TURNER INDUSTRIES GROUP, LLC LESSONS LEARNED POST-HURRICANE TURNAROUNDS Houston Business Roundtable May 10th, 2006 REPRESENTATIVE TURNAROUNDS Case 1 - 90,000 BPD refinery in Colorado •Full plant outage 1st qtr 06’ - planned 42 days oil-to-oil •350,000 direct man-hours (all contractors) •Peak loading of approximately 1,000 directs Case 2 - 200,000 BPD refinery in Louisiana •FCCU, Alky, HDS & Sulfur Block 1st qtr 06’ - planned 32 days oil-to-oil •100,000 direct man-hours (Turner only) •Peak loading of approximately 350 directs CASE 1 350,000 direct man-hours with a total installed cost of approximately $80MM (including Capital Projects) Planned peak manpower loading of approximately 1,000 directs Planned for 4th qtr 2005 (subsequently deferred to 1st qtr 2006) HDS, Crude & SRU 3-year run-life to Spring 2008 AU, FCC, Cat-Poly, VRU & Amine 5-year run-life to Spring 2010 1,200 expense work items ULSD project ($450MM) FCC revamp adding a 3rd stage separator ($4MM) CAPEX scope ($2MM) The turnaround presented specific issues not representative of a "typical" turnaround (2) large capital projects with an anticipated peak manpower at or around the turnaround time frame TA hampered by a lack of availability with regard to plant access, lay down areas, office locations, contractor trailers, Owner personnel, contractors and craftsman Local market is not conducive to heavy industrial construction The turnaround timing was during winter conditions TA would reach an over maximum manpower density To account for these factors, the estimated productivity factors were increased over typical industry standards 50% productivity loss (30% outage factor and 20% nontypical outage factor) 10% contingency 15% allowance for scope growth Concerned with ability to attract and retain craft labor Instituted plan to over-man the turnaround in the initial stages in order to assure retention for; Scope growth Contingency Unanticipated productivity losses Absenteeism & attrition Recruiting issues P3 schedule developed to account for resource loading contingency Developed schedule under normalized conditions (no allowances or contingency) Leveling techniques used to optimize the schedule to front-end load resources (direct labor) Added productivity factors to allow for reconciliation to the final budgeted man-hours Developed external Excel based spreadsheet used to adjust to additional 25% man-power allowance Re-allocated manpower in P3 via hard logic Design craft wage rates to attract quality craft & supervision Original wages were set for 4th qtr 05’ execution TA execution window was deferred to 1st qtr 06’ Conducted an analysis of current, prevailing and anticipated wage rates that would be required for the new TA timeframe TA, originally targeted for 4th qtr 05’, was on the downward side of the 4th qtr 05’ peak New TA window would be in the midst of peak manpower requirements in the Gulf South This presented several critical (high risk) factors with regard to contracting and labor Description of Threat Severity Probability Lack of resources (general) HIGH MEDIUM Lack of qualified crafts and their availability HIGH HIGH Lack of resources in view of Colorado HIGH MEDIUM Continual decline of qualified work force HIGH HIGH Workforce attracted away from industrial sector Lack of specialty welders HIGH HIGH MEDIUM MEDIUM Impact of Threats •Unable to attract craft •Unable to adequately staff •Safety concerns •Potential QA issues •Increased personnel turnover •Schedule slippage •Increased LPO Additional risk to TA due to industry manpower requirements Would need to implement new wage & compensation structure Allow for “market-plus” condition w/ “Market” = Gulf South Ensures wage rates would be sufficiently higher than those in the Gulf-South Coupled with other incentives and completion bonuses would allow us to attract and maintain quality craft & supervision However, Hurricane’s Katrina & Rita shifted the industry and further exposed the TA Projects & TA’s were shifting to 1st qtr 06’, already the predicted peak Increased industry peak manpower requirements above those previously forecasted Re-build effort attracted craftsman away from the industrial sector Developed risk model for three different wage rate / incentive structures Based on HBR data and contractor surveys Survey contractors for current / relevant experiences with post-hurricane wages Optimize wage structure to remove profit motive Ensure increase goes to craft Develop flexible attractive wage & incentive structure for current environment Offer contingency for RLT approval OPTION “0” - Maintain current wage & compensations structure at pre-hurricane structure Description of Threat Probability Consequence Forces contractors to recruit non-familiar craftsman HIGH Safety, QA, productivity Forces contractors to recruit less skilled craftsman to match wage rates Lower skill set equals decreased safety performance Lower skill set equals decreased productivity HIGH Safety, QA, productivity Will increased attrition and turnover (less