3 4 5 6 7 8 MRWA-W-108 Designate the ownership of these hydrants: · where a hydrant could be removed and the maximum spacing distance still be met, this hydrant shall be marked as "Water Agency owned". · all other hydrants shall be marked as "Council Owned". E DN100 RESERVE TABLE 300-C Will be mostly Council Owned SEW or YVW 00 I&J E SCALE: R. JAGGER R. JAGGER DN150 DATE 1/12/16 CP / JT / RJ CWW B. VANOS 01/09/16 CWW SEW C. PAXMAN 01/09/16 SEW YVW J.TOMASI 01/09/16 YVW DATE 2 RESERVE APPROVED 3 57 J 58 B J H J DN150 B C E DN100 59 B K L 60 F L DN100 A K L L 61 G 1mm = 2m at A3 F 50 49 APPROVED: NAME 01/05/16 CP / JT / RJ 1 D 56 51 F DN100 52 MRWA WATER SUPPLY STANDARDS DATE: PUBLISHED FIRST ISSUE DESCRIPTION <DN63PE B C DATE: FIRST DRAFT REV D J DRAWN: CHECKED: NAME H 1 DN100 L MELBOURNE RETAIL WATER AGENCIES DESIGNED: 55 RESERVE The front of every property shall be no more than the maximum hydrant spacing / 2 from the nearest hydrant. 2 D NOTES Regarding FIGURE 300-A to C: 1. Example is suitable for: · DW only networks, and · NDW networks, however · For DW network of a dual water system, all hydrants installed as part of step "L" shall not be installed. 2. Colours denote unique SOB areas. 3. Uncoloured lots are part of SOBs which extend off the example area and so are incomplete. 4. Letter markings next to valves and hydrants correspond to the Step ID in Table 300-A. 5. Detailed placement of hydrants (ie: offset / inline etc) shall be as per MRWA-W-304. 6. All connections within a court bowl should be counted in with connections on the adjacent network main, (ie: where practical, court bowl SOBs shall include some network main). 120m 200m D I A WATER RESIDENTIAL COMMERCIAL HIGH DENSITY RURAL AGENCY INDUSTRIAL URBAN CWW, SEW or YVW 200m 120m 50m 500m 90m CWW 120m MFB I&J C L <DN63PE B J TABLE 300-C: MAXIMUM HYDRANT SPACINGS CFA PE < DN6 RES ERV E B Will probably all be Water Agency Owned WATER MAIN MAXIMUM MAX NUMBER NUMBER OF PROPERTIES SIZE (DN) CONNECTED VALVE SPACING VALVES OF SOB <DN150 25 (YVW), 40 (CWW & SEW) 300 / 500m * 200-300 750m 6 100 375 N/A 1000m 450 N/A 1150m 8 N/A 1500m 525 / 600 675 / 750 N/A 1900m 10 > 750 5000m # N/A * 300 in urban areas, 500 in rural areas. # Valve spacing for larger mains shall be decided in consultation with the Water Agency. G B 54 TABLE 300-B: MAXIMUM SOB SIZES F F L DN100 M Place a hydrant at the end of DN100 mains in court bowls and dead ends. Ensure fire fighting hydrant is within 60m of the furthest kerb of a dead end rd. Place a hydrant adjacent to a valve in each SOB (typically the highest valve unless the SOB includes a dead end hydrant). Placement at the highest valve is especially important where there is a significant rise in the SOB. (ie: >2m difference in elevation). Place a hydrant at the lowest point in the SOB where the SOB has a difference in elevation >5m Identify where the distance between neighboring hydrants is excessive. Place as few additional hydrants as possible in the SOB to ensure that the distance between hydrants is not excessive. · additional hydrants not required for DW network where dual water. · locate adjacent to valve(s) where practical as a first priority. · ensure the distance between hydrants is approximately equi-distant as a second priority. · all of these hydrants shall be designated "Council Owned". B TABLE 300-B DN100 D TABLE 300-B DN100 L Identify all SOBs containing a length between valves in excess of the limit. Place additional valves as required to reduce the distance to < the maximum. Identify all SOBs containing too many shut off valves. Place additional valves centrally as required to reduce the number of shut off valves. F E DN100 K F N63P DN100 J B J 0 I 10 0 53 10 C I&J <D F F DN H A L L D DN G E 3P B TABLE 300-B N6 F 12 SECTION 8.2.7.5 MRWA-W-108 <DN6PE C D E 11 DN100 <D Valve all offtakes from >DN300 mains at the tee Valve all offtakes from <DN280 mains at the splay. CWW & SEW do not require valves on DN100 offtakes from DN100 mains Valve the smaller main (if >DN100) adjacent to tapers / reducers Valve just after transition to sub-mains Valve offtakes to court bowls where there are more than 10 connections between the intersection and the valve inserted as part of Step D Identify all SOBs containing too many property service connections. Place as few valves as possible in these SOBs to meet this requirement, locating valves: · to create SOBs of approximately equal size. · at un-valved offtakes (if present). · at high points where practicable, especially where there is a significant elevation change in the SOB (ie: > 2m). DN375 DN100 A B NDW OR DW OF DUAL KEY REFERENCES DW ONLY WATER SECTION 8.2.7.2 SECTION 8.2.7.3 DN300 A 10 FIGURE 300-A: SOB DESIGN EXAMPLE - RELEVANT TO CWW (RESIDENTIAL MFB AREAS) (40 lot SOB and max 120m between hydrants shown) TABLE 300-A: RETICULATION SHUT OFF BLOCK (SOB) DESIGN PROCESS STEP PROCESS STEP DESCRIPTION 9 DN1 2 DN100 1 4 SHUT OFF BLOCK DESIGN APPERTUNANCE PLACEMENT DATE R. CARRUTHERS 01/09/16 D. O'DONOVAN D. ERREY 5 01/09/16 01/09/16 H MRWA-W-300A ISSUED 2016 6 7 8 9 10 11 VERSION NO. 2 12 1 2 3 4 5 6 FIGURE 300-B: SOB DESIGN EXAMPLE - RELEVANT TO CWW (RESIDENTIAL CFA AREAS) AND ALL SEW RESIDENTIAL AREAS (40 lot SOB and max 200m between hydrants shown) A 7 SCALE: 8 9 10 A DN10 0 L L 3 N6 <D F F F E DN100 RESERVE <DN63PE D 56 A J J H J B C F D I I&J E DN100 D <DN63PE D 56 RESERVE B 59 B K J 57 J A DN100 55 E B DN150 B C ERV 58 B DN150 RES 57 J B D DN100 DN100 RESERVE DN375 DN100 I&J I&J C F 00 00 DN1 D I 54 <DN63PE <DN6PE <DN6PE 55 E B I&J D ERV 3PE < DN6 54 DN100 DN100 I&J B E B <DN63PE RES DN375 DN100 D RESERVE I DN1 DN100 I J DN150 58 B F&H J DN150 B B C C E DN100 59 B K DN100 DN100 DN300 60 DN100 DN100 DN300 60 L 61 DN100 DN100 F DN100 F DN100 J 61 F DN100 A L DN100 A K B F F 00 0 I 53 F J E B 3PE < DN6 10 0 1 DN N63P 10 F <D DN E B I&J J F N63P F F DN100 10 0 D 53 DN DN I&J PE E 3P N6 <D D B C 12 FIGURE 300-C: SOB DESIGN EXAMPLE - RELEVANT TO ALL YVW RESIDENTIAL AREAS (25 lot SOB and max 200m between hydrants shown) 1mm = 2m at A3 This standard should be read in conjunction with MRWA-S-300A. DN100 <D 11 G G RESERVE RESERVE J F 49 50 F F DN100 49 50 R. JAGGER B. VANOS 2 1 DATE: DATE 1/12/16 CP / JT / RJ CWW B. VANOS 01/09/16 CWW FIRST DRAFT 01/05/16 CP / JT / RJ SEW C. PAXMAN 01/09/16 SEW YVW J.TOMASI 01/09/16 YVW DESCRIPTION 1 DATE 2 APPROVED 3 4 H APPROVED: NAME PUBLISHED FIRST ISSUE REV MRWA WATER SUPPLY STANDARDS DATE: DRAWN: CHECKED: NAME H F 52 51 MELBOURNE RETAIL WATER AGENCIES DESIGNED: J DN100 52 51 K DATE SHUT OFF BLOCK DESIGN EXAMPLES APPERTUNANCE PLACEMENT R. CARRUTHERS 01/09/16 D. O'DONOVAN D. ERREY 5 01/09/16 01/09/16 6 7 8 9 10 MRWA-W-300B ISSUED 2016 11 VERSION NO. 2 12 5 6 E A RELEVANT MRWA -W-300 FIGURE COLOURED PATCH (1 PER VALVE) COVER / SURROUND DISC (1 PER VALVE) POST (1 POST FOR EACH DW / NDW CLUSTER) COLOURED PATCH KERB DISC COVER / SURROUND DISC C C B A C LINE B LINE KERB B LINE C MARKER POST (TRIANGLE AT TOP TO POINT TOWARDS FITTING) PROPERTY VALVE MARKER DISC (WHEN NO KERB) REFER NOTE 4. 1800±500 VALVE OR HYDRANT LINE URBAN PROPERTY LINE RURAL AREA DEVELOPED AREA LEGEND: D KERB C G LINE E DRINKING (W) WATER MAIN LINE B A URBAN P R O P E R T Y LIN C A NDW WATER MAIN KERB RELEVANT MRWA -W-301 FIGURE 12 RB POST KE KERB 11 DEVELOPED AREA E A 10 LIN ROAD CATS EYE (BLUE) 9 RB POST 8 KE RURAL AREA OPEN RESERVES OR ROADS WITHOUT KERBS PAVED ROAD (ABUTTED BY URBAN PRIVATE PROPERTY) PAVED ROAD (ABUTTING PUBLIC OPEN SPACE OR RURAL PRIVATE PROPERTY) B 7 TABLE 300-A: HYDRANT & VALVE MARKING REQUIREMENTS NOT CLUSTERED CLUSTERED HYDRANT VALVES (PER VALVE) VALVES Valve Cluster Definition: More than 2 valves in close proximity, ie: · 3 valves within a 6m diameter circle · 4 valves within a 8m diameter circle · 5 valves within a 10m diameter circle, etc or, · As directed by the water agency (this is irrespective of whether valves are DW or NDW) A 4 DRINKING (W) WATER MAIN 3 NON-DRINKING (NDW) WATER 2 ROAD PATCH 1 MAIN FIGURE 300-A: OPEN RESERVES OR ROADS WITHOUT KERBS HYDRANT MARKER POST VALVE MARKER POST HYDRANT MARKING CATS EYE HYDRANT MARKING REFLECTIVE PATCH VALVE MARKING DISC D FIGURE 300-D: TYPICAL POSITIONING OF VALVE AND HYDRANT MARKERS FENCE ROAD CL KERB VALVE MARKER DISC DEVELOPED PROPERTY E 100 to 150 E HYDRANT PATCH FOOTPATH HYDRANT CATS EYE HYDRANT OR VALVE GENERAL NOTES: MAIN MAIN 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. FIGURE 300-B: PAVED ROAD (ABUTTED BY URBAN PRIVATE PROPERTY) F MARKER POST (TRIANGLE AT TOP TO POINT TOWARDS FITTING) KERB VALVE MARKER DISC ROAD CL 100 to 150 Valves shall be marked differently according to whether they are deemed to part of a "valve cluster" as defined in Table 300-A. All hydrants (whether temporary, DW, NDW) require the same marking as indicated in this drawing unless the hydrant is on an irrigation only or less reliable supply. When temporary end of line hydrants are removed, all markings shall be removed concurrently. When a main is renewed or decommissioned, all redundant markings shall be completed removed. 