Development Control Committee Special Meeting to be held on 27th January 2010 Part 1 - Item No. 4 Electoral Division affected: Wyreside Hazardous Substance Consent Application: HSC/09/01 Hazardous Substances Consent application for the underground storage of 1.2 million tonnes of natural gas and associated facilities including the construction of an above ground compressor station and pipelines. Preesall Saltfield, Stalmine/Preesall, Wyre Estuary Contact for further information: Stuart Perigo, 01772 531948, Environment Directorate [email protected] Executive Summary Application - The application is for Hazardous Substances Consent (HSC) for the underground storage of 1.2 million tonnes of natural gas associated with a planning application for the development of underground caverns to store gas and associated above ground infrastructure (ref 02/09/0159). The planning application includes: 6 (initially 7 but subsequently amended) multiwell locations to create underground salt caverns by solution mining. Creation of caverns up to a maximum of 36 to store up to 10 million standard cubic metres of natural gas each) (initially 42 but subsequently amended). Compressor station compound comprising of two compressor buildings ancillary equipment access roads and car parking area. Seawater pump station compound comprising a pumping station stand by generator and switchgear building transformers and ancillary infrastructure access roads and car parking area. Northern booster pump station compound comprising the booster pump station building a switchgear and standby generator building transformers a de-brine facility ancillary infrastructure access roads and car parking areas. Southern booster pump station compound comprising the booster pump station building a switchgear and standby generator building transformers a de-brine facility ancillary infrastructure access roads and car parking areas. Reception compound comprising the control building laydown area for materials and equipment. Gas manifold and distribution infrastructure. Seawater pipeline from the Fleetwood fish dock to the perusal site Brine discharge pipeline from the perusal site to a point approximately 2.3km offshore to a two port diffuser. Four power communication control pipelines from the Fleetwood dock to the perusal site. Electricity cables from the united utilities switchgear at the Stanah switchyard 2 to the new electricity substation. Temporary drilling compounds to the Fleetwood fish dock and at the Stanah switchyard. Extension to sea wall at west way to accommodate brine outfall and new observation platform. Pipeline link to interconnector. Comprehensive landscape scheme. New access road from A588 and new upgraded internal access road within the site. at Preesall Saltfield, Stalmine/Preesall, Wyre Estuary. Recommendation – Summary That having first taken into consideration all the information submitted in connection with the application, the application be refused for the following reasons: 1. The application contains insufficient information to: I. Properly assess and ensure the geology of the area is capable of accommodating the proposed development; II. Demonstrate its relationship to former solution mining activities or surface development; and III. Establish there is no opportunity for migrating gas through the geology or via former mining activities; contrary to Policies 2, and 71 of the LMWLP. 2. The applicant has failed to demonstrate that the development would not present an unacceptable risk of gas migration given the relationship of the proposal to former operations and its proximity to residential areas on the east side of the estuary and the more densely populated Fleetwood peninsula throughout its operation, decommissioning and long term aftercare management contrary to Policies 2 and 3 of the LMWLP. 3. The failure to provide an adequate risk assessment for the proposal would result in considerable and understandable fear and distress within the local communities attributable to the nature of the proposal and the potential consequences of any accident occurring and would be contrary to Policy 2 of the LMWLP. 4. The proposal would not maintain appropriate distances between establishments and areas of public use contrary to the provisions of the SEVESO II Directive and that any measures to maintain appropriate distances could only be achieved by the closure of a section of the Wyre Way within the application boundary. Background There is a complex mineral extraction planning history in the Preesall area initially associated with the extraction of brine by solution mining to serve the former ICI works at Hillhouse in Fleetwood and more recently associated with proposals to 3 create underground caverns by solution mining for the storage of natural gas. This application relates to a proposal for underground gas storage in caverns created by solution mining which is the subject of a planning application reported on the agenda (ref 02/09/0159) This report relates to an application for Hazardous Substance Consent (HSC) to store 1.2 million tonnes of gas in underground caverns. The application must be considered in tandem with the planning application for the creation of caverns in salt by solution mining. A summary of the more recent history relating to the proposal to create caverns for gas storage and for HSC associated with such is set out in the 'History' section of this report. Applicant’s Proposal The proposal is for the large-scale storage of natural gas with a projected maximum content of 1.2 million tonnes (described as 10 million standard cubic metres per cavern), at a temperature of up to 50C at a pressure of up to 80 bar absolute, in an unspecified number of underground caverns to be created by solution mining in salt layers. The development would extend over an area of 505.6 hectares. Although the locations of the caverns are not identified in the application, the planning application states that up to 36 caverns would be created from six drilling compounds accommodating up to six wellheads each. The Hazardous Substance Consent (HSC) application has been submitted in tandem with the planning application for the creation of the caverns by solution mining, above ground associated pumping and compressor stations and associated pipelines. The HSC application refers to the Environmental Impact Assessment (EIA) to that application, which outlines the potential environmental impacts of the proposal and mitigation measures to be taken to minimise any adverse impacts. The HSC application is accompanied by a supporting statement setting out the planning history; an overview of the proposed scheme; the need for the proposed scheme; health and safety issues; the applicant's safety policy; and the planning policy context. Supporting documentation has also been submitted in respect of gas releases and thermal radiation effects associated with wellheads and associated pipe work ('Consequence Modelling from Well Heads’). The boundaries of the two applications are common. Supplementary Environmental Information (SEI) has been submitted in support of the planning application and the application for HSC. The most relevant part of the SEI for the purposes of the HSC relates to hydro geological and geological information. Further information has been submitted in respect of geology and amended plans have been submitted in respect of a change to the application boundary and a change to the internal layout of some of the plant and equipment to reflect changes that were similarly made to the application boundary. The internal changes included the relocation of the northern booster pumping station and the reduction of wellhead compounds from 7 to 6. A series of pipelines would connect the wellheads and each gas storage cavern to a compressor station, which would be connected to the national gas transmission (NTS) network in the vicinity of St Michael’s-on-Wyre. This connection does not