for immediate release - Summit County Engineer`s Office

ALAN BRUBAKER P.E., P.S.
_____________________________________________________________________________________________________________________________ _____
SUMMIT COUNTY ENGINEER
FOR IMMEDIATE RELEASE
July 29, 2017
Summit County Engineer’s Office
Contact: Heidi Swindell
Phone: 330 643-8170
http://summitengineer.net
Summit County Engineer’s office has summer road work planned
Akron, Ohio – Alan Brubaker, P.E., P.S., Summit County Engineer has finalized the summer road work
plans to take place in various locations around the County for 2011. Despite decreasing revenues, the
Summit County Engineer’s office has allocated $1.49 million for pavement maintenance in the Capital
Improvements Program this year, an increase of 24% over the 2010 pavement maintenance allocation.
This is due to cost saving administrative and personnel changes, allowing more room in the budget for
improving the County’s roads and bridges.
The Summit County Engineer’s office bid process was opened up to other communities in Summit
County. The larger purchasing power created by bidding for pavement maintenance items as one unit
had lead to a smaller per unit costs for all participants, while the municipalities still maintain local control
over the projects. The Summit County Engineer’s office will administer the County-wide program.
“Times are tough financially for local governments and the taxpayers,” said Engineer Brubaker. “As a
result we, as elected officials, must identify ways to cooperate to reduce the costs of services. It just
makes sense to develop this new collaboration among Summit County communities. A regional
approach can save money and promote efficiency in our road programs without reducing the level of
services. It's a win-win-win situation for the County, municipalities, and the townships.”
Many officials were involved in the creation of the County-wide program. The Summit County
Engineer’s office would like to thank Summit County Council, the Summit County Executive, and
participating officials from Bath, Copley, Coventry, Northfield Center, Sagamore Hills, Springfield, and
Twinsburg Townships as well as the cities of Akron and New Franklin and the village of Richfield.
“It has been my general philosophy to go back to the basics”, said Brubaker. “That means we reduced
overhead costs, cut unnecessary projects that would require us to borrow more money and instead live
within our means to perform our fundamental job function – maintenance and repair of County roads
and bridges”.
Please find below the upcoming projects in your area:
2011 Summit County 405 and 409 Resurfacing Program
Owner
Road
From
To
Summit County Engineer (405 and
409)
Boston Mills Rd.
Richfield Corp.
Line
Black Rd.
Summit County Engineer (409)
Columbia Rd.
Myersville Rd.
Minor Rd.
Black Rd.
Green Corp. Line
Medina Line Rd.
Riverview Rd.
Krumroy Rd.
Cleve-Massillon Rd.
Bath Township (405 and 409)
Lakeview Dr.
Knollwood Ln.
N. Revere
all
#2056
All
Bath Township (409)
Lakeview Dr.
Big Spruce Dr.
Harvest Dr.
Idlebrook Dr.
Woodhaven
Blvd.
Ranchwood
Spur
Rolling View Dr.
Tee Dr.
Retreat Dr.
Heather Hills rd.
Spring Crest Dr.
Bittersweet Rd.
Derrwood Dr.
Cliff Spur Dr.
Briar Hill Spur
Fox Chase Dr.
Green Dr.
Fairway Dr.
Montrose Ave
Clouse St.
#2056
all
all
all
Boltz Rd
All
All
All
all
All
all
all
all
all
all
all
all
all
all
all
all
all
all
all
all
All
All
All
All
All
All
All
All
All
All
All
All
All
All
All
Copley (409)
N. Plainview Rd.
SR 162
dead end.
Coventry Township (409)
Aqua
all
All
Carr
Dorwil
Dorwil Ct.
all
all
all
All
All
All
Dot Ct.
Durst
Edgepark
all
all
all
All
All
All
Heath
Hummel
N. Viona
all
all
all
All
All
All
Oak Grove
Peninsula
Rhine
S. Viona
UHL
Vaughn Trail
(part)
W. Willowview
Wrico
Springfield (405 and 409)
Klagges Blvd.
Fenn Rd.
Springfield (409)
Broadview Rd.
Canova
E. Pace
E. Willowview
Hohman
Hottle
Monte Vista
Overland
Parnell
Port
Wagoner
all
all
all
all
all
All
All
All
All
All
all
all
all
All
All
All
Monroe Falls
Ave.
