PRE - CONSTRUCTION HEALTH AND SAFETY INFORMATION PROJECT: Installation of High Voltage Electric Fencing & Close Circuit Television LOCATION: Clipstone Colliery Site CLIENT: CLIENT REF: Coal Authority CA18/2388 DATE: January 2013 Pre-Construction Health and Safety Information – Clipstone Colliery Electric Fencing INDEX 1.0 DESCRIPTION OF THE PROJECT 1.1 1.2 1.3 1.3.1 1.3.2 1.3.3 Project description and Programme Details Details of Client, CDM Co-ordinator & Other Consultants Extent & Location of Existing Records & Plans Existing Drawings Existing Health and Safety Files Other Drawings and Reports 2.0 CLIENT’S CONSIDERATIONS & MANAGEMENT REQUIREMENTS 2.1 2.1.1 2.1.2 2.1.3 2.1.4 2.1.5 2.1.6 2.1.7 2.1.8 2.2 2.2.1 2.2.2 2.2.3 2.2.4 2.2.5 2.2.6 2.2.7 Planning For and Managing Construction Work Including Safety Goals for the Project Structure and Organisation Safety Goals Arrangements for Monitoring and Review Communication and Liaison Between Client and Others Unforeseen Eventualities Communication of Continuing Health & Safety Issues Security Requirements Welfare Facilities and Compound Health & Safety Requirements of Client’s Employees / Others Involved in the Project Site Hoarding Requirements Client Permits Fire Precautions Emergency Procedures and Means of Escape Prohibitive / Restricted Areas and Authorisation Requirements Client’s Designated Confined Spaces Smoking and Parking Restrictions 3.0 ENVIRONMENTAL RESTRICTIONS & EXISTING ON SITE RISKS 3.1 3.1.1 3.1.2 3.1.3 3.1.4 3.1.5 3.1.6 3.1.7 3.1.8 3.1.9 Safety Hazards Boundaries and Access Restrictions on Deliveries, Waste Collection or Storage Adjacent land Use Existing Storage of Hazardous Materials Location of Existing Services Ground Conditions, Underground Structures or Water Courses Existing Structures – Stability, Structural Form, Fragile or Hazardous Materials Previous Structural Modifications Including Weakening or Strengthening Fire Damage, Ground Shrinkage, Movement or Poor Maintenance Affecting the Structure Difficulties Relating to Plant and Equipment on the Premises Health and Safety Information Contained in Earlier Design or ‘As Built’ Drawings Health Hazards Asbestos Existing Storage of Hazardous Materials Contaminated Land Existing Structures Containing Hazardous Materials Health Risks Arising from Client’s Activities Gas 3.1.10 3.1.11 3.2 3.2.1 3.2.2 3.2.3 3.2.4 3.2.5 3.2.6 Pre-Construction Health and Safety Information – Clipstone Colliery Electric Fencing 4.0 SIGNIFICANT DESIGN AND CONSTRUCTION HAZARDS 4.1 4.2 4.2.1 4.2.2 4.2.3 4.3 4.3.1 4.3.1.1 4.3.1.2 4.3.1.3 4.3.2 4.3.2.1 4.3.2.2 4.3.2.3 4.3.3 4.3.3.1 4.3.3.2 4.3.3.3 4.3.3.4 4.3.3.5 4.3.3.6 4.3.3.7 4.3.3.8 4.3.3.9 4.3.4 4.3.4.1 4.4 4.4.1 Design Assumptions and Control Measures Arrangements for Coordination of Ongoing Design Work Changes to Design Principles Ongoing Design Items Contractors Design Items Information on Significant Risks Identified During Design Position and Design to Minimise Risks from Site Hazards Overhead/Underground Services Traffic management On/Around the Site Contaminated Ground Health Hazards Hazardous Substances Manual Handling Waterborne Diseases Safety Hazards Temporary Works/Stability of Structures Excavations Plant and Equipment Lifting Operations Electrical & Mechanical Works Fragile Materials Confined Spaces Tree Felling Work at Heights Other Hazards Protection of the Public Construction Materials requiring Particular Precautions Material Safety Data Sheets 5.0 ENVIRONMENTAL IMPLICATIONS 5.1 5.2 5.3 5.4 Noise and Vibration Contamination of the Ground and Watercourses Noise, Mud, Dust and Vibrations Site Waste Management Plan 6.0 THE HEALTH AND SAFETY FILE 7.0 THE CONSTRUCTION PHASE HEALTH AND SAFETY PLAN Appendices The following Appendices are provided as separate attachments in the eTender System: Designer’s Risk Assessment Site Waste Management Plan Pre-Construction Health and Safety Information – Clipstone Colliery Electric Fencing 1.0 1.1 DESCRIPTION OF THE PROJECT Project Description and Programme Details The project involves the construction of an electric fence around the perimeter of the existing listed headstocks and listed buildings to prevent unauthorised access. The works comprise of: Take off palisade uprights to existing fence and barbed wire Extend vertical columns Attach fine weld mesh fence to outer face of posts Refix vertical palisades to fencing Inside of fencing apply electric fencing. These wires have 150mm