form 4 part of the current proposal for HSC nor is the subject of the planning application for the creation of the caverns and gas storage. The interconnecting pipeline to the NTS is the subject of a planning application that is currently before Wyre Borough Council. There are no submissions accompanying the application to indicate that level of residual risk associated with the development, or its possible effects other than those forming part of the planning application and supporting statement to the application. Description and Location of Site The HSC application boundary reflects the boundary of the planning application. It extends approximately from the mid point of the Wyre Estuary extending from the sewerage works in the north, incorporating Arm Head, Barnaby's Marsh, Burrows Marsh and as far as the proposed compressor station in the south adjacent to Burrows Farm. The area extends inland to Cote Walls Farm. The area is shown on the attached plan. A full description of the overall site is provided as part of the planning application report. Legislative Background EEC Directive 96/82/EC requires Member State's to introduce controls to prevent major accidents, which involve dangerous substances, and to limit their consequences for man and the environment. It requires the identification of lower and upper tier establishments where dangerous substances are present. Top tier establishments where the quantity of dangerous substances exceeds the specified quantity are required to prepare a safety report, provide public access to the report, prepare testing of on-site and off-site emergency plans and inform members of the public likely to be affected by a major accident. The Health and Safety Executive control these requirements. Article 12 of the Directive requires land use planning controls to apply to both upper and lower tier establishments to ensure that the objectives of preventing major accidents and limiting the consequences of such accidents are taken into account in land use planning policies. These objectives are to be pursued through the siting of new establishments. In the UK there is a system of control through the HSC process under the provisions of the Planning (Hazardous Substances) Act 1990. The provisions to this legislation give hazardous substance authorities the opportunity to consider whether the proposed storage or use of the proposed quantity of the hazardous substance is appropriate in a particular location, having regard to the risks arising to persons in the surrounding area and the environment. In this instance, as the planning application is a 'County Matter' the County Council is deemed to be the hazardous substance authority. In dealing with such an application the County Council must have regard to any material considerations and in particular, but without prejudice to the generality of the foregoing: a) To any current or contemplated use of the land to which the application relates; 5 b) To the way in which land in the vicinity is being used or is likely to be used; c) To any planning permission that has been granted for development of land in the vicinity; d) To the provisions of the development plan; e) To any advice which the Health and Safety Executive have given following consultations in pursuance with Regulations under Section 7(2) (Section 9 of the Hazardous Substances Act 1990). Where there is a planning application and a HSC application being considered together, it may not be possible to act upon one authorisation without the other. The guidance recommends that related applications be dealt together. The HSC controls do not duplicate the requirements of the Health and Safety Act. Rather, the controls acknowledge that even after all reasonably practicable measures have been taken to ensure compliance with Health and Safety legislation there will remain the residual risk of an accident that cannot entirely be eliminated. The HSC controls seek to ensure that this residual risk, to people in the vicinity or to the environment, is taken into account before a hazardous substance is allowed to be present in a controlled quantity. The extent of the risk in any particular case will depend upon where and how a hazardous substance is to be present; and the nature of existing and prospective uses of the application site and its surroundings. The Health and Safety Executive are required to advise local authorities on the nature and severity of the residual risk to persons in the vicinity arising from the presence of the hazardous substance and the Environment Agency are required to advise on the risk to the environment. Site History There is an extensive history of brine workings in the area to the east of the estuary, associated with the former ICI plant at Hillhouse. The earliest application dates back to 1947 with subsequent permissions for brine pumping up to 1998. These operations have now all ceased, although above ground wellheads are still evident. There is clear evidence at the surface of ground settlement and subsidence associated with the past workings, most particularly in the eastern part of the proposed site. Planning permission was also granted and implemented for the storage of mercury waste within one of the previously worked salt cavities. An application was made in 1998 to the Department of Trade and Industry (DTI) for the construction of a gas pipeline from Burrow’s Farm to St Michael’s-on-Wyre, in connection with the proposed Fleetwood Power Station. The DTI has confirmed that no consent was issued and the application has now lapsed. Two applications for HSC and two planning applications for the creation of caverns and gas storage facilities have previously been submitted to the County Council. An application for HSC was submitted in September 2004 (HSC/04/01). The application was refused on 3rd December 2004 and an appeal was lodged. 6 An application for HSC was submitted in April 2005 (HSC/05/01). An appeal was lodged against the failure of the County Council to determine the application. The County Council resolved to object to the application on 26th July 2005. Following a public inquiry, the Secretary of State dismissed the appeal on 16th October 2007. A planning application for the creation of caverns by solution mining to store natural gas and associated above ground infrastructure was submitted in 2003 in conjunction with HSC/04/01 (ref 02/03/1455). An appeal was lodged against nondetermination of the application but the appeal was subsequently withdrawn. A further planning application for the creation of caverns by solution mining to store natural gas and associated above ground infrastructure was submitted in December 2004 (ref 02/04/1415). An appeal was similarly lodged against the non-determination of the application. The main issues considered by the Secretary of State were the following: Need, alternatives and principle of development Geology, storage technology, mining industry Risk (gas migration/explosion), risk assessment, fear as a material consideration Sustainability of the working/disposal of mineral salt Impact on internationally, nationally, and locally designated sites and protected species Landscape and visual amenity Impact on the Wyre Estuary/Wyre Way and other footpaths Highway safety and highway impact on amenity Noise impact on areas east and west of the Wyre Estuary Economic/tourism impact Human rights The Inspector to the public inquiry and the Secretary of State concluded that the proposal would not accord with the objectives of the SEVESO II Directive, that any measures to maintain appropriate distances could only be achieved by the closure of this length of the Wyre Way, and that this amounts to sufficient reason to refuse the application for HSC. She also considered that the accuracy and adequacy of the current level of geological knowledge of the site is insufficient to allow the granting of a meaningful HSC, and that this amounted to a further reason justifying a refusal of HSC. The Secretary of State dismissed the appeals on 16th October 2007. A copy of the Secretary of States decision is appended to the report on the planning application. A planning application for the development of underground caverns to store gas and associated above ground infrastructure at Preesall Saltfield, Stalmine/Preesall, Wyre Estuary was submitted in March 2009 (ref 02/09/0159). The proposal includes the development of: 6 (initially 7 but subsequently amended) multiwell locations to create underground salt caverns by solution mining. Creation of caverns (up to a maximum of 36 to store up to 10 million standard cubic metres of natural gas each) (initially 42 but subsequently amended). 