Market impact analysis of HVDC MWh charge October 2014 Objective • Transpower has asked us to model the potential impacts on the New Zealand wholesale electricity market of changing the HVDC HAMI charge to a MWh charge • • HAMI charge = HVDC revenue requirement allocated to SI injection customers on the basis of their historical anytime maximum injection (HAMI). HAMI is the average of the 12 highest injection quantities at each location for the current and previous four years MWh charge = HVDC revenue requirement allocated to SI injection customers on the basis of annual energy injection. In this analysis, the average annual energy injection over the last 5 years is used. Analysis summary I • vSPD is used for the analysis to simulate the market dispatch and prices over the 12 month post pole 3 period of Aug 13 to July 14. • ~177MW of additional capacity was offered at Benmore, Roxburgh and Clyde power stations to reflect potential unoffered capacity that could be available in the market as a consequence of removing the current HAMI charge. • Considered impact on: – System costs = estimate of fuel costs under the assumption of cost-reflective offers (offer price x cleared offer quantity at each injection location*) – Load market costs = aggregate costs faced by loads in the spot market (nodal price x quantity at each offtake location*) – Generation revenue = aggregate revenue earned by generators in the spot market (nodal price x quantity at each injection location) – Spot market nodal prices *Offtake and injection quantities are based on the data in the final pricing case files. Analysis summary II • Two scenarios were considered in regard to the response of SI generators to a MWh charge: – Unchanged offer prices: Under this scenario it is assumed that no changes are made to SI generator offer prices. The extra capacity is offered at the highest tranche price. – Adjusted offer prices: In this scenario it is assumed that SI generators increase energy offer prices as a result of the MWh charge. • The analysis indicates a reduction in system costs of $17.4m and $16.8m over the 12 month period for the unchanged offer and adjusted offer scenarios respectively. • The additional capacity displaces higher cost generation which reduces system costs relative to the existing charging approach. This is valid in both scenarios. The adjusted offer price scenario does result in some higher cost generation being dispatched, due to the increased offer prices, however this is smaller than the reductions in system cost due to the additional generation. Hence, the difference in system costs between two scenarios is quite small. Analysis summary III • The analysis illustrates a reduction in peak spot prices >10% (and average spot prices) for both scenarios with an increase in off-peak spot prices in the adjusted offer price scenario. • With higher priced periods generally coinciding with higher demand periods, the net impact is a reduction of load costs in the spot market and also generator revenue. • The additional SI generation capacity and reduced peak prices signal a reduced demand for NI peaking generation. This would have flowon effects into the peak hedge market and peak generation investment. Analysis summary IV • • The calculated reduction in system costs ~$17.4m is larger than the $3.5m over 3 years (~$1.2m per annum) estimated reduction calculated by the EA in its recent work on HVDC problem definition. Potential reasons for the differences are: – Differences in the assumptions on offering the additional SI generation capacity (EA analysis assumes the additional capacity would be offered at the maximum of an estimate of the long-term water value ($80/MWh) and the maximum observed market offer price whereas we assumed the highest energy offer tranche price at the generator was a reasonable estimate of the generators’ willingness to sell given prevailing market conditions and portfolio effects). This is applicable when comparing to the baseline scenario (B1). – EA analysis covered both the pre and post pole 3 periods (Aug 11 to Jul 14) whereas our analysis is concentrated on the post pole 3 period (Aug 13 to Jul 14). We suspect that the majority of the benefits are in the post pole 3 period of the analysis. – Treatment of frequency keeping constraints – in the EA analysis it appears these constraints are removed whereas we retain these constraints (but adjust with the additional capacity) in our analysis. Removing constraints would tend to reduce system costs. – We use a slightly different threshold for adjustment of offers to detect the potential HAMI impact on unoffered generation (1% of HAMI vs the EA usage of fixed thresholds). Both studies are estimates which are based on assumptions of market behaviour neither of which would be exact. We have undertaken a sensitivity using the same offer price adjustment assumption as the EA analysis. This indicates a reduced system