Zero Waste Business Case DRAFT for EXPERT REVIEW Submitted to: Environmental Standards Branch C/O 3rd floor, 2975 Jutland Rd Victoria BC V8W 9M1 Attn: Jennifer Maxwell [email protected] Submitted by: Innes Hood, P.Eng Innes Hood Consulting Inc. 338 East 14th St North Vancouver, BC V7L 2N6 Tel 604 988-0444 Email [email protected] In association with: Earthvoice Strategies, Kelleher Environmental May, 2013 1 Zero Waste Business Case: Final Report Table of Contents Glossary ......................................................................................................................................................... 6 Acronyms ...................................................................................................................................................... 6 Summary ....................................................................................................................................................... 8 Context ...................................................................................................................................................... 8 Scope and Methods .................................................................................................................................. 8 Results ....................................................................................................................................................... 8 Introduction ................................................................................................................................................ 10 Objectives ............................................................................................................................................... 10 Scope of Analysis..................................................................................................................................... 10 Zero Waste Approach to Increased Diversion ........................................................................................ 12 Provincial Waste Management Hierarchy .......................................................................................... 13 Data limitations ....................................................................................................................................... 14 Report Structure ..................................................................................................................................... 14 Methodology............................................................................................................................................... 15 Overview of Collection, Recycling and Disposal Process in BC ............................................................... 15 Analytic Framework ................................................................................................................................ 17 Materials Quantification Methodology .................................................................................................. 19 Material Forecast ................................................................................................................................ 19 Disposal by Material (2010) ................................................................................................................ 22 Diversion by Material (2010) .............................................................................................................. 22 Disposal and Diversion Forecast by Scenario...................................................................................... 23 Incremental Diversion by Material and Scenario (2025) .................................................................... 24 Incremental Diversion by Milestone Period ....................................................................................... 26 Economic Analysis Methodology ............................................................................................................ 28 Assumptions ........................................................................................................................................ 28 Data Sources for Costs and Revenue .................................................................................................. 29 Municipal Costs ................................................................................................................................... 29 Commodity Revenue........................................................................................................................... 30 Industry Stewardship Costs & Revenues ............................................................................................ 30 Material Diversion in the Zero Waste Scenarios................................................................................. 31 Costs and Revenue by Material and 5Rs Activity ................................................................................ 31 2 Zero Waste Business Case: Final Report Calculation of Costs and Benefits........................................................................................................ 34 Employment Impact Methodology ......................................................................................................... 34 Input-Output Multipliers..................................................................................................................... 34 Reuse-Recycling-Recovery: Jobs-Per-Tonne-of-Material Ratios ......................................................... 35 Energy and GHG Impacts ........................................................................................................................ 36 Human Health and Toxicity Impacts ....................................................................................................... 38 Results ......................................................................................................................................................... 39 Economic Business Case ......................................................................................................................... 39 Distributional Impacts ............................................................................................................................. 41 Sensitivity Analysis .............................................................................................................................. 41 Job Creation and Economic Impact Results ............................................................................................ 42 Direct, Indirect and Induced Impacts .................................................................................................. 42 Downstream Impacts .............................................................................................................................. 44 GHG and Energy Impacts ........................................................................................................................ 45 Zero Waste Business Case Results Summary .......................................................................................... 45 Discussion.................................................................................................................................................... 47 Distributional Impacts ............................................................................................................................. 47 Impact of Increased Diversion on Landfill Costs ................................................................................. 48 Leakage ............................................................................................................................................... 48 Conclusions ................................................................................................................................................. 49 Recommendations .................................................................................................................................. 49 References .................................................................................................................................................. 51 Appendix: Local Government Survey on Waste Management Costs and Practices ................................... 54 3 Zero Waste Business Case: Final Report List of Tables Table 1: Business Case for Zero Waste Summary ........................................................................................ 9 Table 2: Recycling, Reuse and Remanufacturing Sector Categories ........................................................... 18 Table 3: Materials Quantification Task List ................................................................................................ 19 Table 4: Waste Forecast by Sector (2010 – 2025); Business as Usual Scenario ........................................ 20 Table 5: Waste Forecast by Sector (2010 – 2025); 62% Diversion Scenario .............................................. 20 Table 6: Waste Forecast by Sector (2010 – 2025); 81% Diversion Scenario .............................................. 21 Table 7: Disposal Tonnage by Material, (2010).......................................................................................... 22 Table 8: Diversion by Material (2010) , [tonnes] ....................................................................................... 23 Table 9: Percent of 2010 Disposed Tonnes Which Will Be Diverted by 2025 ............................................ 24 Table 10: Scenario Two Incremental Diversion by Category and Segment, 2025 (Tonnes) ...................... 25 Table 11: Scenario Three Incremental Diversion by Category and Segment, 2025 (Tonnes) ................... 26 Table 12: Scenario Two Incremental Diversion by Milestone Year and Material ...................................... 27 Table 13: Scenario Three Incremental Diversion by Milestone Year and Material ................................... 27 Table 14: Economic Impact Analysis Task List ............................................................................................ 28 Table 15: Material Allocation by 5Rs Activity ............................................................................................ 31 Table 16: Unit Costs and Revenues by Material and Activity ..................................................................... 33 Table 17: Calculation of Net Costs & Benefits ........................................................................................... 34 Table 18: Employment Impact Task List ..................................................................................................... 34 Table 19: Input Output Multipliers, (Jobs per $1 million)........................................................................... 35 Table 20: Input Output Calculation ............................................................................................................ 35 Table 21: Downstream Jobs-Per-Tonne-of-Material Ratios ....................................................................... 36 Table 22: GHG Emissions from Waste Diversion Options Compared to Landfilling, Including Carbon Sinks (tonnes CO2e/tonne), Scenario 2 and 3 ..................................................................................................... 37 Table 23: Energy Savings from Waste Diversion Options Compared to Landfilling (GJ/tonne), Scenario 2 and 3 ........................................................................................................................................................... 38 Table 24: Human Health and Ecosystem impact by 5R activity [kG/ Tonne material] .............................. 38 Table 25: Calculation of Incremental Economic Benefit (Cost) of Higher Waste Diversion ....................... 39 Table 26: Economic Benefits (Costs) of Higher Waste Diversion Scenarios (Relative to BAU in 2025) ($ millions)....................................................................................................................................................... 40 Table 27: Summary of Expenditures and Revenues by Scenario (Relative to BAU in 2025) ($ millions)... 41 Table 28: Public Sector versus Private Sector Costs of Higher Waste Diversion ........................................ 41 Table 29: Sensitivity Analysis on Economic Benefit (Cost) ......................................................................... 42 Table 31: Scenario Two Job Creation and Economic Impacts in Material Collection and Processing ........ 