KARNATAKA POWER CORPORATION LIMITED [A GOVERNMENT OF KARNATAKA ENTERPRISE] TENDER DOCUMENT FOR THE WORK OF Providing Galvalium sheets to vehicle parking shed and service station at garage complex, SVP colony, Jog EXECUTIVE ENGINEER (Civil, Maintenance) KARNATAKA POWER CORPORATION LIMITED Jog Falls – 577 435 CONTENTS Sl No Particulars 01 Declaration 02 Section – 1: Special Attention 03 Section – 2: Definition of terms 04 Section – 3: Schedule of contract form 05 Section – 4: Tender for works 06 Section – 5: Condition s of Contract 07 Section – 6: General Conditions 08 Section – 7: General Specifications 09 Section – 8: Price Bid 10 Section – 9: Royalty Charges 11 Section – 10:Service tax format 12 Section – 11: Drawings 2 KARNATAKA POWER CORPORATION LIMITED SHARAVATHYVALLEY HYDRO ELECTRIC PROJECT Office of the Executive Engineer (Civil – Maintenance) Jog Falls-577 435, SagarTq, Shivamogga (D). Telephone: 08186 – 244202 Fax: 08186 - 240294 NOTICE INVITING TENDER (Two Cover System) (THROUGH e-PROCUREMENT PORTAL ONLY) Name of work: Providing Galvalium sheets to vehicle parking shed and service station at garage complex, SVP colony, Jog TENDER REFERENCE KPCL/SVP/CSE(M)J/2016-17/ ETND-41 Approximate value of work Rs. 31.78 Lakhs EMD : Rs. 63,600/Contract performance Guarantee: The contractor shall furnish a Contract Performance Guarantee (CPG) equivalent to 10% (Ten percent) of the contract price or amount put tender whichever is higher in the form of FDR/ TDR/ BG from any schedule bank acceptable to the corporation in the prescribed format and valid throughout contract period and maintenance period. For other details, view e-procurement portal www.eproc.karnataka.gov.in under Pre-qualification Tender section Contract period: Two Months Last date for receipt of tenders: 10.12.2016 up to 23.59.59Hours Place of opening of PQR bids Office of the Executive Engineer (Civil – Maintenance) ),Jog Falls-577 435 SagarTq, Shivamogga District. Telephone: 08186 – 244202 Bidders, who have not registered in e-procurement portal, may do so by registering through web sitewww.eproc.karnataka.gov.in AG Nanjundappa Executive Engineer (Civil – Maintenance), Jog SagarTq, Shivamogga (D) 3 Falls-577 435, KARNATAKA POWER CORPORATION LIMITED SHARAVATHYVALLEY HYDRO ELECTRIC PROJECT Office of the Executive Engineer (Civil – Maintenance), Jog Falls-577 435, SagarTq, Shivamogga District. Telephone: 08186 – 244202, Fax: 08186 - 240294 No. KPCL/SVP/CSE(M)/2016-17/ ETND-41 Date:11.11.2016 NOTICE INVITING TENDER (Two cover system) (THROUGH e-PROCUREMENT PORTAL ONLY) 01. Item rate tenders are invited through GoK e-procurement platform website https://eproc.karnataka.gov.in from eligible KPCL registered contractors / Agencies, having adequate financial resources, State of Art technology, suitable construction equipments and technical manpower with sufficient past experience in executing civil/similar nature of work including building for the following work at SVP COLONY ,Jog, SagarTq, Shivamogga Dist.. Karnataka State. Name of work Approximate value of work (In Lakhs) Providing Galvalium sheets to vehicle parking shed and service station at 31.78 Lakhs garage complex, SVP colony, Jog EMD (Rs) Tender processing fees (Non refundable Contract Class of period for Contractor completion of work 63,600/- As per eProcurement portal of GoK Two months 02. Calendar of events: Last date for receipt of tenders Date of opening of Technical bid(Cover 1) Date of opening of Financial bid (Cover 2) Class–II and above : 10.12.2016 up to 23.59.59 Hours : 13.12.2016 at 16.30 hours : 14.12.2016 at 10.00 hours 03. Eligibility criteria: 01) Any individual/company/ firm registered as contractor in KPCL. 02) No joint venture/Consortium is permissible. 03) Bidders shall not be under declaration of ineligibility for corrupt and fraudulent practices issued by the Government of Karnataka. 04) Non of the contracts of the bidder should have been terminated /foreclosed/EMD forfeited on account of his default in KPCL or elsewhere during last three years. 05) The bidder should possess the following documents; i) KPCL registration certificate. ii) Income tax PAN. iii) VAT registration certificate. iv) Independent PF code. v) Service Tax registration certificate. 4 04. MINIMUM PRE-QUALIFICATION REQUIREMENTS: Cover – 1 (TECHNICAL BID) 01. The intending bidder should have successfully completed at least one civil/similar nature of work amounting to Rs. 15.89 Lakhs. Work done certificate issued from State / Central Government / Government undertakings from the officers not below the rank of Executive Engineers or equivalent cadre shall be furnished. 02. The intending bidder should have achieved in at least two financial years a minimum annual financial turnover of Rs.31.78 Lakhs in the last five (5) financial years i.e., 2011-12, 2012-13, 2013-14, 2014-15 & 2015-16 (Financial turnover of previous years will be given weightage of 10% per year to bring them to the present price level). Turn over certificate duly certified by Chartered Accountant shall be furnished. 03. The bidder should furnish following documents. i) KPCL registration certificate. ii) Income tax PAN. iii) VAT registration certificate. iv) Independent PF code. v) Service Tax registration certificate. 04. DECLARATIONS: To be furnished in the format enclosed to bid document. Note: The above documents shall be uploaded along with other documents, failing / not satisfying the above criteria the tenders are liable for rejection. 05. Instruction regarding e-procurement:i. The bid is to be submitted through the GoK e-Procurement platform https://eproc.karnataka.gov.inonly. ii. Bidders, who have not registered in the GoK e-Procurement portal, may do so by registering through web site https://eproc.karnataka.gov.in. iii. The bidder can access tender documents on web site. The blank tender documents can be accessed through the e-procurement portal web site https://eproc.karnataka.gov.inand for assistance if any may contact HP Help desk Telephone Nos. 080-25501216, 080-25501227 or email at [email protected] for Payment Reconciliation : ([email protected], 94800 51521).Filled tenders along with EMD must be electronically submitted on line through internet within the date and time published in e-Procurement portal. The tender will be opened at prescribed time and date in presence of the bidders who wish to attend at the Office of the Executive Engineer ( Civil Maintenance ), KPCL, Jog - 577 435, Sagar Taluk, Shivamogga District. Ph:08186-244202. iv. After login to bidders, please scroll down to the right side bottom to see list of tenders. Please click there to find the details of NIT and down load copy of the tender. The tender can be down loaded in the portal as per prescribed date and time published in the portal. Only interested Bidders who wish to participate should remit on line transaction fee for tender after registering in the portal. The transaction fee is not refundable. v. Other details can be seen in the Bid documents. 06. Sub-letting of the work is not allowed. 5 07.BID VALIDITY: The validity of the bid shall be 180 days from the date of opening of the Technical bid (Cover – 1 ) 08. i. EMD: 63,600/-The e-Payment of EMD shall be made through Direct Debit / Credit Card / National Electronic Fund Transfer (NEFT) or over the counter (OTC) only through ICICI Bank. Only on receipt of full EMD along with bid, the bid will be opened and considered for evaluation. ii. Contract performance Guarantee: The successful bidders shall furnish a Contract performance guarantee (CPG) EQUIVALENT TO 10% (Ten percent) of the contract amount in the form of DD/BG from any schedule bank acceptable to the Corporation in the prescribed format before entering in to agreement and valid throughout contract period and maintenance period. iii) The prospective bidder should not coerce any other bidders to derail the healthy and competitive bidding process. Such acts entail the disqualification for participating in the tender process. The prospective bidder shall not resort to anti - competitive practices like price rigging, cartelization, ring formation or adopt unfair practices both Civil and Criminal aimed at preventing other bidders from quoting for the tender. Any acts that inhibits competition or any act that will be detrimental to the interest of Karnataka Power Corporation Ltd, if the bidder is found to have resorted to such practice as specified above, he and others who act in concert with him shall be debarred from quoting for this tender and for future tenders for a further period of three years. iv)KPCL reserves the right to verify any information/document furnished by the bidder should the circumstances so warrant in the overall interest of the Corporation. In case the information or the documents furnished are found to be incorrect or invalid, then tenders of such bidders will be cancelled and the EMD furnished by such bidders will be forfeited. v)KPCL reserve the right to accept or reject all the bids without assigning any reasons thereof. 09. COVER – 2( FINANCIAL BID ) a) Tender Schedule ”B” (Price Bid). b) The bidder shall sign and enclose the scanned copy of the details of service tax component duly filled as per the format is enclosed to the price bid. Cover-1 (Technical Bid) will be opened first. Cover-2 (Financial Bid) of those bidders who have furnished satisfactorily all required details/documents mentioned in cover-1 (Technical Bid) will only be opened. 10 GENERAL CONDITIONS:i. The original documents in support of documents furnished along with the bid should be produced for verification at any stage of tender process as and when sought for, failing which, the bids are liable for disqualification. ii. Rates shall be quoted in tender schedule ‘B’ (Bid) in the website itself. iii. The tender document is part and parcel of the agreement. iv. Conditional tenders are liable for rejection. 6 v. vi. vii. viii. ix. x. xi. xii. xiii. xiv. xv. xvi. 11. 12. The successful bidder shall give an under taking that they would abide by the provisions of the Employees Provident Fund Act and should have their independent PF Code . The Bidder shall obtain insurance coverage for all the workers deployed for this work. Insurance shall protect the contractor against all claims applicable under the workmen Compensation Act 1948. The Bidder shall quote rates Inclusive of all applicable taxes, including service tax, levies, duties and cess, Building Workers Welfare Cess @1 % etc., as per the latest GoK and GoI prevailing rules as on the date of price bid document. The rates quoted shall be inclusive of all applicable taxes including service tax. The bidder shall submit a declaration regarding the applicability of Service tax under various options by indicating the applicable option in the S.T. format (Declaration of Method of Payment of Service Tax) enclosed to the Bid document. The Bidder shall quote rates inclusive of PF as per the applicable rate as issued by the PF department from time to time and if any variation occurs it shall be paid / refunded by / to the Corporation against documentary evidence. As per Building and other construction workers’ Welfare Cess Act 1995, 1% Cess on bill amount shall be recovered in the work bills. KPCL shall recover the Income Tax, Work Contract Tax / VAT etc., at the prevailing applicable rates. If any variation in taxes & duties will be to the account of KPCL. The bidder should maintain register of labours deployed and wages paid for the workers and shall produce the documents whenever called for by the competent authority. Remittance towards PF shall be commensurate with the labour component of the work involved. The Bidder shall remit PF of labours to Bidders permanent PF code number only. In case the dates notified above are declared as holiday, the immediate next working day will be reckoned. If the bidder makes any alteration in the condition of contract or puts any condition of his own, such a tenders are liable for rejection. The bidder shall register himself under section 7 and their worker who will be engaged for the work under section 12 of the building and other construction workers act 1996. If not the successful bidder may do so immediately before award of work. Further details of the work or any clarifications can be obtained from the office of the Executive Engineer (Civil Maintenance), KPCL, Jog 577435, SagarTaluk, ShivamoggaDistrict during office hours. Corrigendum / modification / corrections, if any, will be published in the web site only. For Karnataka Power Corporation Limited, AG Nanjundappa Executive Engineer (Civil – Maintenance), Jog Falls-577 435, SagarTq, Shivamogga (D) 7 CC: : MD - for kind information. : TD/FD - for kind information : Deputy Commissioner & District Tender Bulletin Officer, Shivamogga for kind information with a request to publish in District Tender Bulletin. : ED(H)/ED(T)/ED(BTPS)/ED(F) - for kind information. : ED(CC) - for kind information with a request to make arrangements for publishing the Brief : NIT in the leading news paperof Karnataka state. : CCES/CCEK/CCED/CE (E,I&TA)/CCET/CE(C)BTPS, CE(Unit -3)BTPS / CEC: RPCL/ECES/ECEV/ECEC/ CEED / CETD - for kind information. : SE (CSD) - for kind information with a request to publish in KPCL website. : CSS(R)/SEC (RO)/CAS/SEE(S)/SEE (MGHE)/SEE (GP)/CKS/CPS/CRS. : Copy for information & vide publicity to:: CSE(R)/CSE(D)GP/EE(CCM)RTPS/EE(PCM – 1 &2)RTPS/ CAE(PH)/CAE(B)/CAE(D)/EE(MSP)J/AGM(F)J/ EE(TA)/Kargal. : AO (K)/AO (IA) KARGAL/CSAE (RL)/ (RC) : Contractors Association- Kargal / Gerusoppa / Mastikatte / Dandeli/Sagar/Shakthinagar : Notice board. 8 KARNATAKA POWER CORPORATION LIMITED DECLARATION (Declaration to be given by the BIDDER at the time of submission of the completed BID) Name of work: Providing Galvalium sheets to vehicle parking shed and service station at garage complex, SVP colony, Jog 01. 02. 