BIT Past Assignments Northern College Programme Business Information Technology Assessment exercises and suggested answers Year 1999/2000 by Nigel R Hartland Assignment 1 Newcompany Ltd have been making widgets for many years. A new machine has become available that will make widgets in a shorter space of time, using less raw materials. 1. Assuming the cost of the machine is £50,000 and the machine will produce the following savings every year, calculate the Net Present Value and the Internal Rate of Return of this investment. Ignore inflation. Use a discount rate of 5%. Use 2 decimal places for the IRR calculation Year Net Savings £ 1 15,000 2 12,000 3 11,000 4 9,000 5 6,000 6 5,000 7 2,000 2. If the companies IRR is 6% is the investment worth the risk ? 3. Comment on the usefulness of these methods for appraising projects. 4. What other factors could come in to project appraisal as well as the financial benefits to be considered ? Saved: July 29, 2017 Page 1 BIT Past Assignments (20% course mark weighting) Suggested answer- (other answers may be suitable) 1. Using the given values: Year Discount Factor Net Savings £ Projected Savings £ 0 1 -50,000 -50000 1 0.952 15000 14280 2 0.907 12000 10884 3 0.864 11000 9504 4 0.823 9000 7407 5 0.784 6000 4704 6 0.746 5000 3730 7 0.711 2000 1422 4 marks NPV £1,931.00 2 marks IRR 6.39% 2 marks 2. As the calculated IRR of 6.39% is greater than the companies IRR of 6% you would invest, as the company will get better returns than investing the capital elsewhere. 2 marks 3. Very useful for what if analysis- you can play with the figures without spending any money, try out different scenarios etc. 4 marks 4. Who decides the IRR or the discount rate? Saved: July 29, 2017 Page 2 BIT Past Assignments Company culture - are they innovative or not? Innovative companies may be prone to risk taking and accept delays in getting good returns. The type of technology used can have a bearing as well, IT projects tend to have short time spans as technology is soon outdated. These therefore may have shorter payback periods. 5 marks 1 mark for presentation Saved: July 29, 2017 Page 3 BIT Past Assignments Northern College Programme Business Information Technology Assessment exercises and suggested answers Year 1999/2000 by Nigel R Hartland Assignment 2 1. The following project has been given to you. Draw (freehand) a network (arrow) diagram showing the various stages of the project. Determine the critical path and determine how many days it takes to complete the project. Activity Duration Days Preceding activity A 2 - B 3 - C 2 A,B D 3 C E 2 C F 2 E G 4 D H 2 F I 2 G J 6 H,I Consider the following questions: 2. If each day of the project costs £250 what is the overall cost of the project ? 3. What would happen to the projects' duration if the activity D was increased by two days? 4. Could activity F be increased by two days such that it did not affect the overall project duration ? 5. What is the maximum amount activity F could be increased by such that it does not increase the overall project duration ? Saved: July 29, 2017 Page 4 BIT Past Assignments 6. Input the data to produce the equivalent diagram (as of part 1) in MS Project 98 and print it out. (20% course mark weighting) Suggested answer: 1. Diagram should look similar to the following: where are Earliest Event Times and Latest Event Times 1. Path B,C,D,G,I,J 20 DAYS 2. £5000 3. D is on the critical path therefore any increase in its duration increases the overall duration. Therefore, it will Increase the overall duration by two days, overall cost raised to £5500. 4. Yes, there is spare capacity on this route to increase the duration of F. 5. 3 days, note the creation of a duplicate critical path B,C,E,F,H,J. Any further increase on F will increase the overall duration of the project. 6. See next page: Saved: July 29, 2017 Page 5 BIT Past Assignments . The following diagram shows how the chart will look (note the expected answer is usually presented in landscape view rather than portrait which is used here for simplicity): Saved: July 29, 2017 Page 6 BIT Past Assignments Northern College Programme Business Information Technology Assessment exercises Year 2000/2001 by Nigel R Hartland Assignment 1 A company has been considering whether to invest in new machinery which will make their production processes more efficient. You have been asked to answer the following questions: 1. Assuming the cost of the machine is £30,000 and the machine will produce the following savings every year, calculate the Net Present Value and the Internal Rate of Return of this investment. Ignore inflation. Use a discount rate of 10% and the discount factor figures from the notes for these calculations. For the Projected Savings and NPV calculations use 0 decimal places. For the IRR calculation use 2 decimal places. Year Net Savings £ 1 12,000 2 10,000 3 8,000 4 6,000 5 4,000 6 3,000 7 1,500 2. If the companies IRR is 12% is the investment worth the risk? Saved: July 29, 2017 Page 7 BIT Past Assignments 3. Describe (briefly) the advantages and disadvantages of project appraisal methods such as these? 