Spoke Cryomodules Sébastien BOUSSON (IPNO), Christine DARVE (ESS) On behalf of the CNRS/IPNOrsay and ESS teams www.europeanspallationsource.se April , 2016 Spoke cryomodule overview: Executive summary • IPN Orsay is taking in charge the design of the ESS spoke cryomodules. The design activity is 99% achieved, up to a very high level of details. The only remaining design work to perform is to implement DC Bias capacity of the power coupler doorknob (for margins...). • WP4 is in the design validation phase: prototypes of all sub-components have been fabricated and are under test to have an experimental validation of their performances before starting series productions. • Excellent performances, well above specifications have been already reached on the spoke cavities prototypes allowing to start the procurements for the cavity mass production (niobium supply and cavity fabrication). • Other validation steps, also on prototypes, are planned for the coming months: power coupler conditioning, tests at Uppsala University of cavity+coupler and of the prototype cryomodule at full power. • Collaboration with UU well in place, with many technical exchanges and already common experiments performed on HNOSS (UU horizontal cryostat) with spoke cavities. • IPN Orsay Infrastructure is being adapted to be ready for the mass production and tests of the spoke cryomodule components. 2 Schedule: main blocks • Main objective: deliver to ESS the last (#13) spoke cryomodule for Xmas 2018 Achieved or estimated dates for Reference milestones for the production phase: the call for tender publication Cavity production start : May/June 2016 (2 months delay, no further consequences) Cryomodule production start : December 2016 First cryomodule shipped to Uppsala: 14 Aug 2017 RFI date (ready for installation): January 2018 Last cryomodule tested & validated in Uppsala: 20 Dec 2018 i.e. cryomodule production rate = 1 cryomodule every 5 weeks 3 Spoke cryomodule requirements & technical performances Warm linac The 13 spoke cryomodule composing the first superconducting acceleration stage. SCRF linac (T=2K) The cryogenic distribution system for the spoke section (valve boxes, cryolines, cryo end box) The IPNO task includes all activities linked to the design, prototyping, series production, preparation, assembly and then testing of the spoke cryomodule components (cavities, power couplers, cold tuning systems, cryostat). The 13 cryomodule validation tests at nominal RF power will be done by the Uppsala University team, already strongly involved 4 in the project, in their newly built and operational FREIA facility. Spoke cryomodule requirements & technical performances Double Spoke SRF Cavities • Double spoke cavity (3-gaps), 352.2 MHz, b=0.50 • Goal: Eacc = 9 MV/m [Bp= 62 mT ; Ep = 39 MV/m] • 4.2 mm (nominal) Niobium thickness • Titanium Helium tank and stiffeners • Lorentz detuning coeff. : ~-5.5 Hz/(MV/m)2 • Tuning sentivity Df/Dz = 130 kHz/mm Cold Tuning System Power Coupler • Ceramic disk, 100 mm diameter • 400 kW peak power (335 kW nominal) • Antenna & window water cooling • Outer conductor cooled with SHe • Doorknob transition from coaxial to ½ height WR2300 waveguide • Slow tuning (stepper motor): Max stroke: ~ 1.3 mm Tuning range: ~ 170 kHz Tuning resolution: 1.1 Hz • Fast tuning (piezo-actuator): Applied voltage up to +/- 120V Tuning range at 2K: 675 Hz (min) Spoke Cavities design & prototype performances 1/2 DOUBLE-SPOKE CAVITY Frequency [MHz] Beta_optimum Operating gradient [MV/m] Temperature (K) Bpk [mT] Epk [MV/m] G [Ohm] r/Q [Ohm] Lacc (=beta optimal x nb of gaps x λ /2) [m] Bpk/Eacc [mT/MV/m] Epk/Eacc P max [kW] 352.21 0.50 9.0 2 61 38 133 427 0.639 6.8 4.3 335 3 spoke cavity prototypes have been fabricated and tested in vertical cryostat: #1 fabricated by SDMS (Fr), #2 and #3 fabricated by ZANON (It) Niobium is from Tokyo Denkai (Japan) ZA 01 Romea ZA 02 Giulietta SD 01 Germaine 6 Spoke Cavities design & prototype performances 2/2 Spoke cavity prototype test results (Jan15 – Feb16): • Excellent performances, well within specifications (both on Eacc & Qo) Pcav<0.5W Chemical etching Ultra pure water high pressure rinsing Cold tuning system design & prototype performances 1/2 Design features: • Double lever arm tuner (“Saclay-type”). • Actuators : one stepper motor and two piezos per tuner (one for redundancy). CTS parameters / design results Cavity sensitivity 128 kHz/mm Cavity stiffness 20 kN/mm Max cavity deformation 1.28 mm Course / Tuning range 1.28 mm / 160 kHz Resolution 1 Hz/step Piezo tuning range @ RT @2 K ~ 1.5 kHz ~ 800 Hz (tbc) Cold tuning system design & prototype performances 2/2 4 prototypes tuners fabricated by ESIM (Fr) and tested (Cryo, VT) • With 50 mm piezos length All specifications reached • With 90 mm piezos length (purpose: extra margin Bad performances. Analysis in progress: pre-load? high stress (differential thermal shrink)?... Cavity ID VT date Piezo #1 Piezo #2 Tuner sensitivity @2K Tuner sensitivity @4K Tuner sensitivity @300K Cavity sensitivity @300K Detuning range Piezo #1 @2K Detuning range Piezo #2 @2K Frequency @4K (w/o tuner) Frequency @2K (w/ tuner) Pressure sensitivity (w/o tuner) Pressure sensitivity (w/ tuner) Static Lorentz coefficient ZA01 ZA02 SD01 ZA01 Romea Giulietta Germaine Romea janv-15 feb-15 apr-15 juin-15 Noliac 50 mm Noliac 50 mm PI 36 mm PiezoMec. 90 mm Noliac 50 mm Noliac 50 mm Noliac 50 mm PI 90 mm kHz/mm 78 88 68 kHz/mm 79 92 73 82 kHz/mm 67 kHz/mm 144 Hz 930 953 542 306 (+/- 120V) Hz 680 717 791 0 (issue) MHz 352.453 352.123 352.038 352.409 MHz 352.429 352.100 352.032 352.419 Hz/mbar 25.5 23.3 5.5 Hz/mbar 28.8 28.8 14.5 Hz/(MV/m²) -8.5 -6.8 -8.1 - Coarse tuning range Power coupler & prototype performances 1/2 Design features: Coaxial geometry, capacitive coupling. Ceramic: disk, 6 mm thick, TiN coated Designed for 400 kW peak (25 kW CW) Eq. average power : 25 kW CW. 3 cooling channels: • water for ceramic window & antenna • 5 K SC He for outer conductor 4 power coupler prototypes have been fabricated: #1 and #2 fabricated by SCT company (Fr) #3 and #4 fabricated by PMB Company (Fr) Power coupler port 100 mm diameter Power coupler & prototype performances 2/2 First conditioning happened in end January 2016, at CEA premises (availability of RF source ) Due to an accidental disabling of all securities, the conditioning went on without any protection/interlock on… … and at ~100 kW, vacuum was too high, an arc discharge occurred and one of the coupler ceramic cracked. The second power coupler test is now being prepared. Cryomodule design & prototyping 1/2 Thermal shield All cryomodule parts are fabricated and delivered Gate valves Vacuum vessel & its Mechanical support Cold/warm transition Blankassembly of some parts Inter-cavity belows Coupler/vacuum vessel interface Cryomodule design & prototyping 1/2 First test at 80 K in the cryomodule (without the cavity package) in February 2016 Spoke cryomodule components Integration and Verification Several test results are validation of components ability to perform as required by ESS and thus are mandatory before launching series production: • Cavity test in vertical cryostat (achieve 9MV/m and nominal Qo) Required prior tendering for niobium production for series (December 2015) i.e. one successful test to be achieved in October 2015 at the latest Done ! • Cavity with coupler test in HNOSS (RF coupling successful, achieve 9MV/m and CTS) The test requires around 100 kW of RF power Required prior tendering for the power coupler mass production (Dec. 2016) i.e. one successful test to be achieved in Dec 2016 at the latest On time (Summer 2016) • Prototype cryomodule test (validate cryo, assembly, overall results) Required prior tendering for the series production of spoke cryomodules (Dec. 2016) i.e. one successful test to be achieved in Dec. 2016 (ideally), or March 2017 (at the latest) On time (Nov. 2016 – few margin) 14 Organization at IPN Orsay 2015: an average of 12 FTE has worked on ESS WP4 (spoke) (it was 9 in 2014, 7 in 2012 & 2013) Projected for 2016, 2017 & 2018 is 14 FTE/year In total, in 2015, about 24 IPN Orsay persons have been working for