Safety in Mines Research Advisory Committee Final Project Report Technology transfer of the risk assessment tool for rock-related risk issues A.v.Z Brink Research Agency: CSIR: Division of Mining Technology Project Number: SIM 03 02 01 Date: March 2005 1 Executive summary The outcome of earlier SIMRAC projects, GAP 608 and Gap 714 was a prototype software package that was a combination of an expert system approach for determining overall risk assessment, a risk control recommendation, and a basic Graphic Information System (GIS) approach for graphically overlaying input parameters and the output risk. The expert system used a Bayesian probabilistic approach to combine various types of workplace-related information, a quantified seismological environment, and exposure of underground staff to provide an overall rock engineering (RE) risk rating. The risk assessment was dynamic in that it was recalculated each time any input parameters changed, for example each time a seismic event was recorded in the area of interest. The objective of this project was to provide clear documentation of an actual application of a rock engineering risk assessment tool as developed earlier. As the validity of risk assessment cannot be shown by relating to specific short term incidents, the project attempted to evaluate the method after an extensive period of use with a large data set. This could not be achieved in real time because of severe limitations in access to real-time seismic data on mines, as well as system interfacing to an operational mine’s database for rock engineering parameters. The project ran a case study demonstration over two years on, primarily, seismological data. The continuous risk assessment on dynamically changing input parameters was proven. The case study allowed for correlation between assessed risk and the subsequent hazards experienced. The case study included a continuous assessment of RE risk on a mining section on the Ventersdorp Contact Reef (VCR) in the Far West Rand. Over a time window of one year, a significant majority of the larger events (Magnitude > 1) in the immediate vicinity of the operating panels were preceded by a noteworthy increase in the risk levels. Similarly, a significant minority of all high risk levels did not manifest into a relatively large event. These conclusions were subjective and reached by viewing the risk display over a period of time. An objective and quantified measure of determining success rate was not proposed in this project. Absolute quantification of success rate should be possible, but then again, the implication is that this concept is being presented as a seismic prediction tool, rather than RE risk assessment. The project may be criticised in that the non-seismic aspects of RE risk assessment did not contribute to the case study evaluation. The interfacing problems to a mine’s RE database did not allow for the inclusion of real non-seismic data and the researcher had to resort to simulated data. However, the concept of using continuously changing input evidence whilst determining the probability of an output hypothesis being true, was well proven. The software platform used was appropriate for development and proof of concept, but an operational tool, interfacing to mine systems and user interfacing, still needs to be developed. The project output is compiled on a CD, comprising all the evaluation coding, input data and results. Future software implementation of the now proven concept should be undertaken by a professional software developer, without needing to understand the basic principles employed in this demonstration/evaluation version. The remaining outstanding aspects of this potentially useful tool are mainly the real-time data and user interfacing. It is recommended that these aspects be addressed in a future project. 2 Acknowledgements The author would like to express his gratitude to the Mine Health and Safety Council for financial support of project GAP 03 02 01 and their patience. Malcolm Drummond from GeoVision is acknowledged for his contribution in developing the visualisation platform for this project. Dr Steve Spottiswoode are recognised for his valuable comments and probing questions. 3 Table of contents Executive summary ......................................................................................................... 2 Table of contents ............................................................................................................. 4 List of figures ................................................................................................................... 5 1 Summary of related earlier SIMRAC work (GAP 608 and GAP 714) ................. 6 1.1 Introduction .................................................................................................................. 6 1.2 Development of a software tool for the integrated assessment of rock engineering risk .................................................................................................................................... 7 1.3 Development of probabilistic risk assessment using an expert system philosophy ....... 8 2 Implementation of an expert system approach for risk assessment. .................. 9 2.1 Defining the input parameters for RE risk assessment ............................................... 10 2.1.1 The prior probability .......................................................................................... 10 2.1.2 The individual probability parameters................................................................ 11 2.1.3 Temporal change in event rate as an input parameter towards RE risk assessment ...................................................................................................... 11 2.1.4 Apparent Volume as an risk indicator of possible rock burst damage................ 12 2.1.5 Energy Index as an risk indicator of possible rock burst damage ...................... 