HYDROCARE Activities of PP1

HYDROCARE
Activities of PP1 -CINFAI
Valerio Lucarini, PhD
[email protected]
Overview (from AF)
Institution
PP 1
LP
National
Consortium
of
Universities for the Physics
of the Atmospheres and of
the Hydrospheres
EU
Member
State
Country
(Y/N)
(Code)
Y
IT
Total financial
contribution
478.100,00
PP1/LP is responsible for 5 actions (1.1, 1.2, 2.4, 2.5, 5.1)
and for 2 WPs (WP1 and WP5), participates also to WP2
Main Objectives



Coordination and management of the
technical/administrative goals of the project
(payment claims, reporting, assemblies of
partners). (WP1)
Reconstruction of the hydrological cycle in the
CADSES area by renalyses, local models, global
models. (WP2)
Dissemination by publications and conferences
of the technical/administrative goals attained,
and related training (WP5).
Work Package 1 – Action 1.1
Month of
start
(mm/yy)
Month
of
end
(mm/yy)
01/2006
12/2007 Continuous
coordination
ad Notes and reports
management of the project
to/from partners
performed by the Lead
and European
Partner: check of the technical
bodies.
status of the project, contacts
with the European bodies
(especially JTS) and with the
PP
representatives.
Organization of the meetings
of the Assembly of Partners
and
of
the
Managing
Committee.
People:
Description of activities,
components, means
Expected output /
deliverables
Costs
(in €)
64.700,00
Valerio Lucarini (TD), Veronica Benedettelli (ATD)+
Carmelo Grasso, Donato Di Camillo, Janka Strakova (Staff)
Work Package 1 – Action 1.2
Month of
start
(mm/yy)
Month
of
end
(mm/yy)
01/2006
12/2007 Organization and management Transmission of the
of
the
administrative
invoices and proofs
aspects of the project:
of expenditures to
basic
administrative
the
Managing
duties, definition of the
Authority.
terms of joint convention,
Redistribution
of
check of the financial
the
ERDF
status of the project,
contributions to the
financial
flux
partners.
management,
contacts
with the Managing and
Payment Authorities.
People:
Description of activities,
components, means
Expected output /
deliverables
Costs
(in €)
86.400,00
Carmelo Grasso, Donato Di Camillo, Janka Strakova (Staff)
Work Package 2 – Action 2.4
Month of
start
(mm/yy)
Month
of
end
(mm/yy)
01/2006
12/2007 Reconstruction of the large- Quantitative
scale hydrological cycle in
characterization at
the CADSES area by highhydrometeorologic
resolution model-assisted
al level of dry vs.
climatological definition
wet years and dry
of the tropospheric flux of
vs. wet seasons.
water of Mediterranean
Correlations
origin. Analysis of mean
between
the
state,
variability
and
various
water
extreme events.
balances
at
regional scale.
People:
Description of activities,
components, means
Expected output /
deliverables
Costs
(in €)
88.700,00
Valerio Lucarini (Researcher), Robert Danihlik (Tech. Collab.)
NWF Model




Limited Area highresolution weather
forecast model
We may run it in hindcast mode (24 hours
runs) every day for for
1961-2000
Works as magnifying
lens for the CADSES
area
Very flexible in terms
of resolution and area
of interest
Work Package 2 – Action 2.5
Month of Month of
start
end
(mm/yy) (mm/yy)
01/2006
People:
12/2007
Description of activities,
components, means
Expected output /
deliverables
Statistical intercomparison of the Degree of agreement
reconstruction
of
the
between
the
hydrological cycle in the in
various models.
the CADSES area as obtained
Deficiencies of
from models of different level
weather forecast
of complexity. Analysis of the
models
in
differences between forecast
modelling
the
and climate models in the
statistics
of
definition of the seasonal
precipitation.
climatology as well as of the
statistics of the extreme
events.
Costs
(in €)
87.200,00
Valerio Lucarini (Researcher), Ida Kriegerova (Tech. Collab.)
DATASETS
INTERCOMPARISON




NCEP and ERA 40
reanalyses
IPCC 4AR models
simulations for XX
century and climate
change projections
Other datasets for LAMs
(such as PRUDENCE
project of the V FW)
Observations
RIVER BASINS
BALANCES
(RiverNet)
ODER
DANUBE
ELBE
Work Package 5 – Action 5.1
Month of
start
(mm/yy)
Month of
end
(mm/yy)
01/2006
12/2007
Description of activities, components,
means
Expected output
/
deliverables
Costs
(in €)
Organization of meetings, conferences Public events,
and seminars during the project
publications,
duration to disseminate the obtained
brochures,
results. Preparation of paper and
outreach in
multimedia publications. Training
the
press.
activities.
Development
and
Publicly
maintenance of the web-site of the
accessible
project. PP2 will contribute to the
web-site
organization of public events with a
budget of 10000 euros. PP6 will
contribute with a total budget of
2500 euros. PP11 will participate to
this action within the budget of PP1.
163.600,00
People: Valerio Lucarini (TD), Veronica Benedettelli (ATD),
Carmelo Grasso, Donato di Camillo, Janka Strakova (Staff)
Collaboration foreseen: PP2, PP6, PP11
Web-site

HYDROCARE is
already on-line

Public Section
(Technical Reports,
Outreach, Links,
Press)

Private Section
(Reporting,
confidential
documents, etc)
http://www.hydrocare-cadses.net
Publicity
activities



Press Releases
Page on the
Febraury 2006
issue of
Parliament
Magazine
Media
Partnership with
Radio Lotte?
Conclusions



PP1 is strongly committed to making of
HYDROCARE a real success
PP1 encourages collaborations with all PPs in
order to coordinate the execution of the actions
It especially important to coordinate the
publicity and dissemination activities: we need to
decide very soon location and time of
conferences, meetings, training initiatives and we
need a common action on media.