REPORT TO THE NCOP ON HOSPITAL REVITALISATION GRANT PERFORMANCE AS AT END OF 2010/11 QUARTER 2 DR S DHLOMO MEC FOR HEALTH- KWAZULU NATAL AND Ms M GOVENDER MEC FOR HUMAN SETTLEMENTS AND PUBLIC WORKS- KWAZULU NATAL CONTENT • • • • • • Spending on grant for first 2 quarters Projected 2010/11 Outcome Performance and monitoring by project and category Co-ordination of Hospital Revite projects Performance of contractors and consultants Reporting and co-ordination between Health and Public Works • Capacity to implement programme • Way forward 2 TRENDS IN GRANT FINANCIAL PERFORMANCE 2005/06 TO 2009/10 2005/06 2006/07 2007/08 2008/09 2009/10 Adjusted Appropriation R 223,938 R 317,300 R 360,194 R 330,404 R 449,558 Actual Outcome R 111,821 R 225,900 R 333,684 R 330,404 R 225,000 Nominal Difference R 112,117 R 91,76 R 26,510 R 0,00 R 224,558 -50.06% -28,93% -7,35% 0% -49,95% R'000 % Variance •HRG budgets have grown rapidly over the past five years •Planning and project management has not kept pace, resulting in under expenditure due to delays – explained later 3 2010/11 MTEF HRG ALLOCATIONS R'000 2010/11 2011/12 2012/13 Main Appropriation R 500,815 R 551,698 R 572,560 •Grant allocation increases by a nominal 27 percent from R449.5 million in 2009/10 to R500,8 in 2010/11 •Projected allocations are expected to increase further than currently shown due to rescheduling on the 2009/10 under spent funds, currently negotiated with the National Treasury. •To be finalised during Adjustment Estimates process 4 BUDGET REVISIONS (cumulative) Quarter 1 Quarter 2 Quarter 3 Quarter 4 Original Optimised Adjusted Actual 54,003 50,048 54,003 54,002 109,288 100,385 100,535 101,011 293,989 282,206 199,191 500,815 500,815 384,277 • The original budget was revised in conjunction with NDoH as part of the optimisation plan; • Adjusted budget is as per DG (NDoH) directive, to be formalised in the Adjustments Estimates 5 QUARTER 2 FINANCIAL PERFORMANCE -by project 2010/11 MAIN BUDGET Institution PIA King George V DoPW Lower Umfolosi DoPW Ngwelezane DoPW Rietvlei DoPW Dr John Dube DoPW Edendale DoPW Madadeni DoPW Hlabisa IDT Dr Pixley ka Seme IDT King Edward VIII PPP Empangeni Tertiary DoH Grant Management DoH Total END OF Q2 ACTUAL VARIANCE % SPENT 201,294,000 43,812,238 157,481,762 21.77% 22,903,000 3,655,639 19,247,361 15.96% 49,510,000 10,477,453 39,032,547 21.16% 26,877,000 6,530,551 20,346,449 24.30% 2,425,000 0 2,425,000 0.00% 59,427,000 8,296,000 51,131,000 13.96% 35,500,000 0 35,500,000 0.00% 10,572,000 1,245,424 9,326,576 11.78% 28,010,000 622,721 27,387,279 2.22% 56,637,000 24,079,533 32,557,467 42.52% 250,000 0 250,000 0.00% 7,410,000 2,291,000 5,119,000 30.92% 500,815,000 101,010,558 399,804,442 20.17% 6 QUARTER 2 FINANCIAL PERFORMANCE -by category INFRASTRUCTURE Institution PIA King George V DoPW Lower Umfolosi DoPW Ngwelezane DoPW Rietvlei DoPW Dr John Dube DoPW Edendale DoPW Madadeni DoPW Hlabisa IDT Dr Pixley ka Seme IDT KE8 PPP Empangeni Tertiary DoH Grant Management DoH Total 2010/11 MAIN BUDGET HEALTH TECHNOLOGY END OF Q2 ACTUAL 2010/11 MAIN BUDGET END OF Q2 ACTUAL 93,257,000 41,962,479 106,000,000 963,335 ORGANISATIONAL DEVELOPMENT 2010/11 MAIN BUDGET QUALITY ASSURANCE END OF Q2 ACTUAL 1,815,000 2010/11 MAIN BUDGET GRANT MANAGEMENT END OF 2010/11 Q2 MAIN ACTUAL BUDGET END OF Q2 ACTUAL 886,424 222,000 0 0 0 18,292,000 1,407,814 851,000 3,762 3,027,000 2,052,315 733,000 191,748 0 0 34,826,000 8,826,043 12,632,000 417,893 1,830,000 1,233,516 222,000 0 0 0 21,770,000 4,272,003 2,200,000 804,583 2,597,000 1,453,965 310,000 0 0 0 2,425,000 0 0 0 0 0 0 0 0 0 44,323,000 8,296,000 15,104,000 0 0 0 0 0 0 0 3,000,000 0 32,500,000 0 0 0 0 0 0 0 7,071,000 0 1,200,000 504,631 1,841,000 740,793 460,000 0 0 0 27,710,000 622,721 300,000 0 0 0 0 0 0 0 47,637,000 24,079,533 9,000,000 0 0 0 0 0 0 0 0 0 250,000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 7,410,000 2,291,000 300,561,000 89,466,593 179,787,000 2,694,205 11,110,000 6,367,013 1,947,000 191,748 7,410,000 2,291,000 