spacing with the top strand being 3.4m high Test, commission and provide live system Trench for electric supply to fence & cameras Installation of CCTV and associated equipment Programme The works have been scheduled to commence March 2013 and are envisaged to last for approximately 8 to 12 weeks. Pre-Construction Health and Safety Information – Clipstone Colliery Electric Fencing 1.2 Details of Client, CDM Co-ordinator and Other Consultants Client: The Coal Authority 200 Lichfield Lane Mansfield Nottinghamshire NG18 4RG Tel: Contact: 01623 637378 Phil Brandreth Contract Engineer: JMC Engineering (UK) Ltd P.O.Box 36 Alfreton Derbyshire DE55 1NG Tel: Fax: Contact: 01773 718810 Designer: JMC Engineering (UK) Ltd P.O.Box 36 Alfreton Derbyshire DE55 1NG Tel: Fax: Contact: 01773 810510 01773 580805 Mr Terry Hastelow or Bill Denton CDM Co-ordinator: The Coal Authority 200 Lichfield Lane Mansfield Nottinghamshire NG18 4RG Tel: Fax: Contact: 01623 637223 01623 637398 Ian Smith Principal Contractor TBC Local Health & Safety Executive Office: Health and Safety Executive, City Gate West Level 6 (First Floor) Toll House Hill Nottingham NG1 5AT Tel: Fax: 0115 971 2800 0115 971 2802 1.3 Extent and Location of Existing Records and Plans 1.3.1 Existing Drawings Mr Ian Rimmer Drawings relevant to the project are available by contacting Phil Brandreth on 01636 637378. 1.3.2 Existing Health and Safety Files The Client has a Health and Safety File entitled ‘Demolition of Clipstone Colliery Surface Structures – Health and Safety File’ March 2009, and will be made available to the Principal Contractor before the Contract commences. 1.3.3 Other Drawings and Reports All information thought to be relevant to the site is contained in the Health and Safety File mentioned above (including all known service drawings). Contact Ian Rimmer on 01773 810510 / 07887 983369. Pre-Construction Health and Safety Information – Clipstone Colliery Electric Fencing 2.0 CLIENT’S CONSIDERATIONS & MANAGEMENT REQUIREMENTS 2.1 Planning For and Managing Construction Work Including Safety Goals for the Project 2.1.1 Structure and Organisation The Client will provide details of the management structure and organisation for this project at the pre-start meeting. However, the Principal Contractor shall provide a diagram in the Construction Phase Health and Safety Plan to show their intended management structure and organisation for the project. 2.1.2 Safety Goals The safety goals for this project are to protect the health, safety and welfare of all personnel working on this project and others who may be affected by their activities. To identify the measures needed to eliminate hazards, or if not possible to do so, to reduce and control the risks associated with the installation of the electric fence and close circuit television (CCTV). The Principal Contractor is required to implement preventive and protective measures to achieve satisfactory completion of the works with ZERO accidents and maintain compliance with all applicable health and safety legislation. Particular reference must be given to the requirements of the Construction (Design and Management) Regulations 2007. 2.1.3 Arrangements for Monitoring and Review The Principal Contractor shall insert into the Construction Phase Health and Safety Plan their arrangements for monitoring and reviewing performance measured against the Health and Safety Goals. 2.1.4 Communication and Liaison between Client and Others The Principal Contractor shall ensure that whilst executing the works throughout the period of this contract, provisions are in place for allowing access to site for Clients staff and their nominated representatives, Health and Safety Executive, Local Authority or Environment Agency staff. 2.1.5 Unforeseen Eventualities The Principal Contractor shall submit to the CDM Co-ordinator details of any unforeseen eventualities encountered during the project execution resulting in substantial design changes or which might affect resources, immediately they are encountered. This will enable consideration to be made of the health and safety implications and effect on resources. 