03. I / We have studied the site conditions, labour conditions and read the Bid documents and related matters carefully and diligently and that I/We have submitted the Bid having studied, understood and accepted the full implications of the Bid document. The requirements of the BID documents as stated above will be fulfilled by me/us to the satisfaction of the Corporation. I / We hereby declare that the bid submitted by me / us has no conditions contravening the commercial conditions of the bid. I/We agree that should I/We fail to execute the agreement or to commence the work, an amount equal to the amount of Earnest Money shall be absolutely forfeited to the CORPORATION or out of any other money due to me / us from any other work in CORPORATION / State Government / Central Government / or otherwise. I/We hereby distinctly and expressly declare and acknowledge that before the submission of this Bid, that I / We have carefully followed the instructions, read the relevant Indian Standard Specifications and I/We have made examination of the Bid document and drawings, specifications, quantities and of the locations where such work is to be done and have made myself/ ourselves aware of the scope and specifications of the work to be done and availability of the quantities of materials required. I/We distinctly agree that I/We would hereafter make no claim or demand upon the CORPORATION based upon or arising out of any alleged misunderstanding or misconceptions or mistake on my / our part of the said covenants, agreements, stipulations, restrictions and conditions. Any notice required to be served on me / us shall be considered to have been served on me/us if delivered to me/us personally or forwarded to me/us by post (Registered or ordinary) or bye-mail or left at my/our address given in the Bid documents. I/We fully understand the terms and conditions of the contractto be entered into between me/us and the CORPORATION and thewritten CONTRACT shall be the foundation of the rights of both theParties. I / We hereby declare that none of his contracts have beenterminated/foreclosed/EMD forfeited on account of his default in KPCLor elsewhere during last Five years. Dated the -------------- day of --------------2015. Bidder Signature 9 SECTION - 1 SPECIAL ATTENTION 1. The Bidder shall carefully study and understand all the tender specifications, technical, commercial and general conditions before submitting the Bid. 2. The Bidder or his authorized representative shall visit the site and get conversant with the site conditions and other pertinent matters and details before submitting the bid. 3. The bid document contains special attention, definition of terms,and condition of contract, price bid, and tender documents. The tender documents can be accessed on web site. The blank tender documents can be accessed through the e-procurement portal web site https://eproc.karnataka.gov.inand for assistance may contact HP Help desk Telephone Nos. 080-22485867 / 22485927. Filled tenders along with EMD must be electronically submitted on line through internet within the date and time published in e-Procurement portal. The tender will be opened at prescribed time and date in presence of the tenderers who wish to attend at the Office of the Executive Engineer(Civil, Maintenance) KPCL, Jog Falls - 577435, SagarTaluk, Shimoga District. 4. Bids containing any conditions whatsoever are liable for rejection. 5. Bids with stipulations for settlement of dispute by referenceto arbitration are liable for rejection. 6. Tender without EMD, tenders not properly uploaded shall be rejected. 7. The bid document will be opened at prescribed time and date in presence of the tenderers who wish to attend at the Office of the Executive Engineer(Civil, Maintenance) KPCL, Jog Falls - 577435, SagarTaluk, Shimoga District. 8. Final acceptance rests with the corporation. Corporation reserves the right to accept any or reject any or all tenders without assigning any reasons thereof. 9. Rates quoted in price bid shall be final. The tenderer shall quote for all items in the price bid. Items for which no rate or price is entered by the tenderer, the payment for such item will not be made and shall be deemed to be covered by the other rates and prices in the price bid. Rebates, if any offered by the tenderer shall be provided only at the end of the prescribed Price bid only. 10. The contractor shall quote his rates inclusive of service tax and all other applicable taxes, levies, duties and cess, Building Workers Welfare Cess etc., as per the latest GoK and GoI prevailing as on the date of NIT. 10 SECTION – 2 DEFINITION OF TERMS 01. “Owner / Corporation” shall mean the Karnataka Power Corporation Ltd., on whose behalf the NIT is issued and shall include its successors and assignees as well as its authorized officers / representatives. 02. “Engineer” shall mean Chief Engineer of the corporation in charge of the project or such other officer as may be appointed to act as the Engineer for the purpose of the contract and shall also mean and include the SUPERINTENDING ENGINEER and EXECUTIVE ENGINEER or other officers directly in-charge of the work or any Part thereof. The Engineer where named as a final authority for decision shall mean only the Chief Engineer who is in charge of the project. 03. ENGINEER-IN-CHARGE’ shall mean the EXECUTIVE ENGINEER directly in-charge of the work or his duly authorized officer who shall direct and supervise the work. 04. ‘BID’ shall mean the proposal / document that the bidder submit in the prescribed and specified form. 05. ‘BIDDER’ Bidder shall mean the firm / party who quotes against this notification. 06. ‘CONTRACTOR’ shall mean the Successful Bidder whose Bid has been accepted by the CORPORATION and who has entered into an Agreement with the CORPORATION for the fulfillment of the CONTRACT and shall include his heirs, legal representatives, successors and permitted assignees. 07. SITE’ shall mean and include all the area in which operations in respect of the work are carried out. This term shall also include materials, stacking yard and the area where temporary structures are put up for installing machinery etc., 08. ‘MONTH‘ shall mean month as reckoned by English calendar. 09. SPECIFICATION’ shall mean collectively all the terms and stipulations contained in various sections of the ‘CONTRACT’ known as General Conditions, the Specifications and such Amendments, Revisions, Deletions or Additions, as may be made in the Agreement and all written Agreements made or to be made pertaining to the method and manner of performing the work or the quantities and qualities of the materials to be furnished under this ‘CONTRACT’. 10. ‘PLANT / EQUIPMENT’ shall mean and include any or all plant, machinery, tools and other implements of all description necessary for the execution of the work in safe and workman like manner. 11. The expression ‘WORK’ or ‘WORKS’ where used in this contract shall unless there be something in subject or context repugnant to such construction be construed to mean the work or works to be executed under or by virtue of the contract, whether temporary or permanent, whether original, altered, substituted, additional or modified. 11 12. ‘CONTRACT’ shall mean the order and associated specifications executed by the OWNER and the CONTRACTOR including other documents agreed between the parties or implied to form a part of the CONTRACT. 13. The word ‘CONTRACT PRICE’ shall mean the total of all payments as estimated from unit prices and estimated quantities set forth in the contract which are to be paid to the CONTRACTOR for the work to be done under the CONTRACT. 14. ‘DATE OF CONTRACT’ shall mean the calendar date on which the OWNER and Contractor have signed the ‘CONTRACT’ 15. ‘CONTRACT PERIOD’ shall mean period during which the Contract shall be executed as agreed between Corporation and Contractor in the contract reckoned from the date of Letter of Intent. 16. ‘MAINTENANCE PERIOD’ shall mean the period, after the issue of certificate of completion by the ENGINEER, during which the structure has to function without any trouble. 17. ‘ENGINEER’S INSTRUCTIONS’ shall mean any drawings and / or instructions oral and / or in writing, details directions and explanations issued by the ENGINEER or the OWNER from time to time during the ‘CONTRACT PERIOD’. 18. ‘WRITING’ shall include any manuscript, typewritten, fax, e-mail or printed statement, under or over signature and / or seal as the case may be. 19. NOTICE IN WRITING or WRITTEN NOTICE’ shall mean a notice in writing, typed or printed or hand written characters sent (unless delivered) personally or by any agreed system of electronic transmission to the last known private or business address or registered office of the addressee and shall be deemed to have been received when in the ordinary course of post it would have been delivered. 20. ‘BIDDER’S WORKS’ shall mean and include the land and other places that are used by the Contractor for the performance of the “works”. 21. ‘Virtual COMPLETION’ shall mean all ‘work‘ completed as directed and the ‘Site’ is cleared to the satisfaction of the ENGINEER. 22. Date of award of contract shall mean the date of issue of the letter of intent. 23. The words Tenderer and bidder shall have the same meaning wherever used in the contract. 24. ‘ACT OF INSOLVENCY’ shall mean any Act of Insolvency as defined by the Presidency Towns insolvency Act, or the Provisional Insolvency Act or any amending statute. 25. Words imparting the singular only shall also include the plural and vice versa, where the context requires. 26. Wherever figures are given in this contract under the work ‘Elevation’ or an abbreviation of it or where figures representing elevations are given, they shall mean the elevation relative to the arbitrary permanent bench mark fixed by the ENGINEER for the particular work, located as shown on site plan or a datum level established by the CORPORTION. 12 27. Wherever in this contract, the words directed, required, ordered, designated considered necessary, prescribed or words of like import are used, it shall be understood that the direction, requirement, permission, order, designation or prescription etc., of the engineer is intended. Similarly, the words approved, acceptable, satisfactory or words of like import shall mean approved by / or acceptable or satisfactory to the Engineer, unless another meaning is plainly intended. 13 SECTION -3 SCHEDULE OF CONTRACT FORM GENERAL RULES AND DIRECTIONS FOR THE GUIDANCE OF THE CONTRACTOR 01. All works proposed to be executed by contract will be notified in the form of NOTICE INVITING TENDER (NIT) put up on the notice boards of concerned offices/e-procurement. It may also be published in the NEWS Papers wherever required. 02. NIT will state the work to be carried out as well as the date for submitting and opening tenders and the time allowed for carrying out the work. Also the amount of earnest money to be deposited along with the tender.Every contractor who intends to tender for the work advertised by the KPCL shall be a Registered Contractor in KPCL ofrequired Class as per rules of registration of Contractor of Karnataka Power Corporation Limited. 03. Authorized copies of the specifications, designs and drawings and Schedules of rates and any relevant documents required in connection with the work will be open for inspection to contractors at concerned offices during office hours. 04. In the event of the tender being submitted by a firm, it must be signed separately by each partner thereof or in the even of the absence of any partner, it shall be signed on his behalf by a person holding a power of attorney authorizing him to do so. Such power of attorney should be produced with the tender and it must be disclosed that the firm is duly registered under the Indian Partnership Act. 05. Receipts for payments made on account of work executed by a firm, shall also be signed by the all the partners except where the contractor are described in their tender as a firm in which case the receipts shall be signed in the name of the firm by one of the partners or by some other person, having authority given by the firm. 06. Any person who submits a tender shall fill up in the Website stating at what rate for each item of price bid document i.e., Schedule-B (memorandum showing items of work to be carried out), he is willing to execute Only one rate for each item of work shall be quoted. Tender which proposes any alteration in the works specified in the tender or in the time allowed for carrying out the work, or which contains any other conditions, unless permitted by the corporation is liable for rejection. 07. The officer calling for tenders shall open tenders in the presence of Contractors or their representatives who wish to be present at that time. i) If the rate (s) quoted by the Contractor for any item (s) of work is (are) below 75% or above 125% of the rates provided in the estimate as recast on the basis of schedule of rates of the year of submission of tender for the work, such tender is liable to be rejected at the discretion of the accepting authority depending upon the type of item (s) for which such rates are quoted. However, such a tender can be considered for acceptance at the discretion of the accepting authority,withan additional security in the form a Bank Guarantee / FD / TDR acceptable to the Corporation, for an amount of 5% of the tendered amount of such smaller sums as may be decided by the accepting authority and provided further that this security shall be furnished before entering into agreement. The additional security deposit so obtained shall be released immediately after completion of such item / items. 08. 14 ii) The officer competent to dispose off the tender shall have the right of accepting any or rejecting any or all the tenders without assigning any reasons and is not bound to accept the lowest tender. 09. The rates tendered and accepted hold good until the fulfillment of the contract except as provided in Clause-13 of the conditions of the contract. 10. The measurements of work will be taken according to the standard methods in use in the Public Works Department/Corporation. 11. The tender of any bidder who does not accept the conditions contained in the tender documents unless otherwise permitted by Corporation is liable for rejection. 12. Each tenderer should give clearly in his tender, details of his place of residence and postal address. The delivery of the communication at the above named place or posting in the post box regularly maintained by the Post office or sending by letter registered for acknowledgement or other communication shall be deemed sufficient proof thereof. 13. The earnest money of the rejected tenderers will be returned by e-procurement cell after opening /processing of the tender. The earnest money deposit shall not bear any interest. 