40mm washouts shall be marked as valves. Type, location, fixture arrangements and orientation of markers to be in accordance with MRWA-W-301. Refer to water agency product catalogues for details of marking products. Locate marker posts at right angles to the main with post facing towards the valve or hydrant. Where there is a valve cluster of the same network (DW or NDW) only one marker post is required at the valve cluster. Where there is a valve cluster containing both NDW and DW valves, a single DW and a single NDW post will be required. The construction contractor is to install these markings. F HYDRANT PATCH 200±100 G FOOTPATH G HYDRANT CATS EYE HYDRANT OR VALVE MAIN MAIN FIGURE 300-C: PAVED ROAD (ABUTTED BY PUBLIC OPEN SPACE OR RURAL LAND) MELBOURNE RETAIL WATER AGENCIES H REV DESCRIPTION 1 DATE 2 APPROVED 3 DESIGNED: DATE: DRAWN: CHECKED: NAME DATE: DATE CWW SEWL SEWL YVW YVW 4 H APPROVED: NAME CWW NOT TO SCALE MRWA WATER SUPPLY STANDARDS DATE VALVE AND HYDRANT MARKING ARRANGEMENTS MRWA-W-300 ISSUED 2012 5 6 7 8 9 10 11 REVISION NO. 3 12 3 4 · BLACK (FOR OPERATIONAL HYDRANTS) 1300 ± 200 (RESERVES & RURAL) 7 · RED (FOR FIRE FIGHTING NORMALLY OPEN VALVE ON <DN250 MAIN HYDRANTS) or · DARK BLUE (FOR VALVE) REFLECTOR DISC (BLUE) NORMALLY OPEN VALVE ON >DN250 MAIN NORMALLY OPEN <DN250 VALVE OFF >DN250 MAIN NORMALLY CLOSED VALVE NON-DRINKING WATER VALVES WHITE (FOR DW) or PURPLE (FOR NDW) NORMALLY OPEN VALVE ON <DN250 MAIN NORMALLY OPEN VALVE ON >DN250 MAIN NORMALLY OPEN <DN250 VALVE OFF >DN250 MAIN A. Colour patch to be preformed thermoplastic road marking product as per AS4049.2. B. The substrate shall be thoroughly cleaned or roughened and chemically treated as required to achieve a strong bond between the marking and substrate. C. Ensure divide line between colours is orientated correctly to indicate the size / status of the main on either side of the valve. 350 ± 50 >50 THESE MARKINGS TO BE INSTALLED BY CONSTRUCTION CONTRACTOR FIRE SERVICE OFFTAKE BOLT OR PIN CONCRETE SURROUND KERB VALVE MARKER DISC ABOVE GROUND HYDRANTS TO BE MARKED AS PER FIGURE 305-C. VALVE MARKER DISC BACK OF KERB FACE OF KERB EXTENT OF MARKING TRAFFICABLE VALVES IN PAVED AREAS (NO SURROUND) NON TRAFFICABLE VALVES IN CLUSTERS OR WHEN NO KERB PIN WITH KINK VALVE WITH COLOURED PATCH (REFER FIG 301-B) REFER FIG 301-E FIGURE 301-D: MARKER INSTALLATIONS EXAMPLES (PLAN VIEW) DESCRIPTION DATE 2 APPROVED 3 Lettering to be stamped or etched at least 0.03mm deep DO NOT FIT DISCS TO BLUE STONE PAINTED AREA DIVIDE VALVE (FOR USE IN MAINS > DN375) OFFTAKE OR RETICULATION VALVE SCOUR CONTROL VALVE HYDRANT CONTROL VALVE AIR VALVE CONTROL VALVE FROG MOUTH CONTROL VALVE D BYPASS VALVE CROSS CONNECTION VALVE WASHOUT Where necessary, recycled water may be indicated with a separate dedicated disc. E F 450 ± 50 CATS EYE BOND 150 FIGURE 301-F: CATS EYE WHITE ROAD PAVEMENT NOTES on Figure 301-E: 1. Attach to ground using hotmelt marker adhesive (bituminous) or two pack epoxy adhesive as per AS1906.3. 2. Apply as per manufacturers instructions. Roughen surface with cold chisel & use wire brush to thoroughly clean surface before application. 3. Cats eyes are not required at Acceptance of Works. 4. Cats eyes are required at End of Defects. DESIGNED: DATE: DRAWN: CHECKED: NAME DATE: DATE CWW SEWL SEWL YVW YVW LIP OF KERB FIGURE 301-H: ROAD PAVEMENT HYDRANT REFLECTIVE PATCH NOTES on Figure 301-H: Ø75 A. Use preformed thermoplastic road marking product, white in colour as per AS4049.2 or as per water agency products catalogue. A.A. Use wire brush to thoroughly clean surface before application. A.B. Bond using gas torch until well adhered. Apply as per manufacturers instructions. FIGURE 301-G: SPINDLE CAP FOR VALVES NOTES on Figure 301-G: 1. Required for normally shut valves (red) 2. Required for dialysis patient valves (blue). All dialysis shut off block valves shall be capped and have an attached waterproof label with the customer's address. B. Patch may be applied using vicroads approved marking G paint. C. Point triangle to hydrant (if hydrant in road, point triangle towards road center). D. Patches are not required at Acceptance of Works. E. Patches are required at End of Defects. NOT TO SCALE MRWA WATER SUPPLY STANDARDS H APPROVED: NAME CWW 4 DV V SCV HV AV FV BP XC WO VALVE TYPE 1. For fastening into concrete (kerb or surround): use 316 SS 3. For fastening to plastic covers or surrounds, grind off plastic concrete pins, pre-drilled with 5mm min masonry bit. protrusions in area to which disc is to be fitted, drill through cover 2. For fastening to ductile iron, drill hole, tap thread and fasten with and attach disc with 316 SS, M6, 60mm long cup head bolts & pan head M6, 25mm (1 inch) long 316 SS metal thread screws. 316 SS nuts and washers. MELBOURNE RETAIL WATER AGENCIES H C TABLE 301-C: VALVE DISC LETTERING DISC EXAMPLE: DRINKING WATER CROSS CONNECTION VALVE DISC EXAMPLE: NON DRINKING WATER BYPASS VALVE NDW Hydrant on main >DN250 BELOW GROUND HYDRANTS LETTER(S) Ø6.5mm BP DW Hydrant on / off main >DN250 NOTES Regarding Fastening Arrangements: FIGURE 301-E: VALVE MARKER DISCS 100 to 150 FACE TRIANGLE PATCH TOWARDS HYDRANT CENTRE OF ROAD LIP OF KERB LIP OF KERB BACK OF KERB FACE OF KERB FOOTPATH FOOTPATH 200 ± 100 Ø40mm and MIN 2mm THICK 316 SS W VALVE CONCRETE FASTENING PIN DETAIL VALVE IN ROADWAY ABUTTING OPEN SPACE REFER FIG 301-A WATER PLASTIC VALVE SURROUNDS 4.8mm OD, 50mm LONG B Hydrant connected to main >DN250 XC 250 ± 20 HYDRANT HYDRANT IN URBAN ROADWAY F DW Hydrant on main <DN250 W CONCRETE Plain (no colour) Hydrants offset from >DN250 mains or located on valve bypass NDW Hydrant on pipework shall be marked Black main <DN250 VALVE MARKER DISC FOR LONE VALVES WHERE THERE IS A KERB CENTRE OF ROAD HYDRANT KERB FASTENING POSITION 100 to 150 REFER FIG 301-F If Rectangular Cover FIGURE 301-C: HYDRANT / FLUSHING BOX COLOURS ABOVE GROUND HYDRANTS WATER A Lilac (if NDW) FOR TRAFFICABLE VALVES IN CLUSTERS OR WHEN NO KERB ROAD PAVEMENT E LIP OF KERB BACK OF KERB FACE OF KERB FOOTPATH 200 ± 100 REFER FIG 301-H 12 CONNECTED TO CONNECTED TO <DN250 MAIN >DN250 MAIN PLAIN (NO COLOUR) YELLOW RED TOP BLACK TOP 1 1 LILAC LID 2 LILAC & 2 YELLOW LILAC BELOW RED TOP LILAC BELOW BLACK TOP BELOW GROUND ABOVE GROUND BELOW GROUND ABOVE GROUND TRAFFICABLE VALVE SURROUNDS HYDRANT IN ROADWAY ABUTTING OPEN SPACE MARKER POST 11 LEVEL DIALYSIS SOB VALVE TRAFFICABLE VALVES IN NATURE STRIPS 1 DW DW NDW NDW NORMALLY CLOSED VALVE VALVE D REV SYSTEM Hydrant connected to main <DN250 CEMENT STABILIZED SOIL (5%) FIGURE 301-A: MARKER POST INSTALLATION (SECTION VIEW) MARKER POST 10 OTHER VALVES >250 G 9 TABLE 301-B: HYDRANT / FLUSHING BOX COLOURS DRINKING WATER VALVES POST AS PER WATER AGENCY PRODUCT CATALOGUE REFER FIG 301-A 8 NOTES Regarding Figure 301-B: A C 6 FIGURE 301-B: VALVE SURROUND COLOURING H (FOR HYDRANT) or V (FOR VALVE) POINT THE POST TRIANGLE TO THE SURFACE FITTING AND ROAD B 5 70 2 70 1 DATE MRWA-W-301 VALVE AND HYDRANT MARKING DETAILS (CWW and SEW ONLY) ISSUED 2012 5 6 7 8 9 10 11 REVISION NO. 3 12 1 2 3 4 5 6 7 8 9 10 a. A All surface box covers and frames to be in accordance with AS 3996: class D loading trafficable and the water agency product catalogue. Hinge covers to close in the direction of traffic. When the valve is part of a valve cluster or there is no kerb, the valve cover shall be fitted with an identification disc. Refer MRWA-W-300 & 301 for details. No surround is required for valve covers in road pavement. b. c. d. 12 NON TRAFFICABLE NOTES on Valves in Road Pavement: TRAFFICABLE 11 A VALVE DISC MARKER ( IF REQUIRED) SV WATER WATER VALVE VALVE NOTES on Valves in Nature Strips & Open Reserves: Valve markings refer MRWA-W-301 Valve markings refer MRWA-W-301 B PAVEMENT Valve disc marker ( if required) FSL Concrete surround (if required). Refer Note C. 100 to 350 C A. Where the main is aligned close to the kerb such that non trafficable covers (which are larger) would clash with the kerb, trafficable covers shall be used (which are substantially smaller). B. Non trafficable covers shall not be cut down in size. C. Trafficable covers with concrete surrounds shall be used in nature strips where vehicles are likely to regularly mount the kerb (Refer Figure 302-C). This includes : C.A. All valves within industrial or commercial driveways, C.B. All valves within 5m of any road intersections. C.C. All valves within 2m of residential driveways. D. Elevate cover up to 75 above finished surface level and grade soil away to reduce water entry into the shroud. E. Hinge covers to close in the direction of fall of land. F. When the valve is part of a valve cluster or there is no kerb, the valve surround shall be fitted with an identification disc. Refer MRWA-W-300 & 301 for details. Compacted crushed rock as per MRWA-W-201 (Type R in road pavement) (Type F in nature strip). Shroud must be clear of surface fitting GRADE Plastic surround 100 to 350 50 30 Minimum cover compacted crushed rock over lip of cover C KERB 2 cups cement spread over surface of compacted crushed rock 5m 2m RESIDENTIAL DRIVEWAY 150 / 225 DWV white PVC SN4 pipe shroud Compacted crushed rock as per MRWA-W-201 (Type F). 