Landslides and Engineered Slopes – Chen et al. (eds) © 2008 Taylor & Francis Group, London, ISBN 978-0-415-41196-7 The evaluation of failure probability for rock slope based on fuzzy set theory and Monte Carlo simulation Hyuck-Jin Park Department of Geoinformation Engineering, Sejong University, Republic of Korea Jeong-gi Um Department of Environmental Exploration Engineering, Pukyung National University, Republic of Korea Ik Woo Department of Ocean System Engineering, Kunsan National University, Republic of Korea ABSTRACT: Uncertainty is pervasive in rock slope stability analysis due to various reasons and sometimes it causes serious rock slope failures. Therefore, since 1980’s the importance of uncertainty has been recognized and subsequently the probability theory has been used to quantify the uncertainty. However, not all uncertainties are objectively quantifiable. Some uncertainties, due to incomplete information, cannot be handled satisfactorily in the probability theory and the fuzzy set theory is more appropriate. In this study the random variable in rock slope stability analysis is considered as fuzzy number and the fuzzy set theory is employed. In addition, the Monte Carlo simulation technique is utilized to evaluate the probability of failure for rock slope. This overcomes the shortcomings of the previous studies, which are employed vertex method, first order second moment method and point estimate method. Since the previous studies used only the representative values from membership function to evaluate the stability of rock slope, the approximated analysis results were obtained in the previous studies. With Monte Carlo simulation technique, more complete analysis results can be secured in the proposed method. The proposed method was applied to the practical example. According to the analysis results, the probabilities of failure obtained from the fuzzy Monte Carlo simulation coincide with the probabilities of failure from the probabilistic analysis. 1 INTRODUCTION One of the difficulties in slope stability analysis is uncertainty inevitably involved in the variability of the material properties and the geotechnical model. The natural materials comprising most slopes have an innate variability difficult to establish and to predict and therefore, the variability of geologic material is one of the major sources of uncertainties. In addition, insufficient amount of information for site conditions and incomplete understanding of failure mechanism are also another sources of uncertainties. Therefore, the presence and the significance of uncertainties in slope stability analysis has been appreciated for long time. Consequently several approaches such as observation method (Peck, 1969) have been suggested to deal properly with uncertainty. The probabilistic approach has been proposed as an objective tool for representing uncertainty in failure model and material characteristics. Many probabilistic analyses have been published in literature (Einstein and Baecher, 1982; Mostyn and Small, 1987; Mostyn and Li, 1993; Nilsen, 2000; Park and West, 2001; El-Ramly et al., 2002; Pathak and Nilsen, 2004; Park et al., 2005). However, the probabilistic analysis requires the statistical parameters and distribution type for random variables in order to quantify the uncertainty. That is, the mean, standard deviation and probability density function for uncertain parameters are prerequisite in order to carry out the appropriate probabilistic analysis. However, a large amount of information and data are required to obtain statistical parameters and distribution type for random variable but in many practical conditions, the amount of data is frequently limited. Consequently it is difficult to secure statistical parameters and distribution type of the uncertain variable, and this situation makes the application of probabilistic analysis difficult. The uncertainties caused by limited or incomplete information cannot be handled satisfactorily 1943 2 FUZZY MONTE CARLO SIMULATION METHOD 2.1 Fuzzy set theory In classical set theory, an element either belongs or does not belong to the set. That is, the membership of classical set theory is defined in strict sense. When a certain element x belongs to set A, x is a member or element of a set A and can be written x|A (1) Whenever x is not an element of a set A, we write x|A 1.0 Membership function in the probability theory and the fuzzy set is more appropriate (Dodagoudar and Venkatachalan, 2000). Therefore, the present study proposed the utilization of fuzzy set theory in order to overcome the limitations of the probabilistic approach. Fuzzy set theory has been proposed by Zadeh (1965) and it has been known as appropriate approach for dealing with uncertainty mainly caused by incomplete information. Consequently, fuzzy set theory has been employed in many slope stability analyses (Juang & Lee, 1992; Lee and Juang, 1992; Davis and Keller, 1997; Juang et al., 1998; Dodagoudar and Venkatachalan, 2000; Giasi et al., 2003; Li and Mei, 2004). However, the previous studies combined the fuzzy set theory with the approximate method such as point estimate method or first order second moment method. Since the approximate methods use only few representative values from uncertain parameters, the analysis cannot provide accurate analysis results. Therefore, this study proposed the new approach incorporating the Monte Carlo simulation which provides complete analysis results with fuzzy set theory. 