EN/CV SPS Tunnel visit for crab cavities Minutes Date: 6 January 2016 Location: SPS LSS6 Participants: W.Bannister, P.Pepinster, G.Vandoni Summary of requests COOLING CRG S.Claudet RF E.Montesinos VENTILATION RF P.Baudrenghien Warm compressor RF powering Raw Demi Faraday cup ? Crab equipment zone 100kW Crab equipment zone ? Crab equipment zone 8bar Crab equipment zone COMPRESSED AIR CRG S.Claudet Valves 15 COOLING CRG S.Claudet CRG S.Claudet RF E.Montesinos RF E.Montesinos VENTILATION VSC V.Baglin Cold box Gas heater RF powering RF powering Raw ? Demi Demi 100 kW 0.5 kW PA6 alcove LSS6 QD617 LSS6 QD617 LSS6 QD617 10 kW LSS6 QD617 8 bar 8 bar 8 bar PA6 alcove LSS6 QD617 LSS6 QD617 Vacuum pumps COMPRESSED AIR CRG CRG VSC S.Claudet S.Claudet V.Baglin Valves Valves Valves 15 15 11 Observations LSS6 DEMINERALIZED WATER : the branching off is available, already equipped with valves at the longitudinal position of the helium pumps or blanked off at the longitudinal position of the crab-cavity cryomodule. To install valves, it is necessary to empty the line in the sector, which is done as soon as magnets need to be replaced. For instance, the line is empty now –the isolation valves on the blanked-off branches may be installed now, in YETS (action). COMPRESSED AIR: branching off is available at the level of the QD (see figure) and further downstream. However, EN/CV will only provide a line closer to the final equipment: manifolds for distribution will be installed by the end-users. Compressed air is also needed at the cold box, where branching off is already available (nd equipped with valves) RAW WATER: This is needed for cryogenics, in two positions. At the crab-cavity cryomodule, a gas heater may need a water heat exchanger, 5kW power. The raw piping is not used in this sector. In order not to fill the whole line along the half arc, available sectorization may be used: one set of valves close to TI12 and one set at the TA6 alcove (not easy to access for verification, see figure 1). Figure 1 The two green valves on stainless steel pipe, seen from below (tunnel ceiling) At the PA6, behind the lifts, raw water is also needed for the cold box. Branching off is available at the -5 level, where two DN100 Tees are equipped with blank flanges, which may be substituted by valves (figure 2a). Easier, at the lower elbow of the two stainless steel lines, it should be possible to install two Tees by welding: routing back to the cold box, the pipes would follow the existing ones (2b). Fig.2a Raw water lines in the shaft, -5 level Fig.2b Raw water lines in the TA6 Fig. 3 - Connection points for the coldbox on the raw water circuit in TA6. Observations BA6 RAW WATER: At top of PA6, the raw water circuit has been decommissioned, cut, and partly re-used as rejection line of the sump (“puisard”, rising of clear waters of the BA). The circuit needs to be modified to recover its initial function, while a new dedicated rejection pipe shall be added for the sump. In BA6 cooling station, the raw water circuit needs to be reconnected to the SPS loop. Raw water pipes to be reconnected Reconnection point of raw Reconnection point of raw water circuit on SPS loop water circuit on SPS loop (supply) (return) Figure 4 DEMINERALIZED WATER : The existing manifolds were used to feed surface equipment, which has now disappeared. The isolation valves are under the false floor. Seen the number of manifolds in the area foreseen for the future crab cavity equipment (at least 3 manifolds) it will be easy to find an isolation valve sufficiently close to the client equipment. Figure 5: Demi water manifolds in BA6 Compressed air and ventilation requests will be easy to handle even during beam runs.
© Copyright 2026 Paperzz