Status of items announced in the budget 2010

Const. Organization
1.Status of Items Announced in Budget 10-11
2. Planning of N.G. conversion in NGP Divn.
3. Targeted works 2010-11.
Status of Items Announced in Budget 10-11
DOUBLING
• Item No. 116 ( XXIX) of Budget Speech
• Durg – Rajnandgaon 3rd line ( 30.889 Km)
STATUS
• Included in Pink Book - 2010-11.
• Cost of project - `147.06 Crores.
• Budget Grant - `10.00 Crores. for 2010-11
• Detailed estimate sanctioned by Rly.Bd in Oct. 10.
• Tenders for geo-tech. exploration, earthwork and minor
bridges, opened on 4.11.10 & 11.11.2010
Contd…
New Gauge Conversion works
• Item No 115 (i) Budget speech
• Chhindwara -Nainpur – Mandla Fort (182.25 Km)
STATUS
• Included in Pink Book - 2010 -11.
• Cost of project - ` 556.54 Crores.
• Budget Grant for 10 - 11: ` 1.00 Crores.
• The detailed part estt. of NIR - MFR for ` 145.8 Cr. sent
to Railway Board in May-10 for sanction after conducting
FLS departmentally.
• Tender for major bridges of NIR-MFR opened on 4.10.10.
Contd…
Gauge Conversion Project
(Either completed or will be completed )
• Item No 113 (x) of Budget speech
• Balaghat- Katangi (46.8Km) of Jabalpur - Gondia
• STATUS
• Included in Pink Book - 1996-97.
• Gondia - Balaghat including MOIL siding (42+7
Km) section commissioned in the year 2005
• Balaghat-Katangi[46.8] - Section completed &
commissioned on 7.05.2010
Contd…
New line Project
• Item No 111 of Budget speech
• Mandir Hasaud- Naya Raipur (20.00 Km)
sanctioned as material modification to Raipur –
Titlagarh doubling of East Coast Railway
Status:
• Included in Pink Book - 2010-11.
• Cost of project - ` 77.32 Crores.
• Budget Grant for 2010-11 - Nil
• Budget demanded in R E -1.00 crore
• Part estimate for ` 28 Lakhs. for preliminary activities
sanctioned by GM/SECR.
• FLS is in progress.
Contd…
Updating of Socially Desirable
Rail Connectivity Proposals
• Item No 102 of Budget speech (Sr. No.10)
• Barwadih- Chirimiri/Ambikapur [182 km]
• RET Survey report submitted on 17.05.03 for ` 406.86
Crs. with ROR (-) 4.85%. Project shelved by Rly. Bd.
dated 28.07.03. Updating done as desired by Rly. Bd.
and updated report submitted on 16.2.09. with ROR (-)
9.05%. Board again desired in May-10 for updating.
Updated estimate under finance vetting..
• TDC - Dec. -2010
Contd…
Updating of proposals
Lohardaga-Korba (326 Km.)
(via Dharmjaygarh & Pathalgaon)
•
•
•
•
•
•
Item No 102 of Budget speech (Sl No. 63)
RET survey sanctioned in 1998.
Report Submitted to Rly. Board in 2003.
Cost ` 621.67 crores & ROR (+) 07.25 %.
Project shelved by Board in 2003.
Updated estimate with operating deptt. for
calculation of ROR.
• TDC - Dec.-2010
Contd…
Updating of proposals
Pendra Road –Korba/Gevra Rd. (121.7 Km.)
(via Pasan, Sundargarh & Deepika)
•
•
•
•
•
•
Item No 102 of Budget speech (Sl. No. 82)
PET survey sanctioned in 1996-97.
Report submitted to Board in 2003.
Cost ` 344.43 Crores & ROR (+)15.23%.
Updated estimate under finance vetting.
TDC - Dec-2010.
Contd…
Updating of proposals
Raigarh - Mand Colliery to Bhupdeopur
(63 Km. with Fly over)
• Item No 102 of Budget speech (Sl. No. 88)
• PET survey sanctioned in 2008-09.
• Report submitted to Railway Board in July -2009 at
the cost of ` 310.64 Crores & ROR (+) 29.58%
• Updated report submitted to Board in Aug. -10 at
the cost of ` 344.20 crores and ROR (+) 26.33%
Contd…
Updating of proposals
Raipur – Jharsuguda (310 Km.)
