Now

critical path or deterministic
expected value?
deterministic
Fixed and known in
advance, representing a
high level of certainty
when planning.
Click here for Hint
or
crashing
or
incident
or
AON?
incident
A project with no
previously planned timing
and a high degree of
dependence on its
immediate environment
for successful resolution.
Click here for Hint
immediate predecessor or milestone or
precedence relationship?
immediate predecessor
A task that must be
completed before
another task can start.
Click here for Hint
AON
or
AOA
or
WBS?
WBS
Work Breakdown
Structure, a document
specifying the tasks
required to finish a project.
Click here for Hint
milestone
or
slack
or
incident?
milestone
A point of significance in
the time line of a project.
Click here for Hint
AOA
or
AON
or
Gantt chart?
AOA
A style of project network
diagram in which arrows
represent tasks and their
connections with nodes
represent precedence
relationships.
Click here for Hint
standard normal distribution
or probabilistic?
or
probabilistic
Variable or not well
known in advance;
subject to randomness.
This represents
uncertainty in planning.
Click here for Hint
incident
project
or
path
or
PERT?
project
A unique collection of
activities creating a
particular outcome.
Click here for Hint
backward scheduling or CPM
forward scheduling?
or
backward scheduling
Scheduling backward
from a project’s deadline
to its start time.
Click here for Hint
AOA
or
AON
or
Gantt chart?
AON
A style of project network
diagram in which nodes
represent tasks and the
connecting pathways
represent precedence
relationships.
Click here for Hint
forward scheduling or backward scheduling
or critical path?
forward scheduling
Starting an activity as
soon as possible,
regardless of its deadline.
Click here for Hint
CPM
or
PERT
or
WBS?
PERT
Program Evaluation and
Review Technique, a
project management
methodology developed
by the US Navy.
Click here for Hint
standard normal distribution or
probabilistic or deterministic?
standard normal
distribution
A normal distribution with
a mean of zero and a
variance of 1.
Click here for Hint
expected value or probabilistic
Central Limit Theorem?
expected value
The mathematical
expectation of a random
variable, calculated as
the weighted average of
all possible values that
may occur.
Click here for Hint
or
critical path
or
milestone
or
expected value?
critical path
The longest path through
a project network;
determines the length of
the entire project.
Click here for Hint
backward scheduling or PERT
iterative planning?
iterative planning
Adjusting plans at short
intervals, to reflect
emerging information.
Click here for Hint
or
PERT
or
precedence relationship
or
path?
precedence relationship
A dependency between
two tasks, usually
requiring that one task
be completed before the
other task is started.
Click here for Hint
PERT
or
CPM
or
WBS?
CPM
Critical Path Method,
a project management
methodology developed
by DuPont Corporation.
Click here for Hint
path
or
precedence relationship
or
crashing
Expediting the
completion of a task or
group of tasks, to finish a
project sooner.
Click here for Hint
crashing?
path
or
precedence relationship
Gantt chart?
Gantt chart
A scheduling diagram
that illustrates activities
across a horizontal time
line.
Click here for Hint
or
PERT
or
precedence relationship
path
Any sequence of linked
activities that connect
the beginning with the
end of a project network.
Click here for Hint
or
path?
slack
or
incident
or
crashing?
slack
The degree to which a
task may be delayed from
its early start without
delaying the project.
Click here for Hint
standard normal distribution or PERT
Central Limit Theorem?
or
Central Limit Theorem
The observation that
sample values approximate
a normal distribution,
regardless of the
underlying distribution of
the population being
sampled.
Click here for Hint