7 Compressor station compound comprising of two compressor buildings ancillary equipment access roads and car parking area. Seawater pump station compound comprising a pumping station stand by generator and switchgear building transformers and ancillary infrastructure access roads and car parking area. Northern booster pump station compound comprising the booster pump station building a switchgear and standby generator building transformers a de-brine facility ancillary infrastructure access roads and car parking areas Southern booster pump station compound comprising the booster pump station building a switchgear and standby generator building transformers a de-brine facility ancillary infrastructure access roads and car parking areas Reception compound comprising the control building laydown area for materials and equipment. Gas manifold and distribution infrastructure. Seawater pipeline from the Fleetwood fish dock to the Preesall site. Brine discharge pipeline from the Preesall site to a point approximately 2.3km offshore to a two port diffuser. Four power communication control pipelines from the Fleetwood dock to the perusal site. Electricity cables from the United Utilities switchgear at the Stanah switchyard to the new electricity substation. Temporary drilling compounds to the Fleetwood fish dock and at the Stanah switchyard. Extension to sea wall at west way to accommodate brine outfall and new observation platform. Pipeline link to interconnector. Comprehensive landscape scheme. New access road from a588 and new upgraded internal access road within the site. By letter dated 10th June 2009 Supplementary Environmental Information (SEI) was submitted. This information responded to matters raised as part of the initial consultation process and included a number of technical documents relating to geological and geotechnical matters. By letter dated 18th September 2009, the application was amended partly as a result of responses to the consultation process and discussions with the Health and Safety Executive and partly in view of land ownership issues. When the amendments to the planning application were made, the information was similarly submitted in respect of the HSC application. Planning Policy The requirement for the determining authority to have regard to the provisions of the development plan so far as it is material to the application brings into play Section 38 (6) of the Planning and Compulsory Purchase Act 2004, which requires that the determination must be made in accordance with the plan except where material considerations indicate otherwise. There are no specific policies in the development plan relating to the storage of hazardous substances, however, there are a significant number of policies relating to the protection of the environment and 8 protection on the quality of life. All the relevant policies to the proposal as a whole are listed in the report on the planning application and against which the planning application has been considered. The following policies are considered to be most relevant to the assessment of the HSC: European Policy Energy for a Changing World – An Energy Policy for Europe – sets out the need for Europe to deliver sustainable, secure and competitive energy. The thrust is on sustainability and the need to reduce carbon emissions but forecasts imports of gas to continue to increase and the need for the security of gas supply. It recognises the risk of supply failure is growing and that additional storage facilities would help the security of supply. EU Habitats Directive EU Directive – Control of Major Accidental Hazards Involving Dangerous Substances National Energy Policy The 2003 Energy White Paper The Energy Challenge 2006 (2006 Energy Review Report) The Energy White Paper, Meeting the Energy Challenge – A White Paper on Energy (May 2007): sets out the Governments current international and domestic energy strategy and builds on the 2003 Energy White Paper and the Energy Review – the Energy Challenge of 2006. Four energy goals are identified: To put the UK on a path to cutting CO2 emissions by 60% by 2050, with real progress by 2020. To maintain the reliability of energy supplies. To promote competitive markets in the UK and beyond. To ensure that every home is adequately and affordably heated. Relevant Guidance/documentation SEVESO II Directive The Planning (Hazardous Substances) Act 1990 The Planning (Hazardous Substances) Regulations 1992 The Planning (Control of Major-Accident Hazards) Regulations 1999 Circular 04/200 - Planning Control for Hazardous Substances PPG1 PPG7 PPG9 PPG14 MPG1 General Policy and Principles The Countryside: Environmental Quality and Economic and Social Development Nature Conservation Development on Unstable Land General Considerations and the Development Plan System Regional Spatial Strategy (RSS) Policy CZ2A Coastal Development Policy CZ3 Coastal Communities and Economic Development 9 Policy ER1 Policy ER5 Policy ER9 Management of the North West's Natural, Built and Historic Environment Biodiversity and Nature Conservation Policy ER8 - Development and Flood Risk Minerals Extraction Lancashire Minerals and Waste Local Plan Policy 2 Policy 3 Policy 15 Policy 16 Policy 18 Policy 20 Quality of Life Buffer Zones Internationally Important Nature Conservation Sites Nationally Important Nature Conservation Sites Locally Important Nature Conservation Sites Wild Fauna and Flora Lancashire Minerals and Waste Core Strategy (LMWCS) Policy CS1 Policy CS2 Policy CS3 Policy CS4 Policy CS5 Safeguarding Lancashire's Mineral Resources Minimising the need for mineral extraction Meeting the demand for new minerals Identifying sites and areas for mineral extraction Achieving Sustainable Minerals Production Wyre Borough Local Plan (WBLP) (saved policies) Policy SP2 Policy SP14 Policy ENV2 Policy ENV4 & 5 Policy ENV6 Policy ENV13 Policy ENV14 Policy ENV16 Policy TREC12 Strategic Location for Development Standards of Design and Amenity Open Coastline Nature conservation Protected Species Development and Flood Risk Development and Flood Defences Ground Water Protection Public Rights of Way Wyre Borough Local Plan Review 2001 – 2016 (1st Deposit Draft) ENT2 TOUR12 Undeveloped Coastline Public Rights of Way Other relevant publications 'Parliamentary Statement of Need for Additional Gas Supply Infrastructure' laid before Parliament by the then Secretary of State for Trade and Industry in May 2006 Energy Markets Outlook – Dec 2008 Department for Business Enterprise and Regulatory Reform - Gas Storage in your area – Your questions answered British Geological Survey – Underground Gas Storage British Geological Survey – Mineral Planning Factsheet – Salt – Jan 2006 British Geological Survey – Mineral Planning Fact sheet – Underground Storage – Feb 2008 10 Consultations The following bodies have been consulted on the application. Their comments are summarised below: Health and Safety Executive (HSE) – The HSE has assessed the risks to the surrounding areas from the likely activities should HSC be granted. The HSE has assessed the risk of harm from the maximum quantity of hazardous substances for which consent is being sought. Risks that may arise from the presence of other