(via. Kharotapalan, Baloda Bazar, Bhatgaon & Sarangarh.)
•
•
•
•
•
•
Item No 102 of Budget speech (Sl. No. 89)
RET survey sanctioned in 1999-2000
Report submitted to Railway Board in Feb-2003.
Cost ` 971.96 crores & ROR (-) 20%.
Project was shelved by Board in Aug. -2003
Updating of abstract estimate under progress &
will be submitted to finance for vetting shortly.
• TDC - Jan -2011.
Contd…
Updating of proposals
Ramtek – Gotegaon (275 Km.)
(via Khawasa, Sioni & Dhuma)
•
•
•
•
•
•
•
Item No 102 of Budget speech (Sl. No. 92)
RET survey sanctioned in 1995.
Report submitted to Railway Board in April 1999.
Cost `. 528.21 crores & ROR (-) 11.50%
Updated report submitted to Board in Mar. 2005.
Project was shelved by Board in Oct. 2005.
Updating in progress and will be submitted to
Board by Jan -2011.
Contd…
Updating of proposals
• Item No 118 (i) of Budget speech
• Wadsa - Desaiganj - Gadchiroli - 49.5 Km
•
•
•
•
(Cost sharing)
RET survey sanctioned in Aug -1995.
Initial report submitted in July - 1998.
Updated report submitted in Aug - 2010.
Cost ` 232.40 crores & ROR without sharing
() 3.88% & with 50% cost sharing by State Govt.
ROR (-) 0.40%
Planning of N. G. conversion
in NGP division
Planning of N.G. conversion in NGP Divn.
Section
Blocking
Opening
(a) JBP - Sukrimangla (43.41km)
Oct-2011
June-2012
(b) Sukrimangla-Nainpur (70.1 km)*
Oct-2012
June-2013
* Subject to acquisition of forest land in Seoni Distt.
(c) Nainpur – Mandla Fort (42.2 Km.)
Oct -2012
June -2013
Contd.
Section
(d) Nainpur - Balaghat (75.4 Km.)*
Blocking
Opening
Dec -2012
Dec-2013
* Subject to acquisition of forest land in Balaghat Distt.
(e) NGP - Ramakona (86 Km.)
Oct-2012
June-2013
(f) Ramakona - CWA (64 Km.)
Jan -2013
Dec –
2013
(g) Nainpur - Seoni (76 Km.)
Dec - 2013 Dec-2014
(h) Seoni - Chhindwara (64 Km.)
Dec – 2014 Dec - 2015
Progress of Major Items
Jabalpur – Nainpur - Balaghat
Sr. No
Items
Scope
Progress
1.
Earth work
(Lakh Cum.)
108
40%
2.
Major Bridges
(Nos.)
49
60%
3.
Minor Bridges
(Nos.)
313
54%
Contd.
Sr. No
Progress of Major Items
Jabalpur - Sukarimangla
Items
Scope
Progress
1.
Earth work
(Lakh Cum.)
14
66%
2.
Major Bridges
(Nos.)
15
65%
3.
Minor Bridges
(Nos.)
82
68%
Contd.
Progress of Major Items
Nagpur - Chhindwara
Sr.
No
Items
1.
Earth work
(Lakh Cum.)
Scope
Progress
99.23
20%
work
completed.
Agency available for 27
Lakh. Cum.
Major Bridges (Nos.)
(a) Sub - Structure
2.
(b) Super Structure (Nos.)
Completed - 12
27
In progress - 12
Tender to be finalized - 3
87 steel W/O placed on MMR/WS
girders and trade. 42 girders
received, launching of
girders taken up.
Contd.
Sr.
No
Items
3.
Minor Bridges
(Nos.)
4.
Tunnel
Scope
Progress
254
36 - completed.
169 - Segments casted.
Launching in mega block.
34 - In progress.
5 - To be closed.
10 - Tender to be finalized.
2
Tender under finalization.
Issues to be Finalized
(1)
Operational Requirements
(i)
Crew movement to & from Sukrimangla during Ist phase
conversion from Oct -11
(ii)
Running of BG DMU or normal ICF coaches on converted
section of JBP – Sukrimangla from June - 12.
