Status_5November_2015

ELENA Injection septum and
extraction hardware status
J. Borburgh, M. Hourican, A. Prost
Injection septum
2015 up to now
• SM12 re-measured magnetically (TE/MSC)
• Cooling manifold installed (EN/CV)
• Magnet support delivered (EN/MME)
• Magnet installed (TE/ABT)
• Hydraulic hoses ordered (TE/ABT)
• Magnet pre-aligned (EN/MEF/SU)
From now onwards (2016)
• Electrical and hydraulic connections to be installed
• Final alignment
• Commissioning of system to be done
05/11/2015
Status of ELENA septa
2
Status Fast Deflector hardware
Requirement: 9 units + spare feedthroughs
• 2015
• 2 units for ring (Phase 1): 01/14 – 11/15
•
•
•
•
(presently being acceptance tested at TE/VSC)
Tanks and electrodes NEG coated
Electrical DC test done at ABT/SE;
pulsed tests to be scheduled
• 7 units for TLs (Phase 2): 01/15 – 11/16
• NEG coating to be confirmed.
• All tanks being manufactured; delivery expected by
Christmas 2015
• All under vacuum parts delivered
• 2016 (foreseen)
•
•
•
•
•
•
05/11/2015
Base plates supports to be manufactured.
Spare parts to be ordered.
Vacuum preparation of phase 2 elements at TE/ABT.
Vacuum acceptance at TE/VSC.
Electrical testing to be done (DC and pulsed).
Installation in ELENA.
Status of ELENA septa
3
Resources
Injection septum requested budget 30 kCHF (99264);
•
•
Committed up to now 12 kCHF
Expected for 2016 3 kCHF
Total expected CtC 15 kCHF
Fast Deflector requested budget 522 kCHF (99264);
• Committed up to now:
•
170 kCHF for material and services
•
1 MY for TTE (~ 94 kCHF)
• Expected for 2016 56 kCHF
Total expected CtC 320 kCHF
05/11/2015
Status of ELENA septa
4