13 2.1.6 Peak ground motion as an risk indicator of possible rock burst damage ........... 14 3 Evaluation of the risk assessment software. .................................................... 16 3.1 Incorporating rock mechanics parameters ................................................................. 16 3.2 A case study on continuous risk assessment ............................................................. 17 4 Conclusions ..................................................................................................... 18 5 References ....................................................................................................... 19 Appendix A ...................................................................................................................... 1 Appendix B .................................................................................................................... 31 4 List of figures Figure 1.1 Production losses as result of seismicity as a function of the magnitude of the damaging seismic events .................................................................................... 7 Figure 1.3 A schematic of the integrated approach towards risk assessment .......................... 8 Figure 2.1 Rate of change in the number of events per time unit, with the red contour relating to a doubling in the event rate. .............................................................................. 12 Figure 2.2 Rate of change in the Apparent Volume as observed in a short-term long-term ratio .......................................................................................................................... 13 Figure 2.3 As in Figure 2.1 and Figure 2.2 but this time the rate of change in Energy Index is overlain on the mining operation........................................................................ 14 Figure 2.4 A plot of the number of times during the previous 30 days that an estimated peak particle velocity of .2 m/s was exceeded ............................................................ 15 Figure 3.1 Total working area to be considered in terms of risk to the underground personnel. The area includes the active panels and the back areas ................................... 16 Figure 3.2 The process of linking a geographical area of an active panel to a set of attributes 17 5 1 1.1 Summary of related (GAP 608 and GAP 714) earlier SIMRAC work Introduction The primary output of this project is to provide clear documentation of actual applications of a rock engineering (RE) risk assessment tool on gold and platinum mines. In order to do this, reference is needed to the earlier work that resulted in the concept and development of a RE risk assessment tool to be evaluated. GAP 608 (Brink et al., 2000) reviewed all applicable work in South Africa that was carried out with the aim to define various methods to ‘quantify’ hazard and/or risk in the context of the rock engineering stability of the rock mass. GAP 714 (Brink et al., 2002) developed a ‘beta’ version of a software package employing an expert system approach in combining these various hazards and risk parameters. A number of SIMRAC projects have addressed the issue of hazard and/or risk in gold and platinum mines, with a specific emphasis on the hazard and/or risk posed by rock-related incidents. Often, the distinctions between hazard and risk were unclear. It advisable to review the respective definitions of hazard and risk from Mine Health and Safety Act No 29 of 1996: Hazard is a physical situation, object or condition, which, under specific circumstances has the potential to cause harm, whereas risk is a measure of the likelihood that some specific harm, arising from an incident (a particular hazard). The generic equation: Risk = Hazard * Vulnerability ( 1-1) Was extended by Menoni et al.,1997, to: Risk = Seismic Hazard * Induced physical hazard * Systemic Vulnerability ( 1-2) where Induced physical hazard = rock related damage in working place, with the potential to cause injuries, and triggered by ground motion; support failure; or fall of ground. (definition extended by Brink et al., 2000) Systemic Vulnerability = Exposure of people; economic vulnerability; quality of information. (definition extended by Brink et al., 2000). The first term, Seismic Hazard, was subsequently also extended to included probability of occurrence. For this reason it could be argued that it is rather Seismic Risk. The final risk formula developed for software implementation could therefore be written as: RE risk = Seismic Risk * Systemic Vulnerability ( 1-3) In this case Seismic Risk is the probability that a specific working place can experience damage as result of a seismic event within a specified time period (that is Seismic Hazard and Induced physical hazard as in Equation (1-2)). The Systemic Vulnerability is a combination of numerous weighting factors. RE risk is a unitless parameter that now quantifies the rock related risk in a working place at a specific time. The risk may be specific as the risk of injury and/or fatality or the economic risk (loss of equipment or production) or both. Being a unitless parameter, RE risk has a 6 disadvantage in that the comparison of different areas on a mine, or the same area at different times, is not possible if exactly similar parameters are not used as input. The deliverable of GAP 714 was a prototype software package that is a combination between an expert system approach for determining overall risk assessment, a risk control recommendation, and a basic GIS approach for graphically overlaying input parameters and the output risk. The expert system uses a Bayesian probabilistic approach to combine various types of workplace-related information, a quantified seismological environment, and exposure of underground staff to provide an overall RE risk rating. The risk assessment is dynamic, in that it is recalculated each time