Tallmadge Corp
Ln
Tallmadge Corp
Ln
Portage Lakes
Dr.
all
all
all
all
Canova
all
Canova
Canova
all
Fenn Rd.
dead end
dead end
Port
All
All
All
All
End
All
End
End
All
409 resurfacing is also known as Seal Coat or Chip Seal.
The contractor places an emulsion on the roadway, spreads gravel on top of the emulsion, compacts the stone
into the emulsion with a roller, and then sweeps the excess gravel from the road the same day and then again
after about a week.
409 is much less expensive than hot mix asphalt, prevents water from causing cracks and potholes in the
pavement, and increases tire traction.
405 resurfacing is also known as Motor Paving. The contractor uses a portable mixer on-site to prepare the
asphalt mixture, places it on the roadway, and then compacts it with a roller. 409 is then placed on top of the 405.
405 is less expensive than hot mix asphalt but is used in conjunction with 409 when the roadway crown or edges
need to be re-established. A further advantage is that 405 is more flexible than hot mix asphalt and can resist
small movements in the road base that would crack hot mix asphalt.
Lytle Construction is the contractor for this year’s combined 405/409 contract. This contract includes the Summit
County Engineer’s Office and Bath, Copley, Coventry, and Springfield Townships.
The value of this year’s contract is $830,784.50 and will be performed in August and September.
2011 Summit County 448 Resurfacing Program North
Owner
Road
From
To
Summit County Engineer
Bath Rd.
Old Mill Rd.
Revere Rd.
Revere Rd.
Twinsburg C.L.
Bath Rd.
Shade Rd.
Ravenna Rd.
Shade Rd.
Maple Leaf Hill
Reserve Dr.
Rain Tree Rd
Olentangy Dr.
all
all
all
all
all
all
All
All
Rainbow Lane
Logwood
Rusticwood
Timberwood
all
all
all
all
All
All
All
All
Willow Lake Dr.
Countryside Dr.
Edge Lake Oval
all
all
all
All
All
All
Bath Twp
Richfield Village
Sagamore Hills Twp
448 resurfacing is also known as Hot Mix Asphalt. The asphalt is prepared in an asphalt plant, transported to the
site in heated trucks, placed on the roadway in the desired thickness, and then compacted with a roller. 448 is
the most durable (and most expensive) asphalt pavement and resists cracking and rutting more than 405 and 409
resurfacing. It is used in locations that have heavy traffic and a high percentage of truck traffic.
Karvo Paving Company is the contractor for this year’s 448 contract in the northern half of Summit County. This
contract includes the Summit County Engineer’s Office and Bath, Richfield, and Sagamore Hills Townships.
The value of this year’s contract is $1,040,523.10 and will be performed in August, September, and October.
2011 Summit County 448 Resurfacing Program South
Owner
Road
From
To
Albrecht Rd.
Pickle Rd.
Edith
Green Corp. Line
Portage Line
Killian Rd.
W. Rhine
W. Pace
W. Olden
Cargo
Snow
Gable
E. Olden
all
all
all
all
all
all
all
all
all
all
all
all
all
all
Summity County Engineer
Coventry Twp.
Rome
all
all
Westview Dr.
Silver Ridge
Greensfield Ln
Westmount Dr.
Conestoga Tr.
all
all
all
all
all
all
all
all
all
all
Copley Twp
448 resurfacing is also known as Hot mix Asphalt. The asphalt is prepared in an asphalt plant, transported to the
site in heated trucks, placed on the roadway in the desired thickness, and then compacted with a roller. 448 is
the most durable (and most expensive) asphalt pavement and resists cracking and rutting more then 405 and 409
resurfacing. It is used in locations that have heavy traffic and a high percentage of truck traffic.
Northstar Asphalt is the contractor for this year’s 448 contract in the southern half of Summit County. This
contract includes not only the Summit County Engineer’s Office, but also Coventry Township and Copley
Township.
The value of this year’s contract is $597,890.00 and will be performed in August, September, and October.
Akron-Peninsula Road Resurfacing
Akron-Peninsula Road will be improved this year from 1,200’ south of Truxell Road to Orchard St. in Village of
Peninsula. The existing road will be milled, pavement repairs will be performed, new asphalt will be placed, and
new pavement markings will be applied.
The Shelly Company is the contractor for this project.
The value of this contract is $453,252.65. This work is being funded 100% by federal funds.