dedicated craftsman) Increases recruiting time frame HIGH LTI, Recordable, Fatality MEDIUM Cost & schedule creep (LPO) MEDIUM Safety, QA, productivity HIGH Cost & schedule creep (LPO) OPTION “1” - Modify wage & compensation to “level 1” Added approximately 10% to wages w/ an added safety & completion bonus equivalent to 10% of base wage rate Description of Threat Increases TA cost Probability HIGH Consequence Approximate $1MM Forces contractors to recruit non-familiar craftsman MEDIUM Safety, QA, productivity Forces contractors to recruit less skilled craftsman to match wage rates Lower skill set equals decreased safety performance MEDIUM Safety, QA, productivity Lower skill set equals decreased productivity Will increased attrition and turnover (less dedicated craftsman) Increases recruiting time frame LOW LTI, Recordable, Fatality LOW Cost & schedule creep (LPO) MEDIUM Safety, QA, productivity MEDIUM Cost & schedule creep (LPO) OPTION “2” - Modify wage & compensation to “level 2” Added approximately 25% to wages w/ an added safety & completion bonus equivalent to 25% of base wage rate Recommended structure to drive risk profile to “low” (schedule driven TA) Description of Threat Probability Consequence Increases TA cost HIGH Approximate $5MM Forces contractors to recruit non-familiar craftsman LOW Safety, QA, productivity Forces contractors to recruit less skilled craftsman to match wage rates Lower skill set equals decreased safety performance Lower skill set equals decreased productivity LOW Safety, QA, productivity LOW LOW Will increased attrition and turnover (less dedicated craftsman) Increases recruiting time frame LOW LTI, Recordable, Fatality Cost & schedule creep (LPO) Safety, QA, productivity LOW Cost & schedule creep (LPO) Turnaround Results Wages: The wage structure ended up below current Gulf Coast norm as competition grew from other turnarounds and posthurricane rebuilding efforts Wage rates were set at option “1” with safety & completion bonus to be earned separate from wages The execution team did not implement contingency for raising wages to option “2” Per diem and travel were paid The safety & completion bonus were separated from wage rates instead of earned in real time Wages affected recruiting but did not affect retention Manpower: The turnaround was 10-15% under-manned and 2025% under managed. Contingency factor too low (10%) Used incorrect resource profile as the basis for recruiting Manpower profile based on estimated man-hours per logic driven P3 schedule No allowance for over-manning No allowance for contingency or scope growth Relaxed English speaking requirement to attract craft of Hispanic decent and from Puerto Rico Absenteeism: was report to be at approximately 10% Although securing manpower was an issue, absenteeism & attrition appeared to be a non-issue Safety, Quality & Productivity: poor performance by all standards (4) recordable injuries on 500,000 direct man-hours (including capital projects) Weld rejection rate was high, especially on alloy piping Leaks on start-up Start-up delayed due to Capital Projects, expense work completed on time Contributing factors: Competing turnarounds in Gulf Coast paying higher wages than anticipated Per diem for working locally (per diem never adjusted) Contractors were stretched beyond their ability to provide a “known” work force. Recruiting non-familiar craftsman or craft from non-Gulf Coast regions Inadequate allocation of QC resources (Owner driven) Inordinate amount of late scope additions & discovery items (added 150,000 man-hours) Increased unit congestion above 1,500 directs vs. 1,000 planned CASE 2 100,000 Turner direct man-hours with a total installed cost of approximately $125MM (including Capital Projects) Planned peak manpower loading of approximately 1,000 directs TA premises set by Owner for a sequential unit turnaround of the FCC, Alky, HDS and Sulfur units FCC revamp executed by Cat Specialist HDS & Sulfur units executed by GC Turner-Industries expense and CAPEX related scope of work in the FCC and Alky units. The Owners planning premises made some allowances for typical turnaround inefficiencies Owner Alliance estimating manual plus 20% or Page & Nations plus 40% Expected significant scope growth through discovery Mobilized contractor supervision and some craft early To account for these factors, the Owner made allowance over their typical standards Allowance for discovery, analysis, recommendation & repair in TA timeline Concerned with ability to attract and retain craft labor Manpower / resource profiles Resource loading the P3 schedule with the total estimated man-hours Inclusive of productivity factors Included indirects on an individual task basis Levelized using a systems turnover based priority Craft labor rates were estimated pre-hurricanes Adjusted 1st qtr 06’ Subsequent analysis of the prevailing wages rates and compensation structures for competing projects and turnarounds forced several revisions to the compensation structure Initially the wages were set for