Application of the Joint Probability Approach to Ungauged Catchments for Design Flood Estimation By Tanvir Mazumder Student ID: 13762067 M. Eng. (Hons) Thesis School of Engineering and Industrial Design University of Western Sydney August 2005 Principal Supervisor: Dr. Ataur Rahman Associate Supervisor: Dr. Surendra Shrestha Associate Supervisor: Professor Steven Riley 1 Acknowledgements I would like to thank my Principal Supervisor Dr. Ataur Rahman for his assistance, guidance and valuable advice in undertaking this research. I would also like to acknowledge my Associate Supervisors Dr. Surendra Shrestha and Professor Steven Riley for their continued support and direction while undertaking this thesis. I also thank the School of Engineering and Industrial Design for supporting this research work. Statement of Authentication The work presented in this thesis is, to the best of my knowledge and belief, original expect as acknowledged in the text. I hereby declare that I have not submitted this material, either in full or in part, for a degree at this or any other institution. Tanvir Mazumder (Signature) TABLE OF CONTENTS ABSTRACT-----------------------------------------------------------------------------------viii ACRONYMS AND ABBREVIATIONS---------------------------------------------------x 1.0 INTRODUCTION -------------------------------------------------------------------------1 1.1 Background --------------------------------------------------------------------------1 1.2 Objectives ---------------------------------------------------------------------------4 1.3 Thesis outline ----------------------------------------------------------------------4 2.0 DESIGN FLOOD ESTIMATION METHODS BASED ON THE JOINT PROBABILITY APPROACH ----------------------------------------------------------6 2.1 General ------------------------------------------------------------------------------6 2.2 Flood estimation methods overview --------------------------------------------6 2.3 Rainfall-based flood estimation methods---------------------------------------7 (i) Empirical methods -----------------------------------------------------8 (ii) Continuous simulation method -------------------------------------11 (iii) Design Event Approach ---------------------------------------------12 (iv) Joint Probability Approach-----------------------------------------13 2.4 Description of the Joint Probability Approach -------------------------------15 (i) Approximate methods--------------------------------------------------15 (a) Discrete methods ------------------------------------------------------15 (b) Simulation techniques ------------------------------------------------17 (ii) Analytical methods ---------------------------------------------------18 i (1) Methods based on U.S. Soil Conservation Service’s curve number procedure--------------------------------------------------------------19 (2) Methods based on Eagleson’s kinematic runoff model ---------19 (3) Methods based on other types of rainfall-runoff models ------20 (4) Methods based on geomorphologic unit hydrograph ----------21 2.5 Recent research on the joint probability approach to design flood estimation-----------------------------------------------------------------22 2.6 Index of major research works on the Joint Probability Approach-------26 2.7 Joint probability approach to ungauged catchments -----------------------32 2.8 Description of the Monte Carlo Simulation Technique to design flood estimation of Rahman et al. (2002)------------------------------------32 2.8.1 General ---------------------------------------------------------------32 2.8.2 Event definition -----------------------------------------------------33 2.8.3 Distribution of flood-producing variables -----------------------33 2.8.3.1 Duration -----------------------------------------------------------34 2.8.3.2 Intensity -----------------------------------------------------------35 2.8.3.3 Temporal pattern -------------------------------------------------35 2.8.3.4 Initial loss ---------------------------------------------------------36 2.9 Simulation of derived flood frequency curves -----------------------------37 2.10 Proposed research ------------------------------------------------------------37 3.0 DESCRIPTION OF DATA ---------------------------------------------------------40 3.1 Pluviograph data-----------------------------------------------------40 3.2 Catchments for the validation of the new technique---------------------------42 ii 3.2 Summary ---------------------------------------------------------------------------43 4.0 METHODOLOGY IN THE PROPOSED RESEARCH ---------------------44 4.1 Steps in the proposed research ----------------------------------------------44 4.2 Rainfall analysis --------------------------------------------------------------45 4.3 Loss analysis -----------------------------------------------------45 4.4 Calibration of runoff routing model --------------------------48 4.5 Simulation of streamflow hydrograph ----------------------------------------49 4.6 Testing the hypothesis whether storm-core duration can be described by an exponential distribution-------------------------------------------------50 4.7 Program to compute weighted average IFD table at an ungauged catchment ------------------------------------------------------53 5.0 RESULTS --------------------------------------------------------------------------------55 5.1 Distribution of storm-core duration ------------------------------------------55 5.2 Derivation of intensity-frequency-duration curves ---------------------------------------------------------------------------- 56 5.3 Regionalisation of the distributions of various flood producing variables -------------------------------------------------------------56 5.3.1 Storm-core duration -----------------------------------------------------------57 5.3.2 Storm-core rainfall intensity ------------------------------------------------59 5.3.3 Storm-core temporal patterns------------------------------------------------59 5.3.4 Initial loss-----------------------------------------------------------------------60 5.3.5 Continuing loss, storage delay parameter, non-linearity parameter and baseflow-----------------------------------------------------------------------61 iii 5.4 Derived flood frequency curves with regionalised parameters of the input variables----------------------------------------------61 5.5 Sensitivity analyses-------------------------------------------------------------71 5.5.1 Continuing loss ---------------------------------------------------------------71 5.5.2 Catchment storage parameter (k) ----------------------------74 5.6 Comparison among Joint Probability Approach, Probabilistic Rational Method and Quantile Regression Technique--------------------76 6.0 SUMMARY AND CONCLUSIONS--------------------------------------------------82 6.1 Summary --------------------------------------------------------------------------82 6.2 Conclusions---------------------------------------------------------84 6.3 Recommendation of further study----------------------------------------------85 REFERENCES--------------------------------------------------------------------------------86 APPENDICES Appendix A: List of study pluviograph stations----------------------------------97 Appendix B: FORTRAN program to compute weighted average IFD table at an ungauged catchment ----------------------------------------99 Appendix C: Distributions of storm-core durations for selected catchments-100 Appendix D: IFD tables for the study catchments----------------------------------------109 Appendix E: IFD curves for selected catchments----------------------------------------144 Appendix F: Flood frequency curves for selected test catchments--------------------148 Appendix G: A Numerical example illustrating the identification of a storm-core--154 iv TABLES Table 2.1: Index of previous research on the Joint Probability Approach--------------26 Table 3.1: Selected gauged catchments for validating the new technique --------------42 Table 3.2: Selected additional test catchments and relevant data ------------------------43 Table 4.1: Hourly pluviograph data for Pluviograph Station 76031(Mildura Mo) 46 Table 4.2: Parameter file a76031.psa for rainfall analysis (for Station 76031) -47 Table 4.3: Important output files from program mcsa5.for (for Station 76031) 47 Table 4.4: Parameter file a40082.lan- (Bremer River catchment) for rainfall analysis-----------------------------------------------------------------48 Table 4.5: Output file for a40082-(Bremer River catchment) for rainfall analysis----48 Table 4.6: Parameter file re1s1.par (region-1, station-1) for simulation of streamflow hydrograph ---------------------------------------------------------52 Table 4.7: Output file for re1s1.par (region-1, station-1) for simulation of streamflow hydrograph---------------------------------------52 Table 5.2.1: IFD table for Station 76031-----------------------------------------------------58 Table 5.4.1: Radius of subregions for the Boggy Creek catchment ----------------------62 Table 5.4.2: The percentage difference between the DFFCs and observed floods for the Boggy Creek catchment----------------------------------------64 Table 5.4.3: Radius of subregions for the Tarwin River catchment ---------------------65 v Table 5.4.4: Percentage differences between the DFFCs and observed floods for the Tarwin River catchment-----------------------------------------66 Table 5.4.5: Radius of subregions for the Avoca River catchment ---------------------67 Table 5.4.6: The percentage difference between the DFFCs and observed floods for the Avoca River catchment------------------------------------------70 Table 5.6.1: Flood estimation obtained by three methods (QRM, PRM and JPA) -----------------------------------------------------------78 Table 5.6.2:Median relative error values (%) for three methods JPA, QRT and PRM-----------------------------------------------------------------------------80 FIGURES Figure 2.1: Classification of design flood estimation methods------------------------------7 Figure 2.2: Flood Estimation by Design Event Approach ---------------------------------14 Figure 2.8.1: Histogram of storm-core durations dc at pluviograph station Mildura MO (76031) ------------------------------------------------------34 Figure 2.9: Schematic diagram of Monte Carlo Simulation--------------------------------39 Figure 3.1: Locations of the selected pluviograph stations in Victoria -------------------41 Figure 3.2: Distribution of record lengths of the selected pluviograph stations --------41 Figure 4.3: Baseflow separation for the Bremer River Catchment -----------------------51 Figure 4.4: Observed vs. computed streamflow data for a selected event for the Bremer River catchment----------------------------------------------------51 Figure 4.5: Output windows to compute weighted average IFD table ------------------54 Figure 5.1.1: Histogram of storm-core duration for Pluviograph Station 82121-------56 vi Figure 5.2.1: Plot of IFD curves for Station 76031-----------------------------------------58 Figure 5.3.1: Various zones in Victoria for regionalisation of storm-core duration---59 Figure 5.3.2: Sample storm-core temporal pattern database for ≤ 12h durations for a region with 3 pluviograph stations for the Boggy Creek catchment---------------------------------------------60 Figure 5.4.1: Derived flood frequency curves for the Boggy Creek catchment using regionalised parameters--------------------------------------62 Figure 5.4.2: Derived flood frequency curves for the Tarwin River catchment using regionalised parameters---------------------------------------65 Figure 5.4.3: Derived flood frequency curves for the Avoca River catchment of using regionalised parameters-----------------------------------67 Figure 5.4.4: Box plot of relative errors for the three test catchments--------------------69 Figure 5.5.1: Effects on derived flood frequency curves for the Boggy Creek Catchment of using different continuing loss values---72 Figure 5.5.2: Effects on derived flood frequency curves for the Tarwin River Catchment of using different continuing loss values------------------------------------------------73 Figure 5.5.3: Effects on derived flood frequency curves for the Avoca River Catchment of using different continuing loss values -----73 Figure 5.5.4: Effects on derived flood frequency curves for the Boggy Creek Catchment of using different k values----------------------74 Figure 5.5.5: Effects on derived flood frequency curves for the Tarwin River Catchment of using different k values----------------------75 vii Figure 5.5.6: Effects on derived flood frequency curve for the Avoca River Catchment of using different k values-----------------------76 Figure 5.6.1: Box plot for relative errors for JPA-----------------------------------------80 Figure 5.6.2: Box plot for relative errors for PRM ---------------------------------------81 Figure 5.6.3: Box plot for relative errors for QRT----------------------------------------82 viii Abstract Design flood estimation is often required in hydrologic practice. For catchments with sufficient streamflow data, design floods can be obtained using flood frequency analysis. For catchments with no or little streamflow data (ungauged catchments), design flood estimation is a difficult task. The currently recommended method in Australia for design flood estimation in ungauged catchments is known as the Probabilistic Rational Method. There are alternatives to this method such as Quantile Regression Technique or Index Flood Method. All these methods give the flood peak estimate but the full streamflow hydrograph is required for many applications. The currently recommended rainfall based flood estimation method in Australia that can estimate full streamflow hydrograph is known as the Design Event Approach. This considers the probabilistic nature of rainfall depth but ignores the probabilistic behavior of other flood producing variables such as rainfall temporal pattern and initial loss, and thus this is likely to produce probability bias in final flood estimates. Joint Probability Approach is a superior method of design flood estimation which considers the probabilistic nature of the input variables (such as rainfall temporal pattern and initial loss) in the rainfall-runoff modelling. Rahman et al. (2002) developed a simple Monte Carlo Simulation technique based on the principles of joint probability, which is applicable to gauged catchments. This thesis extends the Monte Carlo Simulation technique by Rahman et al. (2002) to ungauged catchments. The Joint Probability Approach/ Monte Carlo Simulation Technique requires identification of the distributions of the input variables to the rainfall-runoff model e.g. rainfall duration, rainfall intensity, rainfall temporal pattern, and initial loss. For gauged catchments, these probability distributions are identified from observed rainfall and/or streamflow data. For application of the Joint Probability Approach to ungauged catchments, the distributions of the input variables need to be regionalised. This thesis, in particular, investigates the regionalisation of the distribution of rainfall duration and intensity. ix In this thesis, it is hypothesised that the distribution of storm duration can be described by Exponential distribution. The distribution of rainfall intensity is generally expressed in the form of intensity-frequency-duration (IFD) curves. Here, it is hypothesised that the IFD curves for ungauged catchment can be obtained from the weighted average IFD curves of an appropriate number of pluviograph stations in the vicinity of the ungauged catchment in question. The weighting factors in averaging can be obtained from the distances of the pluviograph stations from the ungauged catchment. It has been found that Exponential distribution can be used to describe the at-site and regional distribution of storm-core duration in Victoria. It has also been found that the Monte Carlo Simulation technique can successfully be applied to ungauged catchments. The independent testing of the new technique shows that the median relative error in design flood estimates by this technique ranges from 49 to 66% which was found to higher than those of the Probabilistic Rational Method (for this the median relative errors were in the range 41% to 47%) and the Quantile Regression technique (which had median relative errors in the range 28% to 51%). The possible reasons for the Joint Probability Approach of having a higher relative error is that the test catchments used in this study were included in the data set of derivation of the runoff coefficients for the Probabilistic Rational Method in the Australian Rainfall and Runoff and Quantile Regression Technique by Rahman (2005). Another reason may be that the Joint Probability Approach adopted provisionally developed regional estimation equation for storage delay parameter (k) of the runoff routing model, and regional average continuing loss value which were obtained from a very small sample of data. It was found that derived flood frequency curves from the Joint Probability Approach were very sensitive to both k and continuing loss values. The developed new technique of design flood estimation can provide the full hydrograph rather than only peak value as with the Probabilistic Rational Method and Quantile Regression Technique. The developed new technique can further be improved by addition of new and improved regional estimation equations for the initial loss, continuing loss and storage delay parameter (k) as and when these are available. x Acronyms and Abbreviations ARI Average Recurrence Interval ARR Australian Rainfall and Runoff AEP Annual Exceedance Probability BOM Bureau of Metrology IFD Intensity-frequency-duration dc Storm-core Duration Ic Storm-core Rainfall-Intensity ILs Initial Loss for Complete Storm ILc Initial Loss for Storm-Core JPA Joint Probability Approach MCST Monte Carlo Simulation Technique TPc Storm-core Temporal Pattern URBS Runoff-Routing Hydrologic Model k Storage delay parameter m Non-linearity parameter PRM Probabilistic Rational Method QRM Quantile Regression Technique JPA Joint Probability Approach DFFC Derived Flood Frequency Curve xi CHAPTER 1 INTRODUCTION 1.1 BACKGROUND Flood is the number one natural disaster on earth in terms of economic damage. Each year floods cause millions of dollars of damage across Australia. Annual spending on infrastructure requiring flood estimation in Australia is about $1 billion. The average annual cost of flood damage in Australia is estimated to be about $400 million (MRSTLG, 1999). Due to global climate change (resulting from greenhouse effects), the severity and frequency of floods and associated damage will increase significantly in the near future in Australia (similar to other parts of the world) (CSIRO, 2001, Muzik, 2002). Also, estimation of streamflow of a given recurrence interval (ARI) is often required in environmental studies. Due to its large economical and environmental relevance, estimation of design flood remains a subject of great importance and interest in flood hydrology. On numerous occasions, floods have to be estimated at locations where there are little or no recorded streamflow data (ungauged catchments). Also due to land use and global climate changes, many of the previously recorded rainfall and streamflow data may become of little relevance for a catchment of interest, and under such a situation, flood estimation techniques for ungauged catchments need to be applied. Thus, flood estimation at ungauged catchments is a major issue in hydrological and environmental design/studies, and is of great economic significance. The currently recommended methods to estimate design floods at ungauged catchments include empirical methods (black box type model) such as Probabilistic Rational Method (I. E. Aust., 1997), Index Flood Method (Hosking and Wallis, 1993; Rahman et al., 1999) and USGS Quantile Regression Method (Benson, 1962). These are limited to peak flows and are not particularly useful when estimation of complete streamflow hydrographs is required, e.g. 1 wetland design. The Design Event Approach that is based on design rainfalls such as RORB (Laurenson and Mein, 1997) and URBS (Carroll, 1994) can be used to estimate design hydrograph at ungauged catchments; a high degree of estimation error is associated with these techniques because of a high degree of error in transposing model parameters from gauged to ungauged catchments and due to a fundamental limitation of the Design Event Approach as discussed below. The Design Event Approach uses a probability-distributed rainfall depth with representative values of other input variables such as rainfall temporal pattern and initial loss and assumes that the resulting flood has the same frequency as the input rainfall depth. The key assumption involved in this approach is that the representative design values of the input variables/ model parameters at different steps can be defined in such a way that they are ”annual exceedance probability (AEP) neutral” i.e. they result in a flood output that has the same AEP as the rainfall input. The success of this approach is crucially dependent on how well this assumption is satisfied. There are no definite guidelines on how to select the appropriate values of the input variables/ model parameters that are likely to convert a rainfall depth of a particular AEP to the design flood of the same AEP. There are many methods to determine an input value, the choice of which is totally dependent on various assumptions and preferences of the individual designer. Due to non-linearity of the transformation in the rainfall-runoff process, it is generally not possible to know a priori how a representative value for an input should be selected to preserve the AEP. In summary, the current Design Event Approach considers the probabilistic nature of rainfall depth but ignores the probabilistic behaviour of other input variables/ model parameters such as rainfall duration and losses. The assumption regarding the probability of the flood output i.e. that a particular AEP rainfall depth will produce a flood of the same AEP is unreasonable in many cases. The arbitrary treatment of the various flood producing variables, as done in the current Design Event Approach, is likely to lead to inconsistencies and significant bias in flood estimates for a given AEP. This results in either over-design or underdesign of flood structures both of which have important economic consequences. 2 A significant improvement in design flood estimates can be achieved through rigorous treatment of the probabilistic aspects of the major input variables/model parameters in the rainfall-runoff models. This can be done through a Joint Probability Approach, which is more holistic in nature that uses probability-distributed input variables/model parameters and their correlation structure to obtain probability-distributed flood output. While ARR (I. E. Aust., 1987) recommended the Design Event Approach to rainfall-based design flood estimation, it recognised the importance of considering the probabilistic nature of the flood- producing input variables. It thus recommended further investigation into the Joint Probability Approaches. More recently, Hill and Mein (1996), in a study of incompatibilities between storm temporal patterns and losses for design flood estimation, mentioned, “A holistic approach will perhaps produce the next significant improvement in design flood estimation procedures”. They found the error in design flood estimates as high as 40% in some Victorian catchments due to inconsistencies in design loss and temporal patterns values alone. The Joint Probability Approach is superior to the currently adopted Design Event Approach because the former can account for the probabilistic nature of the flood producing variables and their interactions in an explicit manner and eliminates the subjectivity in selecting the representative value of a flood producing variable that show a wide variability such as initial loss. Rahman et al. (1998) summarised the previous works (Eagleson, 1972; Beran, 1973; Russell et al., 1979; Diaz-Granados et al., 1984; Sivapalan et al., 1990) on the Joint Probability Approaches to flood estimation and found that most of the previous applications were limited to theoretical studies; mathematical complexity, difficulties in parameter estimation and limited flexibility generally preclude the application of these techniques to practical situations. Rahman et al. (2002) developed a Monte Carlo simulation technique for flood estimation based on the principles of joint probability that can employ many of the commonly adopted flood estimation models and design data. The new technique has enough flexibility for its adoption in practical situations and has the potential to provide more precise design flood estimates than the existing technique. The Monte Carlo Simulation technique by Rahman et al. (2002) has so far been applied to gauged catchments. This thesis proposes to extend the Monte Carlo Simulation technique to 3 ungauged catchments, which involves regionalisation of the distribution of various floodproducing variables and runoff routing model parameters such as rainfall duration, intensity, temporal pattern, losses, and runoff routing model parameters. This study, in particular, will focus on the regionalisation of the distribution of rainfall duration and rainfall intensity. The main objectives of the study are provided below. 1.2 OBJECTIVES This thesis deals with design flood estimation at ungauged catchments. This, in particular, attempts to develop a new design flood estimation technique for ungauged catchments based on the Joint Probability Approach. The objectives of this thesis are: • To extend the Joint Probability Approach of design flood estimation to ungauged • catchments. • distribution. • with the Joint Probability Approach. To assess whether storm duration data in Victoria can be described by an Exponential To develop a method to regionalize the distribution of rainfall intensity for application To compare the new Joint Probability Approach for ungauged catchments with two existing methods: Probabilistic Rational Method and Quantile Regression Technique. 1.3 THESIS OUTLINE This thesis consists of six chapters. The introductory Chapter 1 provides objective of the thesis and a detail background of flood estimation technique. It also presents the overall outline of the thesis. Review of rainfall based flood estimation methods are described in Chapter 2. A detail review of Joint Probability Approach for the design flood estimation is also covered in this chapter. At the end of this chapter, recent research works on the Joint Probability Approach for design flood estimation are reviewed. The research hypotheses to be examined in the thesis are provided at the end of this chapter. 