14. The successful tenderer shall attend the specified office of the KPCL on or before the date fixed by written intimation to him for executing agreement etc. Failure on the successful tenderer to execute the contract agreement as specified herein above would entail forfeiture of EMD. 15. The tenderer is not permitted to withdraw his tender or to make any modifications in the terms and conditions of his tender before expiry of the tender validity period of 180 days. 16. Income Tax at 2.3% of gross amount of the bill or at the rates prescribed from time to time will be recovered from each bill. 17. The contractor shall abide by the prevailing rules on the Income Tax, Sales tax,ServiceTaxand other statuary levies of Govt of Karnataka and local bodies, during the entire period of contract. 15 SECTION - 4 KARNATAKA POWER CORPORATION LIMITED SharavathyValley Project TENDER FOR WORKS I/We hereby tender for execution for the KARNATAKA POWER CORPORATION LIMITED, (herein before and herein after referred to as the Corporation) of the work specified in the under mentioned memorandum within the time specified in such memorandum at the rates quoted for each item specified in the Price Bid (memorandum showing the items of work to be carried out) and in accordance in all respects with specifications, designs, drawings and instructions in writing . MEMORANDUM Providing Galvalium sheets to vehicle parking shed and service station at garage complex, SVP colony, Jog a) Name of work b) Amount put to tender Rs. 31.78 Lakhs c) Earnest money deposit Rs. 63,600/- d) Time allowed for completion of work Two months Should this tender be accepted I/We agree to abide by and fulfill all the terms and provisions of the conditions of the contract annexed hereto and all the terms and provisions contained in the Notice inviting tenders so far as applicable and in default thereof to forfeit and pay to Corporation, the sum of money mentioned in the said conditions. A sum of Rs. 63,600/- is paid through e-procurement portal as Earnest money. I/We agree that should I/We fail to execute the agreement or to commence the work specified in the above memorandum an amount equal to the amount of Earnest Money shall be absolutely forfeited to the Corporation or out of any other money due to me/us from any other works in Corporation/State Government/ Central Government/or otherwise. I/We hereby distinctly and expressly declare and acknowledge that before the submission of this tender, I/We have carefully followed the instructions read the relevant Indian Standard Specifications, and I/We have made examination of the contract documents and plans, specifications and quantities and of the locations where such work is to be done and have made myself/ourselves aware of the scope and specifications of the work to be done and availability of the quantities of materials required. I/We distinctly agree that I/We would hereafter make no claim or demand upon the Corporation based upon or arising out of any alleged misunderstanding or misconceptions or mistake on my/our part of the said covenants, agreements, stipulations, restrictions and conditions. Any notice required to be served on me/us shall be sufficiently served on me/us if delivered to me/us personally or forwarded to me/us by post (registered or ordinary) or left on my/our address given in the tender. 16 I/We fully understand the terms and conditions of the contract to be entered into between me/us and the Corporation and the written contract shall be foundation of the rights of the both the parties. Date……………………… this ………………….day………… of …………….2015 CONTRACTOR Address Witness: Address: M/s…………………………………… …………………………………………………….. …………………………………………………….. Occupation……………………………………… …………………………………………………….. The above tender is hereby accepted by me on behalf of the Corporation. Dated the…………………….day of …………..2015 Executive Engineer(Civil, Maintenance) Jog Falls– 577 435. NOTES: 01. The currency period of the tender shall be 180 days from the date of opening of the tender. If delay in deciding the tender is inevitable, the consent of the tenderer agreeing to keep open his offer for a minimum further period shall be obtained in advance. The minimum further period for which the tenderer is required to keep his offer open should invariably be specified before his consent is obtained if the validity of the tender is required to be extended. 17 SECTION - 5 GENERAL CONDITIONS OF CONTRACT CONDITION OF CONTRACT 5.01 CONTRACT PERFORMANCE GUARANTEE: Clause 01 (a) The contractor shall furnish a Contract performance guarantee ( CPG ) equivalent to 10% ( ten percent ) of the contract price in the form of FDR / TDR / BG from any schedule bank acceptable to the Corporation in the prescribed format and valid throughout contract period and maintenance period. The EMD deposit lodged / paid by the contractor shall be returned to him after the submission of contract performance guarantee by the contractor and after concluding the agreement by the contractor. Clause 01(b) The contract performance guarantee furnished by the contractor shall not bear any interest. Clause 01 (c). Due to Corporation to be set off against contract performance guarantee. All compensation or other sums of money payable by the Contractor to the Corporation under the terms and this contract may be realized or deducted from any amount payable to him or from the interest arising there from or from any sums which may be due or may become due by Corporation to the Contractor on any account whatsoever and in the event of his contract performance guarantee being reduced by reason of any such realization or deduction as aforesaid, the Contractor shall, within ten days thereafter, make good in cash any sum or sums which have been deducted from, or raised by sale of his contract performance guarantee or any part thereof. Clause 01 (d). Releaseof contract performance guarantee. The Contract performance guarantee (CPG) submitted by the contractor shall be returned to him after the completion of maintenance period subject to fulfillment of all obligation of the contract. 5.02 PENALTY FOR DELAY Clause 02 (a) WRITTEN ORDER TO COMMENCE WORK: After acceptance of the tender, the Executive Engineer shall issue a written order to the successful tenderer to commence the work. The Contractor shall enter upon or commence any portion of work only with the written authority and instructions of the Executive Engineer. Without such instructions the Contractor shall have no claim to demand for measurements of or payment for work done by him. Clause 02 (b) Programme of work: The time allowed for carrying out the work as entered in the tender shall be strictly observed by the Contractor. It shall be reckoned from the date of Letter of Indent / Letter of Award. The work shall throughout the stipulated period of the contract be proceeded with, all due diligence (time being deemed to be essence of the contract on the part of the Contractor). To ensure good progress during the execution of the work, the contractor shall be bound to comply with the construction schedule approved the Engineer based on the time schedule. 18 Clause 02 (c)Review of progress and responsibility for delay etc: The progress of all works shall be reviewed by the Executive Engineer with the Contractor during the first fortnight of every month. Such a review shall take into account the programme fixed for the previous month, obligations on the part of the Corporation like supply of materials, drawings etc., and also the obligations on the part of the Contractor. Apportioning of responsibility for delay between Contractor and Corporation: In case the progress achieved fall short of the agreed programme, the reasons for such shortfall shall be examined and a record made thereof apportioning the responsibilities for delay between the Contractor and the Corporation. This record should be signed in full and dated both by the Executive Engineer and Contractor. To the extent the shortfall is assessed as due to the delay on the part of the Contractor, the Contractor shall be liable to pay penalty as indicated Clause 02 (d) below. Grant of extension of time: If the delay is attributable to reasons beyond the control of the Contractor requisite extension of time on an application in writing by the contractor shall be granted by the Executive Engineer or other competent authority in accordance with Clause-5 after obtaining the approval of his higher authorities wherever necessary. Review or progress by Superintending Engineer/Chief Engineer: The Superintending Engineer and Chief Engineer shall review the progress once in every month. These reviews are in addition to the monthly reviews required to be done by the Executive Engineer. The results of the review by the higher authorities shall, wherever necessary be incorporated in the next review by the Executive Engineer. Settlement of dispute regarding shortfall in progress: In case of dispute between the Executive Engineer and the Contractor regarding the responsibility for the shortfall in progress, the matter shall be referred to the Superintending Engineer who shall thereupon give a decision within one month of the date of receipt of reference. The decision of the Superintending Engineer shall be final and binding on the Contractor. Clause 02 (d) Penalty for delay: In respect of the shortfall in progress, assessed as due to the delay on the part of the Contractor as per Clause 02 (b) and 02(c), the Contractor shall be liable to pay as penalty an amount equal to one percent of the estimated cost of the balance work assessed according to the programme, for every day that the due quantity of work remains incomplete provided always that the total amount of penalty to be paid under the provisions of this clause shall not exceed 10% (Tenpercent) of the cost of the entire work as shown in the contract, provided further that in the event of the Contractor making up the shortfall in progress within the stipulated or extended or extended time of completion, the penalty so recovered may be refunded on an application in writing by the Contractor. NOTE:If the Executive Engineer considers it necessary he shall be entitled to take action as indicated in Clause 03 (d) also. 19 Clause 02 (e) Adjustment of excess/over payments: Excess/over payment as soon as they are discovered should be adjusted in the next RA bill of the Contractor and in case the final bill has already been paid, the excess/over payment made shall be recovered from the Contract performance guarantee of the Contractor together with an interest at 13% or such other percentages as Corporation may decide from time to time from the date of such excess or over payment to the date of recovery. 5.03.ACTION WHEN THE WHOLE OF CONTRACT PERFORMANCE GUARANTEE IS FORFEITED: Clause 03 In any case in which under any clause or clauses of this Contract, the Contractor shall have rendered himself liable to pay compensation and/or penalty amounting to the whole of the Contract performance guarantee. The Executive Engineer, on behalf of the Corporation shall have power to adopt any of the following courses as he may deem best suited in the interest of Corporation. Clause 03 (a)Forfeiture of Contract performance guarantee: Without prejudice to Corporation right to recover any loss from the Contractor under sub clauses (b) and (c) of Clause-3 of the contract, to rescind the contract (of which rescission notice in writing to the Contractor under the hand of the Executive Engineer or other competent authority shall be conclusive evidence), and in that case, the Contract performance guarantee of the contractor shall stand forfeited and action will be initiated for encashment of Contract performance guaranteebythe Corporation. Clause 03 ( b )Debiting cost of labour and materials supplied: To employ labour paid by the Corporation and to supply materialsto carry out the work or any part of the work, debiting the Contractor with the cost of the labour and the price of the materials (as to the correctness of which cost and price, the certificate of the Executive Engineer shall be final and conclusive against the Contractor) and crediting him with the value of the work done, in all respects at the same rates as if it had been carried out by the Contractor under the terms of this Contract, and in that case the certificate of the Executive Engineer as to the value of the work done shall be final and conclusive against the Contractor. Clause 03 (c) Recovery of extra cost on unexecuted work: To measure up the work of the Contractor and to take such part thereof as is remaining unexecuted out of his hands, and to give it to another Contractor to complete it, in which case any expenses which may be incurred in excess of the sum which would have been paid to the original Contractor, if the whole work had been executed by him (as to the amount of which excess expenses the certificate in writing of the Chief Engineer shall be final and conclusive) shall be borne and paid by the original Contractor and shall be deducted from any money due to him by Corporation under this Contract or any Contract in Corporation/State Government/Central Government or otherwise or from his Contract performance guarantee or the proceeds of sale thereof or a sufficient part thereof. Clause 03 (d)Action against unsatisfactory progress: If the Contractor does not maintain the rate of progress as required under clause-2and if the progress of any particular portion of work is unsatisfactory even after taking action 20 under Clause-2(c) & (d),the Executive Engineer shall be entitled to take action under clause-3 (b) or 3 (c) at his discretion in order to maintain the rate of progress after giving the contractor ten (10) days notice in writing where upon the contractor will have no claim for any compensation for any loss sustained by him owing to such actions. Clause 03 (e) No compensation for loss sustained on advance action: In the event of any of the above courses being adopted by the Executive Engineer, the Contractor shall have no claim to compensation for any loss sustained by him by reason of his having purchased or procured any materials or entered into any engagements or made any advances on account of, or with a view to the execution of the work or the performance of the Contract and in case the Contract shall be rescinded under the provision aforesaid, the Contractor shall not be entitled to recover or be paid any sum for any work thereof actually performed by him under this Contract, unless and until the Executive Engineer shall have certified in writing the performance of such work and the amount payable in respect thereof, and he shall only be entitled to be paid the amount so certified. 