(iii)
Feasibility of running of truncated NG services on CWA - NIR
& NIR - BTC section after Oct-2012.
Options to be considered
(a)
Close the NG section after Oct 12 till complete conversion,
looking to the drastic reduction in passengers.
(b)
Running of curtailed NG services after augmenting Mech.
facilities need based at NIR by doing material modification of
GC estimates.
3.
Additional infrastructure desired by Mech.
Deptt. (to be decided judiciously in view of no
provision in the estt.)
(A)
(i)
(ii)
At NIR
115 M new washing cum inspection pit line.
Extension of existing shed by 15 M with lighting
arrangement.
Construction of rooms.
100 M line for keeping spare coaches.
Items (i) to (iv) will cost approx. ` 0.7 Crores.
Accommodation for 35-40 maintenance staff.
Development of diesel loco maintenance (` 2.98 Crores)
(iii)
(iv)
(iv)
(vi)
(B)
At MIB - Development of diesel loco maintenance (`3.6
crores)
Targeted works 2010-11
Name of work
PH
Prog.
Remarks
Champa – Bye Pass
15
20%
Rebuilding of Bridge
NO. 99
32
98%
ROB at Uslapur
30
82%
Delaying due to nonacquisition of land
Commissioning
delaying due to non
shifting of HT by
CSEB
Work in progress
ROB at Raigarh –
Kotarlia
ROB at Raipur –
Baloda Bazar
30
50%
Work in progress
30
90%
Work in progress
Contd…
Name of work
Prog.
Remarks
ROB at KM 867/7-8 at Durg Deposit
work
over DRZ line.
90%
Work in
progress.
USL – Development of Model
Goods Shed.
16
100%
Completed.
RSD - Raipur development of
goods shed.
16
100%
Completed.
Jharridih – Additional Dn
loop.
Himgir – Additional Up loop.
PH
16
16
100%
87%
Completed.
Work in
progress.
Contd…
Name of work
PH
(a) KDTR – Remodeling for
dealing with addl. traffic of
JSPL siding.
(b) KDTR – Addl. Loop.
16
Bhilai
–
Relocation
ART/ARME train
16
of
BRJN – Ext.of Dn island
platform for 24/26 coaches.
Prog
Remarks
85% Work in progress
95% Work in progress
96% Work in progress,
GJ work being
done by Div.
16
98% Completed for 24
coach length.
Contd…
Name of work
PH
Prog.
Durg – Development of goods
shed by providing common
loop.
16
Goods
shed
work completed.
96% Signaling work
to be taken up as
per revision.
BSP – Renovation of pit line
NO. 1 & 2 of coaching pit line.
42
55% Work in progress
42
100
Completed.
%
Bhilai Peripheral Yard – Impro.
in freight exam. Facility.
Remarks
Contd…
Name of work
PH
Prog.
Remarks
Bhilai Elect. Loco Shed – Aug.
of homing capacity from 150 to
175
42
100%
Completed.
BSP – Replacement of W. A. on
line No. 1 & Extension of PF
No. – 4
42
100%
Completed.
50%
Work in
progress.
BSP – Replacement of W. A. on
PF No. 3 & Extension of WA on
PF No. - 2
42
PROGRESS OF QUARTERS
Description
BSP-142 units
type-II
PB/OB/ Prog Remarks
LB
PB/242 100% Completed.
Raipur-96 type-II
PB/245
36% Work in progress. 48
Qtrs. by Mar-11.
34% Work in progress. All
type - V by Mar-11
Raipur-11 type-V
& 20 type-IV
PB/248
Raigarh- 10 typeII, 15 type-III
LB/672 100% Completed.
Contd.
Description
PB/OB/
LB
BSP-Replacement
out house 50 units
of
BSP-Replacement
type-I 50 units
of
LB/270
LB/271
Prog
Remarks
85%
Work is
progress.
in
85%
Work is
progress.
in
THANK YOU
WORKS COMPLETED IN
2009 -10 & 2010 -11 (PB)
Sr.
No.
Name of work
Sanc.
Year
Completed
Month
1.
Jamga – Addl. Up loop.