substances have not been taken into account in this assessment. The HSE, in considering the application, has made the assumption that the requirements of the Health and Safety at Work etc. Act 1974, and all relevant statutory provisions, will be met should Consent be granted. The current stage of the design of the establishment, level of detail in the Consent application and the timescales for the determination of the Consent, are insufficient to ensure that this will be the case. Consequently, should HSC be granted, the applicant's attention should be drawn to Section 29 of the Planning (Hazardous Substances) Act 1990. This makes it clear that nothing in any Consent granted can require or allow the building or operation of an establishment which does not comply with the relevant statutory provisions and to the extent that any Consent purports to require or allow and such thing is void. On this basis the HSE has concluded that the risks to the surrounding population arising from the proposed operation(s) are so small that there are no significant reasons, on safety grounds, for refusing HSC. The following condition is recommended: 'The hazardous substance(s) shall not be kept or used other than in accordance with the particulars provided on the application form, nor outside the area(s) marked for storage on the substance(s) on the plan which formed part of the application (see drawing number A.00100.POO Rev 1). A plan is enclosed defining a consultation zone. Should planning permission be granted, the zone will be used for consultation for future developments as part of the HSE's PADHI + land use planning system. National Grid – Gas – no comments received Transco – no comments received Environment Agency – There is insufficient information to fully comment but the gas storage facility will be regulated jointly by the Health and Safety Executive and the Environment Agency under the COMAH regulations and will be assessed at the appropriate time before the gas storage begins. United Utilities – No comments received Lancashire County Council Emergency Planning Section – No comments on the application for HSC. The Section would only become involved if planning permission is granted and the site becomes subject to COMAH and an 'offsite' emergency plan has to be prepared. Natural England – It is not natural England's responsibility to comment on the detail of the submitted geotechnical information and therefore outside Natural England's 11 remit to provide advice on the assessment of likelihood of geological failure but comment as follows on the implications of such events: The development is immediately adjacent to, and beneath the internationally designated Morecambe Bay Ramsar Site, Morecambe Bay Special Protection Area (SPA), and the nationally designated Wyre Estuary SSSI. The boundary for Morecambe Bay Special Area of Conservation is at the mouth of the Wyre Estuary less than 3km to the north of the development site. The proposal has been considered under Regulation 48 of The Conservation (Natural Habitats, &c.) Regulations 1994. Control of Major Accidental Hazards - Geological failure, crown whole collapse or subsidence during construction or operation of the gas storage facility would have a significant effect on the statutory protected site(s), including loss of protected habitat and potential contamination to habitats and species. Loss of habitat adjacent to the estuary would also have significant indirect effects on the SPA and Ramsar site since the area is important for wintering waterfowl and waders. Hazardous Substance Consent – failure of the salt caverns to adequately contain natural gas at such quantities is likely to cause significant environmental damage including pollution and contamination of the Wyre Estuary and river channel and subsequent loss of habitat and protected flora and fauna. Contamination may also disperse and affect the designated features of Morecambe Bay SAC. There is also potential loss of terrestrial habitat through incineration. In order to provide further detail on the potential impacts of this proposal on designated features, further information is required relating to the precise locations of the salt caverns and drilling tunnels. Natural England understands this information will not be available until the ground exploratory works have been completed and the sub surface layout of the scheme has been finalised and would wish to be reconsulted at that stage. Marine and Fisheries Agency – No comments received RSPB - No comments received Wyre Borough Council – Object. The proposal would lead to considerable and understandable fear and distress within the local communities in view of the high level of associated risk and potential consequences of any accident occurring, particularly if the applicant has not satisfactorily addressed the capability of the geology of the area to safely accommodate a development of this nature and scale. Hambleton Parish Council – object for the following summarised reasons: The instability of the proposed site makes it unsuitable for this purpose. The damage to the environment and the open countryside of the Wyre Estuary by the construction of the caverns would be irreparable. It is considered that it would increase flood risk to the area. The proven instability of the area could lead to subsidence and possible damage to the infrastructure. The proposed site is part of the Wyre Estuary, SSI and Ramsar Site. The Wyre Way runs alongside the site and is therefore a protected area. 12 The damage the proposal would do to the long-term tourism plans for the area would be immense. Walkers use the Wyre Way frequently and this proposal would affect the popularity the walk enjoys. Should an accident occur, then it has been proven that emergency evacuation of this area would almost be impossible. There is only one means of travelling south over Shard Bridge. Preesall Town Council – Object to the proposal to store what is considered a dangerous substance. Pilling Parish Council – The application is not welcome and the Parish Council strongly objects for the following summarised reasons. The Parish Council accepts the need for gas storage but the development would make a considerable impact on the immediate population of 60,000 within a 3-mile range of the site. There is a potentially catastrophic impact from a blast occurring in a natural underground environment that can't be proved safe beyond reasonable doubt and could prove hazardous. Recent earth tremors support the state of the unstable ground. The planning application varies too insignificantly to the original that was refused and therefore this application should be refused. The proposal is very complex and beyond the comprehension of most parish councillors and therefore the views expressed reflect the views of the electorate. Head Dyke Lane would need to be upgraded to accommodate the increase in HGV movements associated with the development. It has no provision for cyclists, pedestrians or horse riders. The speed limit should be reduced to 50mph for road safety reasons. The speed limit on Lancaster Road, from Fold House Caravan Park to Land Ends should be reduced to 30mph. Should the application be granted, then periodic monitoring of the ecological environment must be maintained to ensure the effects of the application do not cause deterioration to habitats, marine stocks or birds/animals. Stalmine–with-Staynall Parish Council – no comments received It is the responsibility of the applicant to advertise an application for HSC in the press and post notice on the land. The applicant advertised the application and subsequent amendments thereto in the press and on the land. Two letters from the same household have been received objecting to the planning application, the HSC application and amendments thereto for the following summarised reasons: The boundary to the application still encroaches on third party land outside the control of