5.04. CONTRACTOR TO REMAIN LIABLE TO PAY COMPENSATION IF ACTION IS NOT TAKEN UNDER CLAUSE 3. Clause 04 In any case in which any of the powers conferred upon the Executive Engineer by Clause–3 hereof shall have become exercisable and the same shall not have been exercised, the non-exercise thereof shall not constitute a waiver of any of the conditions hereof and such powers shall notwithstanding be exercisable in the event of any future case of default by the Contractor for which under any clause hereof he is declared liable to pay compensation or penalty amounting to the whole of his CPG and the liability of the Contractor for past and future compensation or penalty shall remain unaffected. Power to take possession of or require removal of or sell Contractor’s properties. In the event of the Executive Engineer taking action under sub-clause (a) or (c) of Clause–3, he may, if he so desires; take possession of all or any tools, plant, materials and stores, in or upon works or the site thereof belonging to the Contractor, or procured by him and intended to be used for the execution of the work or any part thereof, paying or allowing for the same in account at the Contract rate, not being applicable, at current market rates, to be certified by the Executive Engineer whose certificate thereof shall be final. In the alternative, the Executive Engineer may after giving notice in writing to the Contractor or his authorised agent, require him to remove such tools, plant, materials or stores from the premises within a time to be specified in such notice, and in the event of the Contractor failing to comply with any such requisition, the Executive Engineer may remove them at the Contractor’s expense or sell them by auction or private sale on account of the Contractor and at his risk in all respects, and the certificate of the Executive Engineer as to the expense of any such removal, and the amount of the proceeds and expense of any such sale shall be final and conclusive against the Contractor. 5.05. GRANT OF EXTENSION OF TIME: Clause 05 (a) If the contractor shall desire an extension of the time for completion of the work on the ground of his having been unavoidably hindered in its execution or on any other ground, he shall apply in writing to the Executive Engineer before the expiry of the period stipulated in the tender or before the expiry of 30 days from the date on 21 which the cause for asking for extension occurred, whichever is earlier and the Executive Engineer or other competent authority may, if in his opinion, there are reasonable grounds for granting an extension, grant such extension as he thinks necessary or proper. The decision of such competent authority in this matter shall be final. Clause 05 (b) The time limit for completion of the work shall be extended commensurate with its increase in cost occasioned by alterations or additions and the certificate of the Executive Engineer or other competent authority as to such proportion shall be conclusive. 5.06. ISSUE OF FINAL CERTIFICATE – CONDITIONS REGARDING Clause 06 On completion of the work, the Contractor shall report in writing to the Executive Engineer the completion of the work. Then he shall be furnished with a certificate by the Executive Engineer of such completion, but no such certificate shall be given nor shall the work be considered to the complete until the Contractor shall have removed from the premises on which the work shall have been executed, all scaffolding, surplus materials and rubbish, and shall have clean thoroughly all parts of the structure,works in or upon which the work has been executed, or of which he may have had possession for the purpose of executing the work, not until the work shall have been measured by the Executive Engineer or other competent authority, or where the measurements have been taken by his subordinates until they have received the approval of the Executive Engineer or other competent authority, the said measurement, being binding and conclusive against the Contractor. If the Contractor shall fail to comply with the requirements of this clause as to the removal of scaffolding, surplus materials and rubbish, and cleaning on or before the date fixed for the completion of the work, the Executive Engineer or other competent authority may at the expense of the Contractor, remove such scaffolding, surplus materials and rubbish, and dispose off the same as he think fit and clean off such dirt etc., as aforesaid, and the Contractor shall be liable to pay the amount of all expenses so incurred, but shall have no claim in respect of any such scaffolding or surplus materials as aforesaid except for any sum actually realized by the sale thereof. Closure of contract pending completion of minor items: In cases where it is not desirable to keep the contract open for minor items which can be carried out later at discretion of Executive Engineer or other competent authority, the main contract may be finalized after getting a supplementary agreement executed in the prescribed form by the same Contractor for doing the residual work. 5.07. CONTRACTOR TO SUBMIT BILLS MONTHLY IN PRINTED FORM Clause 07 (a)A bill shall be submitted by the contractor on 15th of every month for all the items of works executed in the previous month. All bills shall be prepared in the prescribed printed or typed form in quadruplicate and handed over to the subordinate in charge of the work/Sub-division or division office and acknowledgement obtained. 22 I. II. III. Contractor shall submit bills duly supported by hard copy of detailed measurements of work using electronic spread sheets and making computations thereof. The contractor shall submit diskette/ CD-ROM in addition to the hard copy. In the electronic spread sheet the reference of work order/ job order/ LOI agreements shall be indicated. The countersignature of the contractor or his authorized agent shall be obtained on each page in the hard copy of the detailed measurement spreadsheets prepared by the Junior/ Assistant Engineer which shall be binding on the contractor in all respects. Clause 07 (b) Scrutiny of bills and measurement of work: The details furnished by the Contractor in the bill should be completely scrutinised and the said work should be measured by the subordinate in the presence of the Contractor or his duly authorised agent. The countersignature of the Contractor or the said agent in the measurement book shall be sufficient proof to the correctness of the measurements, which shall be binding on the Contractor in all respects. If the Contractor does not submit the bills within the prescribed time, the Executive Engineer may depute within seven days of the prescribed date a subordinate to measure up the said work. The countersignature of the Contractor shall be obtained in the measurement book concerned with reference to which the bill may be prepared by the Corporation. Clause 07 (c) Filing of objections to measurement by Contractor: Before taking any measurement of any work has been referred to in Clause-7 (b) above, the Executive Engineer or a subordinate deputed by him shall give reasonable notice to the Contractor. If the Contractor fails to attend the measurement after such notice or fails to countersign or to the difference, within a week from the date of measurement in the manner required by the Executive Engineer, then in any such event, the measurement taken by the Executive Engineer or by the subordinate deputed by him as the case may be, shall be final and binding on the Contractor and the Contractor shall have no right to dispute the same. Clause 07 (d) One copy of the passed bill shall be given to the Contractor without any charge. 5.08 PAYMENT PROPORTIONATE TO WORK APPROVED AND PASSED Clause 08 No payment shall be made for any work estimated to cost Rupees five thousand or less until after the whole of the work shall have been completed and a certificate of completion given. But in the case of works estimated to cost more than Rs.5,000/- the Contractor shall on submitting the bill and after due verification by the subordinate as per Clause 7(b) be entitled to receive payment proportionate to the part of the work then approved and passed by the Executive Engineer or other competent authority whose certificate of such approval and passing of the sum so payable shall be final and conclusive against the Contractor. Payment at reduced rates: The rates for several items of works agreed to within shall be valid only when the items concerned are accepted as having been completed fully in accordance with the stipulated specifications. In case where the items of work are not accepted as so completed, the Executive Engineer or other competent authority may make payment on account of such items at such reduced rates as he may consider reasonable in the preparation of final or on account bills. 23 Intermediate payment be regarded as advances All such intermediate payments shall be regarded as payments by way of advance against the final payments only and not as payments for work actually done and completed and shall not preclude the Executive Engineer or other competent authority from requiring any bad, unsound, imperfect or unskilled work to be removed or taken away and reconstructed or re-erected not shall any such payment be considered as an admission of the due performance of the Contract or any part thereof in any respect or the accruing of any claim, nor shall it conclude, determine or affect in any other way the powers of the Executive Engineer or other competent authority as to the final settlement and adjustment, of the accounts, or otherwise or in any other way vary or affect the Contract. Submission of Final bill and its settlement The final bill shall be submitted by the Contractor within one month of the date of actual completion of the work in all respects. His claim shall be settled (except those under dispute) within five months thereafter. Disputed items The contractor shall submit a list of the disputed items within 30 days from the disallowance thereof and if he fails to do this, his claim shall be deemed to have been fully waived and absolutely extinguished. 5.09STORES SUPPLIED BY CORPORATION: DELETED 5.10 UNUSED MATERIALS: D E L ET E D 5.11NO CLAIMS TO COMPENSATION ON ACCOUNT OF LOSS DUE TO DELAY IN SUPPLY OF MATERIALS BY CORPORATION. DELETED 5.12 DEFINITION OF WORK: Clause 12 (a)The expression ‘work’ or ‘works’ where used in these conditions, shall unless there be something in the subject or context repugnant to such construction, be construed to mean the work or works contracted to be executed under or in virtue of the contract, whether temporary or permanent and whether original, altered, substituted or additional. Clause 12 (b) WORK TO BE EXECUTED IN ACCORDANCE WITH SPECIFICATIONS, DRAWINGS, ORDERS ETC., The Contractor shall execute the whole and every part of the work in the most sound and substantial and workman like manner and in strict accordance with the specifications both such regards materials and workmanship. The Contractor shall also conform 24 exactly, fully and faithfully to the designs, drawings and instructions in writing relating to the work signed by the Executive Engineer or other competent authority and lodged in his office and to which the Contractor shall be entitled to have access at such office, or on the site of the work for the purpose of inspection during office hours and the Contractor shall, if he so requires, be entitled at his own expense to obtain copies of the specification and of all such designs, drawings and instructions as aforesaid. The Contractor shall also be responsible for the delivery of structure in sound condition and the execution of the work strictly in accordance with the specifications of the work. Clause 12 (c) ACTION WHERE THERE IS NO SPECIFICATION In case of any class of work for which there is no such specification as is mentioned in Rule-3 General Rules and Directions of the Contract form, such work shall be carried out in accordance with Standard specifications, and in the event of there being no standard specifications, then in such a case the work shall be carried out in all respects in accordance with the instructions and requirements of the Executive Engineer or other competent authority. 5.13 ALTERATION IN QUANTITY OF WORK, SPECIFICATIONS AND DESIGNS, ADDITIONAL WORK, DELETION OF WORK. Clause 13 (a)( i )The Executive Engineer shall have power to make any alterations in omissions from, additions to or substitutions for the original specifications, drawings, designs and instructions that may appear to him to be necessary or advisable during the progress of work. For that purpose or if for any other reasons it shall in his opinion be desirable, he shall have power to order the Contractor to do and the Contractor shall do any or all of the following: a) b) c) d) e) f) Increase or decrease the quantity of any work included in the Contract. Omit any such work. Change the character or quality or kind of any such work. Change the levels, lines, positions and dimensions of any part of the work. Execute additional work of any kind necessary for the completion of the work, and Change in any specified sequence, methods or timing of construction of any part of the work. Contractor bound by Executive Engineer's instructions The Contractor shall be bound to carry out the work in accordance with any instructions in this connection which may be given to him in writing signed by the Executive Engineer or other competent authority and such alteration shall not in any way vitiate or invalidate the Contract. Clause 13 (a)( ii ) ORDERS FOR VARIATIONS TO BE IN WRITING No such variations shall be made by the contractor without an order in writing of the Executive Engineer, provided that on order in writing shall be required for increase or decrease in the quantity of any work where such increase or decrease is the result of the quantities exceeding or being less than those stated in the Schedule-B provided also that if for any reason the Executive Engineer shall consider it desirable to give any such order verbally, the Contractor shall comply with such order and any confirmation in writing of such verbal order given by the Executive Engineer, whether before or after the carrying out of order shall be deemed to be an order in writing within the meaning of 25 this clause, provided further that if the Contractor shall within seven days confirm in writing to the Executive