The work is currently underway and should be complete by July 15, 2011.
Lockwood Road Resurfacing
Lockwood road from SR 619 to State Road will be improved this year. The existing road will be pulva-mixed.
This process grinds the existing pavement and then compacts it back in place to form a stable road base of
recycled from the original road material. Next, an intermediate course of 405 will be placed. This will allow the
crown of the road and proper cross slopes to be formed to ensure adequate road drainage. Finally, a surface
course of 409 will be applied and the lanes will be striped.
Lytle Construction is the contractor for this project. This contract is a joint effort by the County Engineer and the
City of Barberton.
The value of this contract is $191,440.50. SCE local funds will pay for 67% ($128,875.94) of the project and the
City of Barberton local funds will pay for the remaining 33% ($62,564.56) of the project and the work will be
performed in August and September.
Asphalt Rejuvenating
Owner
Road
From
To
Jacoby Rd.
Swartz Rd.
N. Turkeyfoot Rd.
Waterloo Rd.
Krumroy Rd.
Summit Rd.
Darnell Dr.
Vaughn Trail
Portage Line Rd.
SR 241
Ridgewood Rd.
800' w of Arlington
500' w of S. Main St.
SR 224
Pressler Rd.
Easr Ave
Edward Ave.
Tanglewood Dr.
12th St. SW
Lexington Ave.
Independence Av
Belden Ave.
Piedmont Ave.
Lawton St.
Noah Ave.
Greenwood Ave.
Lawton St.
Crosier St.
Quayle Dr.
16th St. SW
19th St. SW
Linden Ave.
Roscoe Ave.
East Ave.
Selzer Ave.
Shatto Ave.
Kenmore Blvd.
Cuyahaga Falls Ave.
De Valera St.
De Valera St.
Independence Ave.
Storer Ave
Stoner Ave.
Diagonal Rd..
Packard Dr.
Inman St.
Hilbish Ave.
Battles Ave.
Chester Ave.
Birchwood Ave.
Joy Ave.
Mallison Ave
Howard St.
N. Hawkins Ave.
Chester Ave.
Riverside Dr.
Home Ave.
Home Ave.
Annapolis Ave.
Diagonal Rd.
Slosson St.
Lawton St.
Storer Ave.
Talbot Ave.
Woodstock Rd.
Indian Tr.
Indian Tr.
Riverside Dr.
Bittaker
Arbour Green Dr.
Autumn Leaves
Mallard Pond Dr.
Darlington Dr.
Medina Line Rd.
West end cul-de-cac
Arbour Green Dr.
Arbour Green Dr.
North end cul-de-sac
East end cul-de-sak
Heatherleigh Dr.
Autumn Leaves Dr.
Anthony Lane
Bavaria Rd.
Boyle
Curry Lane
Harvard St.
Jane's Ct.
Lynne Dr.
Oak Meadow Dr.
Pine Trail
Pine Trail Cir.
Ruby
Spruce Lane
St. Mikala
Twinsburg Corp Ln
Macedonia Corp. Ln
Enterprise Pkwy
W. End (Cul-de-Sac)
Case
Oak Meadow Dr.
Twinsburg Rd.
S. End Round
Stow Rd.
Pine Trail
Harvard
Pine Trail
Adam Run
E. Dead End
Enterprise Pkwy
Highland Rd.
Trisch Cir.
Eton
E. End Round
Curry
Waynesboro
Spruce Lane
Spruce Lane
E. Dead End
Ravenna Rd.
E. End (Cul-de-Sac)
Summit County Engineer
City of Akron
Bath Township
Twinsburg Township
Trisch Cir.
Waynesboro
Wildel
Woodland Glen
Curry
Bradford Park
Twinsburg
Darrow Rd.
Wildel
Oak Meadow
Trisch Cir.
E. End Round
Asphalt Rejuvenating agent is applied to hot mix asphalt that was placed one or two years ago. The agent
restores flexibility and water resilience that the asphalt surface lost due to weathering and the passage of time.
Forty-five minutes after the rejuvenating agent is applied, sand is placed over the agent to absorb excess agent
and provide enhanced vehicle traction. One week later, the excess sand will be swept from the road surface.
Pavement Technology, Inc. is the contractor for this year’s Asphalt Rejuvenating This contract includes the
Summit County Engineer’s Office, City of Akron, and Bath and Twinsburg Townships.