the applicant. Multiple wellhead No 4 is sited in an extremely hazardous position. It's proximity to BW 63 which has a marl roof puts it in extreme danger and highlights the applicants lack of understanding of the former brine field. The applicant has not undertaken any sonar survey of BW63. When the well 13 subsides, as it is only 10m from Grange Pool watercourse, the watercourse will run through it creating a lake similar to that at Agglebys encroaching on the area identified as multiple wellhead 4. The caverns drilled from wellhead 4 will pass over existing caverns, the stability of which has not been established. The applicant's submissions (Gas Threshold Pressure Tests (GYTP) Golder Associates) demonstrate that low static pore pressures can have an adverse impact on the containment of the gas cavern and that further tests should be carried out given the findings into the test borehole. The test borehole is in close proximity to BW129 that lost its air pressure, as did BW128. Within 12 months air from BW128 was found to be entering BW112, through the salt to a distance of some 50m. Significantly, much lower air pressures than those proposed were being used (200PSI). The salt is not capable of accommodating the proposed development. The stability of the ground, in so far as it affects land use, is a material consideration and has been referred to by British Geological Survey (BGS) and the Technical Assessor to the previous public inquiry. The control centre and essential infrastructure is proposed to be located in an unstable area. Evidence at the public inquiry indicated that the distance between certain caverns is less than 10m. The caverns have historically been over worked, which raises the question of their stability. Canatxx have failed to address the advice of the Technical Assessor to the previous public inquiry regarding the need to acquire up to date knowledge of the previous brine field workings. BGS have made it clear that they are not able to comment on the quality or suitability of the salt for gas storage. The applicant is of the view that the salt could accommodate caverns, but do not specify the locations or numbers of such. Article 12 of the Seveso II Directive requires the prevention of major accidents and the limiting of the consequences of such accidents to be taken into account in land use policies and/or other policies especially through controls on the siting of new establishments. It requires appropriate distances to be maintained between establishments and residential areas, areas of public use and areas of particular natural sensitivity or interest. The proposed development covers an area within which there are well used unrestricted footpaths, most particularly the Wyre Way. The inspector to the previous public inquiry concluded that without imposing unreasonable restrictions on members of the public preventing them from using the Wyre Way to protect them from the effects of a major incident the proposed development would not accord with the objectives of the Directive. The Directive regards sewage treatment works as an external hazard. Hackinsall Sewage Treatment Works is surrounded by the proposed development. If the proposed development impacted on the local sewage network, it would cause a serious public health problem. The landscape and ecology plans are impractical. Little if any account has been taken of the instability in the area, the existing and extending 14 subsidence to depths of water in excess of 60m that could not be described as a 'field pond'. The bird surveys are not accurate due to restricted access to land. Advice Director of Strategic Planning and Transport– Observations The planning application and application for HSC are very similar to those previously submitted and refused on appeal. The planning application is for the creation of caverns in salt by solution mining and the construction of above ground infrastructure. Following the creation of caverns it is proposed to store up to 1.2 million tonnes of natural gas that would be imported into the storage facility via an interconnecting pipeline to the national transmission line. Whilst the planning application proposes a number of multiple wellhead locations with up to 6 wellheads in each location facilitating the creation of up to 36 caverns, the location of the caverns as projected to the surface are not identified. This is a fundamental omission relative to the previous application when indicative locations of the caverns were provided as part of the public inquiry. It is also contrary to the information provided for similar developments at Byley and more recently at King Street in Cheshire. The applicant advises that the precise location of the caverns is a matter to be addressed at a later stage through the COMAH process overseen by the Health and Safety Executive. The planning application states there would be up to 36 caverns although similarly does not identify the location of such or project the extent of such to the surface or identify the separation distances between the proposed caverns or the existing caverns. In the absence of such information the applicant is quite simply asking the County Council to grant Hazardous Substance Consent without knowledge of where the storage facilities would actually be other than on the end of a well head somewhere within the application boundary and only identifies a wellhead exclusion zone. Since the submission of both the planning application and the application for HSC, Supplementary Environmental Information has been submitted, primarily relating to geology and geotechnical matters, the boundary of the application has been amended to provide for a revised alignment of the access road, the northern booster pumping station has been relocated and the number of well heads in each multiple well head location has been reduced from 7 to 6. The application has been assessed against the relevant policies and guidance relating to HSC. The proposal is for the underground storage of 1.2 million tonnes of natural gas making it an upper tier establishment. The quantities exceed the specified thresholds for natural gas and therefore HSC is required. The SEVESO II Directive on the control of major-accident hazards requires local authorities to have regard to the objectives of the Directive, which are: To prevent major accidents and limit the consequences of such accidents for man and the environment; In the long term, to maintain appropriate distances between establishments 15 and residential areas, areas of public use and areas of particular natural sensitivity or interest; and In relation to existing establishments, for technical measures so as not to increase risks to people. Guidance for the consideration of applications for HSC is set out in Circular 04/2000. The issues for consideration are the nature and severity of the residual risk arising from the presence of the natural gas to: Persons in the vicinity; and The environment. Risk to Persons The risk to persons is addressed as part of the report on the planning application. The issues raised under safety and security are considered to be equally applicable to this application and therefore are repeated in part as follows. The development involves the underground storage of 1.2 million tonnes of natural gas in underground caverns along with associated surface development over an area of 505.6 hectares (excluding the discharge pipeline). There would be 6 wellhead compounds with up to 6 wellheads in each location giving a potential of up to 36 caverns, although the location and extent of each cavern is not identified or projected to the surface. The wellhead compounds would extend over an area of approximately 1 hectare each, would operate on an un-manned basis and be surrounded by security fencing with a minimum safety zone of 10 metres from the fence to the nearest part of above ground pipework. Personnel would be located in the control