Affinity and Tree Diagrams: A Practical Approach to Control Requirement Volatility in Software Projects B.R Shubhamangala Research Scholar Department of MCA Dayananda sagar Institutions Bangalore-78 [email protected] V Suma Associate Dean Research Industry Incubation Centre, Dayananda sagar Institutions Bangalore-78 [email protected], Abstract— Requirement volatility is considered as a critical risk factor in software enterprises. Requirement volatility is driving the project towards poor quality, higher cost and schedule slippage. Hence, to address volatility, enterprises have taken various measures. Though measures could not effectively address volatility, the major four reasons causing volatility were brought out. By exploring the origin of above said reasons and factors influencing those reasons, it is evident that volatility can be controlled but cannot be eliminated. The four reasons are contributing towards volatility by rendering volatility defects. Hence, research by industrial multiple case study approach is undertaken with the motive of controlling volatility. Projects considered under case study has spanned across major five application domains from six CMMI level 5 certified companies. Defect analysis of each of the four reasons is carried over in pre release and post release phase of the projects. From the defect analysis, a solution of affinity diagram followed by tree diagram to address the volatility is introduced. Effectiveness of solution in controlling volatility is made evident by the practical case study example. Key words: Requirement Volatility; Affinity Diagrams; Tree diagrams; Case study I. INTRODUCTION Competitive business pressure of IT market and ever increasing customer demands, are pushing the IT enterprises to deliver niche quality products. Software quality is determined by requirements [1].Since, the requirements span across all the major activities project development such as cost estimation, schedule allocation, deign specification, coding etc, requirements are identified as key drivers of cost and schedule. Quality, cost and schedule are the critical project success factors and these factors are decided by the requirements. In reality, requirements have become critical risk factor instead of assuring project success, because of changing nature of requirements [2]. Although initial set of requirements called base requirements are well documented, requirement changes occur during software development process and these changes have greater impact on cost, quality and schedule of the project. The requirement changes such as addition, deletion and modification results in re-analysis, redesign, and re-implementation. Hence, due to requirements changing nature, quality of the product will suffer, cost will spiral out of control and schedule increases beyond estimation and this drives the project to be a L Manjunatha Rao Director Department of MCA Dayananda sagar Institutions Bangalore-78 [email protected] challenged task for enterprise. Changing nature of requirements is called volatility. Though enterprises are applying efforts to restrict the frequency of volatility, practically volatility it is growing out of control. Efforts of enterprises have resulted in contributing two facts about volatility. The first contribution is major four underplaying reasons which are causing volatility are brought to light. For the sake of clarity, these reasons are noted as R1, R2, R3 and R4 in this paper. The reasons and corresponding notations are given in table 1. TABLE 1: REASONS CAUSING VOLATILITY Table 1 infers that reasons R1 and R2 are related with human interaction. The reasons R3 and R4are influenced by market and organization polices and addressing the reasons R3 and R4 are out of scope for project technical team. Second contribution is that the reasons R1, R2, r3 and R4 are contributing towards volatility, by rendering volatility defects. By exploring the nature and origin of reasons from R1 to R4, two facts are evident. The first fact is that volatility can be controlled but cannot be eliminated. The second contribution is that the problem is not with requirements volatility but problem is with inadequate approaches in dealing with requirements volatility. In the current scenario, absence of efficient approach to control and manage volatility, is leading to the practical research. Since requirement volatility is a major challenge in all the domains of project development, a multiple case study spanning across five major application domains is undertaken in six CMMI level5certified companies. Since, the enterprises have found strong correlation between the volatility and its corresponding defects caused due to reasons R1 to R4, volatility can be addressed by addressing the defects caused by reasons R1 to R4. This paper presents the results of research undertaken, with respect to pre release and post release volatility defect(VD) density and severity. Based