4. What other financial factors should be considered in project appraisals? (20% course mark weighting) Suggested answers: 1. Calculations should look like the following: Year Discount Factor Net Savings £ Projected Savings £ 0 1 -30,000 -30,000 1 0.909 12,000 10908 2 0.826 10,000 8260 3 0.751 8,000 6008 4 0.683 6,000 4098 5 0.621 4,000 2484 6 0.564 3,000 1692 7 0.513 1,500 770 Calculated NPV = £4,220 Calculated IRR = 15.82% 2. As calculated IRR is greater than the companies IRR, you would invest, as you are getting better returns than investing the capital elsewhere. 3. Advantages: (i) Can try multiple scenarios to see if it is worth investing the money before actually committing any finance to the project - what if analysis. (ii) Can extend analysis to include other factors such as a change in Discount Factor, Inflation etc. Disadvantages: (i) If inflation is not included figures are unrealistic? (ii) uncertainty in Net Savings figures, who decides them, who decides the Discount Factor etc. Other non financial indicators can often have a bearing on the viability of a project- availability of manpower, equipment etc. Saved: July 29, 2017 Page 8 BIT Past Assignments 4. Inflation, tax incentives (Written Down Allowance is one used against capital expenditure) payment of Corporation Tax etc. Saved: July 29, 2017 Page 9 BIT Past Assignments Northern College Programme Business Information Technology Assessment exercises Year 2000/2001 by Nigel R Hartland Assignment 2 1. The following project has been given to you. Draw (freehand) a network (arrow) diagram showing the various stages of the project. Determine the critical path and determine how many days it takes to complete the project. Activity Duration (Days) Preceding activity A 1 - B 2 A C 3 A D 4 A E 2 B,C,D F 3 E G 4 F H 2 E I 3 H J 5 G,I K 2 J Consider the following questions: 2. If each day of the project costs £1000 what is the overall cost of the project ? 3. What would happen to the projects' duration if the activity J was increased by three days? 4. Could activity F be increased by two days such that it did not affect the overall project duration ? 5. What is the maximum amount activity H could be increased by such that it does not increase the overall project duration ? Saved: July 29, 2017 Page 10 BIT Past Assignments 6. Input the data to produce the equivalent diagram (as of part 1) in MS Project 98 and print it out. Include the separate page that shows the legend. (20% course mark weighting) Suggested answers: The diagram should look similar to the one below: where are Earliest Event Times and Latest Event Times 1. Path A, D, E, F, G, Dummy 3, J, K and 21 days 2. Cost = 21 * £1000 = £21,000 3. J is on the critical path, any increase in its duration will increase the overall duration of the project, in this case to 24 days. 4. No, again it is on the critical path and any increase in its duration will increase the overall duration of the project, in this case to 23 days. 5. By 2 days, creating an additional critical path, A,D,E,H,I,J,K. Any further increase will increase the overall project duration. Saved: July 29, 2017 Page 11 BIT Past Assignments 6. The data should look similar to the following, note the diagram is portrait for simplicity, the expected answer is normally produced in landscape: Saved: July 29, 2017 Page 12 BIT Past Assignments Northern College Programme Business Information Technology Assessment exercises Year 2001/2002 by Nigel R Hartland Assignment 1 A company has been considering whether to invest in new machinery which will make their production processes more efficient. You have been asked to answer the following questions: 1. Assuming the cost of the machine is £35,000 and the machine will produce the following savings every year, calculate the Net Present Value and the Internal Rate of Return of this investment. Ignore inflation. Use a discount rate of 15% and the discount factor figures from the notes