CHAPTER THREE METHODOLOGY 3.1 Introduction This chapter describes the method used to prepare specimens and laboratory testing procedures that were used to assess the porous asphalt properties. The right method of sample preparation is important because it will affect all test results. Therefore, the specimen preparation must be done consistently and in the correct manner to assure quality data. 3.2 Preparation of Marshall Specimens Porous asphalt samples were prepared using materials whose properties were described in Chapter 3. Aggregates and fillers were batched in metal containers to produce one specimen weighing approximately 1.1 kg. The samples were compacted by using the Marshall hammer that applied an impact mode of compaction. 3.3 Batching and Preparation of Aggregates Aggregates and fillers were batched in metal containers. Each batch was sufficient to manufacture one sample. The batched aggregates were placed in an oven set at the desired mixing temperature for a period of at least 4 hours. 3.4 Preparation of Bitumen The bitumen that arrived in bulk was subjected to two cycles of heating. Sufficient quantity of bitumen during one laboratory session was placed in the oven at the required mixing temperature until it was fully liquefied for mixing with the 21 aggregates. The SBS and 70P respectively required at least 4 and 2 hours of preheating. The cycle of heating of each bitumen was kept consistent. The mixing and compaction temperatures are dependent on binder viscosity. The guidelines from Darin Tech (2000) provides information on mixing and the range of compaction temperatures for base and rubberized mixes as shown in Table 3.1. Following the recommendations given in Table 3.1, the chosen mixing and compaction temperatures for mixes prepared using the three types of bitumen are outlined in Table 3.2. Table 3.1 Mixing and Compaction Temperatures According to Darin Tech (2000) Binder Type Mixing Temperature Compaction Temperature Base Bitumen 150oC 130oC SBS Modified 185oC 140oC Base Bitumen + DAMA 180oC 5oC 165oC Table 3.2 Mixing and Compaction Temperatures Adopted in This Investigation 3.5 Binder Type Mixing Temperature Compaction Temperature 70P 140oC 130oC SBS 180oC 165oC 70P + DAMA 180oC 165oC Preparation of Moulds A typical 101.6 mm inner diameter steel Marshall moulds were used in conjunction with the Marshall hammer. In addition, moulds for the Marshall hammer must be 22 fitted with a collar. Both steel moulds and their corresponding base plates were placed in the oven together with the aggregates. 3.6 Mixing An electrically heated paddle mixer was used to blend the aggregates and bitumen. The mixer was first calibrated and then set to the required mixing temperature. Mixing of dry aggregates was accomplished in less than 30 seconds. Then, the correct amount of binder and additives was poured onto the dry mixed aggregate and the wet mixing continued for a further 1 minute. The amount of bitumen required was calculated as a percentage of the total mix. Temperatures of the mix immediately prior to compaction shall be within the limits of the specified compaction temperature. Full compaction was then carried out using the Marshall hammer once the mix temperature dropped to the desired compaction temperature. 3.7 Compaction of Marshall Specimen Impact specimens were compacted using an automatic Marshall compaction apparatus. The compaction hammer had a flat circular tamping face and a 4536 g sliding weight with a free fall of 457.2 mm. The mould holder was mounted on the compaction pedestal so as to center the compaction mould over the center of the post. It held the compaction mould, collar and base plate securely in position during compaction of the specimen. The entire batch was placed in a previously prepared mold assembly and the mixture vigorously spaded with a heated spatula or trowel. A heated rod was then used to tamp the mix 15 times around the perimeter and 10 times over the interior. Temperatures of the mix immediately prior to compaction shall be within the limits of the specified compaction temperature. 23 Two filter papers were placed on the surface of the mix and replaced the mold collar. The motor was switched on caused the hammers to apply about 50 blows per face and the compacter was run automatically. When compaction was completed, the sample was allowed to cool to room temperature overnight and later extruded from the compaction mould. Specimen was then carefully transferred to a smooth, flat surface and allowed it to cool to ambient temperature before testing. 