P3K Palomar Infrastructure Balance Adaptations Larger Cass weight load from instrument & electronics Electrical Service Upgrades Higher electric service requirements at Cass, Computer Room and AO Lab Cooling of Cass Electronic Racks Removal of ~6 kW of heat from below primary mirror J.Zolkower P3K 9-22-10 P3KInfrastructure InfrastructureI&T – July 19, 2010 1 Cass Mounted System Weights Current AO Cass System Weights AO Bench AO Rack 1 AO Rack 2 Cables AO System Total 3820 lbs 415 lbs 345 lbs 85 lbs 4665 lbs With Heaviest AO Instrument P1640 P1640 elec. 340 lbs 400 lbs Total w/ Instrument 5405 lbs P3K AO Cass System Weights P3K Bench 3900 lb P3K DM rack 1 525 lb P3K DM rack 2 525 lb P3K Ctrl rack 1 258 lb P3K Ctrl rack 2 348 lb Cables 475 lb Glycol system 260 lb AO System Total 6291 lb With Heaviest AO Instrument P1640 / Cal 380 lbs (est) P1640/ Cal elec. 450 lbs (est) Total w/ Instrument 7120 lbs ~1700 lbs more than current maximum J.Zolkower P3K 9-22-10 P3KInfrastructure InfrastructureI&T – July 19, 2010 2 Balance Adaptations P3K Cass mounted component weights exceed current balance adjustments via moving counterweights New balance adaptations required: Additional ~700 lbs of lead added to weight boxes on Tube upper ring Implementation of up to three ‘dummy’ electronic cabinets: 1. 2. 2 cabinets loaded with 475 lbs of weight, the third with ~200-300lbs To be applied with lower weight Cass instrument / electronic configurations Status: Design concept complete. Risks: Additional load on tube may effect telescope pointing model. No structural concerns have been identified. J.Zolkower P3K 9-22-10 P3KInfrastructure InfrastructureI&T – July 19, 2010 3 Electrical Service Upgrades Power Requirements Computer Room Electronics (2 Racks) Total Rated Power : Total measured continuous measured: Continuous + Intermittent measured: Cass Cage mounted Electronics (4 Racks) Total Rated Power: Total continuous measured: Continuous + Intermittent measured: Current AO system measured: • Highest power AO instrument P1640 • P1640 Cal power TBD 11,870 W 3500 W 5400 W 8900 W 6250 W 7210 W 1035 W ~ 500W Chiller in Coude 220 V / 3 Phase / 42 amp service J.Zolkower P3K 9-22-10 P3KInfrastructure InfrastructureI&T – July 19, 2010 ~ 10,000 W 4 Electrical Service Upgrades Required Electrical Upgrades Computer Room Electronics Add 3x 120V / 30 Amp Receptacles (ready for connection) Cass Cage Add 3x 120V / 30 Amp Receptacles Add Load Center in Cass Cage Insufficient paired conductors available in exiting wrap-up to provide required power (electromagnetic field cancellation concerns) » A new, auxiliary wrap-up will be used to bring required power to Cass » This auxiliary wrap-up will also be used to & from transport glycol to Cass AO Lab Add 3x 120V / 30 Amp Receptacles, Contactors (ready for connection) Coude (Chiller location) Add Breakers, Disc. contactors, and Junction Box J.Zolkower P3K 9-22-10 P3KInfrastructure InfrastructureI&T – July 19, 2010 5 Power Dissipation / Mirror Temperature 13 200" Mirror Temperature 12 AO power off AO power on 11 Mirror Temperature (ºC) 10 Sensor Location 9 N CO2 cleaning caused rapid cooling 8 7 Current AO power ~ 1000 W 6 E SE S SW W NW 5 4 NE 24 hour data gap 3 Month/Day: UT Time J.Zolkower P3K 9-22-10 P3KInfrastructure InfrastructureI&T – July 19, 2010 6 Cass Rack Power Allocation These racks to be cooled ~6100 W J.Zolkower RACK ID MEASURED CONTINUOUS POWER (W) MEASURED Intermittent POWER (W) DM 1 DM 2 Cass 1 