213AHA176001
UJ14
??
EYETS - CABLAGE BPM AFP.6L1
BE-BI
C.
BOCCARD
4
220
LHC1G-YEB1
Works
Under
ground
11/10/2016
•
Length of cables ≈ 350m
•
Estimated duration:
•
Pulling =3d + 3d
•
Connecting + tests =2d + 2d
EYETS 2016-2017 – Works EN-EL-FC
1. Cabling campaigns – Pt1 (Surface)
• Constraints:
•
Electrical lockout
Affaire
Code
Building
N°
PLAN
Title
C213AHA163001
SR1
10357
EYETS - CABLAGE NOUVEAU RPADO SR1
C213AHA168001
SR1
10357
EYETS - FGC-ETHER FOR LHC - SR1
Works
Surface
11/10/2016
Group
User
TE-EPC H. THIESEN
TE-EPC
•
Length of cables ≈ 330m
•
Estimated duration:
•
Pulling =1.5w
•
Connecting + tests =1.5w
J. GOMEZ
COSTA
Nb.
cables
Length
(m)
Cabling
campaign
11
300
LHC1S-YEB1
1
30
LHC1S-YEB1
EYETS 2016-2017 – Works EN-EL-FC
1. Cabling campaigns – Pt2 (Underground)
• Constraints:
•
•
•
•
Liquid Helium in QRL => authorization for the access to the cable trays needed
Electrical lockout
Opening cable passages between UA and RA
Pulled cable through all the arc 1-2
Affaire
Code
Building
N°
PLAN
Title
Group
User
Nb.
cables
Length
(m)
Cabling
campaign
C213AHA174001
UA27
10890
EYETS - CABLAGE VACUUM –
TE-VSC
JP. BOIVIN
1
70
LHC2D-YEB1
C213AHA165001
UA23
11241
EYETS - TDI INTERFEROMETER RESET -
EN-STI
J. LENDARO
1
47
LHC2G-YEB1
C213AHA172001
ARC1-2
??
EYETS - REMPLACEMENT LIAISONS
SAREP THERMOSWI
TE-MSC
P. DENIS
1
5500
LHC2G-YEB1
Works
Under
ground
11/10/2016
•
Length of cables ≈ 5617m
•
Estimated duration:
•
Pulling =1d + 1.5w
•
Connecting + tests =2d + 3d
EYETS 2016-2017 – Works EN-EL-FC
1. Cabling campaigns – Pt3 (Underground)
• Constraints:
•
Electrical lockout
Affaire
Code
Building
N°
PLAN
C213AHA
UJ33
??
Title
Group
User
Nb.
cables
Length
(m)
Cabling
campaign
EYETS - MODIFICATION CABLAGE
COLLIMATION UJ33
EN-STI
J. LENDARO
54
850
LHC3P-YEB1
Works
Under
ground
11/10/2016
•
Length of cables ≈ 850m
•
Estimated duration:
•
Pulling =1w
•
Connecting + tests = 2w
EYETS 2016-2017 – Works EN-EL-FC
1. Cabling campaigns – Pt3 (Surface)
• Constraints:
•
Electrical lockout
Affaire
Code
Building
N°
PLAN
Title
C213AHA163002
SR3
10357
EYETS - CABLAGE NOUVEAU RPADO SR3
C213AHA168002
SR3
10357
EYETS - FGC-ETHER FOR LHC - SR3
Works
Surface
11/10/2016
Group
User
TE-EPC H. THIESEN
TE-EPC
•
Length of cables ≈ 330m
•
Estimated duration:
J. GOMEZ
COSTA
•
Pulling =1.5w
•
Connecting + tests =1.5w
Nb.
cables
Length
(m)
Cabling
campaign
11
300
LHC3S-YEB1
1
30
LHC3S-YEB1
EYETS 2016-2017 – Works EN-EL-FC
1. Cabling campaigns – Pt4 (Surface)
Affaire
Code
Building
N°
PLAN
C213AHA167001
SH4
??
