CENTER CITY CONNECTOR STREETCAR CONSTRUCTION SCHEDULE 2017 Q1 Q2 Q3 2018 Q4 Q1 Q2 Q3 2019 Q4 Q1 Q2 Q3 Q4 Utility Construction - Phase 1 Gas relocations (PSE) - Sections of 1st/Jackson to 1st/Marion Water and sewer work (SPU) - 1st/Jackson to 1st/Madison Utility Construction - Phase 2 CENTER CITY CONNECTOR - UTILITY CONSTRUCTION PHASE 1 SPRING 2017 Before the Center City Connector Streetcar track construction can begin, water main, sewer, electrical, and natural gas utilities must be relocated and replaced along the future streetcar route. This work will provide more reliable and resilient utilities for customers and allow better access to those utilities after the new streetcar tracks are built. The first phase of utility work will start in 2017 and will be focused in Pioneer Square. Water, sewer, electrical, and private utility work - 1st/Madison to Stewart/6th Streetcar Construction WHAT ARE THE BENEFITS? Streetcar track construction (SDOT) - 1st/Jackson to 1st/Seneca Streetcar track construction (SDOT) - 1st/Seneca to Stewart/6th Note: We will have more to share about what to expect during the second phase of utility relocations and streetcar construction as that work gets closer. HOW WILL BUSINESSES BE SUPPORTED DURING THIS WORK? The City is committed to working closely with businesses and residents along the alignment during construction. Proactive outreach and communication is already underway and will include events, small group meetings, door-todoor outreach, fliers/mailers to businesses when updates are needed, regular website updates, phone calls, a 24/7 hotline, and more. Crews will maintain business access throughout construction and creative signage will help direct customers to local businesses. Sidewalks will remain open during construction except in small sections on a temporary basis. The Small Business Development team at the Office of Economic Development has business consulting services available to support small businesses along the route. Contact us for more info. Improved water, sewer, drainage, electrical, and natural gas services Improvements to all-way scramble intersections at Pike, University, and Cherry streets will designate pedestrian crossings more clearly Improvements at all intersections and corners will enhance the pedestrian experience and ensure ADA access The new streetcar will run every 5 minutes at peak times and will connect more people to 1st Ave to live, work, shop, and play WE WANT TO KEEP YOU INFORMED! • Sign up to receive project updates at seattlestreetcar.org/centercity.htm • Contact the project team at [email protected] or 206-615-1070 This document describes the Center City Connector streetcar project utility construction. To receive this information in other languages, large print, Braille, in electronic text, or other accessible formats, please call (206) 615-1070. Este documento describe el proyecto del tranvía Center City Connector. Está disponible en español. Para recibir una copia en español, por favor llame al (206) 615-1070. Tài liệu này mô tả dự án Xe Điện Center City Connector. Tài liệu có sẵn bằng tiếng Việt. Để nhận được bản sao bằng tiếng Việt, xin vui lòng gọi số (206) 615-1070. 此文件詳細介紹了有關 Center City Connector (市中心內線電車)有軌電車新系統的項目。此信息可提供繁體中文的 版本。如需繁體中文的版本,請致電 (206) 615 1070。 NATURAL GAS UTILITY WORK WATER MAIN AND SEWER UTILITY WORK When is the natural gas utility work? When is the water main and sewer utility work? Occidental Ave S Alaskan Way Viaduct Occidental Square S Main St E LIN ST FIR ST HI LL ST T GS IN SK S Jackson St 2nd Ave S 1st Ave S What are the impacts and how will impacts be minimized? Relocating water and sewer lines is a major undertaking. The City will work to minimize impacts during construction. Businesses and residents can expect: PSE will work to minimize impacts to neighbors, the environment, • Some work may require a temporary disruption Safety is our top priority when it comes to designing, and traffic during construction. Businesses and residents can in service to natural gas customers. If a natural constructing, operating and maintaining a natural expect: gas outage is necessary, a PSE representative will gas system that serves more than 800,000 PSE coordinate directly with affected customers. customers. We are committed to listening