4 In Chapter 3, the study area is selected. The data used in this study are described here. A total of 76 pluviograph stations are selected in this study. To validate the new technique of design flood estimation, three gauged catchments are selected from the study area. An additional 12 gauged catchments are also selected here to compare the performances of the new technique with two existing design flood estimation techniques for ungauged catchments. The proposed research methodology is described in Chapter 4. This includes steps in the proposed research, rainfall analysis, loss analysis, calibration of runoff routing model, simulation of streamflow hydrograph, testing the hypothesis whether storm-core duration can be described by an exponential distributions and program to compute weighted average intensity-frequency-duration (IFD) values at an ungauged catchment. A FORTRAN program is also developed in this chapter. Chapter 5 details the results of the study. At the beginning, the distributions of storm-core durations are examined. The IFD curves of the study pluviograph stations are obtained in this chapter. The IFD values at an ungauged catchment are obtained by the proposed method, and derived flood frequency curves are obtained for the three study catchments and compared with the at-site flood frequency analyses. The new method is also compared with Quantile Regression Technique and Probabilistic Rational Method. Finally, Chapter 6 contains summary and conclusions from the thesis. This also includes recommended further research. 5 CHAPTER 2 DESIGN FLOOD ESTIMATION METHODS BASED ON THE JOINT PROBABILITY APPROACH 2.1 GENERAL This chapter of the thesis reviews design flood estimation methods in general with a particular emphasis to rainfall-based design flood estimation methods. This presents a detail review of the design flood estimation methods based on the Joint Probability Approach. At the end of the chapter, a research hypothesis is formulated. 2.2 FLOOD ESTIMATION METHODS OVERVIEW Flood estimation methods can broadly be classified into two groups: streamflow based methods and rainfall based methods (Lumb and James, 1976, Feldman, 1979, James and Robinson, 1986, I. E. Aust., 1987). This classification is presented in Figure 2.1 Streamflow-based methods give estimates of design floods by analysing observed streamflow data at a particular location. However, its application is limited to situations where sufficiently long period of streamflow data are available and catchments conditions remain unchanged over the period of observation. Walsh et al. (1991) mentioned that streamflow data are often unreliable, particularly for large events where rating curves generally undergo large extrapolations. 6 Design flood estimation methods Rainfall based methods Streamflow based methods Event based methods Continuous simulation based methods Design Event Empirical Joint Probability Approach methods Approach Partial continuous simulation Complete continuous simulation Figure 2.1 Classification of design flood estimation methods 2.3 RAINFALL-BASED FLOOD ESTIMATION METHODS Rainfall based flood estimation techniques are commonly adopted in hydrologic practice where there is limitation of recorded streamflow data. Rainfall data generally have greater temporal and spatial coverage than the streamflow data. A rainfall runoff model can be used to generate long series of streamflow data using the available rainfall data. This method can be sub-divided into event-based methods and continuous simulation methods. The current Design Event Approach is an example of event-based methods, which is the recommended method to obtain 7 design floods in Australian Rainfall and Runoff (ARR) using hypothetical rainfall event and runoff routing model. Some important features of rainfall based flood estimation methods are: i) Areal extrapolation of rainfall data can be achieved more easily than the streamflow data due to greater density of rainfall stations than the streamflow gauging stations. ii) Physical features of catchments can easily be incorporated into a rainfall-runoff model, which facilitates extreme flood estimation. iii) Climate changes happen more slowly than the land use changes of a catchment which means that long period of recorded rainfall data can be used in the rainfall runoff model. Rainfall based flood estimation methods can be grouped into four types i) Empirical methods ii) Design Event Approach iii) Joint probability based methods or derived distribution methods iv) Continuous simulation methods. (i) Empirical methods James and Robinson (1986) mentioned that empirical methods use observed streamflow and rainfall data to calibrate one or several coefficients in an equation representing the rainfallrunoff process. Probabilistic Rational Method (I. E Aust., 1987) and USGS quantile regression methods (Benson, 1962) are the most common examples of this approach which is black box type methods. Because they do not incorporate the hydrological process in the system rather than attempt to optimise the design flood output by comparison with the observed rainfall and streamflow data. The application of the empirical methods for practical flood estimation is limited to peak flow estimation only and therefore not particularly useful in cases where complete stream flow hydrographs are required. These methods are widely used for ungauged catchments. 8 The Probabilistic Rational Method is the most commonly used approximate method in Australia. According to Australian Rainfall and Runoff (ARR) (I. E. Aust., 1997) this can be represented by: (2.1) QT = 0.278CTItc,TA Where QT is the peak flow (m3/s) for an average recurrence interval (ARI) of T years, CT is the runoff coefficient for the same ARI which is dimensionless, ItcT is the average rainfall intensity (mm/hr) for a storm duration of tc hours with ARI of T years. Here, tc is the time of concentration in hours and A is the catchment area (km2). The original rational method, Q = CIA for computation of design discharge has further been rationalized in the Probabilistic Rational Method by incorporating the probabilistic nature of rainfall intensity (I) and storm loss and other variables that affect runoff generation through the use of runoff coefficient. ARR (I. E. Aust., 1997) has recommended this method for general use in small to medium sized ungauged catchments in Australia, particularly for South-east Australia. The major problem associated with this method is related to the estimation of runoff-coefficients and the time of concentration. The spatial distribution of CT is based on an assumption of geographical contiguity. Hollerbach and Rahman (2003) found little coherence in spatial distribution of the runoff coefficients for South-east Australian catchments. Rahman (2005) proposed a Quantile Regression Technique for South-east Australian catchments. He developed prediction equations for 2, 5, 10, 20, 50 and 100 years ARIs based on the data of 88 catchments from South-east Australia. These equations are provided below. log Q 2 = − 4 .148 + 0 .667 log( area ) + 1 .417 log( I 12 ) + 0 .930 log( sden ) + 1 .630 log( evap ) R2 = 0.72, Adjusted R2 = 0.70, SEE = 0.23 (6.43% of the mean logQ2) 9 ( 2 .2 ) log Q5 = − 6 .513 + 0 .720 log( area ) + 1 .448 log( I 12 ) + 0 .875 log( sden ) + 2 .439 log( evap ) ( 2 . 3) R2 = 0.75, Adjusted R2 = 0.74, SEE = 0.23 (6.06% of the mean logQ5) log Q10 = −6.551 + 0.682 log( area ) + 1.377 log( I 12 ) + 0.968 log( sden ) + 2.542 log( evap ) ( 2 .4 ) R2 = 0.73, Adjusted R2 = 0.72, SEE = 0.23 (5.89% of the mean logQ10) log Q20 = −6.166 + 0.735 log( area ) + 1.537 log( I 12) + 0.987 log( sden ) + 2.374 log( evap ) ( 2.5) R2 = 0.74, Adjusted R2 = 0.73, SEE = 0.24 (5.88% of the mean logQ20) log Q50 = −6.663 + 0.729 log(area) + 1.266 log(I12) + 0.997 log(sden) + 2.597 log(evap) − 0.086 log(qsa) (2.6) R2 = 0.77, Adjusted R2 = 0.76, SEE = 0.23 (5.48% of the mean logQ50) log Q100 = −6.587 + 0.726 log(area) + 1.351 log( I12) + 1.007 log(sden) + 2.580 log(evap) − 0.084 log(qsa ) (2.7) R2 = 0.76, Adjusted R2 = 0.75, SEE = 0.23 (5.56% of the mean logQ100) Here, various variables are: rainfall intensity of 12-hour duration and 2-year average recurrence interval (I12, mm/h), mean annual class A pan evaporation (evap, mm); catchment area (area, km2); stream density (sden, km/km2), which is the length of stream lines divided by the catchment area; and fraction quaternary sediment area (qsa). The qsa is a measure of the extent of alluvial deposits and is an indicator of floodplain extent in the study area. The explanatory variables evap and I12 are determined at the catchment centroid. 10 (ii) Continuous simulation method Continuous simulation for design flood estimation is a rapidly developing field in hydrology. According to Boughton and Droop (2003) the term “Continuous simulation” when used in flood hydrology refers to the estimation of losses from rainfall and the generation of streamflow by simulating the wetting and drying of a catchment on daily, hourly, and occasionally, sub-hourly time steps.” In this method, the uncertainty or randomness of flood variables like initial loss is avoided. One of the important characteristics of these models is the continuous use of water budget model for the catchment so that continuous antecedent condition to each storm event is known. The particular advantage of this method is that the variability of flood producing variable in the temporal sense is reflected in the time series of flood peaks. Event simulation is necessary when long-term rainfall time series is available. In 1997, Siriwardena and Weinmann (1997) prepared a review of continuous simulation approach for design flood estimation. The review covered a number of loss models and some flood hydrograph models, as well as combined systems. This review referred to earlier studies by James and Robinson (1986) and Thomas (1982). In Australia, continuous simulation method has been advanced by Boughton et al. (2000) as a project of the Co-operative Research Center for Catchments Hydrology. Weinmann et al. (2000) noted that the continuous simulation approach is conceptually the most desirable one. The advantage of continuous simulation method over the Design Event Approach according to Rahman et al. (1998) are: ̇ ̇ It eliminates the need for using synthetic storms by using actual storm records. It eliminates subjectivity in selecting antecedent conditions for the land surface since a water budget is accounted for in each time step of the simulation and thus automatically ̇ ̇ logs antecedent moisture condition (James and Robinson, 1986). It overcomes the problem of accounting for antecedent moisture conditions. It overcomes the problem of critical storm duration because it simulates the resultant flows for all storms (Lumb and James, 1976). 11 ̇ ̇ It handles the antecedent conditions correctly because the continuous time series of flows includes all effects of antecedent conditions. (Huber, et al. 1986). It undertakes a frequency analysis of the variable of interest (peakflow, flow volume, pollutant washoff etc) by statistically analysing the time series of model outputs, as opposed to assuming equal probability of floods and causative rainfall intensity (Huber et al. 1986). The problems associated with the application of continuous simulation are: ̇ ̇ ̇ Loss of sharp events if long time steps are used. Extensive data requirement. Significant amount of time and efforts are required in gathering the precipitation and other climatic data needed for simulation of long ̇ ̇ continuous sequences of these variables. Management of large amount of time series output (data management). Expertise required for determining parameter values which best reproduces historical hydrographs (model calibration effort). According to Kuczera and Coombes (2002), stochastic rainfall models and regional techniques are sufficiently improved now to generate long-term rainfall data in the absence of observed pluviograph data. (iii) Design Event Approach Design Event Approach is the currently recommended technique in Australia for estimation of design floods using runoff routing model (I. E. Aust., 1958, 1977, 1987, 1997). In the Design Event Approach, for a selected average recurrence interval (ARI), a number of trial rainfall durations and their corresponding average rainfall intensities are used with fixed temporal pattern, initial loss and other inputs to obtain a flood hydrograph for each duration. Beran (1973) and Ahern and Weinmann (1982), described the steps involved with the Design Event Approach as shown in Figure 2.2. Here the input parameters at different steps of computation should be selected in such that they result in a flood output of the same ARI as the rainfall 12 intensity input. This is generally done by considering the representative values (e.g. mean or median) of the input variables. Due to non-linearity of rainfall-runoff process and high degree of variability of input variables such as initial loss, this assumption of probability neutrality of other input variables are hardly satisfied. In short, this approach considers only the probabilistic nature of the rainfall depth but ignores the probabilistic behaviour of other input variable such as losses in rainfall runoff modelling. As a result, the Design Event Approach is likely to introduce significant ‘probability bias’ in the final flood estimates and has been widely criticized (Kuczera et al., 2003; Rahman et al., 2002). This can result in either a systematic under or over design of engineering structures, both with important economic consequences (Weinmann et al., 1998). Rahman et al. (1998) made a detail critical review of this method including its limitations. In Australia, the Design Event Approach is commonly used with a runoff-routing model such as RORB (Laurenson and Mein, 1997) and URBS (Carroll, 1994). (iv) Joint Probability Approach The basic idea underlying this approach is that any design flood characteristic could result from a variety of combination of flood producing factors, rather than from a single combination, as done in the Design Event Approach. This approach was pioneered by Eagleson (1972) who used an analytical method to derive the probability of distribution of peak streamflows from an idealized V-shaped flow plane. This approach has been advanced and improved in the last two decades. Ahern and Weinmann (1982) mentioned that Joint Probability Approach which considers the outcomes of events with all possible combinations of input values and, if necessary, their correlation structure, should lead to better estimates of design flows. The method is regarded to be theoretically superior to the Design Event Approach and regarded as an attractive design method (I. E. Aust., 1987). This method is discussed in more details in the following section. 13 Design Rainfall Depth (ARI = Y, Duration = D Temporal and Spatial Patterns of Rainfall Design Rainfall Event Loss Parameters Loss Model (ARI = Y) Rainfall Excess Hyetograph Catchment Response Parameters Catchment Response Model Surface Runoff Hydrograph Baseflow Design Flood Hydrograph (ARI = Y) Figure 2.2 Flood Estimation by Design Event Approach ( Rahman et al., 1998) 14 2.4. DESCRIPTION OF THE JOINT PROBABILITY APPROACH The Joint Probability Approach calculates the probability of an output by considering all possible combinations of design inputs. In this approach, flood output has a probability distribution instead of a single value. Here each input is treated as a random variable. The method of combining probability-distributed inputs to form a probability-distributed output is known as the derived distribution approach. A derived probability distribution can be found in two ways: (i) approximate methods and (ii) analytical methods. The choice of a method to compute a derived distribution from these options is influenced mainly by the level of analytical skills and the computer resources available for the task (Weinmann, 1994). (i) APPROXIMATE METHODS Approximate methods are often used in hydrology to determine derived frequency distribution. There are two categories of approximate methods: a) Discrete methods: Total probability theorem is generally used where continuous distributions of hydrologic variables are discritized. b) Simulation technique: Random samples are drawn from continuous distribution of input variables. A) Discrete methods Here discrete probability distributions are used to describe hydrologic variable, such as rainfall duration, antecedent precipitation index, soil moisture deficit, etc. even though they are really continuous ones. Many researchers e.g. Beran (1973), Laurenson (1974), Russell et al. (1979), Fontaine and Potter (1993) adopted this method. The accuracy of the approach depends on the degree of discretization. In discrete methods, the theorem of total probability is normally used to calculate flood probabilities. Fontaine and Potter (1993) make the simplest application of this. For a given flood, its exceedance probability is the sum of three terms, each being the joint probability of extreme rainfall and antecedent soil moisture. 15 In SCS curve number method (Soil Conservation Service, 1972), it is assumed to be represented by three curve numbers. In fact, this over-simplified assumption is one basic limitation of the proposed Joint Probability Approach. The same concept is applied by Russell et al. (1979) to a rainfall-runoff model represented by three parameters (time of concentration T, infiltration rate I and storage constant R). Russell et al. (1979) used actual storm rainfall records instead of a synthetic storm. The Clark rainfall runoff model (Clark, 1945) which provides the basis for the HEC1 model was used in which rainfall is lagged by a time-area curve and routed through linear storage. It was assumed that infiltration rate would be constant for any particular storm. Laurenson (1974) presented the most general application of total probability, which is described by ‘transformation matrix’ approach. The method requires division of a design problem into a sequence of steps, each step transforms an input distribution into output distributions, which becomes the input to the next step (Laurenson, 1974). In applying the method, input, transformation relation and output should be expressed in matrix form. One particular value of the transformation matrix represents the conditional probability of obtaining an output value given a value of the input. The ‘transformation matrix’ method provides a wide range of application (Laurenson, 1973; Laurenson, 1974; Ahern and Weinmann, 1982; Laurenson and Pearse, 1997) when the stochastic nature of the hydrologic system needs to be accounted for. The above examples demonstrate how the theorem of total probability can be applied for calculating design flood probabilities. If all the random variables involved in the design are independent, computation of flood probabilities becomes very simple once probabilities of those input variables are given. For the case of dependent variables, application of the theorem becomes relatively difficult. Beran (1973) presented a procedure that sampled the possible ways in which a storm of a given ARI could cause floods, and derived their joint probability distributions. The unit hydrograph method was used as catchment response model. In applying the method, smoothing of flood probability distributions may be required because of discretizing continuous distributions into class intervals. Shen et al. (1990) presented numerical integration to determine the derived distribution. They used a Poisson process for arrival of storm events, exponential distributions 16 for rainfall intensity and duration, Phillip’s equation for infiltration capacity, and the kinematic wave equation to formulate a rainfall runoff model. The results of the study are applicable to given ranges of basin characteristics only. B) Simulation techniques A number of investigators have used simulation methods to determine derived flood frequency distributions. For example, Durrans (1995) represented a simulation procedure to determine derived flood frequency curve for regulated sites, which has been described as “an integrated deterministic-stochastic approach to flood frequency analysis.” It was done in the following steps: 1) Random sampling of unregulated annual flood peak and unregulated flood volume. 2) Random sampling of a dimensionless initial reservoir depth and dimensionless gate opening area. 3) Routing the inflow hydrograph through reservoir. 4) Replication of steps (1) to (3) N times to obtain N outflow hydrograph peaks. Here N is in the order of thousands. Muzik (1993) adopted a modified SCS curve number method in the Monte Carlo Simulation to obtain a derived distribution of peak discharge. The approach combines knowledge of physical processes with the theory of probability in that knowledge of the processes allows putting reasonable limits on the variable values. Here the initial abstraction and five-day antecedent rainfall values (P5) were assumed to be a random variable. The steps involved in the simulation are: (i) generation of a random value of P5; (ii) from the relationship between P5 and S obtaining the maximum potential retention S; (iii) generation of a random value of the initial abstraction Ia; (iv) generation of a random value of total rainfall P; and (v) computation of rainfall excess depth. The rainfall excess depth was then transformed deterministically by means of the unit hydrograph method into a flood hydrograph. Sivapalan et al. (1996) and Tavakkoli (1985) adopted a simulation approach to derive flood frequency curves for an Australian catchment. The method resulted in slight overestimation of flood peaks, which he mainly attributed to the runoff generation model. 17 Muzik and Beersing (1989) studied the transformation process of probability distributions of rainfall intensity for the case of runoff from a uniformly sloping impervious plane. Here kinematic wave and experimentally derived relations were used to compute the peak discharge. Beran (1973) adopted a simulation technique in that the sampling produced lower flood values at smaller ARIs than the expected flood following storms of that same ARI. This method is not a fully generalised simulation approach; it is a combination of the approximate method and the simulation technique. Here probability distributions of storm durations and temporal pattern were based on complete storms and obtained from the observed data but existing IFD (intensity-frequency-duration) curves based on storm bursts were adopted for rainfall depth. Bloschl and Sivapalan (1997) adopted a Monte Carlo simulation method for mapping rainfall ARIs to runoff ARIs. The simulation consisted of the following steps: (i) Draw storm durations from an exponential distribution. (ii) Draw precipitation probabilities from a uniform distribution P [0; 1] and calculate precipitation return period from Tp = 1/(1-p)/m where m is the number of events per year; (iii) get rainfall intensities, p, from the IFD curve using the two previous pieces of information; and (iv) fit temporal pattern to rainfall, apply runoff coefficient to estimate rainfall excess, simulate streamflow hydrograph from the selected runoff routing model, and note the peaks. At the end, the flood peaks were ranked which allowed assignment of an ARI to each event by using plotting positions: Tq = n/j/m where Tq is the return period of the flood, n is the total number of events, and j is the rank. Finally it can be said that the mathematical framework of the Monte Carlo Simulation technique adopted by several previous studies provide examples of practical design flood estimation techniques based on the Joint Probability Approach. (ii) ANALYTICAL METHODS Bates (1994) and Sivapalan et al. (1996) presented examples where an analytical approach was used for deriving flood frequency distributions. A review of these studies is discussed hereunder depending on the runoff routing method adopted. 18 (1) Methods based on U.S. Soil Conservation Service’s curve number procedure Haan and Edward (1986) derived the joint probability density function of runoff Q and maximum water abstraction S by using U. S. Soil Conservation Service (SCS) curve number method. The equation derived is strictly applicable to the SCS curve number method and it becomes much more difficult in situations where a more complex transformation between rainfall and runoff is required. Raines and Valdes (1993) modified Diaz-Granados et al.,’s (1984) approach where the SCS curve number procedure was used instead of Philip’s ( 1957) infiltration equation to estimate runoff. Becciu et al. (1993) presented a derived distribution technique in flood estimation for ungauged catchments. Here point rainfall was described by a Poisson distribution; intensity and duration of rainfall were assumed to be mutually independent random variables. Catchments in Northern Italy showed its capability to satisfactorily reproduce the frequency distribution of the observed data. (2) Methods based on Eagleson’s kinematic runoff model Eagleson’s (1972) has pioneered the derived flood frequency approach by using kinematic model for runoff from an idealized V-shaped flow plane. This approach assumed that storm characteristics are independent random variable with a joint exponential probability function. He used the empirical areal reduction factors to convert point rainfall to catchment-average rainfall. The method has limited practical applicability. Generally, the number of parameters of the derived distributions is large (Wood and Hebson, 1986) and the assumption of independence between rainfall duration and intensity is not likely to be satisfied. Here runoffrouting model utilised kinematic wave equations for both overland flow and channel flow. Cadavid et al. (1991) applied a derived distribution approach to small urban catchments, which included Eagleson’s rainfall model, Philip’s (1957) infiltration equation, and kinematic wave 19 model for runoff routing. Their model did not show good fits, particularly for higher ARI floods. (3) Methods based on other types of rainfall-runoff models In 1986, Bevan (1986) adopted a Joint Probability Approach to flood estimation that combined the topographically base TOPMODEL with a routing model based on catchment width function. In this study, he found that the proportion of saturated area of flood increased with increasing ARIs. Haan and Wilson (1987) mentioned a methodology for computing runoff frequencies based on the Joint Probability Approach. According to them the derived distribution of peak flows was based on the Rational Method, (2.8) Q = CIA The probability distribution of runoff coefficient (C) and I were described by Beta and Extreme Value Type I distributions respectively. They used numerical integration to obtain derived distribution under the assumption of independence of C and I. They found that consideration of runoff coefficient as a random variable provided larger peak flows than that obtained assuming C as a constant, particularly at higher ARIs. Schakke et al. (1967) mentioned that C may be larger for storms with greater ARIs which is also been recognized in ARR (I. E. Aust., 1987). Haan and Wilson (1987) demonstrated the appropriateness of the Joint Probability Approach and suggested further study on this approach. Sivapalan et al. (1996) illustrated the use of intensity frequency duration (IFD) curves in the derived distribution procedure, which would help to unify the theoretical research on derived flood frequency with traditional design practice. They utilised the derived flood frequency methodology to investigate the link between process control and flood frequency. Sivapalan et al. (1996) proposed a method of specifying the joint distribution of rainfall intensity and duration, which considers IFD curves as conditional distributions, and distribution of storm duration as marginal distribution. They specified the joint distribution of rainfall intensity and 20 duration by multiplying IFD curves (conditional distributions) with marginal distributions of duration. They identified that temporal pattern, multiple storms and the nonlinear dependence of runoff coefficients on event rainfall depth are the major factors controlling the shape of flood frequency curve. Bloschl and Sivapalan (1997) investigated the effects of various flood-producing factors (runoff coefficients, antecedent conditions, storm durations and temporal pattern) on flood frequency curve in a derived distribution frame work. They mentioned that “the case of independent intensity-duration gives vastly steeper flood frequency curves than the case of dependent intensity-duration.” They argued that this non-linearity might be the reason that flood frequency curves tend to be much steeper than rainfall frequency curves. It might be noted that the different slopes and shapes of rainfall and flood frequency curves have been observed for many catchments. (4) Methods based on geomorphologic unit hydrograph Hebson and Wood (1982) and Diaz-Granados et al. (1984) have extended Eagleson’s (1972) rainfall-runoff model by means of the geomorphologic unit hydrograph (GUH) theory proposed by Rodriguez-Iturbe and Valdes (1979). The GUH theory assumes that rainfall excess is generated uniformly throughout the catchment area. Their procedure was tested on two Appalachian Mountain catchments and the results compared well with the observed streamflow data. Wood and Hebson (1986) adopted the scaling of rainfall duration by a characteristics basin time, which is a function of basin size. In deriving the joint probability distribution they assumed a uniform rainfall intensity over the excess storm duration and independence between average areal storm depth and excess storm duration. Diaz-Granados et al. (1984) presented an infiltration excess runoff generation model based on Phillip’s (1957) representation of the infiltration process. They tested their procedure against the sample flood frequency distributions for arid and wet climates and achieved good and reasonable fits, respectively. Moughamian et al. (1987) examined the performance of the derived flood frequency models of 21 Hebson and Wood (1982) and Diaz-Granados et al. (1984) on three catchments and found both models performed poorly in every catchment when compared to sample distribution. Sivapalan et al. (1990) developed a flood frequency model that includes runoff generation on partial areas by Hortonian equation and integrated the partial area model with GUH based runoff routing model. For catchment in humid conditions, Sivapalan et al. (1990) found that different runoff generation processes dominate different ARIs of the flood frequency distribution. Torch et al. (1994) applied a model similar to that developed by Sivapalan et al. (1990) to study the relative importance to hydrologic controls of large floods in a small basin. The catchment was situated in Pennsylvania. Here the channel routing model was expressed in terms of the basin’s ‘width function’. 