on the results of research, the reasons are prioritized and the 761 practical fact which is driving the reasons of volatility is found. domains. Projects considered are from medium, low and An effective solution to reduce the volatility is introduced by high complexities and different methodologies of employing affinity diagram and tree diagram in requirements development. Prioritization of volatility reasons based on elicitation and analysis phase. This paper is organized as defects severity is carried over. Secondly solution to reduce follows. Section I comprises of this introduction. Section II volatility is based on the practical study carried over in describes related work. Section III points out research industries. objective Section IV explains research design Section V III. RESEARCH OBJECTIVE explores key findings and analysis. Section VI contributes The following are the research objectives under taken in this Solution to requirements volatility. Section VII draws paper. discussions and Section VIII concludes. 1. What is the percentage of defects caused due to requirement volatility in pre release and post release II. RELATIVE WORK phase? Requirement volatility is inherent issue with requirements, 2. What is the percentage of defects and severity of defects caused due to major four reasons causing the volatility in extensive research work is carried out to find the reasons of pre release and post release phase? volatility, impact of volatility in terms of defects caused due to volatility based on four projects, requirements change 3. Prioritize the reasons causing the volatility based on defects analysis management frame work and measures taken handle volatility in industry. To the authors best knowledge and efforts any 4. Find the underplaying facts that are triggering the reasons of volatility. research undertaken to reduce the volatility, could not be 5. A solution to reduce the volatility. found. The summary of the survey is summarized below. Authors in [3] have undertaken study to investigate the impact IV. RESEARCH DESIGN of requirements instability on software defects. Study indicates the pre release and post release changes, have impact Due to the relative lack of literature on finding the measures on defects generated. Authors also states that insufficient time to reduce the effect of volatility, qualitative exploratory spent on the design phase and inadequate communication with research method is undertaken. Since case study approach is the client could be some of the causes of requirements appropriate for the undertaken research method, case study of changes and consequently software defects. Authors in [4] twenty customized software development projects developed report on the “Industrial case study on Requirement Volatility by six products cum service based hybrid type software measures”. Goal of the study was to empirically validate set of enterprises in India, is undertaken in this research. Projects measures associated with volatility of use case models (UCM). chosen for study have spread across major five potential Analysis results have indicated that measures of size of UCMs application domains of global software development. The are good indicators of requirements volatility. No correlations major domains considered are retail group, Finance, insurance were found between subjective and objective volatility. and banking group, manufacturing and automobile group, Authors in [5] have taken qualitative and quantitative study on Energy and utilities group and Hospital and Pharmacy coming requirements change management and have proposed a model under health care group. Projects chosen are of applications for requirements change management process. Authors in [6] software product type. Projects are chosen from different have taken an empirical investigation of volatility awareness, development methodologies such as web based, object volatility management approaches, an industrial based study. oriented, structured and component based. All the projects are Authors have identified thirteen different approaches in studied from its inception till implementation and also in the managing the projects under volatility. Here volatility annual Contract Maintenance (AMC). Table 2 gives the management is handled in project management perspective. summary of twenty projects studied. Authors in [7] investigated on alternative to requirements Inferences: From table 2 it is evident that twenty projects change. Author proposes that if requirements are firm against from major application domains namely Retail and Hospitality the changes in user needs, risk due to requirements will not sector four projects, banking and Finance sector four projects, increase. Authors in [8] have worked on highlighting the Energy and Utilities sector five projects, four projects from effects of requirement volatility on software engineering Manufacturing and Automobile sector and three projects