any input parameter changes - for example, every time a new seismic event is recorded in the area of interest. RE risk assessment should, however, not be seen as an alternative form of rock burst prediction. The authors of the report on GAP 714 (Brink et al., 2002) had the opportunity to evaluate the various risk assessment methodologies and tools during their consultation with the mining industry. Figure 1.1 shows the distribution of production shifts lost relative to the size of the damaging seismic events. It cannot, of course, be concluded that Mag 1,5 to 2,0 events are a greater hazard than a Mag 3,5 event but that, with their shorter reccurrence time, the former, in fact, pose a greater risk. It was clear that the RE risk, and even seismic risk does not correspond exclusively to the few very large seismic events. Production risk % of shifts lost 1.0 0.9 0.8 0.7 0.6 0.5 0.4 0.3 0.2 0.1 0.0 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 4.50 Magnitude Figure 1.1 Production losses as result of seismicity as a function of the magnitude of the damaging seismic events (from Lenhardt, 1998) 1.2 Development of a software tool for the integrated assessment of rock engineering risk An objective of the earlier work was to develop computer code that would integrate various seismic and non-seismic hazard and/or risk parameters in a single risk assessment. A further objective was to facilitate this integration through an expert system approach. Figure 1.2 schematically demonstrates the approach used in the development of the code for RE risk assessment. The non-seismic (or general rock mechanics) data tends to be linked to face names rather than geographic positions. Similarly, the seismic data is purely geographical, with no links to the actual face names. 7 RE database + face files Expert system evidence probabilities Input matrix 100x100x100 Expert system evaluation of input evidence and display of output risk hypothesis Seismic database Output display array 100x100 Figure 1.2 A schematic of the integrated approach towards risk assessment Basically, the mining configuration is overlain with a 1 km x 1 km grid with a grid resolution of 10 m x 10 m. Each grid element has its own attributes describing the various static risk conditions (typically the conditions describing the vulnerability of the excavation) and the dynamic conditions (parameters describing the seismicity as experienced at that specific grid element). Each grid element allows for 100 attributes. The software, therefore, has to manage an overall risk matrix with dimensions of 100 x 100 x 100. Visualisation of input and output parameters is accomplished through extensions to a basic 2D data-integration environment developed by GeoVision. The environment offers the ability to dynamically view several spatially related datasets together in a single window. Special pipelines were also developed by GeoVision for the import of mine plans, creation and/or editing of static input datasets (input rasters), and the dynamic import of spreadsheet data (output raster). 1.3 Development of probabilistic risk assessment using an expert system philosophy The Bayes' Theorem was adopted as an expert system philosophy for RE risk assessment. The basic concept of this philosophy is that a hypothesis should be developed that is tested against some evidence. In this case the hypothesis states that a rock related incident (rock fall or rock burst damage) would occur within the next eight hours. A prior probability, P(H), is set. This is the probability that such a rock-related incident may occur during the next eight hours (the probability of the hypothesis being true) without any associated evidence. Evidence associated with the hypothesis being true, is for example, the observation that a high event rate is prevailing. The probability of observing such evidence, that is a high event rate, whilst the hypothesis is also true, p(E|H) is determined from previously observed information. Similarly, the probability of observing the evidence, but with a hypothesis that is not true, p(E|~H), is set. Based on Bayes' Theorem, the probability of observing the hypothesis H if the evidence E has been observed is the probability p(H|E). p( H | E ) p( E | H ) p( H ) p( E | H ) p( H ) p( E |~ H ) p(~ H ) ( 1-4) 8 (p(H) is the prior probability of the hypothesis being true and p(~H) the prior probability of the hypothesis not being true.) Similarly, the probability of observing the hypothesis H if the evidence E has not been observed, p(H|~E): p( H |~ E ) p(~ E | H ) p( H ) p(~ E | H ) p( H ) p(~ E |~ H ) p(~ H ) ( 1-5) The initial importance (or Rule Value) of each item of evidence is given as: RV p( H | E) p( H |~ E) ( 1-6) A typical expert system will have a number of possible hypotheses and even more items of evidence that can be associated with these hypotheses. For the purpose of testing the hypothesis of a large rockfall and/or burst within the next eight hours, the expert system only considers this single hypothesis, tested against the available items of evidence. The main advantage of employing an expert system philosophy is that it can cater for uncertainties. The expert system philosophy, from XMaster®, (Chris Naylor Research Limited, Naylor, 1998 and Naylor, 2000) allows for the actual response to whether specific evidence is observed, to be between a 'yes' and a 'no'. It is possible to calculate a new posterior probability for each hypothesis, conditional upon the response. p( H | R) p( H | E ) p( E | R) P( H |~ E ) p(~ E | R) ( 1-7) With a user response of 'yes' then p(E|R) would be 1 because there would be certainty that the evidence had been identified. Similarly, with a user response of 'no' then p(E|R) = 0 if there were certainty that the evidence had not been identified. A 'do not know' will result in p(E|R) =0.5, with all other situations resolved by interpolation. The next step is to calculate the final posterior