Cass 2 2,420 2,420 1,270 140 2,420 2,420 1,270 1,080 Total 6,250 7,210 P3K 9-22-10 P3KInfrastructure InfrastructureI&T – July 19, 2010 8 Cooling System Functional Parameters Basic Functional Requirement Provide system for cooling of Cass mounted electronics in order to minimize the heat dissipated to environment below the primary mirror and dome air. Operating parameters: Ambient temperature range: Target Coolant temperature: Cooling fan air flow: Coolant Mix: Coolant Temperature Range: Facility Chilled water temp: -10ºC to +30ºC 3ºC below ambient Constant speed 35% Propylene Glycol -13ºC to +27ºC 5ºC to 10ºC (seasonal range) Thermal modeling of electronic rack heat exchangers by Thermatron to confirm heat exchanger design within proposed operating parameters and define performance requirement of chiller J.Zolkower P3K 9-22-10 P3KInfrastructure InfrastructureI&T – July 19, 2010 9 Chiller Specification Requirements for Cass Electronics Cooling Total heat load: Max. coolant flow rate: 6100 W 16 GPM » DM Racks: 3x 2 gpm x 2 Racks = 12 gpm » Cass 1 Rack: 2x 2 gpm x 1 Rack = 4 gpm Coldest required supply coolant temp: Warmest required supply coolant temp: -13ºC (3º below lowest ambient) +27ºC (3º below highest ambient) Chiller Construction / Installation for Cass instrument cooling Water cooled chiller: exhaust chiller heat through facility chilled water 7.5 ton capacity chiller from Opti-temp to be installed in Coude lab » Delivery scheduled for Oct 4, 2010 Chiller Construction / Installation for AO Lab: Acquired Neslab System III Liquid to Liquid Heat Exchangers (no cost to project) » Ready for installation after clean-up and testing Cooling requirements are less stringent when operating in AO lab, so refrig of process coolant not req’d No need to move chiller from dome floor to AO lab or long plumbing runs J.Zolkower P3K 9-22-10 P3KInfrastructure InfrastructureI&T – July 19, 2010 14 DM Rack Cooling System Layout Cage inside J.Zolkower Cage outboard P3K 9-22-10 P3KInfrastructure InfrastructureI&T – July 19, 2010 18 Electronic Rack Heat Exchanger Delivery of 10 pcs Week of Sept. 20, 2010 J.Zolkower P3K 9-22-10 P3KInfrastructure InfrastructureI&T – July 19, 2010 19 Cooling Fan Speed Control Proposed solution from Degree C •Accepts up to nine fans •·Synchronizes rotational speeds of 4-wire fans to eliminate “beat” noise and vibration •· Monitors speed of 3-wire fans •· Simultaneously controls up to two types of fans •· I2C and RS232 communication interfaces •· Field configurable through serial interface •· Programmable alarm thresholds & fan curve •· Open collector alarm output •· One onboard/ two external temperature sensors •· Non-volatile memory to store configuration •· Power & Alarm LEDs with external connections •· Software selectable 3.3/5V logic operation •· Isolated Fan and Logic power domains •· Single/Dual power input •· Inrush current limiter for “hot swap” •· Fan failure detection and prediction Delivery of 10 pcs Week of Oct 18, 2010 J.Zolkower P3K 9-22-10 P3KInfrastructure InfrastructureI&T – July 19, 2010 21 Electronic Rack Cooling Work completed Spec and order Heat Exchangers Spec and order Fan Trays & Speed Controller Packaging of DM racks Design & and pre-sourcing of rack plumbing, hose ass’y, manifold & attachment hardware Work Remaining Packaging of Cass 1 control rack Installation of HX, fan trays, plumbing into racks Testing of in-rack cooling system prior to electronic integration Risks More than 72 