Contingency Management Plan LPM-61 Latest Revision 6/4/2015 Large Synoptic Survey Telescope (LSST) Contingency Management Plan Victor Krabbendam LPM-61 Latest Revision: June 4, 2015 This LSST document has been approved as a Content-Controlled Document. Its contents are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. If this document is changed or superseded, the new document will retain the Handle designation shown above. The control is on the most recent digital document with this Handle in the LSST digital archive and not printed versions. The contents of this document are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. i Contingency Management Plan LPM-61 Latest Revision 6/4/2015 Change Record Version Date Description Owner name 1.0 8/14/2008 Initial release as Document5874 C. Claver et al. 1.0 7/25/2011 Revision to LPM-61, title and content change D. Sweeney 1.1 8/10/2011 Updated tables D. Sweeney 9/10/2013 Significant update and rewrite to reflect LSSTPO as an AURA center, new authority levels, pre-FDR updates to cost and schedule, and post-JIM Review recommendations. V. Krabbendam 3 11/10/2014 Document refresh to incorporate 2014 updates to the Large Facilities manual and the conditions of V. Krabbendam the CSA for the LSST MREFC Project. 3.1 3/20/2015 Update to reflect updated contingency calculations V. Krabbendam and for consistency with the CEP 6/4/2015 Proofread and edit for consistency with Cost Estimating Plan, Risk & Opportunity Management R. McKercher Plan, and Scope Options 2 3.2 The contents of this document are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. i Contingency Management Plan LPM-61 Latest Revision 6/4/2015 Table of Contents Change Record ............................................................................................................................................... i Table of Contents .......................................................................................................................................... ii Purpose ........................................................................................................................................................ iii Applicable Documents ................................................................................................................................. iii Acronyms and Definitions ............................................................................................................................ iii Contingency Definitions ............................................................................................................................... iii 1 Introduction .......................................................................................................................................... 1 2 Contingency Elements .......................................................................................................................... 2 3 4 5 2.1 Budget Contingency ...................................................................................................................... 2 2.2 Schedule Contingency ................................................................................................................... 2 2.3 Scope Contingency ........................................................................................................................ 2 Cost and Schedule Contingency Estimation.......................................................................................... 3 3.1 Assessment Tool ........................................................................................................................... 3 3.2 Uncertainty Determination ........................................................................................................... 4 3.3 Risk Elements ................................................................................................................................ 5 3.4 Correlations................................................................................................................................... 6 Contingency Management .................................................................................................................... 7 4.1 Approval Authority........................................................................................................................ 7 4.2 Scope Changes .............................................................................................................................. 9 4.3 Opportunity Management .......................................................................................................... 10 4.4 Contingency Assessment ............................................................................................................ 10 Reporting............................................................................................................................................. 11 Appendix A: Activity Based Uncertainty Assessment (Excerpt from LPM-81 Section 10) ......................... 13 Appendix B: LSST Change Request Approval Form .................................................................................... 