from process by simulation method. Authors in[9][10] proposes that health care and pharmacy is studied from six companies. All project managers can assess the complex impact of volatility companies are having quality standards of CMM level 5 in development of projects. The paper discusses that cost, common and ISO standards ISO14001 and ISO9002. Table 2 schedule, and quality impacts as a result of requirements also infers that projects cost range were from 5 to 16 million volatility. The simulation result demonstrates that complex dollars and project contract type were belonging to fixed setoff factor relationships and effects related to requirements price project(FPP)or Staff Augmentation(SA) or Covolatility in software projects. Manage(CM) or Hybrid categories. Development The summary of related work indicates the lack of methodologies used are web based, component based, research approach to reduce the volatility. The research structured and object oriented. undertaken by authors of this paper is very unique in two ways. First the research is taken in five major application 762 TABLE 2: PROJECTS TAKEN FOR CASE STUDY Company Sector A One of the large software company B India’ s brand leader Retail& Hospitali ty NP:04 C&D India’s globally reputed industrial giants E &F Large software Companie s A&F Projects Scheduling lighting to turn on and off based on normal business hours and multi-level day lighting control by server and cell phone. Visual merchandizing and space planning in the shopping mall Automation of customer relation database Single RFID-EAS based tag for inventory visibility and loss prevention in retail Risk estimation in corporate finance and valuation Banking and Automatic analysis, measurement and identification of interest rate, currency Finance exchange and equity market in the share and stocks venture Gold mortgage, loan, automation and database maintenance NP:04 Smart grid based Margin and Collateral Management in corporate treasuries Automation of petroleum terminal operations Energy and Managing petrol storage and distribution- to petrol terminals- Nation wide Utilities Increase in Biomass energy system and its usage in rural economy through advance technical instruments usage and metering NP:05 Tax administration- Nation wide Automation of Citizen’s identification Manufac Modeling and simulation of petrol consumption in Cars turing Automotive mixture preparation and combustion control for spark-ignited and direct-injection gasoline engines automob PLC based software control for hot molding power precise in galvanization plant. ile Software for Radio frequency based automatic action control for material NP: 04 Transferring Robot Health Automatic blood management forecasting in minimally invasive and Care and conventional cardiothoracic surgery pharmac Automatic reactive symptoms gauging based on contrast administration in y patients with renal failure NP:03 Augmented Reality Image Guidance Navigation for Beating Heart Mitral Valve Contract FPP T&M Hybrid Hybrid CM Hybrid SA FPP Hybrid Hybrid Hybrid Hybrid CM FPP FPP Cost in M$ 5-10 FPP CM Object oriented WEB based 8-12 Structered, web based Component based 9-13 Component based Objevt oriented Web based 1016 Component based Objevt oriented Web based 8-14 Component based Objevt oriented Structured Hybrid SA Hybrid DM NP: Number of projects, DM: Development Methodology Table 4: DEFECT ANALYSIS OF DEFECTS CONTRIBUTING VOLATALITY Pre R.S VD :Pre Release Volatility Defects, Post R.S V.D: Post Release Volatility Defects, B; Blocker, M: Major, C: critical, T: trivial 763 V. KEY FINDINGS AND ANALYSIS Analysis of every case study is performed in three dimensions based on the objectives of research stated in this paper. The three dimensions are as follows. The first dimension the defect analysis of volatility in Pre-release phase and post release phase. Second dimension is to discover the contribution of reasons of volatility in defect perspective. Apart from this prioritization of reasons based on defect severity is carried over. Third dimension of study is to find the key factors supporting the reasons of volatility. Below is the summary of key findings and analysis. 1. PRE-RELAESE AND POST RELEASE VOLATILITY DEFECTS Requirements changes are distinguished into two types namely pre-release requirement changes and post release requirement changes Once the requirements gets specified as functional specifications and SLA( Service Level Agreement) and SOW ( Statement of Work) is signed off and requirements gets freeze in the company. Once the requirements gets freeze, project build starts from design. If changes are requested after the requirement freeze and when the project is under anyone of the development stages namely design, coding, testing or implementation, such changes are called pre-release volatility. In other words any requirement changes carried after SOW within UAT (user acceptance test), such changes