0.5 HEIGHT CORE 0.0 SUPPORT x Figure 1. Concept of membership function. membership function in a fuzzy set may admit some uncertainty, its membership is a matter of degree. The membership function can be manifested by many different types of function and different shapes of their graphs. Triangular and trapezoidal shapes are most common types in the membership function. Fig. 1 shows the concept for support, core and height in a trapezoidal shaped fuzzy set. The support is the set of all elements of set x that have nonzero membership in A. In addition, core is the set of all elements of x for which the degree of membership in A is 1. The height of a fuzzy set A may be defined as the largest membership grade obtained by an element in that set. If the height of a fuzzy set A is 1, set A is called normal and otherwise, it is called subnormal. There are two commonly used ways of denoting fuzzy sets. A = x, μA x 1 or (2) A set can be defined by membership function that declares which elements of x are members of the set and which are not. 1, x | A μA (x) = (3) 0, x | A For each x | A, when μA (x) = 1, x is declared to be a member of A. When μA (x) = 0, x is declared to be a nonmember of A. However, in fuzzy sets, which is introduced by Zadeh (1965), more flexible sense of membership is possible. That is, the membership function can be generalized such that the values assigned to the elements fall within a specified range. In fuzzy set, the degree of membership to a set is indicated by a number of between 0 and 1. In fuzzy set theory, each fuzzy set is uniquely defined by a membership function. Since an element’s A= μA (x) x 2.2 Fuzzy Monte Carlo simulation (4) The probabilistic analysis has been known as an effective tool to quantify and model uncertainty. However, limited information for uncertain parameters makes the application of the probabilistic analysis difficult. This is because the probabilistic analysis is carried out on the premise that the precise mean and standard deviation and the appropriate probability density function for uncertain parameter can be obtained. However, in order to obtain the adequate statistical parameters and distribution function for uncertain parameter, a large amount of data is required but it is often not practically possible. Frequently only the maximum and minimum values for uncertain parameter can be obtained and therefore, uncertain parameter can be expressed only with interval between minimum 1944 and maximum. Under this condition, uncertain parameter may be expressed as a fuzzy set, if there is some reason to believe that not all values in the interval have the same degree of support (Juang et al., 1998). Since uncertainties due to incomplete information are pervasive in the procedure of slope stability analysis, several researches utilized fuzzy set theory in slope stability analysis (Juang et al., 1998; Dodagoudar and Venkatachalan, 2000; Giasi et al., 2003). However, the previous researches utilized the vertex method (Dong and Wong, 1987) to evaluate fuzzy input parameters in slope stability analysis. The vertex method is based on the α-cut concept of fuzzy numbers and involves an interval analysis. The basic idea of the vertex method is to discretize a fuzzy number into a group of α-cut intervals. By replacing fuzzy numbers in the slope model with intervals, the fuzzy computation obtains factor of safety in the deterministic slope model. However, when the factor of safety is evaluated from the deterministic slope model using two interval values, the first order second moment method (Giasi et al., 2003) or point estimate (Dodagoudar and Venkatachalam, 2000) has been applied. According to Harr (1987), the first order second moment method and point estimate method are considered as approximate method since the methods do not utilize complete information for random variables to evaluate performance function. The approximate method has been proposed to evaluate the probability using simple calculation with only few representative values of random variable without distribution information. However, since the previous researches used incomplete information in the analysis, there is a possibility that approximate results would be obtained instead of the precise analysis results. Therefore, this study proposed the new approach evaluating the reliability of rock slope with fuzzy number and Monte Carlo simulation. The Monte Carlo simulation is the most complete method of the probabilistic analysis since all the random variables are represented by their statistical parameters and probability density function. In addition, the complete information is employed to evaluate performance function in Monte Carlo simulation. In order to combine Monte