centre, approximately 400 metres from the nearest and up to 1200 metres to the furthest well head compounds as the crow flies. Distances would be increased by accessing the well head compounds via the internal suite access roads. The caverns would be created at a depth of between 300 and 450 metres with minimum and maximum pressures of between 25 and 80 bar absolute, a maximum manifold pressure of up to 90 bar and a minimum riser length of 275 metres. Each cavern would store up to 4.5 billion cubic feet of gas or 10 million cubic metres. Natural gas is highly flammable. To avoid existing caverns associated with the former ICI brine extraction operations it is proposed to directionally drill boreholes to create caverns below the estuary and associated salt marshes. The interconnecting pipelines between the northern booster station, the southern booster station, wellheads and the compressor station pass over existing caverns and in close proximity to the cavern containing mercuric sulphide (Well 107). The nearest distance from a wellhead compound to an inhabited dwelling would be approximately 150m. This would be to the house at Sportsmans Caravan Park and to Riverside Cottage. There are two caravan parks and associated residential properties (one of which is owned by the applicant) and isolated dwellings at Cote Walls Farm and Burrows Farm in close proximity to the proposals. Whilst the nearest proposed wellhead compounds would be some 150m away from the nearest properties, in the absence of details of where the caverns would be created, it is not possible to assess the potential impacts of the proposed caverns on any of the properties within and near to the boundary of the application, most particularly on 16 Riverside Cottage and the Heads Farm House and associated Sportsman’s Caravan Park close to or under which caverns could extend. The applicant identifies the major hazard events involving loss of gas from a wellhead as follows: Vehicle damage. Damage by a deliberate act. Aircraft strike. Catastrophic failure of a wellhead resulting in an unconfirmed loss of gas followed by ignition. It is accepted some of these risks could be minimised by, for example, the employment of appropriate security measures. However, in a worse case scenario of catastrophic failure of a wellhead leading to an unconfirmed loss of gas followed by ignition, there would be danger to humans within a given radius and the risk of spontaneous ignition of wood and similar combustible materials in close proximity. The applicant advises that the opportunity of this happening would be reduced by the design of the caverns and risers, the employment of emergency shutdown valves and best practice. With regard to decommissioning, the applicant has advised that within one year of decommissioning a site, a program would be drawn up; the caverns would be emptied of gas, filled with brine and the boreholes plugged with cement. The wellheads would be cut off 2m below surface level and topsoil would then be spread over the site to restore agricultural use. Ongoing monitoring of the caverns would be implemented for a further agreed period. In the event of a cavern being found to be unfit for purpose either during washing, testing or service, it would be emptied of gas, filled with brine and the boreholes plugged with cement. The wellhead would be cut off 2m below surface if the cavern had been fully developed. In regard to the cavern washing infrastructure the applicant is willing to discuss the possibility of keeping the facilities in place after the cavern washing programme is completed on a no gain/no loss basis. Leaving this infrastructure in situ would minimise disturbance to vegetation that has become established following construction and to the general public. The applicant considers the water washing infrastructure has the potential to be of assistance in enhancing the flood protection of the area, as the infrastructure has a very high flow rate and could be of major assistance in pumping out floodwater from the low lying lands of Fleetwood and Preesall. The applicant acknowledges the need to ensure the health and safety of the local community, workers at the site and any other people. Along with HSC the project would also be covered by the Control of Major Accident Hazards Regulations 1999 (COMAH) under the control of the Health and Safety Executive. This legislation seeks to ensure all workers, members of the public and others are not put into danger. The applicant commits to ensuring that all aspects of the design, construction and operation of the facility meet or exceed the standards imposed by law and accepts responsibility for the health and safety of its employees, contractors, customers and members of the public. It would also ensure all environmental standards are met or would be exceeded and undertake operations in a way to cause least disturbance. 17 There have been a number of incidents involving the escape and migration of gas from underground storage caverns in the recent past where it ignited causing extensive damage and risk to property and inhabitants and which were referred to as part of the previous application and in representations to this application by Protect Wyre Group (Hutchinson and Moss Bluff). There were a number of causes for these incidents, which primarily related to the mis-management of the operation and noncompliance with accepted practices and regulations. Nevertheless, following the incident at Hutchinson changes to American law were introduced requiring stand-offs for facilities of this nature from residential properties/areas. Whilst there are no current requirements or guidance for stand-offs in English law it is accepted that the legislation within which an operation of this nature would operate would be more stringent to minimise the risk of something comparable occurring. Nevertheless, even when operating within a strong legislative regime, incidents for unseen reasons can occur and these can be of a significant scale (e.g. Buncefield) However, irrespective of what safety systems are employed, they are inevitably reliant on man-made plant, equipment and the maintenance and employment of technological safety measures, which have an inherent risk. It is accepted that there are many industrial processes, plant or equipment that are relied upon in this way, but perhaps not of a scale as the current proposal and involving such quantities of a hazardous substance. The applicant has accepted that geological failure constitutes a major risk to the project. There has been extensive working of the salt deposits in close proximity to the proposal resulting in large underground caverns, one of which contains mercury, which in their own right could pose a risk to the proposed operations. The applicants proposed cavern creation techniques (bottom up) are designed to enable minerals other than salt (insolubles such as mudstone inclusions and discrete beds) to fall to the base of the cavern. However the geological occurrence of such minerals may allow gas migration through the surrounding rock strata. Clearly, any such migration could present very significant public dangers dependent upon where and in what concentrations the gas emerges or is able to collect. The integrity of local geology is considered to be very important in determining the acceptability of any particular proposal. The applicant has provided additional geological information as part of the planning application and SEI, which is common to both this application and the planning application. An assessment of this information has been made and is reported in full in the report on the planning application on this agenda. The assessment concludes there is insufficient information to demonstrate that the geology is capable of supporting this development. Given the acknowledged complexity of the geology in this area and the scale of the proposal, that is a very different position to where HSC