Engineer and if such confirmation is not contradicted in writing within fourteen days by the Executive Engineer it shall be deemed to be an order in writing by the Executive Engineer. Clause 13 (a) ( iii )Any additional work which the contractor may be directed to do in the manner above specified as part of the work shall be carried out by the contractor on the same conditions in all the respects on which he agreed to do the main work. Clause 13 (b)The rates tendered and accepted shall hold good for any variations in quantity. Clause 13 (c) Rates for additional, substituted, altered items of work: If the additional, substituted or altered work includes any class of work for which no rate is specified in the Contract, then such work shall be carried out at the rates specified for or derived from similar item of work in the Agreement. In the absence of similar items in the agreement, the rate shall be as specified for or derived from similar items from Schedule of Rates prevalent at the time of execution of such additional, substituted or altered item of work, plus or minus the overall percentage of original tendered rates over the Schedule of Rates of the year in which the tender is accepted as mentioned in Sub-clause (b) above. With regard to the question whether the additional, substituted or altered item/items of work/works is/are similar or not, to that/those in the agreement in the Schedule of Rates of the Division, the decision of the Chief Engineer shall be final and binding on the Contractor. Clause 13 (d)Determination of rates for items not found in estimate or schedule of rates. If the rates for additional, substituted or altered work cannot be determined in the manner specified in Sub Clause 13(c) above, then the Contractor shall within 7 days of the date of receipt by him of the order to carry out the work, inform the Executive Engineer; of the rates which it is his intention to charge for such class of work, supported by analysis of the rate or rates claimed. Thereupon the Executive Engineer shall determine the rate or rates on the basis of observed data and failing this, on the basis of prevailing market rates. Under no circumstances the Contractor shall suspend the work on the plea of non-settlement of rates for items falling under this clause. In the event of any dispute regarding the rates for such items, the decision of the Chief Engineer shall be final. 5.14 TIME LIMITS FOR UNFORESEEN CLAIMS Clause 14 Under no circumstances whatever shall the Contractor be entitled to any compensation from the Corporation on any account unless the Contractor shall have submitted a claim in writing to the Executive Engineer or other competent authority within 30 days of the cause of such claim occurring. 5.15 NO CLAIM TO ANY PAYMENT OR COMPENSATION FOR DELETION OF WHOLE OR PART OF WORK Clause 15 (a) If at any time after the execution of the Contract, the Executive Engineer or other competent authority shall, for any reason whatsoever, require the whole or part of the work as specified in the tender to be stopped for any period or require the whole or part of the work (i) not to be carried out at all or (ii) not to be carried out by the Contractor, he shall give notice in writing of the fact to the Contractor who shall thereupon suspend or stop the work totally or partially as the case may be. In any such case, except as provided hereunder, the Contractor shall have no claim to any payment of compensation whatsoever on account of any profit or advantage which he might have derived from the execution of work in full but which he did not so derive in 26 consequence of the full amount of the work not having been carried out or on account of any loss that he may be put to on account of materials purchased or agreed to be purchased, or for unemployment of labour recruited by him. He shall not also have any claim for compensation by any reason of any alterations having been made in the original specifications, drawings, designs and instructions which may involve any curtailment of the work as originally contemplated. Clause 15 (b) PAYMENT FOR MATERIALS ALREADY PURCHASED OR ORDERED BY CONTRACTOR Where, however, materials have already been purchased or agreed to be purchased by the Contractor before receipt by him of the said notice, the Contractor shall be paid for such materials, at the rates determined by the Executive Engineer or other competent authority provided they are not in excess of requirements and are of approved quality, and/or shall be compensated for the loss, if any, he may be put to, in respect of materials agreed to be purchased by him, the amount of such compensation to be determined by the Executive Engineer whose decision shall be final. Clause 15 (c) LABOUR CHARGES DURING STOPPAGE OF WORK If the Contractor suffers any loss on account of his having to pay labour charges during the period during which the stoppage of works has been ordered under this clause, the Contractor shall, on application, be entitled to such compensation on account of labour charges as the Executive Engineer or other competent authority, whose decision shall be final, may consider reasonable, provided that the contractor shall not be entitled to any compensation on account of labour charges if in the opinion of the Executive Engineer or other competent authority, the labour could have been employed in the same locality by the Contractor for the whole or part of the period during which the stoppage of the work has been ordered as aforesaid. Clause 15 (d) TIME LIMIT FOR STOPPAGE OF WORK The period of stoppage ordered by the Executive Engineer or other competent authority should not ordinarily exceed 6 (Six) months. Thereafter, the portion of work stopped may be treated as deleted from this agreement if a notice in writing to that effect is given to the Executive Engineer or other competent authority by the Contractor within 7 (Seven) days after expiry of the above period. Execution of work deleted The portion of work thus deleted may be got executed from the same Contractor on supplemental agreement on mutually agreed rates which shall not exceed current schedule of rates plus or minus tender percentage. 5.16 ACTION AND PENALTY IN CASE OF BAD WORK Clause 16 If at any time before the CPG is refunded to the Contractor it shall appear to the Executive Engineer or other competent authority or his subordinate in charge of work, that any work has been executed with unsound, imperfect or unskilled workmanship or with materials of inferior quality, or that any materials or articles provided by him for the execution of the work are unsound, or of a quality inferior to that contracted for, or otherwise not in accordance with the contract, it shall be lawful for the Executive Engineer or other competent authority to intimate this fact in writing to the Contractor and then notwithstanding the fact that the work, materials or articles complained of may have been paid for, the Contractor shall be bound forthwith to rectify, or remove and reconstruct the work so specified in whole or in part as the case may require, or if, so required, shall remove the materials or articles at his own charge and cost; and in the event of his failing to do so within a period to be specified by the Executive Engineer or the competent authority in the 27 written intimation aforesaid, the Contractor shall be liable to pay a penalty not exceeding 1% (one percent) of the amount of the estimate for every day not exceeding ten days during which the failure, so continues, and in the case of any such failure the Executive Engineer or other competent authority may rectify or remove, and re-execute the work or remove and replace the materials or articles complained of as the case may be at the risk and expense in all respects of the Contractor. Should the Executive Engineer or other competent authority for any valid reason consider that any such inferior work or materials as described above is to be accepted or made use of, it shall be within his discretion to accept the same at such reduced rates as he may fix therefore. 5.17WORK TO BE OPEN TO INSPECTION - CONTRACTOR OR RESPONSIBLE AGENT TO BE PRESENT Clause 17 (a) All works under or in course of execution or executed in pursuance of the Contract shall at all times, be open to the inspection and supervision of the Executive Engineer or other competent authority and his subordinates, and the Contractor shall, at all times, during the normal working hours, and at all other times at which reasonable notice of the intention of the Executive Engineer or other competent authority or his subordinate to visit the work shall have been given to the Contractor, either himself be present to receive orders and instructions or have a responsible agent duly accredited in writing present for the purpose. Orders given to the Contractor's duly authorised agent shall be considered to have the same force and effect as if they had been given to the Contractor himself. EMPLOYMENT OF TECHNICAL STAFF Clause 17 (b)The Contractor shall employ the following minimum technical staff during execution of the work. i) One Graduate Engineer, when the cost of the work to be executed is `5.00 lakhs or more. ii) One qualified Diploma Engineer when the cost of the work to be executed is more than `2.00 lakhs but less than `5.00 lakhs. iii) In addition to (i) and (ii) above the Contractor shall employ different types of such technical personnel as may be directed by the Executive Engineer to ensure efficient execution of work. The technical staff so employed shall be available at site whenever required by Engineer in-charge to take instructions. Clause 17 (c) If the Contractor fails to employ the technical staff as aforesaid, he shall be liable to pay a sum of `10,000/- (Ten thousand only) each for each month of default in the case of Graduate Engineers and `5,000/- (Five thousand only) each for each month of default in case of Diploma Holders. Clause 17 (d) If the contractor himself possesses the required qualification and is available at the site for receiving instructions from the Executive Engineer or other competent authority vide sub-clause 17(a) above it will not be necessary for the technical staff to be available at the site for receiving instructions. 28 5.18 NOTICE TO BE GIVEN BEFORE WORK IS COVERED UP Clause 18 The Contractor shall give not less than five days notice in writing to the Executive Engineer or his subordinate in charge of the work before covering up of or otherwise placing beyond the reach of measurement of any work, in order that the same may be measured and correct dimensions thereof taken before the same is so covered up or placed beyond the reach of measurement, and shall not cover up or place beyond the reach of measurement, any work without the consent in writing of the Executive Engineer or other competent authority or his subordinate in charge of the work and if any work shall be covered up or placed beyond the reach of measurement without such notice having been given or consent obtained, the same shall be uncovered at the Contractor's expense, and if default thereof no payment or allowance shall be made for such work or for the materials with which the same was executed. 5.19 CONTRACTOR LIABLE FOR DAMAGES DONE AND FOR IMPERFECTIONS FOR TWELVE MONTHS AFTER CERTIFICATE OF COMPLETION Clause 19 If the Contractor or his workmen or his servants shall break, deface, injure or destroy any part of the structure in which they may be working, or any building, road, fence, enclosure or grass land or cultivated ground contiguous to the premises on which the work or any part thereof is being executed, or if any damage shall be done to the work, while it is in progress from any cause whatever or if any imperfections become apparent in it within twelve months of the grant of a certificate of completion, final or otherwise, by the Executive Engineer or other competent authority, the Contractor shall make good the same at his own expense, or in default, the Executive Engineer or other competent authority may cause the same to be made good by other workmen, and deduct the expenses (of which the certificate of the Executive Engineer or other competent authority shall be final) from any sums that may be due or may thereafter become due to the Contractor, or from his CPG or the proceeds of same thereof, or of a sufficient portion thereof. 5.20 CONTRACTOR TO SUPPLY PLANT, LADDERS, SCAFFOLDINGS, ETC., AND IS LIABLE FOR DAMAGES ARISING FROM NON-PROVISION OF LIGHTS, FENCING ETC. Clause 20 The Contractor shall supply at his own cost all materials, plant, tools, appliances, implements, ladders, cordage, tackle, scaffolding and temporary works requisite for the proper execution of the work, whether, in the original, altered or substituted form and whether included in the specifications, or other documents forming part of the Contract or referred to in these conditions or not, and which may be necessary for the purpose of satisfying or complying with the requirements of the Executive Engineer or other competent authority as to any matter as to which under these conditions he is entitled to be satisfied or which he is entitled to require together with carriage therefore, to and from the work. The Contractor shall also supply without charge requisite number of persons with the means and materials necessary for the purpose of setting out works, and counting, weighing and assisting in the measurement or examination at any time and from time to time of the work or the materials. Failing this, the same may be provided by the Executive Engineer or other competent authority at the expense of the Contractor and the expense may be deducted from any money due to the Contractor under the Contract or from his CPG or the proceeds of sale thereof, or of a sufficient portion thereof. The Contractor shall provide all necessary fencing and lights required to protect the public from accident, and shall also be bound to bear the 29 expense of defence of every suit, action or other legal proceedings, that may be brought by any person for injury sustained owing to neglect of the above precautions, and to pay any damages and costs which may be awarded in any suit, action or proceedings, to any person, or which may with the consent of the contractor be paid by the corporation for compromising any claim by any such person and deducted from any money due to contractor by the corporation under this contractor at any contract in corporation or from his CPG or the proceeds of sale thereof or a sufficient part thereof. 