Carlo simulation with fuzzy set theory, uncertain parameter is considered as fuzzy number and its membership function is decided by means of available information and engineering judgment. Then Monte Carlo simulation is utilized to evaluate the probability of slope failure from fuzzy numbers of uncertain parameters. In most rock slope stability analyses, the friction angle of discontinuity is considered as uncertain parameters. This is because the number of the direct shear tests which are carried out to acquire shear strength of discontinuity is always limited and therefore, the true value of friction angle cannot be evaluated. Consequently, in the present study the friction angle is considered as fuzzy number and its membership function is decided on the basis of analysis for laboratory test results. However, in the Monte Carlo simulation, the cumulative density function for uncertain parameter is required. In the present study, the membership function is adapted to cumulative density function in the calculation of performance function. Then in Monte Carlo simulation, the process takes a single value selected randomly from its cumulative distribution. The randomly selected parameter is used to generate a single random value for factor of safety. By repeating this process many times to generate a large number of different factors of safety, a cumulative density function for factor of safety can be obtained and then probability of failure is evaluated. 3 CASE STUDY The proposed method in the present study has been applied to practical example in order to check the feasibility and validity of the proposed approach and compare with the probabilistic analysis results. A slope has been selected and the detailed field investigation has been carried out. The dip direction and dip angle of the slope are 325 degree and 65 degree, respectively and its height is 40.8 m. The slope is composed of Precambrian metasedimentary rock. Approximately 350 discontinuity data has been obtained on scanline survey and 6 discontinuity sets were identified by means of clustering process (Table 1). Among 6 discontinuity sets, 2 sets (set 2 and set 4) are analyzed as kinematically unstable for planar failure. In this study, the analysis for only planar failure is performed since the analysis results of planar failure are easy to compare to other analysis results. In addition, the direct shear test is carried out in order to acquire the shear strength parameter for discontinuity. Based on the 19 direct shear test results, the friction angle ranges from 20.9 to 46.3 and their mean and standard deviation are 34.6 and 8.2, respectively (Fig. 2). However, even if 19 tests were performed, the probability density function cannot be determined due to severe scattering as can be seen in Fig. 2. Even the previous Table 1. gation. Discontinuity sets observed from field investi- Discontinuity sets Representative orientation Set 1 Set 2 Set 3 Set 4 Set 5 Set 6 217/77 320/30 061/66 311/40 196/56 183/05 1945 0.12 5 0.10 4 0.08 Frequency Frequency 6 3 2 0.04 0.02 1 0 0.06 0.00 20 - 25 25 - 30 30 - 35 35 - 40 40 - 45 0 45 - 50 Figure 2. 1 2 3 Factor of safety Friction Angle Figure 3. Results of direct shear tests. Results of probabilistic analysis for joint set 2. 0.16 3.1 Results of probabilistic analysis In order to compare to other analysis results, the deterministic analysis based on the limit equilibrium approach has been carried out for joint set 2 and 4, which are analyzed as kinematically unstable on the stereonet analysis. This analysis has been performed with same input values for all the deterministic parameters used in the probabilistic analysis and mean value of the distribution for random parameter. The factor of safety for set 2 is evaluated as 1.20 and the factor of safety for set 4 is 0.82. That is, joint set 2 has been analyzed as stable in the deterministic analysis but unstable for joint set 4. The probabilistic analysis is also carried out for set 2 and set 4 using the procedure proposed by Park et al. (2005). In the present study, the orientation of discontinuity is taken into account for the deterministic parameter and therefore, the single fixed dip direction and dip angle for discontinuity orientation is employed in the probabilistic analysis. On the other hand, the friction angle for discontinuity is considered as the random variable. The mean value and standard deviation have been used and subsequently normal distribution 0.12 Frequency researches proposed normal distribution for probability density function of friction angle (Mostyn and Li, 1993; Nilsen, 2000; Pathak and Nilsen, 2004; Park et al., 2005), it is not easy to decide normal distribution as probability density function for friction angle in this study due to uncertainty. Therefore, the friction angle is considered as fuzzy number whose support is between 20.9 and 46.3 in this study. The triangular shape is chosen for membership function of the friction angle and the core value of membership function is decided to 34.6 which is mean value of the test results. In addition, on the basis of Hoek’s suggestion (1997) in rock slope stability analysis, cohesion is not considered in slope stability analysis. 