WP3.2.2 GINA Trials execution

GNSS for INnovative Road Applications
WP3.2.2 GINA Trials execution
Trials execution Status
8th June 2010
Brussels
Introduction
MAIN ITEMS:
 WP3.2.2 trials execution currently ongoing
 Exhaustive Trials Campaing concluded (both GMV & Navteq vehicles)
 Exhaustive Trials analysis phase ongoing
 GMV vehicle data preliminary results
 Navteq vehicle data ready for analysis
 End2End trials SW development and integration concluded
 End2End trials OBEs production & installation currently ongoing after initial delays
 Enforcement trials expected to be carried out once end2end trials are running
 AENOR trials arrangments to be finished, final dates for the test (Summer 2010) to be concluded soon
Company’s
PM#4 WP3.2.2 GINA Trials Execution
08/06/2010
Page 2
GNSS for Innovative road Applications
logo
Exhaustive Trials definition
Exhaustive Trials Concept
1. GNSS OBU
2. GNSS Reference System
3. Evaluation Routes
4. Geobjects Definition
GINA EXHAUSTIVE TRIALS:
 Evaluation of GNSS system peformance in terms of Position performance, Distance calculation performance,
geo-objects detection performance and charging performance
 Different configurations to be tested for results comparison




GNSS
GNSS + EGNOS (SISNET)
GNSS + CANBUS
GNSS + CANBUS + EGNOS (SISNET)
 Two different vehicles operated by different Companies (GMV & Navteq)
 Use of different defined geobjects with different definitions to test OBU performance
 One vehicle subject to pre planned challenging routes (GMV) and other vehicle following its daily routes
(Navteq)
Company’s
PM#4 WP3.2.2 GINA Trials Execution
08/06/2010
Page 3
GNSS for Innovative road Applications
logo
Exhaustive Trials Status
GMV Vehicle
Navteq Vehicle
Trial campaign succesfully concluded in
April 2010
Navteq Trial campaing succesfully
concluded June 2010
Data from the OBU and reference
system collected and processed
OBU and Reference system Data
to be handed out by Navteq
Processed Data analysed and first set
of results evaluated
OBU and Reference data to be
processed as in GMV vehicle
Second analysis phase to introduce
corrections and fine tunning
Analysis phase for Navteq Data to
take place after GMV analysis ends
Evaluation Report and related results
deliverable expected to start after 2nd
evaluation
Navteq results to be included
together with GMV vehicle in the
evaluation Report
GINA: Evaluacion de Sistemas GNSS/GALILEO
en el marco de aplicaciones EFC/RUC.
Procedimiento, Metodologia y Resultados
Company’s
11/05/2010
Page 4
GNSS for Innovative road Applications
logo
End2End Trials definition
1 EFC System Architecture
2 GINA end2end Trials Architecture
Company’s
PM#4 WP3.2.2 GINA Trials Execution
08/06/2010
Page 5
GNSS for Innovative road Applications
logo
End2End Trials RUC Centre
FEATURES:
 User Interface & services communications through web applications
 Billing Generator Module
 Compliant with Netherlands EFC scheme requiriments (i.e privacy)
 Report and charges generation
 user profiles information and modification
Company’s
PM#4 WP3.2.2 GINA Trials Execution
08/06/2010
Page 6
GNSS for Innovative road Applications
logo
RUC Service Centre Status
Billing Module fully
operative
 End user interface
operative


Additional functionalities
may be developed to
provide additional
information, e.g.
 Geographical
objects map
 Publish table of
tariffs
Users log into the
system anonymously
with the device number
of their vehicle
 Definition of charging
schemes and tariffs
ongoing
 Integration test with
VAS Module ready

Company’s
GINA Trials Execution
29/07/2017
Page 7
GNSS for Innovative road Applications
logo
End2End trials VAS Platform
RITA Reports online with test data at:
http://194.79.89.182/Gina/
The following features already functional and integrated
– General Traffic Information
•
Displays the zones, total Kms and average speed for all OBU IDs between a
given time interval
– Total vehicles by speed interval
•
Displays the vehicle count across a series of speed intervals for a given time
interval
– Traffic statistics by date
•
Displays the total amount of
– Traffic statistics by zone
Company’s
PM#4 WP3.2.2 GINA Trials Execution
08/06/2010
Page 8
GNSS for Innovative road Applications
logo
End2End trials VAS Platform Status
General Traffic Information
Total Vehicles per speed interval
Traffic Statistics By Date
Traffic Statistics By Zone
Company’s
PM#4 WP3.2.2 GINA Trials Execution
08/06/2010
Page 9
GNSS for Innovative road Applications
logo
E2E trials VAS Platform

