MICE Collaboration meeting at Berkeley 9 – 12 February 2005 AFC Module progress Presented by Wing Lau --with input from AFC group members Status of Progress Action Who Progress made status Implement central repository for drawings -- need detector information to add to official drawing WL Done. Instrumentation for absorbers must be specified and incorporated into design (temperature sensors, liquid level sensors, …) SI Basically complete. On-going liasing with Mississippi on CKOV1 drawings; with Tortora on Calorimeter etc Diffuser still to be added Hyperlink to drawing gallery is now available Proposal now available (see Shigeru’s summary talk) and will be discussed among the AFC group as an on going action for Absorber R&D Define absorber heater implementation YI / SI Continue working to define worst-case magnet forces and collect magnet design notes into design report MG/ YI/ SY Check if a 1600mm gap between AFC & Tracker matching coils WL/ UB Revise absorber vent pipe size to make it adequate for He case WL Get RAL seismic design criteria and verify that designs meet them WL/ PD Done Done Ditto Yury and the team at RAL has now completed that work. Stephanie completed the FEA on forces and displacements. We are now homing in on the rail and anchoring design details Ullisee has completed the calculations and advised that either gap distance (800mm or 1600mm) is acceptable as far as forces and current density are concerned. However, the group has a preference to the 800mm gap. Agreed to increase this to 15mm diameter. Drawing being updated Done This is not considered significant as RAL site has relatively low floor response. A static “G” of 0.3 would be sufficient for all components with a natural frequency of above 33Hz. Comp lete. Done Done Who Progress made status Evaluate stresses at module interconnect flanges and bolts SV Ongoing Define RFCC module tie-in to rail system SV Work out gusset arrangement to transfer CC forces to RFCC module vacuum shell. SV Steve Verostek had done detail FEA on bolt / flange connection and the work is still ongoing This is now in he hands on the RAL design team Await Mike Green to finalise the Cold Mass support arrangement before deciding on how and where to put these gussets Evaluate the need for redundant LH2 relief paths EB / TB This is part of the on-going R&D activity on the Hydrogen System R&D. Ongoing Evaluate merits of cryocooler heater vs. 3-stage cooler w/o heater Evaluate absorber heat load with more realistic assessment of surrounding temperatures (is proposed MLI adequate?) Finalize interface between radiation shield and detector module - must forces be transmitted Consider participation in KEK and/or Fermilab absorber tests (some coordination maybe called for) MG Concluded that this is no longer an option for our current design Done EB/ MG/ SY Thermal model set up. Elwyn and his team are making progress on this Ongoing WL Stephanie has done the calc. Forces and displacement s at modules are acceptable for the 7 cases being considered. Done YI / SI MICE Absorber R&D will be carried out at KEK for the 1st absorber. We are still in discussion with Shigeru on whether the thermal test of the 2nd & 3rd absorbers should be done at KEK or RAL. Work is by and large complete. It shows that the 3 focus coils should be powered in series. The 2 Coupling Coils could be powered up either in series or separately. Ongoing Done Done Action Evaluate magnet interaction during quench -- does one quench induce others EB / MG Raise Change note on the radiation shield design SY / WL Ongoing Ongoing Done Action Who Progress made status Window QC – round robin exercise WL Work is on-going. Ongoing Understand QC requirements for absorber windows and assign oversight responsibility WL Need to discuss with the group on who is the best person to do this On going Hydrogen system R&D TB / EB Progress being made. See the previous summary talk. On -going Status of Progress Action Who Progress made status Implement central repository for drawings -- need detector information to add to official drawing WL Done. Instrumentation for absorbers must be specified and incorporated into design (temperature sensors, liquid level sensors, …) SI Basically complete. On-going liasing with Mississippi on CKOV1 drawings; with Tortora on Calorimeter etc Diffuser still to be added Hyperlink to drawing gallery is now available Proposal now available (see Shigeru’s summary talk) and will be discussed among the AFC group as an on going action for Absorber R&D Define absorber heater implementation YI / SI Continue working to define worst-case magnet forces and collect magnet design notes into design report MG/ YI/ SY Check if a 1600mm gap between AFC & Tracker matching coils WL/ UB Revise absorber vent pipe size to make it adequate for He case WL Get RAL seismic design criteria and verify that designs meet them WL/ PD Done Done Ditto Yury and the team at RAL has now completed that work. Stephanie completed the FEA on forces and displacements. We are now homing in on the rail and anchoring design details Ullisee has completed the calculations and advised that either gap distance (800mm or 1600mm) is acceptable as far as forces and current density are concerned. However, the group has a preference to the 800mm gap. Agreed to increase this to 15mm diameter. Drawing being updated Done This is not considered significant as RAL site has relatively low floor response. A static “G” of 0.3 would be sufficient for all components with a natural frequency of above 33Hz. Comp lete. Done Done Comp. visible TOF0 Chev 2 TOF 1&2 Magnetic Shield Detector