View Touch Screen Installation Guide (650-220

View Touch Screen Monitor Installation Guide
Product Description
The Phoenix Controls View touch screen monitor is a
BACnet® MS/TP based networked user interface used to
display data and edit setpoint variables for vivariums,
hospitals, biocontainment spaces, operating rooms, patient
rooms, and nurses stations. The View can display data
from Phoenix Controls Traccel, Theris, PCM50X and
APM2 BACnet MS/TP devices, and 3rd party BACnet
MS/TP devices. The View is a 7" diagonal capacitive touch
screen panel that is flush mounted using a standard 90
cubic inches electrical box (Raco 942 or Thomas and Betts
H3BD341). It is intended to be installed in corridors
outside of critical environments to provide users with
information related to operating conditions inside the
space. The View can display up to 24 parameters
simultaneously and is capable of high and low limit,
change of state, and multi-state alarms. Each parameter is
capable of a user defined title and units of measure. The
View connects to the MS/TP bus and can be used to
display flow, temperature, humidity, air changes per hour,
offset, occupancy, and control setpoint variables available
on the MS/TP network.
•
•
Use Raco 9004R for 16" on center studs
Use Raco 9006R for 24" on center studs
NOTE:
Self-tapping screws may be necessary to complete
installation
Figure 1. Raco 9004R strap on wood stud
Rough-In Installation
For the View to be installed correctly, the rough-in phase
of the project must be completed properly. This section
will outline the specific considerations the General
Contractor must address so that wiring, installation of the
View, and commissioning will go smoothly.
Required Parts to be Supplied by the
Installer
The following is a list of parts required and supplied by
the installer for the View.
Rough in Box
• 3-Gang, Non-Gangable, 90 cubic inches Gang Box
(Raco 942 or Thomas and Betts H3BD341) Qty 1
per View
NOTE:
Self-tapping screws may be necessary to complete
installation
Figure 2. Raco 942 3-gang box on Raco 9004R
strap
Power and Signal Cabling
• Power: 24 Vac transformers
• Power cable: 2 conductor stranded twisted pair, 1622 AWG (18 AWG recommended), unshielded
• Network Cabling: Recommend using a 22 AWG
(.65mm cable) for networking, with three-conductor,
stranded, twisted-shielded cable with drain wire and
the following characteristics:
• Impedance between 100 and 130
• Distributed capacitance between conductors less
than 30 pF/ft (100pF/m)
• Distributed capacitance between conductors and
shield less than 60pF/ft (200pF/m)
NOTE:
Rough In Box Supports
For easiest installation, use the following mounting straps
to attach the rough-in box to the studs:
•
Phoenix Controls recommends using a 22 AWG
(.65mm) cable. Alternative wire sizes which meet
the cabling specifications may be used, but will not
extend the maximum length of cable
Terminating resistors (see section Network Layout Bus Topology below)
1
650-220-003 Rev. B
7/14
Installation Overview
•
•
EMT Conduit (if required by local code)
Repeaters, if necessary (see Network Layout - Bus
Topology below)
Parts Included with the Unit
The following parts are included with the View touch
screen:
•
•
View touch screen monitor - 7" diagonal display with
power and communication terminal blocks
Hardware - The View comes fully assembled with a
package of hardware. The hardware includes (4) #832x1" Screws, (4) #10-32x1", and (4)#10 flat
washers.
Network Layout - Bus Topology
Network Cabling
Refer to Power and Signal Cabling on page 1 for cabling
requirements.
IMPORTANT:
The #8 screws and #10 washers are to be used with
the Raco 942 box, and the #10 screws and #10
washers are to be used with the Thomas and Betts
H3BD341 box.
NOTE:
•
Depending on the quality of the installation, it may be
necessary to reduce the baud rate to avoid intermittent
communications. The baud rate will be determined by the
slowest device on the network. Using a larger gauge wire
will not allow the maximum length of cable per segment
to be extended.
Faceplate - The faceplate of the View is designed to
snap-fit onto the unit allowing it to seal snugly against
the wall to ensure dust and moisture will not affect the
unit (IP54). If the View is mounted on a concrete
wall, additional sealing may be necessary to ensure the
IP rating of the device. Available options for the
faceplate are white, white with simulated stainless,
black, and black with simulated stainless. All faceplate
options have a gasket on the surface that contacts the
wall to seal out moisture and dust.
