LHC_Coordination_20170321

LHC-EYETS 2016/17
Coordination meeting #23
21st March, 2017
EYETS follow up – EN-ACE-OSS
EYETS 2016-2017: General infos
•
LHC-EYETS completed on Sunday 30th April. All the activities must be completed by Friday 14th April
•
IMPACT: intervention period EYETS-LHC-2016/17
•
Phone ‘piquet’: 161669
•
OSS website (planning, constraints, …):
https://espace.cern.ch/en-dep-mef-lpc/EYETS2016-2017/Global%20Schedules/Forms/AllItems.aspx
•
INDICO: https://indico.cern.ch/category/7198/
•
Unlock out W14 (3rd April - 7th April)
•
LHC back to BE-OP on Friday 14th April
•
The cryogenics filling started from mid March only LIMITED cryogenics lock out
authorisations can be delivered
•
Tests started in the Machine FENCES are in place DO NOT CROSS!!!!
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
2
No Access in the Surface
& Underground Areas
DSO Test
DSO TEST
All points  7th & 8th April
 If the PZ85 lift replacement is not completed:
- NO access to LHCb from the LHC machine from 6th April
afternoon, to Monday 10th April in the morning;
- Access on 10th, 11th and 12th from 8am to 4pm
 The patrol of Point 8 (including LHCb) is foreseen on 6th April in the
afternoon)
 All the openings LHC Machine / Experiments must be closed at latest on
31st March
 All the openings inside the LHC machine must be closed by the 31st March
 From 3rd April the patrols will start
 The Experiments must be patrolled for the DSO test
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
3
TETRA procedure when degraded network
After the discussion in the CSAP and in a dedicated meeting held with the A&T
DSOs, the following procedure is proposed:
• Access is not generally forbidden to the underground when TETRA is not
available.
• The evident corollary is that the undergrounds must not be evacuated when
TETRA is not working.
• In case of TETRA malfunctioning a warning should be sent to "active" activity
leaders (people who declared an IMPACT, and these IMPACTs are "active"),
warning them that communication capabilities are reduced (no TETRA, or
even no TETRA and no GSM), and that they should consider to postpone
their activities.
• If the risk analysis of the activity concluded that TETRA is mandatory as
safety measure (lone worker...), the activity must be postponed.
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
4
PM85 intervention
Schindler would like to verify the
status of PM85 pit this Friday 24
mars at 12h45.
 No access to P8 during 10
minutes.
 Two people will be in place (-1
and 0 floor) to advise everyone.
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
5
Filling of Inner Triplets: NO ACCESS
IT in LSS1 and 5
filling will start on Wednesday 22nd March, morning
IT in LSS2 and LSS5
 filling will start on Friday 24th March, morning
Access in the IT area, when ITs are filled with Liquid Helium:
- Authorization of the complex manager;
- Max duration of the intervention 10 min;
- Access only in the transport area;
- Intervention well justified.
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
6
TETRA measurement campaign in the LHC
IT/CS wants to carry out in LHC:
•
Deep measurements campaign in the LHC to check if the TETRA coverage can be improved
(e.g. few meters with no TETRA coverage at the centre of some arcs, FB atex radios performing worse than standard radios)
•
Validate the radio infrastructure against PIM
(interference phenomenon caused when several high-power networks are transmitted together)
After the discussion in the CSAP and in a dedicated meeting held with the A&T
DSOs, the following procedure is proposed:
•
•
•
•
Access is not generally forbidden to the underground when TETRA is not available.
The evident corollary is that the undergrounds must not be evacuated when TETRA is not
working.
In case of TETRA malfunctioning a warning should be sent to "active" activity leaders (people
who declared an IMPACT, and these IMPACTs are "active"), warning them that
communication capabilities are reduced (no TETRA, or even no TETRA and no GSM), and
that they should consider to postpone their activities.
If the risk analysis of the activity concluded that TETRA is mandatory as safety measure (lone
worker...), the activity must be postponed.