Module Radiation Shield AFC modules 1&3 Coupling Modules 1&2 ☑ ☑ ☑ ☑ ☑ ☑ ☑ Status of Progress Action Who Progress made status Implement central repository for drawings -- need detector information to add to official drawing WL Done. Instrumentation for absorbers must be specified and incorporated into design (temperature sensors, liquid level sensors, …) SI Basically complete. On-going liasing with Mississippi on CKOV1 drawings; with Tortora on Calorimeter etc Diffuser still to be added Hyperlink to drawing gallery is now available Proposal now available (see Shigeru’s summary talk) and will be discussed among the AFC group as an on going action for Absorber R&D Define absorber heater implementation YI / SI Continue working to define worst-case magnet forces and collect magnet design notes into design report MG / YI / SY Check if a 1600mm gap between AFC & Tracker matching coils WL/ UB Revise absorber vent pipe size to make it adequate for He case WL Get RAL seismic design criteria and verify that designs meet them WL/ PD Done Done Ditto Yury and the team at RAL has now completed that work. Stephanie completed the FEA on forces and displacements. We are now homing in on the rail and anchoring design details Ullisee has completed the calculations and advised that either gap distance (800mm or 1600mm) is acceptable as far as forces and current density are concerned. However, the group has a preference to the 800mm gap. Agreed to increase this to 15mm diameter. Drawing being updated Done This is not considered significant as RAL site has relatively low floor response. A static “G” of 0.3 would be sufficient for all components with a natural frequency of above 33Hz. Comp lete. Done Done Heater/thermometer assemble for MICE absorber AL. block CX-1050-SD HTR-25-100 Thermometers in absorber AC Bridge 370S CX-1050-SD 3716; 16ch Scanner L-H2/LHe Level sensor in absorber DC ~mA DC Current for L-H2/LHe should be optimized (KEK R&D). V4 V3 LHe LH2 CX-1050-SD Wiring of thermometers, level sensor & heaters 4 wires measurement for thermometers and heaters AC Bridge 370S with16ch Scanner Max. 16 CH 6 for absorber (8 6, 2 at top ) 2 for windows 2 for LH2 pipes 2 for C-He pipes 3 for Cryocooler 1 for magnet bore MICE absorber monitor/control (R&D at KEK, plan) LAN PC IEEE-488/RS232C cc1mA DCPS DCPS DCPS 0.1mA Keithley 2700 Inside Abs. Abs. HTR-UP Abs. HTR-DWN CRYOSTAT READ OUTS CRYOCOOL HTR 16 CX-1050SD’s Abs. LEVEL 3-HTR CX-1050 5-CX-1050 P&VAC Sensors ALRAM, VALVES, CRYOCOOLER-OFF, HEATER-OFF… MICE absorber monitor/control (plan) Programmable Controller or LOGIC LAN DIO Contacts PC / WS DIRECT CONTROL IEEE-488 DMR 1-6 2CH AC Bridge 370S DCPS DCPS DCPS cc1mA Keithley/ADC Inside Abs. Abs. HTR-UP 16 CX-1050SD’s CRYOCOOL HTR CRYOSTAT Abs. LEVEL CX-1050 Abs. HTR-DWN READ OUTS 3-HTR 5-CX-1050 P&VAC&LEVEL Sensors Digital meter relay for MICE absorber/Cryocooler DMR; DIGITAL METER RELAY (Digital comparator) Watanabe (Japan) for example INPUT WSM-452HR-R3NNNX-22VD ; DC 0-199.99 mV WSM-452HR-R3NNNX-32VD ; DC 0-1.9999 V WSM-452HR-R3NNNX-42VD ; DC 0-19.999 V WSM-452HR-R3NNNX-52VD ; DC 0-199.99 V OUTPUT( 4.5 digit set) HI-relay (NC, HO) LO-relay (NC, NO) Scaling; A-B (V) C-D (Unit) DC24V Status of Progress Action Who Progress made status Implement central repository for drawings -- need detector information to add to official drawing WL Done. Instrumentation for absorbers must be specified and incorporated into design (temperature sensors, liquid level sensors, …) SI Basically complete. On-going liasing with Mississippi on CKOV1 drawings; with Tortora on Calorimeter etc Diffuser still to be added Hyperlink to drawing gallery is now available Proposal now available (see Shigeru’s summary talk) and will be discussed among the AFC group as an on going action for Absorber R&D Define absorber heater implementation YI / SI Continue working to define worst-case magnet forces and collect magnet design notes into design report MG/ YI/ SY Check if a 1600mm gap between AFC & Tracker matching coils WL/ UB Revise absorber vent pipe size to make it adequate for He case WL Get RAL seismic design criteria and verify that designs meet them WL/ PD Done Done Ditto Yury and the team at RAL has now completed that work. Stephanie completed the FEA on forces and displacements. We are now homing in on the rail and anchoring design details Ullisee has completed the calculations and advised that either gap distance (800mm or 1600mm) is acceptable as far as forces and current density are concerned. However, the group has a preference to the 800mm gap. Agreed to increase this to 15mm diameter. Drawing being updated Done This is not considered significant as RAL site has relatively low floor response. A static “G” of 0.3 would be sufficient for all components with a natural frequency of above 33Hz. Comp lete. Done Done Force profile received from Yury in January 2005 Forces (MN) Case No. AFC 1 RFCC 1 AFC 2 RFCC 2 AFC 3 1 -0.088 -0.214 0 0.214 0.088 2 0.037 0.186 0 -0.186 -0.037 3 0 -0.211 0 0.211 0 4 -0.398 0 0 0 0.398 5 0.312 -0.313 0 0.313 -0.312 6 -0.084 0.095 -0.313 0 0.401 7 -0.0878 -0.2213 0.0009 0.3057 -0.3121 Case 1: Forces (in MN) for Flip mode, Stage 6, p=240 MeV/c, β=42cm MICE cooling channel FEA model with the loading and boundary conditions Case 1: FEA result case 1: horizontal reaction forces 40000 30000 reaction forces N 20000 10000 0 1 2 3 4 5 6 7 -10000 -20000 -30000 -40000 Case 1: vertical reaction force Max reaction force in Y direction at the support base is 44548 N 50000 40000 30000 reaction forces N 20000 10000 0 -10000 -20000 -30000 -40000 -50000 1 2 3 4 5 6 7 8 9 10 8 