2.5 RECENT RESEARCH ON THE JOINT PROBABILITY APPROACH TO DESIGN FLOOD ESTIMATION A review of the most recent works is presented below with a particular focus on the results of the studies in relation to practical applicability of the Joint Probability Approach to design flood estimation. Kuczera et al. (2000) represented “KinDog kinematics model” which was used to route the rainfall to the catchments outlet. This is based on the “Field-william kinematic model”. It conceptualises rainfall excess as Hortonian overland flow routed through a non-linear storage into the channel. Two more analytical attempts to estimate the flood probability distribution with the derived distribution methodology are by Iacobellis and Fiorentino (2000) and by Goel et al. (2000). Iacobellis and Fiorentino (2000) assumed that the peak direct flow is expressed as the product of average runoff per unit area, u(a), and the peak contributing area, a. They assumed that the probability distribution of u(a) is conditional and is related to the probability distribution of the rainfall depth occurring in a duration equal to the characteristic response time. 22 Goel et al. (2000) used a stochastic rainfall model which assumes that rainfall intensity is, either positively or negatively, correlated to the rainfall duration for the generation of the rainfall. Here Rainfall runoff processes were modelled using an φ-Index infiltration model and a triangular geomorphoclimatic instantaneous unit hydrograph model. Yue (2000) represented Gumbel distribution model in derived flood frequency analysis. Based on this model, one can obtain the Joint Probability distributions, and the associated return periods of two correlated variables if their marginal distributions can be represented by the Gumbel distribution. Weinmann et al. (2002) highlighted some of the theoretical and practical limitations of the currently used Design Event Approach to rainfall based design flood estimation. They noted that Monte Carlo simulation has the advantage that it can utilise some of the models and design data used with the Design Event Approach, which would allow it to be more readily applied to flood estimation in practical situations. Rahman et al. (2002) presented a more holistic approach of design flood estimation based on the principle of Joint Probability Approach. This Monte Carlo simulation technique based on the Joint Probability Approach offers a theoretically superior method of design flood estimation as it allows explicitly for the effects of inherent variability in the flood producing factors and correlations between them. Rahman et al. (2002c) presented a study illustrating how Monte Carlo simulation technique can be integrated with industry-based model such as URBS. It was found that the integrated URBS-Monte Carlo Technique can be used to obtain more precise flood estimates for small to large catchments. Rahman et al. (2002b) examines the variability of initial losses and specification of its probability distribution for use in the Joint Probability Approach. It was found that the use of a mean value instead of the probability distribution of initial losses reduces flood magnitudes significantly, particularly at smaller average recurrence intervals. 23 Heneker et al. (2002) represented the ways of overcoming the Joint Probability problem by allowing design rainfall obtained from ARR to be directly converted into rainfall excess. They employed a continuous simulation approach using calibrated stochastic point rainfall, stochastic evaporation and water balance models to determine rainfall excess exceedance probabilities for various durations. Charalambous et al. (2003) extended the URBS-Monte Carlo Simulation technique to two large catchments in Queensland. They found that the URBS-Monte Carlo Simulation technique can easily be applied to large catchments. Although the limited data availability in their application introduced significant uncertainty in the distributions of the input variables e.g. IFD curves. Kuczera et al. (2003) suggested that the current revision of ARR needs to articulate the shortcomings of the design storm approach, identify calibration strategies, which gives guidance about its reliability in different application. They also notify that event Joint Probability methods based on Monte Carlo Simulation are computationally less demanding but require specification of the probability distribution of initial conditions. Kader and Rahman (2004) applied the Joint Probability Approach to design flood estimation for ungauged catchments. They attempted to find out how the distribution of rainfall intensity can be regionalised in the state of Victoria in Australia. They examined the regional relationship between two types of design rainfalls, Australian Rainfall Runoff (ARR) and Joint Probability Approach (JP). They found that the regionally predicted JP IFD values to be linearly correlated with the corresponding ARR IFD values. They also found that ARR IFD values are generally higher than the corresponding JP IFD values. The developed regional relationship between JP IFD and ARR IFD values did not produce satisfactory derived flood frequency curves for the ungauged catchment. Rauf and Rahman (2004) examined the sampling properties of rainfall events for constructing intensity frequency duration (IFD) curves in ARR method and Joint Probability Approach. To examine how frequently the same rainfall spell can appear in the data series across various durations in the Victorian state a term “commonality” was used which measured the frequency 24 of repetition of the storm event of a duration in the storm events of subsequent longer duration. They found for 91 stations in Victoria that about 50% storm burst events share common rainfall spells in ARR method implying that many data points across various durations are not independent. Carroll and Rahman (2004) investigated the subtropical rainfall characteristics for use in the Joint Probability Approach to design flood estimation in South-east Queensland. It was found that the complete storm durations in South-East Queensland can be approximated by an exponential distribution but the storm core durations are better approximated by the Gamma distribution. They also discussed the application of Multiplicative-cascade model for temporal pattern distribution. It was suggested that a regional temporal pattern distribution can be used to generate temporal pattern for either complete storm or storm-core in South-east Queensland. Rahman and Carroll (2004) examined the effects of spatial variability of the flood producing variable on derived flood frequency curves in the Joint Probability Approach. It was found that a spatial variation of 20% in mean rainfall duration from sub-catchment to sub-catchment would have little effect on the derived flood frequency curve and it is not necessary to consider different parameters of the initial loss distribution for various sub catchments in the Monte Carlo Simulation for medium to large catchments. 25 2.6 INDEX OF MAJOR RESEARCH WORKS ON THE JOINT PROBABILITY APPROACH Table 2.1 has been compiled to show a number of significant technical reports and papers that have played a major role in the past on the research and development of the Joint Probability Approach to design flood estimation. Table 2.1 Index of previous research on the Joint Probability Approach to design flood estimation Year 1972 Title Author(s) Dynamics of flood frequency Eagleson, P.S Summary This paper assumed that storm characteristics (duration and intensity) are independent random variables. 1973 Estimation of Design Floods and the Beran, M. A. This paper presented a procedure that sampled the possible Problem of Equating the Probability ways in which a storm of given ARI could cause floods, and of Rainfall and Runoff. derived their Joint Probability distributions. It was found that the derived flood frequency curves were much flatter than the observed ones. 1974 Modelling of Stochastic- Laurenson, E. M. Deterministic Hydrologic Systems. This paper represents the most general application of total probability theorem which is described by ‘transformation matrix’ approach. 1982 Considerations for design flood Ahern, P.A. and This paper mentioned that Joint Probability Approach, estimation which considers the outcomes of events with all possible using catchments Weinmann, P.E. modelling. combinations of input values and, if necessary, their correlation structure, obtain better estimates of design flows. 26 1982 A derived distribution flood using frequency Hebson, C and Horton order Wood, E.F. They used Eagleson’s (1972) partial area runoff routing model and their runoff routing model was based on the Ratios. third-order geomorphologic unit hydrograph model. Their procedure was tested on two Appalachian Mountain catchments and the results compared well with the observed streamflow data. 1993 Derived, physically based Muzik, I This paper represented a modified SCS curve number distribution of flood probabilities. method in the Monte Carlo Simulation to obtain a derived Extreme distribution of peak discharge. Here the initial abstraction Hydrological Events: Precipitation, Floods and Droughts. and five-day antecedent rainfall values were assumed to be a random variable. 1996 Process Controls Frequency.1. on Derived Flood Sivapalan, M., They proposed a Flood Bloschl, G. and distribution of rainfall intensity and duration, which Frequency Gutknecht, D. method of specifying the joint considers IFD curves as conditional distributions, and distribution of storm duration as marginal distribution. 2000 Derived distribution of floods based Iacobellis, V. and They assumed that the peak direct flow is expressed as the on the concept of partial area Fiorentino, M. product of average runoff per unit area, u(a), and the peak coverage with a climate appeal. contributing area, a. They assumed that the probability distribution of u(a) is conditional and is related to the probability distribution of the rainfall depth occurring in a duration equal to the characteristic response time. 27 2000 A derived flood frequency Goel, N. K., Kurothe, They presented a stochastic rainfall model which assumes distribution for correlated rainfall R.S., Mathur, B.S. that rainfall intensity is, either positively or negatively, intensity and duration. correlated to the rainfall duration for the generation of the and Vogel, R.M rainfall. 2000 The Gumbel Mixed Model applied Yue, S. He represented Gumbel distribution model. Based on this to model, one can obtain the Joint Probability distributions, storm frequency analysis. and the associated return periods of two correlated variables if their marginal distributions can be represented by the Gumbel distribution. 2002 Overcoming the joint probability Heneker, T., This paper represented the ways of overcoming the Joint problem associated with initial loss Lambert, M., and Probability problem by allowing design rainfall obtained estimation in design flood estimation Kuczera, G. from ARR to be directly converted into rainfall excess. They employed a continuous simulation approach using calibrated stochastic point rainfall, stochastic evaporation and water balance models to determine rainfall excess exceedance probabilities for various durations. 2002 Integration of Monte Carlo Rahman, A, This paper describes how a Monte Carlo simulation simulation technique with URBS Carroll, D.G, and technique can be applied with the industry-based runoff model for design flood estimation. routing model URBS to determine derived flood frequency Weinmann, P.E. curves. 28 2002 Monte Carlo Simulation of flood Rahman, A, This technique is appropriate for the derivation of flood frequency curves from rainfall. Weinmann, P.E, frequency curves in the ARI range 1 to 100 years for small Hoang, T.M.T., and gauged catchments. Laurenson, E.M 2002 Monte Carlo simulation of flood Weinmann, P.E., This paper has highlighted some of the theoretical and frequency curves from rainfall-the Rahman, A., practical limitations of the currently used Design Event way ahead. Hoang, T, Laurenson, Approach to rainfall based design flood estimation. E.M., and Nathan, R.J. 2002 The use of probability distributed Rahman, A., This study examines the role played by initial loss initial modelling in flood estimation for selected Victorian losses in design estimation. flood Weinmann, P.E. and Mein, R.G. catchments. It has been shown that the variability of initial loss in the Victorian catchments can be described by a fourparameter Beta distribution. 2003 Application of Monte Carlo Charalambous, J., They found that the URBS-Monte Carlo Simulation Simulation Technique with URBS Rahman, A., and technique can easily be applied to large catchments. Model for Design Flood Estimation Carroll. D. Although the limited data availability introduced significant in Large Catchments. uncertainty in the distributions of the input variables e.g. IFD curves. 29 2003 Joint Probability and Design Storms Kuczera, G., They suggested that the current revision of ARR needs to at the Crossroads Lambert, M., articulate the shortcomings of the design storm approach, Heneker, T., identify calibration strategies, which gives guidance about Jennings, S., Frost, A. its reliability in different application. They also notify that and Coombes, P event Joint Probability methods based on Monte Carlo Simulation are computationally less demanding but require specification of the probability distribution of initial conditions. 2004 Appropriate spatial variability of Carroll, D. and This paper describes the effects of spatial variability of flood producing variables in the Rahman, A flood producing variables on design flood frequency curves Joint Probability Approach to design in the Joint Probability Approach. flood estimation. 2004 Regionalization of design rainfalls in Kader, F., and This paper represents how the distribution of rainfall Victoria, Australia for design flood Rahman, A. intensity can be regionalized in the state of Victoria in estimation Australia. by Joint Probability Approach. 2004 Investigation of Sub tropical rainfall Carroll, D., and This paper examines the relationship between rainfall characteristics for use in the Joint Rahman, A. intensities of complete storm and storm core and the Probability application of multiplicative cascade model for temporal Approach to design flood estimation pattern distribution is also discussed here. 30 2004 Study of fixed duration design rainfalls in Australian Rauf, A., and This study examines the sampling properties of the rainfall Rainfall Rahman, A. events in the Australian Rainfall-Runoff (ARR) method and Runoff and Joint Probability based Joint Probability Approach to identify any systematic design rainfalls. differences between them. It has been found that ARR design rainfall estimates are generally higher than the Joint Probability based estimates, however these differences vary with location, duration and ARI. 2004 An improved framework for the Nathan. R. J and This paper presented a methodology that reduces the characterisation of extreme floods Weinmann .P.E. practical problems involved in the derivation of both and for the assessment of dam standards safety. methodology is based on the use of Monte Carlo Simulation. 31 and risk based design estimates. Here 2.7 JOINT PROBABILITY APPROACH TO UNGAUGED CATCHMENTS Estimation of hydrologic variables at ungauged sites is perhaps among the oldest challenges for the hydrologic practitioner. In fact, flood and environmental flow estimation at catchments with no streamflow data is a common problem faced by practicing engineers and environmental scientists In Australia, of the 12 drainage divisions, seven do not have a stream with 20 or more years of data (Vogel et al., 1993). Thus flood estimation at ungauged catchments is a major issue in hydrological and environmental design in Australia. The currently recommended methods to estimate design floods at ungauged catchments include empirical methods such as Probabilistic Rational Method (I. E. Aust., 1987), Index Flood Method (Hosking and Walls, 1993; Rahman et al., 1999) and USGS Quantile Regression Method (Benson, 1962). Generally, these provide only the flood peak estimate. Design flood estimation based on Joint Probability Approach using Monte Carlo simulation technique (Rahman et al., 2002) has shown potential to become a practical tool for estimation of design flood for small catchments. The application of this technique to ungauged catchments will require regionalisation of the parameters of the input variables in a region such as rainfall duration, intensity and initial loss. The proposed research intends to adopt Monte Carlo Simulation Approach of Rahman et al. (2002) to ungauged catchments and hence this will be discussed in more details in the next section. 2.8 DESCRIPTION OF THE MONTE CARLO SIMULATION TECHNIQUE TO DESIGN FLOOD ESTIMATION OF RAHMAN ET AL. (2002) 2.8.1 General The Design Event Approach treats rainfall intensity as a random variable, and uses a number of trial rainfall burst durations with fixed temporal patterns to obtain design flood estimates. In contrast, Monte Carlo Simulation Approach by Rahman et al. (2002) requires rainfall events to provide random duration unlike the rainfall bursts of predetermined durations used in the Design Event Approach. For the purposes of the proposed method, two types of rainfall events were defined. These are as follows. 32 2.8.2 Event definition A complete storm is a period of ‘significant’ rainfall that is separated from previous and subsequent rainfall events by a ‘dry’ period. Here a period is defined a ‘dry’ if it lasts at least 6 h. A complete storm is considered to be ‘significant’ if it has the potential to produce significant runoff. This is assessed by comparing its average rainfall intensity with a threshold intensity. Thus, for a complete storm, the average rainfall intensity during the entire storm duration (ID) or a sub-storm duration (Id) must satisfy one of the following conditions: I D ≥ f1 × 2 I D (2.9) I d ≥ f ×2 I d 2 (2.10) Where f1 and f2 are reduction factors, the threshold intensity 2ID is the 2 year ARI design rainfall intensity for the selected storm duration D, and 2Id is the corresponding intensity for the sub-storm duration d. The use of smaller values of f1 and f2 captures a relatively larger number of events. A numerical example illustrating the identification of a storm-core has been given in Appendix G. For each complete storm, a single storm-core can be identified, defined as ‘the most intense rainfall burst within a complete storm. It is found by calculating the average intensities of all possible storm-bursts, and the ratio with an rainfall intensity 2Id for that duration d, then selecting the bursts of that duration which produce the highest ratio. 2.8.3 Distribution of flood-producing variables In the Monte Carlo Simulation Approach by Rahman et al. (2002), four variables were considered for probabilistic representation. These were rainfall duration, rainfall intensity, rainfall temporal pattern and initial loss. 33 2.8.3.1 Duration The storm-cores are selected from the hourly pluviograph data of selected stations and analysed for storm-core duration (dc), average rainfall intensity (Ic), and temporal patterns (TPc). Figure 2.8.1 shows a typical histogram of the frequencies of different storm-core durations, indicating that dc values are approximately exponentially distributed. This implies that, at a particular station, there are many more short duration storm-cores than longer duration ones and that number of storms reduce exponentially with duration. 0.7 0.6 Probability 0.5 0.4 Probability 0.3 0.2 0.1 0 1--10 11-- 21-- 31-- 41-- 51-- 61-20 30 40 50 60 70 7180 Storm core duration (h) Figure 2.8.1 Histogram of storm-core durations dc at pluviograph station Mildura MO (76031) The exponential distribution has one parameter and its probability density function is given by: p(dc)=(1/β)e-dc/ β (2.11) where p stands for probability density, dc is the storm-core duration and β is the parameter of the exponential distribution. The parameter β can be taken as the mean of the observed dc values in a pluviograph station or over a region. 2.8.3.2 Intensity 34 In practice, the conditional distribution of rainfall intensity is expressed in the form of intensity-frequency-distribution (IFD) curves, where rainfall intensity is plotted as a function of rainfall duration and frequency. The IFD curves for storm-core rainfall intensity were developed in a number of steps, as described below from Rahman et al. (2002). (i) The range of storm-core duration dc is divided into a number of class intervals (with a representative or midpoint for each class). For example 2-3 h (representation duration 2 h), 4-12 h (6 h), 13-36 h (24 h). For the data in each class interval (except the 1 h class), a linear regression line is fitted between log(dc) and log(IC). The slope of the fitted regression line is used to adjust the intensities for all duration within the interval to the representative duration. (ii) An exponential distribution is fitted to the partial series of the adjusted intensities within the class interval, and design intensity values IC (ARI) were computed for ARIs of 2, 5, 10, 20, 50 and 100 years. (iii) For a selected ARI, the computed Ic (ARI) values for each duration range were used to fit a second-degree polynomial between log(dc) and log(Ic). The adopted Monte Carlo simulation scheme starts with the generation of a dc value from its marginal distribution. Given this dc and a randomly generated ARI value, the rainfall intensity value Ic is then drawn from the conditional distribution of Ic , expressed in the form of IFD curves. 2.8.3.3 Temporal pattern A rainfall temporal pattern is a dimensionless representation of the variation of rainfall intensity over the duration of rainfall event. The time distribution of rainfall during a storm are characterised by a dimensionless mass curve, i.e. a graph of dimensionless cumulative rainfall depth versus dimensionless storm time. The ‘temporal pattern generation model’ applied by Hoang (2001) could generate design temporal patterns for storm-cores (TPc). However, Rahman et al. (2002) adopted historic temporal patterns instead of generated temporal patterns. Here the observed 35 temporal patterns are expressed in dimensionless form in 10 time intervals and are drawn randomly from the sample corresponding to the generated dc value during the simulation of streamflow hydrograph. The observed temporal patterns are expressed in two groups: one up to 12 hours duration, and the other greater than 12 hours duration. Storms with less than 4 hours durations are assumed to have the same temporal patterns as the observed 4 to 12 hours storms. 2.8.3.4 Initial loss The initial loss for a complete storm (ILs) is estimated to be the rainfall that occurs prior to the commencement of surface runoff. The storm-core initial loss (ILc) is the portion of ILs that occurs within the storm-core. The value of ILc can range from zero (when surface runoff commences before the start of the storm-core) to ILs (when the start of the storm-core coincides with the start of the complete storm event). Rahman et al. (2002b) proposed following equation to estimate ILc from ILs: ILc = ILs[0.5 + 0.25log10(dc)] (2.12) This relationship gives ILc = ILs at dc = 100 hours, and ILc = 0.50 × ILs at dc = 1 hour. The use of the ILs distribution with an adjustment factor, such as the one proposed in Equation 2.12, is preferable to the use of ILc directly, as ILs is more readily determined from data and can probably be derived using existing design loss data. However, Equation 2.12 tends to slightly underestimate observed values of ILc. Rahman et al. (2002b) also adopted a four-parameter Beta distribution to describe the distribution of ILs in that the four parameters are estimated from the observed lower limit (LL), upper limit (UL), mean and standard deviation of the ILs values. 2.9 SIMULATION OF DERIVED FLOOD FREQUENCY CURVES 36 This is the main component of the modelling framework for simulating flood frequency curves, known as Monte Carlo Simulation Technique. The basic principle of this technique involves simulation of a large number of flood events from a large number of rainfall events based on a wide range of likely combinations of floodproducing variables. The flood peaks from the simulation are subjected to flood frequency analysis to derive flood frequency curves. The overall procedure is illustrated in Figure 2.9. 