PD40 High Impact Low Probability Event Mitigation RCP2 Portfolio Overview Document Portfolio: Expenditure Class: Expenditure Category: As at date: Expenditure Forecast Real 2012/13 NZ$ (m) CAPEX High Impact Low Probability Event Mitigation Base Capex Grid – Enhancement & Development 15 November 2013 2014-2015 2015-2016 2016-2017 2017-2018 2018-2019 2019-2020 Total in RCP2 1.43 2.80 2.88 1.47 1.04 1.04 9.23 Need Identification This portfolio aims to improve system security by implementing economic investments to reduce the extent of high impact, low probability (HILP) events at key substations. The HILP Mitigation portfolio will: Describe the reason for proposing a project ( i.e. need or trigger) implement mitigation measures identified in the HILP event investigations , where appropriate . In many cases measures become economic when combined with fleet asset replacements. This portfolio allows for the immediate implementation of simple, relatively low cost ‘quick fix’ economic mitigations not combined with other work; and implement two HILP mitigations at Islington substation that were identified in the HILP event review for that site: 1 2 o low voltage supply upgrade: The LVAC system supports the operation of all substation equipment and control systems. The main LVAC switchboard is a single point of failure; some of the equipment is old and a fire risk. Analysis shows that an upgrade of the LVAC system is economic o fire protection upgrade: The fire detection and suppression system within the Islington Control and adjacent Condenser buildings is inadequate for such a strategic site. A control building fire could interrupt supply to part of the upper South Island. An indicative economic 1 We plan to undertake 15 HILP risk investigations at critical substations over the RCP2 period, as part of the Investigations programme. 2 Refer Report on Islington Substation High Impact Low Probability (HILP) Event Study. 1 PD40 High Impact Low Probability Event Mitigation analysis (based on the possible extent and duration of such an outage) has demonstrated that all of the fire mitigation measures identified are economic to implement. What is the timing of the need and the confidence level that issue(s) will eventuate HILP investigations conducted to date lead us to believe that HILP studies at additional sites are highly likely to identify further risks that warrant mitigation in the short term. While specific work requirements are not yet known, we estimate that expenditure of $1m per annum will be required to undertake such works. With regard to the works at Islington, we intend to start the projects in 2014/15 and complete the work by 2017/18. As such, we have a high level of confidence that the work will be completed during RCP2. Long list of options and high level assessment Option Type Transmission options Option Fit Feasible Practical GEIP Security Cost Short list a) Special Protection Scheme (SPS) to enable maintenance or unusual operating conditions b) Shunt compensation by installing capacitors for voltage support c) Install addition bus section circuit breaker and bus zone protection d) Substation reconfiguration e) Grid reconfiguration f) System Operator intervention/operational measures Building options g) Improving Local service supply h) Installation of firewalls and fire suppression systems Fit for purpose – will meet the transmission need. Technical feasibility – complexity of solution; reliability, availability and maintainability of the solution; future flexibility – Grid Development Strategy. Practicality of implementation – Solution implementable by required date (probability of proceeding); property and environmental risks; implementation risks. Good electricity industry practice (GEIP) – consistent with good international practice; ensure safety and environmental protection; accounts for relative size, duty, age and technological status. System security (additional benefit resulting from an economic investment) – improved system security; system operator benefits (controllability); Dynamic benefits (modulation features and improved system stability). Indicative cost – whether an option will clearly be more expensive than another option with similar or greater benefits. 2 PD40 High Impact Low Probability Event Mitigation Short list of options Option 1 – Do Nothing / operational measures ‘Do-nothing’ may result in widespread loss of supply, and reduced supply security for extended periods. The system operator manages the load and re-dispatches generation to ensure asset loading and bus voltages are within limits post-contingency. Economic HILP mitigation measures across the RCP2 period 3 The types of remedial work that may be completed within this project include: Option 2 – HILP mitigation measures installation of firewalls installation of fire suppression systems in control rooms re-arranging circuit and transformer connections for greater diversity across buses mitigating risks around overcrossings of transmission circuits and buses improving local service supply; and special protection schemes to enable maintenance or unusual operating conditions. High Impact Low Probability (HILP) mitigation measures at Islington The specific HILP measures planned for the Islington site are: a. low voltage supply upgrade: shift the LVAC main switchboards and DC batteries and chargers from the cable basement to a location adjacent to, or in the main building; and replace the existing LVAC local service transformers and install four 33 kV/415 V units to supply the Islington site and Regional Control South; and b. Islington substation fire protection upgrade: a number of fire mitigation measures can be implemented to reduce fire risks at the Islington substation buildings. We are carrying out analysis to determine our preferred approach to fire mitigation strategy at Islington. P50 option costs Brief description of the approach used to estimate capex, and, if applicable, opex 3 In the case of the work to be undertaken at Islington, a desk-top assessment of a high level scope and ‘building block’ costs were used to estimate the cost. The approach and key assumptions used to compile the cost estimates have included (to the extent feasible): the likely location of new assets based on a desktop review of aerial photographs, site layout drawings, underground services drawings, and available cable ducts a likely scope assessment has been used to estimate materials and work quantities Based on mitigation measures identified from HILP investigations of Bromley and Islington substations. 