are called as pre-release volatility. If any changes made in the project once the project is deployed or in the annual contract period, such changes are called Post release Volatility. Magnitude of prerelease and post release volatility is measurable through defects percentage. All the projects under study were examined to find the pre-release defects percentage and post release defect percentage in all the three low, medium and high complexity projects. To get the volatility defects, change request management, review, auditing, inspection report, customer feedback, test log sheets, project post mortem report were considered. The summary of the defects found are summarized in table 3. Table3: VOLATILITY DEFECT CLASSIFICATION. Domain Complexity Pre Release VD% Range Retail and hospitality High Medium Low High Medium Low High Medium Low High Medium Low High Medium Low 54-62 30-42 23-34 60-65 35-48 25-28 50-55 30-32 16-20 50-56 32-36 15-20 70-75 50-55 30-32 Banking and Finance Energy and utilities Manufacturing$ automobile Health care and pharmacy VD: Volatility Defects Post release VD% Range 10-12 8-9 3-5 12-14 10-12 8-10 13-16 10-12 8-9 11-13 8-10 5-6 10-18 8-11 2-3 Inferences: From table 3 it is evident that pre-release volatility defects are in the higher range compared to post release defects. As the complexity increases, defects percentage also enhances. The maximum Pre release volatility defects are in the percentages of 75%,, 65%, 34% and post release defect are in the percentages of 18%, 13% and 10% for high, medium and low complexity projects respectively. Lesson learnt from table 3 is, if measures are taken to reduce the pre-release volatility defects, post release defects can be controlled. Post release defects are the major drivers of poor quality, cost overrun and schedule slippage. Hence, post release defects must to be reduced to improve project success factor and to derive better business value. It is also observable from the table 3 that percentages of volatility defects are dependent on project complexity and application domain. B. DEFECTS CAUSED DUE TO REASONS CONTRIBUTING VOLATILITY Volatility defects are caused due to four major reasons and given in table 1. If the patterns of defects caused by each of the four reasons of volatility are found, then those causes can be prioritized and later measures can be applied accordingly to reduce the volatility. Hence, the defect percentage caused by the entire four major causes of volatility, for all the projects under study are found both in pre-release and post release period. Defects percentage was found in all the three complexities and under all the five application domains. For the ease of analysis the defects percentage caused by R1-R4 is converted to grading from 1 to 10, where grading 10 indicates highest percentage of defects and 1 indicates lowest percentage of defects. Severity of defects caused due to reasonsR1to R4 are also found is summarized in table 4. Inferences: Table 4 infers that major cause for volatility are the reasons R1 and R2, accounting Poor initial understanding of customer needs and system and Customer requested change respectively.R1 and R2 are the major cause of higher percentage of defects in the grade of 9. R1 and R2 are also causing the defects of blocker type. Blocker type defects are very fatal for the system performance and must to be eliminated. R3 and R4 are contributing very less towards the volatility. Lesson learnt from table 4 is that, R1 and R2 are the major players of requirements volatility in all the application domains. Hence, if measures are designed to control R1 and R2, requirement volatility can be effectively controlled. If R1 and R2 are controlled, impact of other reasons R3 and R4 will automatically get reduced. C. KEY FACTORS INFLUENCING THE REASONS WHICH ARE CONTRIBUTING VOLATILITY Following detailed analysis of reports, customer feedback, discussions with project development personnel, it is found that two major reasons are laying the foundation for reasons of volatility. They are 764 1. Gap exists between customer need and customer statement of need. This concept is given in figure 1.Customer realizes this gap iteratively, only after viewing the product. Hence customer keeps changing the requirements. 