2.10 PROPOSED RESEARCH From the literature review, it has been found that the Monte Carlo Simulation technique of design flood estimation is based on a sounder probabilistic formulation than the currently recommended method Design Event Approach. The proposed research is aimed to extend the Monte Carlo Simulation technique of Rahman et al. (2002) to ungauged catchments. This requires the regionalization of the distributions of rainfall duration, rainfall intensity, rainfall temporal pattern and initial loss. This also requires identification of regional average values of the fixed variables in the runoff routing model such as continuing loss, runoff routing model parameters and baseflow. The proposed research, in particular, is aimed at investigating the regionalisation of the distribution of rainfall duration and intensity. In this research, IFD curves are generated from the historical pluviograph data. Here, the ARR IFD curves are not used in the Monte Carlo Simulation, although the ARR IFD values of standard durations and ARIs are used as threshold values in selecting the storm-core events from the pluviograph data. The following hypotheses were tested in this research: Hypothesis 1: H0: The at-site and regional distribution of storm-core durations in the study area can be described by an Exponential distribution. H1: The at-site and regional distribution of storm-core durations in the study area cannot be described by an Exponential distribution. 37 Hypothesis 2: H0: The IFD curves at an ungauged catchment can be obtained from the weighted average IFD curves of an appropriate number of pluviograph stations in the vicinity of the ungauged catchment. H1: The IFD curves at an ungauged catchment cannot be obtained from the weighted average IFD curves of an appropriate number of pluviograph stations in the vicinity of the ungauged catchment. The weighting factors in obtaining the average IFD values can be obtained from the distances of the pluviograph stations from the ungauged catchment. That is, ⎡ ⎢ ⎢ IFDuc = ⎢⎢ ⎢ ⎢ ⎣⎢ 1 x1 + 1 1 x2 + 1 x3 ⎤ ⎥ ⎤ ⎥ ⎡ IFD 1 + IFD2 + IFD3 + ...⎥ + ...⎥⎥ × ⎢⎢ ⎥ x2 x3 ⎥ ⎥ ⎣⎢ x1 ⎦ ⎥ ⎦⎥ (2.13) Where IFDuc = Weighted average IFD value at the ungauged catchment; IFD1 = IFD value of the nearest pluviograph station from the ungauged catchment; IFD2 = IFD value of the 2nd nearest pluviograph station from the ungauged catchment; x1 = distance between the ungauged catchment and the nearest pluviograph station; and x2 = distance between the ungauged catchment and the 2nd nearest pluviograph station, and so on. ANALYSIS Select stormcore events DATA GENERATION AND SIMULATION dc 38 Storm-core duration (dc) Ic Identify component distributions Storm-core rainfall intensity (Ic) Storm-core temporal pattern (TPc) TPc ILc CL Initial losses (ILs, ILc) Rainfall excess hyetograph Design loss analysis Runoff model calibration Baseflow analysis Derived flood frequency curve Route through runoff routing model (m = 0.8, k from calibration) BF Peak of simulated streamflow hydrograph Figure 2.9: Schematic diagram of Monte Carlo Simulation (Rahman et al., 2002) CHAPTER 3 39 DESCRIPTION OF DATA 3.1 PLUVIOGRAPH DATA To generate flood frequency curves using the Joint Probability based Monte Carlo Simulation technique two sets of data are required: (i) Time series pluviograph data to identify probability distributions of rainfall variables, e. g. duration, intensity and temporal pattern. (ii) Time series pluviograph data on the catchment and streamflow data at the catchments outlet location to identify probability distribution of initial loss. In addition, rainfall and streamflow data for a number of selected events are needed to calibrate the parameters of the adopted runoff routing model. In this study, Victoria is selected as the study area. A total of 76 pluviograph stations are selected from Victoria having a reasonably long record lengths. The locations of the selected pluviograph stations are shown in Figure 3.1. The names of the selected pluviograph stations are shown in Appendix A. The average record length of the selected pluviograph stations is 30 years, the range is 7 years to 128 years and the 75th percentile is 37 years. The distribution of record lengths of the selected stations is shown in Figure 3.2. 40 76,031 77,087 80,110 80,109 80,102 82,039 80,006 81,049 79,082 79,052 79,079 81,038 81,115 81,003 88,029 81,013 82,011 82,121 82,076 83,031 83,067 83,074 82,016 88,153 79,046 87,029 87,152 89,016 89,025 83,025 83,017 86,142 84,005 83,033 87,097 86,038 87,033 90,058 90,166 84,123 84,125 84,112 84,078 86,224 86,314 85,026 85,103 85,236 85,106 85,072 Figure 3.1 Locations of the selected pluviograph stations in Victoria 30 25 Frequency 20 15 10 5 0 1--10 10--20 20--30 30--40 40--50 Record le ngth (years) Figure 3.2 Distribution of record lengths of the selected pluviograph stations 41 3.2 CATCHMENTS FOR THE VALIDATION OF THE NEW TECHNIQUE Three gauged catchments are selected from Victoria for validating the derived flood frequency curves obtained from the new technique. Some important characteristics of these catchments are shown in Table 3.1. Table 3.1 Selected gauged catchments for validating the new technique Catchment Streamflow station Catchment area 2 Period of streamflow data (km ) (years) 108 1974-1998 No. Boggy Creek at 403226 Angleside Tarwin (25) River 227226 127 East Branch Avoca River at Amphitheatre 1957-1979 (22) 408202 78 1975-1999 (25) An additional 12 gauged catchments were selected from Victoria (listed in Table 3.2) to compare the performances of the new technique with two other design flood estimation methods: the Probabilistic Rational Method and Quantile Regression Technique. To apply the quantile regression technique, data of the four flood producing variables were obtained: rainfall intensity of 12-hour duration and 2-year average recurrence interval (I12, mm/h), mean annual class A pan evaporation (evap, mm); catchment area (area, km2); stream density (sden, km/km2), which is the length of stream lines divided by the catchment area; and fraction quaternary sediment area (qsa). The qsa is a measure of the extent of alluvial deposits and is an indicator of floodplain extent in the study area. The explanatory variables evap and I12 are determined at the catchment centroid. These data for the selected 12 catchments are provided in Table 3.2. 42 Table 3.2 Selected additional test catchments and relevant data StationID 226410 227200 229218 230204 234200 401215 404207 405205 405212 405214 405229 408202 Lat (deg) 38.33 38.54 37.67 37.47 37.81 36.87 36.61 37.41 37.1 37.15 36.64 37.78 Lon (deg) 146.53 146.67 145.26 144.67 143.59 147.7 146.06 145.56 145.06 146.13 144.87 144.54 AREA (km2) 88.8 215 36.3 79.1 324 471 451 108 337 368 108 629 I12:2 (mm/h) 4.18 4.9 3.98 4.35 3.6 4.5 4.11 4.5 3.74 4.19 3.5 4.02 EVAP (mm) 1200 1216 1200 1153 1188 1000 1447 1125 1200 1100 1500 1320 SDEN QSA (km/km2) (Fraction) 1.48 0.01 1.22 0.1977 1.29 0.124 2.12 0.4273 1.6 0.1883 1.34 0.0061 1.07 0.1608 1.4 0.0406 1.68 0.0556 1.8 0.1518 1.05 0.45 2.24 0.4316 3.3 SUMMARY This chapter selects study pluviograph stations from Victoria as well as test catchments that will be used to validate the new technique. All the necessary data were obtained and checked for the purpose of this study. 43 CHAPTER 4 METHODOLOGY IN THE PROPOSED RESEARCH 4.1 STEPS IN THE PROPOSED RESEARCH The proposed research aims to extend the Monte Carlo Simulation Technique of Rahman et al. (2002) to ungauged catchments. This will involve the following steps: • • Obtain the at-site distributions of storm-core duration at the selected pluviograph stations. • Obtain the regional distributions of storm-core durations for Victoria. • pluviograph stations. Obtain the intensity-frequency-duration (IFD) curves at the selected Develop a FORTRAN program to compute IFD curves at an ungauged catchment from the IFD curves of the nearby pluviograph stations according to • the proposed Equation 2.13. • patterns at the selected pluviograph stations. Obtain the dimensionless mass curves of the observed storm-core temporal • Obtain the regional distribution of initial loss in the selected study area. • parameters of the runoff routing model and baseflow. • are obtained, the simulation of the streamflow hydrographs can be carried out. Obtain the regional average values of fixed variables continuing loss, Once the regionalized values of all the variables for the runoff routing model Apply the Monte Carlo Simulation technique (for ungauged catchments) to test catchments and compare the results with the observed flood frequency curves. 44 • Compare the results obtained from the Monte Carlo Simulation technique (for ungauged catchments) with other design flood estimation techniques for ungauged catchments i.e. the Probabilistic Rational Method and Quantile • Regression Technique. Make conclusions regarding the applicability and validity of the Monte Carlo Simulation technique (for ungauged catchments). The proposed research will apply the Monte Carlo Simulation technique of Rahman et al. (2002), and hence major steps of this technique are described below. 4.2 RAINFALL ANALYSIS In Applying the Monte Carlo Simulation Technique of Rahman et al. (2002), hourly pluviograph data at a given pluviograph station is analysed to select storm-core rainfall events. These storm-core events are then analysed to obtain probability distributions of storm-core duration ( dc ), average rainfall intensity ( I c ), and temporal patterns ( TPc ). For rainfall analysis, a FORTRAN program called mcsa5.for is used (Rahman et al., 2002). This program requires hourly pluviograph data (sample shown in Table 4.1). The input to the program is given via a parameter file e.g. a76031.psa. An example of parameter file for Pluviograph Station 76031 (Mildura Mo) is shown in Table 4.2. Important output files from the program mcsa5.for are listed in Table 4.3. 4.3 LOSS ANALYSIS To identify the probability distribution of storm-core initial loss (ILc), a FORTRAN program called Losssca.for (Rahman et al., 2002) is used. The basic data input to this program are hourly streamflow and rainfall data. The required input to the program is given through a parameter file, with extension lan, e.g.a40082.lan. The parameter file for the Bremer River catchment (Station 40082) is shown in Table 4.4. Important output files from the program losssca.for are listed in Table 4.5 45 Table 4.1 Hourly pluviograph data for Pluviograph Station 76031(Mildura Mo) Variable Year, Month, Day, Rainfall Quality Station ID Type Hour (mm) Code 76031 10 19530403190000 0.000 1 76031 10 19530403200000 0.000 1 76031 10 19530403210000 0.000 1 76031 10 19530403220000 0.020 1 76031 10 19530403230000 1.770 1 76031 10 19530404000000 2.800 1 76031 10 19530404010000 0.350 1 76031 10 19530404020000 0.140 1 76031 10 19530404030000 0.000 1 76031 10 19530404040000 0.000 1 76031 10 19530404050000 0.000 1 76031 10 19530404060000 0.000 1 76031 10 19530404070000 0.000 1 46 Table 4.2 Parameter file a76031.psa for rainfall analysis (for Station 76031) Input Description a76031 Station ID 76031.dat Data file, rainfall in mm 6 Dry period, between successive complete storm events, in hour 0.4 Reduction factor, F1 0.5 Reduction factor, F2 17.90 2 I 1 (Log-normal design rainfall intensity, 2 year ARI-1 hr duration), mm/hr 2.85 2 0.70 I12 (Log-normal, ARI-2 year, duration-12 hr), mm/hr 2 I 72 (mm/hr) 41.50 50 6.75 50 I12 (mm/hr) 1.62 50 I 72 (mm/hr) I1 (mm/hr) 0.00 Skewness(G) 140 Catchment area, km2 76031a.txt Streamflow data file name Table 4.3 Important output files from program mcsa5.for (for Station 76031) Output Description a76031. dit Duration, intensity and total rainfall for complete storm a76031.dcs Duration of complete storm a76031.cdr Storm-core duration a76031.tpo Output file for temporal pattern analysis a76031.ifd IFD table 47 Table 4.4 Parameter file a40082.lan- (Bremer River catchment) for rainfall analysis Input Description a40082 Station ID 130 Catchment area, km2 40082.dat Data file, rainfall in mm 40082a.txt Streamflow data file (hourly), streamflow in m3/s Table 4.5 Output file for a40082-(Bremer River catchment) for rainfall analysis Output Description a40082.ssr Starting time of surface runoff a40082.ics Initial loss for complete storm ( ILS ) a40082.slp ILS statistics (lower limit, upper limit, mean and standard deviation) 4.4 CALIBRATION OF RUNOFF ROUTING MODEL To determine flood frequency curve for a station, runoff routing model needs to be calibrated for the station. In Monte Carlo Simulation technique of Rahman et al. (2002), the adopted runoff routing model uses a storage discharge relationship of the form S = kQ m (4.4.1) where S is the catchment storage in m3, k a storage delay parameter in hour, Q the rate of outflow in m3/ s and m is non-linearity parameter (taken as 0.8). The objective of model calibration is to determine a value of k that results in satisfactory fit for a range of recorded rainfall and runoff events at the catchment outlet. The following strategy (Rahman et al., 2002) has been found to be useful in calibration: 48 (i) Select a number of rainfall and runoff events from the observed data at the catchment outlet. (ii) For about two-thirds of the selected rainfall and runoff events, calibrate the model for an appropriate value of k . At first, change the initial and continuing loss value to match the rising limb of the computed and observed hydrographs and to obtain a volume balance. When these are achieved, provisionally fix the initial and continuing loss value but change the k value to match the peak. (iii) From the values of k obtained above, select a global k value for all events. (iv) Finally, use the selected k value with the remaining observed rainfall and runoff events to validate the calibrated model. A FORTRAN program called cali4.for (Rahman et al., 2002) is used for the runoff routing model calibration. Figure 4.3 and Figure 4.4 show baseflow separation and observed vs. computed streamflow data for the Bremer River catchment, respectively. 4.5 SIMULATION OF STREAMFLOW HYDROGRAPH To simulate the streamflow hydrograph a FORTRAN program called mcdffc3.for (Rahman et al., 2002) is used. The required input to the program is given through a parameter file e.g.re1s1.par. An example of parameter file is shown in Table 4.6. Important output files from the program mcdffc3.for are listed in Table 4.7. In this study, 20,000 simulation runs were adopted to sufficiently reflect all the possible variability and combinations of the various flood-producing variables that could occur in real flood generation process. The set of simulated flood peaks (NG), obtained as above, is used to construct a derived flood frequency curve. As these flood peaks are obtained from a partial series of storm-core rainfall events, they also form a partial series. Construction of the derived flood frequency curve from the generated partial series of flood peaks involves the following steps as per Rahman et al. (2002): 49 (i) Arrange the NG simulated peaks in decreasing order of magnitude. (ii) Assign rank (m) 1 to the highest value, 2 to the next and so on. (iii) For each of the ranked floods, compute an ARI from the following equation: ARI = NG + 0.2 m − 0.4 × 1 λ ≅ NY + 0.2 m − 0.4 (4.5.1) where NG is the number of simulated peaks, m is the rank, λ is the average number of storm-core events per year for the catchment of interest, and NY is the number of years of simulated flood data. (iv) Prepare a plot of ARI versus flood peaks, i.e. a plot of the empirical flood frequency curve defined by the simulated flood peaks. 4.6 TESTING THE HYPOTHESIS WHETHER STORM-CORE DURATION CAN BE DESCRIBED BY AN EXPONENTIAL DISTRIBUTION Previous study on a smaller number of pluviograph stations in Victoria (Rahman et al., 2002) indicated that probability distribution of storm-core durations can be approximated by an Exponential distribution. To test the statistical hypothesis that storm-core duration data in one of the selected 76 pluviograph stations follow an Exponential distribution, Chi-squared test was applied at 5% level of significance. The Chi-squared test is based on the Chi-squared statistic, which is related to the weighted sum of squared differences between the observed and theoretical frequencies. The Chi–squared test is given by the following equation. κ2 =∑ k i =1 (oi − ei ) 2 ei (4.6.1) Where; Where κ 2 is a value of a random variable whose sampling distribution is approximated very closely by the chi-squared distribution with ν = k −1 degrees of freedom. The symbols oi and ei represents the observed and expected frequencies, respectively, for the ith cell. 50 100 Q (m3/s) 10 1 Streamflow 0.1 Baseflow 61 55 49 43 37 31 25 19 13 7 1 0.01 Time Interval (h) Figure 4.3 Baseflow separation for the Bremer River Catchment 45 40 35 Qobs Qcom Q (m3/s) 30 25 20 15 10 5 0 1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 Tim e Interval (h) Figure 4.4 Observed vs. computed streamflow data for a selected event for the Bremer River catchment ( IL = 16 mm, CL = 0.65 mm/h, k = 10 h, m = 0.8 , Start of event = 23/02/1975 at 10 am) 51 Table 4.6 Sample parameter file re1s1.par for simulation of streamflow hydrograph. Here IL is initial loss and CL is continuing loss Input Description Reg1s1 Catchment name a Run Sequence 20000 No of simulations 13.1 Mean durations 108 Catchment area, km2 reg1s1.ifd IFD file name reg1s1.tem TP file name 0 IL-Lower Limit 89.00 IL-Upper Limit 23.00 IL-Mean 19.00 IL-SD 10 TP intervals 1.90 CL 0.8 m 21 k 1.16 Baseflow 2000 Length of simulation Table 4.7 Sample output file for re1s1.par for simulation of streamflow hydrograph Output Description aReg1s1.gdc Generated storm-core durations aReg1s1.gic Generated storm-core rainfall intensities aReg1s1.glc Generated storm-core loss values aReg1s1.ffc Derived flood frequency curves 52 4.7 PROGRAM TO COMPUTE WEIGHTED AVERAGE IFD TABLE AT AN UNGAUGED CATCHMENT In this study, a FORTRAN program has been developed called ucat1.for to compute the IFD table at an ungauged catchment from the IFD tables of the pluviograph stations in the vicinity of the ungauged catchment. The program contains 1320 lines of codes and is given in Appendix B. The program ucat1.for operates as follows: (i) At first, the IFD tables of all the selected 76 pluviograph stations have been stored in a data file called text10.dat. (ii) When the program executes, it asks the user to enter latitude and longitude of the ungauged catchment. (iii) Then it calculates the distances between the ungauged catchment and all the 76 pluviograph stations. (iv) After that, these distances are sorted in a data file called text11.srt. (v) In the next step, the program asks the user to enter the radius of proposed region (km). Depending on the radius of the candidate region, the program finds out how many stations fall within that region and stores the names of these stations in a data file called text12.reg. The program at this moment allows selection of maximum five pluviograph stations in a region. (vi) To calculate the average IFD table, the program takes only those station’s IFD table which falls in the proposed region. The relevant IFD tables are stored in a file called text14.ilt. (vii) Finally, depending on the number of stations in a region, the program calls the appropriate subroutine and calculates the IFD table at the ungauged catchment using Equation 2.13. The final IFD table for the ungauged catchment is called ‘regional. ifd’. As an example, Figure 4.5 shows an output window of the program ucat1.for to compute the IFD table for latitude 36.74 degree and longitude 146.40 degree. Here the candidate region has a radius of 50 km. 53 Figure 4.5 Output windows to compute weighted average IFD table 54 CHAPTER 5 RESULTS 5.1 DISTRIBUTION OF STORM-CORE DURATION The histograms of storm-core durations for all the selected 76 pluviograph stations were obtained. Figure 5.1.1 shows a typical histogram for pluviograph Station 83033 while the other histograms are provided in Appendix C. The examination of the shape of the histogram indicates an Exponential distribution. A hypothesis test was then conducted to see whether an Exponential distribution is adequate to approximate the distribution of storm-core duration in a particular pluviograph station by adopting a Chi-squared test as discussed in Section 4.6. The test result for Station 83033 is discussed below. In the Chi-squared test for the Station 83033 the observed Chi-squared value was 12.91 and the critical value 7.81 (for alpha = 0.05 and degree of freedom 3) and hence Ho was rejected i.e. the data for Station 83033 cannot be described by Exponential distribution. It was found that only 42% stations passed the test for regional Exponential distribution. Haddad and Rahman (2005) also tested for the Gamma distribution but did not find any better results. This thesis did not conduct any further investigation with other candidate distributions as it was assumed that an exponential distribution would be enough to approximate the distribution of storm-core duration as far as the practical application of the Monte Carlo Simulation Technique to design flood estimation is concerned. 55 5.2 DERIVATION OF INTENSITY-FREQUENCY-DURATION CURVES The intensity-frequency duration (IFD) curves of the selected 76 pluviograph stations were obtained by using the method described in Section 4.2. The IFD table for Station 76031 is shown in Table 5.2.1. Plots of the IFD tables revealed that the obtained IFD curves were consistent in that they do not intersect each other. IFD tables for the study catchments are provided in Appendix D. A sample IFD plot is shown in Figure 5.2.1 for Station 76031. Each of the IFD tables was saved in a database for selection by the developed FORTRAN program in estimating the IFD table for the selected ungauged Frequency catchment. IFD curves for the selected catchments are provided in Appendix E. 80 70 60 50 40 30 20 10 0 1--10 10-20 20-30 30-40 40-50 50-60 60-70 70-80 80-90 Storm-core duration (dc) (hour) Figure 5.1.1 Histogram of storm-core duration for Pluviograph Station 83033 5.3 REGIONALISATION OF THE DISTRIBUTIONS OF VARIOUS FLOOD PRODUCING VARIABLES To apply the Monte Carlo Simulation Technique, we need to have distributions of storm-core duration, intensity, temporal patterns and initial loss, and also the values of the fixed input variables continuing loss, parameters of the runoff routing model and baseflow. To apply the Monte Carlo Simulation technique for the ungauged 56 catchments, we need to have regionalized values of the above distributions and fixed input variables. 5.3.1 Storm-core duration To regionalize the distribution of rainfall duration, Victoria was provisionally divided into four hydrometeorological zones, namely Zone 1 (South-eastern Victoria), Zone 2 (North-eastern Victoria), Zone 3 (North-western Victoria) and Zone 4 (South-western Victoria), roughly cutting the state into quadrants along the Great Dividing Range and North from Melbourne, as shown in Figure 5.3.1. The mean values of storm-core durations are 14.5h, 13.1h, 10.5h and 12.7h respectively for Zones 1, 2, 3 and 4. These regional average values of the storm-core durations were used to fit the regional Exponential distribution and hypothesis testing was conducted against the at site storm-core duration data to assess the viability of a regional Exponential distribution. Using the Chi–squared test, the null hypothesis of a regional Exponential distribution cannot be rejected (at 5% level of significance) for any of the stations in Zones 1, 2, 3 and 4. The regional Exponential distributions with these mean storm-core duration values were adopted in the Monte Carlo simulation for generation of streamflow hydrographs. 57 Table 5.2.1 IFD table for Station 76031 (Intensity values are in mm/h and ARI in years) ARI-0.1 7.298 3.732 1.158 0.219 0.088 0.05 0.032 ARI-1 9.242 4.958 1.97 0.687 0.425 0.325 0.264 ARI-1.11 9.934 5.329 2.12 0.743 0.461 0.354 0.288 ARI-1.25 10.709 5.744 2.288 0.805 0.502 0.386 0.315 ARI-2 13.801 7.397 2.958 1.055 0.664 0.514 0.422 ARI-5 19.83 10.618 4.261 1.54 0.979 0.765 0.632 ARI-10 24.392 13.053 5.245 1.907 1.218 0.954 0.791 ARI-20 28.953 15.488 6.229 2.274 1.457 1.144 0.95 1000 ARI-50 34.984 18.706 7.53 2.758 1.773 1.395 1.16 ARI-100 39.546 21.141 8.514 3.125 2.012 1.585 1.319 ARI-500 50.138 26.793 10.798 3.976 2.567 2.025 1.689 ARI-1000 ARI-1000000 54.7 100.164 29.227 53.485 11.781 21.583 4.343 7.995 2.805 5.186 2.215 4.106 1.848 3.435 ARI=1 ARI=1.11 ARI=1.25 100 ARI=2 ARI=5 10 Ic(mm/h) Duration(hours) 1 2 6 24 48 72 100 ARI=10 ARI=20 ARI=50 1 ARI=100 ARI=500 0.1 ARI=1000 1 dc(h) 10 100 ARI=1000000 Figure 5.2.1 Plot of IFD curves for Station 76031 (ARI in years) 58 VICTORIA AUSTRALIAN CAPITAL TERRITORY Zone 3 Zone 2 NEW SOUTH WALES Zone 1 Zone 4 Figure 5.3.1 Various zones in Victoria for regionalisation of storm-core duration 5.3.2 Storm-core rainfall intensity To regionalise the distribution of storm-core rainfall intensity, Equation 2.13 was used using 1, 2, 3, 4 or 5 pluviograph stations in a region. This means that IFD curves for an ungauged catchment will be obtained based on the IFD curve(s) of the nearest 1, 2, 3, 4 or 5 pluviograph stations. For this purpose the developed FORTRAN program called ucat1.for was used. 5.3.3 Storm-core temporal patterns To form regional database of storm-core temporal patterns, the observed temporal patterns of the nearest 1, 2, 3, 4 or 5 pluviograph stations are pooled together in such a way that if IFD curves are obtained from 2 pluviograph stations, temporal pattern database will also be obtained from the same 2 pluviograph stations. For this purpose 59 the developed FORTAN program called ucat1.for was used. A sample plot of the temporal patterns is shown in Figure 5.3.2 100 90 Cumulative % rain 80 70 60 50 40 30 20 10 0 1 2 3 4 5 6 7 8 9 10 Period Figure 5.3.2 Sample storm-core temporal pattern database for ≤ 12h durations for a region with 3 pluviograph stations for the Boggy Creek catchment 5.3.4 Initial loss To regionalise the distribution of initial loss, the results from Rahman et al. (2002b) is adopted in that they adopted a four-parameter Beta distribution to specify the distribution of initial loss. Based on 10 catchments data from Victoria, Rahman et al. (2002b) obtained the regional average values of the four parameters of the Beta distribution from the observed values of initial losses as 1mm (lower limit), 72mm (upper limit), 25mm (mean) and 13mm (standard deviation). These values are adopted in this study to fit regional Beta distribution for initial loss. The whole of Victoria was considered to be a single region with respect to initial loss distribution. 60 5.3.5 Continuing loss, storage delay parameter, non-linearity parameter and baseflow The regional average values of continuing loss was taken from Rahman et al. (2001) as 1.76 mm/h. The regional value of storage delay parameter (k) of the adopted runoff routing model was obtained from the following equation, again based on the study of Rahman et al. (2001). log(k) = -0.837 + 1.013log(A) (5.1) where k is storage delay parameter in hour and A is catchment area of the ungauged catchement in km2. The value of the non-linearity parameter (m) of the adopted runoff routing model was taken to be 0.8. The average baseflow was taken to be 0.53 m3/s based on the study of Rahman et al. (2001). It may be noted here that the regional average values of continuing loss and regional estimation equation of storage delay parameter (k) were based on a very small sample size and thus likely to introduce a high degree of error in design flood estimates. 