Best Value @ BXL3.0

Best Value @ Plan
Elaboration Third
Beatrix Lock
Johannes Hiemstra
Outline
•
•
•
•
•
Introduction to Rijkswaterstaat
Project: Third Beatrix Lock
Best Value Process
Metrics
Lessons Learned
Rijkswaterstaat
2
Best Value @ BXL3.0
Rijkswaterstaat
•
•
•
•
Agency of Ministry of Infrastructure and the Environment
Founded in 1798
Around 9,000 employees
Annual budget: 4 to 5 billion euros
Rijkswaterstaat
3
Best Value @ BXL3.0
Procurement Strategy
•
Rijkswaterstaat...
– is a leading client in the Netherlands
– focuses its attention on the users of the network
– focusing more on core tasks
– is handing over more work to the market in integrated
contracts to capture value from the market
Rijkswaterstaat
4
Best Value @ BXL3.0
Rijkswaterstaat
5
Best Value @ BXL3.0
The project: Why?
• Growth of transport on
inland waterways
• More bigger ships in the fleet
• Berth capacity
Rijkswaterstaat
6
Best Value @ BXL3.0
Rijkswaterstaat
7
Best Value @ BXL3.0
Rijkswaterstaat
8
Best Value @ BXL3.0
Project
Phases
Initiative
Exploration
Plan elaboration
Realization
Concept Decision
Initial Decision
Preference Decision
Spatial Decision
Decision Points
Third Beatrix Lock
2012-2013
2013-2014
=award contract
Rijkswaterstaat
9
Best Value @ BXL3.0
Delivery Decision
Scope
•
Deliverable: Concept Decision (OTB/MER) within 18 months after
awarding the contract and thereafter as soon a possible a Final
Decision
• Project goals:
1. Delivery before December 2013
2. Delivery of design during OTB/MER that meets the available
construction budget of 215,4 mln
3. Delivery of the Concept Decision within
the available budget of 2,1 mln
4. Minimization of transactions between
client and vendor
Rijkswaterstaat
10
Best Value @ BXL3.0
SELECTION
Dominant
Simple
Differential
(non-technical
performance
measurements)
CLARIFICATION/
PRE-AWARD
Clarification
Technical review
Detailed technical
schedule
© 2013, Arizona State University, PBSRG
11
MANAGEMENT
BY
RISK MINIMIZATION
Risk Management
Quality Control
Quality Assurance
Rijkswaterstaat
Best Value @ BXL3.0
Filters
Kwaliteit van de gegadigden
Tijd
1
2a
EMVI
MEAT
3
gunning
Award
WR enand
WRR
DRDR
Selectie-,Selection
inschrijvingsen beoordelingsfase
Phase
Filters
Filter 1
Filter 2
Filter 3
-Project Capability Interviews
Past
performance (PC)
-Risk Assessment (RA)
-Value Added (VA)
-Cost
© 2011, Arizona State University, PBSRG
12
2b
Filter 4
Identify
MEAT
Pre-
UitManagement
Clarification
Award
voering
By Risk
Phase
fase
Minimization
Filter 5
Clarification
Rijkswaterstaat
Best Value @ BXL3.0
Filter 6
Weekly
Report
Most Economically Advantageous Tender
Rijkswaterstaat
13
Best Value @ BXL3.0
Rijkswaterstaat
14
Best Value @ BXL3.0
Best Value during the Execution
Rijkswaterstaat
15
Best Value @ BXL3.0
Quality control by client (as explained by IMT)
Preference Decision
Concept Decision
Initial
conditions
Final
conditions
Natural laws
Natural laws
Time
16
© 2013, Arizona State University, PBSRG
Rijkswaterstaat
Best Value @ BXL3.0
Quality control by the client
Proactive
Reactive
Period
Period
Must be expert
Detailed takeoff
Minimal impact to the spatial decision
Provides regional/legal expertise Blames engineering consultant for
issues
Assists with design
Lack of perceived value
High perceived value
© 2013, Arizona State University, PBSRG
17
Rijkswaterstaat
Best Value @ BXL3.0
Metrics
Schedule:
Delay: 0%, delivery 4 months
ahead of client schedule
Budget: 0% over budget
Change orders: 12%,
90% caused by the client
Rijkswaterstaat
18
Best Value @ BXL3.0
Metrics
Quality:
no major comments
by QC Ministry,
average number of
minor comments
Rijkswaterstaat
19
Best Value @ BXL3.0
Rijkswaterstaat
20
Best Value @ BXL3.0
Lessons Learned
• No QC by regional department, shows that client
values expertise of the vendor. Vendor steps up its
own QC and delivers high performance
• It shows that emphasis on
selecting on value with MEAT
will result in selecting the
Best Value vendor instead
of just lowest price
• BVP very useful for
engineering services
Rijkswaterstaat
21
Best Value @ BXL3.0