probability of the hypothesis being true if various bits of evidence of various degrees of confidence are observed. The simplest approach is to calculate the final posterior probability by the successive application of the appropriate formulae for a single item of evidence to each of the items of evidence in turn. Initially, the hypothesis starts off with the given prior probability. This prior probability is updated by the application of one item of evidence, which may or may not be observed with a given degree of uncertainty, to produce a new posterior probability. This new posterior probability is then used as the new prior probability for a re-application of the same equation to the next item of evidence. The process continues in this way until all of the items of evidence have been accounted for. 2 Implementation of an expert system approach for risk assessment. The following parameters are combined through a probabilistic approach: The potential for significant ground motion in a specific excavation, the intensity of such ground motion, the vulnerability of the excavation, and the exposure and quality of data used as weighting factors. 9 To achieve this any parameter that can be shown to be relevant evidence that a specific hypothesis may be true, should be considered. The hypothesis in this case is that a rock related incident with the potential to cause injuries and/or fatalities might occur within the following shift. The code was developed to allow for up to ten seismic parameters to constitute the seismic risk. These parameters may be used as evidence to quantify the probability for a large ground motion at a particular point on or close to the reef plane. The respective position of the seismic events is given in 3-D but the risk evaluation is done on a 2-D plane of the mine workings. The seismic input parameters used are the respective changes in short term / long term ratio as observed in event rate, apparent volume and energy index. In adopting the Bayes’ Theorem expert system approach, the outcome that is hypothesised, is that a rock related incident might occur during the current or next shift within the boundaries of the grid resolution, i.e. 10 m. Smoothing is applied to include the input parameters of adjacent grid elements, which results in an effective resolution of about the dimensions of a typical panel length. 2.1 Defining the input parameters for RE risk assessment With reference to equation ( 1-4); p( H | E ) p( E | H ) p( H ) p( E | H ) p( H ) p( E |~ H ) p(~ H ) , the various input parameters need to be defined. 2.1.1 The prior probability The first input to the risk assessment process, is the prior probability, p(H). That is the probability that the hypothesised outcome will occur without any evidence being observed that either supports or rejects the hypothesis. p(H) is estimated by looking at all the related incidents in area of interest and over a period of time. The prior probability is then: p( H ) # of incidents (# of grid pnts) (# of shifts) ( 2-1) where # of incidents is the number of rock related incidents that caused physical harm; # of grid pnts is the number of grid elements included in the working areas; and # of shifts is the number of shifts during the review period. The test area selected was a mini-longwall on the VCR in the Far West rand comprising seven panels. The area was subdivided into a 1000 m by 1000 m area with a 10 m grid resolution. Seismicity for a period of one year was analysed (975 events with Mmin = - 0,5 and MMax = 3.) The number of events per grid point larger than Magnitude 1, or even the number of such events that may influence a grid point, was too low to be able to quantify any changes in parameter behaviour. For the purpose of quantifying the prior probability, it was decided to group all the seismicity in this area. A total of 70 events larger than Magnitude 1 occurred in this area. The prior probability of an event happening during any eight hour shift is therefore the number of events/the number of shifts per year. The result for this area under consideration is a prior probability, p(H) = 0.064. 10 2.1.2 The individual probability parameters Each input parameter or piece of evidence is quantified in terms of the probability of observing the evidence with the hypothesis being true, p(E|H) , and the probability of observing the evidence, but with a hypothesis that is not true, p(E|~H). Equation ( 1-7) allows for the actual response to whether specific evidence is observed, being between a 'yes' and a 'no'. The specific individual parameters used were: Temporal change in event rate; Temporal changes in Apparent Volume; Temporal changes in Energy Index ; Number of PPV (peak particle velocity) exceeding a specific threshold. Each parameter is described and quantified in the following sections. 2.1.3 Temporal change in event rate as an input parameter towards RE risk assessment The concept of using a change in event rate was developed by Brink et al., (2001) for the application towards early warning of goafing at Moonee Colliery in Australia. The same concept was applied in this project. A short term event rate (for the previous ten events), versus a longer term event rate (for the previous fifty events) was used. Should a short term versus longer ratio of larger than two be observed, it was considered as a 100% positive indication that this specific input evidence was observed. The opposite would be a ratio of 0,5 implying a 0% indication that a change in event rate was observed. As before for prior probability, P(H), the same area and seismicity is used. The probability of observing the evidence (a high event rate ratio) with a true hypothesis (an event larger that Mag. 1) during the following shift is p(E|H) = 0,67. This means that 67% of the larger events were preceded by an event rate ratio of at least two. Similarly, the probability of experiencing a shift (eight hours) with the evidence being