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
7
UX45 – NO access
No access on the
“overhead” area
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
8
Work authorizations (Helium spill risk)
Document Id
1738609
1738911
1739823
1742339
1742554
1743236
1745101
Document Version
1
1
2
1.1
1
1
1
1745139
1746508
1749199
1752496
1752734
1752794
1753084
1753427
1754991
1754996
1756958
1758697
1761122
1761124
1761270
1762938
1764526
1764976
1
1
1
1
1
1.1
1
1
1
1
1
1
1
1
1
1.01
1
1
1767698
1767516
1
0.5
1769055
1769057
1767952
0.5
0.5
0.1
updated on 21st March 2017
Title
Status
Exceptional Authorisation: HSE-RP-AS Survey in IT areas (EYETS 2016)
Released
Exceptional Authorisation: EN-ACE-SU: Maintenance in IT Areas (EYETS 2016/17)
Released
Work Frame Authorisation: EP-UAT-AFP installation, Phase 2
Cancelled
Exceptional Authorisation: EN-MEF-MM Radiographie Industrielle EYETS 2016/17
Released
Exceptional Authorisation: TE-VSC activities in IT areas during EYETS 2016-17
Released
Exceptional Authorisation: Installation of LHCb Forward Shower Counters - EYETS 2016-17
Released
Exceptional Authorisation: Campagne de cablage Zone Triplet LSS2R - EYETS 2016/17
Released
Exceptional Authorisation: EP-ADO, EN-EA-EC Installation of shielding for the ALFA experiment EYETS
2016/17
Released
Exceptional Authorisation: EN-ACE-SU: Radial measurement in IR1 and IR5 (EYETS 2016/17)
Released
Exceptional Authorisation (IT): BE-ICS-AS etalonnage ODH EYETS 16/17
Released
Exceptional Authorisation: EN-ACE-CL: Verification de plans en zones IT (EYETS 2016/17)
Released
Exceptional authorisation: SMB-SE-FAS :Installation of Crack Meters in RB 26, EYETS 2016/17
Released
Exceptional Authorisation: EN-ACE-SU: Campagne de mesure sans ventilation en arc 78 (EYETS 2016/17) Released
Exceptional Authorisation: HSE-RP-AS Etalonnage dans zones IT (EYETS 2016/17)
Released
Exceptional Authorisation: EN-MEF-MM Radiographie Point 5 EYETS 2016/17
Released
Exceptional Authorisation: EP-UHC, Removal/Installation of ECAL in RP84 (IT 8L) EYETS2016-17
Released
Exceptional Authorisation: BE-ASR-SU Inspection of Sealing (All ITs) EYETS2016-17
Released
Exceptional Authorisation: EN-MEF-MM Radio-Tomographie Sector 8-1 YETS 2016/17
Released
Exceptional Authorisation: EN-ACE-SU: Travaux de Maintenance dans les ITs 1,2,5 et 8 (EYETS 2016/17) Released
Exceptional Authorisation: EN-EL Fibre optique RA 47 EYETS2016/17
Released
Exceptional Authorisation: BE-ICS réparation détection incendie RA67 EYETS2016/17
Released
Exceptional Authorisation: HSE cartographie RP pour ITs point 5 EYETS2016/17
Released
Exceptional Authorisation: EN-ACE-SU: Remplacement fil IR1L (EYETS 2016/17)
Released
Exceptional Authorisation: HSE cartographie RP pour ITs point 1L EYETS2016/17
Released
Work Frame Authorisation: EN-EL-CF Pose de cables dans Arc
Released
Exceptional Authorisation: BE-ICS-AS Replacement of ODH flash. Request for Activities in the Inner Triplet
Areas at T < 80 K
Released
Exceptional Authorisation: EN-ACE-CL Photographies for layout database
Under Approval
Exceptional Authorisation: SMB Request for Activities in the Inner Triplet Areas at T < 80 K for cleaning
activities
Under Approval
Exceptional Authorisation: EN-ACE-SU Photographies in the Inner Triplet
Under Approval
machine
Schedule
Exceptional Authorisation: EN-STI-ECELHC
Test of
Robot in IT1
at T < 80 Kfor LHC EYETS EDMS 1768162;
Under Approval
INDICO 624874
9
LHC-EYETS: electrical constraints
AUG TEST
Point
Day
Point
Day
LHC1 + ATLAS
6th January
BA1
13th February
LHC18 + SM18
10th January
BA2
15th February
LHC2 + ALICE
16th March
BA3
16th February
LHC3 + PM32
16th January
BA4 + CNGS
28th February
LHC4
8th March
BA5
1st March
LHC5 + CMS
5th January
BA6
20th January
LHC6
9th March
BA7
10th January
LHC7
7th March
LHC8
27th February
PS + PSB
14th & 15th January
Prevessin
4th March
BA80
4th April
Meyrin + Adm.