9 10 Super-module reaction forces foot Normal Operation Case 1 Flip 240Mev/c y force/foot z force/foot z force/side Case 2 Non flip 240 y force/foot z force/foot z force/side Symmetric Quench Case 3 AFC Q Case 4 y force/foot z force/foot z force/side CC Q Case 5 y force/foot z force/foot z force/side DET Q y force/foot z force/foot z force/side Non Symmetric Quench Case 6 CCQ non sym y force/foot z force/foot z force/side Case 5 DET Q non sym y force/foot z force/foot z force/side y grav ymag zmag y grav ymag zmag y grav ymag zmag y grav ymag zmag y grav ymag zmag y grav ymag zmag y grav ymag zmag AFC Pos 1 AFC RF/CC RF/CC AFC AFC RF/CC RF/CC AFC AFC 2 3 4 5 6 7 8 9 10 -0.4 -0.8 -1.2 0.2 -0.4 0.8 0.4 0.2 0.4 -0.4 -0.5 -0.9 -0.1 -0.2 -1.2 -4.4 -5.6 2.8 -1.2 4.4 3.2 2.9 5.7 -1.2 -3.2 -4.4 -2.2 -4.2 -0.4 0.0 -0.4 0.0 -0.4 0.0 -0.4 0.0 0.0 -0.4 0.0 -0.4 0.0 0.0 -1.2 4.4 3.2 -2.9 -1.2 -4.4 -5.6 -2.8 -5.7 -1.2 3.2 2.0 2.0 4.2 -0.4 0.8 0.4 -0.2 -0.4 -0.8 -1.2 -0.2 -0.4 -0.4 0.5 0.1 -0.1 -0.2 -0.4 0.3 -0.2 0.1 0.2 -0.4 1.9 1.5 0.5 1.0 -0.4 -0.9 -1.3 -0.3 -0.5 -1.2 -3.1 -4.3 2.0 -1.2 3.1 1.9 2.0 4.0 -1.2 5.5 4.3 3.8 6.9 -1.2 0.4 -0.9 0.2 0.5 -0.4 0.0 -0.4 0.0 -0.4 0.0 -0.4 0.0 0.0 -0.4 0.0 -0.4 0.0 0.0 -0.4 0.0 -0.4 0.0 0.0 -1.2 3.1 1.9 -2.0 -1.2 -3.1 -4.3 -2.0 -4.0 -1.2 -5.5 -6.7 -3.1 -6.9 -1.2 -0.4 -1.6 -0.4 -0.5 -0.4 0.3 -0.2 -0.1 -0.4 0.3 -0.1 0.1 0.2 -0.4 1.4 1.0 0.3 0.6 -1.2 -0.5 -1.7 0.6 -1.2 0.7 -0.5 0.6 1.2 -1.2 8.4 7.2 5.0 10.0 -0.4 -0.1 -0.5 0.1 -0.4 0.3 -0.1 0.1 0.2 -0.4 0.5 0.1 0.2 0.4 -1.2 4.4 3.2 -3.0 -1.2 -4.5 -5.7 -2.5 -5.5 -1.2 3.9 2.7 1.8 3.8 -0.4 1.7 1.3 -0.5 -0.4 0.5 0.1 -0.1 -0.4 -0.3 -0.7 0.1 -0.4 -1.9 -2.3 0.5 -0.4 0.9 0.4 -0.3 -0.4 -0.2 -0.6 0.1 -0.4 -1.3 -1.7 0.3 -1.2 3.2 2.0 -2.0 -1.2 -5.5 -6.7 3.1 -1.2 -0.4 -1.6 0.4 -1.2 -9.3 -10.5 5.0 -0.4 0.0 -0.4 0.0 -0.4 0.0 -0.4 0.0 -0.4 0.0 -0.4 0.0 -0.4 -0.4 -0.8 0.2 -1.2 -3.2 -4.4 2.2 -1.2 5.5 4.3 -3.8 -1.2 0.4 -0.9 -0.2 -1.2 -3.8 -5.0 2.0 -0.4 -0.5 -0.9 -0.1 -0.4 1.9 1.5 -0.5 -0.4 -0.9 -1.3 0.3 -0.4 -1.4 -1.8 0.4 -0.4 -0.3 -0.7 -0.1 -0.2 -0.4 -1.9 -2.3 -0.5 -1.0 -0.4 0.9 0.4 0.3 0.5 -0.4 -1.8 -2.2 -0.5 -1.0 -0.4 1.5 1.1 0.3 0.7 Rail – mounting concept Combined Roller Bearing Force transfer concept - Y Status of Progress Action Who Progress made status Implement central repository for drawings -- need detector information to add to official drawing WL Done. Instrumentation for absorbers must be specified and incorporated into design (temperature sensors, liquid level sensors, …) SI Basically complete. On-going liasing with Mississippi on CKOV1 drawings; with Tortora on Calorimeter etc Diffuser still to be added Hyperlink to drawing gallery is now available Proposal now available (see Shigeru’s summary talk) and will be discussed among the AFC group as an on going action for Absorber R&D Define absorber heater implementation YI / SI Continue working to define worst-case magnet forces and collect magnet design notes into design report MG/ YI/ SY Check if a 1600mm gap between AFC & Tracker matching coils WL/ UB Revise absorber vent pipe size to make it adequate for He case WL Get RAL seismic design criteria and verify that designs meet them WL/ PD Done Done Ditto Yury and the team at RAL has now completed that work. Stephanie completed the FEA on forces and displacements. We are now homing in on the rail and anchoring design details Ullisee has completed the calculations and advised that either gap distance (800mm or 1600mm) is acceptable as far as forces and current density are concerned. However, the group has a preference to the 800mm gap. Agreed to increase this to 15mm diameter. Drawing being updated Done This is not considered significant as RAL site has relatively low floor response. A static “G” of 0.3 would be sufficient for all components with a natural frequency of above 33Hz. Comp lete. Done Done Ulisse Bravar 26 January 2005 •This note presents the optic solutions for MICE Step III for a large number of different running conditions. •Two gap distances between the two spectrometers are considered, 800 mm and 1600 mm. •For the 800 mm gap, a table with forces and peak fields on coil surfaces for the worst case scenarios is attached, courtesy of H. Witte •For the 1600 mm gap, all currents in the MICE coils are equal to or less than the worst case currents of the 800 mm gap. •Hence, for the 1600 mm case, forces and peak fields are also lower than the ones in the 800 mm case. •In conclusion, currents, peak fields and forces both in the 800 mm and in the 1600 mm gaps are within tolerances. Status of Progress Action Who Progress made status Implement central repository for drawings -- need detector information to add to official drawing WL Done. Instrumentation for absorbers must be specified and incorporated into design (temperature sensors, liquid level sensors, …) SI Basically complete. On-going liasing with Mississippi on CKOV1 drawings; with Tortora on Calorimeter etc Diffuser still to be added Hyperlink to drawing gallery is now available Proposal now available (see Shigeru’s summary talk) and will be discussed among the AFC group as an on going action for Absorber R&D Define absorber heater implementation YI / SI Continue working to define worst-case magnet forces and collect magnet design notes into design report MG/ YI/ SY Check if a 1600mm gap between AFC & Tracker matching coils WL/ UB Revise absorber vent pipe size to make it adequate for He case WL Get RAL seismic design criteria and verify that designs meet them WL/ PD Done Done Ditto Yury and the team at RAL has now completed that work. Stephanie completed the FEA on forces and displacements. We are now homing