SMART data collection and inteGRation platform to

Technical overview
H2020-Water1b-2015
PM2 Stockholm
14-15 June 2017
This project has received funding from the European Union’s Horizon 2020 research and innovation programme under
grant agreement no 689785
saltgae.eu
CO
H2020-Water1b-2015
WP1: ended in M9
•
MS1-Best performing microalgal/bacteria consortium identified
•
•
Results: Tested WW: tannery, fish ponds, cheese whey
Tannery: D. salina on 10% (sterilised WW - not applicable) reality salinity will be too low, mixed consortium of
self selected algae expected
Algen salinity tests for existing & marine & saltpan species
Fishpond: Spirulina and Chlorella low nutrients in WW; how will be solved?
Whey WW (original WW from Silvio or not?): Tetraselmis suecica on 5% WW, WW inhibitory for Spirulina and
•
•
•
Chlorella
•
•
Study of microbial community: dominant algal and bacterial species and their associations; primers designed for
quantification of algal-bacterial ratio in demos-done
Pending tasks: MS1 to be submitted (reviewed by CO and TM)
saltgae.eu
CO
H2020-Water1b-2015
WP2: Valorisation of Sludge
•
•
•
M2 - Design and dimensioning of process for Primary Treatment and pre-treatment (i.e. DAF) (BBA M12): done
for all demo sites
M3 – Anaerobic Digestion processes and CO2 recovery optimised at lab scale (NOVA M18): in progress!
Pending:
 supply of equipment to demo sites – Who, Where, What – WG discussion!
 AD trials for methanogenic phase – results needed for further work and construction
 salinity levels (needed for AD reactors construction, DCU needs it)
 optimisation of CO2 recovery?
 List of equipment for demos: in deliverable D2.1– communication with partners – is there anything
unclear about who delivers what & who pays?
 Containers equipment at KOTO (BBA, KOTO; ALGEN) - what goes in to the containers? WG dissussion
saltgae.eu
CO
H2020-Water1b-2015
WP3: Valoristaion of HRAP effluents
•
•
M4 – Selection of pre-treatment strategy; Relevance of ED on each studied sample assessed; New pump and ERD
tested in lab environment (iBET M16)
Pending / deviations:
 ED tested on WW from Arava and KOTO at lab scale, will not be implemented (no budget, not feasible) report to PO? (EXT, BBA no budget for ED
 EXT does ED lab scale tests: delivery of WW (done? Costs!) few m3 of pretreated WW delivered to
who/when?? WG discussion!
 Pump tests needed on demo sites: transfer of PM / hours from WP3 to WP6?
 Delay in supply of pumping station – BBA
 BBA has no budget for pretreatment and RO (who delivers and pays for demos?) + pumps – does DCU
supply? WG discussion!
 Only RO at ARV and kOTO (really both?)
saltgae.eu
CO
H2020-Water1b-2015
WP4: Valorisation of algae biomass
•
•
Objectives: optimisation of harvesting, biomass refinements, develope and demonstrate animal feed, coatings and
adhesives, 3D printing
Results / pending:
 optimisation of harvesting
 biomass refinements
 animal feed trials: need to adapt to situation
o Produmix new numbers and proposed changes (no need for PO approval probably):
o testing for fish meal and antimicrobial activity (instead of soya replacement and omega 3);
o partners need to send algae (200g dry sample);
o NEW CALCULATIONS-is this acceptable/feasible for partners to provide? Fish meal: 76,5kg needed,
AB: 64,6 kg algae needed (141 kg total, previously: 533 kg)
o Archimede sent 150kg of algae for tests;
 Coatings: what has been done?
 3D printing, progress?
saltgae.eu
CO
H2020-Water1b-2015
WP4: Valorisation of algae biomass
•
Pending:
 D4.1. (M14) - next month! Systems design for harvesting and refinement, algae characterisation
saltgae.eu
CO
H2020-Water1b-2015
WP5: HRAP Integration and Process Optimisation
Pending:
• D5.1 deliverable
• Sensor system construction and integration in existent system (OXI-BBA-DCU-ARV-KOTO-ARCH)-WG
discussion!
• OXI: Chemitec doing tests for P and Chl (Sample from ARCH in process, KOTOs will be delivered after PM)
• Decision about how many modules, which sensors, range (budget!)
• Proposed: pH, cond, NH4, NO3, PAR, Chl; one per pond// offline: P in supernatant after harvesting (tests running)
• OXI needs info on Chl levels
• Sensors for WP3 (RO-DCU), WP2 (AD-BBA), anyone else?: WG discussion!
saltgae.eu
CO
H2020-Water1b-2015
Working Groups discussions: topics to cover
WP2
• Supply of equipment to demo sites – Who, Where, What
• Containers equipment at KOTO (BBA, KOTO; ALGEN) - what goes in to the containers?
WP3
• BBA has no budget for pretreatment and RO (who delivers and pays for demos?) + pumps – does DCU supply?
• EXT does ED lab scale tests: delivery of WW (samples sent? Costs!) few m3 of pretreated WW delivered to
who/when??
WP5
• Sensor system construction and integration into existing system (OXI-BBA-DCU-ARV-KOTO-ARCH
• Sensors for WP3 (RO-DCU), WP2 (AD-BBA), anyone else?
saltgae.eu
CO
H2020-Water1b-2015
Deviations
•
•
•
•
•
Species
ED only lab scale
Salinity in Italian demo
Biomass use
Size of AD
•
 DoW partA & partB
saltgae.eu
CO
H2020-Water1b-2015
Deliverable planning
•
•
•
•
Table of contents
Assignment of work
Main story
Coverage of DoW
•
•
•
Structure
Spelling
Language
•
Dates, avoid unnecessary delays
WP leader
Deliverable editor
Next:
D4.1 Systems design for harvesting and refinement, algae characterisation (IBET M14 Jul-2017 )
D2.2 Optimisation of anaerobic processes and CO2 recovery solution (NOVA M18 Nov-2017 )
D3.2 Optimisation of final systems ready for demonstration trials (IBET M18 Nov-2017)