43 Table 32: Scenario Three Job Creation and Economic Impacts in Material Collection and Processing ..... 44 Table 33: Full Time Equivalent Job Impacts on Downstream Reuse, Recycling and Recovery Sectors ...... 45 Table 34: GHG and Energy Impacts of Zero Waste Strategy in 2025 [GJ].................................................. 45 Table 35: Zero Waste Business Case Summary Results (Relative to BAU, 2025)....................................... 46 Table 36: Trends in Cost Shifting from Implementation of Zero Waste Strategies Compared to Landfilling .................................................................................................................................................................... 47 4 Zero Waste Business Case: Final Report List of Figures Figure 1: Scope of Zero Waste Analysis ..................................................................................................... 12 Figure 2: Zero Waste Economic and Employment Impacts Process Map.................................................. 15 Figure 3: Solid Waste Process Map (Scenario 1) ........................................................................................ 16 5 Zero Waste Business Case: Final Report Glossary Zero waste A solid waste management policy framework that goes beyond recycling to focus first on reducing waste and reusing products and then recycling and composting/digesting the rest. Reduce The first priority within a “5Rs” waste management hierarchy of reduce, reuse, recycle, plus recover and residual management. The objective of this strategy is to reduce by as much as possible the amount or toxicity of material that enters the solid waste stream and also the impact on the environment of producing it in the first place. Reuse The second waste management priority is to ensure that materials or products are reused as many times as possible before entering the solid waste stream. Recycle The third waste management priority is to recycle as much material as possible. Recovery The fourth waste management priority is to recover as much material and/or energy from the solid waste stream as possible through the application of technology. Residuals management The fifth waste management priority is to provide safe and effective residual management. This activity takes place once the solid waste stream has been reduced by efforts under the first 4 Rs, through the application of technology primarily in the form of well-designed and secure landfills. Direct effects Direct effects are the direct impact on wages, GDP and FTEs of increased industry output within that industry. For example, a waste hauler would experience directly the impact of increased output with the Waste Management industry. Indirect effects Indirect Effects measure the value of additional economic demands that the direct economic activity places on the supplying industries in the region. When firms produce goods or conduct business, they must make many purchases. Some of these are from suppliers in the area. Induced effects Induced effects accrue when workers in the direct and indirect industries spend their earnings on goods and services in the region. Induced effects can also be called household effects. Downstream jobs Downstream sectors are those that experience an economic impact due to changes in the flow through of material inputs to their business. In this sense, the reuse, remanufacturing and recycling reliant industries are downstream of the collection, landfill and processing sectors. They see an economic impact due to changes in the availability of collected materials, which represent a throughput for their operations. An example of a downstream company is a glass bottle manufacturer that receives recycled glass to transform into a new product. Acronyms 5Rs Hierarchy of reduce, reuse, recycle, recovery and residuals management 6 Zero Waste Business Case: Final Report BAU CR&D EPR FTE GDP GHG GJ ICI MRF WTE Business as Usual Construction, renovation and demolition Extended producer responsibility Full time equivalent Gross domestic product Greenhouse Gas Giga Joule Industrial Commercial and Institutional Material recovery facilities Waste to energy 7 Zero Waste Business Case: Final Report Summary Context As British Columbians, we recycle more today than we ever have before. We are also throwing more into the landfill than we ever have before. Based on current trends, by 2025, British Columbians will generate approximately one million tonnes more landfill waste every year than we do today. That increase in garbage is expected to raise municipal waste management costs by $120 million per year. But increasingly, we are finding better ways to extract the value from materials in the waste stream, which creates new economic opportunities and jobs. “Zero Waste” is a solid waste management policy framework that goes beyond recycling to focus first on reducing waste and reusing products and then recycling and composting/digesting the rest. Many communities across Canada, the US and globally (including many in BC) have explored or adopted zero waste principles (including Metro Vancouver). This study seeks to answer the question, “Is there a business case for a zero waste strategy in British Columbia?” It examines the economic, jobs, energy, greenhouse gas emissions, and other environmental impacts for British Columbia of one business as usual and two alternative waste diversion scenarios in 2025. Scope and Methods “Waste” has five possible pathways, known as the waste prevention hierarchy, or the “5Rs”: reduce, reuse, recycle, recover, residuals management. Residuals management is landfilling in most cases, so when we talk about “waste diversion” we mean directing waste down one of the other four pathways: reduce, reuse, recycle, or recover. This study compares estimated societal costs and benefits of two higher waste diversion scenarios compared to one business as usual scenario in 2025. The three waste scenarios used in this analysis were derived from the BC Stats report, Solid Waste Generation in British Columbia 2010 - 2025 Forecast (2012). The business as usual scenario assumes a status quo approach to waste management in BC with diversion rates remaining constant at 43% over the study period from 2010 to 2025 and a focus on recycling as the primary diversion strategy. Scenarios Two and Three are based on diversion strategies that incorporate the 5Rs. Scenario Two assumes an increased diversion rate to 62% in 2025 while Scenario Three assumes an 81% diversion rate in 2025. For each scenario, materials were allocated proportionally across the 5Rs using professional judgment to arrive at the total target diversion rate. Costing by 5Rs activity and material was developed from primary research combined with available data sources. Material diversion forecasts were combined with 5R costs and benefits to estimate the net benefit of implementing the zero waste strategy. Results This study demonstrates that there is a positive business case for increasing waste diversion. This study also demonstrates that there are significant societal benefits as a result of increased diversion including new jobs, increased GDP, reduced GHG emissions, and reduced environmental and human health risks. 8 Zero Waste Business Case: Final Report The key findings of this study are summarised in Table 1 as follows: The costs to local governments/taxpayers for waste management are projected to increase from $377 million per year in 2010 to $450 million per year in 2025, should the waste diversion rate remain at the current 43%. There is a positive business case for implementing a Zero Waste Strategy for BC. Depending on how aggressively it is implemented (i.e., 62% vs 81% diversion), by 2025 a Zero Waste Strategy will produce between $56 million and $126 million of annual net economic benefit1; will create between $27 million and $89 million in new annual GDP and generate between $755,000 and $2.5 million in new annual income tax revenue for BC. Reduce, reuse and recycling produces greater societal benefits than energy recovery or disposal. The business case for zero waste is strengthened if supporting policies are developed that encourage the creation and retention of remanufacturing facilities within BC, and prevent leakage to other jurisdictions. Table 1: Business Case for Zero Waste Summary Summary Net Economic Benefit New GDP New Jobs New Revenue to Province (Income tax) GHG reductions Projected Net Annual Benefits in 2025 $56 to $126 million $27 to $89 million 304 to 1,005 $756,000 to $2.5 million 1,047 to 2,277 kT/yr 1 The net economic benefit represents the net savings to the waste management system as a whole for scenarios two and three compared with the business as usual scenario. If the net economic benefit is positive, the overall economic cost of waste management has been reduced relative to BAU. If the net waste management benefit is negative, the overall economic cost of waste management has increased relative to BAU. See “Economic Business Case”, page 38 for a detailed explanation of the calculation of net economic benefit. 9 Zero Waste Business Case: Final Report Introduction The BC Ministry of Environment retained Innes Hood Consulting Inc. to develop a business case for zero waste in British Columbia. One business as usual (BAU) and two alternative scenarios are developed. The business as usual scenario assumes a status quo approach to waste management in BC with diversion rates remaining constant at 43% over the study period from 2010 to 2025. Implementation of a 5Rs strategy is used to achieve increased diversion rates. Scenario Two assumes a diversion rate of 62% by 2025, while Scenario Three assumes an 81% diversion rate by 2025. Objectives The objective of this analysis is to provide an estimate of the costs and benefits of increasing waste diversion in BC. The analysis includes financial metrics, employment and environmental impacts, relative to the business as usual scenario. Specifically, the analysis includes: Assessment of potential diversion quantities by material and 5Rs strategy: o Reduction, o Reuse, o Recycling, o Recovery, and o Residuals management. Incremental direct solid waste management costs from 5Rs activities. Incremental direct solid waste management revenues and expenditures from: o Sale of recyclables, o Reduction and reuse, and, o Disposal cost reductions. Distributional implications of who pays, and commentary on how costs shift from public sector to private sector. Energy and GHG impacts for the waste management sector. Incremental government revenue resulting from waste and material management (personal, corporate). Incremental changes in the provincial gross domestic product (GDP). Employment impacts including changes to wages and full time employment equivalent numbers for: o Direct jobs, o Indirect jobs, and o Induced jobs. Scope of Analysis The scope of the analysis is presented in Figure 1. This analysis is bounded spatially within British Columbia and temporally by materials and financial transactions that occur after a product has been 10 Zero Waste Business Case: Final Report consumed and before the material is re-manufactured. Waste streams include residential, ICI and CR&D sectors. On the downstream side, the analysis is bound once material is sold into secondary markets. Specifically, the analysis includes: Costs of waste collection and disposal to define the baseline or business as usual scenario, Effects on the generation of waste through implementation of reduction and reuse activities, Industry stewardship collection and processing costs, Costs and revenues from shifts from local government disposal or recycling of material to industry stewardship programs, and Costs and revenues from waste to energy processing of recovered material. The analysis excludes a number of items such as: Costs of consuming the original good; The economic activities arising from re-manufacturing activities that occur primarily outside British Columbia; Household time and other household costs for sorting, washing and cleaning diverted material; The externality cost of extracting and processing virgin material for the manufacturing of goods and services, however, the energy and GHG impacts of re-use versus virgin material is addressed; Wider economic effects, such as impacts of a zero waste strategy on the rate of inflation, effects on competitiveness and trade patterns; and Administrative and compliance costs required by the Provincial government to develop and enforce additional waste reduction and diversion strategies. 