to our • Temporary traffic impacts, such as lane closures and limited customers, maintaining an informed and open access to on-street parking 2017 work includes: conversation about our work, and being responsive to o Laneofand parking restrictions be limited • Relocation intermediate pressure (IP)will natural gas to when customer needs. crews are working line along S Jackson St between 1st Ave S and 2nd PSE monitors over 26,000 miles of natural gas pipeline Ave S (expected June 2017) across six counties in our service area. Learn more • Some night work may be required • Replacement and relocation of four service regulators about natural gas safety at pse.com/safety. o If necessary, PSE will follow all applicable city along 1st Ave S between Columbia St and S Main St requirements (expected June 2017)regarding acceptable noise levels at night • •Relocation of may intermediate (IP) natural gas in service to Some work require apressure temporary disruption line alonggas 1st customers Ave between Madison St and Yesler natural Wayoand 1stgas Aveoutage S between S Washington Strepresentative If aalong natural is necessary, a PSE and S will Maincoordinate St (expected July to August 2017) directly with affected customers To learn more, visit pse.com/seattlecore Call 1-888-404-8733 to leave a voicemail for the project team. Example of PSE natural gas relocation work Email [email protected] with your questions and comments pse.com/seattlecore Jackson to Main PROPOSED WATER AND SEWER WORK SECTIONS What are the impacts and how will impacts be minimized? Construction (cont.) Safety seattlestreetcar.org Main to Yesler 99 3rd Ave S S Washington St Yesler to Columbia SJ AC KS ON Yesler Way Columbia to Marion SM AIN ST Seattle Ferry Terminal Note: Additional sections of IP natural gas pipeline along 1st Ave between Stewart St and Seneca St will need to be relocated in 2018. More details about this work will be shared closer to construction. 1S TA VE SW AS HIN GT ON t sS me Ja 99 WA Y e Av Segment 2: Section of IP natural gas line to be relocated in July to August 2017 JAMES ST y err Ch Segment 1: Section of IP natural gas line to be relocated in June 2017 St CHERRY ST Natural gas service regulator to be relocated and replaced St COLUMBIA ST ia mb lu Co Legend MARION ST t 1s ve dA 2n e Av ay nW ka s Ala e Av rio Ma 3rd rn ste We t nS LE R 5 St MADISON ST on dis Ma Contracting crews hired by the City will install a new water main, reline the existing sewer main, and make drainage improvements. We expect this work to occur from fall 2017 to the end of 2018. SPRING ST S St SENECA ST ca e en The first phase of water and sewer utility relocation work is between Jackson and Marion streets. The map below shows the proposed work sections. Some sections may happen simultaneously to speed up overall work. We will know more detail on the sequence of work by section as we get closer to construction. YE S Puget Sound Energy (PSE) expects to start their first phase of natural gas utility relocation work in June 2017 and wrap up in August 2017. Where is this work? • Temporary water outages o Seattle Public Utilities (SPU) will work with residential and business customers to determine the best times for water outages o SPU will provide advance notification to customers • Most parking will be restricted along 1st Ave and load zones will be shifted to side streets o SDOT is working closely with businesses and resident buildings with the goal to replace load zones 1 for 1 within one block of the current location; we will implement load zone changes before the work starts • We are working with King County Metro to coordinate bus routes and detours during construction • Northbound lanes on 1st Ave will be closed to through traffic between Jackson and Cherry streets for most of this work starting in fall 2017 o This is to allow space to preserve the London Plane trees in the center median o We will work to keep a southbound lane open during the day with intermittent closures during nights and weekends o There will be intermittent northbound local access while crews move work zones and complete sections • Multiple intersection closures o Intersection closures will take place at night and on weekends Example of water main installation
© Copyright 2024 Paperzz