3 PD40 High Impact Low Probability Event Mitigation typical component costs for material and work quantities have been taken from TEES (cost estimation software) typical material and plant costs have been determined with reference to period supply contracts currently in place and historic installation costs respectively; and typical installation costs (such as fire protection work) were informed by similar historic projects and or current quotes from service providers and applied based on the requirements of the site. With regard to the economic mitigation measures that will be undertaken at sites following detailed HILP event investigations, a provision has been made for the work based on mitigation measures for sites investigated to date. Option 1 – Do Nothing/operational measures $0 Total forecast expenditure on this project during RCP2 is $9.2m, and comprises: Option 2 – HILP mitigation measures HILP event mitigation measures across the RCP2 period – $5.2m (our level of confidence in this estimate is low as ‘building block’ costs are based on relatively few projects; and HILP event mitigation measures at Islington – $4.0m. Net benefits and outputs Option 1 – Do Nothing / operational measures (reference case) No investment is undertaken under this option. This provides the reference case with which the benefits of other options can be compared. Economic HILP event mitigation measures Based on HILP event investigations to date, we believe the economic benefits of risk mitigations can range from $3-5m at each site. Not all exposures warrant immediate, independent, action – at some sites it is more cost effective to undertake incremental work, on the back of fleet asset replacements, to complete identified remedial measures. The site specific HILP event investigations will help us to understand the HILP events each site may be exposed to, and quantify potential benefits, in order that relevant mitigation measures may be identified. The mitigating measures enable us to protect our substations against catastrophic events. Option 2 – HILP mitigation measures 1. HILP mitigation measures at Islington a. Low voltage supply upgrade – undertaking this work will reduce the likelihood and consequence of HILP LVAC events and improve the flexibility, operation and maintenance of the system; and b. Fire protection upgrade – this work will reduce the likelihood and consequence of HILP fire events. 4 PD40 High Impact Low Probability Event Mitigation Option risk assessment Option 1 – Do Nothing/ operational measures Some events have a low likelihood of occurrence. However, the consequences when they do occur is severe and may impair safe operations, power system stability, personnel safety, and delay restoration of supply. These situations cannot be fully mitigated using operational measures. Option 2 – HILP mitigation measures HILP event risks will be reduced by implementing the mitigation measures. Preferred option(s) What is the currently preferred option / sequence of options / or short-listed options? Option 2. The work programme for the Islington site has already been determined; work to be undertaken at other sites will be determined progressively during RCP2, as HILP reviews are completed. Set out the reasons for choosing the preferred option(s). Mitigations have a positive net benefit. Steps to completion A HILP event investigation has been carried out for Islington substation, and mitigating measures identified. Further HILP event investigations are being carried out at key substations to identify risks arising from HILP events and possible means of mitigation, following which preliminary economic analysis will be carried out to determine whether the identified mitigation measures are likely to be economic. What are the next step(s) in choosing the solution In accordance with our business case process (as described in section 3.6.1 of the AM03 - Planning Lifecycle Strategy) the next steps will be to: carry out a detailed investigation (BC2) to formally select the preferred options for works at Islington carry out detailed investigations (BC2) to confirm preferred options for other sites where HILP event risks have been identified which will not be addressed under fleet management strategies and for which preliminary economic analyses show net benefit in each case, obtain internal approval to proceed with the project (BC3). When did / will the steps in the internal approval process occur / take place and where were / will they be documented and described We will follow the following process for preparing the investment proposal for the work at Islington: conduct BC2 investigation to confirm the preferred option complete the consultation with affected stakeholders submit the preferred solution for Board approval; and 5 PD40 High Impact Low Probability Event Mitigation complete the BC3 for project execution. The work undertaken at each site, and hence the required services and assets, will be site specific. Identify the key services and assets that will need to be procured to complete the preferred option We expect to outsource the detailed design of the preferred solution. In accordance with our Procurement Policy, we will ensure that a robust and auditable purchase decision-making process is followed. We will complete a Procurement Plan to document the procurement process and for audit purposes. The plan helps us plan for the external procurement of goods and services in a way that ensures we are making the most appropriate purchasing decision for our stakeholders and ourselves. Projects not properly scoped can lead to cost overruns and not meeting deadlines. During the planning process, we will ensure project scope is adequately defined and it can be implemented within the required timeframe and cost. We will ensure the project is designed to its specification, the appropriate design reviews are completed and detailed factory inspections are carried out to manage risks. Identify the key delivery risks In the process of procurement, it is essential that we select a supplier that is able to consistently meet quality requirements. Quality must not be compromised in favour of other factors because of the critical influence of quality on risk to safety and the network. If applicable, we will standardise specifications and procurement of primary equipment to limit diversity and increase inter-changeability. This also allows procurement efficiencies to be attained. Safety is paramount, the design of all equipment installed must be safe to operate and maintain without compromising performance. Vendors are selected with great care to ensure safe installation and commissioning work and full compliance with all our safety requirements and expectations. All works required on-site will be carried out in full compliance with all of our safety requirements and expectations. Supporting Documents and Models List of all relevant documents (including relevant policies and consultant reports) taken into account in estimating project costs and describing anticipated deliverability. Report on Islington Substation High Impact Low Probability (HILP) Event Study Report on Bunnythorpe Substation High Impact Low Probability (HILP) Event Study Transmission Tomorrow (https://www.transpower.co.nz/resources/transmission-tomorrow). SP03 - Site Strategy – Islington substation 6
© Copyright 2026 Paperzz