in on the rail and anchoring design details Ullisee has completed the calculations and advised that either gap distance (800mm or 1600mm) is acceptable as far as forces and current density are concerned. However, the group has a preference to the 800mm gap. Agreed to increase this to 15mm diameter. Drawing being updated Done This is not considered significant as RAL site has relatively low floor response. A static “G” of 0.3 would be sufficient for all components with a natural frequency of above 33Hz. Comp lete. Done Done Status of Progress Action Who Progress made status Implement central repository for drawings -- need detector information to add to official drawing WL Done. Instrumentation for absorbers must be specified and incorporated into design (temperature sensors, liquid level sensors, …) SI Basically complete. On-going liasing with Mississippi on CKOV1 drawings; with Tortora on Calorimeter etc Diffuser still to be added Hyperlink to drawing gallery is now available Proposal now available (see Shigeru’s summary talk) and will be discussed among the AFC group as an on going action for Absorber R&D Define absorber heater implementation YI / SI Continue working to define worst-case magnet forces and collect magnet design notes into design report MG/ YI/ SY Check if a 1600mm gap between AFC & Tracker matching coils WL/ UB Revise absorber vent pipe size to make it adequate for He case WL Get RAL seismic design criteria and verify that designs meet them WL/ PD Done Done Ditto Yury and the team at RAL has now completed that work. Stephanie completed the FEA on forces and displacements. We are now homing in on the rail and anchoring design details Ullisee has completed the calculations and advised that either gap distance (800mm or 1600mm) is acceptable as far as forces and current density are concerned. However, the group has a preference to the 800mm gap. Agreed to increase this to 15mm diameter. Drawing being updated Done This is not considered significant as RAL site has relatively low floor response. A static “G” of 0.3 would be sufficient for all components with a natural frequency of above 33Hz. Comp lete. Done Done Who Progress made status Evaluate stresses at module interconnect flanges and bolts SV Ongoing Define RFCC module tie-in to rail system SV Work out gusset arrangement to transfer CC forces to RFCC module vacuum shell. SV Steve Verostek had done detail FEA on bolt / flange connection and the work is still ongoing This is now in he hands on the RAL design team Await Mike Green to finalise the Cold Mass support arrangement before deciding on how and where to put these gussets Evaluate the need for redundant LH2 relief paths EB / TB This is part of the on-going R&D activity on the Hydrogen System R&D. Ongoing Evaluate merits of cryocooler heater vs. 3-stage cooler w/o heater Evaluate absorber heat load with more realistic assessment of surrounding temperatures (is proposed MLI adequate?) Finalize interface between radiation shield and detector module - must forces be transmitted Consider participation in KEK and/or Fermilab absorber tests (some coordination maybe called for) MG Concluded that this is no longer an option for our current design Done EB/ MG/ SY Thermal model set up. Elwyn and his team are making progress on this Ongoing WL Stephanie has done the calc. Forces and displacement s at modules are acceptable for the 7 cases being considered. Done YI / SI MICE Absorber R&D will be carried out at KEK for the 1st absorber. We are still in discussion with Shigeru on whether the thermal test of the 2nd & 3rd absorbers should be done at KEK or RAL. Work is by and large complete. It shows that the 3 focus coils should be powered in series. The 2 Coupling Coils could be powered up either in series or separately. Ongoing Done Done Action Evaluate magnet interaction during quench -- does one quench induce others EB / MG Raise Change note on the radiation shield design SY / WL Ongoing Ongoing Done Who Progress made status Evaluate stresses at module interconnect flanges and bolts SV Ongoing Define RFCC module tie-in to rail system SV Work out gusset arrangement to transfer CC forces to RFCC module vacuum shell. SV Steve Verostek had done detail FEA on bolt / flange connection and the work is still ongoing This is now in he hands on the RAL design team Await Mike Green to finalise the Cold Mass support arrangement before deciding on how and where to put these gussets Evaluate the need for redundant LH2 relief paths EB / TB This is part of the on-going R&D activity on the Hydrogen System R&D. Ongoing Evaluate merits of cryocooler heater vs. 3-stage cooler w/o heater Evaluate absorber heat load with more realistic assessment of surrounding temperatures (is proposed MLI adequate?) Finalize interface between radiation shield and detector module - must forces be transmitted Consider participation in KEK and/or Fermilab absorber tests (some coordination maybe called for) MG Concluded that this is no longer an option for our current design Done EB/ MG/ SY Thermal model set up. Elwyn and his team are making progress on this Ongoing WL Stephanie has done the calc. Forces and displacement s at modules are acceptable for the 7 cases being considered. Done YI / SI MICE Absorber R&D will be carried out at KEK for the 1st absorber. We are still in discussion with Shigeru on whether the thermal test of the 2nd & 3rd absorbers should be done at KEK or RAL. Work is by and large complete. It shows that the 3 focus coils should be powered in series. The 2 Coupling Coils could be powered up either in series or separately. Ongoing Done