07-08
July-09
2.
IB – Addl. Dn loop.
07-08
Sep-09
3.
Parmalkasa – Conversion of
“C” class stn. into “B” class
with 4 lines.
05-06
Oct-09
Contd.
Sr.
No.
Name of work
Sanc.
Year
Completed
Month
Salva - Conversion of “C” class 06-07
stn. into “B” class with 4 lines.
Belpahar – Addl. Dn loop.
07-08
Nov-09
6.
Uslapur – Development
model goods shed.
of 05-06
Apr-10
7.
Raipur
–
Store
depot. 08-09
Development of goods shed.
June-10
8.
Jharradih – Addl. Loop line.
05-06
Aug-10
9.
Bhilai – Jamul cement siding 07-08
Electrification including yard.
Feb-10
4.
5.
Dec-09
STATUS OF LAW BOOK WORKS
Sr.
No.
Name of work
Sanc.
Year
Status
1.
BSP : Extn. Of existing shunting 04-05 Completed
neck by 180m at coaching depot.
2.
BEF : Development of full rake 07-08 Completed
handling point.
3.
JRMG : Development of full 07-08 Completed
rake handling point.
Contd.
Sr.
No
Name of work
Sanc.
Year
Status
4. MXA: Provision of dispatch signal 06-07 Completed
for line No. 5, 6 & 7 towards ore
yard and for line No. 2, 3 & 4
towards DUG and DRG.
5. Surakachar : Electrification of 06-07 Completed
Siding.
6. BRJN : Electrification of Orient 06-07 Completed
Collieries siding.
Contd.
Sr.
Name of work
No.
7. Shifting of 04 Nos. of Cross –
ovar at JRMG Railway Station.
8. RSD : Signaling facility for
reception and dispatch for line
No. 7
Sanc.
Status
Year
08-09 Completed
07-08
Clubbed
with PI
work.
TDC- Mar11
WORK IN PROGRESS
Name of Work
Sanc.
Year
Brajrajnagar – Extension of 07-08
Dn island platform for
24/26 coaches.
Anti.
Cost
2.40
In. Crs.
TDC
Prg.
Oct-10
98%
Remarks
ESP & IP approved. Slewing of main line and major OHE alterations
completed. PF extension work completed except stone surfacing.
Contd.
Name of Work
Himgir – Addl. Up loop
In. Crs.
Sanc.
Year
07-08
Anti.
Cost
4.46
TDC
Prog.
Nov-10
87%
Remarks
Existing relay room will be used. 100 % E/W, bridge work and ballast
supply completed. FOB - 100 % & Linking 60%. OHE - 48 foundation
out of 53 done & 28 mast erected, steel received. S & T progress - 80%.
CRS sanction obtained.
In Crs.
Contd.
Name of Work
Sanc.
Year
1.Kirodimalnagar – Addl. Loop. 06-07
2.Kirodimalnagar – Remodeling 08-09
for dealing with additional
traffic of JSPL siding.
Anti. TDC Prog
Cost
.
4.20 Nov-10 85%
6.00 Nov-10 60%
Remarks
Work is planned in two stages.
Stage -I – Up loop and one Dn loop work at KDTR.
Stage – II – 2nd Dn loop.
Connection for all 3 loops planned for simultaneous commissioning to
avoid redundant works. CRS sanction awaited. E/W – 95%, Building
& Bridge work – 100%, S & T – 95%, Track Linking in progress.
Contd.
Name of Work
Bhilai – Relocation
ART/ARME train
In. Crs.
Sanc. Anti. TDC Prog.
Year Cost
of 08-09 5.41 Dec-10 96%
Completed work
 Formation, track, extension of culvert.
 Shed (40x12) 140 ton for crane.
 S & T goomty (3mx3m) & Inspection pit.
Balance work in progress
 Service building for C&W staff – Upto plinth level completed.
 SIP & SWR to be revised after ESP alteration due to U/M LC in yard to be
manned & relocation of point.
 CRS sanction for D cabin submitted on 20.09.10
Contd.
Name of Work
Sanc.
Year
Bilaspur Yard - Raising of 07-08
speed for Bye pass line &
up through line.
In. Crs.
Anti.
Cost
3.10
TDC
Prog.