5.4 DERIVED FLOOD FREQUENCY CURVES WITH REGIONALISED PARAMETERS OF THE INPUT VARIABLES To identify number of pluviograph stations to be included in obtaining IFD values at an ungauged catchment, subregions were formed with one, two, three, four or five pluviograph stations and derived flood frequency curves were obtained. Each time, the radius of the subregion was selected in such a way that it captures one, two, three, four or five stations. The method was applied to three selected test catchments: Boggy Creek catchment, Tarwin River catchment and Avoca River catchment. The resulting radius of the subregions for the Boggy Creek catchment is shown in Table 5.4.1. The obtained derived flood frequency curves (DFFC) for the Boggy 61 Creek catchment is shown in Figure 5.4.1 which shows that there is no significant differences in the DFFCs whether a subregion consists of one, two, three, four or five stations. In obtaining these DFFCs, regional values for other input variables such as storm-core duration and initial loss were obtained using the procedures mentioned in Section 5.3. Table 5.4.1 Radius of subregions for the Boggy Creek catchment Subregion Number of Area (km2) pluviograph stations in the subregion Subregion one 1 1.40 Subregion two 2 20.09 Subregion three 3 36.64 Subregion four 4 43.68 Subregion five 5 47.79 1000 DFFC - 1 station (DFFC1) DFFC - 2 stations (DFFC2) Q (m /s) DFFC- 3 stations (DFFC3) 3 DFFC- 4 stations (DFFC4) DFFC- 5 stations (DFFC5) Observed floods (partial series) 100 10 1 10 100 ARI (years) Figure 5.4.1 Derived flood frequency curves for the Boggy Creek catchment using regionalised parameters For the Boggy Creek catchment, the percentage differences between various sets of DFFCs and observed floods are presented in Table 5.4.2, which shows that the 62 absolute differences between the DFFCs and observed floods vary from 0.07% to 16.3% over the ARIs of 2, 5, 10, 20, 50 and 100 years. The median absolute difference is the lowest (1.35%) for Sub-region 1 that contains only one station. For Sub-regions 2, 4 and 5, the median absolute difference is close to 5%. For Sub-region 3, the median absolute difference is the highest (12.75%). For the Tarwin River catchment, all the DFFCs show significant departures from the observed floods as shown in Figure 5.4.2. However, DFFC for Sub-region 4 (with four stations in the sub-region) shows the least departure. The radius of various subregions for the Tarwin River catchment is shown in Table 5.4.3. For the Tarwin River catchment, the percentage differences between various sets of DFFCs and observed floods are presented in Table 5.4.4, which shows that the absolute differences between the DFFCs and observed floods vary from 38.9% to 60.5% over the six ARIs. The median absolute difference is the lowest (40.95%) for Sub-region 4 that contains four stations. 63 Table 5.4.2 The percentage difference between the DFFCs and observed floods for the Boggy Creek catchment. ARI Obs. DFFC % % DFFC % % diff. DFFC (years) floods (Sub-reg- diff. diff. (Sub- diff. (abs) (Sub (abs) reg-2) 3 (m /s) 1) % diff. % diff. DFFC (abs) (Sub reg-3) % diff. % diff. DFFC (abs) (Sub reg-4) % diff. % diff. (abs) reg-5) 2 30.00 29.22 2.60 2.60 29.31 2.30 2.30 34.47 -14.90 14.90 27.52 8.27 8.27 30.02 -0.07 0.07 5 46.00 45.51 1.07 1.07 42.30 8.04 8.04 50.42 -9.61 9.61 42.00 8.70 8.70 44.00 4.35 4.35 10 60.00 57.50 4.17 4.17 55.00 8.33 8.33 62.25 -3.75 3.75 54.00 10.0 10.0 56.50 5.83 5.83 20 72.00 72.92 -1.28 1.28 70.00 2.78 2.78 79.63 -10.60 10.60 67.80 5.83 5.83 67.80 5.83 5.83 50 92.00 90.70 1.41 1.41 84.00 8.70 8.70 107.00 -16.30 16.30 91.60 0.43 0.43 83.80 8.91 8.91 100 102.00 103.00 -0.98 0.98 96.00 5.88 5.88 118.50 -16.18 16.18 108.0 -5.88 5.88 104.20 -2.16 2.16 Median 1.35 6.96 12.75 7.07 5.09 64 Table 5.4.3 Radius of subregions for the Tarwin River catchment Subregion Number of pluviograph Area (km2) stations in the subregion 1000 Subregion one 1 17.01 Subregion two 2 44.68 Subregion three 3 47.66 Subregion four 4 68.50 Subregion five 5 69.79 DFFC- 1 station (DF FC1) 3 Q (m /s) DFFC-2 station (DFFC2) DFFC-3 station (DFFC3) DFFC -4 station (DFFC4) DFFC- 5 station (DFFC5) Observed floods - partial series 100 10 1 ARI (years) 10 100 Figure 5.4.2 Derived flood frequency curves for the Tarwin River catchment using regionalised parameters 65 Table 5.4.4 Percentage differences between the DFFCs and observed floods for the Tarwin River catchment. ARI Obs. DFFC (years) floods (Sub-reg- 3 (m /s) % diff. % diff. DFFC % % diff. DFFC (abs) (Sub- diff. (abs) (Sub reg-2) 1) % diff. % diff. DFFC (abs) (Sub reg-3) % diff. % diff. DFFC % % (abs) (Sub diff. diff. reg-4) (abs) reg-5) 2 44.00 17.3 60.5 60.5 19.50 55.6 55.6 18.13 58.80 58.80 24.09 45.25 45.25 21.54 51.05 51.05 5 66.00 27.7 58.0 58.0 31.10 52.8 52.8 30.20 54.24 54.24 39.10 40.76 40.76 36.03 45.41 45.41 10 88.00 36.9 58.0 58.0 41.10 53.3 53.3 38.20 56.59 56.59 51.80 41.14 41.14 46.90 46.70 46.70 20 112.00 45.3 59.5 59.5 52.46 53.1 53.1 50.20 55.18 55.18 65.90 41.16 41.16 59.02 47.30 47.30 50 141.00 59.5 57.8 57.8 62.20 55.8 55.8 62.20 55.89 55.89 84.22 40.27 40.27 80.90 42.62 42.62 100 164.00 66.6 59.3 59.3 73.10 55.4 55.4 73.90 54.94 54.94 100.1 38.96 38.96 92.90 43.35 43.35 Median 58.7 54.3 55.53 40.95 46.06 66 For the Avoca River catchment, all the DFFCs also show significant departures from the observed floods as shown in Figure 5.4.3. The radius of various subregions for the Tarwin River catchment is shown in Table 5.4.5. Table 5.4.5 Radius of subregions for the Avoca River catchment Subregion Area (km2) Number of pluviograph stations in the subregion Subregion one 1 27.18 Subregion two 2 43.35 Subregion three 3 49.94 Subregion four 4 55.72 Subregion five 5 56.50 3 Q (m /s) 100 DFFC - 1 station (DFFC1) 10 DFFC - 2 stations (DFFC2) DFFC- 3 stations (DFFC3) DFFC- 4 stations (DFFC4) DFFC- 5 stations (DFFC5) Observed floods (partial series) 1 1 ARI (years) 10 100 Figure 5.4.3 Derived flood frequency curves for the Avoca River catchment of using regionalised parameters 67 For the Avoca River catchment, the percentage differences between various sets of DFFCs and observed floods are presented in Table 5.4.6, which shows that the absolute differences between the DFFCs and observed floods vary from 0.81% to 41.2% over the six ARIs. The median absolute difference is the lowest (13.3%) for Sub-region 5 that contains five stations. However, for Sub-regions 1, 3 and 4, the median absolute difference is very similar (15%) to that of the Sub-region 5. Based on the results of the three test catchments, it is found that the new technique shows a relative error in design flood estimation in the range of 0.07% to 60.5% with a median value of 16.9% (ignoring the sign of the relative errors). The overall distribution of relative errors for the three test catchments over the six ARIs is presented in the box plot in Figure 5.4.4 (considering the sign of the relative errors). The observed relative errors with the new technique seems to be acceptable as Rijal and Rahman (2005) found that other methods currently applied for ungauged catchments in South-east Australia show a relative error generally higher than this. For example, Rijal and Rahman (2005) found that the Probabilistic Rational Method and Quantile Regression Technique show a median relative error value of about 40% and there is a 10% chance that relative error values may exceed 100% with these two methods. It is also found here that a sub-region consisting of four stations provide more reasonable design flood estimates in that IFD curves and temporal pattern data at the ungauged catchment is obtained from the nearest four pluviograph stations. 68 80.00 60.00 40.00 20.00 0.00 -20.00 Floodquantile Figure 5.4.4 Box plot of relative errors for the three test catchments 69 Table 5.4.6 The percentage difference between the DFFCs and observed floods for the Avoca River catchment. ARI Obs. DFFC (years) floods (Sub-reg- 3 (m /s) % diff. % diff. DFFC % % diff. DFFC (abs) (Sub- diff. (abs) (Sub 1) % diff. % diff. DFFC (abs) (Sub reg-3) reg-2) % diff. % diff. DFFC % % (abs) (Sub diff. diff. reg-4) reg-5) (abs) 2 26.00 15.84 39.0 39.0 15.28 41.2 41.2 15.72 39.54 39.54 17.11 34.1 34.1 15.85 39.04 39.04 5 36.00 26.10 27.5 27.5 26.01 27.7 27.7 26.10 27.50 27.50 28.10 21.9 21.9 27.09 24.75 24.75 10 44.00 35.79 18.6 18.6 34.70 21.1 21.1 34.10 22.50 22.50 37.10 15.6 15.6 36.98 15.95 15.95 20 52.00 43.80 15.7 15.7 44.00 15.3 15.3 45.30 12.88 12.88 46.50 10.5 10.5 46.40 10.77 10.77 50 62.00 57.92 6.58 6.58 59.80 3.55 3.55 61.05 1.53 1.53 60.08 3.10 3.10 62.50 -0.81 0.81 100 69.00 66.70 3.33 3.33 75.59 -9.5 9.5 69.90 -1.30 1.30 77.90 -12.9 12.9 73.10 -5.94 5.94 Median 17.21 18.2 17.69 14.29 13.36 70 5.5 SENSITIVITY ANALYSES This study used regional distributions of storm-core duration, intensity and temporal pattern, which were obtained from the analyses of the observed rainfall data in the region as discussed in Section 5.4. The distribution of initial loss was obtained from the study of Rahman et al. (2002b). The fixed variables used in the simulation of streamflow hydrograph were continuing loss (CL), catchment storage parameter (k), and baseflow (BF) and fixing non linearity parameter (m) as 0.8. It would have been ideal to have regional equations for the CL and k values as function of catchment characteristics. However, this study did not focus on this; rather it has used regional average values of CL based on a small number of rainfall and streamflow events, and a provisionally developed regional equation for k, as mentioned in Section 5.3 from the study of Rahman et al. (2001). This section investigates the impact of CL and k values on the derived flood frequency curves (DFFC) by assigning different possible values of these parameters. 5.5.1 Continuing loss To examine the sensitivity of CL on the derived flood frequency curve, four tentatively selected continuing loss values (0.1 mm/h, 0.52 mm/h, 0.80 mm/h, and 1.76 mm/h) were adopted. The results for the Boggy Creek Catchment is presented in Figure 5.5.1, which indicates that CL value has significant effect on derived flood frequency curve. The CL value of 1.76 mm/h gives DFFC having the best match with the observed floods. As the CL value decreases, DFFC overestimates the observed floods. For 10 years ARI, the derived floods increase by 25%, 30%, and 45% for decrease in CL values by 94%, 70%, and 55%, respectively. For the Tarwin River Catchment, the same four continuing loss values were used. Here, the differences in derived flood frequency curves with the observed flood frequency curve is relatively high as shown in Figure 5.5.2 with all four values of CL. For the continuing loss value of 0.1 mm/h, the difference between the two curves is minimum. 71 For the Avoca River Catchment, the CL value of 0.1 mm/h gives DFFC having the best match with the observed floods as shown in Figure 5.5.3. It is found here that DFFCs are very sensitive to CL value, thus it is very important to derive regional prediction equation for CL with catchment characteristics or to obtain a regional average CL value based on a large number of observed rainfall and streamflow events in the region of interest. This is not done here as it falls beyond the scope of this study. 1000 DFFC- 3 stations, CL=1.76 mm/h DFFC- 3 stations, CL=0.80 mm/h DFFC- 3 stations, CL=0.52 mm/h DFFC- 3 stations, CL=0.10 mm/h Observed floods (partial series) 3 Q (m /s) 100 10 1 10 100 ARI (years) Figure 5.5.1 Effects on derived flood frequency curves for the Boggy Creek Catchment of using different continuing loss values 72 1000 DFFC - 3 stations, CL =1.76 mm/h DFFC - 3 stations, CL =0.80 mm/h DFFC - 3 stations, CL =0.52 mm/h DFFC - 3 stations, CL =0.1 mm/h Observed floods - partial series 3 Q (m /s) 100 10 1 ARI (years) 10 100 Figure 5.5.2 Effects on derived flood frequency curves for the Tarwin River Catchment of using different continuing loss values 1000 Q (m3/s) 100 DFFC- 3 stations, CL 0.1 mm/h DFFC- - 3 stations, CL =0.52 mm/h DFFC - 3 stations, CL =0.80 mm/h 10 DFFC-3 stations, CL =1.76 mm/h Observed floods (partial series) 1 1 ARI (years) 10 100 Figure 5.5.3 Effects on derived flood frequency curves for the Avoca River Catchment of using different continuing loss values 73 5.5.2 Catchment storage parameter (k) The next sensitivity analysis examined the impact of storage parameter value (k) on the derived flood frequency curve (DFFC) for the above three catchments. Four different k values were used: the k value used in Section 5.4 plus three additional k values, which are 50%, 75%, and 150% of original k value used in Section 5.4. The result for the Boggy Creek Catchment is presented in Figure 5.5.4 which shows that for a k value of 16.7h and a continuing loss value of 1.76 mm/h, there are no significant differences between the derived flood frequency curves and the observed floods. For k value of 12.52h, the DFFC significantly overestimates the observed floods. For 10 years ARI, 150% increase in k value reduces derived flood estimate by 22%. Some 50% and 75% decrease in k values increase the derived floods by 74% and 25% respectively. 1000 Q (m3/s) 100 DFFC- 3 stations, k=8.35, CL=1.76 mm/h DFFC- 3 stations, k= 12.52, CL= 1.76 mm/h 10 DFFC- 3 stations, k= 16.7,CL= 1.76 mm/h DFFC- 3 stations, k= 25.05,CL= 1.76 mm/h Observed floods (partial series) 1 1 ARI (years) 10 100 Figure 5.5.4 Effects on derived flood frequency curves for the Boggy Creek Catchment of using different k values 74 1000 3 Q (m /s) 100 DFFC - 3 stations, k =9.8, CL=1.76 mm/h DFFC - 3 stations, k =14.7,CL=1.76 mm/h DFFC - 3 stations, k =19.6,CL=1.76 mm/h DFFC - 3 stations, k =29.4,CL=1.76 mm/h Observed floods - partial series 10 1 1 ARI (years) 10 100 Figure 5.5.5 Effects on derived flood frequency curves for the Tarwin River Catchment of using different k values For the Tarwin River Catchment, k value of 9.8h gives the closest match with observed floods. As the k value increases, the DFFCs decrease sharply as shown in Figure 5.5.5. At 10 years ARI, an increase in k values of 50%, 100% and 200% from k = 9.8h, the derived floods decrease by 28%, 43%, and 60%, respectively. For the Avoca River catchment, k value of 6h gives the best match where DFFC shows least difference with the observed floods. An increase in k value reduces the DFFC sharply as shown in Figure 5.5.6. At 10 years ARI, an increase in k value from 6h to 9h (50%), 12h (100%), and 18h (200%), the derived floods decrease by 28%, 46%, and 60%, respectively. It is found that DFFC is highly sensitive to k value, thus it is important to derive regional prediction equation for k as function of catchment characteristics (such as catchment area and/or main stream length). This would require calibration of runoff routing model (S=kQm) for a large number of catchments in the region of interest based on a large number of observed rainfall and streamflow events. This is not done here as it falls beyond the scope of this study. 75 1000 3 Q (m /s) 100 DFFC-3 stations, k =18.00, CL=1.76 mm/h DFFC-3 stations, k =12.00, CL=1.76 mm/h DFFC-3 stations, k =9.00, CL=1.76 mm/h DFFC-3 stations, k =6.00, CL=1.76 mm/h Observed floods (partial series) 10 1 1 ARI (years) 10 100 Figure 5.5.6 Effects on derived flood frequency curve for the Avoca River Catchment of using different k values 5.6 COMPARISON AMONG JOINT PROBABILITY APPROACH, PROBABILISTIC RATIONAL METHOD AND QUANTILE REGRESSION TECHNIQUE To assess the performance of the Joint Probability Approach (JPA) to ungauged catchment developed here and two empirical methods (Probabilistic Rational Method and Quantile Regression Technique), twelve additional test catchments from Southeast Australia were selected as mentioned in Chapter 3. These are gauged catchments having recorded streamflow data. 76 The Probabilistic Rational Method was applied to these catchments using the runoff coefficients from the Australian Rainfall Runoff (I. E. Aust., 1987). The Quantile Regression Technique was based on the prediction equations developed by Rahman (2005) as mentioned in Section 2.3. The JPA was applied to each of these test catchments based on regionalized parameters of k, CL and BF as mentioned in Section 5.3. The IFD curve at each of the test catchments was estimated using Equation 2.13 based on the IFD curves of 4 nearby pluviograph stations for each of the test catchments. Flood estimates obtained by the three methods are provided in Table 5.6.1. 77 Table 5.6.1 Flood estimation obtained by three methods (QRM, PRM and JPA) (Flood estimation in ML/day) Catchment ID 226410 Q2 OBS. 2200 Q5 QRM 1554 PRM 1373 JPA 1900 OBS. 4250 QRM 2826 Q10 PRM 2011 JPA 2937 OBS. 5000 QRM 4286 Q20 PRM 2452 JPA 3801 OBS. 5800 QRM 5089 Q50 PRM 2673 JPA 4665 OBS. 10000 Q100 QRM 8365 PRM 2967 JPA 5875 227200 3450 3217 4424 2073 11200 6195 6478 3456 17400 8528 7901 4665 20300 10908 8612 5875 26000 11201 9560 7257 229218 7100 706 2024 1900 1740 1237 2964 2764 2000 1942 3615 3542 2850 2163 3941 4147 3400 2715 4375 5270 230204 1460 1875 2206 2937 2900 3286 3230 4492 3850 5218 3939 5529 4820 6279 4294 6912 5800 6151 4767 8640 234200 3000 3105 5431 1728 4350 5916 7953 3024 8100 8648 9699 3974 12200 10831 10572 5875 17000 12776 11736 7516 401215 1700 3818 3139 3110 3250 6757 4597 5529 4200 8860 5606 7430 5100 12074 6111 9158 6050 18639 6784 12441 404207 6100 4804 5124 3628 18000 10586 7504 5702 25000 14538 9151 7430 35500 18290 9975 9417 52000 21895 11073 11923 405205 8100 1731 2839 2764 1300 3069 4158 4060 1750 4468 5071 5184 1950 5486 5527 6220 2200 7115 6136 7776 405212 6000 3563 11072 2419 15500 6840 16214 4147 19000 10011 19773 5702 21500 12644 21552 6912 26500 17085 23925 8985 405214 7200 4159 5006 3283 13000 7623 7330 5011 18500 10866 8939 6739 26000 14282 9744 8294 35500 15568 10817 9676 405229 1200 1470 1645 1728 2000 3092 2410 2937 3500 4708 2939 3974 5900 5261 3203 5356 12000 6268 3556 7257 408202 1900 1617 1845 1728 4200 3105 2703 2764 4900 4892 3296 3801 5150 5634 3593 4838. 5400 6754 3988 6393 OBS. 16000 30100 4000 6450 18100 6500 71000 2350 28000 46000 20100 5600 QRM 10061 PRM 3311 JPA 6825 13303 10666 8985 3214 4881 5875 10368 7532 5318 15482 13094 9244 22012 7569 15897 26300 12354 13478 8462 6846 9244 20824 26693 10713 18887 12068 12614 7498 3967 8640 8210 4450 8121 78 All these test catchments are gauged and the streamflow data were analysed by graphical method to obtain design flood estimates. These estimates are referred to as ‘Observed flood estimates’ (Qobs). The difference between the observed flood estimates (Qobs) and JPA or QRT or PRM was referred to as relative errors, i.e, Relative Error (%) = (Qobs- QJPA)/ Qobs *100 (5.2) Relative Error (%) = (Qobs - QQRT)/ Qobs *100 (5.3) Relative Error (%) = (Qobs- QPRM)/ Qobs *100 (5.4) Based on the absolute values of the relative errors, the median values of relative errors are shown in Table 5.6.2 for the three methods, which shows that the new Joint Probability Approach has median relative error in the range 49 to 66% which are higher than those of the Probabilistic Rational Method (which shows median relative errors in the range 41% to 47%) and the Quantile Regression technique (which has median relative errors in the range 28% to 51%). Considering the sign of the relative errors, box plots of the relative errors were prepared for the three techniques in Figures 5.6.1, 5.6.2 and 5.6.3, which show that the Joint Probability Approach has an overall wider error band as compared to the Probabilistic Rational Method and Quantile Regression Technique. The possible reasons for the Joint Probability Approach of having a higher relative error is that the test catchments used in this study were included in the data set of derivation of the runoff coefficients in the Australian Rainfall and Runoff and Quantile Regression Technique by Rahman (2005). Another reason may be that the Joint Probability Approach adopted provisionally developed regional estimation equation for storage delay parameter (k) of the runoff routing model, and regional average continuing loss value which were obtained from a very small sample of data. It was found in Section 5.5 that derived flood frequency curves from the Joint Probability Approach were very sensitive to both k and continuing loss values. 79 Table 5.6.2 Median relative error values (%) for three methods JPA, QRT and PRM (based on absolute values) ARI (years) 2 5 10 20 50 100 JPA 49.2 60.17 66.77 59.84 60.93 61.24 QRT 28.91 41.27 38.40 35.72 41.64 51.20 PRM 44.33 42.88 42.21 41.99 47.09 46.10 100.00 0.00 -100.00 -200.00 8 8 8 -300.00 Q2 Q5 Q10 Q20 Q50 Q100 Figure 5.6.1 Box plot for relative errors for JPA 80 8 200.00 8 8 8 8 Q20 Q50 100.00 0.00 -100.00 Q2 Q5 Q10 Q100 Figure 5.6.2 Box plot for relative errors for PRM 81 300.00 8 6 8 6 200.00 8 8 6 6 100.00 0.00 -100.00 Q2 Q5 Q10 Q20 Q50 Q100 Figure 5.6.3 Box plot for relative errors for QRT The flood frequency curve for all these catchments are presented in Appendix F. 82 CHAPTER 6 SUMMARY AND CONCLUSIONS 6.1 SUMMARY Chapter 2 of this thesis reviews design flood estimation methods based on the Joint Probability Approach/ Monte Carlo Simulation technique. This approach was first introduced by Eagleson (1972) and has been widely researched in the last three decades. Eagleson (1972) adopted analytical method to obtain derived flood frequency curves from the marginal distributions of various flood-producing variables. Many other researchers adopted the analytical approach by Eagleson (1972). But the problems with this approach are that this has limited flexibility and this involves complicated mathematical functions for real catchments and thus has limited practical applicability. On the other hand, the Monte Carlo Simulation technique is an approximate form of the Joint Probability Approach which can be applied easily in practice. In recent years in Australia, there have been significant research and development on the Monte Carlo Simulation technique, which has so far been tested to gauged catchments. This research aimed to extend the Monte Carlo Simulation technique to ungauged catchments. A research proposal was prepared in Chapter 2 in that it was assumed that the distribution of storm-core duration can be described by an Exponential distribution and rainfall intensity distribution at an ungauged catchment can be obtained from the rainfall intensity distribution of the nearby ungauged catchments. In Chapter 3, Victoria was selected as the study area, and a total of 76 pluviograph stations were selected. The data of these selected stations were obtained from the Bureau of Meteorology and abstracted using HYDSYS database software. A total of three gauged catchments from Victoria were selected to apply the new technique of design flood estimation. An additional 12 gauged catchments were also selected from Victoria to compare the performances of the new technique with two existing techniques for 82 ungauged catchments namely, the Probabilistic Rational Method and Quantile Regression Technique. Chapter 4 outlines the steps in the proposed research and demonstrates the method of rainfall analysis, loss analysis and runoff routing model calibration, which are major components on the Monte Carlo Simulation technique. A FORTRAN program (containing 1370 lines) was also developed in this chapter to estimate intensityfrequency-duration (IFD) curves of an ungauged catchment based on the IFD curves of the pluviograph stations in the selected region. Chapter 5 obtains the storm-core durations and IFD curves of the selected 76 pluviograph stations. This also presents the regionalization of the distributions of other input variables in the Monte Carlo Simulation technique. The developed FORTRAN program was then applied and derived flood frequency curves were obtained for the three test catchments with various candidate regions consisting of one, two, three, four and five pluviograph stations. Finally, the new technique was applied to additional 12 test catchments and results were compared with the Probabilistic Rational Method and Quantile Regression technique. The technique presented here is readily applicable to Victoria; however, this can easily be extended to other states. The application of the technique involves the following steps: 1) Obtain the latitude and longitude of the ungauged catchment within Victoria for which design flood estimation is required. 2) Run the FORTRAN program (ucat1.for) and enter the latitude and longitude of the ungauged catchment selected in Step (1). 3) Enter the radius of the proposed region and note the number of pluviograph stations falling within the region. 4) If the number of pluviograph stations obtained in (3) is other than 4, increase/decrease the radius of the zone so that the final zone contains 4 pluviograph stations. This is because it was found that region with 4 pluviograph stations provided relatively more accurate derived flood frequency curve. 83 5) Once the radius of the zone is finalised, the program computes the IFD table in the ungauged catchment based on the selected IFD tables of the four pluviograph stations falling within the region and prepare the database of the observed temporal patterns. 6) Run the program mcdffc3.for to generate the derived flood frequency curve for the ungauged catchment. In running this program, select the value of storm-core duration as per the location of the ungauged catchment in one of the four stormcore duration zones shown in Figure 5.3.1. The parameters of the initial loss distribution are obtained from Section 5.3.4. The values of continuing loss, storage delay parameter (k), non-linearity parameter (m) and baseflow are obtained from Section 5.3.5. Use 20,000 simulation runs in obtaining the derived flood frequency curve. 6.2 CONCLUSIONS This thesis attempts to extend the Monte Carlo Simulation technique to ungauged catchments for design flood estimation. The new technique has been applied to Victorian pluviograph stations and selected test catchments. Following conclusions can be made from this study: • It has been found that the Monte Carlo Simulation technique can successfully be applied to ungauged catchments. The developed FORTRAN program allows estimation of intensity-frequency-duration curves at an ungauged catchment in Victoria based on a region defined by the user that consists of one to five nearest • pluviograph stations. The independent testing of the new technique shows that the median relative error in design flood estimates by this technique ranges from 49 to 66% which was found to be higher than those of the Probabilistic Rational Method (for this median relative errors were in the range 41% to 47%) and the Quantile Regression technique (which had median relative errors in the range 28% to 51%). The possible reasons for the Joint Probability Approach of having a higher 84 relative error is that the test catchments used in this study were included in the data set of derivation of the runoff coefficients in the Australian Rainfall and Runoff and Quantile Regression Technique by Rahman (2005). Another reason may be that the Joint Probability Approach adopted provisionally developed regional estimation equation for storage delay parameter (k) of the runoff routing model, and regional average continuing loss value which were obtained from a very small data sample. It was found that derived flood frequency curves from the Joint Probability Approach were very sensitive to both k and continuing loss • values. The developed new technique can further be improved by addition of new and improved regional estimation equations of initial loss, continuing loss and storage delay parameter (k) as and when these are available. 6.3 RECOMMENDATION FOR FURTHER STUDY To enhance the developed method of design flood estimation for the ungauged catchment following research should be undertaken: • • • Develop new and improved regional estimation equations for initial loss, continuing loss and storage delay parameter (k) of the runoff routing model. Test the new technique to other study area. Examine whether the climate change has affected the distributions of rainfall duration, intensity and temporal patterns and if so its implication on the derived • • flood frequency curves. Validate the technique for a dataset which has not been used in the development of the Probabilistic Rational Method and Quantile Regression Technique. Results of this study show that Joint Probability Approach (JPA) although represents the slopes of the flood frequency curves very well, there is consistent underestimation in the flood magnitudes. Some hybrid method combining JPA and quantile estimates can further improves design flood estimates for ungauged catchments. 