guidelines for construction of play ground in integrated

GUIDELINES FOR CONSTRUCTION OF PLAY GROUND IN INTEGRATED ACTION PLAN DISTRCITS
AS IDENTIFIED BY GOVERNMENT OF INDIA
1. PARAMETERS:
i) Not more than one play ground in one village,
ii) The play ground will be for the games/ sports, such as football, volleyball, hockey,
kabbadi etc. and the size of play ground should be constructed accordingly.
iii) The play ground will be fenced by constructing ditch cum bund with plantation on ditch/
bund
2. NON-NEGOTIABLES IN WORK EXECUTION:
The construction of play grounds will be subject to all MAHATMA GANDHI NREGA processes
and conditionalities, such asi) Muster Rolls to be maintained on worksite, with copies in Gram Panchayat and to be
electronically maintained on nrega.nic.in,
ii) Social Audits to be done through Gram Sabhas,
iii) Wage payments will be through banks/ post office accounts.
iv) No contractor and machine will be deployed.
3. CONFORMITY TO MAHATMA GANDHI NREGA PROCESSES IN PLANNING AND EXECUTION:
i) Works for play grounds shall be approved by the Gram Sabha and the Gram Panchayat and
shall also be part of the annual shelf of projects identified under MAHATMA GANDHI NREGS.
ii)
The Administrative & Financial sanction for the
play grounds to be constructed under MAHATMA GANDHI NREGS will follow the process
defined for MGNREGA works.
4. ESTIMATES:
i) After approval of works by the Gram Panchayat, the concerned Technical Assistant/ Junior
Engineer of the Gram Panchayat will prepare estimate of the work as per drawing/ design/
specification of the play ground and prevailing SOR for MAHATMA GANDHI NREGA works in the
area.
1
ii) In leveling of the play ground the estimates will be prepared by working out cutting and
filling, so that the cutting is equal to filling. In estimate only the cutting will be charged if
filling is within the maximum lead permitted in the SOR, if filling is beyond the permitted
lead, only than for lead, extra will be charged.
iii) The TS for these works will be issued by the concerned as per norms/ power delegated for
MGNREGA works.
5. EXECUTION:
i) For construction of play ground, the concerned GP will be the Implementing Agency.
ii) Every play ground constructed will be treated as independent work. The PO will issue muster
roll to the GP accordingly.
ii) Mate will be deployed only if the quantum of other works taken up in the Panchayat justifies
their need.
iii) The measurement/ assessment of the work carried out will be made weekly and after the
work is completed, as per the task / activities specified in the estimate by the concerned J.En.
/TA. The entries of measurement with assessment of work will be entered in measurement
book as well in the muster roll.
iv) Maintenance of the play ground and its proper use will be the responsibility of the Gram
Panchayat.
6. MONITORING AND REPORT:
Progress and quality of play grounds under MAHATMA GANDHI NREGS shall be the
responsibility of the District Programme Coordinator (DPC).
2