/w EPDw UKMTE4 ed 16774186 Week 7: Trade-Offs, Change Management, and Project Closure - Discussion Change Management (graded) Change continually happens during a project as you learn more information and make adjustments. Some changes have small impacts and can be easily worked around without much effort. However, what happens when the proposed change affects the project's scope? Discuss change requests and what kinds of questions you would have for the customer if he/she requested a change to the project scope. What are the possible implications of this change request? Responses Response Author 312487156,31143 309525139 Project Scope Change Control Date/Time 0 4/8/2012 8:23:27 AM Professor Firestone Class, scope change control is key to keeping your projects on time and within budget. You'll have a great understanding of how we can do this after this week's discussion. So dig in. 312487156 RE: Project Scope Change Control 309525139 Summers Love-Morrison 4/14/2012 7:36:06 PM I think that inorder to control scope change you must maintain some kind of consistency throughout the entire project. TO be honest Scope change may be considered a little risky if done at the wrong time. When making tremendous changes like this, one must ensure that it has been thoroughly reviewed. 311433658 RE: Project Scope Change Control 309525139 Kathryn Martinez 4/12/2012 7:31:58 AM To control scope change you must be consistent on what you work at because if not through experience things get forgotten and you let go they get pilled up and your work load is heavier than what you expected. When your project is put together and you know what you want it is easier for you to get through your projects. From personal experience when I started a diet plan for myself when choosing the right products and advice my husband and I went to the bookstore to find information on how to loose weight. We found the book we wanted to use and created a plan to get ourselves through. The best way is creating a plan and sticking to it, things will get you side tracked and pull you away from your goals but making a consistent schedule helps you keep things in perspective. 311305425 RE: Project Scope Change Control 309525139 4/11/2012 8:57:54 PM Kevin Shaw Scope change is always a risk in a project. The project mananger should try to prevent scope change when ever possible, but when it does occur the project mager should keep the sponsor and customer well informed on what will happen to the project if the change does occur. 311057917,31131 310975561 RE: Project Scope Change Control 309525139 4/11/2012 5:41:04 AM Shadina Pennybaker Scope change shouldn't be tolerated at all, because as soon as you let it happen once it may happen again. If you give some one a inch they'll take a mile, in other words, if you let someone get away with something once they'll try it again. 311314899,31147 311057917 310975561 RE: Project Scope Change Control Derek Cavanaugh 4/11/2012 11:18:10 AM Scope change is something that a PM will have to deal with in almost every project they are associated with. It is a matter of business and it isn't something that can be controlled from the beginning of the project in the contract. It is something that needs to be able to be handled with care and a good PM should be able to handle what the customer wants. If the customer does want something that would completely change a project then the PM has to also be able to communicate that to the customer and be able to let them know what will be involved and if it is even possible during the project. 311476542,31168 311314899 311057917 RE: Project Scope Change Control Mercedes Santana 4/11/2012 9:13:15 PM Derek, I agree that the scope change is inevitable in almost every project. The changes can be big or small and the PM should be able to handle it in the best possible way. Always keeping the Customers needs as a priority. Scope changes can affect cost, time, or staff to name a few. 311686301,31177 311476542 311314899 RE: Project Scope Change Control Sindy Guerra 4/12/2012 9:55:09 AM Yes, the whole idea of change management is to be able to handle all the changes as best as possible. It is interesting that you said that we must keep the customers needs as a priority. And I agree with that, but as I was reading in the book The Complete Idiots Guide to : Project Management 2nd Ed, it states that "projects often change direction, shape or size. Goals, Budget. Schedule. Work plan. Priorities. Personnel. Any or all of these can change during the life of a project" (pg. 295). The customers contract us as Pms in or der to manage their projects because they do not know how to. Although they are our priority, we must keep everything else in balance or else our project can crash. Communication is always key. 311777465,31195 311686301 311476542 RE: Project Scope Change Mercedes Santana 4/12/2012 6:46:17 PM Control You are right Cindy, they hire us to get because we are capable of executing the project as they have envisioned. We are there to run the project from beginning to end to bring to life a project they may have just had an idea of what it could be. communication is definitely key in all parts of the working project in order to not loose time, money, or resources. 