85 REFERENCES Ahern, P. A. and Weinmann, P. E. (1982). Considerations for Design Flood Estimation Using Catchment Modelling. Hydrology and Water Resources Symopsium, Melbourne, Australia, 44-48. Bates, B. C. (1994). Regionalisation of Hydrologic Data: A Review. Cooperative Research Centre for Catchment Hydrology (CRCCH) Report 94/5. Dept. of Civil Eng., Monash University, Australia. Becciu, G., Brath, A. and Rosso, R. (1993). A Physically Based Methodology for Regional Flood Frequency Analysis. Pro. ASCE Hydraul. Div. San Francisco, 461466. Benson, M. A. (1962). Estimation of Design Floods and the Problem of Equating the Probability of Rainfall and Runoff. Symposium on the Design of Water Resources Projects With Inadequate Data, Madrid, Spain, 33-50. Beran, M. A. (1973). Estimation of Design Floods and the Problem of Equating the Probability of Rainfall and Runoff. Symposium on the Design of Water Resources Projects With Inadequate Data, Madrid, Spain, 33-50. Beven, K. J. (1986), Hillslope Runoff Process and Flood Frequency Charcteristics, Hillslope Processes, Edited by A.D. Abrahams, Allen and Unwin, 181-202. Bloschl, G. and Sivapalan, M. (1997). Process Controls on Flood Frequency. 2. Runoff Generation, Strom Properties and Return Period. Centre for Water Research 86 Environmental Dynamics Report, ED 1159 MS, Department of Civil Engineering, The University of Western Australia. Boughton, W., Srikanthan, S. and Weinmann, P. E. (2000). Benchmarking A New Design Flood Estimation System. Hydro 2000, 3rd International Hydrology and Water Resources Symposium of the Institution Engineers, Australia, Perth, Australia, the Institution of Engineers, Australia. Boughton, W. and Droop, O. (2003). Continuous Simulation for design flood estimation- a review. Environmental Modelling & Software, 18, 309-318. Carroll, D. G. (1994). The BCC Catchment Management Runoff Routing Model Manual, Version 3.3, Brisbane City Council, Brisbane, Australia. Carroll, D. and Rahman, A. (2004). Investigation of subtropical rainfall characteristics for use in the Joint Probability Approach to design flood estimation. In Proc. Second Asia Pacific Association of Hydrology and Water Resources (APHW) Conference, 5-8 July 2004, 2, 27-34. Cadavid, L. J., Obeyekera, T. B. and Shen, H. W. (1991). Flood Frequency Derivation from Kinematic Wave, J. Hydraulic. Eng. ASCE, 117(4), 489-510. Charalambous, J. and Rahman, A. and Carroll, D. (2003). Application of Monte Carlo Simulation Technique with URBS model for design flood estimation of large catchments. In Proc. International Congress on Modelling and Simulation, p.885-890, 14-17 July, Townsville, Australia. Clarke, C.O. (1945). Storage and the Unit Hydrograph. Transaction of ASCE., 110, 1419-1488. 87 CSIRO Atmospheric research (2001) More droughts, more flooding rains. Press Release, 8 May 2001. http://www.dar.csiro.au/news/2001/mr05.html Diaz-Grandos, M. A., Valades, J. B. and Bras, R. L. (1984) A Physically Based Flood Frequencies Distribution. Water Resources Research, 20, 7, 995-1002. Durrans, S. R. (1995). Total Probability Methods for Problems in Flood Frequency Estimation, in Statistical and Bayseian Methods in Hydrological Sciences, Proceedings of the International Conference in Honour of Jacques Bernier, Sep. 1113, Chapter III, UNESCO, Paris. Eagleson, P.S. (1972). Dynamics of Flood Frequency. Water Resource Research, 8, 4, 878-898. Feldman, A.D. (1979), Flood Hydrograph and peak flow Frequency Analysis (Technical paper No 62), The Hydrologic Engineering Centre. San Francisco. Fontaine, T. A. and Potter, K. W. (1993). Estimating Exceedance Probabilities of Extreme Floods. San Francisco, A.H. Division Ed., 635-640. Goel, N.K., Kurothe, R.S., Mathur, B.S., Vogel, R.M., (2000). A derived flood frequency distribution for correlated rainfall intensity and duration. J. Hydrol. 228, 56-57. Haan, C. T. and Wilson B. N. (1987), Another Look at the Joint Probability of Rainfall and Runoff, Hydrologic Frequency Modelling, Edited by V. P. Singh, Reidel Publishing Company, 569-575. Haan, C.T. and Edwards, D.R. (1986). Joint Probability Estimates of Return Period Flows. Transactions of the ASAE, 31(4). 88 Haddad, K. and Rahman, A. (2005). Regionalisation of Rainfall Duration in Victoria for Design Flood Estimation Using Monte Carlo Simulation. International Congress on Modelling and Simulation, Melbourne, 12-15 Dec, 2005. (In press). Hebson, C. T. and Wood, E, F. (1982). A Derived Flood Frequency Distributing Using Horton Order Ratios, Water Resources Research, 18, 5, 1509-1518. Heneker, T., Lambert, M. and Kuczera, G. (2002). Overcoming the Joint Probability problem associated with initial loss estimation in design flood estimation. 28thHydrology and Water Resources Symposium, Institution of Engineers, Australia, 445-451. Hill, P. I. and Mein, R. G. (1996). Incompatibilities between Storm Temporal Patterns and Losses for Design Flood Estimation. Hydrology and Water Resources Symposium 1996, Hobart, Tasmania, 2, 445-451. Hoang, T. (1999). A Joint Probability Approach to Rainfall-based Design Flood Estimation. Project Proposal for PhD research, Dep. Of Civil Eng., Monash University, Clayton, Victoria, Australia. Hoang, T. (2001). Joint Probability Approach to Design Flood Estimation. Unpublished PhD Thesis., Dept. Of Civil Eng., Monash University, Australia. Hollerbach, D. and Rahman , A. (2003). Study of Runoff Coefficients Associated with the Probabilistic Rational Method for Flood Estimation in South-east Australia In Proc. 28th Intl. Hydrology and Water Resources Symp., I. E. Aust., Wollongong, Australia, 10-13 Nov. 2003, Vol. 1, 199-203. Hosking, J.R.M. and Wallis, J.R. (1993). Some statistics useful in regional frequency analysis. Water Resources Research. 29(2), 271-281. 89 Huber, W. C., Cunningham , B. A. and Cavender , K.A.(1986). Continuous SWMM Modelling for Selection of Design Events. Comprison of Urban Drainage Models with Real Catchment Data, Dubrovnik, Yugosslavia, C. Maksimocic & M. Radojkovic Ed. Iacobellis, V. and Fiorentiono, M. (2000). Derived distribution of floods based on the concept of partial area coverage with a climate appeal, Water Resources Research, 36(2), 469-482. Institution of Engineers Australia (1997). Australian Rainfall and Runoff. Institution of Engineers, Australia. Institution of Engineers Australia (1987). Australian Rainfall and Runoff. Institution of Engineers, Australia. Institution of Engineers Australia (1977). Australian Rainfall and Runoff. Institution of Engineers, Australia. Institution of Engineers Australia (1958). Australian Rainfall and Runoff. Institution of Engineers, Australia. James, W. and Robinson, M. (1986). Continuous Deterministic Urban Runoff Modelling. Comparison Of Urban Drainage Models with Real Catchment Data, Dubrovnik, Yugoslavia, C. Maksimovic & M. Radojkovic Ed. 163 pp. Kader, F. and Rahman, A. (2004). Regionalisation of design rainfalls in Victoria Australia for design flood estimation by Joint Probability Approach. In Proc. Second Asia Pacific Association of Hydrology and Water Resources (APHW) Conference, 5-8 July 2004, 2, 3-10. 90 Kuczera, G., Lambert, M., Heneker, T., Jennings, S., Frost, A. and Coombes, P. (2003). Joint Probability and Desgn Storms at the Crossroads. Keynote paper. 28th International Hydrology and Water Resources Symosium, I. E. Aust, 11-13 Nov, Wollongogng, Australia. Kuczera, G., Coombes, J. P. (2002). A Comparative Assessment of Flood Performance of Volume-sensitive Systems. Waterfall Journal, Winter, 7-13. Kuczera, G., Williams, B., Binning, P. and Lambert, M. (2000). “An education web site for free water engineering software.” Hydro 2000, 3rd International Hydrology and Water Resources Symposium of the Institution of Engineers. Perth, Australia. Laurenson, E.M. and Pearse, M.A. (1997), Frequency of Extreme Rainfall and Floods. International Hydrology & Water Resources Symposium, Perth, 392-399. Laurenson, E. M. (1974). Modelling of Stochastic-Deterministic Hydrologic Systems. Water Resources Research, 10, 5, 955-961. Laurenson, E. M. and Mein, R.G. (1997). RORB Version 4 Runoff Routing Program User Manual, Dep. Of Civil Eng., Monash Universities.186 pp. Laurenson, E. M. (1973). Effects on Dams on Flood Frequency. International Symposium On River Mechanics, Bangkok, Thailand, I. A. F. H. Research Ed., 133146. Lumb, A. M. and James, L. D. (1976). Runoff files for flood hydrograph simulation. Journal of the Hydraulics Division, ASCE, 1515-1531. Mcdermott, D. and Pilgrim, I. (1982). Rainfall Temporal Patterns for Design Floods. Journal of the Hydraulics Division, 101, Hy1, 81-95. 91 Ministry for Regional Services, Territories and Local Govt (MRSTLG) (1999). Budget statements 1999-2000. http://www.dotars.gov.au/dept/budget/9900/macdon/MBudget4_99.htm. Moughamian, M. S., McLaughlin, D. B, and Bras, R. L, (1987). Estimation of Flood Frequency: An Evaluation of two derived distribution procedures, Water Resour, Res., 23(7), 1309-1319. Muzik, I. (1993), Derived, Physically based distribution of Flood Probabilities, Extreme Hydrological Events: Precipitation, Floods and Droughts (Proceedings of the Yokohamma Symp, July 1993, IAHS Publ, No.213, 183-188. Muzik, I. (1994). Understanding flood Probabilites. Stochastic and Statistical Methods in Hydrology and Environmental Engineering, Vol. 1, 199-207, K. W. Hipel (ed), Kluwer Academic Publishers, Netherlands. Muzik, I. (2002). A first-order analysis of the climate change effect on flood frequencies in a subalpine watershed by means of a hydrological rainfall-runoff model. Journal of Hydrology, 267, 65-73. Muzik, I. and Beersing, A. K. (1989). Stochastic-Deterministic Nature of an Elemental Rainfall Runoff Process. Water Resour. Res. Vol. 25, No. 8. 1805-1814. Nathan. R. J. and Weinmann P.E. (2004). An improved framework for the characterisation of extreme floods and for the assessment of dam safety. Hydrology and Water Resources Symposium, Institution of Engineers, Australia, May 2002. 186 pp. Philip, J. R. (1957). The theory of Infiltration, 1, The infiltration equation and its solution, Soil Sci., 83, 345-357. 92 Raines, T. H. and Valades, J. B. (1993). Estimation of Flood frequencies for Ungauged Catchments. J. Hydraulic Eng., Am. Soc. Civ. Eng., 119(10), 1138-1154. Rahman, A., Weinmann, E., Hoang, T. and Laurenson, E. (1998). Joint Probability Approaches To Design Flood Estimation: A Review. Technical Report No. 98/8. CRC for Catchment Hydrology. Rahman, A., Bates, B.C, Mein, R.G. and Weinmann, P.E. (1999), Regional Flood Frequency Analysis for Ungauged basins in South-Eastern Australia. Australian Journal of Water Resources, 3(2), 199-207. Rahman, A., Weinmann, P.E., Mein, R.G. (2000). Probabilistic nature of initial losses and its impacts on Design Flood Estimates. In Proc, 3RD Intl, Hydrology and Water Resources Symp., Perth, Western Australia, 20-23 Nov., 2000, Vol, 1, 71-75. Rahman, A., Weinmann, E., Hoang, T. and Laurenson, E.(2001). Monte Carlo Simulation of Flood Frequency Curves From Rainfall, Technical Report No. 1/4. CRC for Catchment Hydrology, Monash University, March. Rahman, A., Weinmann , P.E., Hoang, T.M.T, Laurenson, E.M. (2002) Monte Carlo Simulation of flood frequency curves from rainfall. Journal of Hydrology, 256 (3-4), 196-210. Rahman, A. and Weinmann, E. (2002a). Flood Estimation in Northern Australian Catchments Using Monte Carlo Technique. Proc. 27th National Hydrology and Water Resources Symp., The Water Challenge, Balancing the Risk, I. E. Aust., 20-23 May, Melbourne. CD-ROM Publication. Rahman, A., Weinmann , P.E., and Mein, R.G. (2002b). The use of probabilitydistributed initial losses in design flood estimation. Australian Journal of Water Resources. 6(1), 17-30. 93 Rahman, A., Carroll, D and Weinmann, P.E. (2002c). Integration of Monte Carlo Simulation technique with URBS model for design flood estimation. Proc. 27th National Hydrology and Water Resources Symp., The Water Challenge, Balancing the risk, I.E.Aust., 20-23 May, Melbourne. CD-ROM Publication. Rahman, A., Bates, B.C., Mein, R.G. and Weinmann , P.E..(2002d). Discussion on the paper ‘Regional flood frequency analysis for ungauged basins in south-eastern Australia’. Australian Journal of Water Resources. 4(2): 171-174. Rauf, A. and Rahman, A. (2004). Study of fixed-duration design rainfalls in Australian Rainfall and Runoff and Joint Probability based design rainfalls. In Proc. Second Asia Pacific Association of Hydrology and Water Resources (APHW) Conference, 5-8 July 2004, 2, 60-67. Rahman, A., and Carroll, D. (2004). Appropriate spatial variability of flood producing variables in the Joint Probability Approach to design flood estimation. British Hydrological Society International Conference, London, 12-16 July, 2004, 1, 335-340. Rahman, A. (2005). A quantile regression technique to estimate design floods for ungauged catchments in South-east Australia. Australian Journal of Water Resources. Vol 9, No.1. Accepted on 12 April 2005. (In press) Rijal, N. and Rahman, A. (2005). Design flood estimation in ungauged catchments: Quantile Regression technique and Probabilistic Rational Method compared. (Under review) Russell, S. O., Kenning, B. F. Land Sunnell, G. J. (1979). Estimating Design Flows For Urban Drainag. Journal Of the Hydraulics Division, 105, 43-52. 94 Rodriguez-Iturbe, I. and Valdes, J.B. (1979), The Geomorphologic structure of Hydrologic response, Water Resour, Res., 15(6), 1409-1420. Schaake, J. C., Geyer, J. C. and Knapp, J. W. (1967), Experimental Examination of the Rational Method, Proc, Am, Soc, of Civil Engineers, Vol, 93 (Hy6), 353-370. Shen, H. W., Koch, G. J. and Obeysekera, J. T. B. (1990). Physically Based Flood Features and Frequencies. J. Hydraulic. Eng., Vol. 116, No.4. 494-514. Siriwardena, L., Weinmann, P.E., (1997). Review of continuous simulation approaches to design flood estimation-draft report, Unpublished Report, CRC for Catchment Hydrology, Monash University, Melbourne. Sivaplan, M., Beven, K. J, and Wood, E, F, (1990), On Hydrologic Similarity, 3, A Dimensionless Flood Frequency Model Using a Generalised Geomorphic Unit Hydrograph and Partial Area Runoff Generation, Water Resour, Res., 26(1), 43-58. Sivapalan, M., Bloschl, G. and Gutknecht, D. (1996). Process Controls on Flood Frequency. 1. Derived Flood Frequency. Centre for Water Research Environmental dynamics Report, ED 1158 MS, Department of Civil Eng., The University of Western Australia. Soil Conservation Service (1972). Section 4: Hydrology. National Engineering Handbook Washington D.C.: U.S. Department of Agriculture. Tavakkoli, D. (1985). Simulation von Hochwasserwellen aus Niederschlagan. PhD Thesis, Inst.f. Hydraulic, Technical University of Vienna. Thomas, W.O. (1982). An Evaluation of flood frequency estimates based on Rainfall-runoff modelling. Water Resour. Bull. 18 (2), 221-230. 95 Torch, P. A., Smith, J. A., Wood, E, F. and Troch, F. De. (1994). Hydrologic controls of large floods in a small basin: Central Appalachian case study, J. Hydrol., 156, 285309. Vogel, R.M. McMahon, T.A. and Chiew, F.H.S. (1993). Flood flow frequency model selection in Australia. Journal of Hydrology., 146, 421-449. Walsh, M. A., Pilgrim, D. H. and Cordery, I. (1991). Initial Losses for Design flood Estimation in New South Wales. International Hydrology and Water Resources Symposium, Perth, I. E. Aust. Nat. Conf. Pub. No. 91/19,283-288. Weinmann, P.E. (1994). On the Origin and Variation of Skewness in Flood Frequency Distributions. Water Down Under’94, Adelaide, Australia, 265-270. Weinmann, P.E., Rahman, A., Hoang, T., Laurenson, E.M. and Nathan, R. J. (1998). A new modelling framework for design flood estimation. Proc. Intl. Symp. On Stormwater Management and Intl. Conference on Hydrualics in Civil Engineering 2730 Sep 1998, Adelaide, Australia. 393-398. Weinmann, P. E., Rahman, A., Hoang, T.M.T., Laurenson, E.M. and Nathan, R. J. (2000). Monte Carlo Simulation of flood frequency Curves from Rainfall-The Way Ahead, Australian Journal of Water Resources, Vol.6, No. 1, 71-79. Weinmann, P.E., Rahman, A., Hoang, T.M.T, Laurenson, E.M., Nathan, R.J.(2002) Monte Carlo simulation of flood frequency curves from rainfall-the way ahead. Australian Journal of Water Resources. 6(1), 71-80. Wood, E. F. and Hebson, C.S. (1986). On hydrologic similarity, 1, Derivation of Flood Frequency curve. Water Resources. Res., 22, 1549-1554. 96 Yue, S. (2000). The Gumbel Mixed Model Applied to Storm Frequency Analysis. Water Resources Management, 14, 377-389. APPENDIX A LIST OF STUDY PLUVIOGRAPH STATIONS Table A-1 List of study pluviograph stations ID 76031 77087 79046 79052 79079 79082 79086 80006 80102 80109 80110 81003 81013 81026 81038 81049 81114 81115 82011 82016 82039 82042 82076 82107 82121 83017 83025 83031 83033 Name Mildura MO Hopetoun RWC Wartook Reservoir Rocklands Res. Tottington Horsham Avon R No. 3 Charlton PO Pyramid Hill Cobram Kerang Bendigo Prison Dookie Ag. College Laaenecoorie Weir Natte Yallock Tatura Tatura (Theiss) Wanalta Ck (DAEN) Corryong Euroa Rutherglen Strathbogie PO Dartmout Res Lake Nillahcootie Wangaratta (Ovens R) Jamieson PO Omeo Whitfield Woods Point Latitude (degree) 34.23 35.7 37.1 37.2 36.79 36.7 36.86 36.3 36.06 35.9 35.73 36.75 36.37 36.83 36.94 36.44 36.44 36.63 36.21 36.76 36.11 36.85 36.55 36.86 Longitude (degree) 142.08 142.30 142.40 141.90 143.12 142.20 143.12 143.40 144.12 145.60 143.92 144.28 145.70 143.89 143.47 145.23 145.22 144.87 147.89 145.55 146.51 145.73 147.49 146.00 36.35 37.31 37.11 36.75 37.56 146.34 146.14 147.59 146.41 146.24 97 83067 83074 84005 84015 84078 84112 84122 84123 84125 85000 85034 85072 85103 85106 85170 85176 85237 85256 86038 86071 86074 86085 86142 86219 86224 86314 87017 87029 87031 87033 87036 87097 87104 87105 87133 87153 88023 88029 88037 88049 88153 89016 89025 89094 90058 90166 Bright Shire Council Lake William Hovell Buchen PO Ensay Composite Sarsfield East Cann River PO Genoa Wroxham 2 Crooked River Aberfeldy Glenmaggie Weir East Sale AMO Yallourn SEC Olsens Bridge Traralgon L.V.W Tanjil Bren PO Noojee Eng. HMSD Barkley River Essendon Airport Melb. Regional Office Mitcham Narre Warren Nth Mt St Leonard Coranderrk Dandenong Comp. Koo-Wee-Rup Blackwood Lancefield Laverton AMO Little River Macedon-Forestry Parwan Werribee Cattle Yard Werribee Sewerage Geelong Nth Lerderderg R No.3 Lake Eildon Heathcote PO Lauriston Res Puckapunayal Spring Ck No. 2 Lake Bolac PO Skipton Warrambine No. 3 Mortlake Winchelsea 36.73 36.92 37.5 37.37 37.75 37.56 37.48 37.35 37.38 37.7 37.91 38.11 38.18 38.48 38.22 37.83 37.88 37.52 37.73 146.96 146.38 148.17 147.84 147.73 149.15 149.64 149.48 147.11 146.36 146.81 147.13 146.33 146.33 146.50 146.18 146.00 146.55 144.90 37.81 37.83 37.99 37.57 37.68 38.01 38.2 37.47 37.26 37.86 37.99 37.4 37.7 144.96 145.19 145.34 145.51 145.56 145.19 145.49 144.31 144.71 144.75 144.49 144.55 144.32 37.97 37.95 38.12 37.46 37.23 36.93 37.25 37.00 37.09 37.72 37.68 37.83 38.08 38.25 144.63 144.62 144.36 144.40 145.91 144.71 144.38 145.00 145.71 142.84 143.37 143.88 142.79 143.97 98 APPENDIX B INPUT AND OUTPUT LISTS FOR FORTRAN PROGRAM UCAT1.FOR Inputs: • • Latitude of the ungauged catchment in degrees. • Radius of the candidate zone in km. • directory. • Longitude of the ungauged catchment in degrees. IFD tables of the pluviograph stations in the study region should be in the Temporal patterns data base of the pluviograph stations in the study region should be in the directory. Outputs: • • Weighted average IFD table of the ungauged catchment. Dimensionless temporal pattern file for the ungauged catchment. 99 APPENDIX C DISTRIBUTIONS OF STORM-CORE DURATIONS (Dc values are in hour) Station 77087 Station 79079 80 70 60 70 60 50 40 30 20 10 Frequency Frequency 100 90 80 50 40 30 20 10 0 0 1--10 11--20 21--30 31--40 1--10 41--50 11--20 21--30 120 120 100 100 80 80 F req u en cy Frequency 41--50 51--60 61--70 Station 79082 Station 79046 60 40 60 40 20 20 0 0 1--10 11--20 21--30 31--40 41--50 51--60 61--70 1--10 Storm-core dura tion (Dc) 11--20 21--30 120 Frequency 100 80 60 40 20 0 11--20 21--30 31--40 41--50 51--60 Station 79086 140 1--10 31--40 Storm core durations (Dc) Station 79052 Frequency 31--40 Storm-core durations (Dc) Storm-core duration (Dc) 41--50 Storm-core durations (Dc) 51--60 61--70 100 90 80 70 60 50 40 30 20 10 0 1--10 11--20 21--30 31--40 41--50 51--60 Storm-core durations (Dc) 100 Station 80006 Station 81013 30 20 Frequency Frequency 25 15 10 5 0 1--10 11--20 21--30 31--40 180 160 140 120 100 80 60 40 20 0 1--10 41--50 11--20 Station 80102 40 Frequency Frequency 50 30 20 10 0 11--20 21--30 41--50 51--60 61--70 31--40 41--50 90 80 70 60 50 40 30 20 10 0 1--10 51--60 11--20 Storm-core durations (Dc) 21--30 31--40 41--50 51--60 61--70 71--80 61--70 71--80 Storm-core duration (Dc) Station 81038 Station 80110 70 120 60 Frequency 100 Frequency 31--40 Station 81026 60 1--10 21--30 Storm-core duration (Dc) Storm-core durations (Dc) 80 60 50 40 30 20 10 40 0 20 1--10 0 11--20 21--30 31--40 41--50 51--60 Storm-core duration (Dc) 1--10 21--30 11--20 31--40 41--50 51--60 Storm -core durations (Dc) Frequency Station 88023 Station 81003 120 Frequency 100 200 150 100 50 0 60 1--10 11-- 21-- 31-- 41-- 51-- 61-20 30 40 50 60 70 40 Storm-core duration (Dc) 80 20 0 1--10 11--20 21--30 31--40 41--50 51--60 61--70 Storm-core dura tion (Dc) 101 Station 88153 100 Frequency Frequency Station 88029 50 0 40 30 20 10 0 1--10 1--10 11--20 21--30 31--40 41--50 51--60 11--20 21--30 31--40 Storm-core duration (Dc) Storm-core dura tion (Dc) 200 150 100 50 0 Station 89016 1--10 11-- 21-- 31-- 41-- 51-- 61-20 30 40 50 60 70 Storm-core duration Frequency Frequency Station 88037 150 100 50 0 1--10 11--20 21--30 31--40 41--50 51--60 Storm-core duration (Dc) 60 Station 89025 40 20 0 1--10 11--20 21--30 31--40 Storm-core duration (Dc) Frequency Frequency Station 88049 60 40 20 0 1--10 11--20 21--30 31--40 41--50 51--60 Storm-core duration (Dc) 102 Station 81013 Station 89094 Frequency Frequency 200 40 30 20 10 0 1--10 11-20 21-30 31-- 41-40 50 51-60 61-70 150 100 50 0 1--10 Storm-core duration (Dc) 11--20 31--40 41--50 51--60 61--70 51-60 61-70 Station 81026 Station 90058 100 100 80 50 0 1--10 11-- 21-- 31-- 41-- 51-- 61-20 30 40 50 60 70 Frequency Frequency 21--30 Storm-core duration (Dc) 60 40 20 0 1--10 Storm-core dura tion (Dc) 11--20 21--30 31--40 41--50 Storm-core duration (Dc) Station 81038 70 60 40 20 0 60 1--10 11-20 21-30 31-- 41-40 50 51-60 Storm-core duration (Dc) 61-70 Frequency Frequency Station 90166 50 40 30 20 10 0 1--10 11--20 21--30 31--40 41--50 51--60 60--71 71--80 Storm-core duration (Dc) 103 Station 82016 100 100 80 80 Frequency Frequency Station 81049 60 40 20 60 40 20 0 0 1--10 11--20 21--30 31--40 41--50 1--10 11--20 S torm -core duration (Dc) 21--30 31--40 41--50 51--60 Storm -core duration (Dc) Station 81114 60 Station 82039 40 30 20 10 0 1--10 11--20 21--30 31--40 41--50 51--60 Frequency Frequency 50 Storm-core duration (Dc) 80 70 60 50 40 30 20 10 0 1--10 11--20 21--30 31--40 41--50 51--60 Storm -core duration (Dc) Station 81115 100 Station 82042 60 120 40 100 20 0 1--10 11--20 21--30 31--40 41--50 Storm-core duration (Dc) 51--60 Frequency Frequency 80 80 60 40 20 0 1--10 11--20 21--30 31--40 41--50 51--60 61--70 71--80 81--90 S torm-core duration (Dc) 104 Station 83017 80 70 60 50 40 30 20 10 0 Frequency Frequency Station 82076 1--10 160 140 120 100 80 60 40 20 0 11--20 21--30 31--40 41--50 51--60 61--70 71--80 1--10 11--20 21--30 31--40 41--50 51--60 61--70 71--80 81--90 Storm -core duration (Dc) Storm-core duration (Dc) Station 82107 Station 83025 150 25 100 20 50 0 1--10 11--20 21--30 31--40 41--50 51--60 61--70 71--80 Frequency Frequency 200 15 10 5 Storm-core duration (Dc) 0 1--10 11--20 21--30 31--40 41--50 Storm-core duration (Dc) Station 82121 120 Station 83031 80 140 60 120 40 20 0 1--10 11--20 21--30 31--40 Storm-core duration (Dc) 41--50 Frequency Frequency 100 100 80 60 40 20 0 1--10 11--20 21--30 31--40 41--50 51--60 61--70 71--80 Storm-core duration (Dc) 105 Station 84005 80 70 60 50 40 30 20 10 0 100 80 Frequency Frequency Station 83033 60 40 20 0 1--10 21--30 31--40 41--50 Storm-core duration (Dc) Station 83067 Station 84015 100 100 80 80 60 40 20 51--60 60 40 20 0 0 1--10 11--20 21--30 31--40 41--50 51--60 61--70 1--10 11--20 21--30 31--40 Storm-core duration (Dc) Storm-core duration (Dc) Station 83074 Station 84078 35 120 30 100 25 Frequency Frequency 11--20 Storm -core duration (Dc) Frequency Frequency 1--10 11--20 21--30 31--40 41--50 51--60 61--70 71--80 81--90 20 15 10 41--50 80 60 40 20 5 0 0 1--10 11--20 21--30 31--40 41--50 51--60 61--70 71--80 Storm-core duration 1--10 11--20 21--30 31--40 41--50 51--60 61--70 Storm-core duration (Dc) 106 Station 84112 Station 84125 70 20 15 Frequency Frequency 60 10 5 50 40 30 20 10 0 0 11--20 21--30 31--40 1--10 41--50 21--30 31--40 51--60 41--50 Storm-core duration (Dc) Station 84122 Station 85000 70 35 60 30 50 25 40 30 20 61--70 20 15 10 10 5 0 0 1--10 11--20 21--30 31--40 41--50 51--60 61--70 1--10 11--20 21--30 31--40 41--50 Storm-core duration (Dc) Storm-core duration (Dc) Station 84123 Station 85026 30 51--60 60 50 Frequency 25 Frequency 11--20 Storm -core duration (Dc) Frequency Frequency 1--10 20 15 10 40 30 20 10 5 0 0 1--10 11--20 21--30 31--40 Storm-core duration (Dc) 41--50 1--10 11--20 21--30 31--40 41--50 51--60 Storm-core duration (Dc) 107 Station 85034 Station 85106 140 100 Frequency Frequency 120 80 60 40 20 0 1--10 11--20 21--30 31--40 41--50 51-60 80 70 60 50 40 30 20 10 0 61--70 1--10 11--20 Storm-core duration (Dc) 21--30 31--40 41--50 51--60 61--70 Storm-core duration (Dc) 160 140 120 100 80 60 40 20 0 Station 85170 70 60 1--10 11--20 21--30 31--40 41--50 51--60 61--70 Frequency Frequency Station 85072 Storm-core duration (Dc) 50 40 30 20 10 0 1--10 11--20 21--30 31--40 41--50 Storm-core duration (Dc) Station 85103 100 Station 85176 60 40 20 0 1--10 11--20 21--30 31--40 41--50 Storm-core duration (Dc) 51--60 Frequency Frequency 80 80 70 60 50 40 30 20 10 0 1--10 11--20 21--30 31--40 41--50 51--60 61--70 Storm-core dura tion (Dc) 108 Station 86074 70 120 60 100 50 Frequency Frequency Station 85237 40 30 20 60 40 20 10 0 0 1--10 11--20 21--30 31--40 41--50 51--60 61--70 71--80 1--10 11--20 21--30 31--40 41--50 Storm-core duration (Dc) Storm-core duration (Dc) Station 85256 Station 82011 60 120 50 100 Frequency Frequency 80 40 30 20 10 51--60 80 60 40 20 0 0 1--10 11--20 21--30 31--40 41--50 51--60 Storm-core duration (Dc) 1--10 11--20 21--30 31--40 41--50 51--60 Storm-core duration (Dc) Station 86038 120 Frequency 100 80 60 40 20 0 1--10 11--20 21--30 31--40 41--50 Storm-core duration (Dc) Station 86071 500 Frequency 400 300 200 100 0 1--10 11--20 21--30 31--40 41--50 51--60 61--70 71--80 Storm-core duration (Dc) 109 APPENDIX D: IFD TABLES (Intensity values are in mm/h and ARI in years) Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 6.978 3.585 1.127 0.219 0.09 0.052 0.033 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 7.308 4.641 1.703 0.293 0.099 0.049 0.027 77087 ARI-1 8.488 4.584 1.849 0.663 0.417 0.323 0.265 ARI1.11 9.238 5.037 2.047 0.731 0.457 0.351 0.286 ARI1.25 10.076 5.544 2.269 0.807 0.501 0.383 0.311 ARI-2 13.421 7.561 3.153 1.111 0.676 0.51 0.407 ARI-5 19.944 11.488 4.875 1.703 1.019 0.757 0.597 ARI-10 24.878 14.458 6.178 2.15 1.278 0.945 0.74 ARI-20 29.813 17.426 7.481 2.598 1.537 1.132 0.884 ARI-50 36.337 21.35 9.203 3.19 1.88 1.38 1.074 ARI-100 41.273 24.318 10.506 3.637 2.139 1.567 1.218 ARI-500 52.732 31.209 13.531 4.677 2.741 2.003 1.553 ARI1000 57.667 34.177 14.834 5.125 3 2.19 1.697 ARI1000000 106.852 63.751 27.817 9.586 5.583 4.06 3.132 79046 ARI-1 11.248 6.948 3.191 1.164 0.696 0.513 0.4 ARI1.11 12.007 7.344 3.353 1.236 0.747 0.556 0.438 ARI1.25 12.856 7.787 3.534 1.315 0.805 0.605 0.48 ARI-2 