Objective ATC 07.1

Objective ATC 07.1
ESSIP Plan 2013
Luca DELL’ORTO
DSS/EIPR
13.09.2013
Comprehensive Explanation

Implementation of Arrival MANager (AMAN) (metering, sequencing and advisory tool)
(AMAN)
 Scope: Multi-National (changed in ESSIP Plan ed. 2013 to match the reports
provided by individual ANSPs in the LSSIP 2012 exercise)
 Applicability Area: AT / BA / BE / CH / CZ / DE / DK / ES / FI / FR / HR / IE / IT / LU
/ LV / MAS / NL / NO / PL / PT / RO / SE / UA / UK
 Additional States have implemented basic AMAN functions (sequencing and metering
without advisory tool)
Detailed functionalities:
 AMAN calculates the a/c sequencing for the concerned airport based on the
 flight predicted trajectory,
 environmental data (i.e. holding patterns),
 declared airport capacity transferred into separation criteria (time) and
 ATM separation criteria within TMA/CTR.
AMAN provides strategic advise as to how to establish the calculated airport
arrival sequence (delay on airway, flight in holding)
Requirement: Initial Basic AMAN requires appropriate presentation of airport arrival
sequence (arrival list) to the ACC and APP planning controllers.
ESSIP Plan 2013 / Objective ATC 07.1
2
What is new or has changed in ESSIP Plan ed.
2013
 SCOPE changed from ECAC to Multi-N
ESSIP Plan 2013 / Objective ATC 07.1
3
Link to European ATM Master Plan
 [TS-0102] - Basic Arrival Management Supporting TMA
Improvements (incl. CDA, PRNAV) – ESSENTIAL
ESSIP Plan 2013 / Objective ATC 07.1
4
Most important SLoA
 ASP04 - Implement AMAN with advisory tool (ASP01 only refers to
AMAN function concerning the sequencing and metering).
 ASP02 & ASP03 - Definition, validation and implementation of ATC
procedures for an operational use of AMAN tool, including the
changes in the TMA organisation (SID/STAR and adapted holding
patterns).
Note: The implementation scope has to be defined locally, depending
on the complexity of concerned TMAs
ESSIP Plan 2013 / Objective ATC 07.1
5
Finalisation Criteria and Closed Questions
 Ensure AMAN is part of new systems, or:
 implemented during upgrade of current system.
 AMAN can be implemented as a stand alone system; providing
advice to arrival management using a separate system trajectory
and presentation facility ( stand-alone Controller Working Position
(CWP) for AMAN function)
 AMAN initial basic in operational use?
 Basic AMAN implemented?
ESSIP Plan 2013 / Objective ATC 07.1
6
Supporting Material
 The relevant Operational Requirements Document (ORD) and
functional specification were produced by EATCHIP in 1997/1998.
Note: These documents have not been revised since.
 EROCONTROL Arrival Manager Implementation Guidelines and
Lessons Learned Edition 0.1 17-12-2010
ESSIP Plan 2013 / Objective ATC 07.1
7
ESSIP Report 2012
 This objective exists since 1995 and very slow progress has been
recorded in the last 18 years.
 At December 2012, 10 (out of 21) States declared the objective as
Completed
 No delay reported for the implementation of this objective. This is
mainly due to the postponement of its Full Operational Capability
date, which in 2011 (ESSIP Plan ed. 2012) was changed from
12/2010 to 12/2015.
ESSIP Plan 2013 / Objective ATC 07.1
8
Links and contacts
 Objective Coordinator:
Dell’Orto Luca, +32 2 729 3325
[email protected]
 EUROCONTROL Objective Expert(s):
Paul Conroy +32 2 729 3580
[email protected]
Predrag Terzioski, +32 2 729 3347
[email protected]
ESSIP Plan 2013 / Objective ATC 07.1
9