true, but with the hypothesis not being true, p(E|~H), was 0,016. In other words, during 1,6% of the total number of eight hours shifts the event rate parameter has exceeded the predetermined value, but no event larger than a magnitude 1 occurred during that, or the following shift. The Bayes Theorem input parameters for event rate is summarised in Table 2-1. Table 2-1 The input evidence as quantified for event rate. Parameter p(E|H) p(E|~H) Ryes Rno Event Rate 0,67 0,016 2,0 0,5 Should only event rate be used as input evidence, Figure 2.1 depicts the area of interest with the red contour value highlighting grid points that at the time of the ‘snap shot’ experienced an event rate ratio of more that two. 11 Figure 2.1 Rate of change in the number of events per time unit, with the red contour relating to a doubling in the event rate. 2.1.4 Apparent Volume as an risk indicator of possible rock burst damage Apparent Volume (m3) relates to the volume of rock with coseismic inelastic strain and is calculated as: (From Mendecki (1997)) VA = M/(c3A ) = M2 /(c3 GE) ( 2-1) where c3 =2 (a scaling factor) , M is the seismic moment, A is the apparent stress, G is the shear modulus and E is the released energy. Mendecki (1997) quantifies accelerated deformation through accumulated Apparent Volume, VA. , however, this project recognises accelerated deformation through the rate of change in Apparent Volume. Accumulated Apparent Volume, VA., may create the impression of accelerated deformation through an increased event rate with all events being similar as for Apparent Volume, whereas this project wanted to recognised Apparent Volume rate of change as unique input evidence. A 'short term / long term' Apparent Volume ratio is calculated. The ratio is calculated at each event occurrence and is the median of the Apparent Volume for the last 10 events versus the median for the last 50 events. As before with event rate, Apparent Volume as input evidence towards the hypothesis of a RE incident during the next shift has to be quantified. Table 2-2 Apparent Volume - quantified input evidence parameters Parameter p(E|H) p(E|~H) Ryes Rno Apparent Volume 0,5 0,14 2,0 0,5 Figure 2.2 shows the same events as in Figure 2.1, but now showing the rate of change in the Apparent Volume as observed in a short-term long-term ratio. The red contour implies a 'short term / long term' ratio of two. 12 Figure 2.2 Rate of change in the Apparent Volume as observed in a short-term long-term ratio 2.1.5 Energy Index as an risk indicator of possible rock burst damage The parameter Energy Index was also initiated by Mendecki, (1997) as a way of comparing radiated seismic energy from events of similar seismic moments. An event with Energy Index > 1 would suggest a higher than average shear stress at its location. The opposite applies when Energy Index is < 1. As before, for event rate and Apparent Volume, the Energy Index parameters are quantified as follows for the Bayes’ Theorem: Table 2-3 Energy Index - quantified input evidence parameters Parameter p(E|H) p(E|~H) Ryes Rno Energy Index 0,53 0,15 0,15 -1,0 As in Figure 2.1 and Figure 2.2, Figure 2.3 shows the rate of change in Energy Index as overlain on the mining operation. The scale ranges from -3 for blue, to +0,5 for light green. It can be inferred from this figure that there is some increase in the driving stress of the previous 10 events versus the longer term average, in the top part of the panel. 13 Figure 2.3 As in Figure 2.1 and Figure 2.2 but this time the rate of change in Energy Index is overlain on the mining operation 2.1.6 Peak ground motion as an risk indicator of possible rock burst damage In GAP 714 (Brink et al.,2002), a model was presented of peak ground velocities in the near to far field and applied it to data from a deep level mine. It was assumed that future seismicity is likely to be similar to historical seismicity. A single equation was developed to express peak velocity. The following were assumed: All seismic events occur on Brune-type circular slip zones in plan around each event location. The rock mass is elastic and homogeneous. Site effects and amplification at the skin of the stope are neglected. Models of seismic sources generally consider strong ground motion either in the near field or in the far field. Employing these models the peak velocity can be expressed as a single equation: v = (VS/G) * (r0/R/) ( 2-2) for R>=r0 where VS = shear-wave velocity, = static stress drop, R = hypocentral distance, r0 = source radius and G = modulus of rigidity (Described by McGarr (1991) and also applied by Brink et al.,(2002)) 14 2.1.6.1 Implementation of peak ground motion as risk parameter Figure 2.4 shows an example of the implementation of peak ground motion as a risk parameter. A grid with a resolution of 25 m was placed over the selected area. At each grid element all the seismicity in the area is evaluated for its respective peak ground motion at that point. An arbitrary threshold (say, 1 m/s) is set. The number of times that a grid element experiences a ground motion of more than the threshold is logged. It is clear that the highest values are experienced at the current face position. It is assumed that each grid element is, in fact, in an excavation, and a multiplication factor of 3 is used to allow for site amplification. The peak ground motion and the number of times that an excavation experience significant ground motions, can be linked to physical damage experienced in the excavation (Andersen et al, (1999)). Peak particle velocity (PPV) count, does not necessarily relate to the potential for experiencing a high PPV at a specific grid position, other than that the return time between incidents of high ground motion is shorter. The PPV count is used in this evaluation as an indicator of the vulnerability of the excavation to ground motion. A larger number of large ground motions should relate to the extent of seismic related