11 Zero Waste Business Case: Final Report Extract Virgin Material Primary Manufacture Distribution, Wholesale & Retail Reduce Consumption Scope of Analysis Reuse Collection EPR/Recycle Recover Residuals Sale of Material Waste to Energy Landfill/ Incineration Remanufacture into new products Figure 1: Scope of Zero Waste Analysis Zero Waste Approach to Increased Diversion A zero waste policy framework has been applied to structure the logic applied within this analysis. Zero waste is a solid waste management policy framework that goes beyond recycling to focus first on reducing waste and reusing products and then recycling and composting/digesting the rest. Many businesses now operate in a zero waste mode, and have found that the efficiencies realized by reducing waste to a minimum save money and increase efficiency, thereby increasing profitability. Many 12 Zero Waste Business Case: Final Report communities across Canada, the US and globally (including many in BC) have explored or adopted zero waste principles (including Metro Vancouver) which generally include a combination of: Re-designing the way resources and materials flow through society; Eliminating subsidies for raw material extraction and waste disposal; Hold producers responsible for their products and packaging from “cradle to cradle”. Zero waste generally involves a commitment to three objectives: Maximizing upstream waste reduction through product re-design; Zero Waste or green purchasing and producer responsibility; Maximizing mid-stream longevity (through reuse, repair and durable design) and Maximizing downstream resource recovery (recycling and composting/digestion) – keeping material out of landfill and EFW (which Zero Waste proponents oppose) These objectives are generally achieved through four broad policy instruments: Incentives and disincentives to encourage waste reduction; Extended producer responsibility and design for environment (DfE); Green Purchasing and Community building. Provincial Waste Management Hierarchy2 The provincial waste management strategy is based on the “5Rs” hierarchy of reduce, reuse, recycle, recovery and residuals management. This hierarchy has been used to allocate waste quantities into diversion streams for each of the zero waste scenarios, to enable estimates of expenditures or revenues. Consistent with the 5Rs hierarchy, the first priority is to reduce the amount or toxicity of material that enters the solid waste stream. The second priority is to ensure that materials or products are reused before entering the solid waste stream. The third priority is to recycle as much material as possible. In this analysis, recycling activities can occur either through municipal collection programs, financed by taxpayers, or through stewardship programs funded by industry and producers. The next priority effort within the hierarchy is to recover as much material and/or energy from the solid waste stream as possible through the application of technology. This element depends on the nature and size of the solid waste stream, the availability of technology, demand for its products, political acceptability and the environmental, social and economic impact of applying that technology. Waste-toenergy (WTE) facilities achieving greater than 60% energy efficiency are considered recovery. In the current analysis, for recovery, utilisation of waste-to-energy has been assumed. The final priority is to provide safe and effective residual management. This activity takes place once the solid waste stream has been reduced by efforts under the first 4Rs, through use of well-designed and secure landfills or through incineration (<60% energy efficiency). For certain classes of solid waste, thermal treatment may first be applied to change chemical properties, reduce volume and/or generate energy. 2 BC Ministry of Environment (1994). 13 Zero Waste Business Case: Final Report Data limitations Results of this analysis are based on published data and surveys of a selection of waste management professionals. It was observed through the course of this study that there are limitations to the data consistency and quality that impact the accuracy of the results. These limitations are discussed throughout the report. To address the data limitations, a sensitivity analysis is applied to the results to assess the impact of data uncertainty on the robustness of the overall conclusions. Report Structure The remainder of this report is structured into the following sections: Methodology, Results, Discussion, and Conclusions. 14 Zero Waste Business Case: Final Report Methodology This section presents the methodology, data sources and assumptions used to calculate the economic and employment impacts for each projected waste scenario. A process map to illustrate the tasks completed is presented in Figure 2. The process defined in this analysis was reviewed for consistency with the literature.3 Figure 2: Zero Waste Economic and Employment Impacts Process Map Overview of Collection, Recycling and Disposal Process in BC The waste management sector in BC is complex with a large number of private and public sector players. The roles of public sector versus private sector players vary by location, making generalisations for the industry difficult. A high-level process map of the waste management system is presented in Figure 3 to illustrate the current approach to waste management practices in BC. The services provided by the waste management industry include: 3 Collection and transportation of waste and materials; Operation of transfer stations, recycling facilities and landfills; OECD, (2005). 15 Zero Waste Business Case: Final Report Processing ,including composting and anaerobic digestion for organics; and, cleaning, sorting, grading and baling for other materials; and, Sale of materials to secondary markets. There is significant diversity in the collection and diversion practices and responsibilities in different regional districts throughout the province. Most of the single-family (78%) and multi-family households (80%) in BC receive curbside collection of solid waste and recyclables from their municipal or regional government4. The cost of this service is recovered either through property tax or on the basis of a user fee and may be provided by the local government or contracted out to private sector waste management firms. In contrast, industrial, commercial and institutional (ICI) and construction, renovation and demolition (CR&D) waste collection is handled primarily through private haulers who pick up waste and recycling on a fee for service basis. Waste that is collected by municipal collection or private haulers is taken to either landfills or to transfer stations where the material is compacted and sent to landfills. Landfill ownership may be either public (regional district or municipal) or private. While most landfills are regulated there are a number of private unregulated landfills in the province for which no data is available. Recycled materials collected from both the residential sector and the ICI sector are sent to material recovery facilities (MRFs) who clean, sort, grade and bale the materials. This material is then sold, either to markets within the Pacific Northwest or overseas, primarily to China. Figure 3: Solid Waste Process Map (Scenario 1) 4 Glenda Gies and Associates (2012). 16 Zero Waste Business Case: Final Report While this process map covers the majority of material, it is not exhaustive. For example, scrap cars or heavy duty equipment have not been included within the scope of the current assignment. Leakage from the system is discussed in later sections of the report. Reduction in consumption and re-use is not captured within this process map since these activities reduce the material input. Analytic Framework Recent studies5 identify the value chain for materials diverted from the landfill by three component industries: recycling industries; recycling reliant industries; and the reuse and remanufacturing industries (Table 2). Using this value chain, materials flow first through recycling industries (which collect, process and recover materials); then downstream through either a corresponding recycling reliant industry (focused on primary production, processing the material into a new form); or through the reuse and remanufacturing industries. Materials not diverted flow to the landfill, and for the purposes of this study, recovered materials flow to waste to energy facilities. Based on this model: 5 Materials that are reduced and no longer flow into the economy represent a reduction in economic activity and reduce the overall volume in the value chain. This is most immediately seen in a reduction in collection activities and associated output for this sector; Materials reused are assumed to flow into reuse and remanufacturing industries; Materials recycled are assumed to flow into recycling-reliant industries; Recovered materials flow into waste to energy facilities; Residual volumes are zero in this analysis since it analyzes the impact of the incremental change in landfill diversion between the business as usual scenario one and the two zero waste diversion scenarios, which have higher diversion rates and hence zero incremental residual volumes. DSM Environmental (2009). 17 Zero Waste Business Case: Final Report Table 2: Recycling, Reuse and Remanufacturing Sector Categories Recycling Industries Recycling Reliant Industries (Demand Side) Government Staffed Residential Collection Private Staffed Recycling Collection Compost/Organics Processor Materials Recovery Facilities Recyclables Material Wholesalers Plastics Reclaimers 6 6 Glass Container Manufacturing Plants Glass Product Producers Nonferrous Secondary Smelting and Refining Mills Nonferrous Product Producers Nonferrous Foundries Paper and Paperboard Mills/Deinked Market Pulp Producers Paper-based Product Manufacturers Pavement Mix Producers (asphalt and aggregate) Plastics Product Manufacturers Rubber Product Manufacturers Steel Mills Iron and Steel Foundries Other Recycling Processors/Manufacturers Reuse & Remanufacturing Industries Computer and Electronic Appliance Remanufacturers Retail Used Merchandise Sales Wood Reuse Materials Exchange Services Ibid. 18 Zero Waste Business Case: Final Report Materials Quantification Methodology The tasks to develop the materials forecast are summarised below (Table 3). The results of this analysis are used as input to the financial analysis and business case preparation. Table 3: Materials Quantification Task List Task Compile quantities forecast by segment and material Forecast disposal and diversion by scenario Allocate diversion by 5Rs strategy Description BC Stats developed a forecast of quantities that includes an estimate of material by sector. The analysis evaluates three diversion scenarios including the business as usual 43% diversion scenario and 2 alternative scenarios (62% and 81% diversion). The information above is disaggregated to estimate materials generated, diverted and disposed by Segment, Milestone year, Waste diversion scenario (business as usual - 43%, 62%, 81% diversion), and Material category. Allocation of diverted tonnages by 5Rs strategy is provided using available data from the literature on reduction and reuse, recycling, recovery and residuals management, and available program performance information for recycling, organics diversion and disposal. A description of these tasks is presented below. Material Forecast Material quantities by segment, milestone year and diversion scenario have been developed as part of the BC Waste forecast7. These estimates provide the basis of the current analysis and are presented in Table 4 to Table 6. 7 BC Stats (a) (2012). 