150 / 225 DWV white PVC SN4 pipe shroud 5m FIGURE 302- A: TYPE A TRAFFICABLE VALVE SURFACE ARRANGEMENT D KERB D Minimum cover of nature strip top soil Shroud must be clear of surface fitting > 400 2m 2 of 300 x 300 x 50 Approved hardwood, recycled plastic or concrete support B Valve disc marker ( if required) Valve markings refer MRWA-W-301 TRAFFICABLE COVERS REQUIRED IN THESE PARTS OF THE NATURE STRIP FIGURE 302-D: DRINKING WATER NON TRAFFICABLE VALVE SURFACE ARRANGEMENT VALVE DISC MARKER ( IF REQUIRED) DIRECTION OF TRAFFIC KERB HINGE S.V TRAFFICABLE COVERS REQUIRED IN INDUSTRIAL AREAS WATER VALVE E FIGURE 302-C: TRAFFICABLE VALVE COVERS IN NON TRAFFICABLE AREAS Valve disc marker ( if required) Valve markings refer MRWA-W-301 100 to 350 Shroud must be clear of surface fitting G 2 of 300 x 300 x 50 Approved hardwood, recycled plastic or concrete support GENERAL NOTES: 150 / 225 DWV white PVC SN4 pipe shroud FIGURE 302- B: TYPE B TRAFFICABLE VALVE SURFACE ARRANGEMENT R. JAGGER 1/12/16 CP / JT / RJ 2 PUBLISHED FIRST ISSUE 04/04/12 R.JAGGER X CWW C. RIVETTE 04/04/12 X CWW 1 PRE PUBLISHED DRAFT FOR COMMENT 12/07/11 R.JAGGER X SEWL C.PAXMAN 04/04/12 X SEWL G.REYNOLDS 04/04/12 X YVW K.DAWSON 04/04/12 X YVW A.COSHAM 04/04/12 1 2 APPROVED 3 4 Compacted crushed rock as per MRWA-W-201 (Type F). 150 / 225 DWV white PVC SN4 pipe shroud MRWA WATER SUPPLY STANDARDS 04/04/2011 DATE: 04/04/2011 NEW FIGURE 302-C DATE F > 400 2 cups cement spread over surface of compacted crushed rock DATE: 3 DESCRIPTION >30 Minimum cover compacted crushed rock over lip of cover G FIGURE 302-E: NON-DRINKING WATER NON TRAFFICABLE VALVE SURFACE ARRANGEMENT DRAWN: D. TOLENTINO DATE CHECKED: NAME REV >50 100 to 350 MELBOURNE RETAIL WATER AGENCIES H GRADE Plastic surround NOT FOR USE IN YARRA VALLEY WATER AREA DESIGNED: Minimum cover of nature strip top soil Shroud must be clear of surface fitting 1. Provide a level compacted crushed rock foundation for all covers, surrounds and shrouds (as shown) to the embedment material. Crushed rock to be in accordance with MRWA-W-201. 2. A gap is required between the cover and shroud. The shroud shall be cut at 90 degrees. The shroud shall not contact the cover & be kept > 20 mm clear. 3. Install cover, frame, spindle sleeve, shroud and shroud support so that no loading is transmitted to the valve or pipe. 4. Install an extension spindle where distance from the surface to valve spindle exceeds 350. Fix false spindle to the valve spindle using supplied grub screw where practical. 5. Refer to MRWA-W-205A for stop valve installation details. 6. For non-drinking water valves, the words / letters: "non-drinking water" or "NDW" or "RW" shall be cast / stamped/ embossed or engraved into the cover or lid. 7. For drinking water valves, the words / letters: "Water" or "W" or "Drinking Water" shall be cast / stamped/ embossed or engraved into the cover or lid. 8. For valve marking arrangements refer to MRWA-W-300 & 301. 9. Refer to water agency products catalogue for authorized materials. Compacted crushed rock as per MRWA-W-201 (Type R in road pavement) (Type F in nature strip). Valve disc marker ( if required) Valve markings refer MRWA-W-301 PAVEMENT FSL F E FOOTPATH APPROVED: NAME NOT TO SCALE H DATE VALVE SURFACE ARRANGEMENTS TRAFFICABLE & NON-TRAFFICABLE AREAS R.CARRUTHERS 04/04/12 5 6 7 8 9 10 MRWA-W-302 ISSUED 2012 11 REVISION NO. 3 12 2 3 4 5 6 B >50 GRADE ROUND (NDW) SHOWN Minimum cover of nature strip top soil 12 Minimum cover of nature strip top soil A GRADE FSL 100 to 250 > 400 B Shroud must be clear of surface fitting NOTES on Hydrants in Nature Strips & Open Reserves: a. 225 DWV white PVC SN4 pipe shroud b. c. FIGURE 303-A: NON TRAFFICABLE NON-DRINKING WATER HYDRANT COVERS ROUND (IF NDW) AND SQUARE (IF DW) C d. Hydrant marking if NDW. Refer MRWA-W-01 BOLT AND MAIN ALIGNMENT Hydrant head orientation under the cover Where the main is aligned close to the kerb such that non trafficable covers (which are larger) would clash with the kerb, trafficable covers shall be used (which are substantially smaller). Non trafficable covers shall not be cut down in size. Trafficable covers with concrete surrounds shall be used in nature strips where vehicles are likely to regularly mount the kerb (Ref Figure 303-C). This includes: c.a. All hydrants in industrial areas, c.b. All hydrants within 5m of any road intersections, c.c. All hydrants within 2m of residential driveways. Elevate cover up to 75 above finished surface level and grade soil away to prevent water entry. 2m KERB 2m 5m RESIDENTIAL DRIVEWAY Compacted crushed rock as per MRWA-W-201 (Type R in road pavement) (Type F in nature strip). 5m KERB Concrete surround. Refer Note c (if required). PE flushing box & lid Only SEW allow use of all in one valve controlled hydrant All in one valve controlled hydrant shown. Same arrangement for flushing boxes. FIGURE 303-D: NON TRAFFICABLE COVERS FOR ALL IN ONE VALVE CONTROLLED HYDRANTS OR FLUSHING BOXES C 600 standard Class D heavy cover Hydrant marking if NDW refer MRWA-W-301 TRAFFICABLE COVERS REQUIRED IN THESE PARTS OF THE NATURE STRIP 2 of 300 x 300 x 50 Approved hardwood, recycled plastic or concrete support FSL 100 to 250 600 reinforced concrete or MC shaft and cover arrangement as per Fig 306-C(i) from sewerage standards PAVEMENT 100 to 250 Compacted crushed rock as per MRWA-W-201 (Type F trafficable area) PAVEMENT FSL E 11 Minimum cover compacted crushed rock over lip of cover > 300 Compacted crush rock as per MRWA-W-201 (Type F trafficable area) D 10 A. Hinge covers to close in the direction of the adjacent road lane traffic. B. In trafficable areas a hardwood, recycled plastic or concrete bearer is required to support the surface fitting. C. No surround is required for trafficable hydrant covers. >30 2 cups cement spread over surface of compacted crushed rock 9 NOTES on Hydrants in Road Pavement: A 100 - 250 8 Purple if NDW Hydrant marking if NDW. Refer MRWA-W-301 FSL 7 >50 1 Flushing box shown. Same arrangement for all in one valve controlled hydrant (SEW only) . 4 of 300 X 300 X 50 Approved hardwood, recycled plastic or concrete supports, one each side of shaft. D Compacted Crushed Rock as per MRWA-W-201 (Type R trafficable area) FIGURE 303-E: TRAFFICABLE COVER FOR ROADS FOR ALL IN ONE VALVE CONTROLLED HYDRANTS OR FLUSHING BOXES E KERB TRAFFICABLE HYDRANT REQUIRED IN INDUSTRIAL AREAS FIGURE 303-B: TRAFFICABLE AREA HYDRANT COVERS Hydrant marking if NDW refer MRWA-W-301 FOOTPATH Hinged heavy cover (ie: large fitzroy box) FSL F GENERAL NOTES: 1. 2. 3. 4. 5. G 6. 7. F FIGURE 303-C: TRAFFICABLE HYDRANT COVERS IN NON TRAFFICABLE AREAS Provide a level compacted crushed rock foundation for all covers, surrounds and shrouds (as shown) to the embedment material. Crushed rock to be in accordance with the trafficable section of MRWA-W-201. A gap is required between the cover and shroud. The shroud shall be cut at 90 degrees. The shroud shall not contact the cover & be kept > 20 mm clear. Install cover, surround, spindle sleeve, shroud and shroud support so that no loading is transmitted to the valve or pipe. For non-drinking water hydrants & washouts, the words / letters: "Non-Drinking Water" or "NDW" or "RW" shall be cast / stamped/ embossed or engraved into the cover or lid. For drinking water hydrants & washouts, the words / letters: "Water" or "W" or "Drinking Water" shall be cast / stamped/ embossed or engraved into the cover or lid. For hydrant marking arrangements refer to MRWA-W-300 & 301. Refer to water agency products catalogue for authorized materials. PE non trafficable flushing box with cover & top lip removed All in One Hydrant Controlled Valve & Flushing Box Fittings: · Covers and frames for all in one valve controlled hydrants, washouts and below ground · · domestic meters can be constructed in this way. Cover must be appropriately labeled as "hydrant" or "washout" / "flushing box" or "meter". Only SEW allow the use of all in one valve controlled hydrants. MELBOURNE RETAIL WATER AGENCIES DESIGNED: R. JAGGER 3 REMOVE OLD DETAIL A. NEW FIG 303-C 1/12/16 RJ / CP / JT 2 PUBLISHED FIRST ISSUE 04/04/12 R.JAGGER X CWW C. RIVETTE 04/04/12 X CWW 1 PRE PUBLISHED DRAFT FOR COMMENT 12/07/11 R.JAGGER X SEWL C.PAXMAN 04/04/12 X SEWL G.REYNOLDS 04/04/12 X YVW K.DAWSON 04/04/12 X YVW A.COSHAM 04/04/12 REV DESCRIPTION 1 DATE 2 APPROVED 3 4 APPROVED: NAME Compacted Crushed Rock as per MRWA-W-201 (Type R trafficable area) G FIGURE 303- F: DRIVEWAY, PARKING BAY & FOOTPATH COVERS FOR ALL IN ONE VALVE CONTROLLED HYDRANTS OR FLUSHING BOXES NOT TO SCALE H DATE MRWA-W-303 HYDRANT & WASHOUT SURFACE ARRANGEMENTS R.CARRUTHERS 04/04/12 5 Flushing box shown. Same arrangement for all in one valve controlled hydrant (SEW only). MRWA WATER SUPPLY STANDARDS 04/04/2011 DATE: 04/04/2011 DATE: DRAWN: D. TOLENTINO DATE CHECKED: NAME H > 100 CONCRETE 100 to 250 ISSUED 2012 6 7 8 9 10 11 REVISION NO. 3 12 1 2 3 4 5 6 7 8 9 TABLE 304-A: HYDRANT AND AIR VALVE SELECTION AND ARRANGEMENTS 10 11 12 NOTES Regarding Table 304-A: 1. A 2. 