damage in an area. A higher degree of earlier damage makes an area more vulnerable to the next higher level of ground motion. In Figure 2.4 the centre of the mini-longwall experienced the largest number of ground motions larger than 0,2 m/s. The power law distribution of PPV counts justifies the expectation that this area also would have experienced more large ground motions. Figure 2.4 A plot of the number of times during the previous 30 days that an estimated peak particle velocity of 0,2 m/s was exceeded For peak particle velocity the project is not attempting to recognise a change in the number of PPV counts larger than a preset threshold, and rather used the absolute number of PPV counts exceeding the threshold during the previous 30 days. Table 2-4 Input values for peak particle velocity counts larger than 0,2 m/s for the application of Bayes’ Theorem Parameters p(E|H) p(E|~H) Ryes Rno PPV count 0,8 0,5 3 0 15 3 Evaluation of the risk assessment software. The objective of this project was to provide clear documentation of actual application of a rock engineering risk assessment tool. This could not be achieved in real time because of severe limitations in access to real-time seismic data on mines, as well as system interfacing to an operational mine’s database for rock engineering parameters. The project conducted a demonstration on an ‘off-’line’ case study with two years seismological data as input. A subset of the results of this continuous risk assessment process is captured in Appendix A. The analysis and display software, as well as the seismic data are included in the attached CD (Appendix B). Although a grid resolution of 10 m x 10 m was used, event source size and location accuracy did not allow the process to uniquely link an event to a single grid position. A zone of influence around the event location was used. This zone of influence could be determined, for example, using source dimension, apparent volume or just a 1/(distance to location) relation. For the purpose of this proof of concept a fixed zone of influence of 100 m diameter was used. All the earlier mentioned evidence, namely event rate, Apparent Volume, Energy Index and ground motion is combined in estimating the probability of experiencing a rock related incident at a specific grid element during the next shift. 3.1 Incorporating rock mechanics parameters The earlier-mentioned input parameters were solely based on the 'dynamic' information and did not take into account the vulnerability of the excavation as described by parameters such as ERR, support quality and local ground condition. To incorporate the 'static' risk information, it was necessary to define the total working area, i.e. the active panels and the back areas. The total working area was defined in Figure 3.1. In this example the back areas were only considered in terms of the exposure of people. No specific risk attributes were allocated to any grid position. Figure 3.1 Total working area to be considered in terms of risk to the underground personnel. The area includes the active panels and the back areas The next step was to specify the input parameters to specific active panels. Panels are typically known by name rather that geographic position. A panel name and its associated attributes had to be linked to a specific geographical area. The output of this process is shown in Figure 3.2. Every panel, in terms of its geographical position, was now linked to the RE database. The 16 attributes described the vulnerability of the excavation to large ground motion and also include the exposure at a particular time of day as well as the more general 'Quality of information' (as described by Brink et al., 2002). Figure 3.2 The process of linking a geographical area of an active panel to a set of attributes 3.2 A case study on continuous risk assessment The probability approach leads to a large dynamic range in output levels and the linear display may give the impression of a insignificant risk in some areas. The risk levels as displayed in Appendix A uses a logarithmic scale. Appendix A depicts a series of events from 16 February to 2 March. Each figure represents a risk assessment based on the input evidence immediately prior to the event shown. The event parameters as well as the located position are shown. The scale on the right is used throughout the presentation. It is a logarithmic scale where full-scale relates to a 50% probability, with average weighting factors, that a rock-related incident will take place within the subsequent eight hours. The arrow indicates the position of the last event. The event parameters are shown on the figure. It can be noticed that distant events have a negligible effect on the probability of the RE incident in a particular area. In this application, an event more than 100 m away can only have an influence in terms of peak ground motion which in turn will only be significant should a major event occurs. By following the event sequence in Appendix A, it will be noticed that the first significant event occurred 22 February at 02:35. This event was not preceded by any increase in the assessed risk. A contributing factor to the low prior risk levels is the fact that this area is classified as back area with a three times lower exposure of people than in the stope areas. Within a day the risk in the top panel started to increase, to be followed by a Magnitude 2 event about fifteen hours later during the morning shift (24 February at 10:33). The risk in the top panel stayed high and extended to the neighbouring panel, where another event (Mag. = 1.7) occurred during the blasting time (24 February at 16:35). Another event (Mag. = 1) occurred during the next blasting time (25 February at 16:20). After a further two days the risk on these panels had return to normal. This sequence is just a ‘snap shot’ from of the two year’s data and is very representative of many similar sequences. 