311950977 311777465 311686301 RE: Project Scope Change Control 4/12/2012 9:03:06 PM Shadina Pennybaker I understand change is inevitable, but there isn't a possible way to change any of the constraints without effecting any of the others. Mercedes I don't understand how communication would stop a project from losing any money, time or resources? 311950977 311777465 RE: Project Scope Change Control 4/13/2012 10:08:47 AM Sindy Guerra Shadina, what I have understood from the previous courses I have taken and many of the readings is that we have to envision the three contraints like a triangle. Ideally, they should be balance and each one should be able to have its maximum effect on a project so it can succeed. That is the way we plan all our porjects, but in reality, we know that as the project takes on its toll, we have to make decisions that will inevitably affect one of these constraints. Especially if there is change. When we have to make a change, it is because it is not going the way we planned, and one if not all of these constraints are on top of us. many times we will choose time over scope or cost over time, and so on. It all depends on what goals we have for the project and what is the best option. 311091193 RE: Project Scope Change Control 309525139 Albert Wells 4/11/2012 12:58:17 PM My understanding that scope change occurs when we have the customer, rather they be internal or external, request a change of features usually adding more to the project. This has to be controlled because the larger the scop the larger the project the larger the project the greater the budget. I think when it comes to scope control it really comes down to solid communication with your client. Changing the scope of a project is not bad in my opinion. That being said it needs to be understood by the project team and the client that changing the scope changes the project budget and timeline. If this is understood and compensated for then everything is positive, however the problem is usually wanting additional features with out the expenditure of additional resources. 310931315 RE: Project Scope Change Control 309525139 Aaron Downing 4/10/2012 10:39:13 PM Scope change will most likely occur when the customer requests that something be added to the original plan. It is probably a luxury to actually be able to reduce the scope to cut costs, but either of these situations will lead to change management issues. The customer is of course who you the company is trying to please but from a PM perspective, you also have to balance that with pleasing upper management which means the project better make a profit or it better lead to more business if it doesn't. 310940546 RE: Project Scope Change Control 309525139 Herbert Anderson 4/10/2012 11:06:06 PM Wow, very risky may I add. Scope change has the purpose to modify the project cost and schedule; the main focus of scope change is quantity change and support service change. In any case of the project being added to or change would casus the unknown risk and is often hard to manage. I feel this scope change should be done only in any warning case, such as unknown events like the whether. 310476415 310289532 RE: Project Scope Change Control 309525139 Nazish Raja 4/9/2012 7:08:01 PM Budget’s creating: Project Management costs Subcontractor costs Outsourcing costs Cost of communication Costs of hardware Cost of facilities and utilities, etc. Travel costs Cost of quality Risk contingency http://forwardmomentum.net/blog/keeping-your-project-within-budget/ 310476415 310289532 RE: Project Scope Change Control Sanah Fatima 4/9/2012 11:10:01 PM Change management entails thoughtful planning and sensitive implementation, and above all, consultation with, and involvement of, the people affected by the changes. If you force change on people normally problems arise. Change must be realistic, achievable and measurable. These aspects are especially relevant to managing personal change. Before starting organizational change, ask yourself: What do we want to achieve with this change, why, and how will we know that the change has been achieved? Who is affected by this change, and how will they react to it? How much of this change can we achieve ourselves, and what parts of the change do we need help with? These aspects also relate strongly to the management of personal as well as organizational change. 