5.21 ISSUE OF THE PLANT AND MACHINERY ON HIRE: DELETED 5.22 MEASURES FOR PREVENTION OF FIRE Clause 22 The Contractor shall not set fire to any standing jungle, trees, bush, wood or grass without a written permit from the Executive Engineer. When such permit is given, and also in all cases when destroying cut or dug up trees, bushwood, grass etc., by fire, the Contractor shall take necessary measures to prevent such fire spreading to or otherwise damaging surrounding property. 5.23 LIABILITY OF CONTRACTOR FOR ANY DAMAGES DONE IN OR OUTSIDE WORK AREA Clause 23 Compensation for all damages done by Contractor or his men whether in or beyond the limits of Corporation property including any damage caused by spreading of fire mentioned in Clause-22 shall be estimated by the Executive Engineer and the estimate of the Executive Engineer, subject to the decision of the Chief Engineer on appeal shall be final and the Contractor shall be bound to pay the amount of the assessed compensation on demand failing which the same will be recovered from Contractor as damages in the manner prescribed in Clause-19 or deducted by the Executive Engineer or other competent authority from any sums that may be due or become due from Corporation to the Contractor under this Contract or otherwise. The contractor shall bear the expenses of defending any action or other legal proceedings that may be brought by any person for injury sustained by him owing to neglect of precautions to prevent the spread of fire and shall pay any damages and cost that may be awarded by the court in consequence. 5.24 Employment of Female labour: Clause 24 The employment of female labourers on works in the neighbourhood of soldiers, barracks should be avoided as for as possible. 5.25 WORK ON NOTIFIED HOLIDAYS Clause 25 No work shall be done on any notified holiday without the sanction in writing of the Executive Engineer or other competent authority. 5.26 WORK NOT TO BE SUBLET: Clause 26(a) (i) The Contract shall not be assigned or sublet by the Contractor. However, any specific portion of the work which is of a specialised nature and normally 30 not executable by general Contractor could be got done by a specialised agencies which are executing such works, after obtaining the specific approval of the Executive Engineer in writing in each case. Such consent to sublet the work, if given, shall not relieve the Contractor from any liability or obligation under the Contract and he shall be responsible for the acts, defaults and neglects of any Sub-Contractor or his agents, servants or workmen. Clause 26(a)(ii) CONSEQUENCE OF SUBLETTING WORK WITHOUT APPROVAL, BECOMING INSOLVENT, BRIBING ETC., BY CONTRACTOR & ACTION AGAINST THE CONTRACTOR. If the Contractor shall assign or sublet his Contract or any portion thereof without the specific approval of the Executive Engineer or attempts to do so or becomes insolvent or commences any proceedings to get himself adjudicated as insolvent or make any composition with his creditors or attempt to do so or if any bribe, gratuity, gift, loan, perquisite, reward or advantage, pecuniary or otherwise shall either directly or indirectly be given, promised or offered by the Contractor or any of his servants or agents to any officer or person in the employment of Corporation in any way relating to his contract or if any such officer or person shall become in any way directly or indirectly interested in the contract. the Executive Engineer or any other competent authority may thereupon, by notice, in writing rescind the Contract, and the Security Deposit of the Contractor shall thereupon stand forfeited and be absolutely at the disposal of the Corporation and the same consequences shall ensure as ifthe Contract had been rescinded under Clause3 thereofand in addition the Contractor shall not be entitled to recover or be paid for any work actually performed under Contract. Clause 26 (b) RECOVRY OF EXCESS PAYMENTS BASED ON EXCESS MEASUREMENTS AND ACTION AGAINST CONTRACTOR i) Whenever it is noticed that excess payments have been made to the contractor based on excess measurements recorded by the subordinate in the measurement book and countersigned by the contractor or his duly authorised agent, action shall be taken to recover the excess payments together with interest immediately. Action may also be taken to remove the name of the contractor from the approved list of the contractors and also to black list him. CHANGE IN CLASSIFICATION OF EXCAVATIONS ACCEPTED NOT PERMITTED ii) Once the measurements mentioned in the classification of the excavations are recorded in the measurement book and the same is signed by the Contractor or his authorised agent in token of acceptance, no request for reclassification by the Contractor shall be entertained. 5.27 SUM PAYABLE BY WAY OF COMPENSATION TO BE CONSIDERED AS REASONABLE COMPENSATION WITHOUT REFERENCE TO ACTUAL LOSS Clause 27 All sums payable by a Contractor by way of compensation under any of these conditions shall be considered as reasonable compensation to be applied for the use of Corporation without reference to the actual loss or damage sustained and whether any damage has or has not been sustained. 31 5.28 APPROVAL OF THE EXECUTIVE ENGINEER NECESSARY FOR CHANGING THE CONSTITUTION OF A FIRM BEFORE ENTERING INTO PARTNERSHIP AGREEMENT -CONSEQUENCES OF NOT OBTAINING PRIOR APPROVAL Clause 28 Where the Contractor is a partnership firm, the prior approval in writing of the Executive Engineer or other competent authority shall be obtained before any change is made in the Constitution of the Firm. Where the Contractor is an individual or a Hindu undivided family business/ concern, such approval as aforesaid shall likewise be obtained before the contractor enters into any partnership agreement where under the partnership firm, the firm would have the right to carry out the work hereby undertaken by the Contractor. If prior approval as aforesaid is not obtained the contract shall be deemed to have been assigned in contravention of Clause-26 hereof and the same action may be taken and the same consequences shall ensure as provided in the said Clause-26. 5.29 SETTLEMENT OF DISPUTES - TIME LIMIT FOR DECISION Clause 29 (a)If any dispute or difference of any kind whatsoever were to arise between the Executive Engineer / Chief Engineer and the Contractor regarding the following matters namely, i) The meaning of the specification, designs, drawings and instructions herein before mentioned. ii) The quality of workmanship or materials used in the work, and iii) Any other question, claim, right, matter, thing whatsoever, in any way arising out of or relating to the Contract, designs, drawings, specifications, estimates, instructions, or orders, or those conditions or failure to execute the same whether arising during the progress of the work, or after the completion, termination or abandonment, thereof, the dispute shall, in the first place be referred to the Chief Engineer who has jurisdiction over the work specified in the Contract. The Chief Engineer shall, within a period of 90 (ninety) days from the date of being requested by the Contractor to do so, give written notice of his decision to the Contractor. CHIEF ENGINEER’S DECISION FINAL Clause 29 (b)Subject to other form of settlement hereafter provided, the Chief Engineer’s decision in respect of every dispute or difference so referred shall be final and binding upon the Contractor. The said decision shall forthwith be given effect to and Contractor shall proceed with the execution of the work with all due diligence. REMEDY WHEN CHIEF ENGINEER’S DECISION IS NOT ACCEPTABLE TO CONTRACTOR Clause 29 (c)In case the decision of the Chief Engineer is not acceptable to the Contractor he may approach the Jurisdictional Law Court at Bangalore for settlement of the dispute after giving due written notice in this regard to the Chief Engineer within a period of 90 (ninety) days from the date of receipt of the written notice of the decision of the Chief Engineer. 32 TIME LIMIT FOR CONTRACTOR. NOTICE TO APPROACH LAW COURT BY Clause 29 (d)If the Chief Engineer has given written notice of his decision to the Contractor and no written notice to approach the law court has been communicated to him by the Contractor within a period of 90 (ninety) days from receipt of such notice, the said decision shall be final and binding upon the Contractor. TIME LIMIT FOR NOTICE TO APPROACH LAW COURT BY CONTRACTOR WHEN DECISION IS NOT GIVEN BY CHIEF ENGINEER AS AT (B). Clause 29 (e)If the Chief Engineer fails to give notice of his decision within a period of 90 (ninety) days from the receipt of the Contractor's request in writing for settlement of any dispute or difference as aforesaid, the Contractor may within 90 (ninety) days after the expiry of the first named period of 90 (ninety) days approach the Jurisdictional LawCourt at Bangalore giving due notice to the Chief Engineer. If the contractor fails to approach the law court within the stipulated period as above, he shall have no right to initiate any further legal proceedings. Clause 29 (f) CONTRACTOR TO EXECUTE AND COMPLETE THE WORK PENDING SETTLEMENT OF DISPUTE Whether the claim is referred to the Chief Engineer or to the law courts, as the case may be, the Contractor shall proceed to execute and complete the works with all due diligence pending settlement of the said dispute or differences. OBLIGATIONS OF THE EXECUTIVE CONTRACTOR SHALL REMAIN CONSIDERATION OF DISPUTE. ENGINEER AND THE UNSETTLED, DURING Clause 29 (g)The reference of any dispute or difference to the Chief Engineer or the law court may proceed notwithstanding that the works shall then be or be alleged to be complete, provided always that the obligations of the Executive Engineer and the Contractor shall not be altered by reason of the said dispute or difference being referred to the Chief Engineer or the Law court during the progress of the works. 5.30 CONTRACTOR TO COMPENSATION ACT PAY COMPENSATION UNDER WORKMEN'S Clause 30 (a) The Contractor shall be responsible for and shall pay any compensation to his own workmen payable under the Workmen's Compensation Act 1923 as amended from time to time (VIII of 1923 hereinafter called the said Act) for injuries caused to the workmen. If such compensation is paid by Corporation as a principal employer under sub-section (1) of section 12 of the said Act on behalf of the Contractor, it shall be recoverable by Corporation from the Contractor under sub section (2) of the said section. Such compensation shall be recovered in the manner laid down in Clause-1 above. CONTRACTOR TO PAY EXPENSES OF PROVIDING MEDICAL AID TO WORKMEN 33 Clause 30 (b) The Contractor shall be responsible for and shall pay the expenses of providing medical aid to any workmen who may suffer a body injury as a result of an accident. If such expenses are incurred by the Corporation, the same shall be recoverable from the Contractor forthwith and be deducted without prejudice to any other remedy of corporation from any amount due or that may become due to the Contractor. 5.31 CONTRACTOR TO PROVIDE PERSONAL SAFETY EQUIPMENT, FIRST AID APPARATUS, TREATMENT ETC., Clause 31 The Contractor shall provide all necessary personal safety equipment and first aid apparatus for the use of the persons employed on the site, and shall maintain the same in good condition suitable for immediate use, at any time and shall comply with the following regulations in connection therewith. i) The workers shall be required to use the equipment so provided by the Contractor and the Contractor shall take adequate steps to ensure proper use of the equipment by those concerned. ii) When work is carried on, in proximity to any place where there is a risk of drowning, all necessary steps shall be taken for the prompt rescue of any person in danger. iii) Adequate provision shall be made for prompt first-aid treatment of all injuries likely to be sustained during the course of the work. 5.32 MINIMUM AGE OF PERSONS EMPLOYED BY CONTRACTOR Clause 32 (a)The Contractor shall not employ i) any person who is under age of 15 years ii) Who does not produce a valid certificate of vaccination against small pox in respect of himself/herself as well as all the members of his/her family. Clause 32 (b) Deleted. Clause 32 (c) Deleted. Clause 32 (d) The contractor shall provide potable water facilities to the workers. Clause 32 (e) REMOVAL OF PERSON NOT SATISFYING CONDITIONS: The engineer may direct the removal or to remove through his own agency, from the work any person referred to in sub- clause 32(a) above not satisfying these conditions and no responsibility shall be accepted by the corporation for any delay caused in the completion of the work by such directions for removal. Clause 32 (f) PAYMENT OF FAIR AND REASONABLE WAGES BY CONTRACTOR: Contractor shall pay fair and reasonable wages, which shall not be less than the minimum wages fixed by Government from time to time to the workmen employed by him in the contract undertaking by him. In the event of any dispute arising between the contractor and his workmen on the ground that the wages paid are not fair and reasonable, the dispute shall be referred without delay to the Engineer, who shall decide the same. The decisions shall not in any way affect the conditions in the contract regarding payment to be made by corporation at the agreed Bid rates. 34 5.33 EMPLOYMENT OF SCARCITY LABOUR ETC., Clause 33 (a) If Government declares a state of scarcity or famine to exist in any village situated within 16 kilometres of the work, the Contractor shall employ upon such parts of the work as are suitable for unskilled labour, any person, certified to him by the Executive Engineer or by any person to whom the Executive Engineer may have delegated this duty in writing to be in need of relief and shall be bound to pay to such persons wages not below the minimum which Government may have fixed in this behalf. Any dispute which may arise in connection with the implementation of this clause shall be decided by the Executive Engineer or other competent authority whose decision shall be final and binding on the Contractor. Clause 33 (b) The Contractor shall employ any famine, or other labour of a particular kind or class, if ordered in writing to do so by the Executive Engineer or other competent authority. 