the Gulf-Coast standard plus $3.50 per hour with an additional $3.50 per hour completion bonus The final rate structure was set (2) weeks prior to the oilout date to include the total $7.00 per hour as part of the base wage with an additional $3.50 per hour completion bonus. Turnaround Results Wages: Owner set the wage rates at post-hurricane rates plus additional incentives Per diem was paid but no reimbursement was allowed for travel Wages proved to be sufficient to attract craft labor Attrition was not due to wages Per diem was not adequate to cover the lodging costs posthurricane($60 per day per diem versus $90 per day hotel costs) Manpower: Turner was 10-12% under-manned in the initial stages of the TA Turner’s was able to satisfy their manpower needs pre-TA Previously committed craftsman were either not showing up or left while in process Several factors contributed to the depletion of the recruited work force; The accelerated start of competing projects / turnarounds plus escalating wages by competing projects (3) day orientation cycle (unpaid) Per diem proved to be inadequate for local housing market post-hurricanes Estimating standards used in 2004 and proved to be inaccurate for a 2006 TA TA Execution was during peak manpower requirements in the industry No allowances for scope growth or discovery in resource profile Resource profile in P3 proved to be inaccurate; Pipe resources (fitters & welders) were identified in the P3 schedule for only those activities that involved pipe welding Other activities normally classified as piping activities were classified as boilermaker activities Gives a false measurement of the actual pipe fitters required for the scheduled work. Manpower concerns were alleviated by several factors: Late turnover of systems from decommissioning pushed schedule activities Recruiting effort continued with provisions made for securing non-traditional labor sources Gained peak manpower earlier than scheduled Turner was successful in achieving peak manpower within their scheduled window (adjusted for late turnover) Owner late in turning over discovery work items Absenteeism: Estimated at 10-12% Virus attack on TA (craft, staff & supervision) An issue with the critical craft such as pipe fitters and welders For example: Resource profile calls for (4) welders, the absence of (1) represents a 25% absent rate Completion bonus not a factor at beginning of TA Criteria helped as craft banked several weeks of bonus (no more than 2 absences allowed) Attrition was not due to wages General malaise in industry Safety, Quality & Productivity: acceptable performance (1) recordable injury High weld reject rate. Fit-up issues due to lack of qualified pipe fitters lead to weld reject rates Mechanical craft with productivity ranging from a low of .85 to a high approaching 1.00 (<1.00 poor) Piping craft productivity is forecasted at a .65 No leaks delaying systems start-up Instituted strict QC program to follow flange make-up Increased QC staff above previous “normal” Other contributing factors; Productivity factor used for estimating and resource loading was too low for current condition of labor market Added requirements of post-BP environment increases travel time and complicates logistics A factor of 40% is to low for a turnaround of this magnitude and complexity Crew mixture of foreman to craft was set by Owner on a 121 basis, revised to a 10-1 ratio but this still proves to be too high in a turnaround environment Owner late in turning over discovery work items Improper interpretation of Page unit rates Page is base rate “plus” inefficiencies for non-TA construction activities No account made for 2-year difference in labor market and post-hurricane environment Lessons Learned Wages & incentives; Proved to be insufficient for recruiting in a labor market not in view of the Gulf-South, proved effective in recruiting for Gulf-South work Wages had limited impact on retention as competition increased Incentives proved effective in retaining craft toward end of TA as they start seeking ROF Recognize the market & set attractive per diem Possibly include incentives in bare wages Estimating Revise estimating standards to account for current environment. History does not apply. Plan for contingency wage increases Historical issue of under-estimating contingency & scope growth Anticipate the added requirements of the post-BP environment (increase in travel time and complicated logistics) Increase indirect staffing required to plan, monitor and coordinate craft (supervision, QC, etc.) Planning Develop discovery work within first TA 30% of duration Front-end load manpower, back-end load scope to first 50% duration Develop TA schedule to allow for over-manning in first 50% of duration Include allowances in resource profile as well as timeline Management: Craft supervision has increased responsibility for planning, productivity & QA/QC. Decrease ratio of craft to foreman to 6-8:1 Anticipate additional QC staffing to assure tightness
© Copyright 2026 Paperzz