0.08 0.04 0.00 0 1 2 3 Factor of safety Figure 4. Results of probabilistic analysis for joint set 4. has been chosen for probability density function of friction angle. In order to evaluate the probability of failure, the Monte Carlo simulation approach is employed in the probabilistic analysis. Total 16,000 repeated calculations are carried out. Figs. 3 and 4 show the results of analysis, which show the distributions of the factor of safety. For joint set 2, the probability of failure is evaluated as 29.3% and the probability of failure for set 4 is 73.5%. In case of set 2, the result of the deterministic analysis indicate stable but the result of the probabilistic analysis shows quite high probability of failure. This is because the deterministic analysis does not reflect the variability and uncertainty in input parameter. However, the coefficient of variation for friction angle used in this study is calculated as 23.3% and this is quite high value compared to the other previous researches, which show 10% (Park and West, 2001). It means that the dispersion of direct shear test results used in the present study is too large. That is, the randomly generated friction angle from Monte Carlo simulation ranges from 10 to 59.2 in the confidence interval of 99.8%. Consequently the uncertainty of friction angle is too large and subsequently in 1946 1.0 0.21 0.8 Membership function Frequency 0.28 0.14 0.07 0.6 0.4 0.2 0.00 0 1 2 3 0.0 Factor of safety 10 20 30 40 50 Internal friction angle Figure 5. Results of probabilistic analysis for joint set 2 when COV = 10%. Figure 7. 0.36 0.16 0.27 0.12 Frequency Frequency Triangular membership function. 0.18 0.09 0.08 0.04 0.00 0 1 2 0.00 3 0 Factor of safety 1 2 3 Factor of safety Figure 6. Results of probabilistic analysis for joint set 4 on when COV = 10%. Monte Carlo simulation, too small value of friction angle could be generated and used in factor of safety calculation. This could cause serious error in the evaluation of the probability of failure. Therefore, in order to check out the influence of uncertainty in input parameters, the dispersion of friction angle is reduced to 10% of C.O.V (coefficient of variation) and the probability of failure is recalculated (Fig. 5 and 6). Figures 5 and 6 show that the dispersion of factor of safety is reduced comparing to Figures 3 and 4. The probability of failure for joint set 2 is reduced to 8.8% but the probability of failure for joint set 4 is increased to 94.0%. This is because the lower half of the dispersion for factor of safety in joint set 2 is reduced but the upper half of the dispersion in joint set 4 is reduced. This shows that uncertainty and dispersion of input parameter affect the analysis result. Consequently if the number of data is limited and subsequently the random properties cannot be recognized precisely, the results of the probability analysis can be affected by the dispersion of the input parameters. Figure 8. Results of FMC analysis for joint set 2. 3.2 Fuzzy Monte Carlo simulation As can be seen previously, the friction angle obtained from direct shear test includes a large amount of uncertainty. This uncertainty is usually caused by a lack of test results. A lack of test results prevents the precise understanding of random properties for uncertain parameters and also makes the application of the probabilistic analysis difficult. Therefore, in the present study the friction angle is considered as fuzzy number. The friction angle is considered as triangular fuzzy number and the minimum and maximum values of the membership function are decided as 20.9 and 46.3, respectively on the basis of test results. In addition, the mean value, 34.6 is decided as core in the membership function (Fig. 7). This means that the randomly generated value from Monte Carlo simulation ranged from 20.9 to 46.3. This shows the dispersion of fuzzy number is much smaller than the dispersion used in the probabilistic analysis. The C.O.V of the fuzzy number is calculated as 13.3% on the confidence level of 99.8% and this value is smaller than the C.O.V used in the probabilistic analysis. The distribution of 1947 0.12 Frequency 0.10 0.08 0.06 0.04 0.02 0.00 0 1 2 3 Factor of safety Figure 9. Results of FMC analysis for joint set 4. factor of safety evaluated from fuzzy Monte Carlo simulation is given in Figures 8 and 9. Comparing the factors of safety distribution obtained from fuzzy Monte Carlo simulation with the factors of safety distribution obtained from the probabilistic analysis, the dispersion of factor of safety distribution in fuzzy Monte Carlo simulation is reduced. In accordance with the analysis results, the probability of failure for joint set 2 is 33.5% and the probability of joint set 4 is 72.9%. In case of joint set 2, the probabilities of failure evaluated from the probabilistic analysis and fuzzy Monte Carlo simulation are 29.3% and 33.5% respectively and the analysis results are somewhat different. But in case of joint set 4, the probabilities of failure evaluated from the probabilistic analysis and fuzzy Monte Carlo simulation are 73.5% and 72.9% respectively and the analysis results are quite similar. Consequently, even if the application of fuzzy set theory reduced the dispersion in input value, the probabilities of failure obtained from two different approaches are similar. As a result, the application of fuzzy set theory manages the uncertainty of input parameter effectively. 