16.248 9.548 4.257 1.632 1.037 0.801 0.653 ARI-5 22.874 12.972 5.661 2.246 1.489 1.19 1 ARI-10 27.891 15.557 6.721 2.71 1.832 1.486 1.267 ARI-20 32.911 18.14 7.781 3.172 2.175 1.784 1.537 ARI-50 39.549 21.553 9.18 3.783 2.629 2.178 1.895 ARI-100 44.572 24.133 10.239 4.244 2.973 2.477 2.168 ARI-500 56.238 30.122 12.695 5.315 3.771 3.173 2.802 ARI1000 61.263 32.701 13.753 5.777 4.114 3.473 3.076 ARI1000000 111.35 58.392 24.291 10.37 7.54 6.468 5.815 110 Duration(hours) 1 2 6 24 48 72 100 Station 82011 ARI-0.1 9.332 5.14 1.773 0.376 0.159 0.093 0.06 ARI-1 12.116 7.093 3.167 1.234 0.794 0.62 0.51 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 9.791 5.042 1.623 0.337 0.145 0.087 0.057 ARI1.11 12.705 7.487 3.357 1.3 0.83 0.644 0.527 ARI1.25 13.36 7.926 3.569 1.373 0.871 0.672 0.546 ARI-2 15.948 9.665 4.412 1.668 1.032 0.782 0.625 ARI-5 20.925 13.026 6.053 2.241 1.349 0.999 0.781 ARI-10 24.66 15.554 7.292 2.675 1.588 1.164 0.901 ARI-20 28.382 18.076 8.532 3.108 1.828 1.329 1.022 ARI-50 33.291 21.404 10.17 3.681 2.145 1.548 1.182 ARI-100 36.998 23.918 11.409 4.115 2.384 1.714 1.304 ARI-500 45.593 29.751 14.285 5.122 2.941 2.099 1.586 ARI1000 49.292 32.262 15.523 5.555 3.181 2.265 1.708 ARI1000000 86.104 57.257 27.866 9.877 5.572 3.921 2.923 82016 ARI-1 12.526 6.712 2.749 1.054 0.701 0.564 0.478 ARI1.11 13.529 7.216 2.935 1.117 0.739 0.594 0.503 ARI1.25 14.651 7.779 3.142 1.186 0.783 0.627 0.53 ARI-2 19.124 10.02 3.968 1.464 0.955 0.761 0.641 ARI-5 27.842 14.379 5.571 2.004 1.292 1.022 0.856 ARI-10 34.434 17.672 6.782 2.411 1.547 1.22 1.019 ARI-20 41.026 20.963 7.992 2.819 1.801 1.418 1.182 ARI-50 49.739 25.313 9.591 3.358 2.138 1.679 1.398 ARI-100 56.329 28.602 10.799 3.765 2.392 1.877 1.561 ARI-500 71.631 36.239 13.606 4.711 2.983 2.336 1.94 ARI1000 78.221 39.528 14.814 5.118 3.238 2.534 2.103 ARI1000000 143.893 72.298 26.854 9.176 5.773 4.504 3.729 111 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 7.597 4.18 1.486 0.346 0.156 0.096 0.065 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 10.291 5.886 2.115 0.456 0.191 0.112 0.071 82039 ARI-1 10.436 6.013 2.741 1.187 0.833 0.691 0.601 ARI1.11 11.106 6.408 2.916 1.252 0.873 0.72 0.623 ARI1.25 11.856 6.849 3.112 1.325 0.917 0.753 0.649 ARI-2 14.847 8.611 3.893 1.614 1.094 0.885 0.752 ARI-5 20.676 12.042 5.411 2.177 1.44 1.145 0.957 ARI-10 25.085 14.638 6.558 2.602 1.702 1.343 1.115 ARI-20 29.493 17.232 7.704 3.027 1.964 1.541 1.273 ARI-50 35.321 20.662 9.219 3.589 2.31 1.803 1.483 ARI-100 39.73 23.257 10.365 4.013 2.573 2.002 1.642 ARI-500 49.967 29.28 13.024 4.999 3.182 2.464 2.012 ARI1000 54.375 31.875 14.169 5.424 3.445 2.663 2.171 ARI1000000 98.311 57.726 25.58 9.652 6.061 4.648 3.762 ARI1.11 15.011 9.006 4.094 1.571 0.989 0.758 0.612 ARI1.25 16.102 9.642 4.373 1.676 1.055 0.808 0.653 ARI-2 20.448 12.175 5.486 2.095 1.318 1.011 0.818 ARI-5 28.91 17.099 7.649 2.91 1.832 1.406 1.139 ARI-10 35.307 20.82 9.282 3.526 2.221 1.706 1.382 ARI-20 41.702 24.537 10.915 4.142 2.609 2.005 1.626 ARI-50 50.153 29.45 13.072 4.956 3.123 2.401 1.948 ARI-100 56.546 33.166 14.703 5.572 3.512 2.701 2.192 ARI-500 71.388 41.791 18.49 7.002 4.415 3.397 2.758 ARI1000 77.779 45.505 20.12 7.618 4.804 3.697 3.002 ARI1000000 141.47 82.514 36.367 13.755 8.681 6.684 5.432 82042 ARI-1 14.035 8.436 3.843 1.477 0.93 0.713 0.576 112 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 9.912 5.764 2.064 0.421 0.168 0.095 0.058 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.643 5.459 2.083 0.409 0.153 0.081 0.047 82076 ARI-1 12.026 7.333 3.37 1.278 0.791 0.598 0.478 ARI1.11 12.618 7.712 3.549 1.343 0.829 0.626 0.499 ARI1.25 13.28 8.134 3.749 1.416 0.872 0.657 0.522 ARI-2 15.918 9.821 4.546 1.706 1.041 0.779 0.616 ARI-5 21.059 13.107 6.1 2.271 1.372 1.019 0.799 ARI-10 24.945 15.592 7.276 2.698 1.622 1.2 0.938 ARI-20 28.831 18.077 8.452 3.125 1.872 1.381 1.076 ARI-50 33.968 21.362 10.006 3.689 2.202 1.62 1.26 ARI-100 37.853 23.846 11.182 4.116 2.452 1.801 1.398 ARI-500 46.873 29.614 13.911 5.108 3.033 2.222 1.721 ARI1000 50.758 32.098 15.087 5.535 3.283 2.403 1.86 ARI1000000 89.468 56.853 26.803 9.79 5.774 4.208 3.244 ARI1.11 14.328 8.893 4.236 1.703 1.092 0.844 0.687 ARI1.25 15.338 9.455 4.48 1.807 1.164 0.904 0.738 ARI-2 19.354 11.684 5.446 2.217 1.452 1.144 0.947 ARI-5 27.161 15.989 7.311 3.011 2.015 1.613 1.357 ARI-10 33.057 19.23 8.714 3.609 2.44 1.97 1.67 ARI-20 38.949 22.464 10.113 4.206 2.864 2.327 1.984 ARI-50 46.736 26.732 11.96 4.995 3.426 2.799 2.399 ARI-100 52.625 29.959 13.356 5.592 3.851 3.156 2.714 ARI-500 66.295 37.444 16.593 6.976 4.837 3.986 3.446 ARI1000 72.182 40.666 17.987 7.571 5.261 4.343 3.762 ARI1000000 130.841 72.754 31.866 13.505 9.493 7.909 6.91 82107 ARI-1 13.424 8.388 4.016 1.611 1.027 0.791 0.64 113 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 7.725 4.39 1.554 0.326 0.135 0.078 0.049 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.112 5.496 2.266 0.463 0.172 0.09 0.052 82121 ARI-1 10.132 6.044 2.752 1.079 0.691 0.537 0.439 ARI1.11 10.769 6.437 2.932 1.145 0.731 0.566 0.461 ARI1.25 11.482 6.876 3.133 1.218 0.775 0.598 0.487 ARI-2 14.326 8.627 3.935 1.512 0.95 0.727 0.587 ARI-5 19.873 12.037 5.497 2.083 1.293 0.98 0.784 ARI-10 24.069 14.617 6.677 2.515 1.552 1.172 0.934 ARI-20 28.265 17.196 7.857 2.947 1.811 1.363 1.084 ARI-50 33.813 20.604 9.416 3.518 2.153 1.616 1.282 ARI-100 38.01 23.183 10.595 3.949 2.412 1.808 1.432 ARI-500 47.755 29.17 13.333 4.951 3.014 2.253 1.78 ARI1000 51.952 31.748 14.512 5.383 3.273 2.445 1.93 ARI1000000 93.779 57.441 26.261 9.683 5.855 4.357 3.426 ARI1.11 13.393 8.713 4.313 1.709 1.059 0.796 0.63 ARI1.25 14.356 9.219 4.511 1.79 1.117 0.845 0.673 ARI-2 18.216 11.229 5.299 2.112 1.349 1.041 0.846 ARI-5 25.79 15.117 6.825 2.737 1.8 1.425 1.187 ARI-10 31.544 18.043 7.974 3.209 2.14 1.716 1.446 ARI-20 37.31 20.963 9.12 3.679 2.481 2.006 1.706 ARI-50 44.944 24.816 10.634 4.301 2.93 2.391 2.052 ARI-100 50.725 27.728 11.778 4.771 3.27 2.682 2.313 ARI-500 64.161 34.482 14.432 5.862 4.059 3.359 2.921 ARI1000 69.951 37.389 15.575 6.332 4.399 3.65 3.184 ARI1000000 127.708 66.333 26.955 11.01 7.783 6.555 5.801 83017 ARI-1 12.534 8.258 4.134 1.636 1.007 0.752 0.592 114 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.102 4.461 1.582 0.365 0.164 0.1 0.067 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 9.692 5.391 1.863 0.387 0.16 0.092 0.058 83025 ARI-1 10.41 6.014 2.736 1.169 0.812 0.668 0.576 ARI1.11 11.028 6.382 2.903 1.235 0.853 0.7 0.602 ARI1.25 11.72 6.792 3.09 1.308 0.9 0.736 0.631 ARI-2 14.477 8.432 3.835 1.6 1.087 0.88 0.748 ARI-5 19.849 11.629 5.287 2.168 1.45 1.161 0.977 ARI-10 23.911 14.048 6.386 2.598 1.725 1.374 1.151 ARI-20 27.973 16.467 7.485 3.028 2 1.588 1.325 ARI-50 33.342 19.664 8.938 3.596 2.364 1.869 1.555 ARI-100 37.403 22.083 10.037 4.026 2.639 2.083 1.729 ARI-500 46.832 27.7 12.589 5.024 3.277 2.578 2.133 ARI1000 50.893 30.119 13.688 5.454 3.552 2.791 2.308 ARI1000000 91.359 54.227 24.643 9.736 6.292 4.916 4.044 ARI1.11 13.994 8.183 3.686 1.478 0.973 0.771 0.643 ARI1.25 14.826 8.685 3.92 1.574 1.036 0.821 0.684 ARI-2 18.146 10.687 4.852 1.954 1.286 1.018 0.848 ARI-5 24.62 14.588 6.669 2.695 1.773 1.402 1.166 ARI-10 29.519 17.54 8.043 3.255 2.141 1.693 1.407 ARI-20 34.418 20.491 9.417 3.816 2.509 1.984 1.648 ARI-50 40.894 24.392 11.233 4.557 2.996 2.368 1.967 ARI-100 45.793 27.343 12.606 5.117 3.364 2.658 2.208 ARI-500 57.169 34.195 15.796 6.418 4.22 3.333 2.768 ARI1000 62.069 37.146 17.169 6.978 4.588 3.624 3.009 ARI1000000 110.897 66.553 30.858 12.562 8.258 6.52 5.411 83031 ARI-1 13.25 7.734 3.477 1.393 0.917 0.727 0.606 115 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.406 5.526 2.244 0.475 0.184 0.1 0.059 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 9.712 5.674 2.108 0.474 0.203 0.12 0.077 83033 ARI-1 10.692 7.304 3.825 1.568 0.973 0.729 0.573 ARI1.11 11.266 7.672 4.027 1.676 1.054 0.797 0.632 ARI1.25 11.908 8.084 4.252 1.797 1.144 0.873 0.699 ARI-2 14.466 9.732 5.152 2.278 1.507 1.181 0.968 ARI-5 19.446 12.949 6.906 3.211 2.215 1.789 1.508 ARI-10 23.21 15.385 8.232 3.915 2.752 2.253 1.922 ARI-20 26.974 17.823 9.558 4.618 3.29 2.718 2.339 ARI-50 31.948 21.045 11.31 5.546 4.001 3.335 2.893 ARI-100 35.711 23.484 12.635 6.247 4.538 3.803 3.313 ARI-500 44.447 29.146 15.712 7.876 5.788 4.889 4.292 ARI1000 48.209 31.585 17.037 8.577 6.326 5.358 4.714 ARI1000000 85.699 55.891 30.24 15.56 11.691 10.033 8.932 ARI1.11 13.723 8.206 3.866 1.668 1.147 0.934 0.797 ARI1.25 14.696 8.736 4.099 1.775 1.227 1.004 0.861 ARI-2 18.565 10.84 5.02 2.199 1.546 1.283 1.113 ARI-5 26.079 14.911 6.804 3.019 2.166 1.825 1.609 ARI-10 31.752 17.979 8.148 3.638 2.634 2.236 1.985 ARI-20 37.42 21.043 9.489 4.255 3.102 2.647 2.361 ARI-50 44.908 25.089 11.261 5.071 3.72 3.19 2.859 ARI-100 50.571 28.147 12.6 5.687 4.187 3.601 3.236 ARI-500 63.716 35.244 15.708 7.118 5.271 4.555 4.111 ARI1000 69.376 38.299 17.045 7.734 5.738 4.965 4.488 ARI1000000 125.773 68.734 30.372 13.868 10.39 9.06 8.249 83067 ARI-1 12.852 7.731 3.658 1.573 1.075 0.872 0.741 116 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 11.285 6.692 2.466 0.519 0.21 0.119 0.074 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.013 4.8 1.881 0.464 0.211 0.129 0.085 83074 ARI-1 14.075 8.718 4.125 1.636 1.038 0.798 0.645 ARI1.11 14.629 9.045 4.287 1.717 1.099 0.849 0.691 ARI1.25 15.248 9.412 4.469 1.808 1.166 0.907 0.741 ARI-2 17.704 10.876 5.195 2.167 1.435 1.135 0.943 ARI-5 22.461 13.739 6.617 2.865 1.954 1.579 1.336 ARI-10 26.045 15.908 7.696 3.392 2.345 1.913 1.633 ARI-20 29.621 18.077 8.776 3.917 2.735 2.247 1.93 ARI-50 34.343 20.947 10.206 4.611 3.25 2.687 2.322 ARI-100 37.91 23.118 11.287 5.136 3.639 3.02 2.618 ARI-500 46.188 28.16 13.8 6.354 4.541 3.792 3.305 ARI1000 49.751 30.332 14.883 6.878 4.93 4.124 3.601 ARI1000000 85.227 51.977 25.676 12.099 8.797 7.432 6.545 ARI1.11 10.664 6.707 3.405 1.6 1.144 0.952 0.826 ARI1.25 11.478 7.233 3.684 1.738 1.245 1.038 0.901 ARI-2 14.721 9.314 4.781 2.284 1.648 1.38 1.203 ARI-5 21.024 13.33 6.889 3.339 2.433 2.051 1.799 ARI-10 25.786 16.352 8.471 4.135 3.028 2.56 2.253 ARI-20 30.545 19.367 10.049 4.928 3.622 3.071 2.708 ARI-50 36.834 23.348 12.129 5.976 4.408 3.746 3.311 ARI-100 41.591 26.357 13.701 6.768 5.002 4.257 3.768 ARI-500 52.635 33.338 17.347 8.606 6.383 5.445 4.829 ARI1000 57.39 36.343 18.916 9.397 6.978 5.957 5.287 ARI1000000 104.778 66.275 34.537 17.278 12.903 11.062 9.853 84005 ARI-1 9.934 6.234 3.154 1.476 1.053 0.876 0.76 117 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 6.866 4.513 1.845 0.4 0.157 0.087 0.052 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.124 5.038 1.934 0.407 0.161 0.09 0.054 84015 ARI-1 9.339 6.368 3.308 1.331 0.815 0.605 0.472 ARI1.11 9.99 6.762 3.504 1.427 0.885 0.664 0.523 ARI1.25 10.717 7.204 3.723 1.536 0.965 0.73 0.58 ARI-2 13.618 8.964 4.599 1.966 1.281 0.996 0.812 ARI-5 19.271 12.397 6.308 2.802 1.9 1.522 1.275 ARI-10 23.545 14.994 7.601 3.433 2.369 1.922 1.63 ARI-20 27.82 17.591 8.893 4.064 2.838 2.323 1.986 ARI-50 33.469 21.025 10.602 4.897 3.458 2.855 2.46 ARI-100 37.743 23.622 11.895 5.527 3.927 3.257 2.819 ARI-500 47.666 29.652 14.897 6.99 5.018 4.194 3.655 ARI1000 51.939 32.249 16.19 7.62 5.487 4.597 4.015 ARI1000000 94.526 58.131 29.074 13.895 10.168 8.621 7.614 ARI1.11 10.611 7 3.52 1.407 0.872 0.655 0.517 ARI1.25 11.205 7.442 3.774 1.52 0.943 0.709 0.56 ARI-2 13.586 9.198 4.781 1.966 1.228 0.925 0.732 ARI-5 18.249 12.603 6.723 2.829 1.78 1.345 1.066 ARI-10 21.784 15.172 8.185 3.48 2.197 1.663 1.319 ARI-20 25.321 17.737 9.644 4.13 2.614 1.98 1.573 ARI-50 29.999 21.127 11.569 4.988 3.165 2.401 1.908 ARI-100 33.538 23.69 13.024 5.636 3.582 2.718 2.161 ARI-500 41.759 29.638 16.4 7.142 4.549 3.456 2.75 ARI1000 45.299 32.199 17.853 7.79 4.965 3.774 3.003 ARI1000000 80.591 57.714 32.328 14.246 9.115 6.94 5.53 84078 ARI-1 10.082 6.603 3.291 1.306 0.808 0.606 0.479 118 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.039 5.445 2.355 0.556 0.23 0.131 0.08 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 11.419 6.442 2.466 0.669 0.335 0.221 0.157 84112 ARI-1 10.202 7.125 3.961 1.83 1.227 0.968 0.796 ARI1.11 10.771 7.462 4.152 1.966 1.349 1.081 0.903 ARI1.25 11.406 7.84 4.366 2.118 1.484 1.208 1.024 ARI-2 13.927 9.36 5.224 2.717 2.027 1.727 1.525 ARI-5 18.817 12.345 6.909 3.871 3.089 2.762 2.549 ARI-10 22.507 14.612 8.187 4.739 3.895 3.556 3.346 ARI-20 26.193 16.882 9.466 5.605 4.701 4.356 4.154 ARI-50 31.064 19.885 11.157 6.747 5.767 5.417 5.232 ARI-100 34.748 22.158 12.438 7.61 6.574 6.223 6.052 ARI-500 43.297 27.437 15.411 9.612 8.449 8.098 7.967 ARI1000 46.979 29.712 16.691 10.474 9.257 8.908 8.794 ARI1000000 83.661 52.386 29.456 19.055 17.309 16.99 17.081 ARI1.11 14.332 9.599 5.324 2.741 2.034 1.727 1.52 ARI1.25 14.715 10.142 5.778 2.979 2.183 1.831 1.593 ARI-2 16.295 12.265 7.59 3.933 2.771 2.242 1.882 ARI-5 19.492 16.29 11.128 5.808 3.909 3.034 2.442 ARI-10 21.953 19.284 13.809 7.235 4.766 3.627 2.861 ARI-20 24.432 22.255 16.493 8.666 5.622 4.217 3.279 ARI-50 27.724 26.159 20.045 10.563 6.75 4.994 3.829 ARI-100 30.22 29.101 22.734 12 7.602 5.58 4.244 ARI-500 36.03 35.91 28.984 15.343 9.58 6.936 5.205 ARI1000 38.535 38.835 31.677 16.785 10.43 7.52 5.618 ARI1000000 63.545 67.896 58.542 31.174 18.899 13.317 9.723 84123 ARI-1 13.996 9.108 4.917 2.529 1.902 1.633 1.455 119 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.094 5.888 2.369 0.369 0.108 0.048 0.024 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.736 6.473 2.806 0.52 0.172 0.083 0.044 84125 ARI-1 10.825 7.873 4.038 1.307 0.66 0.427 0.294 ARI1.11 11.443 8.217 4.203 1.398 0.725 0.477 0.334 ARI1.25 12.131 8.604 4.389 1.498 0.796 0.534 0.381 ARI-2 14.853 10.172 5.145 1.888 1.077 0.762 0.57 ARI-5 20.11 13.273 6.652 2.63 1.615 1.205 0.947 ARI-10 24.069 15.634 7.802 3.184 2.017 1.541 1.237 ARI-20 28.021 18.001 8.957 3.734 2.417 1.876 1.528 ARI-50 33.24 21.135 10.487 4.46 2.944 2.318 1.914 ARI-100 37.185 23.509 11.645 5.007 3.342 2.653 2.207 ARI-500 46.339 29.024 14.339 6.276 4.265 3.43 2.888 ARI1000 50.281 31.401 15.499 6.822 4.661 3.764 3.181 ARI1000000 89.541 55.098 27.077 12.253 8.608 7.096 6.112 ARI1.11 11.277 8.607 4.725 1.642 0.854 0.561 0.39 ARI1.25 11.964 9.034 4.924 1.724 0.906 0.6 0.421 ARI-2 14.709 10.737 5.716 2.05 1.115 0.758 0.545 ARI-5 20.078 14.046 7.26 2.679 1.519 1.067 0.793 ARI-10 24.147 16.543 8.426 3.153 1.825 1.303 0.983 ARI-20 28.22 19.038 9.592 3.625 2.13 1.539 1.174 ARI-50 33.608 22.332 11.132 4.249 2.534 1.852 1.428 ARI-100 37.686 24.823 12.298 4.721 2.839 2.089 1.622 ARI-500 47.159 30.604 15.003 5.815 3.547 2.64 2.072 ARI1000 51.24 33.093 16.168 6.285 3.852 2.878 2.266 ARI1000000 91.931 57.884 27.774 10.973 6.892 5.248 4.209 85000 ARI-1 10.663 8.224 4.547 1.569 0.807 0.525 0.363 120 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 7.96 4.876 1.95 0.48 0.215 0.13 0.085 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 6.976 4.378 1.703 0.361 0.143 0.079 0.048 85026 ARI-1 10.203 6.53 3.334 1.517 1.05 0.853 0.724 ARI1.11 10.968 7.004 3.565 1.618 1.118 0.908 0.771 ARI1.25 11.822 7.532 3.822 1.73 1.195 0.971 0.824 ARI-2 15.222 9.63 4.844 2.178 1.502 1.22 1.035 ARI-5 21.832 13.7 6.826 3.05 2.102 1.707 1.45 ARI-10 26.827 16.77 8.32 3.709 2.557 2.077 1.765 ARI-20 31.819 19.837 9.812 4.367 3.011 2.447 2.08 ARI-50 38.416 23.889 11.784 5.237 3.612 2.937 2.498 ARI-100 43.405 26.953 13.274 5.896 4.066 3.307 2.813 ARI-500 54.988 34.064 16.734 7.424 5.122 4.168 3.547 ARI1000 59.976 37.126 18.223 8.082 5.577 4.538 3.864 ARI1000000 109.68 67.632 33.061 14.639 10.109 8.234 7.016 ARI1.11 10.032 6.663 3.411 1.412 0.895 0.682 0.546 ARI1.25 10.813 7.209 3.713 1.549 0.985 0.753 0.604 ARI-2 13.925 9.382 4.913 2.094 1.346 1.035 0.834 ARI-5 19.984 13.61 7.249 3.155 2.049 1.585 1.283 ARI-10 24.564 16.806 9.015 3.957 2.581 2.001 1.623 ARI-20 29.142 20 10.779 4.759 3.113 2.417 1.963 ARI-50 35.194 24.222 13.112 5.819 3.816 2.967 2.413 ARI-100 39.772 27.415 14.876 6.621 4.348 3.383 2.753 ARI-500 50.399 34.828 18.971 8.483 5.583 4.349 3.543 ARI1000 54.976 38.021 20.734 9.285 6.115 4.766 3.884 ARI1000000 100.583 69.833 38.308 17.276 11.415 8.913 7.274 85034 ARI-1 9.334 6.175 3.141 1.29 0.814 0.619 0.494 121 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 6.181 4.082 1.637 0.33 0.123 0.065 0.038 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 6.413 4.476 1.869 0.365 0.129 0.066 0.037 85072 ARI-1 7.932 5.486 2.83 1.071 0.623 0.445 0.336 ARI1.11 8.433 5.832 3.017 1.152 0.674 0.484 0.367 ARI1.25 8.994 6.22 3.226 1.242 0.731 0.528 0.401 ARI-2 11.233 7.766 4.059 1.601 0.96 0.701 0.54 ARI-5 15.596 10.782 5.684 2.301 1.406 1.041 0.81 ARI-10 18.896 13.063 6.913 2.83 1.744 1.298 1.016 ARI-20 22.197 15.345 8.141 3.359 2.081 1.556 1.222 ARI-50 26.559 18.362 9.765 4.058 2.528 1.897 1.494 ARI-100 29.86 20.644 10.993 4.586 2.866 2.155 1.701 ARI-500 37.523 25.943 13.845 5.814 3.65 2.754 2.18 ARI1000 40.823 28.225 15.073 6.342 3.988 3.011 2.386 ARI1000000 73.714 50.969 27.313 11.61 7.356 5.583 4.444 ARI1.11 9.65 6.601 3.347 1.241 0.714 0.508 0.382 ARI1.25 10.484 7.051 3.519 1.303 0.756 0.541 0.41 ARI-2 13.834 8.837 4.202 1.551 0.92 0.673 0.52 ARI-5 20.433 12.293 5.523 2.032 1.237 0.926 0.733 ARI-10 25.457 14.895 6.519 2.394 1.475 1.117 0.895 ARI-20 30.497 17.491 7.513 2.755 1.713 1.308 1.056 ARI-50 37.174 20.917 8.824 3.232 2.027 1.559 1.268 ARI-100 42.233 23.506 9.816 3.593 2.263 1.749 1.429 ARI-500 53.995 29.513 12.115 4.429 2.813 2.189 1.802 ARI1000 59.066 32.099 13.105 4.789 3.049 2.379 1.963 ARI1000000 109.664 57.845 22.961 8.374 5.401 4.265 3.561 85103 ARI-1 8.907 6.196 3.193 1.185 0.677 0.478 0.357 122 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 7.356 4.929 2.039 0.434 0.167 0.09 0.053 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 6.432 3.958 1.499 0.31 0.122 0.067 0.041 85106 ARI-1 10.258 7.129 3.825 1.61 1.01 0.761 0.601 ARI1.11 10.685 7.425 3.985 1.679 1.055 0.795 0.629 ARI1.25 11.163 7.755 4.164 1.757 1.105 0.833 0.66 ARI-2 13.064 9.072 4.877 2.067 1.304 0.987 0.783 ARI-5 16.76 11.635 6.264 2.671 1.693 1.284 1.022 ARI-10 19.551 13.572 7.314 3.127 1.986 1.51 1.203 ARI-20 22.34 15.507 8.362 3.583 2.28 1.734 1.383 ARI-50 26.023 18.064 9.748 4.186 2.668 2.032 1.622 ARI-100 28.809 19.998 10.797 4.642 2.961 2.257 1.802 ARI-500 35.274 24.488 13.23 5.701 3.642 2.778 2.221 ARI1000 38.057 26.421 14.278 6.157 3.935 3.003 2.402 ARI1000000 65.786 45.68 24.722 10.699 6.856 5.242 4.199 ARI1.11 10.283 6.372 2.989 1.153 0.717 0.543 0.434 ARI1.25 11.103 6.84 3.183 1.219 0.756 0.572 0.456 ARI-2 14.386 8.702 3.954 1.481 0.912 0.688 0.548 ARI-5 20.813 12.322 5.444 1.989 1.215 0.913 0.726 ARI-10 25.688 15.056 6.566 2.372 1.444 1.084 0.861 ARI-20 30.57 17.788 7.685 2.755 1.672 1.254 0.996 ARI-50 37.03 21.398 9.162 3.26 1.974 1.48 1.174 ARI-100 41.919 24.127 10.279 3.641 2.203 1.65 1.309 ARI-500 53.279 30.463 12.869 4.527 2.733 2.046 1.623 ARI1000 58.173 33.191 13.983 4.908 2.961 2.216 1.757 ARI1000000 106.975 60.369 25.082 8.703 5.234 3.913 3.102 85170 ARI-1 9.55 5.954 2.815 1.094 0.682 0.517 0.413 123 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.179 5.882 2.613 0.566 0.214 0.113 0.065 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.484 5.067 1.906 0.419 0.175 0.101 0.064 85176 ARI-1 10.536 7.83 4.387 1.746 1.017 0.724 0.542 ARI1.11 11.329 8.271 4.571 1.833 1.083 0.779 0.59 ARI1.25 12.215 8.764 4.777 1.929 1.156 0.841 0.644 ARI-2 15.753 10.715 5.604 2.316 1.449 1.092 0.864 ARI-5 22.655 14.487 7.224 3.07 2.02 1.586 1.306 ARI-10 27.879 17.327 8.453 3.64 2.453 1.963 1.646 ARI-20 33.105 20.16 9.683 4.21 2.885 2.341 1.989 ARI-50 40.015 23.9 11.311 4.964 3.458 2.843 2.446 ARI-100 45.244 26.726 12.543 5.533 3.891 3.223 2.793 ARI-500 57.386 33.283 15.404 6.857 4.897 4.107 3.603 ARI1000 62.616 36.105 16.636 7.426 5.33 4.489 3.952 ARI1000000 114.746 64.21 28.923 13.104 9.65 8.295 7.449 ARI1.11 11.17 7.151 3.535 1.459 0.939 0.726 0.59 ARI1.25 11.609 7.487 3.731 1.545 0.994 0.767 0.622 ARI-2 13.359 8.825 4.512 1.89 1.211 0.931 0.751 ARI-5 16.765 11.425 6.038 2.564 1.634 1.248 0.999 ARI-10 19.339 13.387 7.194 3.074 1.954 1.486 1.185 ARI-20 21.912 15.347 8.35 3.585 2.274 1.725 1.371 ARI-50 25.312 17.937 9.879 4.26 2.696 2.039 1.617 ARI-100 27.883 19.894 11.036 4.771 3.015 2.277 1.802 ARI-500 33.851 24.438 13.723 5.959 3.756 2.828 2.231 ARI1000 36.421 26.394 14.881 6.47 4.075 3.066 2.416 ARI1000000 62.025 45.877 26.42 11.571 7.254 5.429 4.254 85237 ARI-1 10.778 6.85 3.36 1.382 0.89 0.689 0.561 124 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.405 5.195 2.003 0.431 0.174 0.098 0.06 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 7.085 4.214 1.558 0.329 0.134 0.076 0.047 85256 ARI-1 10.164 6.582 3.247 1.289 0.802 0.605 0.48 ARI1.11 10.893 7.055 3.468 1.362 0.84 0.63 0.497 ARI1.25 11.704 7.58 3.712 1.442 0.882 0.658 0.517 ARI-2 14.901 9.643 4.671 1.76 1.053 0.773 0.6 ARI-5 21.054 13.594 6.502 2.374 1.389 1.005 0.769 ARI-10 25.679 16.554 7.872 2.835 1.643 1.182 0.899 ARI-20 30.293 19.504 9.235 3.296 1.898 1.359 1.031 ARI-50 36.383 23.393 11.031 3.903 2.236 1.595 1.206 ARI-100 40.985 26.33 12.387 4.363 2.491 1.774 1.338 ARI-500 51.662 33.14 15.531 5.428 3.084 2.189 1.647 ARI1000 56.258 36.07 16.883 5.887 3.34 2.368 1.78 ARI1000000 102.031 65.239 30.339 10.454 5.887 4.153 3.109 ARI1.11 9.231 5.84 2.815 1.113 0.698 0.531 0.425 ARI1.25 9.702 6.183 3.01 1.202 0.757 0.577 0.462 ARI-2 11.589 7.547 3.786 1.558 0.992 0.76 0.612 ARI-5 15.28 10.199 5.291 2.249 1.449 1.117 0.903 ARI-10 18.078 12.204 6.427 2.771 1.795 1.387 1.123 ARI-20 20.878 14.207 7.563 3.293 2.141 1.657 1.342 ARI-50 24.581 16.855 9.063 3.984 2.598 2.013 1.633 ARI-100 27.383 18.857 10.198 4.506 2.944 2.283 1.853 ARI-500 33.891 23.505 12.831 5.718 3.747 2.91 2.363 ARI1000 36.694 25.507 13.965 6.24 4.093 3.179 2.583 ARI1000000 64.636 45.451 25.265 11.444 7.539 5.867 4.772 86038 ARI-1 8.811 5.534 2.641 1.034 0.645 0.49 0.391 125 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 7.157 4.281 1.56 0.31 0.12 0.066 0.039 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 6.503 4.383 1.87 0.429 0.174 0.098 0.059 86071 ARI-1 10.255 6.322 2.938 1.118 0.69 0.52 0.414 ARI1.11 11.037 6.759 3.139 1.214 0.761 0.58 0.466 ARI1.25 11.91 7.248 3.363 1.321 0.839 0.647 0.525 ARI-2 15.386 9.202 4.262 1.746 1.155 0.916 0.763 ARI-5 22.149 13.017 6.016 2.57 1.769 1.444 1.236 ARI-10 27.26 15.905 7.344 3.192 2.233 1.846 1.597 ARI-20 32.369 18.794 8.672 3.813 2.698 2.248 1.96 ARI-50 39.122 22.612 10.427 4.634 3.312 2.78 2.44 ARI-100 44.229 25.501 11.756 5.255 3.776 3.182 2.804 ARI-500 56.086 32.21 14.84 6.697 4.855 4.118 3.65 ARI1000 61.193 35.099 16.168 7.317 5.32 4.521 4.015 ARI1000000 112.077 63.893 29.406 13.501 9.949 8.541 7.655 ARI1.11 9.288 6.53 3.575 1.549 0.987 0.751 0.599 ARI1.25 9.855 6.925 3.79 1.642 1.047 0.797 0.635 ARI-2 12.116 8.501 4.646 2.013 1.284 0.978 0.78 ARI-5 16.528 11.571 6.311 2.734 1.746 1.331 1.063 ARI-10 19.867 13.892 7.569 3.278 2.095 1.597 1.276 ARI-20 23.206 16.214 8.827 3.823 2.444 1.864 1.49 ARI-50 27.62 19.281 10.489 4.542 2.905 2.217 1.772 ARI-100 30.96 21.602 11.745 5.087 3.253 2.483 1.985 ARI-500 38.714 26.989 14.663 6.35 4.063 3.102 2.481 ARI1000 42.054 29.309 15.919 6.894 4.412 3.369 2.695 ARI1000000 75.341 52.43 28.437 12.313 7.885 6.024 4.822 86074 ARI-1 8.781 6.176 3.383 1.465 0.934 0.71 0.566 126 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.261 5.133 2.036 0.47 0.199 0.116 0.073 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 7.613 5.217 2.269 0.527 0.214 0.12 0.073 86142 ARI-1 11.935 7.642 3.875 1.726 1.175 0.945 0.794 ARI1.11 12.672 8.1 4.098 1.822 1.24 0.996 0.837 ARI1.25 13.496 8.61 4.347 1.929 1.312 1.054 0.886 ARI-2 16.778 10.644 5.336 2.356 1.601 1.286 1.081 ARI-5 23.17 14.595 7.256 3.187 2.165 1.74 1.464 ARI-10 28.002 17.578 8.706 3.815 2.592 2.084 1.754 ARI-20 32.833 20.559 10.153 4.443 3.019 2.428 2.045 ARI-50 39.218 24.497 12.066 5.273 3.584 2.883 2.429 ARI-100 44.048 27.475 13.512 5.901 4.011 3.228 2.72 ARI-500 55.261 34.388 16.868 7.358 5.003 4.028 3.395 ARI1000 60.09 37.365 18.313 7.986 5.43 4.372 3.686 ARI1000000 108.21 67.02 32.709 14.238 9.687 7.807 6.588 ARI1.11 10.329 7.3 4.025 1.755 1.121 0.853 0.681 ARI1.25 10.99 7.718 4.237 1.856 1.194 0.914 0.732 ARI-2 13.614 9.377 5.084 2.261 1.485 1.155 0.94 ARI-5 18.699 12.596 6.731 3.051 2.053 1.628 1.35 ARI-10 22.531 15.023 7.976 3.647 2.483 1.987 1.661 ARI-20 26.357 17.447 9.221 4.244 2.914 2.347 1.974 ARI-50 31.409 20.647 10.866 5.033 3.483 2.823 2.388 ARI-100 35.227 23.067 12.111 5.629 3.914 3.183 2.702 ARI-500 44.087 28.682 14.999 7.014 4.914 4.021 3.431 ARI1000 47.901 31.099 16.243 7.61 5.345 4.381 3.746 ARI1000000 85.886 55.177 28.636 13.553 9.639 7.978 6.884 86219 ARI-1 9.737 6.926 3.835 1.664 1.055 0.8 0.634 127 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.002 4.496 1.604 0.356 0.154 0.092 0.059 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 6.775 4.06 1.488 0.3 0.117 0.065 0.039 86224 ARI-1 12.469 7.099 3.2 1.385 0.977 0.814 0.711 ARI1.11 13.073 7.418 3.335 1.446 1.023 0.855 0.748 ARI1.25 13.746 7.773 3.486 1.514 1.075 0.9 0.789 ARI-2 16.428 9.187 4.086 1.785 1.28 1.081 0.955 ARI-5 21.64 11.931 5.252 2.313 1.68 1.433 1.279 ARI-10 25.574 14.001 6.132 2.712 1.982 1.699 1.524 ARI-20 29.503 16.068 7.01 3.11 2.285 1.966 1.77 ARI-50 34.694 18.797 8.171 3.636 2.684 2.319 2.095 ARI-100 38.618 20.861 9.048 4.034 2.986 2.585 2.341 ARI-500 47.724 25.649 11.084 4.958 3.688 3.205 2.912 ARI1000 51.645 27.71 11.961 5.355 3.99 3.472 3.158 ARI1000000 90.697 48.237 20.691 9.316 6.999 6.131 5.613 ARI1.11 9.792 6.153 2.881 1.063 0.635 0.468 0.364 ARI1.25 10.43 6.551 3.066 1.132 0.677 0.498 0.388 ARI-2 12.972 8.139 3.806 1.405 0.841 0.619 0.482 ARI-5 17.928 11.233 5.246 1.937 1.16 0.855 0.666 ARI-10 21.677 13.572 6.335 2.339 1.4 1.033 0.805 ARI-20 25.425 15.911 7.422 2.74 1.641 1.211 0.944 ARI-50 30.38 19.002 8.86 3.271 1.959 1.445 1.127 ARI-100 34.128 21.34 9.947 3.672 2.2 1.623 1.266 ARI-500 42.831 26.768 12.471 4.603 2.758 2.035 1.588 ARI1000 46.579 29.106 13.558 5.004 2.998 2.213 1.726 ARI1000000 83.931 52.4 24.387 8.999 5.394 3.982 3.107 86314 ARI-1 9.222 5.796 2.714 1.002 0.599 0.441 0.343 128 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 7.39 4.556 1.756 0.38 0.154 0.087 0.054 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 6.98 3.795 1.316 0.294 0.13 0.079 0.052 87029 ARI-1 10.717 6.76 3.26 1.3 0.822 0.628 0.506 ARI1.11 11.457 7.184 3.44 1.367 0.864 0.661 0.532 ARI1.25 12.285 7.657 3.642 1.441 0.911 0.697 0.562 ARI-2 15.59 9.543 4.446 1.738 1.098 0.842 0.68 ARI-5 22.036 13.216 6.013 2.318 1.463 1.124 0.91 ARI-10 26.914 15.993 7.199 2.756 1.739 1.337 1.083 ARI-20 31.792 18.769 8.385 3.195 2.015 1.549 1.257 ARI-50 38.242 22.439 9.953 3.775 2.38 1.83 1.485 ARI-100 43.12 25.214 11.139 4.213 2.656 2.043 1.658 ARI-500 54.449 31.658 13.893 5.232 3.296 2.536 2.06 ARI1000 59.328 34.433 15.079 5.671 3.572 2.749 2.233 ARI1000000 107.955 62.087 26.897 10.044 6.321 4.866 3.955 ARI1.11 10.264 5.976 2.722 1.142 0.779 0.633 0.539 ARI1.25 11.082 6.493 2.968 1.237 0.838 0.676 0.573 ARI-2 14.346 8.551 3.949 1.619 1.073 0.853 0.712 ARI-5 20.714 12.558 5.857 2.36 1.532 1.198 0.986 ARI-10 25.533 15.588 7.3 2.921 1.88 1.461 1.194 ARI-20 30.353 18.617 8.742 3.482 2.228 1.723 1.402 ARI-50 36.725 22.62 10.649 4.222 2.688 2.07 1.679 ARI-100 41.546 25.649 12.09 4.783 3.035 2.333 1.888 ARI-500 52.739 32.679 15.438 6.083 3.843 2.943 2.374 ARI1000 57.56 35.707 16.879 6.644 4.191 3.206 2.583 ARI1000000 105.605 65.881 31.243 12.226 7.658 5.827 4.671 87031 ARI-1 9.534 5.514 2.501 1.056 0.726 0.593 0.509 129 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 7.112 4.154 1.514 0.322 0.132 0.076 0.047 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 7.036 4.492 1.784 0.384 0.153 0.085 0.051 87033 ARI-1 9.471 5.727 2.645 1.043 0.667 0.516 0.421 ARI1.11 10.182 6.108 2.805 1.111 0.715 0.557 0.457 ARI1.25 10.977 6.534 2.984 1.187 0.77 0.603 0.497 ARI-2 14.151 8.231 3.696 1.491 0.988 0.787 0.659 ARI-5 20.342 11.533 5.084 