ACI-NA Total Industry Estimate

Based on Total Industry Estimate , ACI-NA Total
Capital Needs are 53% higher than the NPIAS Cost
Total Industry Estimate in $Billions (2011-2015)
28.0
52.2
52.0
NPIAS
ACI-NA
Ineligible
AIP-Eligible
Note: large, medium and small hubs are based on ACI-NA survey and other hubs are based on FAA NPIAS report.
www.aci-na.org
1
What NPIAS Fails To Capture?
 PFC-funded projects & other projects with identified
funding (bonds, local funding, etc.)
 Airport funded air traffic control facilities and airport or
TSA funded security projects
 AIP-eligible projects that airports did not report to the FAA
because there would be a low probability of getting
additional AIP funding
 AIP-ineligible projects
– Automobile parking structures, hangars & air cargo buildings
– Revenue producing portion of passenger terminals
– Improvements to highway and transit systems beyond the
airport property line
www.aci-na.org
2