The quality of the cable, the number of
the devices, and the amount of data to
be passed across the bus influence the
practical cable length and
communications speed (baud rate).
Shield Grounding
Ground drain wire at single point earth (panel) ground.
Do not terminate on BACnet device grounds, but tie
drain wire through with wire nuts. Tape off drain wire at
other end of network segment.
Terminating resistors (provided by others)
Installation Overview
Matched resistors are required at the end of each network
segment bus and should be wired across Data (+) and
Data (-) communication terminals for signal integrity.
Use matched resistors with specifications of 120 1/4W
±5%.
Networking Considerations
NOTE:
BACnet MS/TP networks are very sensitive to proper
cable specifications, installation, and the number of
devices on a network segment. The cable quality and
length, together with network load, will influence the
speed of communication (baud rate).
•
•
Each BACnet network segment can accommodate a
maximum unit load of 32.
• Each View counts as 1 unit load.
• Other BACnet devices may count as whole
or fractional unit loads.
Phoenix Controls recommends limiting each network
segment to no more than 50 BACnet devices, even
when the total unit load is less than or equal to 32
If a View is first or last device on the network
segment, jumper J2 (View internal terminating
resistor) can be installed instead of using a physical
terminating resistor.
Segment length
4000 ft. (1219m) maximum per network segment using
recommended wire.
Devices per segment
Phoenix Controls recommends limiting each network
segment to no more than 50 BACnet devices, even when
the total unit load is less than or equal to 32.
Repeaters (provided by others)
Cable runs longer than 4000 ft. (1219 m) require
repeaters.
2
650-220-003 Rev. B
7/14
View Wiring Recommendations
Pulling Wires Into the Electrical Box
Due to the configuration of the View mounting bracket
and back cover, care must be taken to ensure that the
power and communication wires will clear the View
components when installed in the gang box. Refer to the
figure below to determine which knockouts to use to
ensure that the strain relief and wires will clear the View
once it’s installed in the wall.
•
•
•
•
•
To connect the wiring to the View, use the terminal
connectors. Use a small flat screwdriver to tighten the
terminal connector screws once the wires have been
inserted.
Power cables should be kept apart from
communication and other types of wiring to avoid
any ambient noise transmission to them.
If power cables must cross communication cables, do
so at a 90-degree angle.
The board connectors accept 22 AWG wires
(.65mm) per pole. Power cables should be 16-22
AWG, 18 AWG (1.02 mm diameter) recommended.
Keep all wires away from high speed data
transmission cables (for example, Ethernet, etc.).
Connecting Power and Communication
Wires
Power Wiring
Figure 3. Knockout selection locations
Figure 4. Wires pulled through knockout (strain
relief not shown)
View Wiring Recommendations
•
All wiring must comply with electrical wiring
diagrams as well as national and local electrical codes.
The power terminal is labeled TB1 on back of the View
touch screen. Strip power supply wiring (24 Vac) and
connect to the terminals marked L1 and L2 on the
supplied power connector. If an earth ground is necessary
(per local code), terminate to the ground terminal on the
power connector.
Figure 5. Power cable termination
NOTE:
When sharing power with other devices, a
consistent polarity for the AC wiring should be
maintained (L1 to L1, L2 to L2 and ground to
ground).
3
650-220-003 Rev. B
7/14
Installing the View in the Rough-In Box
Communication Wiring
Communication terminal is labeled TB4 on the back of
the View touch screen. Strip network wires and connect to
the appropriate terminals marked B+, A-, and GND on
the supplied connector.
Jumper
Description
J1 (PU)
Pull up resistor1
J2 (TRM)
Terminating resistor - Enables the terminating
resistor in the View touch screen.
NOTE: Only use if it is the first or last device
in a network run)
J3 (PD)
Pull down resistor1
1
Install J1 and J3 as a pair
Figure 6. Communication cable termination
MS/TP communication wiring is polarity sensitive.
Maintaining the polarity of the communication
wires (B+ to B+, A- to A-, GND to GND, and drain
wire to drain wire) must be done in order to
guarantee proper communication.