310359636 RE: Project Scope Change Control 309525139 Sharon Jno-Baptiste Griffin 4/9/2012 8:29:35 PM Scope change is where a request is considered to change the agreed scope and objectives of the project to accommodate a need not originally defined to be part of the project and change control is the management process for requesting reviewing, approving, carrying out and controlling changes to the project's deliverables. Change Control is usually applied once the first version of a deliverable has been completed and agreed. Scope change control would be the request reviewing, approving, and carrying out and controlling changes to the project scope. http://www.epmbook.com/scope.htm 310021785 RE: Project Scope Change Control 309525139 John Sebastien 4/9/2012 9:47:39 AM Project Managers must consider that the scope change has to be in-line with the strategic objectives of the organization undertaking that project and any future changes required to be brought up in the scope must always follow this basic principle. The moment you feel the scope is not in-line with the organizational objectives, the usefulness of project seizes to exist and such projects should either be immediately closed or their scope re-aligned with the strategic objectives of the organization. A change control system will include the following: • Recognizing that a change is needed • Reviewing all requested changes • Ensuring that any change is beneficial • Evaluating the benefits of the requested change • Identifying alternatives that would achieve the same result • Identifying all impacted tasks • Analyzing these impacts and how they affect project performance in terms of time, money and scope • Approving or rejecting the request • Communicating the approved changes to all stakeholders • Changing the baselines for performance monitoring • Updating the project scope definition • Implementing the change • Documenting the change http://www.contactpakistan.com/Communitylibrary/PDFs/article0519_ScopeChangeManagement. pdf 310743011 310049515 RE: Project Scope Change Control 309525139 Frederick Rock 4/9/2012 10:59:05 AM Change orders exists because there are additions that need to be reckoned with in terms of cost and time. Some reasons for Change Orders are: Design changes, unforeseen conditions, and Material Substitutions. 310743011 310049515 RE: Project Scope Change Control Echo Woolf 4/10/2012 5:02:12 PM Change management is necessary because the project never goes as planned. The customer will most likely change their mind throughout the project and the project team may encounter issues resulting in changes that need to be made. The reason this information is logged, besides needing to have historical data, is to hold those accountable. Thus, it serves as a point of reference. Rather than have a "he said, she said" battle, the log can be referred to of the changes that were made, when those changes were approved and who approved them. This way there is no question. Going back to these records becoming historical data; future projects may refer back to this log to see some of things that were done on projects. If it was successful, they may use the changes again. On the other hand, if they aren’t so successful the project team will know what changes to avoid. 309785120,31041 309689765 RE: Project Scope Change Control 309525139 Joseph Allen 4/8/2012 5:18:06 PM Change control is important to the project, change will occur in a project and it is important to have a good process. In my organization we use "change orders". These change orders may be submitted to the customer for approval or used only internally to track changes. Any deviation in scope, schedule or time is documented and typically signed off on by the project manager and the customer. The change order is then distributed through the organization so that it is clear the changes that are made and each department can contribute to how this will affect their portion of the project if they had not been consulted prior to the change. The customer signs off on the change order so that they are clear in the change and how it will affect the project. It isn't a perfect system, but it is a process that informs all of the stakeholders involved. 310415638 309785120 309689765 RE: Project Scope Change Control Miriam Hassan 4/8/2012 7:57:10 PM In my experience I have found change orders to be a very effect tool when implementing changes into the schedule, whether internally or at the request of the customer. Changes to any work scope are inevitable and at times not feasible, however, when a customer is adamantly requesting a change it is in the best interest of the Project Manager to give it some attention. Researching and analyzing the impact the change will have and providing documentation to the customer is essential. To protect him/herself and the company, change order clauses should be implemented as part of the contract. At times when changes are not feasible, the mere presentation of additional costs and impact on the schedule are sufficient in deterring customers from insisting on too many changes/additions to the original plan. 310415638 309785120 RE: Project Scope Change Control David Page 4/9/2012 9:34:20 PM I agree I like the idea of change orders as this is very informative to everyone and allows for all the correct people to be informed. Should the customer try to implement changes in the scope then it is worthwhile for the PM to evaluate the change request and if there are implications to the existing project then the PM has the ability to rework the budget, schedule and performance based on the customers support and eliminate some of the issues that may be presented due to these changes. However, if these changes come from internal to the project then the PM has the time to re-evaluate the request and make a well informed decision based on the information at hand. Losing control of the scope can and more than likely will cause larger issues for the project. 