Diapositiva 1

Work Package 2
Coordination with EGEE activities
Marco Verlato
(INFN-Padova)
CYCLOPS Review
26 October 2007
Bruxelles, Belgium
Layout





2
INFN role in the project
WP2 objectives
WP2 results and future plans
List of Deliverables
Conclusions
INFN role in the project





3
INFN is involved in several EU and National Grid
projects (EGEE-II, EGI-DS, OMII-Europe,
EUMed/China/IndiaGrid, EELA, BioinfoGRID, IGI,
LIBI, etc.)
INFN is leading the Middleware Engineering activity
in EGEE-II (and its successor EGEE-III)
INFN is involved in all of the 5 WPs of the
CYCLOPS project
Its main role in CYCLOPS is leading the WP2, i.e.
coordinating with the EGEE activities
A significant role played in WP4 too, i.e. defining
research and innovation strategies for a einfrastructure for Civil Protection applications
WP2 objectives
From the DoW:





4
CYCLOPS main goal is “to bridge the gap between
Grid and CP communities”
WP2 aims “to carry out CP and Grid communities
inter-dissemination” (project objective 5)
Operational goals:
“Tutorial on EGEE platform for Civil Protection
agencies”
“Civil Protection framework and EGEE coordination”
 to establish a two way communication channel
between CYCLOPS and EGEE projects
WPs Interdependencies
Civil Protection
system
Analysis
Full time coverage of the
CYCLOPS core activities
carried out by WP3 and WP4
Management
Research & Innovation
Strategy Definition
Dissemination and Exploitation
5
WP2 tasks




Start date: PM3
Duration: 18 Months
WP Leader: INFN
Tasks:
–
–

T2.1: Dissemination and tutorial of the EGEE middleware
to the Civil Protection community
T2.2: Civil Protection Framework and EGEE middleware
evolution coordination
Effort in Person Months: 21.5
Part.
PeM
6
DDSC
1,25
11,75
3,25
1,75
TEI-CR
SNBPC
1,75
1,75
Task 2.1 activities so far
T2.1: Dissemination and tutorial of the EGEE
middleware to the Civil Protection community
–
Talk about EGEE platform at Project Open Conference in
June 2006
–
Writing the Training Event Plan and the EGEE Cookbook
for Civil Protection users
–
1st CYCLOPS Training Workshop held in Bologna the 1113 April 2007
Agenda and training material available under the “Events”
menu of the project web site www.cyclops-project.eu
A complete report is available in the First Training
Workshop (D10) document
7
The GILDA Project (https://gilda.ct.infn.it)
•15 sites in 3 continents
•> 2800 certificates issued, >15%
renewed at least once
•> 100 tutorials and demos performed
in 21 months
•> 1,000,000 hits (> 50,000 unique
visits) on (of) the web site from 10’s
of different countries
•> 0.6 TB of training material
downloaded from the web site
8
The First Training Workshop





9
It suffered the delay in the transfer of funds from EC to DPC
and from this to Partners (ANPC and TEI-CR could not attend)
Delivered at PM11 (April ‘07) instead of PM7
14 participants (DPC, EMA, CNR-IMAA and INFN represented)
First half day of workshop on CYCLOPS activities, then grid
tutorial with theory and hands-on
Positively evaluated by participants through questionnaire
Task 2.1 results and future plans

Measure of success according to DoW:
–
Number of training events  1
–
Number of attendees at training events  14
–
Questionnaire for self-evaluation of training events 
average score = 5/6
(1:poor, 2:insufficient, 3:fair, 4:good, 5:very good, 6:excellent)

