UK Link Technology Refresh Annie Griffith January 2008 Progress Since Last Update OAT Final few tests in OAT Phase 2 now underway – 96% complete No outstanding defects UAT 97% complete Final few tests in progress 3rd Full scale trial migration completed Independent review by IBM has verified quality, appropriateness and completeness of testing and data migration validation Dress Rehearsal commenced Cut-over and Implementation Outage still planned at 4 days All Go/No-go points defined Back-out points and processes defined Error scenarios worked through and recovery actions understood MOD proposal 184 drafted to include: 2 partial non-business days for SPA processing and queries (25th & 26th Feb) 4 days relief from data logger liabilities (24th-27th Feb) Cutover Weekend Back-out Points Go-No/Go Point G5 Sat 23rd Feb 11:00 Data loggers Complete G6 Sun 24th Feb 11:00 Migrations Completed Back-out Action Needed Re-start production services. Restart Batch schedule Recovery Time to BAU 1-2 hours 13:00 Sat 23rd Reverse file transfer configuration changes Reverse file system re-routing changes and application re-pointing Restart production service and commence batch catch-up 12 hours +1 days catch-up 23:00 25th Feb G7 Mon 25th Feb 11:00 Data Rec. Completed Reverse file transfer configuration changes Reverse file system re-routing changes and application re-pointing Restart production service and commence batch catch-up 12 hours + 2 days catch-up 23:00 27th Feb G8 Mon 25th Feb 17:00 On Line Verification complete Reverse file transfer configuration changes Reverse file system re-routing changes and application re-pointing Restart production service and commence batch catch-up 12 hours +2.5 days catch-up 20:00 28th Feb G9 Mon 26th Feb 09:00 Transfer Routes and data validated Reverse file transfer configuration changes Reverse file system re-routing changes and application re-pointing Restart production service and commence batch catch-up 12 hours + 3 days catch-up 10:00 29th Feb Implementation Communications Specific updates around the implementation will be emailed to the standard distribution lists UKLC Operational Shipper Contacts Will use the existing xoserve Customer teams for communications Will be using the xoserve web site for general updates Example Failure Scenarios Scenario Likely Action (will always be dependant on nature of fault/failure) Unable to produce Invoices Can delay Capacity Invoice to 13th March If delay over 7 days UNC allows for issue of estimated invoice xoserve is unable to send out files to Shippers If fault is at new UK Link Data Centres would FTP files to IX at existing data centres No changes are being made to IX so believe failure is unlikely, however, if necessary options exist for issue of paper invoices, emailing files or transfer to alternative media and courier xoserve is unable to receive files from shippers If fault is between IX and new UK Link Data Centres would FTP files No changes are being made to IX so all Shipper files should still be received in IX as now. A shipper receives the incorrect file Will alert other party upon notification, suspend Shipper file issue until exact nature of fault verified. Will back-out. Would expect Shipper system validation to reject and not process. If experienced, likely to be du to a configuration error which can be easily rectified. The data within a file is found to be incorrect or corrupt Action dependent on nature of error May require Network Code Contingency to be invoked to prevent any further data corruption or propagation of corrupt data Will attempt to fix and then catch-up Next Steps Completion of OAT Phase 2 Progress UAT to completion Conclude Dress Rehearsal Prepare & issue pre-implementation Shipper comms Early Interface Implementation Finalise Implementation Planning Addendum Supplementary Information presented previously Major Milestones Date Milestone 14/01/08 Interface Routing Implemented 21/01/08 UAT Completed 21/01/08 OAT Completed 27/01/08 Dress Rehearsal Completed Feb Mod Approved 01/02/08 Bulk Data Migration Started 21/02/08 Readiness Verified 23/02/08 Start Outage 25/02/08 Start Catch Up 28/02/08 Complete Catch Up 30/05/08 End of Post Implementation Support Go/No-Go Decision Points ID Date Input Output G1 11th Jan Interface Plans Agreed Move to early interface implementation G2 22nd Jan UAT and OAT Completed Initiate Bulk Data Migration G3 01ST Feb Dress Rehearsal completed, All plans in place Start pre-cutover activities G4 21st Feb All approvals in place Approval to start G5 23rd Feb Data loggers Complete Start Outage G6 24th Feb 11:00 Migrations Completed Desk top rollout and reconciliation checks G7 25th Feb 11:00 Data Rec. Completed Release to internal users for screen verification G8 25th Feb 17:00 On Line Verification complete Start batch catch up G9 26th Feb 09:00 Transfer Routes and data validated Release to internal other systems G10 26th Feb 10:00 Files generated and verified Release to Shippers G11 26th Feb 12:00 Batch catch-up progress OK Enable peripheral applications System Impacts System Saturday 23rd Feb Sunday 24th Feb Monday 25th Feb Tuesday 26th Feb Wed’s 27th Feb Conquest Outage Outage Returns PM and will reflect UK Link As UK Link As UK Link IAD Will have data as 22nd Will have data as 23rd Will have data as 23rd Will have data as 23rd Will have data as 24th , 25th SP Transfer No Run No Run No Run Run 24th and 25th Run 26th and 27th Data Loggers 23rd Run No Run No Run Run 24th and 25th Run 26th and 27th DN Link Outage Outage As UK Link As UK Link As UK Link
© Copyright 2026 Paperzz