South African Airways Scope of Work for HVAC Refurbishment/Replacement at Airways Park and Inflight Services Buildings Address: South African Airways Airways Park and Inflight Services Jones Road O.R. Tambo International Airport 1627 Background Airways Park is fed by twenty one (21) Air Handling units and seven (7) Chillers in Total. All Air Handling units do not have heating Capabilities and of the seven (7) Chillers, only three (3) are operational. Additionally the Chillers are over twenty years old and have a life expectancy of twenty (20) years. Inflight Services is fed by twenty three (23) Air Handling units and heating is achieved via a hot water coil, fed from a boiler system. Heating via this method is very inefficient and costly, especially due to the fact that the vast piping systems are old and leaking. Scope of Work - Airways Park Heating: Site Establishment (Health and Safety, Security, Access) Detailed Design, complete with Piping and Instrumentation Diagram (must be approved by SAA Facilities Engineering) Manufacture Equipment as per Price Schedule. Local support for all equipment supplied. Install Equipment as per Price Schedule. Must be easily maintainable. Commission all Equipment. Contractor will be responsible for maintenance during installation and up to 3 months after final completion (during this time training and handover to onsite maintenance team will take place) Training of Site Staff (allow for 3 months after completion of Project). This system is primarily responsible for heating during winter months and must ensure that 18 – 22 Degrees Celsius is achieved and maintained in all areas of the building. The Control System must allow for Local SMART Control at the Air Handling Unit (e.g. capable of switching between heating and cooling) and linked to a centralised control unit located at the Main Chiller Plant (all controls used must be Building Management System compatible). The control system input must be wired to at least 1 thermocouple per floor of a Block (average of floor temperatures to be used as an input for temperature control). New Power supply cables for Heating Elements and Air handling units (existing cable will be replaced by 1 new cable) must be routed to each Air handling unit from a central point. Safe isolation and removal (if applicable) of any items that are changed. There should be no impact on operations during any phase of this project (all work impacting operations must be carried out after normal business hours 17h00 – 04h00, except in areas that operate 24 hours a day, where special arrangements must be made with the SAA Project Manager). SAA is open to alternative tried and tested heating solutions; however those are to be submitted as completely standalone bids with payback models. Chillers F- Block: Site Establishment (Health and Safety , Security, Access) Detailed Design, complete with (Piping and Instrumentation Diagram must be approved by SAA Facilities Engineering) Manufacture and Supply Equipment as per Price Schedule. Local support for all equipment supplied. Must be easily maintainable. Removal of existing chillers unit (No disruption to operations, chiller to be removed, installed, commissioned, fully functional one at a time) - Install Equipment as per Price Schedule. Commission all Equipment. Contractor will be responsible for maintenance during installation and up to 3 months after final completion (during this time training and handover to onsite maintenance team will take place) Maintenance and Operational Manuals to be handed over (2 hard copies and 2 Softcopies) Training of Site Staff (allow for 3 months after completion of Project). This system is primarily responsible for cooling during summer months and must ensure that 18 – 22 Degrees Celsius is achieved and maintained in all areas of the building. The Control System must allow for Local SMART Control (same as Air handling unit) at the Chiller Unit (e.g. capable of switching between heating and cooling) and linked to a centralised control unit located at the Main Chiller Plant (all controls used must be Building Management System compatible). The control system input must be wired to at least 1 thermocouple per floor of a Block (average of floor temperatures to be used as an input for temperature control). Safe isolation and removal of all items that are changed/replaced. Chillers are to be wrapped and transported to our storage facility in Inflight Services. There should be no impact on operations during any phase of this project (all work impacting operations must be carried out after normal business hours 17h00 – 04h00, except in areas that operate 24 hours a day, where special arrangements must be made with the SAA Project Manager). One unit is to be removed, new one installed and commissioned and be fully functional to carry the load when the second/third/fourth is done. The cooling towers are to be fully refurbished (one at a time – no impact to operations). Chillers H- Block: Site Establishment (Health and Safety , Security, Access) Detailed Design, complete with Piping and Instrumentation Diagram (must be approved by SAA Facilities Engineering) Manufacture and Supply Equipment as per Price Schedule. Local support for all equipment supplied. Must be easily maintainable. Removal of existing chillers unit (No disruption to operations, chiller to be removed, installed, commissioned, fully functional one at a time) - Install Equipment as per Price Schedule. Commission all Equipment. Contractor will be responsible for maintenance during installation and up to 3 months after final completion (during this time training and handover to onsite maintenance team will take place) Maintenance and Operational Manuals to be handed over (2 hard copies and 2 Softcopies) Training of Site Staff (allow for 3 months after completion