has been granted for other UGS projects elsewhere in the UK. The applicant does not have control over all properties that may be directly affected by the proposal. It is accepted that best practices may be employed and that the operation of the site would have to comply with COMAH (Control of Major Accident Hazards Regulations 1999) process. The HSE has advised that they will assess the proposal for the purpose of these regulations and in light of a Pre Construction Safety Report (PCSR). The HSE has advised that whilst they cannot prohibit the commencement 18 of construction of the project, the operation of a COMAH site can be prohibited if the necessary demonstrations have not been made. Whilst the COMAH process is independent of the planning application and HSC process, it is important to recognise the process and not seek to duplicate the controls. At the end of the operational life it is proposed to fill the caverns with brine. A longterm plan for decommissioning and the after management of the site to ensure safety and security would be required. The planning application and HSC application are, to all intents and purposes the same as the previous application in terms of the creation of caverns, above ground infrastructure and the amount of gas to be stored albeit in 36 caverns rather than 24 has previously proposed. The Inspector to the previous public inquiry and the Secretary of State concluded that the proposed development was unacceptable and would not accord with the SEVESO II Directive in that the proposal neither limited the consequences of accidents for the public, who are encouraged to report to the area for recreation, nor maintained appropriate distances between establishments and areas of public use. She accepted the conclusions of the Inspector that the proposal would not accord with the objectives of the SEVESO II Directive and that any measures to maintain appropriate distances could only be achieved by the closure of a length of the Wyre Way and that amounted to sufficient reason to refuse the previous application. The Secretary of State also concluded that the accuracy and adequacy of the current level of geological knowledge of the site was insufficient to allow the granting of a meaningful HSC and that amounted to a further reason for justifying a refusal. The HSE has made an assumption that the development if approved would be carried out in accordance with all relevant legislation, including the Health and Safety at Work Act. They advise that the current stage of the design of the establishment, level of detail in the consent application and the timescales for determination of the consent are insufficient to ensure this would be the case. However, they do refer to the Hazardous Substances Act 1990 that makes clear that nothing in any consent granted can require or allow the building or the operation of an establishment which does not comply with the relevant statutory provisions. On this basis the HSC has concluded that the risks to the surrounding population arising from the proposed operation(s) are so small that there are no significant reasons, on safety grounds, for refusing HSC. The HSE propose a minimum consultation zone around identified areas/properties for future development. Risk to the Environment The Wyre estuary and Morecambe Bay area are subject to a number of national and international designations that reflect their importance for wildlife and nature conservation. The Wyre Estuary is designated as a Site of Special Scientific Interest (SSSI) and falls within the Morecambe Bay Ramsar site, Special Protection Area (SPA) and SAC, in view of their international importance for mudflat and salt marsh habitats, and the fauna and birds they support. There are a number of BHS designated for their vegetation, bird, invertebrate and mammal interest on the west side of the estuary. An assessment of the impacts of the proposal on the environment in terms of the marine and estuarine ecology and water quality has been undertaken as part of the 19 assessment of the planning application. The construction and operation of the brine discharge and seawater pipeline into the Irish Sea would cause short-term disturbance to intertidal and subtidal habitats and associated species during construction. The discharge of brine would cause localised mortality of sessile species during the operational phase of the pipeline, although recovery of these species is likely to be completed in a relatively short period of time. Scarce piddock and turf species were identified close to the route of the pipeline, but these species have been reported to have rapid rates of recovery one year following cessation of a discharge, hence effects on these species are not considered to be significant. The discharge is located some 2km to the southwest of the nearest boundary of Morecambe Bay SPA and Ramsar site and Wyre Estuary SSSI. The applicant’s modelling has demonstrated that the hyper-saline plume from the discharge would not extend to these designations. In light of the assessment work undertaken to date, it is considered that there would be no significant effect on the qualifying features of the Liverpool Bay pSPA or the Shell Flats and Lune Deep dSAC. It should be noted that a discharge consent issued by the Environment Agency was obtained in 2007 and includes a requirement for a programme of discharge monitoring. The route of the brine discharge and seawater pipeline across the Fylde Peninsula would lead to both temporary and permanent loss of land within Fleetwood Promenade – Coastal and Dune Grassland Biological Heritage Site (BHS), Rossall School Fields BHS and Fleetwood Marsh Industrial Lands BHS. This would in turn lead to loss of habitat that is known to support terrestrial invertebrate populations such as the Roesel’s bushcricket and striped snail. Subsequent landscaping and habitat management would minimise the potential impacts on these sites and the species they support. Vegetation clearance would be timed to occur outside the bird nesting season where possible and habitat enhancement would ensure that the availability of bird breeding habitats in the medium to long term is not significantly reduced. Potential impacts to the Wyre Estuary are associated with the proposed directional drilling operation, which has the potential to cause widespread contamination of the estuary should an accidental spill of bentonite occur. However, the implementation of appropriate safeguards and mitigation measures would minimise the potential risks associated with this activity. The Preesall area supports populations of rock sea-lavender and purple rampingfumitory. Although one field that is known to support the latter would be affected during construction, the programme of habitat replacement and enhancement would enhance the habitat potential for these species. Ponds known to support great crested newts would not be lost to the Scheme, but disturbance to their terrestrial habitat may occur. Therefore, a detailed Method Statement would be produced to accompany the submission of a licence application to Natural England in order to ensure that the favorable conservation status of the great crested newts is not affected. 