The value of this year’s contract is $174,986.80 and will be performed in August, September, and October.
2011 Crack Sealing Program for Summit County
Owner
Road
From
To
Cleve-Massillon Rd.
Summit Rd.
Portage Lakes Dr.
State St.
Springside Dr.
Cleveland-Massillon Rd.
S.Turkeyfoot Rd.
SR 93
Ghent Rd.
Jacoby Rd.
S. Main St.
New Franklin Corp Line
Brittian Rd.
Bellevue Ave.
G. Washington Blvd.
Cramer Ave.
Springfield Center. Rd.
Wilbeth Rd.
Schocalog Rd.
Woodridge St.
Triplett Blvd.
Independence
Hawkins Ave.
Triplett Blvd.
Hoover Ave.
Wedgewood Dr.
I-77
Ridgewood Rd.
Winston St.
Arlington Rd.
Cuyahoga Falls Corp.
Hardesty Blvd.
Springfield Lake Blvd.
Hilbish Ave.
dead end east
Arlington Rd.
Covington Rd.
Hancock Ave.
Hilbish Ave.
Pin Oak Rd.
Aspenwood Rd.
Ridge Dr.
Willow Ln.
Stone Gate Blvd.
Shaw Ext.
Wye Rd.
Roberts Ridge
Charles Lane
Sandin Rd.
Woodhaven Blvd.
Pin Oak Rd.
Reserve Dr.
Ridge Dr.
Medina Line Rd.
Hametown Rd.
Cleve-Massillon Rd.
Ira Rd.
Roberts Ridge
Ranchwood Rd. Ext.
Cul-de-Sac
Cul-de-Sac
Cul-de-Sac
Stone Gate Blvd.
Cul-de-Sac
Cul-de-Sac
Cleve-Massillon Rd.
Cul-de-Sac
Cul-de-Sac
Shaw Rd. Extention
Summit County
Engineer
City of Akron
Bath Twp
Robinwood Hills Dr.
Inner Circle Dr.
Candlewood Ln.
Arbour Green Dr.
Autumn Leaves Dr.
Mallard Pond Dr.
Darlington Dr.
Shaw Rd.
Robinwood Hills Dr.
Ira Rd.
Medina Line Rd.
west Cul-de-Sac
Arbour Green Dr.
Arbour Green Dr.
Robinwood Hills Dr.
Cul-de-Sac
Cul-de-Sac
Cul-de-Sac
east Cul-de-Sac
Heatherleigh Dr.
Autumn Leaves Dr.
Fairington Ave.
Remmington Ave.
Wilshire Dr.
Maralroy Way
Ansley Court
Quincy Dr.
Shillings Way
Devereux Dr.
Greensfield Lane
Greensfield Cir.
Ridgewood Rd.
Fairington Ave.
Medina Line Rd.
Remmington Ave.
Wilshire Dr.
Shillings Way
all
all
Westview Dr.
Greensfield Lane
Remmington Ave.
Cul-de-Sac
Remmington Ave
Dead end
Cul-de-Sac
Cul-de-Sac
All
All
both Cul-de-Sacs.
Cul-de-Sac.
Anchor Lane
Barry Lane
Beacon Hill Blvd
Brookfield Ln.
Brookgate Way
Brookhaven Ct
Brookledge Ct
Brookline Ct.
Brookpointe Circle
Brookrun Ct.
Brookside Ln.
Brookwood Ct.
Buoy Ct.
Charlton Circle
Charter Dr.
Country View Pkwy.
Crestwood Ln.
Dory Dr.
East Oakmont Way
Fairhaven Dr.
Fantail Dr.
Foghorn Ln.
French St. (off Aurora)
French St. (off Sp Crk)
Golden Link Blvd.
Hazel Dr.
Hill Ct.
Twinsburg Rd.
Olde 8 Rd.
Brandywine Rd.
Meadow Brooke Way
Twinsburg Rd.
Meadow Brooke Way
Brookgate Way
Meadow Brooke Way
Brookfield Lane
Brookside Lane
Brookfield Lane
Brookgate Way
Charter Dr.
Bayberry Dr.
Olde 8 Rd.
Twinsburg Rd.
Morningside Dr.
Scupper Lane
Skyhaven Rd.