3. 4. B 5. 6. 7. 8. C 9. 10. 11. Hydrants typically used alone between DN250 to <=DN375 unless the main has a significant rise or fall or the main is pumped or has a PRV (in which case an air valve will likely be required). All air valves shall be combination (dual action) air valves. Air valves plus hydrants are typically required on mains >DN375. The designer shall undertake hydraulic and air handling analysis to confirm the optimum fitting type, size and location of air fittings. Air valve requirements should be determined using water agency approved air valve supplier software (and software settings used by the water agency) and an appropriate surge analysis. Options nominated first are preferred if practical. Offsetting the fitting may be impracticable if there is no space in the non trafficable area and there is no reasonable opportunity to make enough space by altering the location of other assets. Locating the air valve below ground may be impracticable if: A- the surface cannot be raised to above the 1 in 100 year flood level, or B- there is inadequate cover over the main to locate the surface fitting below ground and it is unreasonable to lower the main to accommodate the surface fitting below ground, or C- there is inadequate clearance from other buried assets and those assets cannot be reasonably moved. YVW air valves must be Offset and Above Ground. If this is not possible, contact YVW. Locate hydrant away from areas where vehicles will likely park. Locate hydrants >3m from kerb and in front of driveways or within 10m of an intersection. Above ground in line air valves are not acceptable as above ground fittings must have a valve at the offtake (in case they get knocked over)). Select iii or iv according to where the surface fitting could be best located. Require min 2m offset of above ground fitting from offtake valve. Require 800 separation of below ground air fitting and offtake valve. In line hydrants connected to >DN250 trafficable mains would only be acceptable if there was no alternative. There is no other option than for air valves connected to trafficable mains to be offset and located in a non trafficable location. For above ground air valves, they should be located as far from the road pavement as practical and in such a way as to minimise the chance of accidental collision. A B C GENERAL NOTES: 1. 2. 3. D >200 FSL Main connection detail as per FIG 305-G or H F Surface fitting detail as per FIG 305: A, D, E or F If FIG 304:iv. Vertical bend >DN250 MAIN ROAD PAVEMENT Main connection detail as per FIG 305: I, J of K FALL If FIG 304:iii Horizontal bend followed by vertical bend at end of line. FIGURE 304-i: SECTION VIEW. IN LINE ARRANGEMENT BACK OF KERB Surface fitting detail as per FIG 305- A, B, C or D E Valve required where "offtake valve" indicated in Table 304-A. DN100 DN100 pipework. Require a DN150 to DN100 taper where A.V is >DN100. FOOTWAY RESERVE OR MEDIAN STRIP VALVE >800 (if below ground), or >2m (if above ground A.V) FIG 305-A HYDRANT (IF WITH AIR VALVE) ROAD PAVEMENT R. JAGGER >800 (if below ground), or >2m (if above ground A.V & YVW) >5m (if above ground A.V & CWW or SEW) For hydrants and <DN100 air valves, DN100 pipework. For >DN100 air valves, DN150 pipework. VALVE (IF REQUIRED) Valve required where "offtake valve" indicated in Table 304-A. CLARIFIED PREFERENCES 1/12/16 RJ / CP / JT 2 PUBLISHED FIRST ISSUE 04/04/12 R.JAGGER X CWW C. RIVETTE 04/04/12 X CWW 1 PRE PUBLISHED DRAFT FOR COMMENT 12/07/11 R.JAGGER X SEWL C.PAXMAN 04/04/12 X SEWL G.REYNOLDS 04/04/12 X YVW K.DAWSON 04/04/12 X YVW A.COSHAM 04/04/12 DATE APPROVED 3 4 APPROVED: NAME NOT TO SCALE H DATE HYDRANT AND AIR VALVE ARRANGEMENTS R.CARRUTHERS 04/04/12 5 G FIGURE 304-iv: STANDARD OFFSET ARRANGEMENT (PLAN) MRWA WATER SUPPLY STANDARDS 20/02/2011 DATE: 20/02/2011 3 2 ROAD PAVEMENT MAIN DATE: DRAWN: D. TOLENTINO DATE CHECKED: NAME H F BACK OF KERB MELBOURNE RETAIL WATER AGENCIES DESIGNED: FIG 305-A, D, E or F AIR VALVE OR HYDRANT >200 >200 FIGURE 304-iii: DOUBLE OFFSET ARRANGEMENT (PLAN) 1 >800 FOOTWAY RESERVE OR MEDIAN STRIP FIG 305-A, D, E or F AIR VALVE OR HYDRANT >800 MAIN DESCRIPTION E VALVE FIGURE 304-ii: SECTION VIEW. TYPICAL OFFSET ARRANGEMENTS G REV >DN250 MAIN FIG 305-A HYDRANT (IF WITH AIR VALVE) BACK OF KERB VALVE (IF REQUIRED) D >800 FIG 305-A, D, E or F AIR VALVE OR HYDRANT Valve required where "offtake valve" indicated in Table 304-A. For definitions of trafficable and non-trafficable refer to MRWA-W-201. Require an air egress fitting between any two valves to facilitate charging of the water mains. Hydrants shall be located adjacent to valves wherever possible (as per Figure 205-K). 6 7 8 9 10 MRWA-W-304 ISSUED 2012 11 REVISION NO. 3 12 1 2 3 4 5 6 7 8 9 10 11 12 LEGEND A NOTE: HYDRANT (FIG 305-A) HYDRANT OR AIR VALVE (FIG 305-A, D, E or F) ALL IN ONE VALVED HYDRANT (FIG 305-B) FRONT BOUNDARY ALWAYS LOCATE NATURE STRIP VALVES AND HYDRANTS AS CLOSE AS PRACTICAL TO THE SPLAY CORNER Underground fittings may be single offset where practical. Above ground fittings shall be double offset where practical. AIR VALVE (FIG 305-D, E or F) > DN250 MAIN KERB Locate valves and hydrants in the nature strip as close to the splay corner as practical VALVED RISER PLUS HYDRANT OR AIR VALVE (FIG 305-C or D) FIGURE 304B-D: CWW-SEW- YVW NON TRAFFICABLE MAIN >DN250 · · · · B FRONT BOUNDARY <DN250 FRONT BOUNDARY MAIN IN LINE VALVED RISER PLUS AIR FITTING. WHEN FIG 304B-C CANNOT BE INSTALLED DUE TO SITE CONSTRAINTS. CWW or YVW IN LINE HYDRANTS or CWW or SEW BELOW GROUND AIR VALVES. > DN250 MAIN KERB FRONT BOUNDARY KERB C > FIGURE 304B-C: NON TRAFFICABLE MAIN >DN250 FIGURE 304B-A: CWW-SEW-YVW NON TRAFFICABLE MAIN <DN250 · FIGURE 304B-B: SEW NON TRAFFICABLE HYDRANTS ON MAINS >DN250 IN LINE STANDARD HYDRANT CWW or YVW- OFFSET VALVE CONTROLLED HYDRANT OR AIR VALVE SEW- OFFSET VALVE CONTROLLED AIR VALVE YVW AIR VALVE TO BE ABOVE GROUND ALL OTHER FITTINGS TO BE BELOW GROUND · · · · IN LINE ALL IN ONE VALVED HYDRANT TRAFFICABLE MAINS <DN250 C DN450 MAIN KERB FIGURE 304B-E: NON TRAFFICABLE MAIN >DN450 · · · NON TRAFFICABLE OFFSET VALVE CONTROLLED AIR VALVE + HYDRANT YVW AIR VALVE SHALL BE ABOVE GROUND CWW - SEW AIR VALVE SHALL BE BELOW GROUND D D FRONT BOUNDARY FRONT BOUNDARY FRONT BOUNDARY NON TRAFFICABLE AREA > 5m > KERB E B FRONT BOUNDARY > DN250 MAIN KERB A <DN250 KERB MAIN <DN250 > 3m FIGURE 304B-F: SEW TRAFFICABLE MAIN <DN250 FIGURE 304B-G: CWW-YVW TRAFFICABLE MAIN <DN250 IN LINE STANDARD BELOW GROUND HYDRANT OFFSET STANDARD BELOW GROUND HYDRANT <DN250 < 10m > MAIN · TRAFFICABLE MAINS >DN250 · DN450 MAIN ROAD PAVEMENT > DN250 MAIN E FIGURE 304B-H: CWW-YVW TRAFFICABLE MAIN <DN250 · > DN250 MAIN KERB KERB MAIN DN450 MAIN FIGURE 304B-I: CWW-SEW ABOVE GROUND AIR VALVES IN LINE STANDARD BELOW GROUND HYDRANT WHERE IT IS IMPRACTICAL TO OFFSET LOCATE HYDRANT IN FRONT OF DRIVEWAY OR WITHIN 10m OF INTERSECTION, and OFFSET >3m FROM BACK OF KERB WHERE PRACTICAL. · · · WHERE BELOW GROUND AIR VALVE IMPRACTICABLE. LOCATE ABOVE GROUND AIR VALVES IN NON TRAFFICABLE AREAS > 5m FROM ROAD PAVEMENT. MAIN MAY BE LOCATED IN A NON TRAFFICABLE OR TRAFFICABLE AREA. F F > DN250 MAIN FRONT BOUNDARY KERB KERB > 3m SEW Shown G FRONT BOUNDARY < 10m > DN250 MAIN > KERB > CWW / YVW Shown FIGURE 304B-L: CWW-SEW-YVW TRAFFICABLE MAIN >DN450 FIGURE 304B-J: CWW-SEW-YVW TRAFFICABLE MAIN >DN250 · · · DN450 MAIN VALVE CONTROLLED OFFSET BELOW GROUND HYDRANT OR AIR VALVE YVW AIR VALVE TO BE ABOVE GROUND ALL OTHER FITTINGS TO BE BELOW GROUND FIGURE 304B-K: CWW-SEW-YVW TRAFFICABLE MAIN >DN250 · · · in line below ground valved hydrants or air valves where it is impractical to offset locate hydrant or air valve in front of driveway or within 10m of intersection, and offset main >3m from back of kerb. · · · OFFSET VALVE CONTROLLED AIR VALVE PLUS HYDRANT YVW AIR VALVE TO BE ABOVE GROUND ALL OTHER FITTINGS TO BE BELOW GROUND MELBOURNE RETAIL WATER AGENCIES DESIGNED: R. JAGGER DATE APPROVED: NAME PUBLISHED FIRST ISSUE 01/12/16 RJ / CP / JT X CWW B. VANOS 1/10/2016 X CWW R.CARRUTHERS 1/12/2016 1 PRE PUBLISHED DRAFT FOR COMMENT 12/03/16 RJ / CP / JT X SEWL C. PAXMAN 1/10/2016 X SEWL D. O'DONOVAN 1/12/2016 X YVW J. TOMASI 1/10/2016 X YVW DESCRIPTION 1 DATE 2 APPROVED 3 4 D. ERREY 5 KERB G FIGURE 304B-M: CWW-SEW-YVW DIVIDE VALVE ON MAIN >DN450 · · OFFSET BYPASS WITH HYDRANT AND AIR VALVE. AIR VALVE LIKELY REQUIRED WHERE THIS IS AT A DISTINCT HIGH POINT NOT TO SCALE H DATE 2 REV DN450 MAIN MRWA WATER SUPPLY STANDARDS 1/02/2016 DATE: 1/02/2016 DATE: DRAWN: R. JAGGER CHECKED: NAME H FRONT BOUNDARY <DN250 MAIN FRONT BOUNDARY HYDRANT AND AIR VALVE ARRANGEMENT EXAMPLES 1/12/2016 MRWA-W-304B ISSUED 2016 6 7 8 9 10 11 REVISION NO. 2 12 1 2 3 4 5 6 7 HYDRANT SURFACE DETAILS Install markings as per MRWA-W-301 FSL A FSL 9 Install markings as per MRWA-W-301 Standard 600 shaft (concrete or PP). If PP, install as per Fig 306C(i) from sewerage standards Install markings as per MRWA-W-301 8 2. 