ELENA Injection septum and extraction hardware status J. Borburgh, M. Hourican, A. Prost Injection septum 2015 up to now • SM12 re-measured magnetically (TE/MSC) • Cooling manifold installed (EN/CV) • Magnet support delivered (EN/MME) • Magnet installed (TE/ABT) • Hydraulic hoses ordered (TE/ABT) • Magnet pre-aligned (EN/MEF/SU) From now onwards (2016) • Electrical and hydraulic connections to be installed • Final alignment • Commissioning of system to be done 05/11/2015 Status of ELENA septa 2 Status Fast Deflector hardware Requirement: 9 units + spare feedthroughs • 2015 • 2 units for ring (Phase 1): 01/14 – 11/15 • • • • (presently being acceptance tested at TE/VSC) Tanks and electrodes NEG coated Electrical DC test done at ABT/SE; pulsed tests to be scheduled • 7 units for TLs (Phase 2): 01/15 – 11/16 • NEG coating to be confirmed. • All tanks being manufactured; delivery expected by Christmas 2015 • All under vacuum parts delivered • 2016 (foreseen) • • • • • • 05/11/2015 Base plates supports to be manufactured. Spare parts to be ordered. Vacuum preparation of phase 2 elements at TE/ABT. Vacuum acceptance at TE/VSC. Electrical testing to be done (DC and pulsed). Installation in ELENA. Status of ELENA septa 3 Resources Injection septum requested budget 30 kCHF (99264); • • Committed up to now 12 kCHF Expected for 2016 3 kCHF Total expected CtC 15 kCHF Fast Deflector requested budget 522 kCHF (99264); • Committed up to now: • 170 kCHF for material and services • 1 MY for TTE (~ 94 kCHF) • Expected for 2016 56 kCHF Total expected CtC 320 kCHF 05/11/2015 Status of ELENA septa 4
© Copyright 2026 Paperzz