ESS 15WP4 Spoke cryomodule Major Procurements 1/2 1. Niobium procurement & lead time • • • • • 2. In progress - Cost estimated to ~ 2.0 M€ 2 good offers received Order all niobium for spokes in one single procurement Supplier strategy: only 1 (for the ~ 4 tons of Nb) Performance mitigation strategy: buy niobium equivalent to 3 more cavities. Spoke cavities procurement & lead time • • • • In progress - Cost estimated to ~ 4.0 M€ 3 good offers received Order the 26 spoke cavities in one single procurement Supplier strategy: only 1 – it’s cost effective & less required work for fabrication follow-up (2 contractors is of course possible, but no clear advantages, not necessary for schedule reasons for instance) • Performance mitigation strategy : buy 3 more if within allocated budget • Allocated production lead time will allow 2 phases: - a pre-production (4 units) to check production processes and quality, constituting a Go/NoGo for phase 2. - a series production for the remaining 22 units 16 Spoke cryomodule Major Procurements 2/2 3. Spoke power couplers procurement & lead time • • • • • 4. Scheduled between June 2016 and June 2018 - Cost estimate: ~ 1.1 M€ Several companies worldwide & Europe – Prototypes: SCT (Fr) and PMB (Fr) Order the 26 power couplers in one single procurement, to a single supplier Spare strategy: no spare (ESS guideline), but with option for 1 or 2 spares Allocated production lead time will allow 2 phases: - a pre-production (2 to 4 units) to check production processes and quality, constituting a Go/NoGo for phase 2. - a series production for the remaining (22 or 24) Spoke cold tuning systems procurement & lead time • Scheduled between June 2016 and June 2018 - Cost estimate: ~ 0.5 M€ 5. Cryomodule parts procurement/assembly & lead time • Scheduled between July 2016 and Sept. 2018 - Cost estimate: ~ 4.0 M€ 17 Top risks • #1 (Main risk): success-oriented schedule: no room for a failure – Typically: a cavity VT failure, a cryomodule assembly failure implying a partial or full disassembly/re-assembly of a cryomodule. – Mitigation: anticipate as much as possible the series production, to give schedule margin during series production, without taking additional risk: this is the followed scenario with the intermediate validation tests. • #2: No spare: neither for sub-components nor for a complete module – A failure during production of a sub-component, or a lower performing component (cavity, power coupler, cryomodule...). – Mitigation: integrate options in procurement for additional production (yield) and use whenever possible the prototype cryomodule parts (except for cavities). • #3: Failure of a test/preparation facility: RF source, vertical cryostat,... – Cavity, coupler or cryomodule tests and preparations rely on heavy infrastructure that might have failures – Mitigation: have fallback solutions: for RF, several sources will be available at UU (FREIA) and 1 at IPNO; for cryo test, 2 VC will be available at IPNO,... Next Six Months • Conditioning of the 2 sets of power coupler pairs • Develop and validate several cavity procedures: • Cavity H degassing at 550 °C to cure from Q-disease • Cavity venting procedure without inducing particle contamination • Achieve the prototype valve box fabrication • Perform a test of a cavity + power coupler in HNOSS before sept. 2016 • Achieve preparation and assembly of the spoke cryomodule for Oct. 2016 • Start niobium and cavity mass production within 2 months 19 Summary • All 3 cavity prototypes already tested in VT and showed excellent performances, with important margins w.r.t. specifications • Design of all components for the spoke cryomodule is 99 % achieved • Fabrication and assembly of the spoke cryomodule prototype and valve box, close to completion; the prototype cryomodule should be ready for test in Oct. 2016. • The actual schedule allows us to deliver the last spoke cryomodule to ESS on time (Dec. 2018), with realistic time allocated for the different activities…but only little (no ?) margin to cover for potential failures. 20
© Copyright 2026 Paperzz