310421427,31052 309572574 RE: Project Scope Change Control 309525139 John Sebastien 4/8/2012 11:26:22 AM Changes in the initial project scope can negatively impact the overall success of project, which can eventually lead to project failure. However, if a change becomes necessary, they must stick within the project’s timeframe and budget. Also, the PM must set a clear change control process that the team and the stakeholder undoubtedly understand. The entire team must be aware of who is responsible or accountable for these changes, which can be done during project progress meetings. However, since the scope is subjected to changes during the project execution, every effort must be made to maintain flexibility in the WBS. 310522735,31121 310421427 309572574 Project Request/Change Control Log Professor Firestone 4/9/2012 9:41:30 PM Everyone, let's look a deeper look at a very important 'component' to help manage changes: the change request/control log. A Change Control Log is used to track the status of all of the individual Change Requests. What are some tracking items you would expect to see on the Change Control Log? 311219323,31076 310522735 310421427 RE: Project Scope Change Control Melissa Burr 4/10/2012 5:09:52 AM Any changes that impact the project or are requested by either the PM or other senior leaders of the project would put this request in this log. This is a great way to track requests and check on status of them throughout the project. 311219323 310522735 RE: Project Request/Change Control Log Sanah Fatima 4/11/2012 6:36:49 PM Melissa, In addition to your post, as per our book, The most important responsibilities of a project manager are planning, integrating, and executing plans. Almost all projects, because of their relatively short duration and often prioritized control of resources, require formal, detailed planning. The integration of the planning activities is necessary because each functional unit may develop its own planning documentation with little regard for other functional units The last three elements require further explanation. Very few projects are completed within the original scope of the project. Scope changes are inevitable and have the potential to destroy not only the morale on a project, but the entire project. Scope changes must be held to a minimum and those that are required must be approved by both the project manager and the customer/user. (Kerzner, Harold. Project Management: A Systems Approach to Planning, Scheduling, and Controlling, 10th Edition. John Wiley & Sons (P&T), 4/13/09. pp. 411 - 412). <vbk:9780470885932#outline(11.1)> 310765652 310522735 RE: Project Request/Change Control Log David Page 4/10/2012 5:51:44 PM The log should cover the request number, description, the requester, priority, request date, decisions, status, date implemented/canceled, and comments. The log is a way to track the changes and the history associated with those changes. This is a great thing to keep for records and as end of project records for reference for future projects. 311114110 310530386 310421427 RE: Project Scope Change Control Frederick Rock 4/10/2012 6:23:42 AM Some of the changes you could expect to see are: Current Status - to Identify what the status of the change is whether its work in progress, or open... Priority - Identify the level of importance of the change Change Request - Description of the change Assigned to owner - who is going to ensure it is accomplished expected completion date - When is it going to be completed Impact summary - what is the impact to the project. 311114110 310530386 RE: Project Request/Change Control Log Sharon Jno-Baptiste Griffin 4/11/2012 2:07:22 PM Frederick just to add that the log should also have the original Change Request form plus a statement of the current status and the ultimate outcome in terms of effect on schedule and budget. 312471437 310779224 310421427 RE: Project Scope Change Control Robyn Little 4/10/2012 6:19:00 PM Some tracking items would be costs, supplies available and needed, time schedules of past, present, and future planning, the amount of labor available in comparison to time needed for project completion. These could all impact the scope and add needed changes. I would expect to see all of these components updated and available on a control log. 312471437 310779224 RE: Project Request/Change Control Log Derek Cavanaugh 4/14/2012 6:59:39 PM Robyn, the tracking items you listed were great. When you mentioned the amount of labor available in comparison to time needed for project completion, I just wanted to say that this is something very critical to analyze because they will both impact the added financial resource needed to complete the project or manage the changes to the project. Because resources are the limiting factor, it is imperative to track those items in order to ensure that the benefit is maximized. 