4th January
BA81
5th April
Meyrin W. + ISR
28th January
BA82 + 85
6th April
COMPLETED for LHC
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
10
LHC-EYETS: Maintenance
CV Maintenance
Point
Weeks
Start
Finish
LHC1
50 – 51 – 1 – 2
15th December
11th January
LHC2
9-10-11
27th February
19th March
LHC3
8 10 12 & 14
20th March
24th March + 4th April
LHC4
2–3–4
10th January
27th January
LHC5
49 – 50 – 51 – 1
5th December
6th January
LHC6
6–7–8
6th February
24th February
LHC7
9
27th February
3rd March
LHC8
3–4–5
16th January
3rd February
Cryo Maintenance
Point
Weeks
Start
Finish
LHC1
2–3–4
11th January
24th January
LHC2
11-12
13th March
24th March
LHC4
9 – 10
27th February
10th March
LHC6
6–7–8–9
6th February
3rd March
LHC8
7–8
13th February
24th February
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
11
LHC-EYETS: constraints W12 and W13
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
12
LHC-EYETS: constraints W12 and W13
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
13
LHC-EYETS: constraints W12 and W13
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
14
Safety aspects: VIC follow up
Activity
Group
Location
Status @ 20th February
Cabling & Fibre
EN-EL-FC
Gael Girardot
Antonio Gonzales
Adrian Grinand
LSS8
LSS5R
LSS2R
LSS6
LSS7
UJ33
Arc 6-7 (for TE-MSC thermoswitch)
P4 (UA/RA)
UL557 + TZ76
VIC Approved
VIC Approved
VIC Approved
VIC Approved
VIC not needed
VIC Approved
VIC Approved
VIC Approved
VIC Approved
ALFA shielding installation
EP- Alfa
Mickael Lazzaroni
LSS1
VIC Approved
UD62 and UD68 activities
EN-STI
UD62 & UD68
DIMR completed
ODH flash in UJ14
BE-ICS
UJ14 (ITs)
VIC not needed
RE42 water cleaning
SMB-SE
RE42
VIC Approved
Cabling for Radmon
EN-EL
RR73 / 77
VIC Approved
Curage des réseaux de drainage
SMB
UJ33
VIC Approved
Cleaning
SMB
UA23
VIC to be organised
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
15
Lineal schedule Co-activity P1
-
LSS1L
o W11-12-13  AFP activities
o W14  ALFA shielding installation  NO co-activity (3-4th April)
-
LSS1R
o W 12 à AFP activities
o W13  ALFA shielding installation  NO co-activity (27-28th Mars)
o W13-until the end of EYETS  NO ACCESS  ElQA test 12
-
Arc12
o W13-14  NO ACCESS  ELQA test sector 12 dates TBC
o From W15 NO ACCESS  Powering tests
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
16
LSS1L
Personal ODH MANDATORY
in the arc
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
17
P1 – LSS1R
Personal ODH MANDATORY
in the arc
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
18
Point 18 – Arc 1.2
Personal ODH MANDATORY
in the arc
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
19
LSS2L – P2
Personal ODH MANDATORY
in the arc
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
20
LSS2R - Arc 2.3
Personal ODH MANDATORY
in the arc
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
21
Point 3
Personal ODH MANDATORY
in the arc
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
22
Arc 3.4 - LSS4L
Personal ODH MANDATORY
in the arc
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
23
Point 4
Personal ODH MANDATORY
in the arc
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
24
LSS4R – Arc 4.5
Personal ODH MANDATORY
in the arc
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
25
LSS5L
Personal ODH MANDATORY
in the arc
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
26
P5 – LSS5R
Personal ODH MANDATORY
in the arc
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
27
Arc 5.6
Personal ODH MANDATORY
in the arc
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
28
LSS6L – P6 - LSS6R
Personal ODH MANDATORY
in the arc
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
29
LSS7L – P7
Personal ODH MANDATORY
in the arc
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
30
LSS7R
Personal ODH MANDATORY
in the arc
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
31
Arc 7.8
Personal ODH MANDATORY
in the arc
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
32
LSS8L
Personal ODH MANDATORY
in the arc
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
33
P8 - LSS8R
Personal ODH MANDATORY
in the arc
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
34
Arc 8.1
Personal ODH MANDATORY
in the arc
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
35
Next Coordination meetings
Week 13  28th March @9h00, room 30-7-010
Week 14  4th April @9h00, room 30-7-010
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
36
LHC-EYETS: linear schedule Baseline
38
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
LHC-EYETS: Constraints
39
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
IT intervention on analogic phones
• The intervention is scheduled 5th April.
• The intervention starts at 20h00 and should finish by midnight.
• Upgrade the 4 nodes sequentially, so not all sites are down at the
same time. However, all analogue and IP phones will be affected at
a particular time during the intervention (red phones and lifts
included).
• The mobile phones, the fire brigade and the CCC are redundant so
they will be able to call/receive calls at anytime.
LHC machine Schedule for LHC EYETS EDMS 1768162;
INDICO 624874
40