Olde 8 Rd.
all
Schooner Lane
SR 82
Springcreek
SR 82
SR 82
Meadow Brooke Way
Scupper Lane
Kathy Lane
Dorwick Dr.
Cul-de-Sac
Cul-de-Sac
Cul-de-Sac
Cul-de-Sac
Cul-de-Sac
Cul-de-Sac
Cul-de-Sac
Dead end
Cul-de-Sac
Cul-de-Sac
Cul-de-Sac
Anchor Lane
Joey Lane
Dead end
Cul-de-Sac
Cul-de-Sac
Morningside Dr.
All
Scupper Lane
Dead end
Dead end
Macedonia Corp Line
dead end
Cul-de-Sac
Copley Twp
Northfield Center
Karen Ln.
Kathy Ln.
Kenwick Dr.
Laurie Ln.
Ledgemont Rd.
Litehouse Trail
Lowell Ln.
Lucy Ln.
Meadow Brooke Way
Morningside Dr.
Natalie Blvd.
North Oakmont Dr.
Northfield Ave.
Oakmont Dr.
Outrigger Ln.
Oviatt Dr.
Pebble Brooke Court
Pin Oak Circle
Pleasantview Dr.
Rolling Brooke Way
Schoepf Rd.
Schooner Ln.
Scupper Ln.
Skyhaven Rd.
Skylane Dr.
South Oakmont Rd.
Springcreek Rd.
Surry
Vesta Ave.
Olde 8 Rd.
south Cul-de-Sac
Lowell Lane
Barry Lane
Skyhaven Rd.
Olde 8 Rd.
Beacon Hill Blvd.
Olde 8 Rd.
all
Fairhaven Rd.
Springcreek
Oakmont Rd.
Olde 8 Rd.
Olde 8 Rd.
Anchor Lane
Olde 8 Rd.
Brookside Lane
Olde 8 Rd.
Highland Rd.
Meadow Brooke Way
from hill to the north
Foghorn
Foghorn
E. Oakmont Way
Pleasantview Dr.
Oakmont Rd.
Sagamore Twp. Line
Morningside Dr.
Northfield Ave.
Kathy Lane
dead end
Dorwick Dr.
Kathy Lane
dead end
Foghorn Lane
Marwyck Dr.
dead end
All
dead end
Cul-de-Sac
Cul-de-Sac
dead end
N. Oakmont Rd.
Fantail Dr.
Shady Lane
Cul-de-Sac
Cul-de-Sac
Beacon Hill Blvd.
Cul-de-Sac
Cul-de-Sac
Anchor Lane
Anchor Lane
N. Oakmont Rd.
Cul-de-Sac
E. Oakmont Way
Cul-de-Sac
Brandywine Rd.
SR 82
Adam Run
Anthony Lane
Bavaria Rd.
Boyle Pkwy.
Bradford Park
Buchtel
Case
Curry
Darien
Enterprise Pkwy
Estate
Eton
Evans Way
Hadden
Harvard
Isabel
Jane's Ct.
Katz
Twinsburg Corp. Limit
Twinsburg Corp. Limit
Macedonia Corp. Limit
Enterprise Pkwy.
Waynesboro
Harvard
Harvard
W End (Cul-de-Sac)
Evans Way
W. Dead End
SE End (Cul-de-Sac)
Harvard
Adam Run
Highland
Case
Marwell
Oak Meadow
W. Dead End
Evans Way
E. Dead End
Enterprise Pkwy
Highland Rd
N. End Round
Hadden
Yale
Trisch
Twinsburg Corp. Limit
Twinsburg Corp. Limit
Twinsburg Rd..
Hadden
Liberty
Twinsburg Corp. Limit
Eton
Twinsburg
E. End Round
Lynne
Twinsburg Twp.
Lynne Dr.
Marwell
McCausland
Myrna
Oak Meadow
Pam Ct.
Park Ridge
Pine Trails
Pine Trails Cir.
Ridgetop
Ruby
Sara Fletcher Ct.
Spruce
St. Mikala Ct.
Timber
Trisch Cir.