RITA providing PAYD per vehicle details in central system.
Company’s
PRESENTATION TITLE VERDANA (9)
29/07/2017
Page 10
GNSS for Innovative road Applications
logo
End2End Trials OBUs
GPRS communications
provision
Mobile Phone Operator
Selection – Vodafone
NL
110 SIM Cards
Provided up to
December 2010
OBUs – Service Centre
communications tested
and operational
January 2010
February 2010
ARVAL selected
companies contact
volunteer drivers
Final Drivers and
vehicle models list and
locations arranged
December 2009
March 2010
100 OBES Bill of
Material reception
finished completely
100 OBEs production
and reception in GMV
finished
OBEs GINA FW
Integration and Testing
almost finished
April 2010
May 2010
June 2010
Contract signed
December 2009
Volunteer Drivers
enlistment
OBEs Production
OBEs Installation
ARVAL Related
companies contact
started
September 2009
OBEs Shipment to the
Netherlands process
started
May 2010 (40
units)
Volunteers drivers
appointments for
installation ongoing
June 2010
(ARVAL
volunteers)
OBEs Installed &
running in the
Netherlands
June 2010
EVENTS:
 OBEs materials provision delays and uncompliant materials produced a big delay in the process start
 Installations appointments and material shipments had to be rescheduled thus increasing the final delay
 Process already started and expected to be finished without any more setbacks
Company’s
PM#4 WP3.2.2 GINA Trials Execution
08/06/2010
Page 11
GNSS for Innovative road Applications
logo
Geo-Objects Definition
GP4
GP5
GP1
GP0
GP2
GP3
GINA GEOBJECTS:
 Use of different geobjects classes in order to check OBU geobject recognition performance
 Different classes
 Different geobjects definition methodology
 Different sizes for same geobjects
 Different sub sets of geobjects for the different trials
 End2end trials geobjects
 GMV exhaustive trials geobjects
 Navteq exhaustive trials geobjects
Company’s
PM#4 WP3.2.2 GINA Trials Execution
08/06/2010
Page 12
GNSS for Innovative road Applications
logo
Geo-Objects Definition Status
Exhaustive Trials Geobjects
End2End Trials Geobjects
Status:
Status:
 Exhaustive geobjects definition closed
 End2End geobjects definition closed
 GMV exhaustive trial geobjects
 Navteq exhaustive trials geobjects
 End2end geobjects placed around
strategic locations
 GMV exhaustive geobjects defined
 volunteers likely routes
 51 different geobjects



 main roads
Entry/Exit points
Segments (Higway and urban)
Cordon / Charging areas
 Postal codes areas
 3 locations



 20+ geobjects defined
Amsterdam
The Hague
Rotterdam
 Segments (Higways)
 Different legal definitions and methodologies

Geobjects x1, x2, x4
 Charging Areas
 Nijmegen
 Navteq exhaustive Geobjects defined
 Utrecht
 Cordons & entry/exit points (crossings)
 Adapted to navteq vehicle routes
 X geobjects defined
 Rotterdam
 The Hague
Company’s
PM#4 WP3.2.2 GINA Trials Execution
08/06/2010
Page 13
GNSS for Innovative road Applications
logo
Enforcement trials status
ITEMS:
 Enforcement Trials expected to take place after end2end trials kickoff
 Date: July 2010
 Place: not decided yet
 Enforcement Trials will be split in two different phases
 OBU – Enforcement Platform communication testing (Remote)
 Enforcement live trials involving OBU & ANPR systems
 1 OBU will be installed in a test vehicle
 Test vehicle will drive around the area of the ANPR system
 ANPR will trigger the central system into asking the OBU
Company’s
PRESENTATION TITLE VERDANA (9)
29/07/2017
Page 14
GNSS for Innovative road Applications
logo
ASCENDI (AENOR) trials status
Specification and development in progress
1. Fleet Management
•
•
GIS Map with real-time vehicle positioning
Ready for test
2. Incident Management
•
•
Automatic detection of time taken from incident detection to arrival on site.
Under development
3. Contract obligations enforcement
•
•
Provide reports with information regarding specific sites and times
monitored per day
Under development
4. Reports
•
Current version under review by ASCENDI
Specification details under discussion with ASCENDI for 2 and 3
¿? Date and location ¿?
Company’s
PRESENTATION TITLE VERDANA (9)
7/29/2017
Page 15
GNSS for Innovative road Applications
logo
ASCENDI (AENOR) Trials
VEHICLE TRACKING
Company’s
PM#4 WP3.2.2 GINA Trials Execution
08/06/2010
Page 16
GNSS for Innovative road Applications
logo
ASCENDI (AENOR) trials
Fleet Management Report
Incident Management Report
Company’s
PM#4 WP3.2.2 GINA Trials Execution
08/06/2010
Page 17
GNSS for Innovative road Applications
logo
ASCENDI (AENOR) trials
Contract Obligations Enforcement Reports
Company’s
PM#4 WP3.2.2 GINA Trials Execution
08/06/2010
Page 18
GNSS for Innovative road Applications
logo
Next Steps & Open Points
Open Points
Actions Needed
- GMV Exhaustive trials results
analysis
 Review 1st analysis results (DATE)
 Fine Tune results (DATE)
 Prepare evaluation Report (DATE)
- Navteq Exhaustive trials results
analysis
 Collect Navteq vehicle data (DATE)
 Process data results (DATE)
 Evaluate and compare results (DATE)
- End2End Trials Campaign Start
 Ship all the remaining OBUs (DATE)
 Finish installations for the 100 OBUs (DATE)
 Start data collection process
- End2End Trials Platform
 Introduce charging schemes & tariffs (DATE)
 Feed real data into the platform
- Enforcement Trial definition
 Carry out Enforcement Communication Trials (DATE)
 Carry out Enforcement Live Trials (DATE)
- AENOR Trials
 End definition phase together with ASCENDI (DATE)
 Carry out defined tests (DATE)
Company’s
PM#4 WP3.2.2 GINA Trials Execution
08/06/2010
Page 19
GNSS for Innovative road Applications