5.34 CONTRACTOR NOT ENTITLED TO ANY CLAIM OR COMPENSATION FOR DELAY IN EXECUTION OF WORK - BORROW PITS Clause 34 The Contractor shall not be entitled to claim compensation if there is any delay in the execution of the work on any accountand no claim for extra rate shall be entertained, unless otherwise exclusively specified. 5.35 METHOD OF PAYMENT Clause 35 Payment to Contractor will be made by cheques drawn on any bank with which the Corporation has an account. 5.36 SET OFF AGAINST ANY CLAIM OF CORPORATION Clause 36 Any sum of money due and payable to the Contractor (including the Security Deposit returnable to him) under this Contract may be appropriated by the Corporation and set off against any claim of Corporation in respect of payment of a sum of money arising out of or under any other Contract made by the Contractor with the Corporation. 5.37 RATES INCLUSIVE OF TAXES Clause 37 The rates quoted by the tenderer shall be inclusive of Income Tax, VAT, (Sale Tax), Service Tax, Quarry fees, octroi, duties, royalties, freight charges, ground rent etc., (prevailing as on 30 days prior to the date of opening of the Bid. No extra payment on this account shall be made to the Contractor taxes duties etc, subsequently enforced / Collectable at the future date shall be paid to the Contractor. Any increase in taxes, duties etc., from those prevalent as on 30 days prior to opening of the Bid will be borne by the Corporation and any decrease will be recovered from the Contractor). 5.38 CONTRACTOR TO OBTAIN LABOUR ETC., FROM NEAREST EMPLOYMENT EXCHANGE 35 Clause 38 The Contractor should as far as possible obtain his requirement of labour, skilled and unskilled from the nearest Employment Exchange. The Contractor should give preference to the employment of a released bonded labour on the work entrusted to him. 5.39 DUES TO BE RECOVERED AS IF THEY WERE ARREARS OF LAND REVENUE Clause 39 All money due from Contractor under this Contract may be recovered by Corporation/Government with or without prejudice to the other remedies, as if they were arrears of Land Revenue. 5.40 CONTRACTOR TO COMPLY WITH THE PROVISIONS OF APPRENTICE ACT Clause 40 The Contractor shall comply with the provisions of the Apprentice Act 1961 and Rules and Orders issued there under from time to time. If he fails to do so, his failure will be a breach of Contract and the Superintending Engineer or other competent authority may his discretion cancel the Contract. The Contractor shall also be liable for any pecuniary liability arising on account of any violation by him of the provisions of the Act. 5.41 CONTRACTOR TO SUBSCRIBE TO WORKERS AND CONTRACTORS BENEVOLENT FUND Clause 41 Deleted 5.42 LUMPSUMS IN TENDER- PAYMENT TO CONTRACTOR Clause 42 When the Contract includes lump sums in respect of any items of the work, the Contractor shall not be entitled to payment in respect of the items of the work involved or the part of the work in question at the same rates as are payable under this Contract for each item or if the part of the work in question is not, in the opinion of the Executive Engineer or other competent authority capable of measurement, the Executive Engineer or other competent authority may at his discretion pay the lump sum amount entered in the tender contract and the certificate in writing of the Executive Engineer or other competent authority shall be final and conclusive against the Contractor with regard to any sum or sums payable to him under the provisions of this clause. It will be necessary for the Contractor to produce a statement of expenditure incurred by him for such items of work and the amount payable should be limited to the provisions made in the tender and the Executive Engineer in charge should satisfy himself about the correctness of the statement of expenditure furnished by the Contractor. 5.43 CONTRACTORS NOT TO QUOTE THE PRICE EXCEEDING CONTROLLED PRICE FIXED BY GOVERNMENT Clause 43 5.44 Deleted. CHANGE IN COST – PRICE ADJUSTMENT Clause 44 Deleted. 36 5.45FORCE MAJEURE Clause 45 If at any time during the continuance of the work the performance in whole or in part by either party of any obligation under this Contract, shall be prevented or delayed by reasons of any war, hostility, acts of public enemy, civil commotion, sabotage, fires, explosions, epidemic, quarantine restrictions or other acts of GOD, strike and lock out (hereinafter referred to as eventualities) then, provided notice of the happening of any such eventuality given by either party to the other within 15 (fifteen) days from the date of occurrence thereof, neither party shall, by reason of such eventualities be entitled to terminate this Contract nor shall either party have any claim for damages against the others in respect of such non-performance or delay in performance, and construction work under this Contract shall be resumed as soon as practicable after such eventualities has come to an end or cease to exist. (Any damages cause to the construction work on account of the mentioned eventualities shall be to the Corporation account). Should one or both parties be prevented from fulfilling their contractual obligations by a state of force-majeure lasting continuously for a period of Three months, both the parties should consult each other regarding the further implementation of the Contract, provided always that, if no mutually agreed arrangement is arrived at within a period of 30 days from the expiry of Three months referred to above, the Contract shall be deemed to have expired at the end of the said Three months referred to above. The above mentioned expiry of Contract will imply that both the parties have the obligation to reach an agreement regarding the winding up and financial settlement of the Contract. In case of force majeure events of duration less than 90 Days, suitable extension of the contract period will be considered without any compensation. 5.46 INSURANCE CLAUSE – 46 The Contractor shall take the following insurance covers for the works to be executed at site WORKMEN’S COMPENSATION Insurance: This insurance shall protect the contractor against all claims applicable under the Workman’s compensation Act 1948 (Government of India ). This policy shall also cover the contractor against claims for injury, disability, diseases or death of his or his sub-contractor’s employees, which for any reason are not covered under the Workmen’s Compensation Act 1948. The liabilities shall not be less than: Workmen’s compensation Employee’s Liability As per statutory provisions As per statutory provisions Comprehensive Automobile Insurance: This insurance shall be in such a form to protect the contractor against all claims for injuries, disability, disease or death to members of public including the Corporation’s men and damage to the property of others arising from the use of motor vehicles during on or off site round the clock operations by taking “Third party unlimited liability risk coverage irrespective of the ownership of such vehicles. Comprehensive General Liability Insurance: This insurance shall protect the contractor against all claims arising from injuries, disability, disease or death of members or damage to the property of others due to any act or omission on the part of the contractor, his agents, his employees, his representatives and sub-contractors or from riots, strikes and civil commotion. This insurance shall also cover all the liabilities of the contract. 5.47 SUPPLY OF FIRE WOOD TO LABOURERS: CLAUSE – 47 D E L E T E D 37 SECTION -6 GENERAL CONDITIONS GENERAL CONDITIONS RELATING TO THE EXECUTION OF WORKS 6.01 GENERAL The rates quoted in the tender are to be on the basis that the Contractor himself will procure all machinery and equipment required for the successful execution and completion of the work within the specified time. The responsibility of procuring any items of equipment required for the work will entirely be of the Contractor and no further assistance in the matter of securing foreign exchange etc., can be offered. The Corporation will not provide any foreign exchange for procurement of any equipment. 6.02 ADVANCE TO CONTRACTORS - DELETED 6.03 ACCURACY OF LINES, LEVELS AND GRADES All levels shown on the drawing are based on the benchmarks at the site of work. All levels, drawings, surveys, reference marks shall be based on the standard benchmarks unless otherwise directed by the Engineer-In-Charge in writing. The work shall be carried out true to line, level and grade as specified in approved drawings and specifications or established or indicated by the Engineer-In-Charge. Permanent base lines and cross lines shall be established at sufficiently close intervals with bench marks at all corner points to serve as reference grid. The Contractor shall provide at his expense all templates, pillars, stakes, equipment, materials, labour for establishing the grid lines and pillars and shall be responsible for their maintenance during the whole period of construction. These shall be laid out with prior approval and checked by the Engineer-in-charge. No base lines or benchmarks or reference marks shall be used as reference lines, benchmark or level for the work without the prior approval of the Engineer-In-Charge. The Contractor shall maintain a certified copy of such approved reference lines benchmarks levels and shall not remove any one of them without prior approval of the Engineer-in-charge. The Contractor shall layout the work from reference, base lines and shall be responsible for the correctness of all the measurements and levels in connection there with not withstanding the fact that the same might have been checked by the Corporation staff. Any discrepancy or error detected during the course of execution land/or at the lend of work shall be set right by the Contractor at his own cost in a manner satisfactory to the Engineer-In-Charge. In case of errors, omissions and / or disagreement between written and scaled dimensions on the drawing or between the drawing & specifications, the Contractor shall make a reference to the Executive Engineer, whose elucidation or decision shall be considered authentic and final. The Contractor shall be held fully responsible for any errors or omissions or disagreements, if he fails to refers them to the Executive Engineer and get an elucidation before starting the work or the specific part of the work. 6.04 CO-ORDINATION OF SURVEYS AND SETTING OUT: The Contractor shall conduct surveys under the supervision of the Corporation Engineers and fix up an alignment. The Contractor has to co-ordinate his work with other Contractors under the supervision of the Engineer-in-charge. In case of any deviation or discrepancy in line, level or grade at the meeting faces, the Contractor shall make good the discrepancy at his own cost and without any extra compensation for any additional work involved. Wherever such a discrepancy is found to arise at the junction of work or Contractors, the relative liability to set right their respective 38 discrepancies shall be fixed by the Engineer-In-Charge whose decision shall be final and binding on the Contractor concerned. The Engineer-In-Charges shall, further have the unquestioned right if need be, to rectify the discrepancies and recover the cost from the Contractor or Contractors according to proportion as he may consider reasonable. 6.05 CONSTRUCTION SCHEDULE: The contractor shall adhere to the construction schedule so as to complete the work in all respects in the stipulated period. The Contractor shall also furnish his approach to the work along with the programme indicating briefly his method of working, his plans in tackling the construction programme vis-à-vis the capacity of equipment he proposes to deploy on the various components. the various components of the work. 6.06 WORK TO BE CARRIED OUT ACCORDING TO PLANS: The work shall be carried out strictly in accordance with the approved designs, drawings, and specifications and as per instructions of the Engineer-In-Charge and no deviations or changes are permissible without the written order of the Engineer-In-Charge(not below the rank of the Executive Engineer). 6.07 SAFETY MEASURES : The Contractors shall take all necessary precautions for the safety of workers and preserving their health while working on such jobs as required special protection and precaution. The following are some of the measures listed, but the same are not exhaustive and the Contractor shall augment these precautions, on his own initiative where necessary and shall comply with the direction issued by the Engineer-In-Charge in this behalf from time to time and at all times. a) Providing protective footwear to workers in situation like mixing and placing of mortar or concrete, in quarries, in tunnels and places where the work is done under too much wet conditions. b) Providing protective headwear to workers like underground excavation to protect them against rock falls. c) Providing masks to workers employed on granulators or at other locations where too much of fine dust is floating about the sprinkling water at frequent intervals by water hoses on all stone crushing areas and storage bins to abate dust. d) Getting the workers on such Job periodically for chest trouble due to too much breathing – in fine dust. e) Taking such normal precautions like, not allowing nails and metal parts or useless timber spread around, marking danger areas for blasting, ensuring blasting whistles etc., f) Supporting workmen with proper belts, ropes, etc., when working in shafts, precipitous slope etc., g) Avoiding naked wires etc., which would electrocute the workers, h) Providing good ventilation and lighting. 39 SECTION – 7.00 GENERAL SPECIFICATIONS 7.01 GENERAL All specifications shall conform to the relevant Indian Standard Specifications unless otherwise specified. For works not covered by the IS specifications and/or the portions thereof and if no mention be made therein, the written instructions of the Engineer-in-Charge shall be binding on the Contractor. The work shall be carried out strictly in accordance with the approved plans and designs and specifications and as per the instructions of the Engineer-in-Charge and no deviations or changes are permitted without the written order of the Engineer-in-Charge. The Contractor shall provide at site a work order book. The pages in the work order book shall be machines numbered. The Contractor shall be responsible for obtaining all the orders entered in the order book and he or his authorized agent shall sign the orders issued by the Engineer-inCharge and shall carry out strictly in accordance with these instructions. 