Wayneboro
Wildel
Woodland Glade
Twinsburg
Estate
SE End (Cul-de-Sac)
Marwell
S. End Round
S. End (Cul-de-Sac)
Ridgetop
Stow
Pine Trail
Twinsburg
Havard
S. End Round
Pine Trail
Adam Run
Marwell
Curry
Twinsburg
Twinsburg
Darrow
Curry
Darrow
N. End Round
Twinsburg
Waynesboro
Evans Way
E. End (Cul-de-Sac)
Spruce
Spruce
N. End (Cul-de-Sac)
E. Dead End.
Estate
Ravenna
E. End (Cul-de-Sac)
Twinsburg
Curry
McCausland
Trisch Cir.
E End Round
Crack Sealing is used to close small cracks in hot mix asphalt roads. This prevents water from entering the
pavement and causing pot holes or damaging the road base.
The engineer’s estimate for this year’s contract is $245,810.00 and bids will be opened on July 6, 2011. This
project involves the County Engineer, the City of Akron, and Bath, Copley, Northfield, and Twinsburg Townships.
The work will be performed in September, and October.
2011 Summit County Spot Paving Program
Owner
Road
From
To
S. Main St. (center lanes only)
Quick Rd.
Cleveland-Massillon
Medina Line (various locations)
Everett Rd. Bridge deck
Graybill Rd. Bridge deck
Reimer Rd. bridge deck
Warner Rd.
Top of hill
Turn Lane at Lowes
SR 18
over Riding Run
over Heckman Ditch
over Van Hyning
Mallard Point
to 2000' east
Curry Lane
Darien Lane
Evans Way
Pam Ct.
Park Ridge Ave.
Ridgetop Dr.
Widel Dr.
At 1815 Curry Lane
As Marked out
At 3151 and 3161 Evan Way
At 9465 and 9473 Pam Ct.
At 7893 Park Ridge Ave.
At 1466, 1477, 7845, 7855
At Twinsburg Rd.
Summit County Engr
Twinsburg Twp
SR 303
The Spot Paving Program addresses pavement deterioration that is more extensive than a pothole but still does
not require complete resurfacing. Additionally, this contract is used to resurface bridge decks.
Karvo Paving Co. is the contractor for this year’s Spot Paving Program. This contract includes the Summit
County Engineer’s Office and Twinsburg Township.
The value of this year’s contract is $185,825.00 and will be performed in August, and September. Pavement
Technology, Inc. is the contractor for this year’s Asphalt Rejuvenating This contract includes the Summit County
Engineer’s Office, Bath Township, Twinsburg Township, and the City of Akron.
2011 Summit County Pavement Marking Program
The Pavement Marking Program involves applying new centerline and edge lines to roads as required.
J.D. Striping & Services, Inc. is the contractor for this year’s Pavement Marking Program. This contract includes
the Summit County Engineer’s Office and Copley, Sagamore Hills, and Twinsburg Townships. The City of New
Franklin has also expressed interest on joining this program and will be added to the contract as a change order.
The value of this year’s contract is $81,173.40 and will be performed in September and October.
Northampton Road Bridge Replacement
This project removes and replaces the Northampton Road Bridge over Mud Brook located in the City of Cuyahoga
Falls. The existing bridge was built in 1930 and is nearing the end of its useful life.
Workman Industrial Services is the contractor for this project.
The value of this contract is $542,415.80 and will be performed in August, September and October. 80%
($433,932.64) of the cost of the project is federally funded and the remaining 20% ($108,483.16) of the project is
funded by local Summit County Engineer funds.
The bridge will be closed for approximately 60 days and traffic will be detoured.
Twinsburg Road Culvert (SCE)
This project replaces the road culvert under Twinsburg Road between Brandywine Road and Schoepf Drive in
Northfield Center Township.
This office is currently in the process of selecting a contractor.
The Engineer’s Estimate for this work is $21,976.55. We anticipate that the work will be performed in September.
The contractor has the option of closing the road and detouring traffic for up to 60 consecutive hours.
2011 SCE Culvert Replacement Program
This project is in the final stages of design. The following culverts are under consideration for replacement this
year:
- Culvert under Cottage Grove Road between Klinger and Cope in Coventry Township
- Culvert under Boyden Road just north of Barton Road in Sagamore Hills Township
- Culvert under Boyden Road just north of Barton Road in Sagamore Hills Township
- Culvert under Medina Line Road just south of SR 303 in Richfield Township
The value of this work is estimated to be $120,000.00 and the work should be performed in October and
November.
(NOTE: Unless otherwise stated, traffic will be maintained and 100% local funds (SCE/Townships/Cities) will be
used for each project listed above.)