3. DN100 >100 APPROVED BALL OR BUTTERFLY VALVE DN100 IN LINE ONLY FIGURE 305-C: BELOW GROUND IN LINE HYDRANT WITH ISOLATION VALVE · Only for SEW for mains >DN250 · Only spring hydrants permitted. · Non-trafficable where practical. · Refer to MRWA-W-303 for details. · Not to be offset from main. 1. Use for CWW or YVW where: · Main is >DN250 . 3. Only use spring hydrants. · An offset hydrant would normally be required but this requirement cannot 4. All such hydrants are to be Water Agency owned and not included as part of fire practically be accommodated due to site constraints, ie: other assets too close. fighting spacing (as cannot be accessed by fire fighters). 2. Non-trafficable where practical. 5. Approved polymeric (non-trafficable) or concrete (trafficable) shaft may be used. C Standard 600 or 1070 shaft (concrete or PP). If 600PP, install as per Fig 306C(i) from sewerage standards 600 CLASS D COVER (if 600 shaft) 750 CLASS D COVER (if 1070 shaft) FSL shall be above the 1 in 100 year flood level 5mm thick aluminum checker plate lid with stiffening spacers <600 if Practical 20mm bleed with 316 ss ball valve Ball or butterfly valve. Required only if in line main connection. 20mm bleed with 316 ss ball valve FIGURE 305-I: OFFSET HYDRANT CONNECTION TO MAINS <DN150 > 300 & > 31 SHAFT HEIGHT 2 cups cement spread over surface Concrete surround Compacted 20mm single sized crushed rock FIGURE 305-F: ABOVE GROUND SMALL AIR VALVES FIGURE 305-D: BELOW GROUND AIR VALVE WITH ISOLATION VALVE F G 1. Only for CWW & SEW air valves in non trafficable areas where the air valve is short and would not protrude above ground. 2. Not preferred by YVW. 3. Approved polymeric or concrete shaft may be used as per gravity sewerage standards. 4. 40mm diameter holes to be cut into cover (or use grated cover) equal in area to 1.5 x the air valve orifice area. The cover, once holed, is no longer capable of withstanding the traffic loads. 5. Cover should lie 25mm above the surrounding natural surface level (not to protrude excessively above ground). Surface level shall be above the 1 in 100 year flood level. 6. Valve not required at the offtake where the in line arrangement is used. Loose locating brackets at 10 and 2 o'clock PERSPECTIVE VIEW OF TOP OF SHAFT ARRANGEMENT 1. Use only concrete shaft. 2. Use sufficient 316SS fastened or welded aluminum stiffening angle to support cover to ensure <10mm deflection with a centered 100 kg load. 3. Locate shaft well back from roadway (ie: >5m) if CWW or SEW. AIR VALVE DETAILS DESCRIPTION 1 DATE 2 APPROVED 3 D · Fit valve directly to the offtake tee. FIGURE 305-H: IN LINE AIR VALVE CONNECTION TO MAINS >DN375 DATE: DRAWN: CHECKED: NAME DATE: DATE h NOTES Regarding Air Valves: 1. 2. 3. 4. All options posed here are non trafficable. Air valves shall not be located in trafficable locations. Air valve and riser pipe (from main) should be sized according to the orifice cross sectional area(s), not the bore area of the air valve. Where an air valve > DN200 is calculated as required, multiple smaller valves shall be installed on a manifold instead (ie. 2 x DN200 should be used instead of a single DN300) and the shaft designed accordingly. Air valve marking arrangements only required where L type hydrant covers are used. CWW SEWL SEWL YVW YVW 4 unusually deep (> 1300mm) &/or an above ground air valve is to be constructed. · 'd' and 'h' should be > 0.5 x 'D' D FIGURE 305-K: OFFSET AIR VALVE CONNECTION TO MAINS >DN375 · Only for use in conjunction with Figures 305-D, E or F. · Only usually possible where the water main is unusually deep (> 1300mm) &/or an above G ground air valve is to be constructed. · 'd' and 'h' should be > 0.5 x 'D' · Place special flanged bend directly on tee to initiate a horizontal alignment. MAIN CONNECTION DETAILS NOT TO SCALE MRWA WATER SUPPLY STANDARDS H APPROVED: NAME CWW F d · Only for use in conjunction with Figure · Only possible where the water main is MELBOURNE RETAIL WATER AGENCIES DESIGNED: E D, E or F. 1. Use where not SEW and: 1.1. The required air valve is small enough to fit within the cover, and 1.2. For YVW air valves, or 1.3. For CWW air valves when the air valve is well back from the road (ie: >5m). 2. 40mm diameter holes to be drilled into cover equivalent in area to at least 1.5 x the air valve orifice area. 305-D. 1. Isolation valve must be operable from surface if 600Ø shaft is used to house the air valve. 4. Minimise pit depth, step irons required for 1070Ø shaft > 1000 deep. 2. Approved 600Ø sewer maintenance shaft and cover preferred for air valves less than 300Ø. 5. Lay shaft and supports on compacted 20mm single sized crushed rock (self draining) to 95% rd density. 3. Approved 1070Ø sewer access shaft shall be used for air valves greater than 300 in width. This crushed rock should extent to the embedment layer, extend the full width of the trench 600 neck shall be located over clear ground (not over the air valve). and to a distance of 1m from fitting in both directions. REV FIGURE 305-J: INVERTED SCOUR TEE CONNECTION FOR MAINS >DN225 · Only for use in conjunction with Figures 305-A, FIGURE 305-E: ABOVE GROUND LARGER AIR VALVES NOTES Regarding Details D & E: H d h M12, 316ss bolts 6mm thick, 60mm wide 316ss strap Connect to nearby drain if practical hydrant / air valve and the offtake tee. FIGURE 305-G: STANDARD IN LINE CONNECTION Compacted crushed rock as per MRWA-W-201 (Type F) OFFSET ONLY PADLOCK IN LINE OR OFFSET D Only for use in conjunction with Figures 305-A, B, C or D. Compacted crushed rock as per MRWA-W-201 (Type F) OFFSET ONLY E · Only for use in conjunction with Figure 305-A. · A valve is usually not fitted between the FSL >300 >100 300 x 300 x 50 (4 No.) approved recycled plastic or concrete support >300 >100 Lilac (if NDW) 70 500 to 1000 100 to 250 D C Black 100 to 250 <600 if Practical FSL 300 x 300 x 50 (4 No.) approved recycled plastic or concrete support >300 A Compacted crushed rock as per MRWA-W-201 (Type F / R) FIGURE 305-B: BELOW GROUND ALL IN 1 VALVED HYDRANT FIGURE 305-A: BELOW GROUND HYDRANT · This is the standard for retic pipelines. · Trafficable or non-trafficable. · Only spring hydrants permitted. · Refer to MRWA-W-303 for details. 4. Refer to MRWA-W-303 for surface cover arrangements for hydrants. Refer Table 301-B for hydrant marking arrangements. Hydrants are not to be used in low pressure applications (< 20 m), eg: some irrigation only NDW systems. Spring hydrants are not automatic and require manual opening to allow air ingress and egress. B IN LINE ONLY IN LINE 1. 100 to 250 Di riser length to suit 12 NOTES on Figures 305-A, B & C: FSL SPACER OFFSET 11 600 CLASS B/D COVER <600 if Practical B 10 DATE 5 HYDRANT AND AIR VALVE FITTING DETAILS 6 7 8 9 10 MRWA-W-305 ISSUED 2012 11 REVISION NO. 3 12 1 2 3 4 5 GASKET WASHER 7 8 9 Overlap protective tape over primer by min 150 Overlap primer over pipe coating by min 200 MASTIC FILLER B PRIMER MASTIC FILLER 2 x MS, or 2 x MS, or 2 x DI 2 x DI flanges flanges ACCEPTABLE PIPE COATING 11 Insulation top hat (if required- see note B) WASHER Corrosion protection tape OVER WRAPPING TAPE 10 Corrosion protection tape Fill gap between raised flange faces with primer or mastic A Overlap protective tape over primer by min 150 6 12 Fill gap between raised flange faces with primer or mastic Over wrapping tape A PRIMER Overlap primer over pipe coating by min 200 GASKET MASTIC FILLER MASTIC FILLER B FBE COATED DI FITTING UNCOATED MSCL OR DI FLANGE FIGURE 306A-A: CORROSION PROTECTION OF 2 x DI or 2 x MS UNCOATED FLANGES CEMENT MORTAR REINSTATEMENT 5 mm FIGURE 306A-B: CORROSION PROTECTION OF AN UNCOATED FLANGE CONNECTED TO A COATED FITTING NOTES on Corrosion Protection: C D A. Embedment shall be scalloped under the flanges to enable tape to be wound underneath. B. Insert nylon or acetyl copolymer thermoplastic based insulation top hats with fasteners into all flange holes when mating flange materials are dissimilar, ie: if both flanges are DI or both flanges are steel, no fastener insulation is required. Where flange insulation is required, test flange insulation in accordance with CORR-24. C. FBE coated flange holes shall not be drilled out to make them larger for top hat insertion. Greater than 0.5mm thick sleeving and insulating washers or top hats thin enough to be inserted into flange holes shall be used. This is usually required for M16 & M24 bolt holes. D. Corrosion protection described here is required for all steel or ductile iron flange surfaces which do not have a high integrity coating consisting of one of the following: D.A. Heat applied MDPE PE coating to AS4321. D.B. Fusion bonded epoxy coating to AS/NZS 4158. E. F. G. H. I. D.C. Ductile iron pipe with zinc coating to 200 mg/m² to BS/EN 545. D.D. Ductile iron pipe with polyurethane coating to EN 545 or ISO 2531. Bare, bitumen coated or painted surfaces are not acceptable coatings. These surfaces will be referred to as uncoated. All corrosion protection products shall be as per the water