Title
Group
User
Nb.
cables
Length
(m)
Cabling
campaign
EYETS - CABLAGE 24VDC REDONDANT
P4 -
TE-CRG
B. IVENS
4
205
LHC4S-YEB1
Works
Surface
11/10/2016
•
Length of cables ≈ 205m
•
Estimated duration:
•
Pulling =3d
•
Connecting + tests =4d
EYETS 2016-2017 – Works EN-EL-FC
1. Cabling campaigns – Pt5 (Underground)
• Constraints:
•
•
•
Liquid Helium in QRL => authorization for the access to the cable trays needed
Electrical lockout
Opening cable passages between UL56 et USC55
Affaire
Code
Building
N°
PLAN
Title
Group
User
C213AHA161003
R571
C213AHA161001
10906
EYETS - DEPLACEMENT CABLE DC
TCTW.A4R5
BE-BI
C. BOCCARD
R532
10906
EYETS - BPM POUR TCTW.4L5.B2
BE-BI
C. BOCCARD
C213AHA161002
R532
10906
EYETS - DEPLACEMENT CABLE DC
TCTW.A4L5
BE-BI
C. BOCCARD
C213AHA166001
USC55
10906
EYETS - SIGNAUX TENSION TCTW P5
EN-STI
J. LENDARO
3
60
LHC5G-YEB1
C213AHA173002
UP53
??
EYETS - SEISMIC NETWORK -
EN-MME
M. CABON
4
120
LHC5G-YEB1
Works
Under
ground
11/10/2016
•
Length of cables ≈ 1170m
•
Estimated duration:
•
Pulling =1w + 1.5w
•
Connecting + tests = 4d + 1w
Nb.
cables
Length
(m)
Cabling
campaign
LHC5D-YEB1
6
990
LHC5G-YEB1
LHC5G-YEB1
EYETS 2016-2017 – Works EN-EL-FC
1. Cabling campaigns – Pt5 (Surface)
• Constraints:
•
Electrical lockout
Affaire
Code
Building
N°
PLAN
Title
Group
User
Nb.
cables
Length
(m)
Cabling
campaign
C213AHA163003
SE5
10357
EYETS - CABLAGE NOUVEAU RPADO SE5
TE-EPC
H. THIESEN
11
300
LHC5S-YEB1
C213AHA168003
SE5
10357
EYETS - FGC-ETHER FOR LHC - SE5
TE-EPC
J. GOMEZ
COSTA
1
30
LHC5S-YEB1
Works
Surface
11/10/2016
•
Length of cables ≈ 330m
•
Estimated duration:
•
Pulling =1.5w
•
Connecting + tests =1.5w
EYETS 2016-2017 – Works EN-EL-FC
1. Cabling campaigns – Pt6 (Surface)
Affaire
Code
Building
N°
PLAN
C213AHA167002
SH6
??
Title
Group
User
Nb.
cables
Length
(m)
Cabling
campaign
EYETS - CABLAGE 24VDC REDONDANT
P6 -
TE-CRG
B. IVENS
4
205
LHC6S-YEB1
Works
Surface
11/10/2016
•
Length of cables ≈ 205m
•
Estimated duration:
•
Pulling =3d
•
Connecting + tests =4d
EYETS 2016-2017 – Works EN-EL-FC
1. Cabling campaigns – Pt7 (Underground)
• Constraints:
•
•
•
Works
RP area
Electrical lockout
Opening cable passages in UJ76
•
Length of cables ≈ 8171m
•
Estimated duration:
Under
ground
•
Pulling =1w + 3d + 4d
•
Connecting + tests = 1w + 1w +1w
Affaire
Code
Building
N°
PLAN
Title
Group
User
Nb.
cables
Length
(m)
Cabling
campaign
C213AHA169001
RR77
10538
EYETS - BPM COLLIMATEURS PT7
BE-BI
C. BOCCARD
3
900
LHC7D-YEB1
C213AHA164002
R771
10541
EYETS - CABLAGE UA9
EN-STI
J. LENDARO
24
1590
LHC7D-YEB1
C213AHA174004
R771
10890
EYETS - CABLAGE VACUUM
TE-VSC
JP. BOIVIN
14
1208
LHC7D-YEB1
C213AHA169002
UJ76
10538
EYETS - BPM COLLIMATEURS PT7
BE-BI
C. BOCCARD
1
250
LHC7G-YEB1
C213AHA174003
R74
10890
EYETS - CABLAGE VACUUM
TE-VSC
JP. BOIVIN
9
1150
LHC7G-YEB1
C213AHA164001
TZ76
10541
EYETS - CABLAGE UA9
EN-STI
J. LENDARO
15
830
LHC7P-YEB1
C213AHA174002
TZ76
10890
EYETS - CABLAGE VACUUM
TE-VSC
JP. BOIVIN
12
2220
LHC7P-YEB1
C213AHA187001
TZ76
??