Dec-10 24%
 Work involves number of traffic and power block to carry
heavy slewing of track and relocation of 40 OHE masts.
 Work needs to be reviewed in view of limited returns and
take off point for proposed Electrical Loco Shed on it.
 Work has been kept in abeyance by COM.
Contd.
In. Crs.
Name of Work
Sanc.
Year
Anti.
Cost
TDC
Prog.
Durg – Development of goods
shed by providing common loop
& better unloading facilities.
08-09
7.00
Dec.-10
96%
 Goods platform work nearly completed.
 Placement/withdrawal of trains being done from BSP end.
 Connectivity from NGP end should be done along with 3rd line bet.
Durg – Rajnandgaon to avoid repeated NI and yard modification.
 Renovation of existing shed for labour rest room and merchant room
in progress.
In. Crs.
Contd.
Name of Work
Sanc.
Year
Dadhapara – Belha & 07-08
Urkura – Mandhar (IBS on
Up & Dn lines.)
Anti.
Cost
1.88
TDC
Prog.
Dec.-10
65%
Full quantity of cable procured. Electrical work completed. MDHURK commissioned on 28.7.09.Tender awarded for Dadhapara Belha section. Work in progress.
Contd.
Name of Work
Sanc.
Year
Gevra Road – Run through 08-09
facility.
Remarks
Work proposed for dropping.
In. Crs.
Anti. TDC Prog.
Cost
6.52 Mar-11 5%
Contd.
Name of Work
Sanc. Anti. TDC
Year Cost
Mandhar – New goods 08-09 3.18 NF
terminal.
In. Crs.
Prog.
-
Remarks
ESP Approved. Cost of work is exceeding the abstract estimate
substantially. Detailed estimate is under revision.
Contd.
In. Crs.
Name of Work
Sanc. Anti. TDC Prog.
Year Cost
Rupond – Addl. Common 08-09 3.46 Apr-11
loop to serve new goods
shed.
Remarks
Scope of work revised. ESP approved. Estimate sanctioned. Civil
tender finalised recently. OHE tender finalised. S & T tender opened
on 05.02.10 and discharged. Fresh tender opened on 20.08.10 and
under finalisation.
Contd.
Name of Work
BSP Div. – IBS
(4 location)
In. Crs.
Sanc.
Year
08-09
Anti.
Cost
6.00
TDC
Prog.
Dec-10
20%
Detailed estimated sanctioned. Tender awarded & work
under progress. SWR’s pending in division.
TDC
Dadhapara - Belha
-
Oct-10
Jairamnagar - Latia
-
Nov-10
Gatora - Jairamnagr
-
Nov-10
BSP - Gatora
-
Dec-10
In. Crs.
Contd.
Name of Work
Sanc.
Year
Bhupdeopur – Remodeling 08-09
for dealing with new pvt.
siding.
Anti. TDC
Cost
10.89 NF
Prog.
-
Remarks
Land acquisition required at JSG end land plan submitted.
Revised ESP approved. Land acquisition proceedings
stalled. Work to be truncated to avoid land acquisition and
revised ESP prepared & under finalisation.
Contd.
Name of Work
In. Crs.
Sanc. Anti.
Year Cost
TDC
Bhilai – Addl. Freight 08-09 19.71 Nov-11
maintenance depot at coal
empty
yard
with
3
examination lines & one
shunting neck of full length.
Prog.
28%
S & T and OHE tender finalised. E/W in progress. One
high tension tower in the alignment is yet to be dismantled
by CSEB.
In. Crs.
Contd.
Name of Work
Sanc.
Year
Anti.
Cost
TDC
Prog.
Bhilai – (Exchange yard) 09-10
remodeling with 2 addl. loop
line by extension of D/End.
5.95
Feb-12
-
Remarks:-
Scope of work finalised recently by the division. Detailed
estimate sanctioned during July- 10. ESP under finalisation.
In. Crs.
Contd.
Name of Work
Himgir – Addl. Dn. Loop.
Sanc. Anti. TDC
Year Cost
09-10
5.00
NF
Remarks:-
ESP approved. Work to be executed with 3rd line.
Prog.
-
In. Crs.
Contd.
Name of Work
Sanc.
Year
Anti.