of Project). This system is primarily responsible for cooling during summer months and must ensure that 18 – 22 Degrees Celsius is achieved and maintained in all areas of the building. The Control System must allow for Local SMART Control (same as Air handling unit) at the Chiller Unit (e.g. capable of switching between heating and cooling) and linked to a centralised control unit located at the Main Chiller Plant (all controls used must be Building Management System compatible). The control system input must be wired to at least 1 thermocouple per floor of a Block (average of floor temperatures to be used as an input for temperature control). Safe isolation and removal of all items that are changed/replaced. Chillers are to be wrapped and transported to our storage facility in Inflight Services. There should be no impact on operations during any phase of this project (all work impacting operations must be carried out after normal business hours 17h00 – 04h00, except in areas that operate 24 hours a day, where special arrangements must be made with the SAA Project Manager). One unit is to be removed, new one installed and commissioned and be fully functional to carry the load when the second/third is done. The cooling towers are to be fully refurbished (one at a time – no impact to operations). To Supply all Materials, Installation and commissioning including testing of the Air Handling Units and Chillers and the Removal of the old Air Handling Unit and Chillers for both Airways Park and Inflight Services Building. Scope of Work – Inflight Services Air handling units with Cooling and Heating: Site Establishment (Health and Safety , Security, Access) Detailed Design, complete with Piping and Instrumentation Diagram (must be approved by SAA Facilities Engineering) Manufacture Equipment as per Price Schedule. Local support for all equipment supplied. Install Equipment as per Price Schedule. Commission all Equipment. Contractor will be responsible for maintenance during installation and up to 3 months after final completion (during this time training and handover to onsite maintenance team will take place) Training of Site Staff (allow for 3 months after completion of Project). This system is responsible for SMART Cooling/Heating and must ensure that 18 – 22 Degrees Celsius is achieved and maintained in all areas of the building. The Control System must allow for Local SMART Control at the Air Handling Unit (e.g. capable of switching between heating and cooling) and linked to a centralised control unit located at the Main Chiller Plant (all controls used must be Building Management System compatible). The control system input must be wired to at least 1 thermocouple per floor of a Block (average of floor temperatures to be used as an input for temperature control). New Power supply cables (if applicable) for Heating Elements and Air handling units (existing cable will be replaced by 1 new cable) must be routed to each Air handling unit from a central point. As part of this project all pipework is to be changed (lagging and cladded), in line with design and standards (Local or International). Safe isolation and removal of all items that are changed e.g. Existing Air handling units, piping systems etc. There should be no impact on operations during any phase of this project (all work impacting operations must be carried out after normal business hours 17h00 – 04h00, except in areas that operate 24 hours a day, where special arrangements must be made with the SAA Project Manager). SAA is open to alternative tried and tested heating solutions; however those are to be submitted as completely standalone bids with payback models General The Contractor will be responsible to Clean up and Removal, disposal of all debris associated with the Supply and Installation for both Air Handling Unit , Chillers at Airways including Inflight Services Building. Preferred hours of Work for Receiving, Supply, Installation, and the start-up should be performed during the day between 07:00am till 05:00pm from Monday till Friday. Authorization from SAA Project Manager should be requested in advance (24 hrs prior) should the Contractor need to work after hours and weekends over weekends. The Contractor will provide his/her accredited Safety Rep. on site. The Contractor will provide his/her Project Manager on site. Meetings with SAA Project Manager will be held once a week and as seen fit based on Project Delivery. Project Schedule (Baseline and critical path etc.), Risk Register, Proposed Payment Certificates etc. will be presented and discussed. The Contractor must familiarize him/herself with the Site, hence South African Airways will accommodate the Contractor should they wish for additional Time before the closure of the Tender. The Contractor will responsible for the labelling of the Assets supplied and submit and asset register. During Installation of equipment all Maintenance, Breakdowns and day to day operating of the new equipment will be dealt with by the contractor. Note: SAA’s Maintenance teams will be seconded to the contractor during this period only for Maintenance type activities (Not Project work). The Contractor shall do all relevant reports including identifying the risk weekly if any. The Contractor shall comply with all Health and Safety requirements. The Contractor will be responsible for his/her tools, equipment, materials, and supplies while on Site. The Contractor is responsible to do Security Clearance with the South African Police Department on behalf of all employees and subcontractors under his Management. The Contractor will submit a Proposed Progress Payment Schedule linked to deliverables – Final Approval by SAA. As Drawings to be supplied e.g. As-built, Piping and Instrumentation Diagram. All Guarantees and Warranties.
© Copyright 2025 Paperzz