EYETS - BIC COLLIMATEUR CRYSTAL
TE-MPE
C. MARTIN
1
23
LHC7P-YEB1
11/10/2016
EYETS 2016-2017 – Works EN-EL-FC
1. Cabling campaigns – Pt7 (Surface)
• Constraints:
•
Electrical lockout
Affaire
Code
Building
N°
PLAN
Title
Group
User
Nb.
cables
Length
(m)
Cabling
campaign
C213AHA163004
SR7
10357
EYETS - CABLAGE NOUVEAU RPADO SR7
TE-EPC
H. THIESEN
11
300
LHC7S-YEB1
C213AHA168004
SR7
10357
EYETS - FGC-ETHER FOR LHC - SR7
TE-EPC
J. GOMEZ
COSTA
1
30
LHC7S-YEB1
Works
Surface
11/10/2016
•
Length of cables ≈ 330m
•
Estimated duration:
•
Pulling =1.5w
•
Connecting + tests =1.5w
EYETS 2016-2017 – Works EN-EL-FC
1. Cabling campaigns – Pt8
• Constraints:
•
•
•
Liquid Helium in QRL => authorization for the access to the cable trays needed
Electrical lockout
Opening cable passages between UA and RA
Affaire
Code
Building
N°
PLAN
Title
Group
User
Nb.
cables
Length
(m)
Cabling
campaign
C213AHA165002
UA87
11241
EYETS - TDI INTERFEROMETER RESET
EN-STI
J. LENDARO
1
158
LHC8D-YEB1
C213AHA174004
UA87
10890
EYETS - CABLAGE VACUUM
TE-VSC
JP. BOIVIN
1
70
LHC8D-YEB1
C213AHA186002
UL86
??
EYETS - CABLAGE P8 QURCA/B
TE-CRG
B. IVENS
26
1230
LHC8D-YEB1
C213AHA186001
UL84
??
EYETS - CABLAGE P8 QURCA/B
TE-CRG
B. IVENS
34
1155
LHC8G-YEB1
Works
Under
ground
11/10/2016
•
Length of cables ≈ 2613m
•
Estimated duration:
•
Pulling =1w + 3d
•
Connecting + tests = 1w + 1w
EYETS 2016-2017 – Works EN-EL-FC
2. Optical Fibre – LHC activities
Location
• Works
• LHC Survey BIS fibres (5 weeks)
US’s, UJ's, UA’s, TZ76, USC55
•
Blowing O.F. cables over existing duct infrastructure US’s and UJ’s to UA’s
•
Local distribution (Patchcables installation) UA’s + patching and measurements
• LHC Cryo redundancy LSS and QUI fibres (5 weeks)
•
Local distribution + Blowing O.F. cables US’s and UJ’s to UA’s, UL’s
•
Patching and measurements
• Fibres for LUA9 P7R (1 week)
•
TZ76, UJ76, R771
Blowing O.F. cables over existing duct infrastructure TZ76-UJ76-R771 + patching and measurements
• HL-LHC Relocation fibre cables P1-P1.8 (2.5 weeks )
•
SR1, SM18
Systems disconnection and relocation over the new O.F. cables
• Replacement of RSF cables (3.5 weeks) (acces by LHC)
Constraints:
•
•
•
US’s, UJ's, UA’s, UL’s,TZ76
Electrical lockout in UA’s
Limited working coactivity near blowing activities (2, 3 hours interventions)
No more than 2 works at the same time, draft planning will be proposed to EN-ACE
11/10/2016
EYETS 2016-2017 – Works EN-EL-FC
TI2, TI8
2. Optical Fibre – LHC activities
Location
• Registration and inspections
• Optical Fibre Database
UA27, US's ,UJ's
•
Registration /verification labeling of Cable Hardware
•
Duct/microduct registration
• Verification radiation induced attenuation progression
•
Optical fibre measurements
• O.F. monitoring system
•
US’s, UJ's
UA27, US's ,UJ's, Surface
Patching and Optical fibre measurements
Constraints:
• No working constraints (inspections in front of the racks, visual inspection of cable trays)
11/10/2016
EYETS 2016-2017 – Works EN-EL-FC
3. Support needed
• Departmental Safety Officer (DSO):
• Authorization for access to cable tray
• EN/ACE
• Detail schedule => the 2 cable campaigns of the same point in parallel (if possible)
• VIC
• Electrical lockout
• EN/EA
• Scaffolding, …
• EN/HE
• 50/60 drums to transport and handle
• HSE/RP
• TE/CRG
• Cryo lockout
• TE/EPC
• Electrical lockout
20/10/2015
Coordination meeting
G. Girardot
4. Conclusion
• Activities on all LHC sites.
• The presence of liquid helium in the QRL increase the constraints and risks
for cable works.
• Access constraints during cabling.
• Many fireproof closure will be open.
• Many other groups will be involved in our interventions.
• All new requests will be subject to the approval of the coordination
EN/ACE and EN/EL (resources)
20/10/2015
Coordination meeting
G. Girardot
Thank you for your attention !