7.02 CONTRACTOR’S REPRESENTATIVE AND LABOUR The address of his office shall be given by the Contractor for sending communications, failing which all communications will be sent to the Contractor’s address given at the time of submission of tender and the Corporation shall not be responsible for any delay in receiving them. The Contractor or his duly authorized agent shall be present at the time of setting out, giving profiles, etc., and shall supply the materials such as bamboos, pegs, reference stones etc., and also sufficient number of mazdoors required for taking measurements of work giving line out etc., at his own cost to the Corporation. Chainage stones at every 30 m or as specified by the Engineer-in-Charge shall be fixed or constructed by the Contractor with masonry at his cost to facilitate ready reference. Before starting the excavation, the Contractor or his authorized agent shall be present while taking levels of the ground at the work site. He will further be required to sign the field book and also L-section and cross sections based on the ground levels taken in token of acceptance the work without verifying and accepting the cross section and L-section of the ground it will be assumed that he has accepted the same taken by the Corporation staff and no complaint or claims whatsoever in this behalf will be entertained. The Contractor shall submit daily reports for the following : The working area will be defined by the Engineer-in-Charge from time to time. The Contractor shall not employ on the site any person who is undesirable. If in the opinion of the Engineer-inCharge, any person at the site of work, on behalf of the Contractor is considered un-desirable, the Engineer-in-Charge shall give in writing and the Contractor will be bound by the decision of Engineer-in-Charge to remove such person or persons from the site of work. The Contractor shall not be entitled to any compensation due to damage or loss on this account. 7.03 CLEARANCE OF SITE The Contractor shall have to clean the site of work before the work is commenced and after completion. The rates quoted shall be inclusive of all charges likely to be incurred in carrying 40 out the work of site clearance, initial and final cleaning and shall also hold good under all condition of weather. All gold, oil other minerals of any description whatsoever and all precious stones, treasures, relics, antiques and other similar things that may lie or be discovered on the site shall remain the property of Government and the Contractor shall duly intimate the Engineer-in-Charge or any person duly authorized by his to receive such property. After completion of the work entrusted to the Contractor and before handing over the completed work to the Engineer-in-Charge, the Contractor shall remove all unused and waste material, remove temporary structures, ramps, platforms etc., laying the vicinity of completed work and dispose off as directed by the Engineer-in-Charge. Further, temporary structures for storing water etc., labour sheds or any other sheds put up the Contractor for facility of his work, shall be demolished completely and waste materials disposed. The work site and other areas, which were in his possession in connection with the execution of work, should not present any unsightly or ugly appearance. The completed work will not be taken over by the Engineer-inCharge, unless the final clearance of the site is done as mentioned above. 7.04 DRAWING AND PUMPING All water from the excavation below ground level or from natural surface flows shall be satisfactory pumped out or drained away by the Contractor as directed by the Engineer-inCharge. The water so bailed out shall be disposed off in a manner as not to obstruct other works in the adjoining areas. 7.05 COMMUNICATION LINES AND NATURAL WATER COURSES The Contractor shall not close any communication lines without the permission of the Engineerin-Charge. The Contractor shall also no obstruct any natural lines of drainage without the approval of the Engineer-in-Charge. 7.06 AMENITIES TO LABOURERS The Contractor shall provide adequate supply of pure and wholesome water for the use of labourers. 7.07 SAFETY ENGINEERING Accident prevention shall be an essential part of the Programme of the Contractor for the execution of the work in order to reduce the cost of construction measured in terms of a) Human life sacrificed b) Loss of materials resulting from accidents c) Temporary and permanent injuries to workers d) Loss or damage to equipment e) The cost of workmen’s compensation insurance f) Loss of time due to accidents The safety programme should be developed to cope with the particular hazards for each operation (Blasting, tunneling, drilling, excavation etc.) 41 7.08 SAFETY CODE: The Safety code detailed herein below may be advantageously followed. Scaffolding and Ladders Suitable scaffolding should be provided for workmen for all works that cannot safely be done from the ground, or from solid construction except such short period work as can be done safely from ladders. When a ladder is used, suitable footholds and handholds shall be provided on the ladder and the ladder shall be given an inclination not steeper than 3/4 to 1 (3/4 horizontal and 1 vertical) and an extra mazdoor shall be engaged to hold ladder in position. Platform, Gangways and Stairways: Working platform, gangways and stairways should be so constructed that they should not sag unduly or unequally and if the height of the platform or the gangway or the stairway is more than 3.5 m above ground level or floor level they should be closely boarded, should have adequate width and should be suitable fastened. Safe Access to Working Places: Safe means of access shall be provided to all working platforms and other working places. Every ladder shall be securely fixed. No portable single ladder shall be over 9 m in length while the width between side rails in rung ladder shall be in no case be less than 30 cm for ladder up to and including 3.5 m in length. For longer ladders this width should be increased at least 6 cm for each additional meter of length. Uniform step spacing shall not exceed 30 cm. Adequate precautions shall be taken to prevent danger from electrical equipment. No materials on any other site of work shall be so stacked or placed as to cause danger or inconvenience to any person or the public. The Contractor shall also provide all necessary fencing and lights, to protect the public from accident and shall be vound to bear the expenses of defense of every suit, action or other proceedings at law that may be brought by any person for injury sustained owing to neglect of the above precautions and to pay any damages and cost which may be awarded in any such suit, action or proceedings to any such persons or which may with the consent of Contractor be paid by Corporation to comprise any claim by any such person and recover the same from Contractor. 7.09 SAFETY EQUIPMENT All necessary personal safety equipment as considered adequate by the Engineer-in-Charge should be kept available for the use of the persons employed on the site and maintained in a condition suitable for immediate use and the Contractor should take adequate steps to ensure proper use of equipment by the concerned. 7.10 DISPLAY OF SAFETY PROVISIONS: The safety provisions should be brought to the notice of all concerned by displaying on a notice board at a prominent place at the work spot. The Contractor shall name the persons responsible for compliance of the safety code. 42 SECTION -8 NOTE TO SCHEDULE – B(Pricebid) 1. Description of items given in Schedule – B / Price bid shall be read along with tender notification, general conditions of contract, general conditions relating to works, detailed technical specifications, drawings and all other component parts of the Tender document. 2. The quantities furnished in Schedule – B / Price bid are approximate, Contractor shall quote firm unit rates. In case of quantities varying or deleted from those furnished in the Schedule ‘B’, Clause – 13 of Conditions of Contract will prevail. 3. The rates quoted in the Schedule – B / Price bid shall be for finished items of works. 4. The quoted rates shall include cost and conveyance of all materials constructional plant, labour, supervision, fuel, lubricants, electricity, dewatering, desilting, drainage, approaches, lighting, providing and maintaining communication facilities, all leads and lift etc., No extra payment for these items shall be made on any account. 5. All items shall be executed as per approved designs and pattern and shall comply with the specifications and general conditions enclosed with the Tender documents and orders conveyed by competent authority from time to time during the course of execution. 6. Rates quoted shall include clearance of site both prior to commencement of work and after its completion. 7. Contractor shall quote his rate for all items in Schedule – B / Price bid. The Corporation reserves the right to operate any item included in Schedule ’B’ at its discretion. Contractor shall have no claim whatsoever on grounds of loss anticipated profit, etc., on account of the same. 8. Rates quoted by the Contractor shall be firm and valid till completion of work even if the Contract is split or if some items are deleted. 9. The unit rate quoted shall include minor details of construction, which are obviously and fairly intended and which may not have been referred to in these documents but are essential for satisfactory completion of the work. 10. The rates quoted shall hold good for works below or above ground level, irrespective of elevations unless separate rates are called for at different elevation. 11. The Contractor shall make his own arrangements for providing all necessary plant, materials, machinery and equipment required for the work. The Contractor at his own cost shall arrange the water supply for works. The work shall be completed as per the approved construction Schedule. 12. The rates quoted by the Contractor shall remain unaltered for use of any type of cement such as puzzolana, ordinary Portland, suplhate – resisting etc., directed to be used by the Engineer-in-Charge. 43 13. The lead for sand and rubble is indicated in the lead statement / quarry map. The contractor should obtain all necessary permits from the Forest Department or Mines and Geology Department for extracting materials from the quarries. The rate quoted by the Contractor for the item of work involving usage of coarse and fine aggregate, rubble etc., will remain unaltered irrespective of the quarries used by the Contractor. The Contractor shall ensure a continuous supply of aggregates conforming to the specifications. Royalty charges are included in the estimated rates. The Contractor shall include the prevailing Royalty charges in the rates quoted by him irrespective of whether he brings the materials from: a) b) c) d) KPCL owned quarries. Quarries leased to KPCL by Government, or The quarry owned by the Contractor Other sources including the dump yard and it is the responsibility of the contractor to pay the royalty charges to Government. The Contractor has to produce proof for having paid royalty to Government for that particular work. If the proof is not produced by the Contractor, the royalty charges at the prevailing rates shall be deducted from his bills and remitted to the Government by KPCL. 14. The Contractor should make his own arrangements for the Power required for the work in consultation and permission of Karnataka Power Transmission Corporation Limited. 15. Abbreviations used for the unit of various items are as stated below: Abbreviation Unit Tonnes (1000 Kg) Kilogram Metre Centimetre Milimetre Abbreviation Unit Nos Numbers mt dia deg MS Square metre RCC cum Cubic metre CI di Ductile Iron GRP Running metre Diameter Degree Mild Steel Reinforced Cement Concrete Cast Iron Glass fiber Reinforced Plastic MT kg m cm mm sqm 44 SECTION- 9 ROYALTY CHRAGES 45 46 SECTION - 10 SERVICE TAX DECLARATION BY THE AGENCY EXCUTING NEW WORKS CONTRACTS AWARDED ON OR AFTER 1.7.2012 Tender No: KPCL/SVP/CSE(M)/2016-17/ETND-41 Date:11.11.2016 Name of work:- Providing Galvalium sheets to vehicle parking shed and service station at garage complex, SVP colony, Jog TO: The Executive Engineer(Civil Maintenance)KPC Ltd., Jogfalls-577435 FROM: Sri.________________________________ ________________________________ ________________________________ 1) We are constituted a: a. Proprietary concern. b. Hindu Undivided Family c Partnership firm d. Private/Public Limited Company. e) Co-operative Society/Society. 2) The prices quoted are inclusive of service tax payable by us. The obligation to pay The said tax lies with us. OR The service provided or to be provided by us are not liable to service tax (Give reasons for non-taxability. Separate sheet may be added.) 3) We are not liable to pay service tax as the total value of taxable service for the year 2014-15 is not expected to exceed `10 Lakhs. OR We are registered as a Service Tax Assessee. Our service Tax registration Number is _________________ 4. We are paying service tax under one of the following schemes: a. Paying service tax on the gross amount of the contract after deducting the actual value of goods transferred in execution of works contract, and the VAT/CST payable thereon. b. Paying service tax on 40% of the total value charged on execution of “original works” c. For maintenance, repair, restoration, recondition etc., of goods, we are paying service tax on 70% of the total value charged for the works contract. d. For maintenance and repair not covered by 4 (c) above and finishing services such as glazing, plastering, floor and wall tilling, installation of electrical fittings of an immovable property, we are paying service tax on 60% of the total value charged for the works contract. 5. We declare that the foregoing details disclosed by us and options chosen by us are true and correct. Place: Date: Signature____________________________ Name of signatory____________________ Name of the contractor firm _____________ Note: Strike out whichever provision is inapplicable to you 47 Original works means(a) all new construction,(b) all types of additions and alternation to abandoned or damaged structures and land that are required to make them workable,(c) erection, commissioning or installation of plant, machinery, or equipment or structures. 48
© Copyright 2026 Paperzz