cost impact of $4.2m. This is larger than the EA calculated value, but given the other differences described above, not dissimilar. Analysis summary V • • • • • We have undertaken sensitivity analysis to illustrate a potential range for the system cost impact. An upper bound sensitivity where the additional capacity is offered at the lowest price, indicates a potential reduction in system costs of $55.6m and $55.1m over the 12 month study horizon for the unchanged offer and adjusted offer scenarios respectively. These sensitivities result in excessive SI hydro generation (an infeasible hydro storage trajectory), hence are only a loose upper bound. A sensitivity with an $80/MWh de-minimus price on the additional SI generation capacity indicates a reduction in system costs of $4.2m and $3.6m over the 12 month study horizon for the unchanged offer and adjusted offer scenarios respectively. There are periods where the $80/MWh applied threshold is larger than the offer price of the remaining generation at the station (e.g. Benmore in mid Feb 2014 where all capacity was offered at < $1/MWh). This sensitivity results in the lowest additional energy from SI generators and provides a lower range on the reduction in system costs. All scenarios and sensitivities indicate reduced system costs by releasing additional SI generation capacity. Even where SI generators adjust offer prices in response to a MWh charge there is still be an overall saving in system costs. We note this is based on assumed offer scenarios and against the prevailing market and hydrological conditions observed between Aug 13 to July 14. Approach • We simulated the potential market outcomes (MW and prices) given: – Removal of the current HVDC HAMI charge – Introduction of a MWh charge • The analysis utilised vSPD simulating dispatch and prices post pole 3 (01 August 13 to 31 July 14)* • Recognise that estimating the impact is uncertain given the uncertainty in participant’s response • Analysed scenarios to estimate the potential magnitude of the impact with variants on some key assumptions *vSPD does not have a representation of hydro storage post-process calculations were undertaken to estimate the impact of the changes in generation on hydro storage. ESTIMATING UNOFFERED GENERATION CAPACITY Estimating unoffered generation capacity • Current HVDC HAMI deters additional SI generation capacity above the existing HAMI level • We used the current HAMI level and market offers from Aug 13 to July 14 to estimate the potential “unoffered” generation as a result of HAMI only • If offered generation was within 1% of HAMI level then assume HAMI charge is restricting the offered energy. In these instances energy offers were increased to the full offered capacity of the generating station* • Otherwise we leave offered energy unchanged *Over period 03 Dec 13 to 10 Feb 14 the offered capacity at Benmore was ~ HAMI level but no corresponding Benmore generator outages were observed in POCP. In these instances it was assumed that the HAMI was restricting the offered capacity and the Benmore offered capacity was increased from ~474MW to 534MW. Offer behaviour at Clyde Planned outage Implied HAMI limit Offer behaviour at Roxburgh Implied HAMI limit Offer behaviour at Benmore Additional capacity offered but high price for quantities below HAMI as well could not attribute these high priced offers to HAMI Implied HAMI limit Unoffered generation capacity assumed due to current HAMI • It is estimated that the three most affected gridconnected generators identified (Benmore, Clyde and Roxburgh) have a combined capability of ~177MW that is currently not being offered • It is estimated that the impact on other SI gridconnected generators is smaller with a potential ~10MW of further grid-connected generation not being offered due to the current HAMI charge.* *Manapouri installed capacity = 850MW. Although offers from Manapouri are at HAMI (795MW) the additional potential capacity from Manapouri is restricted to 800MW (due to resource consents) MWH CHARGE CALCULATION Estimating the MWh charge • HVDC MWh charge was calculated using: – HVDC revenue requirement for 2014/15 pricing year ($145m) – Annual average output of SI generators over the last 5 years+ (17,224GWh) – HVDC MWh charge = $145m/17,224GWh = $8.4/MWh +Average over 5 years was chosen to reduce inter-year variability which could occur as a result of wet and dry years *Total SI generation is used which includes some embedded generation this would tend to overestimate the energy injection and underestimate the MWh charge an upper bound for this underestimation is $0.5/MWh ESTIMATING THE MARKET IMPACT Potential market response • • • • • Analysed two scenarios to understand the potential market impact In both scenarios it is assumed that an additional ~177MW of SI generation capacity is offered at Benmore, Roxburgh and Clyde. This additional capacity is offered during times