Tivat International Airport

Airports of Montenegro
General informations
 Airports of Montenegro is a public enterprise established by the
Government of the Republic of Montenegro in 1999.
 Two international airports (Podgorica and Tivat).
Technical characteristics
Podgorica International Airport (TDG):
 Has a single runway which is 2,500m in length long and 45m wide;
 The taxiways at Podgorica airport are, for the most part, 15m wide;
 Capacity:1.000.000 pax/year.
 The footprint of the existing terminal is approximately 5,500m2;
 The cargo facilities are located south of the fuelling station and the
main landside access road;
 The remote technical apron areas are accessed from taxiway Papa,
providing approximately 18,000m2 apron areas;
Technical characteristics
Tivat International Airport (TIV):
 Has a single runway which is 2,500m in length long and 45m wide;
 The passenger apron is approximately 25,000m2 with self manoeuvre
parking for six Code C and one Code D aircraft;
 The taxiway widths are 25m and 20m respectively;
 Capacity:1.000.000 pax/year.
 The terminal at Tivat was completely refurbished in 2006 and has a
total internal area of approximately 4,050m2;
Aircraft and passenger traffic


Number of aircraft and passengers permanently increase in last years, despite
global economic crisis.
In 2011 record number of passengers is served on Podgorica and Tivat airports
(1.258.835 passengers).
Airports of Montenegro Master Plan

Sets out a physical development strategy for Podgorica and Tivat airports for the period
2011to 2030 with sequenced improvements to capacity and service quality in response
to forecast demand;

The document outlines a long range, orderly direction for development which
will yield a safe, efficient, economical and environmentally acceptable airport
system for Montenegro. It provides a two phased outline for development and
gives Airports of Montenegro and government advance notice of pending
needs to aid future policy formulation, budgeting and integration;
Master plan define projects for two periods: short term period (until 2017) and
long term period (2017-2030).

Master plan projects
In short term and long term periods will be necessary to develop following projects at both
airports:

Extension of runway;