16 The contents of this document are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. ii Contingency Management Plan LPM-61 Latest Revision 6/4/2015 The LSST Contingency Management Plan Purpose The LSST project plan includes contingencies for budget, schedule and scope. This document describes the management processes for development and allocation of those contingency resources. This plan covers the approach for addressing the overall LSST scope (performance margins, deliverable scope, and technical approach), the integrated project schedule contingency (schedule float), and the NSF MREFC portion of the funding. NSF has a “No Cost Overrun” policy originally codified in the FY 2009 budget request to Congress that reads: “NSF is implementing a ‘no cost overrun’ policy, which will require that the cost estimate developed at the Preliminary Design Stage have adequate contingency to cover all foreseeable risks, and that any cost increases not covered by contingency be accommodated by reductions in scope." This Contingency Management plan addresses this policy and is the key approach to the successful completion of the Project, on time and on budget. Applicable Documents The following documents are applicable to the development or implementation of this CMP. They are available in the LSST document archive. Change Control Process (LPM-19) Cost Estimating Plan (LPM-81) Document Management Plan (LPM-51) Project Execution Plan (LPM-54) Risk & Opportunity Management Plan (LPM-20) Science Requirements Document (LPM-17) Scope Options (LPM-72) Spare Parts and Consumables Policy (LSE-170) System Engineering Management Plan (LSE-17) Acronyms and Definitions Glossary of Abbreviations (Document-11921) Glossary of Definitions (Document-14412) Contingency Definitions Project Baseline – The approved version of the Project plan, its costs, schedule, and deliverables, that can be changed only through formal change control procedures and is used as a basis of comparison. The contents of this document are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. iii Contingency Management Plan LPM-61 Latest Revision 6/4/2015 Contingency – The project’s overall reserves in excess of the documented baselines for budget, schedule, and technical scope. Contingency is defined as the total estimate uncertainty associated with cost, schedule and technical performance. Contingency Management – The formal process that provides the project the ability and flexibility to solve unforeseen issues that may impact the project’s budget, schedule, and technical performance. The process incorporates activity-based uncertainties and high impact event-based uncertainties. Issue – A risk that has been realized, i.e. the undesired outcome has materialized. Event – A specific incident/item that occurs at unique points in time (specific time, distributed time period, or random) on the project. Events are defined in terms of something happening and are independent of activities. Events with negative consequences, when coupled with their probability of occurrence, impact to the project, and handling approach, are the basis for defined entries in the Risk Register. Activity – A specific task or set of tasks that are required by the project, use up resources, and take time to complete (Project Management, pg. 338) Opportunity – The probability of a non-baselined desirable event occurring and the significance of the occurrence. An opportunity is the opposite of a risk. Opportunity Management – The proactive effort to identify and return resources to the contingency pool. Scope Contingency – Scope in the Project Baseline that can be removed without affecting the overall project objectives, but that may still have undesirable effects on the facility performance. The contents of this document are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. iv Contingency Management Plan LPM-61 Latest Revision 6/4/2015 LSST Contingency Management Plan 1 Introduction The LSST project plan includes contingencies for budget, schedule and scope. This document describes the management processes for the development, review and allocation of the contingency resources. This plan addresses the approach for managing the overall LSST scope (performance margins, deliverable scope, and technical approach), the integrated project schedule contingency (schedule float), and the NSF MREFC portion of the funding. The NSF and DOE have separate budgets, budget contingencies and management processes, but the LSST Director is the single LSST Programmatic authority responsible to both agencies for LSST funds. SLAC National Accelerator Laboratory has detailed plans for the use of DOE contingency. The LSST Project Office (LSSTPO) coordinates the schedule and scope contingencies as a project-wide integrated process in order to ensure broad communication and involvement with both funding agencies. The use of contingency is managed by the LSST Project Manager in conjunction with the LSST Director, Change Control Board (CCB), the AURA Management Council for LSST (AMCL), SLAC where appropriate, and the funding agencies. The processes and approval thresholds for each type of contingency allocation are described in Section 3. The baseline levels of budget, schedule, and scope contingency are set to cover the uncertainties associated with construction, deployment of the observatory and data management systems, and all other project uncertainties. The budget contingency and schedule float were determined using a probabilistic approach to evaluate cost and schedule uncertainties, along with potential risk events in order to provide an integrated Monte Carlo simulation of the resources that may be necessary to address these uncertainties and issues. In the event that contingency funds, schedule float and technical performance margin in the system are expended, or if a descope is a recommended management response to a realized risk, the LSSTPO will negotiate with the Joint Oversight Group (JOG), to identify an appropriate descope option. LSST maintains a Scope Options document (LPM-72) to maintain descope and opportunity options. The use of contingency is controlled by established approval authorities to the baseline project plan and accomplished through a defined change control process. All changes pass through the Change Control Process (LPM-19) regardless of magnitude, and all are reported in the monthly report through the Contingency Report Table and the project earned value data. Unspent contingency funds remaining at the end of the project are returned to the NSF. The LSST Contingency Management Plan is one plan in a group of LSST Project plans that collectively defines a comprehensive approach to managing risk, opportunity, and contingency, which are collectively known as approaches to decision making under conditions of uncertainty. The other two plans are the Cost Estimating Plan (LPM-81) and the Risk & Opportunity Management Plan (LPM-20). The contents of this document are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. 