fans @ >100 cfm flow; Coolant flow @ 16 gpm » Will instrument be sensitive to vibration from fans or coolant flow? J.Zolkower P3K 9-22-10 P3KInfrastructure InfrastructureI&T – July 19, 2010 22 Cooling System Control System Supervisor Requirements Document: http://www.oir.caltech.edu/twiki_oir/bin/viewfile/Palomar/Palm3000/P3KInfrastructure?rev=1;filename=P3K_Cooling_Super visor_Concept_9-17-10.doc Campbell Scientific 3000 data logger/controller The Campbell data logger and control system has a versatile set of analog and digital inputs and outputs that are programmed with a simple interface and is in use at 4 location already at Palomar Observatory. Parameters to be monitored: Ambient air temperature and dew point at cabinet location. Cabinet internal air temperature Cabinet wetness Fan Speed Emergency stop status Sensor Bypass configuration (overrides) Chiller coolant temperature (at chiller) Chiller coolant flow rate (at chiller) Chiller enable state Cabinet skin temperature Cabinet coolant flow rates (TBD) P3K 9-22-10 P3KInfrastructure InfrastructureI&T – July 19, 2010 Cooling System Control Modes of operation: Constant temperature set point (AO Lab operational mode) Controller maintains a constant internal air temperature Ambient Temperature Tracking (Telescope operating mode) Controller maintains a temperature relative to the ambient temperature Dew point avoidance (Telescope operating mode) Controller maintains a temperature relative to dew point for improved safety during high dew point conditions. P3K 9-22-10 P3KInfrastructure InfrastructureI&T – July 19, 2010 Cooling System Control Work completed Hardware spec & ordered Initial design complete Initial software design complete Work Remaining Bench testing to begin after receipt of hardware (Oct 1) Complete System integration and test P3K 9-22-10 P3KInfrastructure InfrastructureI&T – July 19, 2010 Auxiliary Wrap-up Routing South Polar Axis Routing Turning Guide Attached at yoke bottom center J.Zolkower To Coude P3K 9-22-10 P3KInfrastructure InfrastructureI&T – July 19, 2010 30 Auxiliary Wrap-up Routing Dec Axis Tube J.Zolkower P3K 9-22-10 P3KInfrastructure InfrastructureI&T – July 19, 2010 East Arm 31 Dec Axis Wrap-up Concept East Arm Spool Attached To Tube (Tube not shown) Dec axis Igus Cable Carrier Guide trough (cutaway) Attached to East Arm P3K Infrastructure – July 19, 2010 Cass Plumbing & Electric Routing Duct for hose routing Cooling distribution manifold Electric Load Center South side P3K 9-22-10 P3KInfrastructure InfrastructureI&T – July 19, 2010 Cooling Distribution Manifold B&G Balance Valve 2 Required •Cass Cage •AO lab Parker Quick Coupling Stainless Steel Manifold J.Zolkower P3K 9-22-10 P3KInfrastructure InfrastructureI&T – July 19, 2010 34 Cooling / Electrical System Distribution Work completed Distribution Manifold design Spec and pre-source of distribution manifolds, controls, valves, and prefabricated hose ass’y Work Remaining Design of Auxiliary Wrap-up Spec & procurement of Aux Wrap-up components Installation of Chiller in Coude (electric & plumbing) Installation of Neslab at AO Lab Procurement of manifolds, controls, valves, and pre-fab. hose ass’y Installation of Distribution Manifold in AO Lab and Cass Cage Installation of Auxiliary Wrap-up Complete System integration and test Risks Aux Wrap-up varying effect on balance. Need to analyze. J.Zolkower P3K 9-22-10 P3KInfrastructure InfrastructureI&T – July 19, 2010 40
© Copyright 2026 Paperzz