3.8 Determination of Permeability Measurement of coefficient of permeability constituted a major part of the study. A new permeameter similar to the one developed at Leeds University by Hamzah (1995) was designed and fabricated. The coefficient of permeability was calculated using Equation (3.1). k 2.3 aL h1 log At h2 Equation (3.1) Where: k = The coefficient of permeability (cm/s) a = The tube cross sectional area (cm2) A = Sample cross sectional area (cm2) L = Height of sample (cm) t = Time (s) h1 and h2 = Initial level (cm) and final level (cm) In general, a hydraulic gradient was created across the specimen and then the water flow over a period of time was measured. During the test, water in the standpipe fell 24 from heights h1 to h2 over a time period t. The time taken, to the nearest 0.1 s, for water to pass through the two marks on the standpipe was noted using a stopwatch. The average of three readings was calculated for the determination of permeability. Having determined the permeability, each specimen was manually extruded and the physical dimensions measured. 3.9 Determination of Density and Porosity 3.9.1 Marshall Specimen The density of porous asphalt specimens were measured based on the specimen geometry. The heights of specimen were measured using a digital vernier caliper at three different points. Specimen diameter was assumed to be equal to the standard Marshall mould inner diameter. The average of 3 readings was taken for measurements of heights and diameters of specimens. Mix density was calculated from Equation (3.2). D 4M a d 2 h Equation (3.2) Where: D = Compacted specimen density (g/cm3) Ma = Mass of specimen in air (g) d = Diameter of specimen (cm) h = Average height of specimen (cm) Knowing the density, specimen porosity was calculated from Equation (3.3). 25 D P 1001 SG Equation (3.3) Where: P = Porosity of specimen (%) D = Density of specimen (g/cm3) SG = Specific gravity of mix, computed from the specific gravities of individual aggregate size range 3.10 The Marshall Test In the stability test, the specimens were prepared with the specified temperature by immersing in a water bath at a temperature of 60ºC ± 1ºC for a period of 45 minutes. It was then placed in the Marshall stability testing machine and loaded at a constant rate of deformation of 50.8 mm/minute until the maximum load was reached. The stability result was recorded on the Marshall testing machine in kN. The total time elapsed between removing the specimen from the bath and completion of the test was not more than 30 seconds. 3.11 The Resilient Modulus Test The resilient modulus test was conducted using the Universal Asphalt Testing Machine, MATTA according to the ASTM test method D4123 (ASTM, 1999). Each specimen was tested at 25oC after 4 hour-conditioning. A 1200 N peak load was applied along the vertical diameter of the sample. With a fixed level of applied peak force, the test sequence consists of a 5 count of conditioning pulses followed by 5 loading pulses. The pulse period and pulse width were respectively 3000 ms and 100 ms while the rise time was 50 ms. The rise time was measured at the points of 10 % and 90 % of peak force and force pulse diagram is shown in Figure 3.1. 26 Peak Load Load Rise Time Time Pulse Width Pulse Period Figure 3.1 The Force Pulse Level and Timing Diagram (BSI, 1993) 3.12 The Dynamic Creep Test The dynamic creep testing was carried out using the Universal Testing Machine, MATTA and shown in Plate 3.1. The test conditions were pre loading for 2 minutes at 0.01 MPa as a conditioning stress to obtain a proper bedding of the specimen due to its shape that might not really flat. Then, 2 minutes of recovery time was allocated before actual testing. Actual dynamic creep test was conducted at 40ºC for 1 hour loading time and 0.1 MPa applied stress. The results were given as permanent deformation after 1800 pulses or 1 hour expressed in strain. Periodically repeated loading consisting of 1 second loading and another 1 second unloading before application of the next pulse. Hence, the pulse period and pulse width were respectively 2 and 1 sec. The dynamic creep test parameters adopted above was in accordance to Nils Ulmgren (1996). The loading cycle for dynamic creep test is shown in Plate 3.3. 27 Stress (kPa) Plate 3.1 The Dynamic Creep Test in Progress 110 10 10 min 1s 1s Strain () T irr A T A = Strain after conditioning irr = Irreversibel strain (permanent def.) Figure 3.2 Load and deformation (Nils,1996) 28 3.13 Summary This chapter describes the laboratory testing methods and the instrumentation that were used to prepare and test the specimens. Slab and Marshall specimens were prepared for testing the engineering properties and performance of porous asphalt. Marshall specimens were compacted by the Marshall hammer while slab specimens were compacted by a Kango hammer. Apart from permeability, two main performance tests conducted on porous asphalt specimens included stiffness modulus and permanent deformation. 29
© Copyright 2026 Paperzz