2.1.6 Communication of Continuing Health and Safety Issues Following issue of this Pre-Construction Health and Safety Information, any health and safety issues arising from: Design changes made by the Client or Original Designers Ongoing design by the Original Designers or by any other Designers and Design changes made by the Principal Contractor’s or Contractors Designers That the CDM Co-ordinator has been made aware of will be notified to the Principal Contractor by the CDM Co-ordinator. Pre-Construction Health and Safety Information – Clipstone Colliery Electric Fencing 2.1.7 Security Requirements The headstocks and listed buildings on the site have been secured and access routes/entry points to the site blocked off. Access to the site shall be only via the main gate on Mansfield Road. It is particularly important that the access gate to the listed buildings compound is kept securely locked during non working hours. Theft and anti social behaviour has been an ongoing problem at this site for the last two years. The Principal Contractor shall secure any site compound he installs by using temporary fencing such as 1.8m high Heras panels, double clipped with concrete pads and the placing of suitable warning signs. Fencing to a similar standard may be acceptable following prior agreement with the Client. Attention is drawn to the fact that acts of trespass, vandalism and attempted theft can be expected during the project duration. This factor, and the securing and immobilisation of plant and equipment must be considered when formulating security measures. 2.1.8 Welfare Facilities and Compound The Principal Contractor must ensure that adequate welfare facilities are provided for the works in accordance with the Construction (Design & Management) Regulations 2007. Welfare facilities are to be located within the defined site boundary. The Client has no welfare facilities on site. 2.2 Health & Safety Requirements of Client’s Employees / Others Involved in the Project 2.2.1 Site Hoarding Requirements The access gate will be securely locked when the Principal Contractor is not on site. The Principal Contractor needs to secure his immediate work area around the headstocks / listed buildings. 2.2.2 Client Permits The Principal Contractor will be expected to contact the statutory provider for any works required to the services. 2.2.3 Fire Precautions The Principal Contractor shall introduce fire procedures and precautions in accordance with the Regulatory Reform (Fire Safety) Order and Health and Safety Executives Guidance HSG 168 Fire Safety in Construction. Arrangements should include: 2.2.4 An assessment of the risk of fire Provision of suitable/sufficient fire points and trained personnel to act in the event of a fire Introduction of fire assembly points and specifying the means of raising the alarm including any neighbours that may be affected Adoption of simple fire prevention measures including regularly removing all combustible waste and litter to appropriate storage areas Identifying and signing fire exit routes and maintaining clear access at all times for site personnel and emergency vehicles Emergency Procedures & Means of Escape The Principal Contractor shall include details of emergency procedures covering all incidents within the Construction Phase Health and Safety Plan. Pre-Construction Health and Safety Information – Clipstone Colliery Electric Fencing The provision of adequate first aid arrangements and provision of trained first aiders shall be in accordance with the Health and Safety (First Aid) Regulations 1981. The Principal Contractor must record and investigate all accidents/incidents that occur on site and report them to the Client. Any incidents that are classified within the Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 1995 (RIDDOR) or environmental incident must be reported to the appropriate enforcing authority. The nearest Hospital with A&E facilities is: Kings Mill Hospital, Mansfield Road, Sutton in Ashfield, Nottinghamshire. Telephone: 01623 622515 The Principal Contractor shall document the emergency arrangements to be adopted and include: The route to the nearest hospital with an Accident and Emergency Unit The location of first aid equipment and the names of trained first aid personnel The location of spill kits and other arrangements for dealing with environmental incidents 2.2.5 Prohibitive / Restricted Areas & Authorisation Requirements The Principal Contractor shall only access previously agreed areas i.e. the site. Under no circumstances shall the Principal Contractor enter the headstocks or associated listed buildings at the base of the structures. The buildings are in a state of dangerous disrepair. 