Done Action Evaluate magnet interaction during quench -- does one quench induce others EB / MG Raise Change note on the radiation shield design SY / WL Ongoing Ongoing Done Who Progress made status Evaluate stresses at module interconnect flanges and bolts SV Ongoing Define RFCC module tie-in to rail system SV Work out gusset arrangement to transfer CC forces to RFCC module vacuum shell. SV Steve Verostek had done detail FEA on bolt / flange connection and the work is still ongoing This is now in he hands on the RAL design team Await Mike Green to finalise the Cold Mass support arrangement before deciding on how and where to put these gussets Evaluate the need for redundant LH2 relief paths EB / TB This is part of the on-going R&D activity on the Hydrogen System R&D. Ongoing Evaluate merits of cryocooler heater vs. 3-stage cooler w/o heater Evaluate absorber heat load with more realistic assessment of surrounding temperatures (is proposed MLI adequate?) Finalize interface between radiation shield and detector module - must forces be transmitted Consider participation in KEK and/or Fermilab absorber tests (some coordination maybe called for) MG Concluded that this is no longer an option for our current design Done EB/ MG/ SY Thermal model set up. Elwyn and his team are making progress on this Ongoing WL Stephanie has done the calc. Forces and displacement s at modules are acceptable for the 7 cases being considered. Done YI / SI MICE Absorber R&D will be carried out at KEK for the 1st absorber. We are still in discussion with Shigeru on whether the thermal test of the 2nd & 3rd absorbers should be done at KEK or RAL. Work is by and large complete. It shows that the 3 focus coils should be powered in series. The 2 Coupling Coils could be powered up either in series or separately. Ongoing Done Done Action Evaluate magnet interaction during quench -- does one quench induce others EB / MG Raise Change note on the radiation shield design SY / WL Ongoing Ongoing Done Who Progress made status Evaluate stresses at module interconnect flanges and bolts SV Ongoing Define RFCC module tie-in to rail system SV Work out gusset arrangement to transfer CC forces to RFCC module vacuum shell. SV Steve Verostek had done detail FEA on bolt / flange connection and the work is still ongoing This is now in he hands on the RAL design team Await Mike Green to finalise the Cold Mass support arrangement before deciding on how and where to put these gussets Evaluate the need for redundant LH2 relief paths EB / TB This is part of the on-going R&D activity on the Hydrogen System R&D. Ongoing Evaluate merits of cryocooler heater vs. 3-stage cooler w/o heater Evaluate absorber heat load with more realistic assessment of surrounding temperatures (is proposed MLI adequate?) Finalize interface between radiation shield and detector module - must forces be transmitted Consider participation in KEK and/or Fermilab absorber tests (some coordination maybe called for) MG Concluded that this is no longer an option for our current design Done EB/ MG/ SY Thermal model set up. Elwyn and his team are making progress on this Ongoing WL Stephanie has done the calc. Forces and displacement s at modules are acceptable for the 7 cases being considered. Done YI / SI MICE Absorber R&D will be carried out at KEK for the 1st absorber. We are still in discussion with Shigeru on whether the thermal test of the 2nd & 3rd absorbers should be done at KEK or RAL. Work is by and large complete. It shows that the 3 focus coils should be powered in series. The 2 Coupling Coils could be powered up either in series or separately. Ongoing Done Done Action Evaluate magnet interaction during quench -- does one quench induce others EB / MG Raise Change note on the radiation shield design SY / WL Ongoing Ongoing Done Hydrogen System Baseline layout High level vent High level vent Non return valve Vent manifold 0.1 bar Hydrogen zone 2 Vent outside flame arrester Vent manifold H2Detector Extract hood VP2 PV8 P P1 PV7 P PV2 Buffer 3 vessel 1 m Hydrogen supply P P PV1 Metal Hydride storage unit (20m3 capacity) 1 bar Tbed PV3 PV4 Fill valve P HV1 Coolant Out In P2 P 0.5 bar 0.9 bar P P P P3 P HV2 Purge valve P H2 Detector Safety window Purge valve HV3 Absorber window Nitrogen supply 0.9 bar PV6 Helium supply 0.5 bar VP1 P Pressure gauge P Pressure regulator Valve Pressure relief valve Non-return valve Bursting disk VP Vacuum pump Chiller/He ater Unit Who Progress made status Evaluate stresses at module interconnect flanges and bolts SV Ongoing Define RFCC module tie-in to rail system SV Work out gusset arrangement to transfer CC forces to RFCC module vacuum shell. SV Steve Verostek had done detail FEA on bolt / flange connection and the work is still ongoing This is now in he hands on the RAL design team Await Mike Green to finalise the Cold Mass support arrangement before deciding on how and where to put these gussets Evaluate the need for redundant LH2 relief paths EB / TB This is part of the on-going R&D activity on the Hydrogen System R&D. Ongoing Evaluate merits of cryocooler heater vs. 3-stage cooler w/o heater Evaluate absorber heat load with more realistic assessment of surrounding temperatures (is proposed MLI adequate?) Finalize interface between radiation shield and detector module - must forces be transmitted Consider participation in KEK and/or Fermilab absorber tests (some coordination maybe called for) MG Concluded that this is no longer an option for our current design Done EB/ MG/ SY Thermal model set up. Elwyn and his team are making progress on this Ongoing WL Stephanie has done the calc. Forces