when the observed offered capacity was within 1% of the current HAMI limit. SI generators were assumed to follow the same offer strategy with the additional capacity priced at the maximum offer price of that generator. Baseline scenario 1 (Unchanged offer price): It is assumed that SI generators already facing the HVDC charge have adjusted offer prices in response to the existing charge and no further adjustments to offer prices are observed when moving to a MWh charge. Baseline scenario 2 (Adjusted offer price): It is assumed that SI generators respond to the HVDC MWh charge by increasing offer prices to reflect the increased variable cost of SI grid-connected generation through the MWh charge. In addition to these scenarios, two sensitivities were undertaken: – Sensitivity a: Assuming the additional generation capacity is offered as the lowest offer price tranch. This is an attempt to obtain a potential upper bound of the effect. – Sensitivity b: Assuming the additional generation is offered at the maximum of $80/MWh (LRMC of new generation) or the highest priced offer tranch. This is similar to the assumptions used in the EA’s analysis. RESULTS Price impact – Benmore (SI) 500 highest price periods Peak prices reduce in both scenarios Increase in minimum price with MWh uplift 500 lowest price periods • • Additional SI capacity reduces BEN peak spot market prices (in both scenarios) If HVDC MWh charge added to SI offer prices then SI minimum price increases overall still see a reduction in average prices Price impact – Otahuhu (NI) 500 highest price periods Peak prices reduce in both scenarios Increase in minimum price with MWh uplift 500 lowest price periods • • Additional SI capacity reduces OTA peak spot market prices (in both scenarios) If HVDC MWh charge added to SI offer prices then OTA minimum price increases overall still see a reduction in average prices Load during high and low priced periods Benmore Otahuhu Average 3234MW Average 4972MW Average 3676MW Average 4890MW • Expected demand during highest price periods > expected demand during lowest price periods Impact on high spot prices Benmore Otahuhu 12.3% 11% 10.5% 12.6% • Additional SI generation capacity reduces high spot prices • This could have flow-on effects into peak hedge prices Impact on low spot prices Benmore Otahuhu • During lower spot price periods there is an increase in price if SI generators increase energy offer prices in response to the HVDC MWh charge • Can increase costs to loads during periods where prices would otherwise have been lower than the MWh charge (low load and high storage (spill) periods) Impact on average spot prices Otahuhu Benmore 10% 6.7% 2.8% 2.8% • If offer prices are increased, there are periods of lower spot prices (due to additional capacity) and periods of increased spot prices (due to MWh uplift charge) relative to the base case. The net impact is still a reduction (but not by as much as peak prices) Price impact summary • Peak price impact: – In both scenarios, a reduction in peak (99th percentile) spot prices in both islands is observed. – The increased HVDC capacity (post pole 3) does not restrict the additional SI generation capacity and hence both islands experience a reduction in peak prices – This reduction in peak spot prices signals reduced demand for peaking generation with flow-on effects into peaking generation investment and peak hedge prices • Off-peak price impact: – If SI generators increase their energy offer prices in response to the HVDC MWh charge, we observe an increase in lower spot prices as the HVDC MWh charge acts as a floor on SI spot prices. – This also affects NI spot prices during times when the low priced SI generators were setting the NI price. – This can increase the costs to loads during lower priced periods Price impact summary • Net price impact: – We observed a greater reduction in high spot prices than increase in low spot prices and therefore observe an overall net reduction in spot prices • Net market impact: – The reduction in higher spot prices is more likely to occur during high demand periods and the increase in lower spot prices more likely to occur during lower demand periods. – Hence in terms of overall market impact, we observe an overall reduction in load market costs and also a reduction in generation revenue in both scenarios. Impact on generation spot market revenue and load spot market costs If offer prices are not If offer prices are changed adjusted • • • Generator revenue ($m) -217 -81.2 Load market costs ($m) -213.7 -81.8 Net change ($m) (Loss and constraint excess) 3.3 -0.6 The difference between load market costs and generation revenue is the loss and constraint excess (LCE). An increase in the LCE implies a greater difference between load and generation nodal prices which could be due to transmission constraints and/or losses. In the unchanged offer price scenario, the increased SI generation and