2.2.6 Client’s Designated Confined Spaces There are no Client specified confined spaces. 2.2.7 Smoking and Parking Restrictions At no time should operatives’ parked vehicles cause problems to the local residents or businesses. Vehicles are to be parked within the confines of the site. Smoking is not allowed on site or in the welfare facilities. Smoking will only be allowed in the Principal Contractor’s designated ‘smoking’ areas. Pre-Construction Health and Safety Information – Clipstone Colliery Electric Fencing 3.0 ENVIRONMENTAL RESTRICTIONS & EXISTING ON SITE RISKS 3.1 Safety Hazards 3.1.1 Boundaries and Access Welbeck Estates own the freehold for the land upon which the former Colliery is situated and the Coal Authority owns the structures, except for the railway lines which are owned by UK Coal. Access to the site can be gained via heading south from Ollerton along the A614 towards Nottingham, turning right onto the B6030 to Clipstone/Mansfield. Upon entering Clipstone go straight on at the roundabout, along Mansfield Road and the site is on the left just before entering Clipstone Village. See Site Location Plan. The owners of the domestic properties adjacent to the entrance road have a right of access through the entrance road to the rear of their properties, which must be maintained throughout the project. The Client shall secure the site boundaries around the perimeter of the site and restrict access to site personnel and authorised persons only. The Principal Contractor is to note that there is a history of anti social behaviour and unauthorised access to the site, and must therefore ensure the working area is secured appropriately. 3.1.2 Restriction on Deliveries, Waste Collection or Storage The site is located within a residential area, therefore delivery drivers and operatives must adhere to the speed limits and drive with the utmost care and attention at all times. The village of Clipstone is under a 30mph speed restriction and all wagons/vehicles should ensure they adhere to the limits when accessing and leaving site. The Principal Contractor should avoid deliveries to site during peak/busy periods if at all possible which are identified as 8.00am to 9.00am and 4.30pm to 5.30pm The Principal Contractor is to be aware that the A6030 is a main school route. There are three local schools in the area. Samuel Barlow Primary and Nursery School Church Road Clipstone Nottinghamshire NG21 9DF Vicar Water Nursery 123 Mansfield Road Clipstone Nottinghamshire NG21 9AA John T Rice Infant School Braemar Road Forest Town Mansfield Nottinghamshire NG19 0LL Pre-Construction Health and Safety Information – Clipstone Colliery Electric Fencing 3.1.3 Garibaldi College Garibaldi Road Forest Town Mansfield Nottinghamshire NG19 0JX Adjacent Land Use There are currently no work activities being carried out on site. A large volume of traffic passes the front of the site along Mansfield Road. An access track/cycle track passes along the southern boundary from Vicar Water Country Park. Residential properties are situated along the Mansfield Road and to the east of the site. There is a small Industrial Estate to the West of the site. The Principal Contractor must specify arrangements to protect the public, adjacent commercial / residential properties. The adjacent land use comprises of the following: North: Mansfield Road and adjacent footpath which runs parallel to the site. Some houses and farmland are situated to the eastern end of the northern boundary. East: An access track to fields and farmland / Baulker Lane Slaughter House / Greendale Housing Estate South: Farmland, settling ponds and restored and filled settling ponds. National cycle track leading from / to Vicar Water. West: Commercial properties well fenced off from the former Colliery yard. The company Fourtrack Ltd are immediately adjacent to the working area. 3.1.4 Existing Storage of Hazardous Materials No known hazardous materials are stored on site. However, within the listed buildings and headstocks there are numerous hazards such as glazing, battery acids and PCBs. No access is allowed into this area. 3.1.5 Location of Existing Services There are no existing services on the site to be worked. 