1 Contingency Management Plan LPM-61 Latest Revision 6/4/2015 2 Contingency Elements The following subsections provide brief descriptions of the three contingency elements included in the Project baseline – budget contingency, schedule contingency, and scope contingency. All contingency requests are analysed to determine the appropriate project response and the type of contingency to use for resolution – cost, schedule, requirements, scope, approach or any combination thereof. 2.1 Budget Contingency The NSF contingency funding is the amount of money between the project Performance Measurement Baseline budget and the approved Total Project Cost. The amount is intended to address future costs for items in the approved plan that are associated with possible events or conditions arising from causes the precise outcome of which is indeterminable at the time of the budget development and that experience shows will likely result, in aggregate, in additional costs for the approved activity. 2.2 Schedule Contingency Schedule contingency seeks to address uncertainties in task durations and external deliveries like funding. The Project Plan is completely captured in an Integrated Project Schedule (IPS) where activities are defined by duration, predecessors, and successors to form a logic network for the project that will indicate early delivery if no schedule contingency is used. It also provides an accurate float assessment for each activity or path of activities to support management of the plan and resolution of issues as they arise. In some cases, schedule contingency may be insufficient to address changes or issues in the schedule, and re-planning of schedule tasks (possibly including overlapping or parallelization of tasks, increased use of resources – e.g. overtime, outsourcing and alternative strategies) may be required. Requests to change the dates of activities and milestones in the IPS will be made via standard Project Change Requests as described in Section 4. 2.3 Scope Contingency This section describes allocation of the technical margin and implementation of descope options. The Systems Engineering Management Plan (LSE-17) describes the requirement flowdown process and performance assessments of the designs, prototypes, and actual hardware that yield a performance margin against the Science Requirements Document (SRD, LPM-17) design requirements. The Systems Engineering Manager is responsible for monitoring the status of the design performance predictions and works with the Systems Scientist to evaluate the relationship with the SRD. When circumstances allow this margin to be allocated as a response to a realized risk, the Project Manager will evaluate such an option against budget or schedule contingency allocation. In the event that budget, schedule, and margins are fully allocated or insufficient for a realized issue, the project has identified a number of descope options that result in cost savings but also impact the scientific capability of the LSST. These descopes are identified in the LSST Scope Options (LPM-72) document. These reductions would be made only with the approval of the NSF if the LSST project is faced with substantial shortfall from the allocation of planned funding, or if total project costs exceed The contents of this document are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. 2 Contingency Management Plan LPM-61 Latest Revision 6/4/2015 the ability of the project to deal with unexpected costs and schedule delays using budget and schedule contingency. 3 Cost and Schedule Contingency Estimation The amount of Budget and Schedule contingency necessary to complete the Project with a high likelihood of success within the established TPC is determined from a Risk Management Module in the Project Management Control System (PMCS). The methodology described below is a consistent and uniform approach to defining uncertainty distributions at the activity level of the plan using well defined factors and multipliers for specific technical, cost, and schedule assessments similar to Technical Readiness Levels. They are applied to each individual activity in the plan. It is a comprehensive approach specific to the work package scope and conditions. The approach combines technical and cost uncertainty evaluations for a best case cost estimate and combines these and the schedule uncertainty assessment to develop the worst case cost estimate. This +/- range around the baseline "most likely" value provides a reasonable distribution for this costing analysis and yields cost distributions that match expert judgment and historical tendencies to underestimate costs and schedule. The methodology also integrates event based risks into the analysis to model the impact of known conditions with unknown results. These risk events are ported from the LSST Risk Register and applied to any applicable tasks. These Risk Factors also provide the mechanism to correlate the events to multiple activities for one integrated analysis. Ultimately all assessments of uncertainty and risk are subjective, but the NSF panels for the LSST Preliminary Design Review, Cost Baseline Review, and Final Design Review consistently agreed with Project evaluations of the budget and schedule uncertainties. A historical look at 60 NASA projects by T. Amar (Amar 2011) indicates that the cost and schedule contingencies developed by the LSST approach is consistent with a Moderate Risk Project with Semi-Aggressive uncertainty. The uncertainty and risk-based contingency estimation methodology described below provides a standard approach for continued evaluations that can be generated periodically over the duration of the Project to track progress and trends and to evaluate the existing contingency levels with respect to the remaining effort and budgets. 