19 Zero Waste Business Case: Final Report Table 4: Waste Forecast by Sector (2010 – 2025); Business as Usual Scenario Table 1 - Scenario One: Status Quo Tonnes 2010 2011 2012 2013 2014 Disposal 2,911,510 2,943,938 2,995,723 3,041,572 3,091,659 Residential 1,274,971 1,288,622 1,304,672 1,321,830 1,340,199 ICI 1,141,990 1,158,994 1,179,840 1,198,845 1,220,700 CR&D 494,550 496,322 511,211 520,896 530,761 Diversion 1,934,910 1,954,541 1,991,441 2,023,522 1,775,605 Residential 771,200 779,024 793,731 806,518 707,300 ICI 992,807 1,002,879 1,021,813 1,038,274 886,381 CR&D 170,904 172,638 175,897 178,731 181,924 Product Stewardship 242,398 245,241 248,209 251,527 539,124 Total Generated 5,088,819 5,143,719 5,235,373 5,316,621 5,406,388 Diversion Rate 43% 43% 43% 43% 43% 8 2015 3,134,815 1,358,868 1,238,466 537,481 1,512,590 602,052 726,044 184,494 834,836 5,482,241 43% 2016 3,180,175 1,377,723 1,257,402 545,049 1,533,232 610,268 735,933 187,031 846,542 5,559,948 43% 2017 3,218,388 1,396,868 1,272,076 549,444 1,546,484 615,538 742,030 188,915 858,255 5,623,127 43% 2018 3,243,954 1,415,952 1,282,042 545,960 1,553,534 618,336 744,943 190,254 870,004 5,667,491 43% 2019 3,263,630 1,435,143 1,288,985 539,501 1,556,437 619,482 745,726 191,230 881,797 5,701,864 43% 2020 3,288,795 1,454,270 1,297,778 536,747 1,563,426 622,256 748,604 192,566 893,590 5,745,811 43% 2021 3,312,212 1,472,889 1,304,855 534,468 1,570,745 625,161 751,656 193,927 905,314 5,788,271 43% 2022 3,337,599 1,491,322 1,313,054 533,223 1,580,355 628,980 755,893 195,482 916,896 5,834,850 43% 2023 3,366,728 1,509,552 1,322,638 534,537 1,592,982 634,002 761,684 197,296 928,364 5,888,074 43% 2024 3,395,050 1,527,561 1,332,601 534,888 1,605,511 638,984 767,433 199,094 939,693 5,940,254 43% 2025 3,422,322 1,545,330 1,343,098 533,893 1,617,546 643,770 772,938 200,837 950,861 5,990,728 43% 2,699,688 1,179,651 1,065,762 454,275 1,879,809 750,711 861,398 267,700 902,744 5,482,241 51% 2,657,323 1,160,587 1,050,516 446,220 1,928,546 770,012 872,674 285,860 974,079 5,559,948 52% 2,614,959 1,141,523 1,035,271 438,165 1,902,227 786,005 875,096 241,126 1,046,872 5,623,127 53% 2,572,595 1,122,459 1,020,025 430,110 1,975,536 826,122 902,207 247,207 1,060,464 5,667,491 55% 2,530,230 1,103,395 1,004,780 422,055 2,039,337 864,811 924,308 250,217 1,073,838 5,701,864 56% 2,487,866 1,084,331 989,534 414,000 2,112,061 904,918 950,176 256,967 1,087,539 5,745,811 57% 2,445,501 1,065,267 974,289 405,945 2,183,297 944,634 974,485 264,178 1,101,201 5,788,271 58% 2,403,137 1,046,203 959,043 397,890 2,258,614 985,041 1,001,055 272,519 1,114,803 5,834,850 59% 2,360,772 1,027,139 943,798 389,835 2,340,254 1,026,353 1,030,449 283,452 1,128,501 5,888,074 60% 2,318,408 1,008,075 928,552 381,780 2,421,162 1,067,447 1,060,232 293,483 1,141,966 5,940,254 61% 2,276,043 989,011 913,306 373,725 2,500,770 1,108,165 1,090,378 302,227 1,155,137 5,990,728 62% Table 5: Waste Forecast by Sector (2010 – 2025); 62% Diversion Scenario Disposal Residential ICI CR&D Diversion Residential ICI CR&D Product Stewardship Total Generated Diversion Rate 8 2,911,510 1,274,971 1,141,990 494,550 1,934,910 771,200 992,807 170,904 242,398 5,088,819 43% 2,869,146 1,255,907 1,126,744 486,495 2,028,324 811,286 1,034,574 182,465 246,249 5,143,719 44% 2,826,781 1,236,843 1,111,498 478,440 2,156,054 859,613 1,087,773 208,668 252,538 5,235,373 46% 2,784,417 1,217,779 1,096,253 470,385 2,272,557 906,915 1,136,400 229,242 259,648 5,316,621 48% 2,742,052 1,198,715 1,081,007 462,330 2,115,317 844,331 1,020,631 250,355 549,019 5,406,388 49% Spreadsheet provided by Dan Schrier, BC Stats, November 15, 2012 20 Zero Waste Business Case: Final Report Table 6: Waste Forecast by Sector (2010 – 2025); 81% Diversion Scenario Disposal Residential ICI CR&D Diversion Residential ICI CR&D Product Stewardship Total Generated Diversion Rate 2,911,510 1,274,971 1,141,990 494,550 1,934,910 771,200 992,807 170,904 242,398 5,088,819 43% 2,791,967 1,219,849 1,096,300 475,817 2,105,399 847,296 1,064,960 193,143 246,354 5,143,719 46% 2,672,423 1,164,728 1,050,611 457,084 2,309,720 931,417 1,148,280 230,023 253,229 5,235,373 49% 2,552,879 1,109,606 1,004,922 438,351 2,502,765 1,014,490 1,226,999 261,276 260,976 5,316,621 52% 2,433,336 2,313,792 2,194,249 2,074,705 1,955,162 1,054,484 999,363 944,241 889,119 833,998 959,233 913,544 867,855 822,166 776,477 419,618 400,886 382,153 363,420 344,687 2,422,268 2,206,020 2,330,829 2,144,140 2,233,176 987,767 904,141 959,002 944,027 992,432 1,141,434 980,789 1,021,900 972,845 996,459 293,067 321,089 349,928 227,268 244,284 550,784 962,428 1,034,871 1,256,610 1,331,911 5,406,388 5,482,241 5,559,948 5,623,127 5,667,491 55% 58% 61% 63% 66% 1,835,618 778,876 730,788 325,954 2,372,730 1,066,242 1,047,858 258,630 1,347,370 5,701,864 68% 1,716,074 723,754 685,099 307,221 2,520,232 1,141,249 1,102,755 276,229 1,363,642 5,745,811 70% 1,596,531 668,633 639,410 288,489 2,666,140 1,215,845 1,156,068 294,227 1,379,921 5,788,271 72% 1,476,987 613,511 593,720 269,756 2,815,864 1,291,079 1,211,577 313,208 1,396,258 5,834,850 75% 1,357,444 558,389 548,031 251,023 2,971,258 1,367,076 1,269,738 334,444 1,413,006 5,888,074 77% 1,237,900 503,267 502,342 232,290 3,126,184 1,442,921 1,328,367 354,895 1,429,373 5,940,254 79% 1,118,356 448,146 456,653 213,557 3,280,180 1,518,481 1,387,471 374,227 1,445,246 5,990,728 81% 21 Zero Waste Business Case: Final Report Disposal by Material (2010) Disposal by material was estimated using Provincial waste estimates (Table 7). These estimates have been updated to a 2010 baseline based on the change in material disposed between 2006 and 2010. 9 Table 7: Disposal Tonnage by Material , (2010) Material Organics Paper Plastics Multi-material Textiles & rubber Other Wood Ferrous Glass Renovation Non-Ferrous Haz-waste Concrete Drywall Asphalt Total Res [Tonnes] 509,334 215,575 172,439 103,889 71,249 67,955 33,921 33,137 29,544 24,830 12,513 7,949 1,282,336 ICI [Tonnes] 314,507 258,682 156,857 73,335 48,313 28,542 103,087 39,536 35,062 51,489 8,817 15,547 1,133,774 CR&D [Tonnes] 6,018 144,976 149,644 3,853 12,899 83,897 53,264 39,481 494,033 Total, 2010 [Tonnes] 823,841 480,275 329,296 177,224 119,562 241,474 286,652 76,526 64,606 76,319 34,229 23,496 83,897 53,264 39,481 2,910,142 Diversion by Material (2010) An estimate of diversion by material was developed for 2010 using diversion estimates published by BC Stats (Table 8). 9 BC Stats, 2010. 22 Zero Waste Business Case: Final Report 10 Table 8: Diversion by Material (2010) , [tonnes] Material Organics Paper11 Plastics Multimaterial Textiles & rubber Other Wood Ferrous Glass Renovation Non-Ferrous Haz-waste Concrete Drywall Asphalt Total Diversion Rate [%] 21% 41% 3% Quantity [Tonnes] 457,235 892,696 67,497 0% 0 3% 4% 11% 7% 3% 0% 7% 0% 0% 0% 0% 67,497 78,383 241,681 148,057 63,142 0 161,121 0 0 0 0 2,177,308 100% Disposal and Diversion Forecast by Scenario The Provincial Waste Forecast (Table 4 to Table 6) provides an estimate of increased diversion and extended producer responsibility by scenario (Table 9). This estimate was used to forecast quantities of waste diverted by scenario and category. 10 11 BC Stats, 2007 Paper is further broken down into newsprint (10.7%, mixed paper (15%), Cardboard & boxboard (15.3%). 23 Zero Waste Business Case: Final Report Table 9: Percent of 2010 Disposed Tonnes Which Will Be Diverted by 2025 Material Res Diversion (%) Scenario Two ICI CR&D Diversion Diversion (%) (%) Res Diversion (%) Scenario Three ICI CR&D Diversion Diversion (%) (%) Organics 50 50 - 85 85 - Paper 35 35 25 70 70 60 Plastics 30 30 - 80 80 - Multi-material 30 30 - 55 55 - Textiles & rubber 20 20 - 40 40 - Other 30 30 25 65 65 60 Wood 10 10 25 30 30 60 Ferrous 10 10 25 45 45 60 Glass 10 10 - 30 30 - Renovation 15 15 - 35 35 - Non-Ferrous 10 10 25 45 45 60 Haz-waste 35 35 - 75 75 - Concrete - - 25 - - 60 Drywall - - 25 - - 60 Asphalt - - 25 - - 60 36 32 30 71 66 60 Total For some materials (specifically paper grades) the percentage of diversion by material shown for the base case and Scenario Two has already been exceeded in Greater Vancouver12. Alignment of the provincial diversion estimates with data available at the regional district is recommended to enhance the accuracy of subsequent analysis. Incremental Diversion by Material and Scenario (2025) The incremental material diverted from landfill was estimated by combining the disposal tonnage by material (Table 8) with the diversion scenarios provided by the Province (Table 9). The results are summarised in Table 10 and Table 11. These estimates are within 12% of the diversion scenarios developed by the Province in its Waste Forecast Study. 12 Metro Vancouver, 2012 24 Zero Waste Business Case: Final Report Table 10: Scenario Two Incremental Diversion by Category and Segment, 2025 (Tonnes) Material Organics Paper Plastics Multi-material Textiles & rubber Other Wood Ferrous Glass Renovation Non-Ferrous Haz-waste Concrete Drywall Asphalt Total Res [Tonnes] 254,667 75,451 51,732 31,167 14,250 20,387 3,392 3,314 2,954 3,725 1,251 2,782 0 0 0 465,071 Provincial Estimate of Scenario Two ICI [Tonnes] 157,254 90,539 47,057 22,001 9,663 8,563 10,309 3,954 3,506 7,723 882 5,442 0 0 0 366,890 CR&D [Tonnes] 0 1,504 0 0 0 36,244 37,411 963 0 0 3,225 0 20,974 13,316 9,870 123,508 Incremental Diversion, 2025 [Tonnes] 411,921 167,494 98,789 53,167 23,912 65,193 51,112 8,231 6,461 11,448 5,358 8,224 20,974 13,316 9,870 955,470 1,087,000 25 Zero Waste Business Case: Final Report Table 11: Scenario Three Incremental Diversion by Category and Segment, 2025 (Tonnes) Material Organics Paper Plastics Multi-material Textiles & rubber Other Wood Ferrous Glass Renovation Non-Ferrous Haz-waste Concrete Drywall Asphalt Total Res [Tonnes] 432,934 150,903 137,951 57,139 28,500 44,171 10,176 14,912 8,863 8,691 5,631 5,962 905,832 Provincial Estimate of Scenario Three ICI [Tonnes] 267,331 181,077 125,485 40,334 19,325 18,553 30,926 17,791 10,518 18,021 3,968 11,660 744,991 50,338 31,958 23,689 Incremental Diversion, 2025 [Tonnes] 700,265 335,590 263,437 97,473 47,825 149,709 130,889 35,015 19,382 26,712 17,338 17,622 50,338 31,958 23,689 296,420 1,947,242 CR&D [Tonnes] 3,611 86,985 89,786 2,312 7,740 2,157,000 Incremental Diversion by Milestone Period A linear extrapolation is assumed for achieving the increased diversion from 2011 through 2025 by scenario, (Table 12 and Table 13). This represents the incremental diversion relative to business as usual. Three materials forecasts are used for conducting the economic analysis by combining unit costs with the incremental diversion estimates summarised in the tables below. 26 Zero Waste Business Case: Final Report Table 12: Scenario Two Incremental Diversion by Milestone Year and Material Material Organics Paper Plastics Multi-material Textiles & rubber Other Wood Ferrous Glass Renovation Non-Ferrous Haz-waste Concrete Drywall Asphalt Total 2011 2015 2020 2025 [Tonnes] [Tonnes] [Tonnes] [Tonnes] 27,461 137,307 274,614 411,921 11,166 55,831 111,663 167,494 6,586 32,930 65,859 98,789 3,544 17,722 35,445 53,167 1,594 7,971 15,942 23,912 4,346 21,731 43,462 65,193 3,407 17,037 34,075 51,112 549 2,744 5,487 8,231 431 2,154 4,307 6,461 763 3,816 7,632 11,448 357 1,786 3,572 5,358 548 2,741 5,482 8,224 1,398 6,991 13,983 20,974 888 4,439 8,877 13,316 658 3,290 6,580 9,870 63,698 318,490 636,980 955,470 Table 13: Scenario Three Incremental Diversion by Milestone Year and Material Material Organics Paper Plastics Multi-material Textiles & rubber Other Wood Ferrous Glass Renovation Non-Ferrous Haz-waste Concrete Drywall Asphalt Total 2011 2015 2020 2025 [Tonnes] [Tonnes] [Tonnes] [Tonnes] 46,684 233,422 466,843 700,265 22,373 111,863 223,727 335,590 17,562 87,812 175,625 263,437 6,498 32,491 64,982 97,473 3,188 15,942 31,883 47,825 9,981 49,903 99,806 149,709 8,726 43,630 87,259 130,889 2,334 11,672 23,343 35,015 1,292 6,461 12,921 19,382 1,781 8,904 17,808 26,712 1,156 5,779 11,559 17,338 1,175 5,874 11,748 17,622 3,356 16,779 33,559 50,338 2,131 10,653 21,306 31,958 1,579 7,896 15,793 23,689 129,816 649,081 1,298,161 1,947,242 27 Zero Waste Business Case: Final Report Economic Analysis Methodology The tasks used to develop the cost and revenue analysis are summarised in Table 14. Table 14: Economic Impact Analysis Task List Task Compile unit costs and revenue by activity and material Forecast province-wide costs and revenues Sensitivity analysis Assess distributional impacts Estimate energy impacts Estimate incremental tax revenues Forecast changes in the Provincial GDP Description A spreadsheet capturing unit cost estimates for the materials identified in the materials quantification forecast was developed. Unit costs are estimated for 5Rs activities. The analysis applies an incremental cost approach to capture the difference in costs between the BAU scenario (assumed to be disposal or recycling) and the zero waste diversion scenarios (assumed to have higher diversion rates and moving up the waste management hierarchy). The unit costs and revenues are applied to the materials forecast at the provincial level to provide an estimate of incremental waste management costs and revenues by waste management activity and material. Sensitivity analysis is completed on a range of data inputs such as costs as well as commodity values to assess the robustness of the results. The trends regarding costs on 5Rs are identified within the zero waste scenarios at a qualitative level. Energy impacts include changes in trucking, as well as opportunities for waste to energy in the zero waste scenarios. Incremental provincial government tax revenues, personal and corporate, resulting from waste and material management under diversion scenarios two and three are estimated based on estimates of employment impact and changes to private sector activity using input-output results. The incremental changes to provincial GDP under diversion scenarios two and three are estimated using Provincial input-output multipliers. Assumptions Assumptions have been applied to simplify the analysis as necessary. Where assumptions are made, they are generally conservative in nature to limit perceived bias of the results. Sensitivity analysis is completed to assess the impact of these assumptions on the results. Simplifying assumptions made in completion of the economic analysis are summarised below: Unit costs and revenues are assumed to be constant across the period 2010-2025. Available unit cost and revenue figures were gathered from a wide variety of sources as explained above; as far as reasonably possible they were obtained for 2011, but some are for 2010 and others for 2012. As a result the cost and revenue estimates over the period 2010-2025 are approximately equivalent to being calculated in real 2011 dollars; there is no discounting. Transportation costs are assumed to be included in collection costs. Depot and transfer costs are assumed to be included in processing costs. Promotion and education costs are assumed to be included in EPR collection and processing costs. Administrative costs are assumed to be included in collection, landfilling and processing costs. 