3.1.6 Ground Conditions, Underground Structures or Watercourses Except for the access road onto the site which is metalled, the ground conditions range from firm to soft subsoil, comprising coarse and fine material from the demolition process, imported clay materials, with some minestone and mainly underlying sand. The only watercourse is Vicar Water some 800m to the South of the site. 3.1.7 Existing Structures – Stability, Structural Form, Fragile or Hazardous Materials Existing structures on the site are the listed Headstocks and buildings which as detailed in section 1.1 of this document. These structures contain fragile and hazardous materials. 3.1.8 Previous Structural Modifications Including Weakening or Strengthening Pre-Construction Health and Safety Information – Clipstone Colliery Electric Fencing None specified. 3.1.9 Fire Damage, Ground Shrinkage, Movement or Poor Maintenance Affecting Structure None specified. 3.1.10 Difficulties Relating to Plant & Equipment on the Premises None specified. 3.1.11 Health and Safety Information Contained in Earlier Design or ‘As Built’ Drawings None specified 3.2 Health Hazards 3.2.1 Asbestos There is no asbestos material in the designated work area. There is asbestos within the listed buildings and headstocks but there is no authorised access to these areas. 3.2.2 Existing Storage of Hazardous Materials None specified 3.2.3 Contaminated Land There are no known contaminated land issues identified within the defined site area. 3.2.4 Existing Structures Containing Hazardous Materials All structures have been removed apart from the ones listed in Section 1.1 which will be isolated from the project by an exclusion zone. 3.2.5 Health Risks Arising from Client’s Activities The site is unoccupied therefore there are no risks from Client activities. 3.2.6 Gas None specified. Pre-Construction Health and Safety Information – Clipstone Colliery Electric Fencing 4.0 SIGNIFICANT DESIGN AND CONSTRUCTION HAZARDS 4.1 Design Assumptions and Control Measures The design of the works has involved utilisation of the existing palisade fencing. 4.2 Arrangements for Co-ordination of Ongoing Design Work 4.2.1 Changes to Design Principles The Client/Designer shall submit to the Principal Contractor and CDM Co-ordinator during the project execution, any major changes to the design requirements made during the construction phase. These should be submitted in sufficient time to allow the health and safety implications and the affect on resources to be considered prior to commencement of the work. The Designers’ Risk Assessments are provided as an attachment. 4.2.2 Ongoing Design Items The Designers shall submit to the CDM Co-ordinator, during the project execution, all design information, specification, drawings, Designers health and safety issues and other information relevant to any on going design element produced by the original designers or new designers during the construction phase. These shall be submitted in sufficient time to allow the health and safety implications and affect on resources to be considered prior to the commencement of the work element on site. 4.2.3 Contractors Design Items The Principal Contractor will not be responsible for the design of the works. The Principal Contractor shall submit to the CDM Co-ordinator during the project execution all design information, specification, drawings, Designers health and safety issues and other information relevant to any design element produced by the contractor or sub contractor. These shall be submitted in sufficient time to allow the health and safety implications and affect on resources to be considered prior to the commencement of the work element on site. The Principal Contractor is reminded that where the structure is to be used as a workplace, the design must take into account the relevant requirements of the Workplace (Health, Safety & Welfare) Regulations 1992. 4.3 Information on Significant Risks Identified During Design The main risks identified during the design stage are: Working from heights. Establishing a safe system of work to erect the high voltage fencing at height Electricity. Provide safe systems of work/permit to work system for laying cable supply and energising the fence Traffic Management. Interaction with the vehicle movements involved with the importation of soil to the site (Please refer to item 4.3.2.1 of this document for further information). The Pre-Construction Health and Safety Information – Clipstone Colliery Electric Fencing 4.3.1 4.3.1.1 Principal Contractor shall liaise with Ian Rimmer to establish an appropriate traffic management plan. Manual Handling. Lifting and fixing of weldmesh fence panels and stakes, CCTV columns etc Working with cementitious materials Grinding operations Position and Design to Minimise Risks from Site Hazards Overhead/Underground Services There are no known services. However the Principal Contractor is required to undertake any checks and confirm the presence or not of any existing site services using appropriate locating and avoidance tools and carryout the works in accordance with the requirements of HSE guidance note HS (G) 47 Avoiding danger from underground services. 