2.082 1.413 1.147 0.978 ARI-10 25.026 14.028 6.134 2.529 1.735 1.42 1.221 ARI-20 29.711 16.522 7.183 2.976 2.057 1.694 1.465 ARI-50 35.905 19.818 8.57 3.567 2.482 2.056 1.787 ARI-100 40.591 22.311 9.619 4.014 2.804 2.33 2.031 ARI-500 51.471 28.097 12.054 5.051 3.552 2.966 2.599 ARI1000 56.157 30.589 13.103 5.498 3.874 3.24 2.843 ARI1000000 102.859 55.42 23.554 9.949 7.084 5.973 5.282 ARI1.11 9.396 6.318 3.208 1.253 0.756 0.556 0.431 ARI1.25 10.066 6.777 3.446 1.345 0.811 0.596 0.462 ARI-2 12.739 8.609 4.39 1.713 1.03 0.756 0.584 ARI-5 17.95 12.176 6.229 2.428 1.456 1.066 0.823 ARI-10 21.892 14.873 7.619 2.968 1.778 1.301 1.003 ARI-20 25.834 17.57 9.008 3.509 2.1 1.536 1.183 ARI-50 31.045 21.134 10.844 4.223 2.526 1.846 1.422 ARI-100 34.987 23.83 12.233 4.763 2.848 2.081 1.602 ARI-500 44.14 30.089 15.456 6.017 3.596 2.626 2.021 ARI1000 48.082 32.785 16.845 6.557 3.918 2.861 2.201 ARI1000000 87.368 59.648 30.679 11.938 7.127 5.2 3.998 87036 ARI-1 8.797 5.907 2.996 1.171 0.707 0.521 0.404 130 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 6.997 3.83 1.265 0.239 0.093 0.052 0.032 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 6.619 3.9 1.435 0.306 0.126 0.072 0.045 79082 ARI-1 9.187 5.283 2.261 0.815 0.499 0.377 0.302 ARI1.11 9.69 5.58 2.399 0.873 0.538 0.409 0.328 ARI1.25 10.251 5.912 2.554 0.938 0.582 0.444 0.358 ARI-2 12.488 7.237 3.169 1.197 0.757 0.584 0.476 ARI-5 16.845 9.816 4.365 1.701 1.098 0.859 0.708 ARI-10 20.139 11.765 5.269 2.082 1.356 1.067 0.884 ARI-20 23.431 13.715 6.173 2.462 1.614 1.275 1.06 ARI-50 27.782 16.291 7.366 2.965 1.955 1.55 1.293 ARI-100 31.074 18.239 8.269 3.346 2.213 1.759 1.47 ARI-500 38.715 22.763 10.365 4.229 2.812 2.243 1.88 ARI1000 42.005 24.712 11.268 4.609 3.071 2.452 2.057 ARI1000000 74.794 44.125 20.261 8.399 5.643 4.531 3.82 ARI1.11 10.776 6.44 2.928 1.137 0.723 0.558 0.454 ARI1.25 11.681 6.956 3.137 1.2 0.756 0.58 0.47 ARI-2 15.296 9.011 3.965 1.453 0.891 0.672 0.536 ARI-5 22.354 13.011 5.571 1.942 1.155 0.854 0.669 ARI-10 27.697 16.035 6.781 2.312 1.355 0.993 0.772 ARI-20 33.043 19.058 7.989 2.681 1.556 1.133 0.876 ARI-50 40.111 23.053 9.585 3.168 1.822 1.318 1.014 ARI-100 45.459 26.075 10.791 3.537 2.023 1.458 1.119 ARI-500 57.879 33.091 13.59 4.392 2.49 1.785 1.362 ARI1000 63.229 36.113 14.795 4.76 2.691 1.926 1.468 ARI1000000 116.55 66.22 26.798 8.429 4.697 3.33 2.518 79086 ARI-1 9.966 5.979 2.741 1.08 0.693 0.538 0.44 131 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 6.451 4.067 1.57 0.321 0.123 0.067 0.04 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 5.463 3.275 1.31 0.343 0.163 0.103 0.07 87097 ARI-1 9.732 6.161 3.061 1.322 0.885 0.704 0.587 ARI1.11 10.475 6.587 3.268 1.434 0.974 0.783 0.659 ARI1.25 11.306 7.063 3.501 1.559 1.074 0.872 0.741 ARI-2 14.618 8.961 4.425 2.054 1.473 1.232 1.075 ARI-5 21.072 12.66 6.225 3.015 2.254 1.943 1.744 ARI-10 25.953 15.458 7.585 3.74 2.845 2.485 2.258 ARI-20 30.833 18.256 8.945 4.465 3.438 3.029 2.774 ARI-50 37.285 21.954 10.742 5.423 4.221 3.75 3.46 ARI-100 42.165 24.751 12.102 6.147 4.814 4.296 3.98 ARI-500 53.495 31.246 15.258 7.827 6.191 5.565 5.19 ARI1000 58.375 34.043 16.617 8.551 6.784 6.112 5.712 ARI1000000 107.005 61.919 30.161 15.761 12.696 11.568 10.923 ARI1.11 8.34 5.177 2.612 1.248 0.909 0.768 0.675 ARI1.25 9.012 5.587 2.804 1.324 0.957 0.803 0.703 ARI-2 11.697 7.22 3.567 1.625 1.145 0.946 0.816 ARI-5 16.942 10.4 5.044 2.208 1.515 1.229 1.044 ARI-10 20.914 12.804 6.158 2.648 1.795 1.445 1.219 ARI-20 24.889 15.207 7.269 3.087 2.076 1.662 1.395 ARI-50 30.145 18.382 8.737 3.667 2.447 1.949 1.628 ARI-100 34.123 20.783 9.846 4.105 2.727 2.166 1.805 ARI-500 43.36 26.359 12.421 5.123 3.379 2.671 2.217 ARI1000 47.339 28.76 13.529 5.561 3.66 2.889 2.395 ARI1000000 87.004 52.684 24.567 9.925 6.458 5.06 4.169 87104 ARI-1 7.739 4.81 2.44 1.18 0.867 0.736 0.651 132 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.057 3.962 1.293 0.317 0.158 0.105 0.076 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 6.717 3.796 1.336 0.28 0.116 0.067 0.042 87105 ARI-1 10.294 5.287 2.187 0.972 0.735 0.649 0.6 ARI1.11 11.274 5.727 2.34 1.033 0.782 0.692 0.641 ARI1.25 12.374 6.218 2.51 1.102 0.835 0.74 0.686 ARI-2 16.792 8.17 3.182 1.372 1.042 0.928 0.866 ARI-5 25.485 11.953 4.473 1.891 1.442 1.292 1.214 ARI-10 32.097 14.805 5.44 2.281 1.741 1.565 1.475 ARI-20 38.726 17.654 6.403 2.668 2.04 1.837 1.736 ARI-50 47.507 21.415 7.673 3.179 2.433 2.196 2.079 ARI-100 54.157 24.258 8.632 3.565 2.731 2.466 2.339 ARI-500 69.617 30.855 10.854 4.459 3.42 3.095 2.941 ARI1000 76.28 33.695 11.81 4.844 3.716 3.365 3.2 ARI1000000 142.752 61.982 21.323 8.672 6.667 6.056 5.781 ARI1.11 9.127 5.581 2.579 0.987 0.614 0.466 0.373 ARI1.25 9.612 5.947 2.779 1.064 0.658 0.497 0.396 ARI-2 11.536 7.402 3.577 1.371 0.834 0.62 0.486 ARI-5 15.261 10.218 5.138 1.971 1.175 0.858 0.661 ARI-10 18.069 12.341 6.32 2.425 1.433 1.038 0.793 ARI-20 20.871 14.459 7.504 2.881 1.69 1.217 0.924 ARI-50 24.571 17.256 9.07 3.483 2.031 1.454 1.097 ARI-100 27.368 19.371 10.255 3.938 2.288 1.632 1.228 ARI-500 33.858 24.276 13.007 4.997 2.885 2.047 1.532 ARI1000 36.652 26.388 14.192 5.453 3.142 2.226 1.663 ARI1000000 64.48 47.419 26.011 9.998 5.705 4.004 2.965 87133 ARI-1 8.692 5.252 2.401 0.918 0.574 0.438 0.352 133 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 7.522 4.012 1.452 0.389 0.198 0.133 0.096 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.61 5.337 2.032 0.418 0.163 0.089 0.054 87153 ARI-1 12.624 7.509 3.595 1.652 1.193 1.006 0.885 ARI1.11 13.489 8.095 3.889 1.763 1.255 1.047 0.912 ARI1.25 14.456 8.749 4.218 1.887 1.325 1.094 0.944 ARI-2 18.317 11.361 5.531 2.381 1.605 1.286 1.079 ARI-5 25.841 16.454 8.093 3.339 2.154 1.669 1.358 ARI-10 31.532 20.308 10.031 4.062 2.569 1.962 1.576 ARI-20 37.223 24.163 11.969 4.784 2.985 2.257 1.795 ARI-50 44.745 29.258 14.532 5.737 3.536 2.648 2.088 ARI-100 50.435 33.113 16.471 6.458 3.952 2.944 2.31 ARI-500 63.647 42.065 20.973 8.132 4.919 3.633 2.829 ARI1000 69.337 45.92 22.912 8.853 5.336 3.93 3.052 ARI1000000 126.038 84.344 42.239 16.032 9.487 6.894 5.287 ARI1.11 13.321 8.4 3.992 1.526 0.934 0.699 0.552 ARI1.25 14.001 8.804 4.166 1.584 0.968 0.723 0.57 ARI-2 16.701 10.411 4.86 1.817 1.101 0.819 0.643 ARI-5 21.933 13.531 6.21 2.271 1.36 1.005 0.785 ARI-10 25.873 15.884 7.23 2.614 1.556 1.145 0.892 ARI-20 29.804 18.235 8.25 2.957 1.752 1.285 0.999 ARI-50 34.992 21.339 9.597 3.41 2.011 1.471 1.14 ARI-100 38.913 23.685 10.616 3.753 2.206 1.611 1.247 ARI-500 48.006 29.13 12.981 4.549 2.661 1.937 1.495 ARI1000 51.92 31.473 14 4.892 2.856 2.077 1.601 ARI1000000 90.882 54.817 24.146 8.306 4.806 3.475 2.666 88023 ARI-1 12.712 8.038 3.836 1.474 0.905 0.678 0.536 134 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 6.85 4.264 1.607 0.317 0.119 0.064 0.038 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.378 4.574 1.573 0.338 0.145 0.086 0.056 88029 ARI-1 8.743 5.664 2.72 0.996 0.583 0.422 0.323 ARI1.11 9.594 6.198 2.955 1.066 0.618 0.444 0.338 ARI1.25 10.544 6.795 3.216 1.143 0.656 0.469 0.355 ARI-2 14.334 9.175 4.257 1.452 0.811 0.569 0.424 ARI-5 21.717 13.809 6.277 2.051 1.113 0.766 0.561 ARI-10 27.3 17.312 7.803 2.504 1.343 0.917 0.667 ARI-20 32.883 20.815 9.329 2.957 1.572 1.068 0.773 ARI-50 40.263 25.446 11.344 3.555 1.876 1.267 0.913 ARI-100 45.845 28.948 12.868 4.007 2.106 1.419 1.02 ARI-500 58.806 37.081 16.407 5.057 2.639 1.77 1.267 ARI1000 64.388 40.583 17.93 5.51 2.869 1.921 1.374 ARI1000000 120.014 75.486 33.113 10.016 5.16 3.431 2.439 ARI1.11 11.838 6.728 2.913 1.122 0.726 0.571 0.473 ARI1.25 12.854 7.281 3.129 1.19 0.765 0.599 0.494 ARI-2 16.911 9.484 3.991 1.464 0.921 0.71 0.579 ARI-5 24.833 13.777 5.664 1.997 1.225 0.93 0.748 ARI-10 30.832 17.023 6.927 2.399 1.456 1.098 0.878 ARI-20 36.833 20.269 8.189 2.8 1.687 1.265 1.007 ARI-50 44.768 24.559 9.855 3.331 1.992 1.487 1.18 ARI-100 50.772 27.804 11.115 3.732 2.223 1.656 1.31 ARI-500 64.715 35.339 14.04 4.664 2.759 2.046 1.613 ARI1000 70.72 38.584 15.299 5.065 2.99 2.215 1.744 ARI1000000 130.579 70.919 27.844 9.06 5.293 3.894 3.049 88037 ARI-1 10.93 6.234 2.719 1.06 0.692 0.546 0.454 135 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.014 5.208 1.964 0.344 0.116 0.058 0.031 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 7.93 4.557 1.721 0.426 0.197 0.123 0.083 88049 ARI-1 11.887 7.564 3.443 1.127 0.612 0.422 0.309 ARI1.11 12.862 8.063 3.608 1.17 0.636 0.439 0.322 ARI1.25 13.956 8.619 3.793 1.219 0.663 0.458 0.337 ARI-2 18.343 10.827 4.526 1.412 0.768 0.533 0.395 ARI-5 26.969 15.101 5.943 1.79 0.973 0.679 0.506 ARI-10 33.531 18.321 7.01 2.075 1.127 0.788 0.59 ARI-20 40.113 21.534 8.073 2.361 1.281 0.897 0.672 ARI-50 48.833 25.776 9.476 2.737 1.484 1.041 0.781 ARI-100 55.439 28.981 10.535 3.022 1.638 1.149 0.864 ARI-500 70.8 36.416 12.991 3.683 1.995 1.401 1.055 ARI1000 77.423 39.616 14.048 3.968 2.148 1.509 1.137 ARI1000000 143.513 71.48 24.563 6.803 3.677 2.587 1.955 ARI1.11 11.375 6.87 3.276 1.426 0.982 0.8 0.683 ARI1.25 12.025 7.264 3.452 1.486 1.015 0.822 0.698 ARI-2 14.622 8.836 4.151 1.724 1.146 0.911 0.761 ARI-5 19.688 11.896 5.503 2.183 1.403 1.09 0.892 ARI-10 23.523 14.209 6.522 2.529 1.598 1.227 0.994 ARI-20 27.359 16.521 7.538 2.874 1.794 1.366 1.097 ARI-50 32.431 19.576 8.879 3.329 2.052 1.55 1.236 ARI-100 36.269 21.887 9.892 3.672 2.248 1.689 1.341 ARI-500 45.181 27.251 12.243 4.469 2.703 2.014 1.588 ARI1000 49.02 29.561 13.254 4.813 2.899 2.155 1.694 ARI1000000 87.285 52.577 23.324 8.228 4.853 3.556 2.761 88153 ARI-1 10.793 6.517 3.119 1.372 0.953 0.781 0.669 136 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 6.757 3.942 1.37 0.253 0.094 0.05 0.029 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 5.957 3.891 1.503 0.279 0.098 0.05 0.028 89016 ARI-1 8.402 5.147 2.282 0.767 0.433 0.307 0.231 ARI1.11 9.052 5.528 2.45 0.829 0.471 0.336 0.254 ARI1.25 9.778 5.953 2.637 0.899 0.514 0.368 0.28 ARI-2 12.672 7.649 3.383 1.176 0.685 0.498 0.383 ARI-5 18.31 10.952 4.836 1.715 1.019 0.751 0.586 ARI-10 22.573 13.45 5.935 2.122 1.271 0.943 0.74 ARI-20 26.835 15.948 7.033 2.53 1.524 1.135 0.894 ARI-50 32.468 19.249 8.485 3.068 1.858 1.388 1.098 ARI-100 36.73 21.746 9.583 3.476 2.111 1.58 1.252 ARI-500 46.624 27.544 12.133 4.421 2.697 2.027 1.61 ARI1000 50.884 30.04 13.23 4.829 2.95 2.219 1.765 ARI1000000 93.346 54.921 24.172 8.887 5.468 4.134 3.304 ARI1.11 8.459 5.899 2.954 0.999 0.532 0.358 0.256 ARI1.25 8.99 6.302 3.174 1.077 0.574 0.386 0.276 ARI-2 11.111 7.909 4.054 1.39 0.74 0.497 0.354 ARI-5 15.249 11.036 5.764 1.998 1.064 0.713 0.507 ARI-10 18.38 13.4 7.057 2.458 1.309 0.877 0.623 ARI-20 21.513 15.762 8.349 2.918 1.554 1.041 0.74 ARI-50 25.654 18.883 10.056 3.526 1.879 1.258 0.893 ARI-100 28.787 21.244 11.347 3.986 2.124 1.422 1.009 ARI-500 36.062 26.725 14.344 5.054 2.693 1.803 1.279 ARI1000 39.195 29.086 15.635 5.514 2.939 1.967 1.395 ARI1000000 70.421 52.606 28.496 10.099 5.383 3.601 2.552 89025 ARI-1 7.984 5.538 2.756 0.929 0.495 0.333 0.239 137 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.479 5.573 2.059 0.329 0.103 0.049 0.025 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 5.214 3.568 1.466 0.288 0.104 0.053 0.03 89094 ARI-1 11.857 7.74 3.69 1.294 0.73 0.515 0.385 ARI1.11 12.304 7.972 3.801 1.362 0.784 0.561 0.425 ARI1.25 12.802 8.233 3.927 1.437 0.844 0.612 0.47 ARI-2 14.776 9.276 4.427 1.735 1.085 0.824 0.659 ARI-5 18.59 11.321 5.405 2.307 1.56 1.254 1.057 ARI-10 21.458 12.871 6.145 2.736 1.923 1.589 1.374 ARI-20 24.317 14.422 6.885 3.162 2.287 1.93 1.701 ARI-50 28.089 16.472 7.862 3.723 2.77 2.386 2.142 ARI-100 30.938 18.024 8.601 4.147 3.136 2.734 2.482 ARI-500 37.543 21.626 10.317 5.128 3.988 3.549 3.283 ARI1000 40.384 23.177 11.056 5.55 4.356 3.902 3.631 ARI1000000 68.662 38.633 18.414 9.743 8.03 7.453 7.165 ARI1.11 8.369 5.673 2.832 1.027 0.584 0.412 0.308 ARI1.25 8.981 6.033 2.98 1.075 0.611 0.432 0.323 ARI-2 11.419 7.465 3.574 1.265 0.719 0.509 0.382 ARI-5 16.165 10.249 4.734 1.636 0.927 0.658 0.495 ARI-10 19.751 12.353 5.613 1.918 1.084 0.769 0.579 ARI-20 23.336 14.456 6.492 2.199 1.241 0.88 0.663 ARI-50 28.072 17.234 7.655 2.571 1.449 1.027 0.773 ARI-100 31.654 19.335 8.534 2.852 1.605 1.137 0.857 ARI-500 39.969 24.213 10.577 3.506 1.969 1.394 1.05 ARI1000 43.549 26.314 11.457 3.787 2.125 1.505 1.133 ARI1000000 79.223 47.244 20.227 6.592 3.684 2.604 1.959 90058 ARI-1 7.821 5.351 2.699 0.984 0.56 0.395 0.294 138 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 4.897 3.823 1.745 0.327 0.106 0.05 0.026 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 7.521 3.718 1.165 0.249 0.112 0.069 0.047 80006 ARI-1 6.659 5.278 2.989 1.027 0.52 0.334 0.227 ARI1.11 7.261 5.654 3.143 1.073 0.545 0.352 0.241 ARI1.25 7.934 6.072 3.315 1.125 0.574 0.371 0.255 ARI-2 10.627 7.733 4.004 1.331 0.686 0.449 0.313 ARI-5 15.894 10.949 5.348 1.738 0.903 0.599 0.423 ARI-10 19.886 13.372 6.365 2.046 1.068 0.711 0.505 ARI-20 23.881 15.792 7.383 2.355 1.232 0.823 0.587 ARI-50 29.167 18.987 8.728 2.763 1.448 0.971 0.694 ARI-100 33.166 21.403 9.746 3.073 1.612 1.083 0.776 ARI-500 42.457 27.008 12.109 3.791 1.993 1.342 0.964 ARI1000 46.459 29.421 13.127 4.101 2.157 1.454 1.045 ARI1000000 86.358 53.46 23.27 7.186 3.789 2.564 1.852 ARI1.11 10.057 5.381 2.195 0.835 0.552 0.443 0.374 ARI1.25 10.587 5.755 2.377 0.899 0.587 0.466 0.39 ARI-2 12.702 7.239 3.105 1.153 0.726 0.559 0.455 ARI-5 16.827 10.113 4.525 1.649 0.997 0.744 0.587 ARI-10 19.947 12.278 5.601 2.024 1.203 0.884 0.688 ARI-20 23.067 14.439 6.677 2.399 1.408 1.025 0.789 ARI-50 27.191 17.293 8.101 2.896 1.68 1.211 0.924 ARI-100 30.311 19.45 9.178 3.271 1.886 1.351 1.026 ARI-500 37.554 24.456 11.679 4.143 2.363 1.679 1.263 ARI1000 40.673 26.611 12.756 4.519 2.568 1.82 1.366 ARI1000000 71.758 48.074 23.496 8.262 4.617 3.225 2.388 80102 ARI-1 9.584 5.046 2.032 0.778 0.521 0.422 0.361 139 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 6.967 4.008 1.408 0.279 0.11 0.061 0.037 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 6.666 3.719 1.255 0.24 0.093 0.052 0.031 80109 ARI-1 10.547 6.372 2.846 1.016 0.604 0.445 0.347 ARI1.11 11.306 6.845 3.047 1.072 0.629 0.459 0.355 ARI1.25 12.154 7.373 3.272 1.133 0.657 0.475 0.365 ARI-2 15.528 9.48 4.167 1.378 0.77 0.542 0.407 ARI-5 22.086 13.586 5.909 1.852 0.991 0.677 0.494 ARI-10 27.038 16.692 7.224 2.21 1.158 0.781 0.562 ARI-20 31.987 19.799 8.54 2.567 1.327 0.885 0.632 ARI-50 38.525 23.905 10.278 3.039 1.549 1.024 0.725 ARI-100 43.469 27.012 11.593 3.395 1.718 1.13 0.795 ARI-500 54.945 34.227 14.646 4.223 2.109 1.374 0.96 ARI1000 59.886 37.334 15.961 4.579 2.278 1.48 1.031 ARI1000000 109.121 68.303 29.062 8.128 3.96 2.535 1.742 ARI1.11 9.502 5.541 2.413 0.88 0.541 0.409 0.327 ARI1.25 10.192 5.944 2.591 0.948 0.584 0.442 0.354 ARI-2 12.947 7.55 3.3 1.219 0.756 0.575 0.462 ARI-5 18.32 10.679 4.682 1.746 1.091 0.834 0.674 ARI-10 22.386 13.046 5.727 2.145 1.344 1.03 0.834 ARI-20 26.452 15.413 6.771 2.543 1.597 1.226 0.994 ARI-50 31.827 18.541 8.151 3.07 1.932 1.485 1.205 ARI-100 35.894 20.908 9.195 3.468 2.185 1.681 1.365 ARI-500 45.336 26.402 11.619 4.393 2.773 2.137 1.737 ARI1000 49.403 28.769 12.663 4.791 3.027 2.333 1.897 ARI1000000 89.931 52.351 23.064 8.76 5.551 4.287 3.494 80110 ARI-1 8.885 5.181 2.253 0.82 0.502 0.379 0.303 140 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 7.061 4.281 1.596 0.328 0.129 0.071 0.043 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 7.635 4.374 1.548 0.318 0.129 0.073 0.045 81003 ARI-1 8.706 5.512 2.634 1.012 0.621 0.465 0.367 ARI1.11 9.322 5.886 2.809 1.083 0.667 0.501 0.397 ARI1.25 10.011 6.304 3.005 1.163 0.719 0.542 0.43 ARI-2 12.762 7.968 3.781 1.479 0.926 0.704 0.564 ARI-5 18.131 11.202 5.286 2.093 1.328 1.021 0.826 ARI-10 22.196 13.645 6.421 2.556 1.633 1.262 1.026 ARI-20 26.261 16.087 7.554 3.019 1.938 1.502 1.225 ARI-50 31.637 19.313 9.051 3.631 2.341 1.821 1.49 ARI-100 35.704 21.752 10.183 4.093 2.646 2.062 1.69 ARI-500 45.148 27.416 12.81 5.167 3.353 2.622 2.156 ARI1000 49.215 29.855 13.942 5.629 3.658 2.863 2.356 ARI1000000 89.755 54.154 25.209 10.234 6.696 5.268 4.356 ARI1.11 11.676 6.725 2.969 1.169 0.764 0.604 0.503 ARI1.25 12.55 7.155 3.137 1.245 0.823 0.656 0.55 ARI-2 16.04 8.861 3.805 1.547 1.058 0.866 0.744 ARI-5 22.848 12.167 5.098 2.132 1.516 1.278 1.131 ARI-10 28.001 14.659 6.073 2.573 1.862 1.592 1.428 ARI-20 33.155 17.147 7.047 3.013 2.208 1.907 1.726 ARI-50 39.969 20.433 8.332 3.594 2.666 2.325 2.123 ARI-100 45.125 22.917 9.303 4.033 3.013 2.641 2.425 ARI-500 57.098 28.681 11.558 5.052 3.817 3.376 3.126 ARI1000 62.255 31.163 12.529 5.49 4.163 3.693 3.429 ARI1000000 113.654 55.881 22.197 9.858 7.617 6.856 6.454 81013 ARI-1 10.893 6.34 2.818 1.1 0.712 0.558 0.46 141 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.072 4.476 1.489 0.278 0.106 0.058 0.035 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 7.978 4.435 1.499 0.291 0.114 0.064 0.039 81026 ARI-1 9.887 5.759 2.45 0.836 0.489 0.357 0.277 ARI1.11 10.537 6.155 2.618 0.886 0.515 0.374 0.289 ARI1.25 11.263 6.597 2.806 0.942 0.543 0.393 0.302 ARI-2 14.158 8.363 3.556 1.166 0.658 0.468 0.355 ARI-5 19.795 11.805 5.019 1.602 0.882 0.617 0.46 ARI-10 24.057 14.408 6.125 1.931 1.051 0.729 0.539 ARI-20 28.318 17.011 7.232 2.261 1.221 0.842 0.62 ARI-50 33.95 20.453 8.694 2.696 1.445 0.991 0.726 ARI-100 38.209 23.056 9.8 3.025 1.615 1.104 0.807 ARI-500 48.099 29.1 12.369 3.789 2.009 1.367 0.994 ARI1000 52.358 31.704 13.475 4.118 2.178 1.48 1.075 ARI1000000 94.799 57.647 24.5 7.398 3.87 2.609 1.88 ARI1.11 10.792 6.272 2.703 0.965 0.584 0.438 0.347 ARI1.25 11.444 6.643 2.858 1.019 0.617 0.462 0.366 ARI-2 14.045 8.125 3.479 1.234 0.745 0.557 0.441 ARI-5 19.114 11.014 4.689 1.652 0.995 0.743 0.588 ARI-10 22.949 13.199 5.604 1.969 1.184 0.884 0.699 ARI-20 26.783 15.384 6.519 2.286 1.373 1.024 0.81 ARI-50 31.852 18.273 7.729 2.704 1.624 1.21 0.956 ARI-100 35.686 20.459 8.645 3.021 1.813 1.351 1.067 ARI-500 44.589 25.533 10.77 3.756 2.252 1.677 1.324 ARI1000 48.423 27.718 11.686 4.073 2.441 1.818 1.435 ARI1000000 86.633 49.497 20.809 7.23 4.326 3.219 2.54 81038 ARI-1 10.209 5.939 2.564 0.917 0.556 0.416 0.33 142 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 7.8 4.142 1.372 0.285 0.12 0.071 0.046 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.382 4.489 1.467 0.286 0.115 0.065 0.041 81049 ARI-1 10.067 5.615 2.366 0.885 0.566 0.442 0.364 ARI1.11 10.924 6.086 2.555 0.948 0.603 0.469 0.386 ARI1.25 11.883 6.613 2.766 1.019 0.645 0.5 0.41 ARI-2 15.709 8.714 3.609 1.3 0.811 0.623 0.506 ARI-5 23.168 12.811 5.249 1.848 1.135 0.862 0.694 ARI-10 28.811 15.91 6.49 2.263 1.38 1.044 0.837 ARI-20 34.454 19.01 7.73 2.677 1.625 1.226 0.98 ARI-50 41.914 23.107 9.37 3.225 1.95 1.466 1.17 ARI-100 47.557 26.206 10.61 3.639 2.195 1.648 1.313 ARI-500 60.66 33.402 13.49 4.601 2.765 2.07 1.646 ARI1000 66.303 36.502 14.73 5.015 3.01 2.252 1.789 ARI1000000 122.542 67.389 27.089 9.142 5.455 4.066 3.219 ARI1.11 11.208 6.282 2.618 0.934 0.576 0.438 0.353 ARI1.25 11.961 6.694 2.785 0.993 0.612 0.466 0.375 ARI-2 14.966 8.338 3.453 1.229 0.758 0.577 0.465 ARI-5 20.824 11.544 4.755 1.688 1.042 0.794 0.641 ARI-10 25.255 13.969 5.74 2.036 1.257 0.959 0.774 ARI-20 29.686 16.394 6.724 2.383 1.472 1.123 0.907 ARI-50 35.545 19.6 8.026 2.843 1.756 1.34 1.083 ARI-100 39.976 22.025 9.011 3.19 1.971 1.504 1.216 ARI-500 50.266 27.655 11.298 3.997 2.47 1.885 1.525 ARI1000 54.697 30.08 12.282 4.345 2.685 2.05 1.658 ARI1000000 98.861 54.246 22.097 7.809 4.826 3.686 2.983 81114 ARI-1 10.535 5.913 2.468 0.881 0.543 0.413 0.332 143 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 8.382 4.489 1.467 0.286 0.115 0.065 0.041 Station Duration(hours) 1 2 6 24 48 72 100 ARI-0.1 6.859 4.128 1.458 0.259 0.092 0.048 0.027 81114 ARI-1 10.535 5.913 2.468 0.881 0.543 0.413 0.332 ARI1.11 11.208 6.282 2.618 0.934 0.576 0.438 0.353 ARI1.25 11.961 6.694 2.785 0.993 0.612 0.466 0.375 ARI-2 14.966 8.338 3.453 1.229 0.758 0.577 0.465 ARI-5 20.824 11.544 4.755 1.688 1.042 0.794 0.641 ARI-10 25.255 13.969 5.74 2.036 1.257 0.959 0.774 ARI-20 29.686 16.394 6.724 2.383 1.472 1.123 0.907 ARI-50 35.545 19.6 8.026 2.843 1.756 1.34 1.083 ARI-100 39.976 22.025 9.011 3.19 1.971 1.504 1.216 ARI-500 50.266 27.655 11.298 3.997 2.47 1.885 1.525 ARI1000 54.697 30.08 12.282 4.345 2.685 2.05 1.658 ARI1000000 98.861 54.246 22.097 7.809 4.826 3.686 2.983 ARI1.11 9.867 6.064 2.669 0.87 0.479 0.334 0.248 ARI1.25 10.877 6.608 2.873 0.931 0.514 0.359 0.268 ARI-2 14.914 8.771 3.683 1.177 0.653 0.459 0.345 ARI-5 22.806 12.969 5.255 1.655 0.923 0.655 0.495 ARI-10 28.786 16.137 6.441 2.017 1.128 0.802 0.609 ARI-20 34.768 19.304 7.626 2.379 1.333 0.95 0.723 ARI-50 42.68 23.487 9.193 2.857 1.603 1.146 0.873 ARI-100 48.667 26.65 10.377 3.219 1.808 1.293 0.987 ARI-500 62.57 33.992 13.126 4.06 2.284 1.637 1.252 ARI1000 68.558 37.154 14.31 4.422 2.488 1.785 1.366 ARI1000000 128.248 68.655 26.105 8.028 4.529 3.258 2.502 81115 ARI-1 8.965 5.576 2.486 0.815 0.448 0.312 0.231 144 APPENDIX E INTENSITY- FREQUENCY-DURATION CURVES (ARI in years) ARI-1 Station 77087 ARI-1.11 1000 Station 82016 ARI-1 1000 ARI-1.11 ARI-1.25 100 ARI-2 ARI-5 ARI-5 ARI-10 10 ARI-1.25 ARI-2 Ic (mm/h) Ic (mm/h) 100 ARI-20 ARI-10 10 ARI-20 ARI-50 1 ARI-100 0.1 ARI-50 1 ARI-100 ARI-500 1 10 100 dc(h) ARI-1000 ARI-500 0.1 1 ARI-1000000 Station 82011 ARI-1 1000 dc (h) 10 100 Ic (mm/h) ARI-2 ARI-1.11 ARI-5 ARI-10 10 ARI-20 ARI-1.25 100 Ic (mm/h) 100 ARI-2 ARI-5 ARI-10 10 ARI-20 ARI-50 1 ARI-50 1 ARI-100 ARI-100 1 ARI-1000 1 dc (h) 10 100 Station 82039 ARI-500 0.1 ARI-500 0.1 10 dc (h) ARI-1000000 ARI-1.11 100 ARI-1 ARI-1.11 1000 ARI-1.25 ARI-1.25 100 ARI-2 ARI-10 10 ARI-20 ARI-2 100 ARI-5 Ic (mm/h) Ic (mm/h) ARI-5 ARI-10 10 ARI-20 ARI-50 ARI-50 1 1 ARI-100 ARI-100 ARI-500 ARI-500 0.1 1 10 dc (h) 100 ARI-1000 0.1 ARI-1000 1 ARI-1000000 ARI-1.11 dc (h) 10 100 Station 82107 ARI-1 Station 79046 1000 ARI-1.11 ARI-1.25 ARI-5 ARI-10 10 ARI-20 ARI-50 1 ARI-2 100 ARI-5 Ic (mm/h) Ic (mm/h) ARI-2 ARI-10 10 ARI-20 ARI-50 1 ARI-100 ARI-100 ARI-500 ARI-500 0.1 1 10 dc (h) 100 ARI-1000 ARI-1000000 ARI-1000000 ARI-1 1000 ARI-1.25 100 ARI-1000 ARI-1000000 Station 82076 ARI-1 1000 ARI-1000000 ARI-1 Station 82042 1000 ARI-1.11 ARI-1.25 ARI-1000 0.1 1 dc (h) 10 100 ARI-1000 ARI-1000000 145 ARI-1.11 ARI-1 Station 83067 ARI-1 Station 82121 1000 ARI-1.11 1000 ARI-1.25 ARI-1.25 Ic (mm/h) ARI-5 ARI-10 10 ARI-20 ARI-50 1 ARI-2 100 Ic (mm/h) ARI-2 100 ARI-5 ARI-10 10 ARI-20 ARI-50 1 ARI-100 ARI-100 ARI-500 0.1 ARI-500 0.1 ARI-1000 1 dc (h) 10 100 1 10 dc (h) ARI-1000000 ARI-1.11 ARI-1 Station 83074 ARI-1.11 1000 ARI-1.25 ARI-1.25 Ic (mm/h) ARI-5 ARI-10 10 ARI-20 ARI-50 1 ARI-2 100 ARI-5 Ic (mm/h) ARI-2 100 ARI-10 10 ARI-20 ARI-50 1 ARI-100 ARI-100 ARI-500 0.1 1 dc (h) 10 100 ARI-500 0.1 ARI-1000 1 dc (h) 10 100 ARI-1000000 Station 83031 Station 84005 ARI-1 ARI-1.25 ARI-2 ARI-10 10 ARI-20 ARI-5 ARI-10 10 ARI-20 ARI-50 ARI-50 1 ARI-2 100 Ic (mm/h) Ic (mm/h) ARI-5 1 ARI-100 ARI-100 ARI-500 ARI-500 0.1 1 10 100 0.1 ARI-1000 ARI-1.11 1000 dc (h) 10 100 ARI-1.11 1000 ARI-1.25 ARI-1.25 Ic (mm/h) ARI-5 ARI-10 10 ARI-20 ARI-50 1 ARI-2 100 Ic (mm/h) ARI-2 100 ARI-5 ARI-10 10 ARI-20 ARI-50 1 ARI-100 ARI-100 ARI-500 0.1 1 dc (h) 10 100 ARI-1000 ARI-1000000 ARI-1000000 ARI-1 Station 84015 ARI-1 Station 83033 ARI-1000 1 ARI-1000000 dc (h) ARI-1000000 ARI-1.11 ARI-1.25 100 ARI-1000 ARI-1 1000 ARI-1.11 1000 ARI-1000 ARI-1000000 ARI-1 Station 83025 1000 100 ARI-500 0.1 ARI-1000 1 dc (h) 10 100 ARI-1000000 146 ARI-1 Station 84078 ARI-1.11 1000 ARI-0.1 Station 79079 ARI-1 1000 ARI-1.11 ARI-1.25 Ic (mm/h) 100 ARI-5 ARI-10 10 ARI-20 ARI-50 1 ARI-1.25 100 Ic (mm/h) ARI-2 ARI-2 ARI-5 ARI-10 10 ARI-20 ARI-50 1 ARI-100 ARI-100 ARI-500 0.1 ARI-500 0.1 ARI-1000 1 dc (h) 10 100 ARI-1000 1 ARI-1000000 ARI-1 Station 84112 ARI-1.11 1000 10 dc (h) 100 Station 79052 ARI-1 ARI-1.11 1000 ARI-1.25 Ic (mm/h) ARI-5 ARI-10 10 ARI-20 ARI-50 1 ARI-1.25 ARI-2 100 ARI-5 Ic (mm/h) ARI-2 100 ARI-10 10 ARI-20 ARI-50 1 ARI-100 ARI-100 ARI-500 0.1 ARI-1000 1 dc (h) 10 100 ARI-500 ARI-1000 0.1 1 ARI-1000000 100 ARI-1.11 ARI-2 100 ARI-1.11 1000 ARI-1.25 ARI-5 ARI-20 ARI-50 1 ARI-100 Ic (mm/h) 10 ARI-2 100 ARI-10 ARI-5 ARI-10 10 ARI-20 ARI-50 1 ARI-500 ARI-100 ARI-1000 0.1 dc (h) 10 100 ARI-500 ARI-1000000 0.1 1 dc (h) 10 100 ARI-1.11 ARI-1 ARI-1.11 1000 ARI-1.25 ARI-1.25 ARI-2 ARI-5 ARI-10 10 ARI-20 ARI-50 1 ARI-2 100 Ic (mm/h) Ic (mm/h) 100 ARI-5 ARI-10 10 ARI-20 ARI-50 1 ARI-100 ARI-100 ARI-500 0.1 ARI-1000 dc (h) 10 100 ARI-1000000 ARI-1000 ARI-1000000 Station 85034 ARI-1 Station 85000 1000 1 ARI-1000000 ARI-1 Station 85026 ARI-1.25 Ic (mm/h) 10 dc (h) ARI-1 Station 84125 1000 1 ARI-1000000 ARI-500 0.1 1 10 dc (h) 100 ARI-1000 ARI-1000000 147 ARI-0.1 Station 85072 ARI-1 1000 ARI-1 Station 85176 ARI-1.11 1000 ARI-1.11 ARI-1.25 ARI-1.25 ARI-2 Ic (mm/h) ARI-5 ARI-10 10 ARI-20 ARI-50 1 ARI-2 100 Ic (mm/h) 100 ARI-5 ARI-10 10 ARI-20 ARI-50 1 ARI-100 ARI-100 ARI-500 ARI-500 0.1 0.1 ARI-1000 1 dc (h) 10 100 1 ARI-1000000 ARI-1.11 1000 10 100 ARI-1.25 ARI-5 ARI-10 10 ARI-20 ARI-2 100 Ic (mm/h) Ic (mm/h) 100 ARI-5 ARI-10 10 ARI-20 ARI-50 ARI-50 1 1 ARI-100 ARI-100 ARI-500 ARI-500 0.1 1 10 100 dc (h) ARI-1000 0.1 ARI-1000 1 ARI-1000000 ARI-1.11 1000 dc (h) 10 100 ARI-1 1000 ARI-1.11 ARI-1.25 ARI-10 10 ARI-20 Ic (mm/h) ARI-5 Ic (mm/h) ARI-1.25 100 ARI-2 100 ARI-2 ARI-5 ARI-10 10 ARI-20 ARI-50 ARI-50 1 1 ARI-100 ARI-100 ARI-500 ARI-500 0.1 ARI-1000 0.1 1 dc (h) 10 100 ARI-1000 1 ARI-1000000 ARI-1.11 1000 dc (h) 10 100 ARI-1.11 1000 ARI-1.25 ARI-1.25 ARI-2 ARI-5 ARI-10 10 ARI-20 ARI-50 1 ARI-2 100 Ic (mm/h) Ic (mm/h) 100 ARI-5 ARI-10 10 ARI-20 ARI-50 1 ARI-100 ARI-100 ARI-500 0.1 ARI-1000 1 dc (h) 10 100 ARI-1000000 ARI-1000000 ARI-1 Station 86038 ARI-1 Station 85170 ARI-1000000 ARI-0.1 Station 85256 ARI-1 Station 85106 ARI-1000000 ARI-1.11 1000 ARI-1.25 ARI-2 ARI-1000 ARI-1 Station 85237 ARI-1 Station 85103 dc (h) ARI-500 0.1 ARI-1000 1 10 dc (h) 100 ARI-1000000 148 APPENDIX F DERIVED FLOOD FREQUENCY CURVES OF THE TWELVE TEST CATCHMENTS DFFC for 222202 310 260 Q (m3/s) 210 160 110 60 10 1 10 100 ARI (years) 149 DFFC for 223202 210 Q (m3/s) 160 110 60 10 1 10 100 ARI (years) DFFC-for 226204 260 Q (m3/s) 210 160 110 60 10 1 10 100 ARI (years) 150 DFFC for 226410 100 90 80 Q (m3/s) 70 60 50 40 30 20 10 1 10 100 ARI (years) DFFC-for 227200 150 130 Q (m3/s) 110 90 70 50 30 10 1 10 100 ARI (years) 151 DFFC-for 229218 70 60 Q (m3/s) 50 40 30 20 10 1 10 100 ARI (years) DFFC-for 230204 110 Q (m3/s) 90 70 50 30 10 1 10 100 ARI (years) 152 DFFC-for 234200 105 Q (m3/s) 85 65 45 25 5 1 10 100 ARI (years) DFFC-for 235211 85 75 Q (m3/s) 65 55 45 35 25 15 5 1 10 100 ARI (years) 153 DFFC-for 237205 100 90 80 Q (m3/s) 70 60 50 40 30 20 10 0 1 10 100 ARI (years) DFFC for 238229 100 90 80 Q (m3/s) 70 60 50 40 30 20 10 0 1 10 100 ARI (years) 154 APPENDIX G A NUMERICAL EXAMPLE ILLUSTRATING THE IDENTIFICATION OF A STORM-CORE Consider the complete storm given in Figure G1. It has 5 hour duration. The stormcore from this complete storm is identified below. 18 16 14 I (mm/h) 12 10 8 6 4 2 0 1 2 3 4 5 Period Figure G1. A plot of complete storm Total rainfall = 1.5+5.2+8.9+15.4+1.2 = 32.2 mm. Duration = 5 hour Rainfall intensity = 6.44 mm/hour From AUSIFD 2I5=12.8 mm/h P P CHECK: Ist Crieteria: B B I D ≥ f1 × 2 I D 155 2nd Crieteria: I d ≥ f ×2 I d 2 P P B Here, f1 = 0.4 and f2 = 0.5 B B I D ≥ f1 × 2 I D B Ist Crieteria: B So, f1 x 2ID= 0.4 x 12.8 = 5.12 mm/hour P B B P B B Where 6.44 > 5.12 Accept the complete storm. Now find the storm-core, as shown in Table G1. Here 3 hour duration gives the highest ratio, thus, the storm-core consists of 5.2mm, 8.9mm and 15.4mm rainfalls, as plotted in Figure G2. Table G1 Identification of storm-core Storm-core duration A 1 2 3 4 5 Storm-core intensity (mm/h) B 15.40 12.15 9.83 7.75 6.44 2ID (ARR design rainfall), mm/h C 39.40 24.40 18.40 15.00 12.80 Ratio D (=B/C) 0.39 0.50 0.53 0.52 0.50 18 16 14 I (mm/h) 12 10 8 6 4 2 0 1 2 3 Period Figure G2. Identified storm-core 156
© Copyright 2026 Paperzz