Increase capacity of passengers terminals;
Increase apron capacity;
New parking positions for general aviation;
Taxiway widening;
Relocation of fuel interceptors (incl. tanks);
Expansion of air cargo facilities;
New car parking positions and Supporting Facilities (hotel, offices, etc.)
Financing of Master plan projects
Podgorica Airport
 Short time period - 39.956.700 euro;
 Long term period - 47.860.325 euro;
In total: 87.817.025 euro.
Tivat Airport
 Short time period - 22.635.836 euro;
 Long term period – 53.416.050 euro;
In total: 76.051.886 euro.
Master plan projects for Podgorica Airport
Podgorica - Agreed Master Plan
Short Term Developments
Item
Terminal (m2)
- New
- Integrate / Amend Existing
Apron (m2)
Taxiway Widening (Shoulders) (m 2)
Runway Shoulders (m 2)
Earthworks & Drainage
Fire & Rescue Access Road (m 2)
Relocate Fuel Interceptors (incl. tanks)
GSE Parking & Facilities (incl. shelter)
Car Park & Forecourt (m 2)
Fuel Farm Upgrade
Supporting Facilities (e.g. offices, substations)
Unit Rate
€ 1,500
€ 500
€ 120
€ 45
€ 45
10% paving costs
€ 30
Nominal Sum
Nominal Sum
€ 45
Nominal Sum
Nominal Sum
Quantity
12,500
5,500
11,500
58,000
36,000
1,000
9,000
Cost
€ 18,750,000
€ 2,750,000
€ 1,380,000
€ 2,610,000
€ 1,620,000
€ 561,000
€ 30,000
€ 150,000
€ 300,000
€ 405,000
€ 1,000,000
€ 600,000
€ 30,156,000
Sub-Total
Contingency
Consultancy Fees
€ 7,539,000
€ 2,261,700
25%
7.5%
€ 39,956,700
Total Short Term Developments
Long Term Developments - Master Plan
Terminal (m2)
Apron (m2)
Taxiway (m2)
Shoulders (m 2)
Earthworks & Drainage
Car Park & Forecourt (m 2)
Fire & Rescue Training Facilities
Relocation of Fuel Farm
Expansion of Air Cargo Facilities (m 2)
Maintenance Facilities Development (m 2)
Police Station (m2)
Local Roads (m 2)
Airfield Security Fence (m)
€ 1,500
€ 120
€ 90
€ 45
10% paving costs
€ 45
Nominal Sum
Nominal Sum
€ 800
€ 800
€ 1,200
€ 45
€ 90
12,500
27,500
26,000
9,000
18,000
1,500
4,000
1,000
2,500
1,100
€ 18,750,000
€ 3,300,000
€ 2,340,000
€ 405,000
€ 604,500
€ 810,000
€ 100,000
€ 4,000,000
€ 1,200,000
€ 3,200,000
€ 1,200,000
€ 112,500
€ 99,000
€ 36,121,000
Sub-Total
Contingency
Consultancy Fees
25%
7.5%
€ 9,030,250
€ 2,709,075
€ 47,860,325
Total Long Term Developments
Total
€ 87,817,025
Master plan projects for Tivat Airport
Tivat - Agreed Master Plan
Short Term Developments
Item
Temporary Terminal (m2)
Apron (m2)
Taxiways (m2) (incl. GA apron)
Shoulders (m2)
Earthworks & Drainage
AGL & Power Upgrade for Instrument Ops
Integration of ATC, Fire Station & Baggage Services
GSE Facilities
Sea Rescue Facilities
Car Park & Forecourt (m2)
Airfield Security Fence (m)
Unit Rate
€ 850
€ 120
€ 90
€ 45
10% paving costs
Quantity
5,000
16,000
44,500
77,700
1 No.
Nominal Sum
€ 45
€ 90
1 No.
1 No.
10,000
3,000
Cost
€ 4,250,000
€ 1,920,000
€ 4,005,000
€ 3,496,500
€ 942,150
€ 500,000
€ 1,000,000
€ 150,000
€ 100,000
€ 450,000
€ 270,000
€ 17,083,650
Sub-Total
Contingency
Consultancy Fees
€ 4,270,913
€ 1,281,274
25%
7.5%
€ 22,635,836
Total Short Term Developments
Long Term Developments - Master Plan
Terminal (m2)
Apron (m2)
Runway Starter Extension (m2)
Earthworks & Drainage
GSE Facilities
Local Roads (m2)
Supporting Facilities (e.g. offices, substations)
Fire Station
Car Park & Forecourt (m2)
Airfield Security Fence (m)
€ 1,500
€ 120
€ 90
10% paving costs
€ 45
Nominal Sum
Nominal Sum
€ 45
€ 90
16,000
73,000
22,000
1 No.
35,000
18,000
3,500
€ 24,000,000
€ 8,760,000
€ 1,980,000
€ 1,074,000
€ 300,000
€ 1,575,000
€ 500,000
€ 1,000,000
€ 810,000
€ 315,000
€ 40,314,000
Sub-Total
Contingency
Consultancy Fees
25%
7.5%
€ 10,078,500
€ 3,023,550
€ 53,416,050
Total Long Term Developments
Total
€ 76,051,886
Berane Airport
•Total Start up Passenger Potential: 35.000 pax/year;
•Berane Catchment Area Population: 170.000 (including neighbor cities);
•Coverage Area, Country’s North Region;
•Distance to Country’s Existing Operational Airports;
 Podgorica Int. Airport: 145 km (driving distance);
 Tivat Int. Airport: 230 km (driving distance);
 Foreseen Investment Amount: Euro 15.000.000.
Legal framework in the civil aviation area between
Montenegro and Republic of Turkey


Air Services Agreement between the Government of Montenegro and the
Government of the Republic of Turkey (ASA);
Memorandum of Understanding between the Government of Montenegro and the
Republic of Turkey on Cooperation in Enhancing Cooperation in Civil Aviation
Infrastructure and Industry - enhance the cooperation in this field by attracting
investors interested to invest in the realization of joint development projects at the
airports of Podgorica and Tivat, airport Berane, as well as the national air carrier
Montenegro Airlines (signed on 14 March 2012).