predominantly northward HVDC flow results in larger transmission losses and larger nodal price differences between loads and generators, relative to the base case. In the adjusted offer price scenario, there are periods of reduced LCE (lower HVDC flow and smaller price differences) and periods of increased LCE (larger HVDC flow and larger price differences) relative to the base case. The net impact over the 12 month study periods was a slight reduction in the LCE, relative to the base case. Impact on system costs If offer prices are not If offer prices are changed adjusted System cost impact ($m) -17.4 -16.8 • Assuming the observed market offers are cost reflective, the change in cleared generation priced at the current market offer provides an estimate of the impact on system costs. • In both scenarios, an overall reduction in system costs is observed as the additional capacity reduces the dispatch of more expensive generation during high-priced periods. In the case of the adjusted offer price scenario (where SI generator offer prices were increased), this reduction in costs exceeds the increased system cost due to using higher priced generators during off-peak periods. • The adjusted offer prices scenario has a lower reduction due to more expensive generation being used in the NI as a result of the uplift added on SI generators in this scenario. High priced period analysis – 29 Jan 14 (trading period 28) • • Scenario OTA2201 ($/MWh) BEN2201 ($/MWh) Actual 1,864 1,512 Unchanged offer price 1,042 845 Adjusted offer price 1,042 845 In trading period 28 on 29 Jan 2014, actual spot price in NI and SI exceeded $1,500/MWh Estimated unoffered capacity: – – – • • Benmore = 60MW Roxburgh = 0MW Clyde = 0MW Roxburgh and Clyde energy offers were > than 1% away from the HAMI level HAMI is not restricting the energy offer Benmore offered energy was within 1% of HAMI unoffered capacity = offered capacity-offered energy (534MW – 474MW = 60MW) 29 Jan 14 – energy offers Offered energy within 1% of HAMI additional energy offered = offered capacity – offered energy (60MW) at highest-priced offer tranche ($0.03/MWh) Offered energy greater that 1% away from HAMI HAMI is not restricting the energy offer leave unchanged 29 Jan 14 (trading period 28) – adjusted offers and island scheduled generation Benmore With MWh charge 45MW 60MW 40MW • Additional 60MW offered in SI @ $0.03/MWh 45MW of this additional offered SI capacity was scheduled displaced 40MW of more expensive NI generation reduces system costs and spot prices Low-priced period analysis – 05 Jan 14 (trading period 7) • • Scenario OTA2201 ($/MWh) BEN2201 ($/MWh) Actual 0.01 0.01 Unchanged offer price 0.01 0.01 Adjusted offer price 8.73 8.66 In trading period 7 on 05 Jan 2014, actual spot price in NI and SI was $0.01/MWh Estimated unoffered capacity: – Benmore = 60MW @ $975/MWh – Roxburgh = 45MW (32MW @ $50/MWh and 13MW @ $33/MWh) – Clyde = 69MW @ $60/MWh • • Additional capacity offered at prices > clearing price additional capacity not scheduled In adjusted offer price scenario adjusted offer prices sets floor price in the SI price in NI is greater due to transmission losses 05 Jan 14 – energy offers Offered capacity at BEN = HAMI level but no POCP outages and storage >> mean increased energy offers to capacity (534MW – 474MW = 60MW) Offered energy within 1% of HAMI additional energy offered = offered capacity – offered energy (69MW at CYD and 45MW at ROX) at highest-priced offer tranches at each station respectively 05 Jan 14 (trading period7) – adjusted offers Benmore Clyde 69MW 60MW With MWh charge With MWh charge Roxburgh 110kV 32MW Roxburgh 220kV 13MW 05 Jan 14 (trading period 7) – island scheduled generation 40MW 44MW • • Additional MW offered in SI is not scheduled since offer price > market clearing price Increase of SI energy offer prices (adjusted offer price) results in reduction in cheaper SI generation (43MW) and increase in more expensive NI generation (40MW) net increase in system costs and system price Generation impact summary Change relative to actual Reduction in aggregate SI generation in adjusted offer price scenario – displaced by lower-priced NI generators • • • The additional generation capacity in the SI displaces NI generation includes NI thermal and NI hydro If SI generators adjust offer prices to include an uplift to cover the HVDC MWh charge, then we observe a smaller change in SI generation A reduction in NI thermal generation is observed in both scenarios further illustrates that NI thermal peaking usage is being eroded with the additional SI generation during high prices SI generator uplift of energy prices is less of an issue Island generation impact results • Additional SI generation capacity can displace NI generation however this would be dependent on the adjustment of SI generator offer prices in response to the HVDC MWh charge • The percentage change in energy output (relative to actual