4.3.1.2 Traffic Management On/Around the Site The Principal Contractor shall use the access routes identified within section 3.1.1 and put arrangements in place to minimise the impact of vehicle movements on and off the site and to ensure that access roads are free from mud and debris. The Principal Contractor shall load/unload all vehicles within the site boundary. The Principal Contractor shall specify within a site traffic management plan their arrangements controlling all vehicles movements and segregation of vehicles from site personnel and others. vehicles shall be parked within the designated site compound and all reversing vehicles must accompanied by a banksman. The Principal Contractor shall note that imported soils will delivered and spread on the site during theses works. for All be be The village of Clipstone is under a 30mph speed restriction and all wagons/vehicles should ensure they adhere to the limits when accessing and leaving site. The Principal Contractor should avoid deliveries to site during peak/busy periods if at all possible which are identified as 8.00am to 9.00am and 4.30pm to 5.30pm The Principal Contractor is to be aware that the A6030 is a main school route. School locations are as detailed in section 3.1.2. The Principal Contractor should refer to HSG144 - Safe use of vehicles on construction sites. 4.3.1.3 Contaminated Ground There are no known areas of contaminated ground likely to affect the works. However, the Principal Contractor shall specify arrangements for preventing and controlling any contamination of the ground or pollution of any watercourses during the construction works by fuels, oils, materials storage, cleaning of plant and equipment, waste materials or human waste. The Principal Contractor shall ensure that all wastes are managed on site and delivered or removed by a Registered Waste Contractor to a licensed site authorised to receive the waste. A copy of the waste registration certificate shall be provided within the Construction Health and Safety Plan. Any fuels, oils or other chemicals that are to be stored on site shall be contained within an impervious bund/double skinned tanks. 4.3.2 Health Hazards Pre-Construction Health and Safety Information – Clipstone Colliery Electric Fencing 4.3.2.1 Hazardous Substances None specified. 4.3.2.2 Manual Handling Consideration of lifting large panels of weld mesh fencing and uprights for the fencing. 4.3.2.3 Waterborne Diseases Any works in and around foul water systems has the potential to create a possible health risk to site personnel from waterborne diseases e.g. Leptospirosis (Weil’s disease) which is attributable to rat urine. The Principal Contractor must specify arrangements for the prevention of persons contracting waterborne diseases. Although no foul system is operational, there is the potential for Leptospirosis in the waste ground and the Principal Contractor should have the appropriate control measures and welfare facilities in place. 4.3.3 Safety Hazards The following safety issues have been identified and the Principal Contractor must detail within Method Statements the prevention and control measures to be adopted to ensure the safety of site personnel and others during the project. 4.3.3.1 Procedures for the induction of all site personnel and visitors Procedures for securing the site and ensuring no unauthorised persons enter the site Procedures for ensuring that no materials, plant or equipment are left unattended or stored where unauthorised personnel can access them Safety helmet, safety footwear and high visibility clothing to be worn at all times Procedures for plant, delivery access and traffic management A maximum site speed limit of 10 mph Smoking is only allowed in designated areas No alcohol or illegal drugs Fire procedures No fires or burning of materials allowed on site No access into the existing headstock or buildings area. Temporary Works/Stability of Structures No temporary works are envisaged. 