28 Zero Waste Business Case: Final Report Reduction and reuse related costs are reflected as cost savings from avoidance of the need to manage materials within traditional waste management systems. Avoided costs are a combination of collection, landfilling, processing and waste-to-energy costs depending on the waste diversion strategy assumed adopted for a given material type. Recovered materials flow to waste-to-energy facilities which provide a revenue source from the sale of thermal energy. Municipal and private sector costs associated with collection, landfill, and processing are used as proxies for industry revenues. However, due to confidentiality, it was not possible to fully define costs by actor. Revenue from the sale of recyclables is typically shared between the client (local government or a private sector company in the case of the ICI or CRD sectors) and the waste management company collecting the recyclables. However, due to confidentiality, it was not possible to obtain accurate data on the average revenue split. For the purposes of this study, it has been assumed that the waste management company retains 50% of the proceeds from the sale of recyclables which increases its revenues. The other 50% is returned to the client thereby reducing its costs. Industrial structure and linkages are based on 2004 and 2008 data respectively (the most recent data available). This assumes that the technology of producing goods and services, input patterns and relative prices of goods and services remain unchanged, and that there are no new products that might require a different production technology or input mix. Data Sources for Costs and Revenue Estimates of waste management costs by material and activity were developed from publicly available reports supplemented by data gathered from a representative sample of regional districts and municipalities across BC and commercial commodity value research. The data sources reviewed to develop the cost analysis are summarised in the references. In addition to the literature review, waste management experts and service providers were contacted to provide pricing and market insights, and are footnoted throughout the document. Municipal Costs Local governments representing approximately 70% of the province’s population were surveyed to provide costs and insights regarding collection, processing and recycling costs and practices. The survey tool used to interview local government staff is presented in the Appendix. Responses were obtained from the following jurisdictions representing approximately 45% of the province’s population: Abbotsford Capital Regional District Kamloops Surrey City of North Vancouver District of North Vancouver West Vancouver 29 Zero Waste Business Case: Final Report Vancouver Regional District of Nanaimo It is recognised that these jurisdictions represent urbanised areas of the province, and that more remote locations may have different cost structures. This uncertainty is reflected in the sensitivity analysis completed in subsequent sections of the report. Notwithstanding these limitations, utilisation of data obtained directly from municipalities ensures a robust data set. As part of this survey, it was confirmed that landfill post closure and siting costs are incorporated into tippage fees provided. Commodity Revenue Commodity revenues are volatile as they are dependent on global markets which fluctuate for unpredictable reasons over time. For example, by mid-summer of 2012, prices for paper in particular had dropped by 50% from the values reported in the winter of 2011. This rapid and substantial change illustrates the volatility of materials markets which must be taken into consideration in the long term projection of impacts of different diversion scenarios. Interviews with stakeholders in the preparation of this document further emphasized the need to use a standardized commodity revenue source based within the Pacific Northwest. As such, a combination of pricing sources has been used to address price volatility, including: Estimates of commodity prices for recyclables,13 Data from a recent Recycling Marketing Study carried out for Metro Vancouver,14 Ontario metal prices (given that metal prices are reasonably consistent across Canada), Ontario Blue Box program costs (because per material costs are broken out by activity based costing research, and will not be substantially different to BC, even though BC has a deposit return system for beverage containers and Ontario does not) 15, and Encorp Pacific program costs16. To capture the volatility experienced from late 2008 to summer 2011, data from the years 2007-2012 was used (where available) to identify average unit commodity revenues. As noted previously, these are assumed to be constant throughout the period 2010-2025. In addition, sensitivity analysis has been performed on commodity values. Industry Stewardship Costs & Revenues EPR collection and processing costs for printed paper and packaging were based on the estimates used in setting the 2012 fees for the Ontario residential printed paper and packaging Blue Box program which are based on 2010 cost inputs17. The rationale for using this information is it provides accurate and comprehensive data split out by material from an ongoing residential printed paper and packaging EPR program. The per material costs are allocated through activity based costing studies carried out at a 13 recyclingnetworks.net Metro Vancouver, (2012). 15 Stewardship Ontario. (2012). 16 Encorp Pacific. (2012) 17 Stewardship Ontario. (2012). 14 30 Zero Waste Business Case: Final Report number of single stream and multi stream residential recycling programs throughout the province of Ontario and show that costs for collecting and recycling some residential plastic packaging materials are substantially more than the costs of managing paper and metals. Collecting and recycling PET and HDPE is economically attractive, as solid, high value markets are available for both these materials. A major new EPR program for residential printed paper and packaging is being launched in BC in May, 2014, whereby producers will finance the full cost of the residential printed paper and packaging collection and recycling system, thereby taking the costs away from taxpayers and municipal budgets. Material Diversion in the Zero Waste Scenarios Incremental diversion activity by material for the zero waste scenarios is presented in Table 15. Incremental diversion assumes that in the business as usual scenario, the material would have gone to landfill, whereas, within the zero waste scenarios, that material is being diverted into a 5Rs stream. Increased diversion is achieved through reducing and reusing organics and other materials, combined with increased industry stewardship for printed paper and packaging (residential and ICI) and any other materials. The allocation of material by 5Rs stream is based on an assessment of material and diversion strategy. This diversion strategy was reviewed and updated by the Client to ensure consistency with waste management objectives. Changes to the diversion strategy have a significant impact on the zero waste business case. Further analysis to optimise the zero waste business case is recommended. Table 15: Material Allocation by 5Rs Activity Reduce Organics Paper Plastics Multi-material Textiles & rubber Other Wood Ferrous Glass Renovation Non-ferrous Haz-waste Concrete Drywall Asphalt 25% 10% 10% 10% 10% Reuse Recycle 20% 10% % 75% 90% 90% 70% 80% 20% 10% 10% 10% 10% 30% 10% 10% 10% 10% 40% 20% 90% 100% 60% 90% 80% Recover Residuals management 20% 50% 90% 50% 90% 90% Costs and Revenue by Material and 5Rs Activity Table 16 shows the unit costs and revenues derived from the above sources and used in the financial model. The sensitivity analysis assesses the impacts of variations in these costs. The table shows that 31 Zero Waste Business Case: Final Report diversion of high value plastics (PET and HDPE), office paper and metals (particularly aluminum) contribute to the business case for the zero waste strategy. In a fully costed and allocated analysis, diversion of mixed plastics contributes a net high cost to the system. Diversion of residential plastic packaging will become part of a full residential industry stewardship program for printed paper and packaging in May, 2014. A range of industry stewardship programs were reviewed to assess costs and revenues. Due to the diversity in program structure, there is significant variation in the costs of industry stewardship programs. Average multi-material collection and processing costs have been assigned to all plastics, paper and metals collected in multi-material programs, as these materials will be picked up together. In a fully costed and allocated system, collection and processing costs are actually different for each material based on density and level of processing required to make the materials suitable for sale to end markets. 32 Zero Waste Business Case: Final Report Table 16: Unit Costs and Revenues by Material and Activity Landfill Costs ($/tonne) Collection Organics - Leaf and Yard Waste Organics - Food Waste and Kitchen Plastic- PET Plastic HDPE Plastic - Other Aluminum Non ferrous metals Other Wood Contaminated Wood Clean Paper - ONP Paper - MWP Paper - Clean Office Paper Paper - OCC Landfill Fees BAU, Total Industry Stewardship Programs ($/tonne) Collection Costs Costs Revenue Industry Steward ship, Total Industry Steward ship Savings (Costs) Relative to Landfill $98 $107 $205 $98 $98 $107 $205 $98 $92 $107 $199 $117 $325 $422 -$97 $296 $92 $107 $199 $117 $325 $435 -$110 $309 $92 $107 $199 $117 $325 $0 $325 -$126 $92 $107 $199 $68 $325 $2,433 -$2,108 $2,307 $92 $107 $199 $68 $325 $3,294 -$2,969 $3,168 $44 $60 $104 $44 $103 $0 $103 $1 $44 $60 $104 $44 $103 $0 $103 $1 $92 $107 $199 $112 $325 $73 $252 -$53 $92 $107 $199 $112 $325 $86 $239 -$40 $92 $107 $199 $112 $325 $179 $146 $53 $92 $107 $199 $112 $325 $107 $218 -$19 33 Zero Waste Business Case: Final Report Calculation of Costs and Benefits The unit costs and recycling revenues are combined with incremental materials forecast to estimate incremental waste management benefits (cost savings) from implementation of the zero waste strategy. Benefits (costs) are calculated as follows: Table 17: Calculation of Net Costs & Benefits BAU total = BAU collection + BAU landfill costs Industry stewardship total = Industry stewardship costs – Industry stewardship revenue Industry stewardship net benefits (costs) = BAU total – Industry stewardship total WTE net benefits (costs) = BAU collection – WTE cost – recycling collection Employment Impact Methodology The tasks undertaken to estimate employment impacts from implementation of the zero waste strategy are summarised in Table 18. Employment is assumed to result from the flow of materials into B.C. materials management streams and recycling streams both within and outside of B.C. Table 18: Employment Impact Task List Task Select input-output multipliers Assess and apply Jobs-pertonne-of-material ratios Description Input-output multipliers are applied