energy) is shown below energy impact of less than 1% NI SI Unchanged offer prices Adjusted offer prices -0.74% 0.95% -0.04% 0.08% SI generation impact • Largest increases are seen on the Waitaki (Benmore) and Clutha (Roxburgh and Clyde) additional generation capacity NI generation impact • • • Reduction in NI thermal generation in both scenarios even with a MWh charge uplift on SI generator offer prices Waikato (WTO) hydro generation increases under scenarios with increased SI hydro offer prices Total SI generation increase > total NI generation reduction due to increased transmission losses with larger proportion of SI generation HVDC impact results Corresponds to a 4.4% increase in HVDC northward flow over the year • • Additional SI generation increases South-to-North (Northward) energy transfer on the HVDC link under both scenarios, relative to the base case. Under the adjusted offer scenario the reduced South-to-North and increased North-to-South HVDC transfer, relative to the unchanged offer price scenario is a result of higher-priced SI generation (with the MWh charge) being displaced by some lower-priced NI generation. APPENDIX Sensitivity analysis • To understand the potential impact range, we considered variations in the adjustment of energy offers. • These adjustments were: – Low price quantity: Under this sensitivity it was assumed that the additional generation was offered at the lowest observed offer price. The intention of this sensitivity was to understand a potential upper bound on the impact. – Threshold price quantity: Under this sensitivity it was assumed that the additional generation was offered at the greater of $80/MWh* and the highest offer price at the generator. *$80/MWh is an estimate the long-run marginal cost of generation Sensitivities • Baseline scenario 1 (B1: Unchanged offer price): – B1a: Low price quantity – B1b: Threshold price quantity • Baseline scenario 2 (B2: Adjusted offer price): – B2a: Low price quantity – B2b: Threshold price quantity Impact on generation spot market revenue, load spot market costs and system costs Assessed but Infeasible hydro storage CLU hydro storage feasibility Low price quantity (a) sensitivities result in excessive Clutha hydro usage infeasible hydro storage trajectory (inc. Hawea, Wakatipu, Wanaka) WTK hydro storage feasibility • WTK storage within feasible range for all the scenarios (Tekapo, Pukaki, Ohau) Sensitivity summary Low price quantity (a) sensitivities result in excessive Clutha hydro usage infeasible hydro storage trajectory • • • The low price quantity resulted in excessive utilisation of the SI hydro resources resulting in an infeasible hydro storage trajectory the results from these sensitivities, while potentially providing an upper bound, is of limited use given its hydrological infeasibility. The sensitivity with the $80/MWh de-minimus price on the additional SI generation capacity is on the lower range of estimated impacts on system cost and market costs. Under this sensitivity there are periods where the $80/MWh threshold is larger than the offer price of the remaining generation (e.g. Benmore in mid February 2014 where all capacity was being offered at below $1/MWh). This sensitivity results in lowest additional energy and at the lower range of the estimated impact. Reduction in system dispatch costs is observed in all of the sensitivity scenarios even with an adjustment of offer prices in response to the MWh charge. Under this base line scenario the estimated reductions in system costs are with a lower range of -$3.6m, upper range range of $17.3m* and a mid-range of -$16.8m. (* system costs reductions could be higher however we have not been able to robustly estimate an upper bound at this point. The upper bound is likely to be between B1 ($17.3m) and B1a ($55.1m), which resulted in an infeasible hydro trajectory) Results summary – system costs Scenario B1 B1a B1b B2 B2a B2b Metric Reduction Increase Net effect System costs ($m) -17.4 0.0 -17.4 Half hours impacted (%) 57% 0% System costs ($m) -55.6 0.0 Half hours impacted (%) 100% 0% System costs ($m) -4.2 0.0 Half hours impacted (%) 26% 0% System costs ($m) -17.1 0.3 Half hours impacted (%) 59% 41% System costs ($m) -55.1 0.0 Half hours impacted (%) 95% 5% System costs ($m) -4.1 0.5 Half hours impacted (%) 32% 67% -55.6 -4.2 -16.8 -55.1 -3.6 Results summary – load market costs Scenario B1 B1a B1b B2 B2a B2b Metric Reduction Increase Net effect Load market costs ($m) -213.8 0.1 -213.7 Half hours impacted (%) 52.0% 0.6% Load market costs ($m) -626.5 0.3 Half hours impacted (%) 92.3% 0.7% Load market costs ($m) -139.0 0.1 Half hours impacted (%) 24.6% 0.2% Load market costs ($m) -164.9 83.1 Half hours impacted (%) 34.9% 53.3% Load market costs ($m) -511.7 18.2 Half hours impacted (%) 80.4% 12.8% Load market costs ($m) -110.1 104.0 Half hours impacted (%) 16.7% 66.8% -626.2 -138.9 -81.8 -493.5 -6.0
© Copyright 2026 Paperzz