agency product catalogue. Products from a single manufacturer shall be used to ensure compatibility of products. All products shall be applied as per the manufacturers instructions. Step 1: Surface Preparation- All surfaces to be primed shall be prepared to a finish of ST2.5 according to AS 1627.2 class SA2.5. Power wire brush remove all scale, loose rust and old flaking coating. Chisel off all weld splatter and slag. Step 2: Primer- Shall be applied by brush or spray to all uncoated surfaces to a distance of 200mm past coated pipe / fittings. The entire area to be wrapped shall be primed, including all flanges and bolts. Choose one of Mastic or Cap plus mastic / gel SS backing ring FBE coated flange Puddle Flange Thickness Extrusion Weld (full circumference on both sides) Fbe coated di fittings Double thickness of low density PE sleeve E Anticorrosion gel or mastic SS bolt, nut & washers PE stub flange PVC heavy duty "duct tape" TABLE 306A-A: PE PUDDLE FLANGE DIMENSIONS FOR PE MAINS F FIGURE 306A-D: CORROSION PROTECTION FOR GALVANISED BOLTS WITH COATED FLANGES A. B. NOTES Regarding Galvanised Fastener Protection & Corrosive Ground Conditions: C. D. G E. All flanges are to be raised face type. Steel flanges shall be welded in an ISO9001 accredited workshop. No on site welding of steel flanges is permitted. For flange, gasket and fastening details, refer to MRWA-W-306B. Corrosion protection is not required for concrete encased puddle flanges. Any FBE coated fittings which are damaged to the point where bare metal is exposed shall be repaired with a repair product approved by the manufacturer. Otherwise it shall be quarantined and not installed. · · · · Caps and sleeving as shown above are not required where Figure 306A-A or B apply. Stainless steel fasteners in corrosive ground (ie: chlorides > 1000 ppm) shall be protected as shown in Figure 306A-D. CWW does not accept the use of buried galvanised steel fasteners. Either approved mastic or gel plus plastic caps may be used to encapsulate the galvanised fasteners. A. B. C. D. E. F. REV DESCRIPTION 1 DATE 2 APPROVED 3 DATE: DRAWN: CHECKED: NAME DATE: DATE CWW SEWL SEWL YVW YVW 4 F G NOT TO SCALE MRWA WATER SUPPLY STANDARDS H APPROVED: NAME CWW FLANGE THICKNESS (mm) 30 40 FLANGE OD (mm) PIPE OD +100 PIPE OD + (2 x PIPE WALL THICKNESS) 1. The PE puddle flange shall conform to the dimensions described in in Table 306A-A. 2. Puddle flanges cast as part of a thrust fitting (thrust connectors) or welded on puddle flanges are preferred to bolted on mechanical puddle flanges and shall be used where practicable. 3. PE puddle flanges shall be extrusion welded to PE mains. 4. Extrusion welding shall be undertaken in a clean and dry workshop. 5. The extrusion welder shall be qualified to the competency PMBWELD309 or PMBWELD309A or PMBWELD309B. 6. All welds shall be stamped with the welder's name or identification number. All Fasteners (gal or SS) shall be sleeve wrapped to prevent contact with soil. Gal fasteners in the open air (not buried) do not require additional corrosion protection. Triple wind PVC heavy duty "duct tape" to be min 0.18mm thick and 50mm in diameter around the sleeve to prevent water / air ingress under the sleeve. Use low density polyethylene sleeve in accordance with AS 3680. Wrap so that any seem is located at top of the pipe. Ensure that all sleeving between the duct tape on one side and that on the other is not perforated in any way. Ensure flanges and bolts are clean and free of dirt of contaminants prior to being sleeved. DESIGNED: PIPE PE MAIN OUTSIDE DIAMETER <DN280 >DN315 PIPE PE MAIN OUTSIDE DIAMETER <DN500 >DN560 NOTES Regarding Fused PE Puddle Flanges: NOTES Regarding Sleeving: MELBOURNE RETAIL WATER AGENCIES H E FIGURE 306A-E: PE PUDDLE FLANGES Plastic sealing cap (optional) MASTIC Puddle Flange Outside Diameter PE pipe FIGURE 306A-C: PE STUB FLANGE WITH SS FASTENERS GENERAL NOTES: C D Gasket PVC heavy duty "duct tape" J. Step 3: Mastic- Apply mastic to create a gradual and smooth transition from the pipe to the outer diameter of the flange. Application around bolt heads only is not acceptable. Apply mastic by hand, ensuring no significant voids are present. K. Step 4: Protective Tape- Apply petrolatum, butyl or bitumen tape system continuously with 55% overlap, stretching and moulding the tape to limit creases and prevent gaps. L. Step 5: Overwrapping Plastic Tape- Provide physical and mechanical protection of the corrosion protective tape using a PVC overwrapping tape. Apply with 55% overlap, stretching tape to limit creases and prevent gaps. Where DI pipe and fittings are PE sleeved (after step 4), over wrapping tape is not required. M. Step 6: Coating Defect (holiday)Testing. Carry out holiday testing to determine the quality of coatings as per note J of drawing MRWA-W-400. DATE MRWA-W-306A FLANGE ARRANGEMENTS ISSUED 2012 5 6 7 8 9 10 11 REVISION NO. 3 12 1 2 3 4 5 TABLE 306B- A: CLASS 16 (PN16) FLANGE & FASTENING DATA 100 215 178 108 4 18 M16 75 20 70 50 40 20 11 PIPE NOMINAL SIZE FLANGE OUTSIDE DIAMETER PITCH CIRCLE DIAMETER GASKET INTERNAL DIAMETER NUMBER OF HOLES / BOLTS DIAMETER OF HOLES BOLT SIZE LENGTH OF BOLTS (mm) BOLT TENSION (kN) TORQUE (LIGHTLY OILED GAL)- Nm TORQUE (WELL LUBRICATED) TORQUE (PTFE or INSULATED)- Nm DI FLANGE THICKNESS (mm) STEEL FLANGE THICKNESS (mm) 150 280 235 161 8 18 M16 75 20 70 50 40 23 11 225 370 324 241 8 18 M16 75 25 90 60 50 24 15 300 455 406 325 12 22 M20 100 35 160 110 80 30 23 375 550 495 406 12 26 M24 100 50 270 180 145 33 30 450 640 584 485 12 26 M24 120 55 290 200 160 33 30 600 825 756 641 16 30 M27 130 70 420 290 230 42 48 6 750 995 927 796 20 33 M30 130 80 530 380 290 47 48 B 100 230 191 108 8 18 M16 90 50 180 120 96 22 24 150 305 260 161 12 22 M20 90 80 350 240 190 27 31 225 405 356 241 12 26 M24 120 115 610 420 330 34 38 300 490 438 325 16 26 M24 120 115 610 420 330 38 38 375 580 521 406 16 26 M24 130 150 900 610 430 42 48 450 675 610 485 20 33 M30 150 180 1190 810 520 46 58 600 850 781 641 24 36 M33 180 230 1670 1140 745 54 68 8 750 1015 940 796 28 36 M33 180 230 1670 1140 830 59 - D 7. Tighten the nuts to finger tight and check the alignment of the flange faces and gasket. 8. Insert the remaining bolts (with insulators if required) and tighten nuts to finger tight. 9. Determine the correct tightening torque from the above tables. 10. Tighten nuts to 30% of this torque using the star pattern detailed in the figure below. 10. Tighten nuts to 60% of this torque using the star pattern detailed in the figure below. 10. Tighten nuts to 100% of this torque using the star pattern detailed in the figure below. 11. Finish with one final pass, torquing in a clockwise direction. 12. Re-torque fasteners 30 minutes after the initial tightening sequence (to cater for relaxation of the gasket). 13. If galvanised fasteners are to be used, apply corrosion protection measures as detailed in MRWA-W-306A. Torque wrenches used must provide torques to an accuracy of + - 25%, which is typical. In critical applications where torques are substantial (ie: > 200 nm), a more accurate hydraulic tensioner shall be used. 1. Do not allowed gasket materials to be exposed to temperatures above 50 deg C or exposed to contaminants. 2. Thoroughly clean the flange faces to be jointed, ensuring there is no dirt, particles of foreign matter, protrusions or coating build-up on the mating surfaces. Use a scraper or wire brush to remove any irregularities. 3. Ensure that the mating threads of all nuts and bolts are clean and in good condition. 4. If galvanised fasteners are to be used, evenly apply a suitable lubricant (eg: molybdenum sulphide) to all mating threads, including the nut load bearing face. 5. Align the flanges to be joined and ensure that the components are satisfactorily supported to avoid bending stress on the flanged joint during and after assembly. 6. Insert four bolts i(with insulators if required) In locations 1 to 4 as indicated in Figure 306B- A, positioning the gasket in between the flange mating faces. Take care not to damage the gasket surfaces. 