to expenditures. Direct, indirect and induced wages as well as GDP and full time equivalent jobs were determined for each material type. Jobs-per-tonne-of-material ratios are assessed to estimate the downstream impacts of recycled materials re-entering the economy that are not captured using the input-output analysis. These ratios were applied to the volumes of materials quantities to estimate downstream employment impacts associated with the reuse, remanufacture, recycling or incineration of each material. Input-Output Multipliers Input-output multipliers assess the effects on the economy of an exogenous change in final demand for the output of a given industry. The input-output multipliers yield data on the direct impacts of increased industry output on wages, GDP and full time equivalent (FTE) jobs, as well as the indirect impacts on upstream suppliers and induced impacts as a result of employee spending. Indirect effects measure the additional economic value generated for industries that are suppliers to the waste management and remediation sector within B.C. Induced effects are a result of employees spending their earnings on goods and services (assumed to be in BC). An example of a company that may experience indirect effects of increased output within the waste management industry would be the vehicle mechanics that service the waste hauler's trucks. There are numerous examples of companies that may experience induced effects of increased output within the 34 Zero Waste Business Case: Final Report waste management industry, as employees are free to spend their income where they choose. One possible example is local restaurants, where employees may wish to spend incremental income. Downstream sectors are those that experience an economic impact due to changes in the flow through of material inputs to their business. In this sense, the reuse, remanufacturing and recycling reliant industries are downstream of the collection, landfill and processing sectors. Downstream sectors receive an economic impact due to changes in the availability of collected materials, which represent a throughput for their operations. An example of a downstream company is a glass bottle manufacturer that receives recycled glass to transform into a new product. The input-output multiplier for waste management and remediation services used for this analysis is presented in Table 19. It includes waste-to-energy services. These multipliers do not capture all of the downstream impacts of the zero waste strategy. Specifically, reuse, remanufacturing and recyclingreliant industries are not captured. For those impacts, a jobs per tonne of material estimate has been used, as described in the next section. Table 19: Input Output Multipliers, (Jobs per $1 million) Direct Indirect within Province Induced (with Safety Net) 18 Wages 0.31 0.11 GDP 0.63 0.2 FTEs 6.41 2.56 - 0.1 1.5 In general, input-output multipliers are applied to output or revenue data for a given industry sector in order to estimate associated impacts on wages, GDP and jobs. For this study, a proxy has been developed to approximate incremental industry revenues for collection and processing activities (Table 20). Table 20: Input Output Calculation Approximate incremental industry revenues = (Incremental Collection Cost) + (Incremental Landfill Cost) + (Incremental Industry Stewardship Collection and Processing Cost) +(Incremental Waste-to-Energy Cost) + 50% * (Incremental Revenues from the Sale of Recyclables) Reuse-Recycling-Recovery: Jobs-Per-Tonne-of-Material Ratios Reuse, remanufacturing and recycling-reliant industries as well as recovery are downstream of the collection, landfill and processing sectors. These sectors receive an economic impact due to changes in the availability of collected materials, which represent a throughput for their operations. These sectors are different in many ways from traditional waste management industries as they may not purchase their materials from industries that can increase or decrease their production according to demand. 18 Stats Canada (2008) 35 Zero Waste Business Case: Final Report Furthermore, the industry structures for remanufacturing or recycling-reliant industries vary a great deal from the structures of their counterparts that rely on virgin materials or traditional approaches. As a result, employment impacts in the reuse, remanufacturing, and recycling-reliant industries are not well represented by input-output analysis. Instead, estimates for these impacts are established by utilizing ratios for jobs per tonne of material, developed by assessing other recycling studies.19,20,21. Multipliers are applied to data for tonnage of materials in the two zero waste diversion scenarios. In order to maintain a conservative estimate in cases where multiple data sources exist, the lower value has been selected (Table 21). These ratios are then applied to the data for tonnage of diverted materials that are recycled under each scenario. Table 21: Downstream Jobs-Per-Tonne-of-Material Ratios Activity Study # Organics Paper Plastics Multi-material Textiles & rubber Other Wood Ferrous Glass Renovation Non-Ferrous Haz-waste Concrete Drywall Asphalt Reuse & remanufacture Recycling Reliant 1 2 3 1 2 3 n/a n/a n/a - 0.4 - n/a n/a n/a - 1.8 4.16 - - 20 - 9.3 10.3 - 6.2 - - - 2.5 - 8.5 7.35 - - 9.24 / 2.5 - - - - - 2.5 - 2.8 2.8 - - 2.8 - - 20 - - 4.2 - - 7.35 - 2.6 7.85 - 6.2 - - - - - - 20 - - 4.12 - - - - - - - - - 0.02 - - - - - - - - - - - - - - Note: Study # 1 2 3 Morris & Morawski (2011), Institute for Local Self-Reliance (1997), Tellus Institute (2011) Energy and GHG Impacts Two approaches were utilised to estimate energy and greenhouse gas emissions. A simplified analysis was developed to estimate the direct impacts of the 5Rs strategy. In this approach, energy and emissions that occur within BC are estimated based on changes to trucking of material under the different diversion scenarios. In accordance with IPCC guidelines, CO2 from landfills is greenhouse gas neutral. In addition, since the Province requires methane capture in all landfills with more than 10,000 tonnes per year of disposal, the methane from additional material is assumed to be zero. 19 Morris & Morawski (2011), Institute for Local Self-Reliance (1997) 21 Tellus Institute (2011) 20 36 Zero Waste Business Case: Final Report The second approach to calculating GHG emissions uses a lifecycle perspective that also captures the upstream benefits of using recycled material instead of virgin resources. Emission factors for greenhouse gas emissions and energy were extracted from Environment Canada’s WARM model 22. This model provides a streamlined life-cycle approach to characterise GHG and energy impacts of waste management activities. The incremental GHG emissions are presented in Table 22. Incremental energy impacts are presented in Table 23. These factors were combined with tonnage by material to estimate GHG and energy impacts. Table 22: GHG Emissions from Waste Diversion Options Compared to Landfilling, Including Carbon Sinks (tonnes CO2e/tonne), Scenario 2 and 3 Material Newsprint Fine Paper Cardboard Other Paper Aluminum Steel Copper wire Glass HDPE PET Other Plastic Food Scraps Yard Trimmings White Goods 22 Reduce 0 0 0 0 0 0 0 0 0 0 0 -1.04 0.09 0 Recycling -1.53 -4.38 -3.54 -3.98 -6.51 -1.2 -4.11 -0.12 -2.29 -3.64 -1.82 0 0 -1.48 Recovery 1.16 -1.22 -0.33 -0.75 0 -1.04 0 0 2.87 2.15 2.65 -0.78 0.34 -0.27 ICF, 2005 37 Zero Waste Business Case: Final Report Table 23: Energy Savings from Waste Diversion Options Compared to Landfilling (GJ/tonne), Scenario 2 and 3 Newsprint Paper Cardboard Other Paper Aluminum Steel Copper Glass HDPE PET Food Scraps Yard Trimmings White Goods/Electronics Reduce 0.9 2.4 1.7 1.6 0.04 0.04 0.04 0.04 0.04 0.04 1.7 0.8 Recycling 6.5 15.8 8.5 9.5 87.4 12.6 71.7 1.7 64.4 85.3 0 0 Recovery 2.7 2.2 2.3 2.2 0.07 11.0 0.05 0.04 6.5 3.4 0.7 0.9 23.9 8. 7 Human Health and Toxicity Impacts A range of human health and eco-system impacts occur from generation, diversion, transport, processing, and disposal of waste. Impacts include common air contaminants (CO, SOx, NOx, particulate, VOCs and NH3). In addition, hazardous air pollutants such as mercury, dioxins and furans occur from a range of waste management options. In general, reduce and re-use have negligible human health or toxicity impacts, while, recovery and residuals have the highest human health impacts. To quantify human health and ecosystem impacts, multipliers developed by Metro Vancouver23 have been used. Table 24: Human Health and Ecosystem impact by 5R activity [kG/ Tonne material] Recycling & Composting Landfill WTE Human Health Impact (eToluene) -945 60 105 24 Ecosystem Impact (Herbicide equivalents) -2 <0.1 2 23 Metro Vancouver, 2011 A detailed description of the human health and environmental impacts is presented in the Metro Vancouver (2011) report. 24 38 Zero Waste Business Case: Final Report Results This section presents results from the economic and job impact analyses of the implementation of higher waste diversion scenarios. Economic Business Case The economic business case is calculated using the equation in Table 25. Benefits are summed across material types to arrive at the net economic benefit (cost) for the waste management system at the provincial level within the province of BC in 2025. The net economic benefit represents the net savings to the waste management system as a whole for scenarios two and three compared with the business as usual scenario. If the net waste management benefit is positive, the overall economic cost of waste management has been reduced relative to BAU. If the net waste management benefit is negative, the overall economic cost of waste management has increased relative to BAU. Table 25: Calculation of Incremental Economic Benefit (Cost) of Higher Waste Diversion Incremental economic benefit (cost) of higher waste diversion = incremental diversion of material x [ % reduced x net reduction benefit (cost) +% reused x net reuse benefit (cost) +% diverted to Industry Stewardship x net Industry Stewardship benefit (cost) +% diverted to WTE x net WTE benefit (cost )] Table 26 shows the financial benefits (costs) for scenarios two and three. Implementation of scenario two will have an annual net benefit of $56 million by 2025. Implementation of Scenario Three will have an annual net benefit of $126 million by 2025. It should be noted that the fundamental difference between industry stewardship and other programs is who pays for the program, and who manages the program. In all cases where diversion is achieved through industry stewardship programs, costs of existing programs are generally shifted to producers and consumers and away from municipalities and tax payers. There is an assumption that producers who pay for industry stewardship programs will endeavour to make them as economical as possible because of competitive pressures while meeting environmental and other performance targets. Based on this analysis the following observations are made: 1. Those materials with the most significant economic benefit in support of zero waste include organics, high value plastics (PET and HDPE) and non ferrous metals. All papers are also an important focus because of the volumes involved and anticipated demand from end markets over the long term. Focusing policy tools on these materials is recommended in development and implementation of policies at the provincial level. 2. A number of jurisdictions have implemented organics recycling programs throughout BC. Evaluation of these initiatives is recommended to understand program costs and impacts. 39 Zero Waste Business Case: Final Report 3. Implementation of the PPP is scheduled to commence in 2014 and will cover plastics and nonferrous metals. Program monitoring and evaluation by the stewardship agencies is recommended to ensure costs are comparable to other jurisdictions. 