7 QUARTER 2 FINANCIAL PERFORMANCE -Infrastructure INFRASTRUCTURE 2010/11 MAIN BUDGET END OF Q2 ACTUAL VARIANCE % SPENT Institution PIA King George V DoPW 93,257,000 41,962,479 51,294,521 45% Lower Umfolosi DoPW 18,292,000 1,407,814 16,884,186 8% Ngwelezane DoPW 34,826,000 8,826,043 25,999,957 25% Rietvlei DoPW 21,770,000 4,272,003 17,497,997 20% Dr John Dube DoPW 2,425,000 0 2,425,000 0% Edendale DoPW 44,323,000 8,296,000 36,027,000 19% Madadeni DoPW 3,000,000 0 3,000,000 0% Hlabisa IDT 7,071,000 0 7,071,000 0% Dr Pixley ka Seme IDT 27,710,000 622,721 27,087,279 2% KE8 PPP 47,637,000 24,079,533 23,557,467 51% Empangeni Tertiary N/A 250,000 0 250,000 0% Grant Management DoH 0 0 0 0% 300,561,000 89,466,593 211,094,407 30% Total 8 QUARTER 2 FINANCIAL PERFORMANCE -Health Technology 2010/11 MAIN Institution BUDGET King George V106,000,000 Lower Umfolosi 851,000 END OF Q2 ACTUAL 963,335 VARIANCE % SPENT 105,036,665 1% 3,762 847,238 0% 12,632,000 417,893 12,214,107 3% Hlabisa 1,200,000 504,631 695,369 42% Rietvlei 2,200,000 804,583 1,395,417 37% Dr Pixley ka Seme 300,000 0 Dr John Dube 0 300,000 0% 0 0 0% Edendale 15,104,000 0 15,104,000 0% Madadeni 32,500,000 0 32,500,000 0% 9,000,000 0 9,000,000 0% 0 0 0 0% 0 Grant Management 179,787,000 Total 0 0 0% 2,694,205 177,092,795 1% Ngwelezane KE8 Empangeni Tertiary 9 QUARTER 2 FINANCIAL PERFORMANCE -Organisational Development Institution 2010/11 MAIN END OF Q2 BUDGET ACTUAL VARIANCE %SPENT 1,815,000 886,424 928,576 49% Lower Umfolosi 3,027,000 1,830,000 Ngwelezane 2,052,315 974,685 68% 1,233,516 596,484 67% Hlabisa 1,841,000 740,793 1,100,207 40% Rietvlei 2,597,000 1,453,965 1,143,035 56% Dr Pixley ka Seme 0 0 0 0% Dr John Dube 0 0 0 0% Edendale 0 0 0 0% Madadeni 0 0 0 0% KE8 0 0 0 0% Empangeni Tertiary 0 0 0 0% 0 Grant Management 11,110,000 Total 0 0 0% 6,367,013 4,742,987 57% King George V 10 QUARTER 2 FINANCIAL PERFORMANCE -Quality Assurance 2010/11 MAIN Institution BUDGET King George V 222,000 Lower Umfolosi 733,000 END OF Q2 ACTUAL 0 Ngwelezane VARIANCE % SPENT 222,000 0% 191,748 541,252 26% 222,000 0 222,000 0% Hlabisa 460,000 0 460,000 0% Rietvlei 310,000 0 310,000 0% Dr Pixley ka Seme 0 0 0 0% Dr John Dube 0 0 0 0% Edendale 0 0 0 0% Madadeni 0 0 0 0% KE8 0 0 0 0% Empangeni Tertiary 0 0 0 0% 0 Grant Management 1,947,000 Total 0 0 0% 191,748 1,755,252 10% 11 QUARTER 2 FINANCIAL PERFORMANCE -Grant Management 2010/11 MAIN Institution BUDGET 0 King George V 0 Lower Umfolosi END OF Q2 ACTUAL VARIANCE % SPENT 0 0 0% 0 0 0% Ngwelezane 0 0 0 0% Hlabisa 0 0 0 0% Rietvlei 0 0 0 0% Dr Pixley ka Seme 0 0 0 0% Dr John Dube 0 0 0 0% Edendale 0 0 0 0% Madadeni 0 0 0 0% KE8 0 0 0 0% 0 Empangeni Tertiary 7,410,000 Grant Management 0 0 0% 2,291,000 5,119,000 31% 7,410,000 2,291,000 5,119,000 31% Total 12 Q2 EXPENDITURE PERFORMANCE AGAINST REVISED BUDGET Revised Budget Actual TOTAL R 384,276 R 101,011 26% Budget revised fron R 500 815 to fund other priority programmes Infrastructure R 243,457 R 89,466 37% Actual performance 48% including a Lag Payment of R27,865 million for Public Works R 122,383 R 2,694 2% Equipment on tender, most expenditure on Q4 mainly for King George V Hospital R 12,100 R 6,368 53% Spending as planned R 1,947 R 192 10% To spend on Q3 & Q4 R 4,389 R 2,291 52% Spending as planned Health Technology Organisational Development Quality Assurance Programme Management % Spent Comments 13 PERFORMANCE AND COORDINATION MONITORING OF THE PROGRAMME • Each project has a Joint Project Management Team which is involved with implementation and monitoring • Programme Steering Committee meetings held quarterly • Additional Operational and Strategic monthly meetings held for all infrastructure programmes • Health Weekly Progress meetings held to ensure timeous interventions on each project • DPW in the process of procuring a web-enabled project management tool by February 2011 to ensure effective management of project milestones – to interface with WIMS 14 PERFORMANCE OF CONTRACTORS AND CONSULTANTS • Contractors – No contract terminations in 2010/11, however where necessary procedures will be followed – Delays experienced through tender appeals process have negative impact on expenditure (Lower Umfolozi War Memorial Hospital and King George V Creche) – Need to enhance tender technical evaluation process • Consultants – Review of Professional Service Providers terms of appointment currently underway e.g. imposition of penalties – Introduction of Project Managers to manage professional disciplines within each project to eliminate risk & conflict of interest 15 REPORTING AND CO-ORDINATION BETWEEN DOH AND DPW • Monthly Infrastructure Programme Management Committee meetings are in place with the DOH and Implementing Agents • Monthly Progress Reporting through the Standard Reporting Format • Co-ordination by provincial treasury through the IDIP Technical Management Committee in place • Political Leadership will be involved through the establishment of the Provincial Programme Steering Committee. 16 CAPACITY TO IMPLEMENT PROGRAMME Health • Lack of Project Management System by IAs make Grant management ineffective – Intervention: DPW in the process to source the web-based project management tool • Limited Project Managers within Health. – Intervention: Process to fill the GM: Infrastructure and critical project managers posts including dedicated Health Technology and Quality Assurance specialists has started 17 CAPACITY TO IMPLEMENT PROGRAMME Public Works • Lack of Project Management System by IAs make Grant management ineffective – Intervention: DPW in the process to source the web-based project management tool • Limited Project Managers within Health. – Intervention: 11 project managers have been appointed with effect from 01 September 2010, 25 project managers interns to be appointed by January 2011 18 PROJECT UPDATES: PUBLIC WORKS King George V Hospital • Outstanding variation orders and expansion of contracts approved • 3 projects currently forwarded for advertising • Creche project in Appeals process, Hearing scheduled for 26 October 2010 Lower Umfolozi War Memorial Hospital. • Construction of the hospital has started • Optimisation plan developed to ensure projected cashflows are met 19 PROJECT UPDATES: PUBLIC WORKS Ngwelezane Hospital • 4 tenders in adjudication stage, contractors to be on site on December 2010 Rietvlei Hospital. • Poor performance by contractor has resulted to poor expenditure, however, the contractor has been assisted to improve performance • Phase 3B (Staff Accommodation) preparing for tender in Mid-November 2010 20 PROJECT UPDATES: PUBLIC WORKS Edendale Hospital • Delays due to review of the Master Plan by National Department of Health. However National Health have committed to finalise this matter before end of October 2010 Dr John Dube and Madadeni Hospitals. • Professional team to be appointed by end of October 2010. 21 PROJECT UPDATES: IDT Dr Pixley ka Seme Hospital • Delays in approving design by National Health. National Health have committed to finalise this by end of October 2010 Hlabisa Hospitals. • Construction of the Hospital suspended. Enabling works to proceed to construction in January 2011 22 WAY FORWARD • Health – Weekly meetings are held to expedite decisions – The dept will make use of Health Technology service providers in the interim to expedite equipment purchases, until vacancies are filled – Stricter financial reporting is in place with all expenditures being closely monitored. – HR have been requested to fast track the recruitment of new staff. 23 WAY FORWARD • Public Works – DoPW is currently in a process of procuring the Project Management tool and planned to be finalised by February 2011. – Effective implementation of IDIP and ensuring that infrastructure plans are submitted in July of the planning year to promote forward planning. – Interventions as presented in each hospital will be followed up. – Projection to be revised inline with fast-track plan by end of October 2010. 24
© Copyright 2026 Paperzz