and displacement s at modules are acceptable for the 7 cases being considered. Done YI / SI MICE Absorber R&D will be carried out at KEK for the 1st absorber. We are still in discussion with Shigeru on whether the thermal test of the 2nd & 3rd absorbers should be done at KEK or RAL. Work is by and large complete. It shows that the 3 focus coils should be powered in series. The 2 Coupling Coils could be powered up either in series or separately. Ongoing Done Done Action Evaluate magnet interaction during quench -- does one quench induce others EB / MG Raise Change note on the radiation shield design SY / WL Ongoing Ongoing Done Who Progress made status Evaluate stresses at module interconnect flanges and bolts SV Ongoing Define RFCC module tie-in to rail system SV Work out gusset arrangement to transfer CC forces to RFCC module vacuum shell. SV Steve Verostek had done detail FEA on bolt / flange connection and the work is still ongoing This is now in he hands on the RAL design team Await Mike Green to finalise the Cold Mass support arrangement before deciding on how and where to put these gussets Evaluate the need for redundant LH2 relief paths EB / TB This is part of the on-going R&D activity on the Hydrogen System R&D. Ongoing Evaluate merits of cryocooler heater vs. 3-stage cooler w/o heater Evaluate absorber heat load with more realistic assessment of surrounding temperatures (is proposed MLI adequate?) Finalize interface between radiation shield and detector module - must forces be transmitted Consider participation in KEK and/or Fermilab absorber tests (some coordination maybe called for) MG Concluded that this is no longer an option for our current design Done EB/ MG/ SY Thermal model set up. Elwyn and his team are making progress on this Ongoing WL Stephanie has done the calc. Forces and displacement s at modules are acceptable for the 7 cases being considered. Done YI / SI MICE Absorber R&D will be carried out at KEK for the 1st absorber. We are still in discussion with Shigeru on whether the thermal test of the 2nd & 3rd absorbers should be done at KEK or RAL. Work is by and large complete. It shows that the 3 focus coils should be powered in series. The 2 Coupling Coils could be powered up either in series or separately. Ongoing Done Done Action Evaluate magnet interaction during quench -- does one quench induce others EB / MG Raise Change note on the radiation shield design SY / WL Ongoing Ongoing Done Model Absorber thermal model Who Progress made status Evaluate stresses at module interconnect flanges and bolts SV Ongoing Define RFCC module tie-in to rail system SV Work out gusset arrangement to transfer CC forces to RFCC module vacuum shell. SV Steve Verostek had done detail FEA on bolt / flange connection and the work is still ongoing This is now in he hands on the RAL design team Await Mike Green to finalise the Cold Mass support arrangement before deciding on how and where to put these gussets Evaluate the need for redundant LH2 relief paths EB / TB This is part of the on-going R&D activity on the Hydrogen System R&D. Ongoing Evaluate merits of cryocooler heater vs. 3-stage cooler w/o heater Evaluate absorber heat load with more realistic assessment of surrounding temperatures (is proposed MLI adequate?) Finalize interface between radiation shield and detector module - must forces be transmitted Consider participation in KEK and/or Fermilab absorber tests (some coordination maybe called for) MG Concluded that this is no longer an option for our current design Done EB/ MG/ SY Thermal model set up. Elwyn and his team are making progress on this Ongoing WL Stephanie has done the calc. Forces and displacement s at modules are acceptable for the 7 cases being considered. Done YI / SI MICE Absorber R&D will be carried out at KEK for the 1st absorber. We are still in discussion with Shigeru on whether the thermal test of the 2nd & 3rd absorbers should be done at KEK or RAL. Work is by and large complete. It shows that the 3 focus coils should be powered in series. The 2 Coupling Coils could be powered up either in series or separately. Ongoing Done Done Action Evaluate magnet interaction during quench -- does one quench induce others EB / MG Raise Change note on the radiation shield design SY / WL Ongoing Ongoing Done FEA result summary Case No. Max stress MPa Max displacement mm Max horizontal reaction force N Max vertical reaction force N 1 37 0.114 29148 44548 2 28 0.075 21588 33201 3 26 0.063 20672 31797 4 89 0.291 37005 55633 5 70 0.164 3747 9213 6 88 0.28 66833 46302 7 69 0.22 50698 85550 Who Progress made status Evaluate stresses at module interconnect flanges and bolts SV Ongoing Define RFCC module tie-in to rail system SV Work out gusset arrangement to transfer CC forces to RFCC module vacuum shell. SV Steve Verostek had done detail FEA on bolt / flange connection and the work is still ongoing This is now in he hands on the RAL design team Await Mike Green to finalise the Cold Mass support arrangement before deciding on how and where to put these gussets Evaluate the need for redundant LH2 relief paths EB / TB This is part of the on-going R&D activity on the Hydrogen System R&D. Ongoing Evaluate merits of cryocooler heater vs. 3-stage cooler w/o heater Evaluate absorber heat load with more realistic assessment of surrounding temperatures (is proposed MLI adequate?) Finalize interface between radiation shield and detector module - must forces be transmitted Consider participation in KEK and/or Fermilab absorber tests (some coordination maybe called for) Evaluate magnet interaction during quench -- does one quench