17 The input parameters to the expert system were primarily the temporal behaviour of the seismic event parameters. Accepting this, it therefore follows that should all event parameters be maintained but the event occurrence times be randomised, that the information contained in the temporal behaviour should be scrambled. The next sequence in Appendix A contains the same events, therefore the same event characteristics but now with a random time added and/or subtracted (+/- 120 hours) per event. The objective is to demonstrate the validity of the risk assessment process applied in the previous sequence. By scanning through this randomised sequence and comparing it with the previous sequence, the reader will recognise that the precursive risk indication has totally disappeared. This is a substantive proof of the validity of the engaged process. Over a time window of one year more than 80% of the larger events (Mag > 1) in the immediate vicinity of operating panels in the case study area, were preceded by a significant increase in the risk levels as determined by the expert system process. Similarly, less than 40% of all high risk levels did not manifest into a relatively large event. These levels were obtained subjectively by watching the risk display over this period of time. An objective and quantified measure of determining success rate was not proposed in this project. Absolute quantification of the success rate should be possible, but then again, the implication is that this concept is being presented as a seismic prediction tool, rather than a methodology to assess RE risk. 4 Conclusions The concept of integrated RE risk assessment was described and an initial version of the software was developed and used in a case study. This report can not fully describe or demonstrate the application of this code - in particular the dynamic display of information. For this purpose a series of output screen display were captured and presented in Appendix A. The case study included a continuous assessment of RE risk on a mining section on the VCR in Far West Rand. A significant majority of the larger events (Mag > 1) in the immediate vicinity of operating panels were preceded by a significant increase in the assessed risk levels. The deliverable of this project was an evaluation of a prototype software package. The project did not succeed in achieving a real-time evaluation because of a number of system interfacing constraints, specifically to the seismic input parameters. It has to be stressed that the objective of the project was not to provide a tool for the prediction of large seismic events, but to provide an integrated approach towards the dynamic assessment of the overall RE risk at a particular place in the mine; at a particular time; and with cognisance of the exposure of the underground worker to the inferred RE risk. Evaluation of the methodology proved to be difficult. It can only be properly evaluated through extended use in an operational environment. The original proposal intended to have the code tested in real-time on a Far West Rand mine and on a relatively deep platinum mine. It was not possible, and would have been rather ambiguous to define specific case studies and to claim a percentage success rate as in the case of prediction. The project can be criticised in that the non-seismic aspects of RE risk assessment did not contribute to the case study evaluation. The interfacing problems to mine RE data were the cause of this valid criticism. However, the concept of using changing input evidence that could influence the probability of an output hypothesis being true was well proven. A future software implementation of the proven concept should be achievable by a professional software developer, without this person needing to understand the basic principles employed in this demonstration/evaluation version. The important outstanding aspects of this potentially useful tool are mainly the real-time data and user interfacing. It is recommended that such an investment should be made. 18 5 References Andersen, L. and Daehnke. A. 1999. Final project report for internal and unpublished project, Deepmine 4.1.2. Brink, A.v.Z., Hagan, T.O., Spottiswoode, S.M., Malan, D.F. 2000. Survey and assessment of the techniques used to quantify the potential for rock mass instability, SIMRAC Report GAP 608, Department of Mineral and Energy Affairs, South Africa. Brink, A.v.Z., Hagan, T.O. 2002. Software tool for managing rock related hazards in South African mines, SIMRAC Report GAP 714, Department of Mineral and Energy Affairs, South Africa. Brink, A.v.Z. and Newland A.R. 2001. Automatic Real Time Assessment of Windblast Risk, ACARP project C8026, Australian Coal Association Research Program. Lenhardt, W.A. 1998. Zur Risikobewertung bergbauinduzierter Seismizität. Felsbau, 16, Nr. 1, 48-55. McGarr, A. 1991. Observations constraining near-source ground motion estimated from locally recorded seismograms, J. Geophys. Res., pp 16495-16508. Mendecki, A.J. 1997. Quantitative seismology and rockmass stability, in Seismic Monitoring in Mines, A J Mendecki (Ed.), Chapman and Hall, Cambridge, 1997. Menoni, S. Petrini, V. Zonno, G. 1997. Seismic risk evaluation through integrated use of geographical, ENV4 - CT96 – 0279, Istituto di Ricerca sul Rischio Sismico, Milano, Italy. Milev, A.M., Spottiswoode, S.M. and Noble, KR. 1995. Mine-induced Seismicity at East Rand Proprietary Mines, Technical Note, Int. J. Rock Mech. Min. Sci. & Geomech. Abstr., v32, no6, pp 629-632. Naylor, C. 1998. XMaster® : An Easy-to–use expert system shell for Windows. Expert update: The Bulletin Of The British Computer Society's Specialist Group On Knowledge-Based Systems And Applied Artificial Intelligence, Autumn 1998 Volume 1 Number 2. Naylor, C. 2000. Developer's guide, XMaster® , published by Chris Naylor Research Limited. 