4.3.3.2 Excavations A trench will be dug from the main supply board to supply point to feed the electric fence. Depth is envisaged to be less than 1.0m with no access required. There should be consideration of HSE Guidance HSG 185 Health and Safety in excavations. 4.3.3.3 Plant and Equipment The Principal Contractor must provide details of their arrangements to maintain safe delivery, installation, operation and maintenance of any items used for both owned or hired plant and equipment. Evidence of training achievements must be retained on site for all operators of plant and equipment. All plant and equipment used on site must be in accordance with the Provision and Use of Work Equipment Regulations 1998. Pre-Construction Health and Safety Information – Clipstone Colliery Electric Fencing Use of plant and equipment on steep gradients should not be a consideration in this instance. If so, detailed information on safe systems of work need to be provided with appropriate control measures adopted. 4.3.3.4 Lifting Operations An appointed person and lifting plan is required for any lifting operations. Full recognisance of LOLER is required. Consideration of weights when unloading fencing from vehicles. 4.3.3.5 Electrical & Mechanical Works None specified. 4.3.3.6 Fragile Materials None specified. 4.3.3.7 Confined Spaces There are no Client designated confined spaces. 4.3.3.8 Tree Felling None envisaged. 4.3.3.9 Work at Heights When the 3.4m electric fence and the camera columns are erected, there will need to be access at high level. Provide a safe system of work. 4.3.4 Other Hazards 4.3.4.1 Protection of the Public The Principal Contractor must detail within Method Statements, arrangements for preventing unauthorised access to site and the control measures to be established to safeguard others in accordance with HSG 151 Protecting the Public – Your Next Move. Particular attention must be paid in properly fencing the site to prevent unauthorised access. 4.4 Construction Materials Requiring Particular Precautions Not Applicable. 4.4.1 Material Safety Data Sheets The Principal Contractor is required to provide to the CDM Co-ordinator material safety data sheets for any hazardous substances used during the works for inclusion within the health and safety file. The only considerations are likely to be fuels and lubricants used in the plant/machinery on site. Pre-Construction Health and Safety Information – Clipstone Colliery Electric Fencing 5.0 ENVIRONMENTAL IMPLICATIONS 5.1 Noise and Vibration The work operations will generate noise and vibrations, which are likely to affect site personnel and local residents. Therefore, the Principal Contractor must specify their arrangements to prevent or control any exposure to high levels of noise and vibration. To minimise the effects of noise from the works on the surrounding area, work must not take place wherever possible outside of the following time periods. Monday to Friday Saturday - 08:00 to 18:00 08:00 to 12.00 The Principal Contractor will be required to carry out works which have the potential to generate high levels of noise and vibration, therefore, the Principal Contractor must specify their arrangements to prevent or control any exposure to high levels of noise and vibration. Compliance with the Control of Noise at Work Regulations 2005 and Control of Vibration at Work Regulations 2005 must be maintained. 5.2 Contamination of the Ground and Watercourses The Principal Contractor will be required during the works to implement measures to prevent the contamination of the ground or watercourses by fuels, plant, equipment, materials or human waste. The Principal Contractor shall ensure that all waste is managed on site and removed by a Registered Waste Contractor to a licensed site authorised to receive the waste. Any fuels, oils or other chemicals that are to be stored on site shall be contained within an impervious bund. The Principal Contractor shall ensure that all waste is managed on site and removed by a Registered Waste Contractor to a licensed site authorised to receive the waste. Any fuels, oils or other chemicals that are to be stored on site shall be contained within an impervious bund. 5.3 Noise, Mud, Dust and Vibrations The Principal Contractor will be required to implement measures to minimise and control the creation of noise, mud, dust and vibrations. 