NOTE:
Jumper Configuration
The network bias resistors (pull up and pull down - J1 and
J3) increase the noise immunity of the network. This
configuration keeps the B+ and A- biased with a 200 mV
separation generating an idle condition at the receivers
and helps prevent false data on the network segment. The
network segment must be properly terminated to achieve
this effect. No more than two (2) network bias systems
can be active on a network segment at any given time
according to Clause 9 of the ASHRAE STD 135-2012.
Both J1 (pull up) and J3 (pull down) jumpers must be
installed when using biasing resistors.
The terminating resistor (TRM - J2) is installed at both
physical ends of the network segment. If the View is
installed as the first or last device on the network segment,
a separate terminating resistor is not necessary. Install the
J2 jumper to use the internal terminating resistor in the
View.
4
650-220-003 Rev. B
7/14
Figure 7. Jumper location
Installing the View in the Rough-In
Box
Removing the Faceplate
The View is shipped from the factory with the faceplate
installed on the mounting bracket. The faceplate must be
removed before the View can be installed in the rough-in
box. To remove the faceplate, grip the faceplate relief with
your finger on the right side of the unit and push in while
pulling towards you. The faceplate will lift off like a hinge,
simply pull the right side of the faceplate off the mounting
bracket and then pull the faceplate to the right. Then the
left side of the faceplate will be able to completely
removed.
IMPORTANT: When reinstalling the faceplate, push
down on the faceplate around the
perimiter to ensure that it is fully seated.
This ensures the outside gasket is in
place and seated properly.
Securing the View to the Rough-In Box
Figure 8. Faceplate relief location
Figure 10. Power and Communication connectors
Securing the View to the Rough-In
Box
NOTE:
•
This End Up is the top of the View. The View
must be secured to the rough-in box using the
supplied hardware as follows:
If the RACO 942 box was used for the installation,
use the (4) supplied 8-32 x 1" screws and the (4)
supplied #10 washers
If the Thomas and Betts H3BD341 box was used for
installation, use the (4) supplied 10-32 x 1" screws and the
(4) supplied #10 washers
Figure 9. Removing faceplate from mounting
bracket
Connecting Power and Communication
Once the rough-in wiring has been completed, the power
and communication keyed connectors can be terminated
to the back of the View as follows:
Figure 11. View mounted with supplied hardware
WARNING:
When attaching the screws to the
mounting bracket, ensure the screws
are attached snugly. Overtightening the
screws can warp the bracket.
5
650-220-003 Rev. B
7/14
Installing the Faceplate
Installing the Faceplate
Before installing the faceplate, remove the protective
film covering the screen. Align the mounting tabs on
the back of the faceplate with the holes on the
mounting bracket and push firmly to install. The
faceplate has a snap feature that will secure it to the
mounting bracket and to the wall.
Power Up the View
Once the unit has been powered up, the screen should
display: Device Unconfigured: Tap Screen to
Continue.
Refer to the View Touch Screen Monitor User’s Guide
for information on configuring the unit or call your
Phoenix Controls Representative.
Troubleshooting
Unit does not
power up
When the screen is tapped, the user will be presented
with a pop up numeric keypad to enter an
administrative pin and begin configuring the unit.
6
650-220-003 Rev. B
7/14
"Device is
Unconfigured"
screen is
showing
• Check transformer
• Ensure the power (L1 and L2) is
wired correctly at the TB1 plug
• Ensure the power plug is plugged
into TB1
If unit is wired correctly and the
transformer is good, contact Phoenix
Controls Technical Services at: 1-800474-9832.
The unit has not been configured—
contact your local Phoenix Controls
Representative to configure the unit
Power Up the View
Copyright 2014 Phoenix Controls
Phoenix Controls is a business of Honeywell International, Inc. Phoenix and Phoenix Controls are trademarks
of Honeywell International, Inc.
Phoenix Controls products are covered by one or more of the following U.S. patents:
5,251,665
5,304,093
5,545,086 D642894 and other patents pending.
The material in this document is for information purposes only and is subject to change without notice. Phoenix
Controls assumes no responsibility for any errors or for consequential damages that may result from the use or
misrepresentation of any of the material in this publication.
For additional information and a listing of our global offices, visit www.phoenixcontrols.com or call
800- 340-0007.
7
650-220-003 Rev. B
7/14