4 CONCLUSIONS Uncertainty is pervasive in rock slope stability analysis due to various reasons and sometimes it causes serious rock slope failures. Therefore, the probability theory has been used to quantify the uncertainty. However, not all uncertain-ties are objectively quantifiable. Some uncertainties, due to incomplete information, cannot be handled satisfactorily in the probability theory and the fuzzy set theory is more appropriate. In this study the random variable in rock slope stability analysis is considered as fuzzy number and the fuzzy set theory and Monte Carlo simulation are employed. In order to verify the feasibility and validity of the proposed approach, the proposed method was applied to the practical example. In the deterministic analysis results, joint set 2 is analyzed as stable but joint set 4 is analyzed as unstable. On the contrary in the probabilistic analysis results, the probability of failure for joint set 2 is 29.3% and the probability for joint set 4 is 73.5%. The data used in the probabilistic analysis are widely scattered since the COV of friction angle is evaluated as 23.3%. The widely scattered data may cause serious miscalculation in the evaluation of the failure probability since impractical data could be used in the calculation. Therefore, the probability of failure is recalculated with the modified data whose COV is reduced to 10.0% and the probabilities has been changed. The analysis results of the proposed method using fuzzy Monte Carlo simulation are 33.5% for joint set 2 and 73.5% for join set 4 and the COV of the data that considered as fuzzy number is 13.3%. The probabilities from the probabilistic analysis and the proposed method are somewhat similar but the COV of data in the proposed method is smaller than the COV in the probabilistic analysis. Therefore, the fuzzy set theory managed uncertainty in data more effectively than the probabilistic analysis. REFERENCES Davis, T.J. & Keller, C.P. 1997. Modelling uncertainty in natural resource analysis using fuzzy sets and Monte Carlo simulation: slope stability prediction. Int. J. Geographical Information Science. 11(5): 409–434. Dodagoudar, G.R. & Venkatachalam, G. 2000. Reliability analysis of slope using fuzzy sets theory. Computers and Geotechnics. 27: 101–115. Dong, W.M. & Wong, F.S. 1987. Fuzzy weighted averages and implementation of the extension principle. Fuzzy Set and System. 21: 183–199. Einstein, H.H. & Baecher, G.B. 1982. Probabilistic and statistical methods in engineering geology. Rock Mechanics, Supplement. 12: 47–61. El-Ramly, H., Morgenstern, N.R. & Cruden, D.M. 2002. Probabilistic slope stability analysis for practice. Can. Geotech. J. 39: 665–683. Giasi, C.I., Masi, P. & Cherubini, C. 2003. Probabilistic and fuzzy reliability analysis of a sample slope near Aliano. Engineering Geology. 67: 391–402. Harr, M.E. 1987. Reliability based on Design in Civil Engineering. New York. Hoek, E. 1997. Rock Engineering; Course note by Evert Hoek[Online], http://www.rockeng.utoronto.ca/ Hoekcorner.htm. Juang, C.H. & Lee, D.H. 1992. Mapping slope failure potential using fuzzy sets. Journal of Geotechnical Engineering. 118(3): 475–494. Juang, C.H., Jhi, Y.Y. & Lee, D.H. 1998. Stability analysis of existing slopes considering uncertainty. Engineering Geology. 49: 111–122. Lee, D.H. & Juang, C.H. 1992. Evaluation of failure potential in mudstone slopes using fuzzy sets. Proc. of Stability and Performance of Slopes and Embankments. 1137–1151. 1948 Li, W.X. & Mei, S.H. 2004. Fuzzy system method for the design of a jointed rock slope. Proc. of SINOROCK 2004. 2B-18. Mostyn, G.R. & Li, K.S. 1993. Probabilistic slope analysis— state of play. Proceeding of Conference on Probabilistic Method in Geotechnical Engineering: 89–109. Mostyn, G.R. & Small, J.C. 1987. Methods of stability analysis. Soil Slope Instability and Stabilization. Balkema, 71–120. Nilsen, B. 2000. New trend in rock slope stability analysis. Bull. Eng. Geol. Environ., 58: 173–178. Park, H.J. & West, T.R. 2001. Development of a probabilistic approach for rock wedge failure. Engineering Geology. 59: 233–251. Park, H.J., West, T.R. & Woo, I. 2005. Probabilistic analysis of rock slope stability and random properties of discontinuity parameters, Interstate Highway 40. Engineering Geology. 79: 230–250. Pathak, D. & Nilsen, B. 2004. Probabilistic rock slope stability analysis for Himalayan condition. Bull. Eng. Geol. Environ., 63: 25–32. Peck, R.B. 1969. Advantages of limitations of the observational method in applied soil mechanics. Geotechnique, 19: 171–187. Zadeh, L.A. 1965. Fuzzy sets. Information and Control, 8: 338–353. 1949
© Copyright 2026 Paperzz