3.1 Assessment Tool The Risk Management Module is a part of the PMCS that is specifically integrated with Primavera P6, the commercial enterprise level cost and schedule planning tool LSST has customized to allow the system to maintain such details as base and burdened costs in base- and then-year values, activity and resource attributes that help sort EVMS and FastLane data, and scope of work descriptions down to the activity level. The full suite of data attributes collected to resource and plan each activity is described in the Cost Estimating Plan (CEP; LPM-81). The data collected that is specifically relevant to budget and schedule contingency is the baseline resource loads and uncertainty assessment associated with technical, cost, and schedule for each activity. The uncertainty assessment is done uniformly and consistently through a set of defined factors, as well as defined risk multipliers, that are based on a standard rubric for resource loaded activities. For convenience, the uncertainty factors from the CEP are included in Appendix A of The contents of this document are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. 3 Contingency Management Plan LPM-61 Latest Revision 6/4/2015 this plan and described in Table 3.1-1. Table 3.1-1: A description of the uncertainty factors and risk modifiers used in LSST's cost estimating process. Parameter Abbreviation Definition Technical Uncertainty Factor TU Valued 1-15 based on the technical readiness of the element from existing and off-the-shelf to beyond the state-of-the-art. Cost Uncertainty Factor CU Valued 1-15 based on the basis of estimate from an existing catalog item, or some related previous experience to an engineering judgement. Schedule Uncertainty Factor SU Valued 2, 4, and 8 based on the schedule impact from no impact to other scheduled activities to Critical Path impact. Technical Risk Multiplier TM Value is based on Design and/or Manufacturing concerns. Cost Risk Multiplier CM Value is based on Material cost and/or Labor rate concerns. Schedule Risk Multiplier SM Value is based on schedule concern. The risk management module in PMCS runs a Monte Carlo simulation to model these estimate uncertainties, schedule uncertainties, and potential risk events using a triangular distribution of best case, most likely, and worst case to provide the distribution of possible cost and schedule outcomes. A key aspect of this cost assessment is the integration of cost, schedule and risk factors modelled together with activity correlations to provide the cost and duration outcome distribution. 3.2 Uncertainty Determination The risk management tool uses a three point probability distribution for the Monte Carlo simulation. These points are the best case, most likely, and worst case data for cost and schedule associated with each activity in the plan. The Baseline cost and schedule data provided by the subject matter experienced estimator is defined as the "most likely" for both cost and schedule duration. To ensure a methodical and uniform approach to developing "best" and "worst" case values, LSST uses well defined uncertainty factors and Risk multipliers to derive default values. Table 3.2-1 below identifies how the factors and multipliers, identified previously in Table 3.1-1 and described in Appendix A, are used to develop the end points for the distribution. The uncertainty factors and multipliers are captured through a customized interactive portal that calculates the best and worst case values for immediate review and also offers the Cost Account Manager and Estimator the ability to manually override the values. All overrides are documented with a basis for the custom values. The formulas provided have been characterized and evaluated by the subject matter experts to yield reasonable values. Since the original estimate of the factors was done together, the combination of the technical factor and multiplier to augment the cost and schedule assessment yields appropriate distributions. The basic rubric is also applicable to the definitions used for the software development tasks that have custom characterizations (as defined in the CEP) and is extensible to other ranges should the process require a different gain to address uncertainties in later phases of the program. The contents of this document are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. 4 Contingency Management Plan LPM-61 Latest Revision 6/4/2015 Table 3.2-1: How LSST uses uncertainty factors and risk multipliers to develop the Best Case, Most Likely, and Worst Case probability distribution 3-Point Distribution Value Formula Value Range Most Likely Cost This is 100% of the Baseline Activity Cost. Baseline Activity Cost Best Case Cost 100% -[(TU +CU)*CM] * Baseline Cost 40% - 100% of Baseline Cost Worst Case Cost 100% + [(TU*TM)+(CU*CM)+(SU*SM)] * Baseline Cost 100% - 198% of Baseline Cost Most Likely Schedule 100% of the Baseline Activity Duration Baseline Activity Duration Best Case Schedule 100% -[(TU +SU)*SM] * Baseline Duration 77% - 100% of Baseline Duration Worst Case Schedule 100% + [(TU*TM)+ (SU*SM)] * Baseline Duration 100% - 168% of Baseline Duration 3.3 Risk Elements The Risk Management Module is populated with event-based risks that can impact both cost and schedule. Risks imported into the PMCS have the same three-point distribution for schedule duration and cost impact, as well as a probability that defines how often the risk is