10
Plans for next period:
–
DPC/IMAA/INFN team attending the “INFN School for
porting new applications to grid”, 12-23 November 2007
–
the goal is to port RISICO application to grid
–
the next training workshop, to be held close to a CP
community event to broaden the audience, will include the
RISICO porting experience as a practical example
Task 2.2 activities so far
T2.2: Civil Protection Framework and EGEE
middleware evolution coordination
11
–
Talk at EGEE’06 Conference in Geneva, 27 September 2006
–
Participation to periodical EGEE-ITF phone meetings
–
Set up of cyclops VO services and resources on Grid.It, with
CNR-IMAA Registration Authority of INFN CA
–
Technical Expert Group (TEG) meeting with Bob Jones (EGEE
leader) and all partners in Rome, 30 November 2006
–
Several technical meetings with WP3 and WP4 partners
–
Supporting the grid implementation of a WCS prototype
–
Supporting the grid implementation of RISICO prototype
–
Talk at OGF20 in Manchester, 7 May 2007
–
Talk at EGEE User Forum in Manchester, 11 May 2007
–
Poster at EGEE’07 Conference in Budapest, 1-5 October 2007
CYCLOPS VO-enabled resources in Grid.It
Central VO services:
LFC: lfcserver.cnaf.infn.it
VOMS: voms2.cnaf.infn.it
WMS: prod-wms-01.pd.infn.it, glite-rb-00.cnaf.infn.it
Computing and Storage resources:
#CPU
Free
Total Jobs
Running Waiting ComputingElement
---------------------------------------------------------4
1
30
0
30
gridce.ilc.cnr.it:2119/jobmanager-lcgpbs-grid
70
1
40
1
39
gridba2.ba.infn.it:2119/jobmanager-lcgpbs-short
70
1
1762
34
1728
gridba2.ba.infn.it:2119/jobmanager-lcgpbs-long
70
1
2307
11
2296
gridba2.ba.infn.it:2119/jobmanager-lcgpbs-infinite
44
14
8
6
2
grid0.fe.infn.it:2119/jobmanager-lcgpbs-grid
44
0
36
15
21
prod-ce-01.pd.infn.it:2119/jobmanager-lcglsf-grid
539
4
30
4
26
gridce2.pi.infn.it:2119/jobmanager-lcglsf-grid4
25
9
15
12
3
grid001.ts.infn.it:2119/jobmanager-lcglsf-grid
12
2
14
10
4
gridce.sns.it:2119/jobmanager-lcgpbs-grid
738 total CPU-cores (not dedicated)
12
Avail Space(Kb) Used Space(Kb) Type
SEs
---------------------------------------------------------395156380
4970248
n.a
gridse.ilc.cnr.it
445299512
1364038152
n.a
grid007g.cnaf.infn.it
3912509084
481669476
n.a
prod-se-01.pd.infn.it
52670212
656381412
n.a
gridit002.pd.infn.it
3840000000
250000000
n.a
prod-se-02.pd.infn.it
2322948608
19715584
n.a
grid002.ts.infn.it
67267572
3758208
n.a
gridse.sns.it
> 10 TB (not dedicated)
WCS grid implementation schema
The production grid
infrastructure used
as test-bed to
implement
a grid Web
Coverage Service
13
Task 2.2 results and future plans
 Measure of success according to DoW:
–
Number and impact of feedback provided by CYCLOPS to EGEE
 presence at 3 EGEE conferences and 1 TEG meeting
–
Timeliness of information about new middleware functionalities
implemented by EGEE project  no significant functionalities
added to gLite after the training workshop, but cyclops VO
resources kept continuously updated w.r.t. middleware upgrades
 Plans for next period:
14
–
Report to TEG annual meeting and next EGEE events (EGEE
User Forum in February 2008) the results of WP3 and WP4
activities, most notably the “EGEE Request for Enhancement”
document (D14)
–
Keep running the cyclops VO infrastructure and open it to support
RISICO and Flash Flood prototype applications
Deliverables list for WP2
M2.2
M2.1
Training Plan EGEE explained
to CP community
published
D5
Training
Events
Plan
D7
EGEE Cookbook:
A guide for CP
grid users
D17
WP2 activity
final report
done
done
done
PM 23
PM 24
Apr 2008
May 2008
planned
Gen 2008
due
PM 20
Dec 2006
Jun 2007
PM 7
Nov 2006
PM 13
PM 6
Aug 2006
Apr 2007
PM 3
June 2006
due
PM 11
PM 1
15
D10
First Training
Workshop
D13
Second Training
Workshop
Conclusions

Grid concepts and the EGEE middleware services
have been disseminated in several occasions
–
–


16
Towards a wide heterogeneous Civil Protection related
audience (at the Project Open Conference)
Towards CYCLOPS partners (at the Training Workshop and
at several technical meetings)
A more focused training action, aiming to investigate
grid integration approaches and prototyping the
selected use-cases is planned for the next period
CYCLOPS feedback to EGEE planned at next User
Forum at Clermont-Ferrand, 11-14 February 2008