4. Average residential printed paper and packaging EPR costs have been applied based on available data. This has a significant impact on the business case for industry stewardship programs in general and for plastics in particular. It is recommended the industry stewardship costs for PPP be explored in more detail to confirm the assumptions used in the current analysis. Table 26: Economic Benefits (Costs) of Higher Waste Diversion Scenarios (Relative to BAU in 2025) ($ millions) Material Organics Paper Plastics Multi-material Textiles & rubber Other Wood Ferrous Glass Renovation Non-Ferrous Haz-waste Concrete Drywall Asphalt Total Scenario Two [$ millions] $34.7 $1.1 $16.2 -$1.5 $1.8 -$8.2 $0.7 -$0.5 -$0.3 $0.2 $13.3 -$5.7 $1.7 $1.3 $0.8 $55.6 Scenario Three [$ millions] $59.1 $2.2 $43.1 -$2.8 $3.5 -$18.9 $1.8 -$2.0 -$0.8 $0.5 $43.1 -$12.3 $4.0 $3.2 $1.9 $125.6 40 Zero Waste Business Case: Final Report A breakdown of expenditures and revenues by scenario is presented in Table 27. Table 27: Summary of Expenditures and Revenues by Scenario (Relative to BAU in 2025) ($ millions) Scenario Two [$ millions] Scenario Three [$ millions] $53 $98.4 -$20.4 $114.6 $198.8 -$35.4 -$131 -$0.2 -$298.5 -$20.5 Material Revenue $56.4 $147.7 WTE Total Revenue (2) Net Revenue (1+2) -$0.6 $55.8 $55.6 -$1.6 $146.1 $125.6 Expenditures Solid Waste Collection Tippage Recycling Processing Industry stewardship Costs Total Expenditures (1) Revenue Distributional Impacts Allocation of the benefits of the two waste scenarios between public sector and private sector is summarised in Table 28. Implementation of Scenario Two will reduce public sector costs by $33 million per year (in 2025), while implementation of Scenario Three will reduce public sector costs by $70 million per year (in 2025). Table 28: Public Sector versus Private Sector Costs of Higher Waste Diversion Direct Economic Benefits (Costs) Public sector Private sector Total Net Benefit (Cost) relative to BAU BAU, 2025 ($450) ($750) ($1,200) Scenario Two, 2025 [$ millions] $(417) $(727) $(1,150) $55.6 Scenario Three [$ millions] $(380) $(694) $(1,086) $125.6 Sensitivity Analysis Sensitivity analysis was carried out to determine which factors caused a significant change in the forecast results if their values were varied. Table 29 below shows the results of the analysis compared to the base case. Based on this analysis, the business case remains positive for all variables tested. Furthermore: The model is insensitive to changes in commodity values and collection fees. For example, for scenario two, a -25% change in commodity values causes net costs to increase by $0.2 million compared to the base case 41 Zero Waste Business Case: Final Report The model is sensitive to changes in landfill fees. The impact of landfill fees rising to $184/tonne was explored since this is expected to occur by 2015 for Metro Vancouver due to the impact of reduced landfill volumes driven by increased recycling and the banning of organic waste from landfills25. For scenario two, instead of net costs of $55.6 million there would be a net benefit of $108 million. The model is moderately sensitive to processing costs with a 25% change resulting in a 29% change in the benefits. The model is relatively insensitive to changes in WTE costs which are not shown for that reason. Table 29: Sensitivity Analysis on Economic Benefit (Cost) Scenario Two Scenario Three Base Case $55.6 $125.6 Commodity Commodity Landfill Fee Values Values = (-25%) (+25%) $184/tonne $55.3 $55.8 $108 $124.8 $126.5 $225 Collection Fees (+25%) $50.5 Processing Costs (-25%) $72.8 Processing Costs (+25%) $38.2 $112 $162 $89.1 Job Creation and Economic Impact Results Direct, Indirect and Induced Impacts Implementation of a zero waste strategy has a positive benefit in terms of wages, GDP and jobs. By 2025 Scenario Two annually stimulates $12.2 million in additional wages, $27 million in additional GDP and over 300 full time jobs. Scenario Three produces approximately three times that impact26, with $40 million in additional wages, $89 million in incremental GDP and over 1,000 additional jobs. In all cases, direct impacts are roughly two thirds of the total, while indirect impacts are roughly 25 percent, and induced impacts make up the remaining 10 percent. Impact on wages, GDP, full time employment, output and provincial income taxes are shown in Table 30 and Table 31. 25 Sinoski, K. The relationship is non-linear because the percentage composition of the different material types varies from Scenario 2 to Scenario 3 and the economic impact per tonne of incremental diversion varies by material type. For example, organics make up a higher percentage of the incremental diversion in Scenario 2 than in Scenario 3. Hence in Table 26, although the total volume of incremental waste diverted roughly doubles, the economic benefit from organics only increases by about 50% since the volume of organics incrementally diverted only increases by about 50%. 26 42 Zero Waste Business Case: Final Report Table 30: Scenario Two Job Creation and Economic Impacts in Material Collection and Processing Direct impact Wages [$ million] GDP [$ million] FTEs Indirect impact Wages [$ million] GDP [$ million] FTEs Induced impact Wages [$ million] GDP [$ million] FTEs Total impact Wages [$ million] GDP [$ million] FTEs Provincial Taxes [$ million] 2015 2020 2025 $3.0 $6.1 62 $6.0 $12.2 124 $9.0 $18.3 186 $1.1 $1.9 25 $2.1 $3.9 50 $3.2 $5.8 74 $$1.0 15 $$1.9 29 $$2.9 44 $4.1 $9.0 101 $8.1 $18.0 203 $12.2 $27.0 304 $0.25 $0.50 $0.76 43 Zero Waste Business Case: Final Report Table 31: Scenario Three Job Creation and Economic Impacts in Material Collection and Processing Direct impact Wages [$ million] GDP [$ million] FTEs Indirect impact Wages [$ million] GDP [$ million] FTEs Induced impact Wages [$ million] GDP [$ million] FTEs Total impact Wages [$ million] GDP [$ million] FTEs Provincial Taxes [$ million] 2015 2020 2025 $9.9 $20.1 205 $19.8 $40.3 410 $29.7 $60.5 615 $3.5 $6.4 82 $7.0 $12.8 164 $10.6 $19.1 246 $$3.2 48 $$6.4 96 $$9.6 144 $13.4 $29.7 335 $26.8 $59.5 670 $40.3 $89.2 1005 $0.83 $1.66 $2.50 Downstream Impacts The Jobs-Per-Tonne-of-Material ratios allow an analysis of the downstream impacts of materials diverted from landfill and entering the reuse, recycling and recovery sectors. Only direct job impacts are assessed in this case (Table 32). By 2025, Scenario Two leads to more than 2,000 additional jobs in downstream sectors. This is almost seven times greater than the corresponding impact of the diversion strategies on direct jobs in the collection and processing sectors. Scenario Three leads to more than 4,800 jobs, almost five times the corresponding direct jobs impact in collection and processing. Many more jobs are estimated to be created in the downstream sectors because the reuse, remanufacturing and recycling-reliant industries are much more labour-intensive than the collection, landfill, processing and waste-to-energy sectors. The 2011 Tellus Institute study27 examined the impact of recycling on the US economy. It reports that waste disposal is the least labour intensive of the various waste management activities, generating the fewest jobs per ton of waste (0.1 jobs per 1,000 tons). This is due to the fact that the capital intensive equipment used at disposal facilities can handle large tonnages with few employees. Materials collection generates more jobs than disposal but still relatively few. Processing of organics (0.5 jobs per 1,000 tons) and recyclables (2 jobs per 1,000 tons) are somewhat more labour intensive. Manufacturing using recycled materials as inputs creates a 27 Tellus Institute (2011). 44 Zero Waste Business Case: Final Report relatively high number of jobs per 1,000 tons, varying by material type from about 4 jobs per 1,000 tons for paper as well as iron and steel manufacturing, to about 10 jobs per 1,000 tons for plastics manufacturing. Although relatively small tonnages of material are involved, municipal solid waste reuse and remanufacturing activities are particularly job intensive owing to the labour required for disassembly, inspection, repair/refurbishment, reassembly, and testing. It must be noted that not all downstream jobs would be located in BC due to the impact of leakage. For many material types, remanufacturing of the recycled materials is done outside of BC. For example, paper has almost no recycling capacity in BC (less than 1 percent). As an example, the last recycled newsprint mill in BC (Catalyst Paper) closed within the last two years. The magnitude of the potential increase in downstream jobs shows the importance of government policies that encourage the creation and retention of remanufacturing facilities within BC. Table 32: Full Time Equivalent Job Impacts on Downstream Reuse, Recycling and Recovery Sectors Scenario Two Scenario Three 2015 2020 2025 669 1,604 1,338 3,208 2,008 4,813 GHG and Energy Impacts The GHG and energy savings from implementation of the zero waste strategy are summarised in Table 33. Taking a global perspective, GHG emissions reductions would be 1,047 KT/year or 2,277 KT per year by 2025 for scenarios two and three respectively, while energy savings would be 10,535 GJ/year or 26,629 GJ/year by 2025 for scenarios two and three. Table 33: GHG and Energy Impacts of Zero Waste Strategy in 2025 [GJ] Scope GHG Savings [Kilo tonnes] Energy Savings ['000 GJ] GHG Savings [Kilo tonnes] Energy Savings ['000 GJ] Scenario Two Scenario Three 33.6 72.6 465 1000 1,047 2,277 10,535 26,629 Within BC Global Zero Waste Business Case Results Summary A summary of the economic, job creation and environmental benefits of implementing a zero waste strategy is summarised in Table 34. Based on these results, the business case is favourable. 45 Zero Waste Business Case: Final Report Table 34: Zero Waste Business Case Summary Results (Relative to BAU, 2025) Triple Bottom Line Summary Scenario Two (62% diversion rate) Scenario Three (81% diversion rate) Public Sector Benefits (Costs) [$ million] Private Sector Benefits (Costs) [$ million] Direct Economic Benefits (Costs) [$ million] Change in GDP [$ million] $33 $70 $23 $56 $56 $126 $27 $89 Jobs Created (Destroyed) (FTEs) 304 (direct, induced and upstream indirect) 1,005 (direct, induced and upstream indirect) Downstream Jobs Created (Destroyed) (FTEs) Greenhouse Gas Emissions Reduced [KT/Year] Human Health Impacts [KT/year e toluene] Ecosystem Impacts [KT/year Herbicide Equivalents] 2,008 (downstream) 4,813 (downstream) 1,047 2,277 947 1741 1 3 46 Zero Waste Business Case: Final Report Discussion Distributional Impacts The trends regarding expenditures on 5Rs, landfilling, recycling and industry stewardship programs are identified within the zero waste scenarios. Table 35 below provides a qualitative analysis of trends in the shifting of costs among consumers, producers and government. A challenge in developing a quantitative assessment of the impacts is the lack of information on the distribution of costs among industry segments. A second issue is the dynamic nature of landfill fees wherein a reduction in waste sent to landfills might in some cases result in an increase in tippage fees due to the fixed costs associated with landfill operations. The impact of this issue will depend on landfill size and annual throughput. Table 35: Trends in Cost Shifting from Implementation of Zero Waste Strategies Compared to Landfilling 5R Strategy Reduce Reuse Recycle (industry stewardship) Recycle (Municipal) Recovery Residuals Distributional Impact Economic activity in waste management sector is reduced. A reduction in waste will prolong the life of the landfill, but may result in an increase in the disposal cost per tonne of waste. Local government costs are reduced; this could result in savings or other benefits for taxpayers. Potential for diversification of local private enterprise. A reduction in waste will prolong the life of the landfill, but may result in an increase in the disposal cost per tonne of waste. In areas where households pay a per capita landfill fee, costs shift from local government and taxpayers to producers and consumers. Industry stewardship may promote product design changes that lead to a reduction or change in materials which positively impact the amount and type of waste generated. A reduction in waste will prolong the life of the landfill, but may result in an increase in the disposal cost per tonne of waste. Costs are shifted within local government from landfilling to recycling. Depending on commodity prices, local governments may receive revenue from the sale of valuable materials. A reduction in waste will prolong the life of the landfill, but may result in an increase in the disposal cost per tonne of waste. Costs of waste to energy are generally lower than for landfilling, resulting in reduced costs for local government and taxpayers. Where a significant portion of landfill costs are fixed, lower tonnages being landfilled may not benefit net costs as much because the fixed costs will have to be distributed over a lower volume of material being landfilled; this may increase the fee per tonne of landfilling, particularly at small landfills Lower residual waste disposal rates may increase the cost per tonne of waste to operate a landfill; however, the life of the landfill will be