invoked in a simulation. The risk is assigned to each applicable activity so each time the risk is active its impact is correlated to all its assigned activities. Risks are imported from the LSST Risk Register – a key tool in LSST's continuous process to identify, assess, and track events that may occur in the future that can have negative impact on the project. The Risk & Opportunity Management Plan (LPM-20) fully describes the process and describes the full complement of assessments made for each risk. Figure 3.3-1 shows the data form for a particular Risk item. The key parameters used to characterize the risk in the PMCS database have been circled. The key data are the WBS areas to which the risk should be applied, probability of occurrence, the expected cost impact (labor and non-labor) and the schedule impact. Figure 3.3-1: The data form for a particular Risk item in the LSST Risk Register with key parameters circled The contents of this document are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. 5 Contingency Management Plan LPM-61 Latest Revision 6/4/2015 Several steps are required to characterize the risk in PMCS with appropriate best and worst case cost and schedule values: 1. Cost impact is evaluated against the sum of the applicable WBS item baseline costs to determine the worst case value as a percentage. 2. The identified schedule impact is evaluated against the applicable WBS activity durations to establish the worst case schedule impact as a percentage. 3. The probability of occurrence in PMCS defaults to the top of the expected probability range. 4. Each risk is assigned a best case percentage based on three types of risks as described in Table 3.3-2. Table 3.3-2: Definitions of the best case for the three types of LSST risks Risk Type Definition Best Case Assignment 1) Negative impact Event The risk identifies an event that can only have negative impact. There is no better case than the baseline most likely. 100% 2) Positive or Negative Event This risk is for an event that can have a positive or negative impact. For example a large shift in currency rates can go both negative and positive. Best Case = -1*Worst Case 3) Uncertain outcome event This risk type identifies an event that will cause a delay or higher cost. The outcome of these risks can be positive, but since the main deliverable is still necessary, the best case is set at 10% of the worst case. Best Case = -10% * Worst Case This method takes a conservative approach by assigning the high end of the range for the default probability of occurrence. This approach also uses subjective judgement on the third risk type in assigning the best case at 10% of the worst case. This was based on an evaluation of seven such risks in the top 50 in the Risk Register and an assessment of how those risk events could occur. The defined approach for determining a "best case" introduces opportunity into the evaluation. Going forward, LSST has extended the Scope Options (LPM-72) document to include opportunities, and LSST is committed to enhancing the Risk Register, currently focused on negative events, to accept opportunities as a type of event. 3.4 Correlations An important element for a probabilistic analysis of the baseline program plan is to identify correlations that should be considered in the Monte Carlo simulation of the integrated program plan. The Risk Management Module uses a Risk Factor Matrix with WBS assignments that serves to integrate specific risk elements as discussed in Section 3.3. When these elements are applied to multiple activities, they The contents of this document are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. 6 Contingency Management Plan LPM-61 Latest Revision 6/4/2015 are correlated to have the same event-based impact in the simulation. Therefore the risk factors have an implicit correlation of all WBS elements that are assigned the same risk factor. Development of the LSST contingency includes a determination of correlations that exist in the program, an evaluation to determine if they have already been covered through existing Risk Factors, and then the entry of any customized correlations that are appropriate. 4 Contingency Management The Project Manager has direct responsibility for management (allocation, tracking and reporting) of the contingency budget and schedule, and for the re-planning of approved scope modifications. All such changes are coordinated with the Director. The LSST Change Control Process (LPM-19) is the primary process to manage changes, as it will consider and recommend disposition of requests for changes to system-level designs and interfaces, system scope, as well as proposed draw-downs on project contingency, schedule float, and/or technical reserves. All such changes, even those within the authority of the Director and Project Manager, are administered through the Change Control Board (CCB) webbased workflow (https://www.lsstcorp.org/groups/ccb) to involve the senior managers and scientists in the re-working of the plan. The change control process is used to establish the work flow and gates for proposed changes, impact analyses, review, approvals, implementation and reporting. Tracking and reporting the use of budget and schedule contingencies is a key part of management. The Project Manager maintains a log of changes to the baseline PMCS plan to keep a constant record of the budget reserves, and the Earned Value Management System (EVMS) reporting provides a monthly upto-date accounting as described in the Project Controls System Management Plan (LPM-98). Although the total contingency was developed from individual activities and subsystem-defined risk items, contingency is NOT associated with a particular subsystem or WBS line item. No part of the project “owns contingency.” Contingency is reserved to deal with risks identified in the Risk & Opportunity Management Plan (LPM20) and Risk & Opportunity Registries (including the execution of risk mitigation activities) and events with unexpected outcomes during the project. Contingency is NOT used to expand the scientific or technical scope of the project beyond the baseline definition. All uses of contingency are recorded in a contingency log, which will be summarized in the LSST Monthly Earned Value Reports. 