induce others MG Concluded that this is no longer an option for our current design Done EB/ MG/ SY Thermal model set up. Elwyn and his team are making progress on this Ongoing WL Stephanie has done the calc. Forces and displacement s at modules are acceptable for the 7 cases being considered. Done YI / SI Detail arrangement is still being worked out between KEK & RAL Ongoing EB / MG Work is by and large complete. It shows that the 3 focus coils should be powered in series. The 2 Coupling Coils could be powered up either in series or separately. Done SY / WL Done Done Action Raise Change note on the radiation shield design Ongoing Ongoing Absorber test cryostat ATC-002 (dimensions) MICE W W D2; Cryocooler flange (needs larger Cryocooler flange for pips) D1 H2 H1 July 05 Oct 05 Jan 06 Apr 06 July 06 Oct 06 Jan 07 Apr 07 Absorber R & D Thermal performance test on 2nd absorber Thermal performance test on 3rd absorber Hydrogen system R&D Initial design KEK test cryostat comes to RAL Prelim. D & S review Detailed design & procurement Installation & commissioning Test programme Permission to operate Phase 1 deliverable fully installed & tested Thermal performance test on 1st absorber (KEK) Who Progress made status Evaluate stresses at module interconnect flanges and bolts SV Ongoing Define RFCC module tie-in to rail system SV Work out gusset arrangement to transfer CC forces to RFCC module vacuum shell. SV Steve Verostek had done detail FEA on bolt / flange connection and the work is still ongoing This is now in he hands on the RAL design team Await Mike Green to finalise the Cold Mass support arrangement before deciding on how and where to put these gussets Evaluate the need for redundant LH2 relief paths EB / TB This is part of the on-going R&D activity on the Hydrogen System R&D. Ongoing Evaluate merits of cryocooler heater vs. 3-stage cooler w/o heater Evaluate absorber heat load with more realistic assessment of surrounding temperatures (is proposed MLI adequate?) Finalize interface between radiation shield and detector module - must forces be transmitted Consider participation in KEK and/or Fermilab absorber tests (some coordination maybe called for) MG Concluded that this is no longer an option for our current design Done EB/ MG/ SY Thermal model set up. Elwyn and his team are making progress on this Ongoing WL Stephanie has done the calc. Forces and displacement s at modules are acceptable for the 7 cases being considered. Done YI / SI MICE Absorber R&D will be carried out at KEK for the 1st absorber. We are still in discussion with Shigeru on whether the thermal test of the 2nd & 3rd absorbers should be done at KEK or RAL. Work is by and large complete. It shows that the 3 focus coils should be powered in series. The 2 Coupling Coils could be powered up either in series or separately. Ongoing Done Done Action Evaluate magnet interaction during quench -- does one quench induce others EB / MG Raise Change note on the radiation shield design SY / WL Ongoing Ongoing Done Lab G Solenoid Power Supply and Quench Protection The MICE Coupling Coil Power Supply with Quench Protection The MICE Coupling Coil Power Supply with Quench Protection Note: The coil is shown split into two parts. The coil may be split into three or four parts instead of two parts. Detector Magnet Power Supplies Match 1 Match 2 End 1 Center PS PS PS PS Power Supply 10 V, 300 A Power Supply 10 V, 50 A End 2 PS Concluding Comments on Quenches • The focusing and coupling magnets will have passive quench protection. The detector magnet will likely have an active quench protection system. • The three focusing magnets should be in series. • Each coupling magnet should have its own power supply to reduce the charge time. • Like detector magnet coils can be put in series. • A coupling coil quench will quench the rest of MICE. A focus coil quench will not quench a coupling coil. Who Progress made status Evaluate stresses at module interconnect flanges and bolts SV Ongoing Define RFCC module tie-in to rail system SV Work out gusset arrangement to transfer CC forces to RFCC module vacuum shell. SV Steve Verostek had done detail FEA on bolt / flange connection and the work is still ongoing This is now in he hands on the RAL design team Await Mike Green to finalise the Cold Mass support arrangement before deciding on how and where to put these gussets Evaluate the need for redundant LH2 relief paths EB / TB This is part of the on-going R&D activity on the Hydrogen System R&D. Ongoing Evaluate merits of cryocooler heater vs. 3-stage cooler w/o heater Evaluate absorber heat load with more realistic assessment of surrounding temperatures (is proposed MLI adequate?) Finalize interface between radiation shield and detector module - must forces be transmitted Consider participation in KEK and/or Fermilab absorber tests (some coordination maybe called for) MG Concluded that this is no longer an option for our current design Done EB/ MG/ SY Thermal model set up. Elwyn and his team are making progress on this Ongoing WL Stephanie has done the calc. Forces and displacement s at modules are acceptable for the 7 cases being considered. Done YI / SI MICE Absorber R&D will be carried out at KEK for the 1st absorber. We are still in discussion with Shigeru on whether the thermal test of the 2nd & 3rd absorbers should be done at KEK or RAL. Work is by and large complete. It shows that the 3 focus coils should be powered in series. The 2 Coupling Coils could be powered up either in series or separately. Ongoing Done Done Action Evaluate magnet interaction during quench -- does one quench induce