for these calculations. For the Projected Savings and NPV calculations use 0 decimal places. For the IRR calculation use 2 decimal places. Year Net Savings £ 1 16,000 2 12,000 3 9,000 4 7,000 5 5,000 6 4,000 7 1,000 2. If the companies IRR is 16% is the investment worth the risk? 3. What is the danger in using such methods of appraisal ? Saved: July 29, 2017 Page 13 BIT Past Assignments 4. What affect (positive or negative) would the following have on the viability of the project? i. Corporation Tax ii Inflation iii A higher initial capital outlay (20% course mark weighting) Suggested answers: 1. Calculations should look like the following: Year Discount Factor Net Savings £ Projected Savings £ 0 1 -35,000 -35,000 1 0.870 16,000 13,920 2 0.756 12,000 9,072 3 0.658 9,000 5,922 4 0.572 7,000 4,004 5 0.497 5,000 2,485 6 0.432 4,000 1,728 7 0.376 1,000 376 Calculated NPV = £2,507 Calculated IRR = 18.35% 2. As calculated IRR is greater than the companies IRR, you would invest, as you are getting better returns than investing the capital elsewhere. 3. A danger with using such methods is that it doesn't take into account other factors that can affect a project such as financial ones (including inflation) and non financial for example, legal, availability of resources such as manpower, machinery, time etc. Project appraisal methods such as these are only used as a guide to deciding to pursue a project or not. Saved: July 29, 2017 Page 14 BIT Past Assignments 4. Corporation Tax This would tend to reduce the viability of a project as the tax reduces the savings of the project and hence the NPV and IRR. Inflation This would tend to reduce the viability of a project as the inflation reduces the savings of the project and hence the NPV and IRR. Higher initial capital outlay. This would tend to reduce the viability of a project as the outlay will reduce the NPV and IRR. Saved: July 29, 2017 Page 15 BIT Past Assignments Northern College Programme Business Information Technology Assessment exercises Year 2001/2002 by Nigel R Hartland Assignment 2 1. The following project has been given to you. Draw (freehand) a network (arrow) diagram showing the various stages of the project. Determine the critical path and determine how many days it takes to complete the project. Activity Duration (Days) Preceding activity A 2 - B 2 A C 3 B D 1 C E 2 C F 3 D,E G 3 F H 1 F I 2 G,H J 3 I Consider the following questions: 2. If each day of the project costs £3000 what is the overall cost of the project ? 3. What would happen to the projects' duration if the activity D was increased by One day? 4. Could activity E be increased by two days such that it did not affect the overall project duration ? 5. What is the maximum amount activity H could be increased by such that it does not increase the overall project duration ? Saved: July 29, 2017 Page 16 BIT Past Assignments 6. Input the data to produce the equivalent diagram (as of part 1) in MS Project 98 and print it out. Include the separate page that shows the legend. (20% course mark weighting) Suggested answers: The diagram should look similar to the one below: where are Earliest Event Times and Latest Event Times Note in this answer the alternative EET’s and LET’s have not been shown. 1. Path A,B,C,E,F,G,I,J and 20 days (nb dummy often omitted) 2. Cost = 20 * £3000 = £60,000 Saved: July 29, 2017 Page 17 BIT Past Assignments 3. D is not on the critical path, an increase in its duration of one day will not increase the overall duration of the project, but create an additional critical path of A,B,C,D,F,G,I,J. The duration remains 20 days. (nb dummies often omitted) 4. No, it is on the critical path and any increase in its duration will increase the overall duration of the project, in this case to 22 days. 5. By 2 days, creating an additional critical path, A,B,C,,E,F,H,I,J. Any further increase will increase the overall project duration. 6. The data should look similar to the following, note the diagram is portrait for simplicity, the expected answer is normally produced in landscape: Please note when drawing network diagrams if dummies are found to be part of the critical path they are often omitted from the answer given (given that they don’t exist). Students will not be marked down if they include them in their answers. It is however, good practice to include the activities table to show which activities are critical or not, assignments from 2004 have asked for this to be included where possible. Saved: July 29, 2017 Page 18
© Copyright 2026 Paperzz