4.1 Approval Authority The approval to make changes in the LSST Approved Baseline, including project scope, scientific performance, cost and schedule is governed first by the terms and conditions of the Cooperative Service Agreement (CSA), which states: "..prior approval of the cognizant NSF Program Officer is required for: i. ii. Configuration changes increasing the overall program baselines for cost or schedule. Reallocation of funds among subawardees exceeding $250,000 at the Level 2 Work Breakdown Structure. The contents of this document are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. 7 Contingency Management Plan iii. LPM-61 Latest Revision 6/4/2015 Use of cost contingency exceeding $250,000 and/or use of schedule contingency to increase milestones for 30 days or more as referenced in the proposal for construction." All changes requiring the NSF Program Officer’s approval are submitted through the form attached in Appendix B. This form is derived from the CCB process, providing the description of the change and the impacts on budget, schedule, and technical performance. The consequences of the change request are also provided to convey the full nature of the change. The CCB workflow is held pending the positive response on the NSF approval. Table 4.1-1 summarizes the levels of authority required to approve each type of project contingency allocation. Table 4.1-1: Levels of authority required to approve allocation of contingency resources Technical/Scope Budget Schedule Notification Level NSF/JOG/Director Changes in overall science deliverables, Project Scope, Greater than $250,000 for Allocations of contingency and re-distribution of budget between Level 2 WBS Changes greater than 30 days for Level 1 Milestones All allocations of any contingency via the contingency log Project Manager Changes w/out net impact on science deliverables, schedule, or operations costs Allocations and redistribution budget less than $250,000 All changes to Level 2 Milestones but no effect on Level 1 Milestones All changes in baseline LSST Subsystem Managers Changes not affecting subsystem performance or requirements Changes to baseline budget less than $10K and less than 25% of original estimate Changes that delay Level 3 Milestones only without impacting any Level 2 Milestones Changes strictly internal to subsystem Oversight, enforcement, and recording of allocation processes is the responsibility of the Project Manager but is supported by all LSST team members. In certain cases, responsibility for the management of contingency is delegated to the level of management that is consistent with the scope of the requested change. In the course of normal project execution, changes to the WBS budget items may be required in response to non-configuration changes, such as revised vendor quotes, changing economic conditions, commodity price fluctuations, etc. In these cases, the appropriate subsystem project manager(s) will prepare and submit a budget Change Request (CR) to the LSST Project Office explaining the change and requesting contingency funding. If the change is less than $25k in a single WBS element in a single month, the change will be automatically approved and recorded in the contingency log. If the change exceeds $25k or 25% of the original estimate for the item, the change must be approved according to The contents of this document are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. 8 Contingency Management Plan LPM-61 Latest Revision 6/4/2015 the authorization procedure presented in Table 4.1-1. The NSF Program Officer will be informed of all changes in the baseline and contingency allocations via the contingency log reported monthly. The Level 1 milestones for the Project are provided in Table 4.1-2 with the initial date. Table 4.1-2: LSST Level 1 Milestones 4.2 Scope Changes The guiding rationale for proposed scope reductions is to minimize the impact of reductions in light of the LSST system requirements and also to avoid reductions to the construction budget at the expense of higher operating budgets. The scope for the construction of the LSST can be reduced in two The contents of this document are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. 9 Contingency Management Plan LPM-61 Latest Revision 6/4/2015 fundamentally different ways: 1) reductions in the technical and scientific scope or 2) reductions in engineering implementation. If large cuts to the construction budget are realized, Scope reduction is the most likely pathway. The LSST data products provide a metric for evaluation of the impact of scientific scope reductions. Scientific scope reductions for LSST can either reduce the quantity or quality of data products. Other scope reductions to the breadth of the program exist, but the primary metric for evaluation is the scientific impact. The engineering pathway to scope reduction is to make adjustments to the system implementation that supports the project scientific and educational scope. Engineering changes may affect risks, data product quality (e.g. a reduction in resolution, precision, or availability), or they may reduce construction costs by increasing maintenance complexity (e.g. building cheaper infrastructure that will require more frequent or more costly maintenance). Other possible engineering scope options include the supply of spares. LSST has a Spare Parts and Consumables Policy (LSE-170) that provides the requirements for spare parts, but it is common to consider these requirements in the scope options list. LSST’s system requirements provide a framework for analysis of reductions in scientific scope that are specified in the SRD (LPM-17), the LSST System Requirements (LSR, LSE-29) and the Observatory System Requirements (OSS, LSE-30). 