19 Appendix A Technology transfer of the risk assessment tool for rock related risk issues Project Number: SIM 03 02 01 A.v.Z Brink Date time x cor y cor Mag 16 Feb 03:31:34 29403 -39189 -0.2 Comment 1. The arrow indicates the position of the last event. The event parameters are shown on the figure. The risk display is the assessment immediately prior to the event. The scale on the right is used through-out this presentation. It is a logarithmic scale where fullscale relates to a 50% probability, with average weighting factors, that a rock-related incident will take place within the next 8 hours. Date time x cor y cor Mag Date time x cor y cor Mag 16 Feb 16:50:14 29358 -39203 0.8 16 Feb 18:03:48 29388 -39172 0.0 20 Date time x cor y cor Mag Date time x cor y cor Mag 17 Feb 10:56:05 29359 -39193 0.3 18 Feb 16:17:57 29352 -39158 0.1 Date time x cor y cor Mag Date time x cor y cor Mag 20 Feb 07:36:21 29337 -39193 0.4 20 Feb 16:45:17 29279 -39222 0.4 Date time x cor y cor Mag Date time x cor y cor Mag 20 Feb 16:53:52 29435 -39169 0.3 21 Feb 16:33:27 29181 -39275 0.0 Date time x cor y cor Mag Date time x cor y cor Mag 21 Feb 18:29:20 29284 -39215 0.2 22 Feb 01:26:44 29376 -39198 -0.2 21 Date time x cor y cor Mag Date time x cor y cor Mag 22 Feb 01:28:38 29505 -39210 -0.7 22 Feb 01:37:40 29570 -39165 -0.4 Date time x cor y cor Mag Date time x cor y cor Mag 22 Feb 01:43:56 29549 -39187 -0.2 22 Feb 01:45:39 29582 -39354 -0.2 Date time x cor y cor Mag Date time x cor y cor Mag 22 Feb 02:16:59 29146 -39279 -0.4 22 Feb 02:35:09 29262 -39250 1.1 Comment 2. A magnitude 1.1 event happened outside the area designated as working area, therefore with low exposure of people and subsequent low risk. No prior indication of a rockrelated incident is noticed. Date time x cor y cor Mag Date time x cor y cor Mag 22 Feb 09:59:18 29271 -39262 0.8 22 Feb 11:36:04 29284 -39261 0.0 22 Date time x cor y cor Mag Date time x cor y cor Mag 23 Feb 15:52:18 29315 -39195 0.2 23 Feb 23:44:05 29298 -39269 -0.1 Comment 3. The top panel is beginning to experience a high risk Date time x cor y cor Mag Date time x cor y cor Mag 24 Feb 02:52:49 29353 -39203 0.2 24 Feb 10:33:07 29292 -39202 2.0 Comment 4. A Magnitude 2.0 event occurred on the panel where an increased risk could be observed about 15 hours earlier. Date time x cor y cor Mag Date time x cor y cor Mag 24 Feb 16:25:57 29321 -39167 0.1 24 Feb 16:27:58 29273 -39290 0.3 23 Date time x cor y cor Mag Date time x cor y cor Mag 24 Feb 16:35:03 29379 -39166 1.7 25 Feb 04:10:36 29237 -39278 0.5 Comment 5. The second panel suffers a Magnitude 1.7 event after a shift of the higher risk indication onto this panel. Date time x cor y cor Mag Date time x cor y cor Mag 25 Feb 07:42:00 29205 -39263 -0.5 25 Feb 10:03:17 29461 -39173 0.7 Date time x cor y cor Mag Date time x cor y cor Mag 25 Feb 16:20:47 29346 -39184 1.0 25 Feb 16:22:51 29320 -39201 0.0 Comment 6. Another larger event (Mag 1) affects the second panel a day later. Again it happened during the blast. Date time x cor y cor Mag Date time x cor y cor Mag 25 Feb 16:34:59 29459 -39144 0.1 25 Feb 18:28:26 29329 -39196 0.0 24 Date time x cor y cor Mag Date time x cor y cor Mag 26 Feb 16:39:48 29309 -39200 0.1 26 Feb 16:41:47 29281 -39209 0.0 Comment 7. After another two days the risk on these panels had return to normal. Date time x cor y cor Mag Date time x cor y cor Mag 26 Feb 21:57:25 29292 -39199 0.8 27 Feb 16:25:38 29169 -39308 -0.1 Date time x cor y cor Mag 02 Mar 22:59:00 29380 -38743 0.6 25 Random series • Similar events, but now with a random time added/subtracted (+/- 120 hours) per event. • The objective is to demonstrate the validity of the previous sequence. Date time x cor y cor Mag 15 Feb 20:21:59 29317 -39212 0.4 Date time x cor y cor Mag Date time x cor y cor Mag 16 Feb 05:08:59 29440 -39177 0.3 17 Feb 10:11:05 29435 -39169 0.3 Date time x cor y cor Mag Date time x cor y cor Mag 17 Feb 13:35:54 29358 -39203 0.8 17 Feb 10:11:05 29435 -39169 0.3 Date time x cor y cor Mag Date time x cor y cor Mag 17 Feb 18:17:07 29284 -39261 0.0 18 Feb 03:47:46 29582 -39354 -0.2 26 Date time x cor y cor Mag Date time x cor y cor Mag 18 Feb 08:48:38 29359 -39193 0.3 18 Feb 13:43:01 29277 -39329 0.3 Date time x cor y cor Mag Date time x cor y cor Mag 19 Feb 00:10:42 29281 -39342 0.3 19 Feb 09:36:18 29271 -39262 0.8 Date time x cor y cor Mag Date time x cor y cor Mag 19 Feb 16:56:59 29181 -39275 0.0 19 Feb 18:24:34 29505 -39210 -0.7 Date time x cor y cor Mag Date time x cor y cor Mag 20 Feb 03:30:48 29315 -39195 0.2 20 Feb 06:55:08 29284 -39215 0.2 27 Date time x cor y cor Mag Date time x cor y cor Mag 20 Feb 10:48:35 29279 -39222 0.4 20 Feb 18:09:10 29292 -39202 2.0 Date time x cor y cor Mag Date time x cor y cor Mag 21 Feb 04:06:44 29329 -39196 0.0 21 Feb 18:07:35 29205 -39263 -0.5 Date time x cor y cor Mag Date time x cor y cor Mag 22 Feb 01:50:33 29292 -39199 0.8 22 Feb 11:31:39 29321 -39167 0.1 Date time x cor y cor Mag Date time x cor y cor Mag 23 Feb 02:30:00 29376 -39198 -0.2 23 Feb 06:25:25 29237 -39278 0.5 28 Date time x cor y cor Mag Date time x cor y cor Mag 24 Feb 03:10:20 29379 -39166 1.7 24 Feb 07:09:50 29273 -39290 0.3 Date time x cor y cor Mag Date time x cor y cor Mag 24 Feb 07:32:07 29262 -39250 1.1 24 Feb 10:01:57 29146 -39279 -0.4 Date time x cor y cor Mag Date time x cor y cor Mag 24 Feb 10:48:58 29320 -39201 0.0 24 Feb 20:05:04 29346 -39184 1.0 Date time x cor y cor Mag Date time x cor y cor Mag 24 Feb 22:34:48 29298 -39269 -0.1 25 Feb 04:11:31 29549 -39187 -0.2 29 Date time x cor y cor Mag Date time x cor y cor Mag 25 Feb 05:08:04 29309 -39200 0.1 26 Feb 01:52:38 29353 -39203 0.2 30 Appendix B The project output is compiled on a CD, comprising all the evaluation coding, input data and results. The CD includes the following coding and data files: VBA code to be used with Excel.doc A listing of the VBA code used Presentation risk.ppt A PowerPoint Appendix A Sim 03 02 01 data.xls A data set of seismic activity in a section over two years 31 presentation similar to
© Copyright 2025 Paperzz