Cost
TDC
Prog.
Jamga – Yard remodeling.
09-10
4.55
NF
-
Remarks:-
ESP approved. Work to be executed with 3rd line.
In. Crs.
Contd.
Name of Work
IB – Addl. Loop.
Sanc.
Year
Anti.
Cost
TDC
Prog.
09-10
4.13
Dec-11
-
Remarks:-
Site details collected. ESP approved. Estimate vetted. Tender
to be floated.
In. Crs.
Contd.
Name of Work
Sanc.
Year
Anti.
Cost
TDC
Prog.
Mudaria – Addl. Dn. Loop.
09-10
3.00
NF
-
Remarks:-
Heavy cost over runs are noticed in S & T portion of the
estimate. Scope of work reviewed and referred to Board.
In. Crs.
Name of Work
Sanc.
Year
Anti.
Cost
TDC
Prog.
Saragbundia – Conversion of 09-10
goods shed siding into Up
loop cum Dn reception line.
3.13
Oct-11
-
Remarks:ESP approved. Estimate under vetting.
JABALPUR – NAINPUR (113.5 km.)
(Non – Electrified section)
 This part of the project is falling in Seoni, Mandla &
Jabalpur distt. of MP.
 Total land acquisition is 344 hec. (Pvt. 261 + Govt. 50
+ Forest land 33 hec.)
25 hect of Pvt./Govt. & 30 hect of forest land is balance
for acquisition (Seoni district).
One important bridge over Narmada (18 x 30.5 m PSC
box) completed.
Contd.
 There are three major detours (Pindarai - Ghansore 20 km,
Vinayaki - Shikara 9 km, and Bargi - Kachpura 20.7 km), two
minor detours in Shikara – Sukari plus mini diversions at major
bridge approaches. Total length of detour alignment is 62 km.
Earth Work is progressing in 56 Km length .
Item
Earth work
(Lakh. Cum.)
Blanketting
(Lakh cum.)
Scope Prog.
Remarks
81
Earth work in 6 km detour portion
37.53
& in mega block is balance.
7.7
1.54
About 60% qty. to be done in megablock.
Item
Scope Prog.
Major
bridge
(Nos.)
33
Minor
bridge
(Nos.)
194
Ballast
(Cum.)
Remarks
Tender
under
finalized
for
32bridges.Out of which 35%
Completed - 3 Br.
In Progress-21Br.
Out of 115 bridges located in
detour. 53 completed, 65 in
progress. Out of 83 in same
56
alignment
pre-cast
segment
completed for 56
bridges &
balanced 27 bridges in progress.
18000 cum taken in Nainpur–Pendarai
244000 14130
section. For balance tender to be invited.
Gondia – Jabalpur gauge conversion
incl. Balaghat – Katangi (275.20 Km.)
2009-10
Year of
sanction
Anticipated
cost.
Exp. Upto
Mar-10
1996-97
1038.00
453.85
Exp. Upto
Oct.-10
34.48
Overall
progress
62%
Gondia – Balaghat section including MOIL siding
(42+7 Km) already commissioned.
Balaghat–Katangi section 46.8 km completed. CRS after
inspection on 23.02.2010. & section commissioned on
07.05.10
Contd.
 Track Linking – 125 Km. Indent placed for all P. way
materials. 12000 Sleepers transported .
 JBP-Gwarighat (20km) can be opened in June-2011. Thus
abandoning NG alignment from JBP – Gwarighat (9.2 km).
 TDC
Section
Blocking
Opening
(a) JBP - Sukrimangla (43.41km)
Oct-2011
June-2012
(b) Sukrimangla-Nainpur (70.1 km)*
Oct-2012
June-2013
* Subject to acquisition of forest land in Seoni Distt.
(c) Nainpur – Mandla Fort (42.2 Km.)
Oct -2012
June -2013
BALAGHAT – NAINPUR
(75.41 km. non – electrified section)
I- Section falling in distt. of Balaghat & Mandla in MP state.
II-Acquisition of land
Pvt. & Govt land (50.56 hect.) – nearly 100%.
Mandla distt- 100% (20.60 hect.)
Balaghat distt(75.47 hect) case pending with MOEF since
Feb-09 .
Contd.