others EB / MG Raise Change note on the radiation shield design SY / WL Ongoing Ongoing Done Action Who Progress made status Window QC – round robin exercise WL Work is on-going. Ongoing Understand QC requirements for absorber windows and assign oversight responsibility WL Need to discuss with the group on who is the best person to do this On going Hydrogen system R&D TB / EB Progress being made. See the previous summary talk. On -going Task Description An AFC Module window that was damaged during machining was used to test a non-contact measurement method. A standard CMM was also used for comparison. All measurements were made on both sides of the window with the thickness being determined indirectly from the two sets of data. Measurements consisted of 12 radial slices at 15º increments. The center 80 mm of the window is damaged. Measurement Methods •Standard CMM with low contact force •Vision machine with medium magnification lens •Vision machine with high magnification (not yet complete) Summary of Results •Best data obtained from CMM measurement •Vision machine data shows more scatter •Good portion of window is within 40 mm of design thickness Standard CMM Measurement Vision Machine Measurement Window Thickness vs. Radial Location 0.9 0.8 Thickness (mm) 0.7 0.6 0.5 0.4 0.3 0.2 CMM Data As Designed Vision Data (med. mag.) 0.1 0 30 40 50 60 70 Radial Location (mm) 80 90 100 Discussion • The vision machine works best when measuring horizontal, smooth surfaces • The combination of a sloped surface and machining grooves in the window is likely responsible for the data scatter • Preliminary results indicate that the higher magnification lens may provide better results than the medium lens • Overall, the best results are achieved using contact CMM • The following method would provide the highest accuracy: Contact CMM using a low-force tip and appropriate approach angle resulting in no window deflection The window mounted vertically to allow a single set-up Action Who Progress made status Window QC – round robin exercise WL Work is on-going. Ongoing Understand QC requirements for absorber windows and assign oversight responsibility WL Need to discuss with the group on who is the best person to do this On going Hydrogen system R&D TB / EB Progress being made. See the previous summary talk. On -going Action Who Progress made status Window QC – round robin exercise WL Work is on-going. Ongoing Understand QC requirements for absorber windows and assign oversight responsibility WL Need to discuss with the group on who is the best person to do this On going Hydrogen system R&D TB / EB Progress being made. See the previous summary talk. On -going Revised Action list Who Progress made Evaluate the need for redundant LH2 relief paths EB / TB This is part of the on-going R&D activity on the Hydrogen System R&D. Ongoing Evaluate absorber heat load with more realistic assessment of surrounding temperatures (is proposed MLI adequate?) Evaluate stresses at module interconnect flanges and bolts EB/ MG/ SY Thermal model set up. Elwyn and his team are making progress on this Ongoing SV Ongoing Define RFCC module tie-in to rail system SV Steve Verostek had done detail FEA on bolt / flange connection and the work is still ongoing This is now in he hands on the RAL design team Work out gusset arrangement to transfer CC forces to RFCC module vacuum shell. SV Ongoing Window QC – round robin exercise WL Await Mike Green to finalise the Cold Mass support arrangement before deciding on how and where to put these gussets Work is on-going. Understand QC requirements for absorber windows and assign oversight responsibility Hydrogen system R&D WL Need to discuss with the group on who is the best person to do this On going TB / EB Progress being made. See the previous summary talk. On -going Action status Ongoing Ongoing Revised Action list Who Progress made Evaluate the need for redundant LH2 relief paths EB / TB This is part of the on-going R&D activity on the Hydrogen System R&D. Ongoing Evaluate absorber heat load with more realistic assessment of surrounding temperatures (is proposed MLI adequate?) Evaluate stresses at module interconnect flanges and bolts EB/ MG/ SY Thermal model set up. Elwyn and his team are making progress on this Ongoing SV Ongoing Define RFCC module tie-in to rail system SV Steve Verostek had done detail FEA on bolt / flange connection and the work is still ongoing This is now in he hands on the RAL design team Work out gusset arrangement to transfer CC forces to RFCC module vacuum shell. SV Ongoing Window QC – round robin exercise WL Await Mike Green to finalise the Cold Mass support arrangement before deciding on how and where to put these gussets Work is on-going. Understand QC requirements for absorber windows and assign oversight responsibility Hydrogen system R&D WL Need to discuss with the group on who is the best person to do this On going TB / EB Progress being made. See the previous summary talk. On -going EB / SY Initial guess is that the force is in the region of 30 tons. Force calculation will be carried out to verify this number. A new temporary bridging plate will be designed for the Stage IV test New action Action Obtain magnet force on AFC module during Stage IV test when only one AFC module is placed between the two detector solenoids status Ongoing Ongoing Stage IV arrangement – 2 tracker solenoids + 1 AFC module in between Magnet force of this magnitude may cause excessive bending here Magnet force of approx. 30 Tons due to asymmetric quench of magnets Reinforcement gussets Temporary bridging piece
© Copyright 2026 Paperzz