4.3 Opportunity Management An important element in contingency management is the identification of opportunities that allow cost and schedule contingencies to be "replenished" or performance levels to be increased. Like risk management, opportunity management entails early recognition, proactive planning, and aggressive execution of a plan that allows opportunities to materialize. The primary tool to manage opportunities is the scope options list in document LPM-72. This time-based list of both reductions in scope and opportunities to be realized, can be plotted to show evolution as time progresses. Future updates to the Risk Register will include the tracking of opportunities. The Risk process is already designed to be an active management tool that can be adapted to serve both positive and negative events equally. When that capability is in place, the contingency management plan will benefit from an active process to add to the contingency pools. 4.4 Contingency Assessment The management of contingency requires a decision methodology to allocate resources when risks are realized and a response must be executed. While there is no single established process to choosing from budget, schedule or scope contingencies, there are some processes in place to support the decisions. All contingency requests are handled through the change control process, and every request of contingency requires the author to indicate if a scope change is possible as a response. This provides the data to support the decision on allocation of scope, budget, or schedule contingencies if there are choices. The allocation of contingency is also based on the overall status of the project, the available authorized budgets, and the levels of contingency that remain. The Project Manager maintains a model of the The contents of this document are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. 10 Contingency Management Plan LPM-61 Latest Revision 6/4/2015 anticipated use of the budget contingency and strives to keep to that plan. Figure 4.4-1 is a model from the final design phase for LSST where the modelled use of contingency over time is directly related to the activity based development of the estimated contingency. This is shown in the light blue bars. The green bars show the budgeted availability of funds based on the baseline plan and baseline funding profile. The red line shows the actual level of budget contingency (in this example plot, everything is forecast and no contingency had been allocated.) This figure demonstrates the budget contingency evaluation that will continue based on real time status data and the need to stay above the green line. When the final contingency is approved, the working version of the chart will be produced and it will also include a "s" curve that would match a contingency usage profile that recognizes early use to deal with common issues with bid risks, holds tight to contingency in the middle years, and then recognizes that the integration, test, and commissioning period at the end of the project is also commonly a heavy user of contingency. Figure 4.4-1: Model of projected use of contingency over time for the LSST final design phase. 5 Reporting All uses of contingency represent a baseline change, and all occurrences, or allocation of contingency, is tracked and reported monthly. All contingency actions pass through the Change Control Process and approval steps. Those that are approved and implemented are then logged in Document-14547, and all activities are reported monthly using the format provided in Table 5-1. The contents of this document are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. 11 Contingency Management Plan LPM-61 Latest Revision 6/4/2015 Table 5-1: Change Requests with contingency impact chart from LSST's monthly report Change Control ID Description NSF Approval Date Risk ID WBS Allocation ($) Balance ($) Schedule Impact Contingency Balance List LCRs processed with Cost or schedule changes Pending LCRs with Potential PMCS Impact List pending LCRs with expected cost or schedule impact The overall status of remaining contingency, future liens on contingency, and all allocations and returns of contingency funds (as risks are realized or retired) is also reported monthly. To provide a monthly assessment of the cost contingency, this summary table will capture the specific contingency balance, as well as near term risk register items, i.e. known liens on contingency that are not yet processed through change control. The contents of this document are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. 12 Contingency Management Plan LPM-61 Latest Revision 6/4/2015 Appendix A: Activity Based Uncertainty Assessment (Excerpt from LPM-81 Section 10) The uncertainty associated with the plan is assessed for each activity based on technical, cost, and schedule factors. A complete set of standardized factors is assigned to each activity to support two types of contingency analysis. One is an algorithmic analysis programmed into the PMCS to provide a separate estimate for contingency summed from the activity levels. A second analysis uses these factors, combined with other risk assignments, to support a Monte Carlo assessment of the total Project cost and schedule risk exposure. This probabilistic assessment is further defined in the Contingency Management Plan but also uses the same uncertainty factors as some base inputs. The estimator is responsible for assigning the uncertainty factors and for documenting a summary basis for the scores in the "Basis of Risk" field of the