2. Elicitation technique does not have fixed frame work of activities. Elicitation techniques are left to the choice of elicitation team generally consisting of Subject matter expert (SME), Program manager, Practice manager, Quality analyst, and Business development manager (BDM).Due to the gap as depicted in figure 1 and lack of defined frame work for project requirement elicitation, poor requirements are elicited and requirements change has become the inherent part of project development expressed in figure3, one primary need is divided into secondary need and in turn they are divided into multiple tertiary needs. The levels of details can continue till atomic needs are obtained. These atomic needs if translated into requirements, volatility can be controlled. Figure 1.Gap between concept of need and statement of need by customer Fig: 2 Affinity diagram to tree diagram translation This paper contributes the results of research undertaken to find a solution to reduce the gap. Solution is explained in the next section. VI. SOLUTION TO REQUIREMENTS VOLATILITY From the analysis and key findings of case study, it is found that, volatility is common in all the project application domains. Among the four reasons R1 to R4, the major reasons are R1 and R2. Gap between real need of customer to statement of customer, and ad hoc elicitation techniques are the key drivers of R1 and R2. Research contributes that if affinity diagram followed by tree diagrams are used in both requirements elicitation and requirements analysis process, both the underplaying causes which are triggering R1 and R2 can be addressed and requirements volatility can be reduced to a greater extent. Implementation of affinity and tree diagrams is illustrated in figure 2. Consider figure 2. The customer statements are in natural language and it has to be translated into features and then into functional points. Affinity diagram is a good tool to translate the voice of customer to structured themes as shown in fig 2. Under each theme, needs are noted. The major gap exists in interpretation of each need, because need statements a can be atomic also or composition of several needs also. The needs are the statements of high level sometimes abstract level customer requirements. It has to be decomposed into multiple levels in a greater detail to define the real requirements of customer. The major reason for volatility is that the composite need is getting expressed as atomic need and once the project gets started, requirements change requests influxes and volatility surfaces the project build. To explore the depth of every need into multiple levels tree diagrams are used. As Consider an example a case study’ Scheduling lighting to turn on and off based on normal business hours and multi-level day lighting control by server and cell phone” project under Retail hospitality domain given in table 1.When the research team was undertaking case study , the project was suffering from pre-release volatility up to 60% in the first build.. Once the affinity diagram followed by tree diagram is used in the second build, pre-release volatility was drastically reduced to 20%. Considerable reduction in post release volatility was observed. Customer statements were categorized as themes by affinity diagrams and one of such theme was “Electric power must be saved” This theme was categorized into several needs. One of the needs considered for analysis is “Scheduled light control “Tree diagram is applied to this need. From the diagram it is very clear how the high level requirement is decomposed into multiple levels. Practically it involved several levels to get atomic requirements. Fig 3: Implementation of tree diagram 765 VII. DISCUSSIONS The following contributions can be drawn from the study • From the case study it is observed that though project requirement elicitation techniques includes the activities such as Affinity Diagram, Relations Diagram, Prioritization Matrix, Root Cause Tree Diagram, Involvement Matrix, PERT Chart, Risk Diagram (PDPC)) and Mind Map ,and usage of one or more techniques is left to the choice of elicitation team. No assurance that every project team utilizes the affinity diagram tool. Moreover, elicitation technique does not mention use of tree diagram after using affinity diagram. Hence using only affinity diagram in project elicitation does not result in the reduction of Volatility. The research contribution of using affinity diagram followed by tree diagram is unique and effectively reduces the gap. There by volatility also gets reduced. • If volatility gets reduced, requirements stability index also gets increased. If requirements stability increases by 1%, project cost gets reduced by 10% and quality significantly improves. Hence our approach of using affinity diagram followed by tree diagram assures project success. • Potential of the four reasons R1-R4which are causing the volatility is well traceable by defect analysis. From defect analysis it is observed that reasons R1 and R2 are the major players of volatility, because they are contributing high percentage of defects and defects are of blocker and critical type.R3 and R4 are minor players because they are contributing only very less percentage of defects and severity is trivial and major. • Volatility can be controlled by applying correction to R1 and R2.The reasons for selection of R1 and R2 alone is twofold. The first reason is R1 and R2 are major contributes of volatility defects. Second is R1 and R2 are interfaced with human interaction. Hence, measures can be designed to control, where as reasons R3 and R4 