1 1 4 1 8 5 E 4 3 3 10 12 6 4 4 3 6 14 4 BOLTS 2 9 8 BOLTS 1 5 9 13 2 12 BOLTS 2 15 11 16 BOLTS FIGURE 306B- A: BOLT TIGHTENING SEQUENCE F Bolted on mechanical puddle flange a. CWW only permits 316 stainless steel fasteners in buried applications. Galvanized fasteners are allowed where the fasteners are exposed to the open air rather than soil. b. Class 16 flange gaskets shall be full face, solid 3mm thick EPDM rubber (seal-16). c. Class 16 galvanised steel studs (bolts), nuts and washers shall be grade 4.6. d. Class 16 stainless steel studs (bolts), nuts (ptfe coated) and washers shall be 316 stainless steel (A4), class 50. e. Class 35 flange gaskets shall be full face, 1.5mm thick compressed fibre, Teadit style na1000, which contains Aramid fibres, woven wire mesh reinforcement, a nitre rubber matrix and graphited surface on both sides. f. Class 35 galvanised steel studs (bolts), nuts and washers shall be grade 8.8. g. Class 35 stainless steel studs (bolts), nuts (ptfe coated) and washers shall be 316 stainless steel (A4), class 70 . h. Flange gaskets shall conform to WSAA industry standard WSA 109, which includes compliance to AS4020 for potable water contact. i. All stainless steel fasteners shall include the use of PTFE (teflon) or Molybdenum Sulphide (MoS2) coated nuts to reduce seizing, galling and the tightening friction of the nut on the washer (thus reducing the tightening torque required). TABLE 306B-C: PE MAIN CONNECTION TO CLASS 16 FLANGES (PN16) FLANGE PE OD PCD ADAPTOR 110 125 128 215 178 NOT REQUIRED 180 180 195 280 235 NOT REQUIRED 225 SPECIAL ORDER 370 324 225 to 280, or 225 to 315 280 280 300 405 356 NOT REQUIRED 315 315 345 455 406 315 to 355, or 315 to 400 SPECIAL ORDER STUB FLANGE + BACKING RING + ADAPTOR REQUIRED 450 450 480 640 584 450 to 560, or 450 to 630 NOM DI PE STUB FITTING SIZE SIZE 100 150 225 250 * 300 # 375 450 PE BACKING RING SIZE ID B C D PE EQUIVALENT DNPE SIZE(S) ^ 125 180 280 or 315 N/A 355 or 400 400 or 500 560 or 630 Apply torque according to the size of the valve flange (Refer Tables 306B-A & B) E SPECIAL ORDER BACKING RING a 2 pack epoxy resin liberally applied to the pipe and puddle flange mating surfaces. · Install as per manufacturer's instructions. Where fastening torque is not specified: · Firmly fasten the puddle flange bolts to a torque equivalent to that specified for lightly oiled F DN225PE STUB FLANGE · Mechanical puddle flanges shall not be applied to PVC pipe. · Clean mechanical puddle flanges (ie: bolted) fixed to metallic pipe shall be fitted to a clean pipe with DN300 325 VALVE galvanised flange bolts in Table 306B-A (PN16) or Table 306B- B (PN35). 256 315 DN315PE STUB FLANGE, BACKING RING AND PIPE DN225 VALVE 241 205 DN315PE TO DN315PE DN225PE 315 PIPE REDUCER 225 FIGURE 306B-B: MECHANICAL PUDDLE FLANGE CONNECTION G A NOTES Regarding Gasket and Fastener Material Requirements: NOTES Regarding Mechanical Flange Attachment: Ductile iron or PE pipe 12 ^ Equivalent size means that these sizes have the most similar hydraulic capacity. * Flange size 250 is included to enable DN280 PE mains to directly connect to DN250 valves / hydrant tees etc (ie: no adaptor would be required). Socket spigot mains shall not be constructed in DN250 size. # If preferred, DN315PE pipe may directly connect to a DN300 valve for convenience (no adaptor would be required), although the valve in this case would be larger than required. Refer to Figure 306B- B. · all PE adaptors shall be moulded fittings and butt weld fused to pipes / stubs. 7 6 11 Notes Regarding Table 306B-C: 3 10 11 7 16 8 5 2 7 12 8 10 A. The flange and fastening details provided in these tables are based on AS/NZS 4087:2011 and WSAA standard WSA 109-2011. In AS/NZS 4087, figure B5 covers PN16 and figure B6 covers PN35. B. All flanges shall be raised face type. C. "lightly oiled" refers to the application of a good quality lubricating oil and is the usual as received condition of fasteners. A torque K factor of 0.22 has been used to calculate the torque values in Tables 306B- A & B in this case. D. "well lubricated" refers to the application of molybdenum disulfide grease, or equivalent antiseize compound, eg: nickel graphite lubricant such as loctite 771. A torque K factor of 0.15 has been used to calculate the torque values in tables 1 & 2 in this case. Unless proven to be otherwise, assume grey coated nuts fall under "well lubricated". E. "PTFE / Insulated" refers to the application of a PTFE coating or the use of insulating polymeric top hats or washers / with well lubricated fasteners. A torque K factor of 0.12 has been used to calculate the torque values in tables 1 & 2 in this case. F. Torques quoted are minimums. Maximum torque allowable shall be 1.5 x the minimum. G. The bolt lengths described assume Di to Di flanges. Insulated flanges may require longer bolts. H. The nominated gasket internal diameter is the inside diameter of flange class ductile iron pipe, excluding the cement lining. While PN35 class Di pipe has a larger ID than flange class, the nominated gasket inside diameters are larger than pipe cement lining inside diameters (ie: the gasket will not protrude into water flow of any Di pipe). C Flanged Joint Installation Guidelines: 9 NOTES on Tables 306B- A & B: TABLE 306B- B: CLASS 35 (PN35) FLANGE & FASTENING DATA PIPE NOMINAL SIZE FLANGE OUTSIDE DIAMETER PITCH CIRCLE DIAMETER GASKET INTERNAL DIAMETER NUMBER OF HOLES / BOLTS DIAMETER OF HOLES BOLT SIZE LENGTH OF BOLTS (mm) BOLT TENSION (kN) TORQUE (LIGHTLY OILED GAL)- Nm TORQUE (WELL LUBRICATED) TORQUE (PTFE or INSULATED)- Nm DI FLANGE THICKNESS (mm) STEEL FLANGE THICKNESS (mm) UNLESS PROVEN TO BE OTHERWISE, ASSUME GREY COATED NUTS FALL UNDER "WELL LUBRICATED". TORQUES QUOTED ARE MINIMUMS. MAXIMUM TORQUE ALLOWABLE SHALL BE 1.5 x THE MINIMUM. A 7 G GENERAL NOTES: · Where test pressures are < 1600 kPa, class 16 flanges and gaskets are typically screwed onto flange class pipe (which is typically thicker than class 35 ductile iron pipe). FIGURE 306B-C: ALTERNATIVE DN315PE VALVE ARRANGEMENTS · Where there are more than 16 bolts, the same principle as applied in the 16 bolt flange pattern should be utilised. MELBOURNE RETAIL WATER AGENCIES DESIGNED: K. DAWSON 3 PE PUDDLE FLANGES. TORQUE AMENDMENTS 01/12/16 RJ / CP / JT DRAWN: R. JAGGER CHECKED: NAME 2 PUBLISHED FIRST ISSUE 04/04/12 K.DAWSON X CWW R.JAGGER 04/04/12 X CWW 1 PRE PUBLISHED DRAFT FOR COMMENT 12/07/11 K.DAWSON X SEWL C.PAXMAN 04/04/12 X SEWL G.REYNOLDS 04/04/12 X YVW S. TAN 04/04/12 X YVW A.COSHAM 04/04/12 H REV DESCRIPTION 1 DATE 2 APPROVED 3 MRWA WATER SUPPLY STANDARDS 11/03/2011 DATE: 11/03/2011 DATE: DATE 4 APPROVED: NAME H DATE FLANGE DETAILS AND FLANGE FASTENING REQUIREMENTS R.CARRUTHERS 04/04/12 5 NOT TO SCALE MRWA-W-306B ISSUED 2012 6 7 8 9 10 11 REVISION NO. 3 12 1 2 3 4 5 6 7 9 10 11 12 Valve surface details (refer MRWA-W-302) Valve surface arrangements as per MRWA-W-302 A 8 A FSL FSL Downstream manual discharge control valve (if required. Ref note D) GATE VALVE Lugged wafer check valve required if discharging to a Tanker Connection Point (ref Fig 307-C) or a Storm Water drain or pit (ie: discharges to waterways and discharge pits have a flap gate valve at the outlet already). B Tee restraint not required where discharge main is restrained. REFER TO SEWERAGE STANDARD FIGURES MRWA-S-404-D to H FOR OUTLET DESIGN DETAILS B DISCHARGE PIPE ON FALLING GRADE Refer MRWA-W-204 and 205 FIGURE 307-A: SCOUR CONNECTION 2 to 5m FROM OUTLET STRUCTURE FIGURE 307-C: DISCHARGE TO WETLANDS OR WATERWAYS C C Standard 600 shaft (concrete or PP). If PP, install as per Fig 306C(i) from sewerage standards Design and construct pit as a Maintenance Hole in accordance with MRWA Sewerage standards Valve surface details as per MRWA-W-302 600 CLASS D COVER (if 600 shaft) 750 CLASS D COVER (if 1070 shaft) FSL FSL 50 to 150 Spindle extension to surface arrangement as per MRWA-W-302 <600 if Practical D Flap gate 1 to 5 m Downstream manual discharge control valve (if required. Ref note D) Hole in handle to enable connection of operating rod ~30 > 150 <30 Non-return flap Finish mortar flush with pit wall Roughen pipe and seal with epoxy mortar > 2m 4 of 300 x 300 x 50 Approved hardwood, recycled plastic or concrete support >400 >100 D Compacted Embedment 30° E Ball or butterfly discharge control valve. 20mm bleed with 316 SS ball valve E FIGURE 307-D: TANKER CONNECTION POINT NOTES Regarding Tanker Connection Points: Refer MRWA-W-204 and 205 STORAGE VOLUME 1. This arrangement is an alternative to Figure 307-B. It is preferred when the scour water removal plan indicates a single tanker truck could empty the isolated section of main with in the required time (refer to table 8.3 of WSA03). 2. Locate the pit in a non trafficable location if possible. 3. Cover shall be Class D and the shaft shall be reinforced concrete if the pit is located in a trafficable location. 4. Approved polymeric or concrete shaft may be used in non trafficable locations. F 5. Cover should lie 25mm above the surrounding natural surface level (not to protrude excessively above ground) in non trafficable locations. 6. System to be operated as follows; 1) sit on edge of opening, with legs in pit, 2) couple truck hose to quick connector, 3) open discharge control valve & fill tanker, 4) close valve, 5) disconnect hose from quick connector or truck. The shaft shall be sized and dimensioned to enable this. 7. Quick connector is a Bauer couplings for CWW. F FIGURE 307-B: DISCHARGE PIT DETAIL NOTES Regarding Discharge Pits: 1. 