database. Contingency estimates developed in both the algorithmic and probabilistic methodologies are never commingled with base costs (direct, indirect). The method for activity-based estimating of uncertainty is based on standardized scoring of technical, cost, and schedule factors. The factors lie on a roughly linear, numeric scale that corresponds to the rubrics defined in Table 10-1. The scale is qualitative and somewhat subjective, but practical; it has been used in the algorithmic method for contingency estimating in NSF and DOE projects such as LIGO and the U.S. part of the ATLAS detector for LHC. The same detailed assessment is used to develop the best, most likely, and worst case values for cost and duration needed for the integrated Monte Carlo contingency assessment. Table 10-1: Uncertainty Factors Factor Technical Uncertainty Cost Uncertainty Schedule Uncertainty 1 Existing design and off-theshelf hardware Off the shelf or catalog item Not used 2 Minor modifications to an existing design Vendor quote from established drawings No schedule impact on any other item 3 Extensive modifications to an existing design Vendor quote with some design sketches Not used 4 New design within established product line In-house estimate for item within current production line Delays completion of non-critical path subsystem item 6 New design different from established product line. Existing technology In-house estimate for item with minimal company experience but related to existing capabilities Not used 8 New design. Requires some R&D development but does not advance the state-of-the- In-house estimate for item with minimal company experience and minimal in-house capability Delays completion of critical path subsystem item The contents of this document are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. 13 Contingency Management Plan LPM-61 Latest Revision 6/4/2015 art 10 New design. Development of new technology which advances the state-of-the-art Top down estimate from analogous programs Not used 15 New design way beyond the current state-of-the-art Engineering judgment Not used Standard scoring ranges for these parameters are between 1 and 15 for technical or cost uncertainty, and between 2 and 8 for schedule uncertainty. For technical uncertainty, the lowest score (1) corresponds to commercial off-the-shelf items; the highest score (15) corresponds to components significantly beyond the current state-of-the-art. For cost uncertainty, the lowest score (1) corresponds to a vendor quote or catalog price; the highest score (15) corresponds to estimates where no data are available. Schedule uncertainty factors range between 2–8, where the low end corresponds to no schedule impact and the high end corresponds to delay on the critical path. Each uncertainty factor is multiplied by a risk-factor multiplier between 1–4 percent, corresponding to the rubrics in Table 10-2. The choice of multiplier depends on whether the risk is associated with technical, cost, or schedule concerns, and whether the uncertainty applies to design, manufacturing, materials cost, or labor rates. Table 10-2: Risk-Factor Multipliers Condition Technical Risk Cost Risk Risk-Factor Multiplier Design or manufacturing concerns only 2% Design and manufacturing concerns 4% Material cost or labor rate concern 1% Material and labor rate concern 2% Schedule Risk 1% Due to the high proportion of software in the LSST Data Management System, the above tables have been supplemented with ones more relevant to software systems and that table applied to the analysis for the DMS. The contents of this document are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. 14 Contingency Management Plan LPM-61 Latest Revision 6/4/2015 Table 10-3: Uncertainty Factors for Software-intensive projects Factor Technical Uncertainty Cost Uncertainty Schedule Uncertainty 1 Copy of existing implementation using offthe-shelf software Off the shelf or catalog item NA 2 Minor modifications to an existing implementation Prototyped, straightforward implementation No schedule impact on any other item 3 Extensive modifications to an existing implementation NA NA 4 New design similar to existing implementation Prototyped, some redesign required Delays completion of non-critical path subsystem item 6 New design different from existing implementation. Existing technology Module-based estimate, similar to previous work NA 8 New design. Requires some R&D development but does not advance the state-of-the-art Module-based estimate, new requirements Delays completion of critical path subsystem item 10 New design. Development of new technology which advances the state-ofthe-art Top down estimate from analogous programs NA 15 New design way beyond the current stateof-the-art Engineering judgment NA Table 10-4: Risk-Factor Multipliers Condition Technical Risk Cost Risk Risk-Factor Multiplier Design or implementation/deployment concerns only 2% Design and implementation/deployment concerns 4% Material cost or labor rate concern 1% Material and labor rate concern 2% Schedule Risk 1% The contents of this document are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. 15 Contingency Management Plan LPM-61 Latest Revision 6/4/2015 Appendix B: LSST Change Request Approval Form Change Title: ORIGINATOR: LCRORIGINATING SUBSYSTEM: CONTINGENCY REQUEST AMOUNT: DATE: SUBMITTED TO NSF DATE: SUMMARY DESCRIPTION DETAILED DESCRIPTION OF CHANGES APPROVALS CCB Action: Date: Notes: Project Approved By: Date: Notes: NSF Approved By: Date: Notes: IMPACT ANALYSIS TECHNICAL: WBS Change Amount COST: SCHEDULE: OTHER: DOCUMENTS/DESIGNS AFFECTED: IMPACT IF NOT APPROVED: NOTIFICATIONS REQUIRED (parties outside the workflow) The contents of this document are subject to configuration control and may not be changed, altered, or their provisions waived without prior approval. 16
© Copyright 2025 Paperzz