20 The directional drilling under the Wyre Estuary is not expected to disturb wintering wetland birds inhabiting the intertidal zone within the estuary. No construction activities are proposed within the saltmarshes or wider intertidal zone where significant numbers of wintering birds reside and so the effect on the birds here is not considered to be significant. The construction of the Gas Compressor Station, Booster Pump Stations and multiple wellheads, with associated car parks, compounds, and access roads, would lead to a loss of some wintering and breeding bird habitat in the fields that are functionally linked to the Morecambe Bay SPA to the east of the seawall. However, the extent of this habitat loss would be relatively small when considered in the context of the retained wintering bird habitat and the available habitat within the surrounding landscape. A landscape and ecological enhancement strategy would be implemented as part of the Scheme design. Farmland under the ownership of Canatxx Gas Storage Ltd would be enhanced and managed primarily as arable land and short grazed pasture (with the exception of headland areas), which, traditionally, are the preferred feeding habitats for wintering waterfowl. Such management would increase cover and nesting opportunities and extend feeding and roosting resources. The policies of the development plan seek to protect habitats of ecological importance. Providing the development were to be undertaken in accordance with the relevant statutory provisions and there were to be no failure in terms of cavern collapse or catastrophic failure of a wellhead or migration of gas through the rock strata and overburden, the proposal in its current form would not lead to the loss and risk of damage to internationally designated sites and to which the relevant statutory consultees have not raised objection. However, any failure could result in major loss or damage that could not be easily rectified. Nevertheless, given the risk associated with such, the proposed HSC application is considered to be acceptable for the purposes of PPG9, Policies CZ2A, CZ3, ER1 and ER5 of the Regional Spatial Strategy, Policies 2, 3, 15,16,18,and 20 of the LMWLP, Policies SP2, ENV2, ENV4 and ENV6 of the WBLP and Policies ENVT2, ENVT3, ENVT5, and ENVT7 of the WBLPR. These policies seek to afford the strongest levels of protection to sites with international and national nature conservation designations encompassing Ramsar Sites, SPA's, SAC's, National nature Reserves, SSSI's and statuary protected species (Policy ER9). It is also a requirement to maintain, restore and expand habitats set out in the Biodiversity Targets for the North West Region (Appendix A) and most particularly to ensure no loss in the extent of the existing resource of the habitat. The ecological bodies are satisfied that sufficient mitigation or protective measures could be employed to ensure that the development would not present an unacceptable risk to the environment. Whilst any gas leakages/migration and consequent fire/explosions would be likely to have an adverse impact on those interests of acknowledged importance, the HSE has concluded that the risks to the surrounding population arising from the proposed operation(s) are so small that there are no significant reasons, on safety grounds, for refusing HSC. However, this is at odds with the conclusions of the Secretary of State to the previous application and which was refused on appeal in respect of the Wyre Way. The Wyre Way remains in the same alignment as previous and falls well 21 within the consultation zone identified by the HSE. The views of the HSE are therefore somewhat perplexing when there would appear to be no material change in circumstances to those previous. Matters raised in representations With regard to those matters raised in representations, the concerns relate primarily to the geology of the site, the capability of the salt to safely store gas, the potential migratory pathways within the salt, the overlying geology, the proximity and stability of existing caverns associated with former brine workings and the inherent risks associated with gas storage on residents and users of the public rights of way, and most particularly the Wyre Way in the event of an incident. These concerns are very understandable and are shared to some degree by the findings of the County Council's consultants. Conclusion The SEVESO II Directive on the control of major-accident hazards requires local authorities to have regard to the objectives of the Directive, which are: To prevent major accidents and limit the consequences of such accidents for man and the environment; In the long term, to maintain appropriate distances between establishments and residential areas, areas of public use and areas of particular natural sensitivity or interest; and In relation to existing establishments, for technical measures so as not to increase risks to people. Guidance for the consideration of applications for HSC is set out in Circular 04/2000. The issues for consideration are the nature and severity of the residual risk arising from the presence of the natural gas to: Persons in the vicinity; and The environment. If it is accepted that the salt and geology is capable of safely storing natural gas and that a COMAH assessment would satisfactorily ensure that appropriate distances between establishments and residential areas, areas of public use and areas of natural sensitivity or interest and that the residual risk arising from the presence of natural gas to persons in the vicinity and to the environment, then it must be concluded that the storage of gas for the HSC purposes is acceptable. However, this was not the view of the Secretary of State in determining the previous application. Whilst additional information has been submitted in respect of the geology of the site, an assessment of such has concluded that the applicant has not demonstrated the capability of the geology to support the development or address the risks associated with such. In respect of those issues relating to risk to persons and risk to the environment under the assessment of geology it is concluded that there have been no material change in circumstances since the previous application was considered and that irrespective of the conclusions of the Health and Safety Executive, there would still be unacceptable risk to persons using the area for recreation purposes, in 22 particular the Wyre Way, contrary to the provisions of the SEVESO II Directive. In this respect it is considered that the conclusions of the Secretary of State to the previous application for HSC remain material to the consideration of this application and that it should be refused for the same reasons. Recommendation That having first taken into consideration all the information submitted in connection with the application the application be refused for the following reasons: 1. The application contains insufficient information to: I. Properly assess and ensure the geology of the area is capable of accommodating the proposed development; II. Demonstrate its relationship to former solution mining activities or surface development; and III. Establish there is no opportunity for migrating gas through the geology or via former mining activities; contrary to Policies 2, and 71 of the LMWLP. 2. The applicant has failed to demonstrate that the development would not present an unacceptable risk of gas migration given the relationship of the proposal to former operations and its proximity to residential areas on the east side of the estuary and the more densely populated Fleetwood peninsula throughout its operation, decommissioning and long term aftercare management contrary to Policies 2 and 3 of the LMWLP. 3. The failure to provide an adequate risk assessment for the proposal would result in considerable and understandable fear and distress within the local communities attributable to the nature of the proposal and the potential consequences of any accident occurring and would be contrary to Policy 2 of the LMWLP. 4. The proposal would not maintain appropriate distances between establishments and areas of public use contrary to the provisions of the SEVESO II Directive and that any measures to maintain appropriate distances could only be achieved by the closure of a section of the Wyre Way within the application boundary. Local Government (Access to Information) Act 1985 List of Background papers Paper HSC/09/01 HSC/05/01 HSC/04/01 02/09/0159 02/04/1415 Date Contact/Directorate/Tel No. Stuart Perigo Environment 01772 531948 23 02/03/1455 Reason for inclusion in Part II, if appropriate N/A
© Copyright 2026 Paperzz