are not in project teams control domain because, they are pertaining to market conditions, business policies etc. If R1 and R2 are controlled, the process of translating high level customer needs to detailed requirements becomes strategic mandatory process in the enterprises and this leads to reduction of requirements volatility in the case requirements pertaining to policies and market conditions. Hence by controlling R1 and R2, a considerable reduction in R3 and R4 can be observed. VIII. CONCLUSIONS In the current scenario, enterprises are experiencing business pressure to deliver projects with high quality, less cost and with shorter delivery cycles. Enterprises are witnessing the projects are not able to meet the expected quality, cost and schedule due to requirement volatility. Through various ways, robust efforts are applied by enterprises to eliminate volatility, projects are continuing with the issue of growth rate of volatility. But the efforts resulted in two important contributions. The first is the principle contributors of volatility were found and categorized into four reasons. In this paper for the sake of clarity and ease of understanding the four reasons are denoted as R1, R2, R3 and R4.The second contribution is that the fact that due to dynamic nature of SDLC, volatility cannot be eliminated but can be controlled was made evident. Hence, industrial multiple case study research was undertaken to find measures to control volatility. As volatility is correlated with defects, defect analysis of R1, R2, R3 and R4, was carried over in pre release and post release phase. It is found that the reasons R1 and R2 are associated with human interactions. It is also observed that R1 and R2are contributing blocker type, heavy percentage of defects. Reasons R3 and R4 are associated with market risks and policies, hence controlling is out of scope of development team and it was also found that R3 and R4 defect contribution percentage is less and severity is majorly trivial type defects. Key factors driving R1 and R2 are found through the research undertaken. A solution of using affinity diagram followed by tree diagram in both of the requirement elicitation and analysis phase is introduced. A practical example by taking one of the retail domain projects under case study is given. Practical example assures that the usage affinity diagram followed by tree diagram is an effective measure to reduce volatility and by implementing it projects can meet its objectives and enterprises can derive expected business value. REFERENCES [1] [2] [3] [4] [5] [6] [7] [8] [9] [10] 1 Kenyer Domínguez, María Pérez, Anna C. Grimán, Maryoly Ortega, Luis E. Mendoza,” software quality model based on software development approaches” Published in 11 th International Conference on Software Engineering and Applications (SEA '07), Pages 16 ,ACTA Press Anaheim, CA, USA, 2007 M. Takahashi and Y. Kamayachi. “An empirical study of a model for program error prediction”. InProceedings of 8th International IEEE Conference on Software Engineering, pages 330–336. IEEE, Aug.1985 Talha Javed, Manzil-e-Maqsood and Qaiser S. Durrani “A Study to Investigate the Impact of Requirements Instabilityon Software Defects” published in Journal ACM Software Engineering Notes, May 2004 Volume 29Number 4. Loconsole, A.; Borstler, J.; , "An industrial case study on requirements volatility measures," Software Engineering Conference, 2005. APSEC '05. 12th Asia-Pacific , vol., no., pp. 8 pp., 15-17 Dec. 2005 Muhammad Akram Muhammad Akram, M. Hamid Fayaz, M. Imran Shafi, M. Usman Shafique,, “Qualitative AndQuantitative Study For Requirement Change Management Model”,www.iqraisb.edu.pk/icbte/Proceeding_ICBTE_2010/.../104.pdf Thakurta, R.; F. Ahlemann; “Understanding Requirements Volatility in Software Projects—An Empirical Investigation of Volatility Awareness,Manegment approaches and their applicability,43 Hawai international conference,(HICSS) USA,2010 Alan M. Davis et al,”Requirements Change: What’sthe Alternative?”, l IEEE International Computer Software and Applications Conference(COMPSAC’08),2008, ISSN: 0730-3157, July 28 2008Aug. 1 2008, pg 635 – 638 Susan Ferreira et al, “Understanding the effects of requirements volatility in software engineering by using analytical modeling and software process simulation”, Journal of Systems and Software , Volume 82 Issue 10, October, 2009 T. R. Gopalakrishnan Nair, V. Suma, “Four Step Approach Model of Inspection (FAMI) for Effective Defect Management in Software Development”, Inter JRI-Science and Technology journal, Interline publishers, Vol. 3, Issue 1, pp. 29-42, 2010 V. Suma, T.R. Gopalakrishnan Nair, “Better Defect Detection and Prevention Through Improved Inspection and Testing Approach in Small and Medium Scale Software Industry”, International Journal of Productivity and Quality Management (IJPQM), InderScience Publishers, USA, vol.6 , N1, pp. 71-90, 2010. 766
© Copyright 2026 Paperzz