Progress of Major Items as under.
Item
Earth work
(Lakh. Cum.)
Major Bridges
(Nos.)
Scope
Prog.
Remarks
19.0
(Pre.Block)
+ 9.50
( in Block)
Balance Earth work to be
5.65
done in mega block & in
forest area.
16
3.5 completed.
10 under progress.
70%
1 Bridge falling in forest
area.
Contd.
Item
Minor Bridges
(Nos.)
Scope
119
Ballast (Cum.)
141100
Track Linking
(In Km.)
80 Km.
(Incl. Loop
line)
Prog.
Remarks
52%
Pre-cast Segments ready
for 19 bridges. For 32
bridges tender finalised &
47 bridges on detour.
108000
Contract finalised for full
quantity. 20% ballast
being taken in depot.
-
65% P. way
arranged.
material
TDC - 30 months after possession of forest land i. e. Oct - 2012. Full
75 Km will be opened in one stretch.
MANDALA FORT- NAINPUR - CHHINDWARA
(182.25 Km. Non-Electrified)
Year of Anticipated
sanction
cost.
2010-11
556.54
2009-10
Exp. Upto
Overall
Exp.
Upto
Mar-10
progress
Oct-10
0
0%
 The project is being tackled in two phases i. e. (i) Mandla Fort
- Nainpur (42.25 Km.) (ii) Nainpur - Chhindwara (140 Km.)
 Final location survey of Mandla Fort – Chhindwara completed.
Part detailed estimate sent to Rly. Board in May-10.
 Tender floated for Major Bridges on 04.10.10.
 TDC – Dec-2012
Contd..
NAINPUR - CHHINDWARA
(140 Km. Non-Electrified)
 Final
location completed 50 Km. and balance is
under progress.
 Detailed estimate will be submitted
Board by April – 2011.
to Rly.
 TDC
Section
NIR - Seoni (76 Km.)
Blocking
Dec - 13
Opening
Dec -14
Seoni – Chhindwara (64 Km.)
Dec - 14
Dec - 15
CHHINDWARA – NAGPUR GC
(149.52 Km. Non-Electrified)
Year of Anticipated
sanction
cost.
2005-06
585.93
2009-10
Exp. Upto
Overall
Exp.
Upto
Mar-10
progress
Oct-10
123.23
15.06
23%
 The project is covering 53 Km. in Nagpur distt. of Maharastra
& 96.52 km. in Chhindwara distt. of M.P.
 Total land required 328 hec. (128 hec. forest & 200 hect.
private/Govt. land. 80% in M. P. & 20% in Maharastra.
 2nd stage clearance of MOEF for forest land received on
30.9.09. & trees cutting in progress.
Contd.
Item
Scope
Earth work
95.91
(Lakh. Cum.)
Major Bridge
(Nos.)
27
Prog.
Remarks
E/W in progress in six
block sections covering 70
22.08
km. & including two major
bridge approaches.
42%
Sub structure of 12 bridges
completed, 12 bridges in
progress. Design of 3
bridges in prorgress. 43
fabricated spans received
out of 87.
Contd.
Item
Scope
254
(40 in
detour)
Prog.
-
Minor
bridge Segmental
(Nos.)
139
Cast in situ
40
Remarks
18 in situ bridges completed.
Segmental casting completed for
139 bridges. Out of 40 bridges in
detour portion work is in
progress on 3 Br. Tender opened
for 16 bridges under finalisation.
Tender for 2 tunnels of 750 m & 150 m long opened on
22.03.2010.
Tender for 3 viaducts are invited.
All indents for span of 12.2 m & 18.3 m placed on
CEWS/Manmad. 30.5 m spans are being manufactured by
agency. Indents for 45.73 m are being placed with modified
25 tonnes loading on CEWS/Manmad.
 Ballast - Total requirement 3.36 lac. cum. Tender finalised
for the stretch falling in Maharastra State of 0.84Lac cum
and 0.85cum for MP.state and progressed 0.58 lac cum.
 TDC
Section
CWA - ULA (25 Km.
ULA – Saoner (80 Km.)
Blocking
Dec - 10
June - 11
Opening
June -11
June -12
Saoner - NGP (44 Km.)
Dec -12
June -13