5.4 Site Waste Management Plan The Site Waste Management Plan (SWMP) is a relevantly new piece of Legislation which puts legal requirements for construction and demolition works in the UK to draw up and enforce SWMP’s. The plan details the types of waste that will be produced from the works, and details how this will be reused, recycled or disposed off. The aim of the SWMP is to improve resource efficiency within the construction industry in order to reduce the amount of waste produced and recover as much of the remainder as possible. As Client, the Coal Authority is responsible for initially developing the SWMP for the Principal Contractor to develop once on site. The Site Waste Management Plan is provided as an attachment. Pre-Construction Health and Safety Information – Clipstone Colliery Electric Fencing 6.0 THE HEALTH AND SAFETY FILE The requirements to compile a Health and Safety File are specified within the Construction (Design & Management) Regulations 2007. The Health and Safety File is essential to those doing the work as it alerts them to risks and helps them decide how to work safely by containing relevant information that will assist any future construction work including, cleaning, maintenance, alterations, refurbishment and demolition works at any time after the completion of the project. Information required to be submitted to compile the Health and Safety File includes: SECTION 1 - GENERAL Introduction which includes a brief description of the work carried out. Location, including OS co-ordinates. Details of Principal Contractor and CDM Co-ordinator. Planning criteria, requirements, restrictions, SSSI’s, building regulation approval. Date of construction – Start to Completion. Planning Permission. Building Regulations Approval. Warranties – Piling ANSUC – Products Used (cookers, boilers, etc) – Electrical Test Certificate – NICEIC qualified electrician. – Mechanical – Corgi Registered SECTION 2 – RESIDUAL HAZARDS Any residual hazards which may remain and how they have been dealt with, e.g. Mine shafts, contaminated land, buried services etc. SECTION 3 – KEY STRUCTURAL PRINCIPLES Overall scheme design Structural engineer calculations. Overall design principles. SECTION 4 – MATERIAL HAZARDS Hazardous materials used (for e.g. Pesticides, special coatings) materials with appropriate COSHH Data Sheets. SECTION 5 – REMOVAL / DISMANTLING OF ITEMS IN THE CONSTRUCTION Information regarding the removal or dismantling of any item in the projects construction. SECTION 6 – EQUIPMENT FOR CLEANING AND MAINTENANCE Arrangements for access at heights. Maintenance regimes. Manufacturer’s recommendations on products/servicing. SECTION 7 – UTILITIES AND SERVICES Pre-Construction Health and Safety Information – Clipstone Colliery Electric Fencing The nature, location and markings of services SECTION 8 – RECORD DRAWINGS Hard copy and electronic copy on CD-ROM in Adobe PDF and AutoCAD DWG format. List of drawings provided. (Drawings should have a logical list) Record drawings to include: - As built drawings if they differ from the originals. - Specification used in the project. Electrical/Mechanical As built drawings. SECTION 9 – PHOTOGRAPHIC EVIDENCE Photographic evidence at key stages throughout the Project or key elements of the Project Other items deemed to be useful Underground services This information must be passed to the CDM Co-ordinator, by the relevant parties as the design and construction work proceeds to enable the file to be developed throughout the project to enable delivery of the file to the Client as soon as is reasonably practicable following completion of the works. Pre-Construction Health and Safety Information – Clipstone Colliery Electric Fencing 7.0 THE CONSTRUCTION PHASE HEALTH AND SAFETY PLAN The Principal Contractor is required by the Construction (Design & Management) Regulations to develop the Pre-Construction Health and Safety Information and provide a suitably developed Construction Phase health and Safety Plan before the Client can allow the Principal Contractor to commence work. The Principal Contractor should ensure that the content of the Construction Phase Health and Safety Plan adequately addresses the health and safety concerns identified in this Pre-Construction Health and Safety Information and those headings listed in Appendix 3 (pg 105) of L144 “Managing Health and Safety in Construction.” Pre-Construction Health and Safety Information – Clipstone Colliery Electric Fencing
© Copyright 2025 Paperzz