prolonged, reducing costs associated with siting and establishing new landfills 47 Zero Waste Business Case: Final Report Impact of Increased Diversion on Landfill Costs In estimating the costs and benefits of increased diversion, we have assumed the avoided landfill fee is constant and equal to the current average landfill cost of $107/tonne. Sensitivity analysis included the impact of increasing landfill costs to $184/tonne which is seen to be significant and based on projected costs of landfilling in Metro Vancouver in 2015 based on achieving a 70% diversion rate28. It is beyond the scope of this work to examine the market dynamics of avoided landfilling and the impacts on landfill costs since this is a long term marginal cost issue related to the cost of the next increment of landfill capacity compared with other alternatives such as waste to energy. The impact of increased landfill diversion is likely to increase landfill costs meaning that our assumption is a conservative one. Leakage Leakage is defined for the purpose of this study as waste material that is produced in BC and is disposed of or diverted without creating economic returns within the province. According to this definition, leakage includes: Illegal dumping since it generates no economic activity. Material that is exported from BC to landfills outside BC, since the value of the material is lost to BC and the tippage fee is also paid to an entity outside BC. There is also reverse leakage – or inflow – occurring. For instance, plastic bottles purchased in the United States and carried back into BC are not eligible for deposit returns, but may be processed through a municipal blue box or ICI recycling program Exporting of material by BC processors for re-use in international markets is not leakage, since there is economic activity from sorting and collection and the processors receive revenue from selling the product. By its nature, estimating the quantities of leakage is difficult. No data was identified to estimate the amount of illegal dumping, but it is not expected to be significant. Similarly waste exports were identified for the ICI sector in Abbotsford, but no data on the quantities was obtained. It was not possible to identify other regions in the province where exporting waste is occurring, but a reasonable estimate is 50,000 to 100,000 tonnes/year. 28 Ref http://www.richmondreview.com/news/176033441.html 48 Zero Waste Business Case: Final Report Conclusions Overall, higher waste diversion through implementation of a zero waste strategy will produce substantial societal benefits. Scenario Two will have an annual net benefit of $55.6 million by 2025. Implementation of Scenario Three will have an annual net benefit of $126 million by 2025. These benefits accrue almost equally between the private sector and the public sector. In addition to the positive economic impacts, implementation of the zero waste strategy will also have positive job creation, GDP and GHG impacts. By 2025 Scenario Two stimulates $12 million in additional wages annually, $27 million in additional GDP annually and just over 300 full time jobs. Scenario Three produces approximately three times that impact, with $40 million in additional wages annually, $89 million in incremental GDP annually and over 1,000 additional jobs. In all cases, direct impacts are roughly two thirds of the total, while indirect impacts are roughly 25 percent, and induced impacts make up the remaining 10 percent. The potential for creating direct downstream jobs in the reuse, remanufacturing, and recycling-reliant industries is even greater. By 2025, Scenario Two leads to more than 2,000 additional jobs in downstream sectors. This is almost seven times greater than the corresponding impact of the diversion strategies on direct jobs in the collection and processing sectors. Scenario Three leads to more than 4,800 jobs, almost five times the corresponding direct jobs impact in collection and processing. For many material types, remanufacturing of the recycled materials is done outside of BC. The magnitude of the potential increase in downstream jobs shows the importance of government policies that encourage the creation and retention of remanufacturing and recycling-reliant facilities within BC. It should be noted that this number of jobs is small in relation to the full BC economy (which has an employment base of 2.5 million), and the benefits are minimal unless the downstream jobs can be located in BC. Development of a remanufacturing industry in BC utilising the most significant materials (paper, plastics, ferrous and non ferrous metals) is critical to increasing the economic benefits of a zero waste business case. Recommendations Based on the analysis completed, the following recommendations are submitted for consideration: 1. The business structure of a particular EPR program has a significant impact on the cost of program delivery. Ensuring that costs are minimised to industry and consumers will reduce backlash from program implementation. Further analysis on this issue is recommended. Sensitivity analysis revealed that a different mix of zero waste strategies could positively impact the business case for zero waste. Further analysis to optimise the zero waste business case is recommended. 2. Materials quantification forecasts highlight inconsistencies in data collection procedures and material forecasts developed at the provincial level versus at the regional districts. Implementation of a consistent material quantification methodology is recommended to support improved decision making and policy analysis. 49 Zero Waste Business Case: Final Report 3. Costing of 5Rs activities highlights that accessing municipal data is frequently a challenge due to confidentiality requirements. Development of data sharing policies is recommended to improve the transparency of subsequent analysis and to assist municipalities to ensure that pricing across jurisdictions is fair and competitive and that provincially, investment in waste management activities is based on defensible cost data. 50 Zero Waste Business Case: Final Report References AECOM, Economic Benefits of Recycling in Ontario, 2009. BC Ministry of Environment. Guide to the Development of Regional Solid Waste Management Plans for Regional Districts. Retrieved from http://www.env.gov.bc.ca/epd/mun-waste/waste-solid/sw-mgmtplan/guideplan/pdf/guide-swmplan.pdf , December 1994. BC Ministry of Environment, BC Municipal Solid Waste Tracking Report, 2006. BC Ministry of Environment, Economic Impacts of the BC Recycling Regulation, 2008. BC Stats, Recycling in BC, 2007. BC Stats, 2004 British Columbia Economic Multipliers, 2008. BC Stats, BC Solid Waste Flow, 2006 Summary Report, 2010. BC Stats, Electronic Waste Recycling in BC, 2009. BC Stats, Filling the Landfills, 2012. BC Stats (a), Solid Waste Generation in British Columbia 2010 - 2025 Forecast, 2012. BC Stats (b), Municipal Solid Waste 2010 - 2025 Fact Sheet, 2012. Carpet America Recovery Effort, California Carpet Stewardship Plan December, 2011. City of Burnaby, Solid Waste and Recycling by-law (no. 13052), 2012. City of New Westminster, Automated Single Stream collection Program Report from Engineering Department, May 2, 2011. City of Red Deer, Solid Waste and Recycling Bylaw No. 3464, 2011. City of Vancouver Solid Waste Management Branch, Solid Waste Division Report, 2012. Container Recycling Institute, Returning to Work: Understanding the Domestic Jobs Impacts from Different Methods of Recycling Beverage Containers December, 2011. DSM Environmental, The U.S. Recycling Economic Information Update Recycling Economic Information (REI) Update. Prepared for the Northeast Recycling Council, 2009. Duncan Bury Consulting, Overview of stewardship and EPR job and economic impact studies, 2012. Eco Canada, Solid Waste Management Labour Market Research study, 2010. Encorp Pacific. 2011 Annual Report. http://www.return-it.ca/ar2011/index.php, 2012. European Environment Agency. The Role of Recycling in the Green Economy, 2011. 51 Zero Waste Business Case: Final Report Gardner Pinfold Consulting. Prepared for Ministry of Environment Environmental Quality Branch Economic Impacts of the BC Recycling Regulation, 2008. Garry Horn, 2004 BC Economic Multipliers and How to Use Them, 2008. Glenda Gies & Associates, Current System for Managing Residential Packaging and Printed Paper in British Columbia. Prepared for Multi-Material British Columbia, 2012. ICF Consulting, Determination of the Impacts of Waste Management Activities on Greenhouse Gas Emissions, 2005. Institute for Local Self-Reliance Washington, DC. Retrieved from http://www.ilsr.org/recycling-meansbusiness, 1997. Larsen, A.W. et al. Diesel consumption in waste collection and transport and its environmental significance, Waste Management & Research, 2009:27; 652-659, 2009. Local Economy Policy Unit. U.K Jobs From Recycling: Report on Stage II of the Research, 2004. Metro Vancouver (a). Management of Municipal Waste in Metro Vancouver, 2009. Metro Vancouver (b). Environmental Lifecycle Assessment of Waste Management Strategies with a Zero Waste Objective, 2009. Metro Vancouver. Recycling Market Study, May 2012. Metro Vancouver. Waste Composition and Energy Content Projections, 2012. Morris, J. & Morawski, C., Returning to Work: Understanding the Domestic Jobs Impacts from Different Methods of Recycling Beverage Containers. Prepared for the Container Recycling Institute, 2011. National Recycling Coalition. U.S. Recycling Economic Information Study, 2000. North Carolina Department of Environment and Natural Resources. Recycling in North Carolina – Momentum Towards Sustainable Materials Management August, 2011. Organisation for Economic Co-operation and Development. Analytical Framework for Evaluating the Costs and Benefits of Extended Producer Responsibility Programmes, 2005. Randall W Jackson. Recycling and Remanufacturing in Input-Output Models, 2008. Recycling Council of Ontario. Economic Benefits of Recycling, 2012. recyclingnetworks.net (http://www.recyclingmarkets.net/) Region of Peel. Onboard Weigh Scales: A Multi-Family Weight-Based Waste and Recycling Generation Pilot, 2009. 52 Zero Waste Business Case: Final Report Sinoski, Kelly. Metro Vancouver board rejects proposed drop in garbage fees for 2013. Vancouver Sun. October 29, 2012. Stats Canada Catalogue no. 15F0046XDB. Provincial Input-Output Multipliers, 2008. Statistics Canada. Waste Management Industry Survey: Business and Government Sectors,2008, Catalogue 16F0023X. Retrieved from http://www.statcan.gc.ca/pub/16f0023x/16f0023x2010001eng.pdf, 2010. Stewardship Ontario. 2012 Fee Calculation Tables. http://www.stewardshipontario.ca/bb-consultationarchives, 2012. Tellus Institute; Sound Resource Management for Natural Resources Defense Council. More Jobs, Less Pollution, 2011. US Environmental Protection Agency. Standard Volume to Weight Conversion Guide. http://www.epa.gov/smm/wastewise/pubs/conversions.pdf, 2012 Zero Waste Community. Unfinished Business: The Case for Extended Producer Responsibility, 2012. 53 Zero Waste Business Case: Final Report Appendix: Local Government Survey on Waste Management Costs and Practices Municipal and/or Regional Collection Description Single family (curbside) Garbage collection Contract or municipal crew? 2011 $/tonne? if not available then: o 2011 collection costs (contract or operations) o 2011 tonnages Single family (curbside) Recycling collection Contract or municipal crew? 2011 $/tonne? if not available then: o 2011 (net) collection and processing costs (contract or operations) o 2011 tonnages Single family (curbside) Green Bin collection Contract or municipal crew? 2011 $/tonne? if not available then: o 2011 collection costs (contract or operations) o 2011 tonnages Multi-Residential Recycling collection Contract or municipal crew 2011 $/tonne? if not available then: o 2011 collection costs (contract or operations) o 2011 tonnages Landfill Disposal 2011 $/tonne? Organics Disposal 2011 $/tonne? Recyclables Processing MRF – contract or municipal crew? 2011 tonnes processed? 2011 tonnes marketed? 2011 $/tonne? if not available then: o 2011 collection costs (contract or operations) o 2011 tonnages Historical market prices (up to past 5 years)? Any information on Private sector ICI garbage and/or recycling collection costs (by tonne or by lift - typical lift size)? Private sector DLC collection costs (by tonne or by lift – typical lift size)? Private Sector Multi-Res garbage and/or recycling collection costs (by lift - ask typical size or by tonne)? 54 Zero Waste Business Case: Final Report
© Copyright 2025 Paperzz