2. To be used on NDW mains only. Locate nearby >DN300 sewerage main maintenance structures if practical. Pump out pits may only be used on DW mains in cases where there the water main is constructed ahead of drainage. DW Pump out pits shall be decommissioned and replaced with properly constructed drainage system scour connections when drainage becomes available. Use minimum 1050 manhole design. Consider larger manholes for larger mains. Construct pit in accordance with WSA 02- cast in situ manholes. Designers must produce a feasible scour water removal plan and adjust the scour pit design to suit. The plan should take into account: the grade of the main, the volume of water in the main, the volume of the pit, the feasibility of pumping pit contents to a sewer, or the number of eductor truck loads required to empty the main. 1 Pit storage shall be no less than 50 of the water main shutoff volume being removed unless the pit is within 50m of a nearby > DN300 sewer. Water main shutoff volume must be < 300m³. 3. 4. 5. G 6. 7. GENERAL NOTES: A. B. C. D. Scour valve and pipework to provide required main drainage time (refer table 8.3 of WSA 03- MRWA edition). Discharge to drains and water ways is preferred for drinking water. Discharge to a pit or tanker connection point is required for non drinking water. Locate discharge pits nearby >DN300 sewerage main maintenance structures if practical. Downstream valves at the end of the scour line are only required when the discharge cannot be seen or heard at the distribution main's offtake valve which is typically when the drain, pit or waterway is more than 20m away. For tanker connection points, the butterfly valve below the connection coupling provides satisfactory discharge control. Unreinforced concrete to be N20 and reinforced concrete N25. Connections into drains shall be undertaken as per the requirements of the relevant drainage authority. Discharge to wetlands, creeks and drains only permitted for drinking water and treated storm water. Scours are typically sized as per bypass valves, although drainage time and scour flow velocity should also be taken into account (refer to Table 105-A for details). E. F. G. H. MELBOURNE RETAIL WATER AGENCIES H REV DESCRIPTION 1 DATE 2 APPROVED 3 DESIGNED: DATE: DRAWN: CHECKED: NAME DATE: DATE CWW SEWL SEWL YVW YVW 4 NOT TO SCALE MRWA WATER SUPPLY STANDARDS H APPROVED: NAME CWW G DATE 5 SCOUR ARRANGEMENTS FOR > DN300 MAINS 6 7 8 9 10 MRWA-W-307 ISSUED 2012 11 REVISION NO. 3 12 1 2 3 4 <10 CONNECTIONS A 5 6 7 > 2m 10 11 TIMBER / RECYCLED BLOCKS iii) 12 NOTES Regarding Valve & Hydrant Requirements: a. Permanent valve(s) are generally required at temporary c. dead ends as per Option ii) to v). This is to ensure that the minimum number of customers d. are affected when later works are completed. If practicable, <10 existing connections shall be designed Preferred where there are >10 connections into a SOB which is to be completed at a later date (as between the next valve back and the end of line. indicated in Option i). Maintain FL-FL piece to keep distance from b. When swabbing downhill is to occur, permanent valves are anchor. required at the down hill end of the mains to control the swab and keep the main full once swabbing is complete. Preferred where a hydrant is also required for on going operational or fire fighting reasons. ii) B 9 Acceptable where a valve is better set back from the end of the main (ie: at a splay corner) and there are < 10 connections in between. i) (REFER FIGURE 308-E) 8 With respect to Option i), the undisturbed ground behind the washout shall not be disturbed for a distance of at least 2 meters. Where washouts on new mains are to be placed hard up against a blank plate at the end of a previous stage (Options ii, iii & iv), multiple blocks will make it easier to remove the temporary washout, and in the case of Options ii & iii, the increased separation will make it easier to attach the standpipes without them clashing. B (REFER FIG 308-D) BLANK PLATES A Preferred where a hydrant is also required for on going operational or fire fighting reasons. iv) v) Preferred where a larger connection is required to facilitate swabbing at 0.5 to 1.0 m/s. Refer Figure 308-E and accompanying notes. TEMPORARY ARRANGEMENT NOT REQUIRED FIGURE 308-A: END OF PRIOR STAGE ARRANGEMENTS C (REFER FIGURE 308-F) FIGURE 308-B: TEMPORARY CHARGING CONNECTIONS C FIGURE 308-C: PERMANENT CONNECTIONS FIGURE 308-D: EXAMPLE COMPLETED CONNECTION > VALUE IN TABLE 308-A SWAB BEING DISCHARGED Pressure test point METER PE pipe, bolted or butt welded. Flexible lay flat PE sleeve / hose may be acceptable for <DN150 mains where safe to do so. D Testable single detector check valve (or better) Isolation valve (for pressure testing) Chlorine injection tapping SWAB D Connecting hose STANDPIPES E A. B. C. D. F PRIOR CONSTRUCTION MAIN SIZE (DN) 100 OR 125PE 150 OR 18OPE 225 OR 280PE 300 OR 355PE 375 OR 450PE 450 OR 560PE 600 750 Limit of prior construction. Ground must be left undisturbed to this point when extension construction begins. LATTER CONSTRUCTION FIGURE 308-F: PERMANENT END OF LINE ASSEMBLY CWW & YVW- DN225 & DN280PE mains SEW- DN225, DN300 or DN375 mains with all in one valve controlled hydrants SWAB SWAB DISCHARGE HYDRANT HYDRANT HYDRANT DIAMETER LENGTH CONTROL UNIT 1 FLOW 2 FLOW 3 FLOW (mm) (mm) LENGTH (mm) (l/s) (l/s) (l/s) 200 NOT REQUIRED 300 5 250 10 350 NOT REQUIRED 300 20 400 1500 400 1600 20 500 20 475 1800 18 18 550 18 550 2000 26 26 650 26 750 2600 900 SITE SPECIFIC PLAN REQUIRED 900 3200 SITE SPECIFIC PLAN REQUIRED 1050 (Joints and pipe information not shown for clarity) End of prior stage arrangements Temporary chlorination arrangement Permanent arrangement ADD TEMPORARY END OF LINE ARRANGEMENT 1/12/16 RJ / CP / JT 2 PUBLISHED FIRST ISSUE 04/04/12 R. JAGGER X CWW C. RIVETTE 04/04/12 X CWW 1 PRE PUBLISHED DRAFT FOR COMMENT 12/07/11 R. JAGGER X SEWL C.PAXMAN 04/04/12 X SEWL G.REYNOLDS 04/04/12 X YVW K.DAWSON 04/04/12 X YVW A.COSHAM 04/04/12 DESCRIPTION 1 DATE 2 APPROVED 3 DATE 4 APPROVED: NAME · Chlorination and water quality compliance as per WSA 03-2010 / MRWA Specification 04-02. G · Concrete thrust restraints as per MRWA-W-204 and 205A or 205B. · Surface covers as per MRWA-W-302 & 303. NOT TO SCALE H DATE MRWA-W-308 SWABBING, CHLORINATION AND EXTENDING MAINS R.CARRUTHERS 04/04/12 5 indicated in Figure 308-F) between the permanent and temporary hydrants to facilitate charging and chlorination. · Refer to MRWA-W-105 for assembly details. · Where valves cannot be offset, refer to MRWA-W-304A & B for details. F KEY REFERENCES: MRWA WATER SUPPLY STANDARDS 20/01/2011 DATE: 20/01/2011 DATE: 3 the main is close to the maximum spacing (ie: > 2/3rds of the maximum spacing in Table 300-B), the end of line valve and hydrant arrangement shall be permanent (refer Figure 308-F and Figure 308-H). · Where the distance back to the last permanent divide valve on the main is substantially less than the maximum spacing, the end of line valve and hydrant arrangement shall be temporary (refer Figure 308-G). · Temporary end of line assemblies shall be sized as per Table 106-D. · Components shown in red are temporary. · Connect chlorination hose & fittings (as FIGURE 308-H: PERMANENT END OF LINE ASSEMBLY CWW & YVW- >DN300 MAINS. SEW- >DN450 MAINS R. JAGGER downstream system successfully passes its pressure test. · Where the distance back to the last permanent divide valve on NOTES Regarding Fig 308-H: BLANK PLATES DRAWN: R. JAGGER CHECKED: NAME REV DN225 mains, a temporary hose connection between the hydrants will be unable to push the swab with adequate velocity. · In such cases, swabbing flows will need to be delivered though the operation of an in line valve. · This valve (and any bypass valve) shall successfully pass a pressure test to the new system test pressure prior to installation (to ensure it does not leak super chlorinated water back into the in service main). · Install these valves closed and do not operate them until the BLANK PLATE DUCKFOOT BEND & HYDRANT MELBOURNE RETAIL WATER AGENCIES H E NOTES Regarding Large Main End of Line Arrangements: · For > DN300 and in lower pressure (static P < 400 KPa) FLOW REQUIRED TO ACHIEVE A SWABBING VELOCITY OF 0.5 m/s DESIGNED: START OF LATTER CONSTRUCTION TEMPORARY CONSTRUCTION (installed with prior construction) FIGURE 308-G: TEMPORARY END OF LINE ASSEMBLY ON >DN225 MAINS (known as "CHLORINATION ASSEMBLY") E. Single swabs are acceptable for <DN200 mains. (DN100 & 150 swabs are under review) swabbed unless the main contains butterfly Two swabs are required for each swabbing run divide valves. on mains > DN200. Swabbing is to be undertaken in accordance F. Swab discharge drinking water may only be with the swabbing plan (authorised by the discharged to open land where it will pond, to a superintendent) to a velocity of 0.5 to 1.0 m/s. tanker truck or to a storm water system which Swabs are single use only, manufactured from has adequate silt containment and polyurethane foam to AS2281 & AS4020. environmental controls. Swabs are to be marked with the entry point property address using a permanent marker. This is to aid swab reconciliation. All mains >DN100 > 15m long shall be TABLE 308-A: SWABBING REQUIREMENTS G Swab. Inserted just prior to recommencement of latter construction FIGURE 308-E: END OF LINE WITH PERMANENT VALVE AND SWAB DISCHARGE CONTROL ARRANGEMENT NOTES Regarding Swabbing: ISSUED 2012 6 7 8 9 10 11 REVISION NO. 3 12
© Copyright 2025 Paperzz