IR design update MDI (and IR) Summary M. Sullivan SuperB General Meeting Perugia, Italy June 15-20, 2009 1 SuperB Gen meeting June 15-20, 2009 IR design update Outline • Presentations in the MDI session – – – – – IR beam pipe SVT and beam pipe Shielding and QD0/QF1 HOM IFR backgrounds Sullivan Bosi Paoloni Novokhatski Cibinetto • IR topics this meeting – SVT • L0 • L1-4 – Cryostats and SVT Assembly – Energy change – Next IR design 2 SuperB Gen meeting June 15-20, 2009 IR design update MDI presentations • Sullivan presented the latest thoughts on the IR beam pipe and Filippo Bosi presented an SVT perspective on the IR beam pipe – Magic flange – a vacuum connection that can be disconnected that is between the cryostats – After looking at all of the “magic flange” designs we realized that these designs rely on the removal of one of the cryostats first, i.e. one could get to the flange either with long tools or with hand wrenches directly. – The Cornell design is most like a true magic flange that can be disconnected with the cryostat present – however the design has o-rings – Come back to this topic in the assembly discussion 3 SuperB Gen meeting June 15-20, 2009 IR design update IP beam pipe Plan view Side view 4 SuperB Gen meeting June 15-20, 2009 IR design update MDI presentations (cont.) • Filippo presented current thinking on the beam pipe from the SVT group – Perhaps 300 um thick Be – Au layer most likely on the inside (~4 um) – Cooled at the ends or cooled with a very thin layer of liquid • How much power can we expect? • PEP-II had to cool ~500 W after the extra cooling was added to the bellows at each end • Decided as a working assumption to design for 200 W 5 SuperB Gen meeting June 15-20, 2009 IR design update HOM • Sasha Novokhatski showed a work in progress toward calculating the HOM heating for the IR – He observed that we are making cavities in the region between 3 and 6 m – We will want to install absorbers in this area – There will obviously be HOM power in the IP region from the joining of the two beam pipes to one 6 SuperB Gen meeting June 15-20, 2009 IR design update The Present Design 300 DC 200 LER HER QD0 B0 B0 100 mm -100 QF1 QF1 0 B0 B0 -200 300 mrad -300 -7.5 7 5 -2.5 meters 0 BaBar foreward door 200 mrad 2.5 5 M. Sullivan Feb. 12, 2009 SB_IT _ILC_P4_SR_7_5M 7.5 SuperB Gen meeting June 15-20, 2009 IR design update S. Novokhatski 8 SuperB Gen meeting June 15-20, 2009 IR design update Shielding and backgrounds • Eugenio showed the latest on QD0 and QF1 as well as recent work on shielding the DCH from the beam – The shielding became a point of discussion – A large tungsten shield • Weight • Who or what has to hold up this weight – SuperB is very different from PEP-II • PEP-II had a shield around the beam pipe that was at least 10 cm of Fe thick (the permanent magnets) • Eugenio has some first data runs of various backgrounds • Gianluigi Cibinetto presented concerns for neutron backgrounds for the IFR and showed that the neutron rate found for BaBar was already too high for the new IFR detectors 9 SuperB Gen meeting June 15-20, 2009 IR design update IR + SuperB Geant4 Model • • IR P3 Modeled in Geant4: beam pipe and magnetic fields Preliminary look at Luminosity backgrounds: – – – – 10 Beam strahlung from 1400 bunch crossing ( ~6.2 10-6 sec ) 400k evt. pair production ( ~53 10-6 sec ) Neutron production included in the sim. Analysis of this data just started SuperB Gen meeting June 15-20, 2009 IR design update Future activities • Bigger sample production (including Touschek and beam gas contributions): – • – – Shielding thickness optimization (cost benefit considerations) Shielding external design optimization Physics window beam pipe optimization Study neutron production downstream QF1 Primary reflected by the Tungsten shielding 11 SuperB Gen meeting June 15-20, 2009 IR design update Preliminary Suggested Shielding Scheme Actual shield simulation is 3 cm thick 12 SuperB Gen meeting June 15-20, 2009 IR design update IR topics • SVT and L0 – L0 attached to the central chamber – SVT mounts to the beam pipe that is part of the cryostats – Very similar to PEP-II • SVT access – Want access to the SVT on a week time scale (instead of months) • We are presently defining the 300 mrad line as the treaty line between machine and detector 13 SuperB Gen meeting June 15-20, 2009 IR design update SVT and Cryostats • Fast access to the SVT – KEKB does this and if we plan for this up front we can do this too – We need to put the nearby beam components on rails so we can easily move them out of the way also get the components back into position without having to survey them – According to the previous discussion we do not have an easy way of disconnecting the flanges between the two cryostats – So propose putting the SVT and cryostats together outside of the detector and then sliding the assembly into the detector – 14 SuperB Gen meeting June 15-20, 2009 IR design update How to do this? Backward side needs more thought • We have decided that the cryostats have to be mounted on sturdy supports that mostly likely go down to the floor – There are large expulsion forces and we want minimize vibrations – Now there are also these tungsten sleeves that need to be supported – Propose mounting the W sleeves on the cryostat supports and leave enough room inside the W sleeve for something like rails or a trough that we can use to slide the SVT and cryostat assembly in and out of the detector – This gives us quick access to the SVT (1-4) and to L0 and to the Be beam pipe and to the permanent magnets – If this is planned carefully we disconnect nothing – Needs plenty of thought and attention to details 15 SuperB Gen meeting June 15-20, 2009 IR design update Energy change • The quick access to the SVT gives us also quick access to the permanent magnets • This allows us to reconfigure the machine for other energy running relatively quickly by removing or altering the PMs • It probably still takes a week to 10 days for a complete turn around so we don’t want to do this too often 16 SuperB Gen meeting June 15-20, 2009 IR design update Next IR design • Try to make QD0 as easy as we can without changing too much – This is one of the hardest magnets to build so we should at least make it look better on paper – Stay with our philosophy of using the most aggressive design parameters • 7x4 beam energies (larger energy asymmetries are harder) • Smallest beta*s • Largest emittances – Lengthen the cryostat some to cover more of the detector solenoid field with compensating solenoids – perhaps move QF1 out some more 17 SuperB Gen meeting June 15-20, 2009 IR design update Summary • Many good and detailed discussions about the machine and detector interface • Integrating plans are being hatched that look interesting – Quick access – Tungsten shields – Cryostat supports • There will be many more issues to resolve as they surface • IR design work will continue to use aggressive machine parameters in developing new iterations • Good progress! 18 SuperB Gen meeting June 15-20, 2009
© Copyright 2026 Paperzz