311435730,31076 310716399 310421427 RE: Project Scope Change Control 4/10/2012 3:56:49 PM Vanansio Samson Tracking individuals change request involves the followings: 1-Timesheets 2-Collation of information 3-Reporting 4-Meetings and communications If the plan was expressed as; phase, activities, and tasks, so too will the timesheets item. If it was expressed as deliverables, this will show the work against those deliverables. 311435730 310716399 RE: Project Request/Change Control Log Kathryn Martinez 4/12/2012 7:40:28 AM I didn't expect to see time sheets on the list but Vanansio this is a great list of items that can be used to track status. 310825077,31116 310760714 310716399 RE: Project Request/Change Control Log Miriam Hassan 4/10/2012 5:41:28 PM Melissa, Frederick and Vanansio - this is all true, however, shouldn't logging and documenting all aspects of the project as it progresses/or lacks progression be an normal part of the PM's responsibility? Logging the activities provides a safety net in the event something does wrong and the parties involved find themselves in court or at the table mitigating. Also should the project run beyond the schedule or overbudget the PM has the materials needed to provide a report to the owners and his bosses. 310825077 310760714 RE: Project Scope Change Control Sheila Williams 4/10/2012 7:35:51 PM The project control log is intended to assist the project manager keep track of key elements of the project. Some of the items expected on a change control log are: Actions: An action item may be needed to help clarify a task, resolve an issue, or address a potential risk. Issues: the project manger is often confronted with roadblocks that prevent effective delivery of the project. This worksheet can help track these barriers to success to ensure that a timely resolution is provided. Decisions: These decisions can relate to resolving problems, addressing priorities of requirements, or updating the schedule. Decisions are logged to help remind the project team of items in case they come up later in the project. Document Control: Project teams struggle to deal with massive amounts of information that are often housed in multiple sets of documents; this is intended to identify key documents on the project and where they are housed. Stakeholder List: keeping track of project team members and other stakeholders, http://philipdiab.com/freetemplates-2/intro/project-control-log/ 311162087 310760714 RE: Project Scope Change Control Vanansio Samson 4/11/2012 4:25:42 PM You are right Miriam, but remember, a typical change request can request a change to a number of project areas including requests to expand or reduce the scope of the project, requests to modify policies, procedures, plans, or processes, requests to modify expenditures, and requests to update of modify schedules. These are all the responsibilities of the project managers, it can be made internally or externally, directly or indirectly and formally via a written proposal, and cannot be implemented until they are formally approved. 311435357 310421427 RE: Project Scope Change Control Kathryn Martinez 4/12/2012 7:38:59 AM What I would expect to see in the Change control log would be a WBS with check points to make sure that all tasks assigned were completed. When you create a log to track your status it allows you to see your progress and achievements. 311977037 310421427 RE: Project Scope Change Control Shadina Pennybaker 4/13/2012 11:28:24 AM I would expect to see dollar amounts for these changes, I would expect to see times and dates for these changes, and when they were approved or disapproved. 313062832 312490005 310421427 RE: Project Scope Change Control Summers Love-Morrison 4/14/2012 7:42:28 PM The log should consist of the following: Description Request# Request Date Priority Levels Status Comments Remember that you must always keep track of any request that may affect the project. 313062832 312490005 RE: Project Request/Change Control Log 4/15/2012 11:35:07 PM Aaron Downing Yes indeed. Change requests are really the bane of project management. Requests made by the customer need to be documented, because they will more than likely affect the scope, which will in turn add time, complexity and the need for more additional resources. 312516985 310421427 RE: Project Scope Change Control 4/14/2012 8:40:32 PM Herbert Anderson Project Change Control Log Project Manager: <Firstname Lastname> Project Change Control Log Author: <Firstname Lastname> Project Description: <Brief description of the Project> Decision: Change Status: Change Date Approved/Not Date Additional Request Requester Priority In Description Requested Approved/On Canceled/Implemented Comments # Progress/Completed/Canceled Hold The unique number assigned to each request see the Change request form Brief description of the requested change see the Change request form Name of the Person requesting the change See the Change request form See the Change request form Record the approval Record information on the decision status of the Change request obtained from the Project The actual date the change was implemented/canceled https://wiki.cac.washington.edu/display/pmportal/Change+Control+Log+Template 312855351 310421427 RE: Project Scope Change Control 4/15/2012 6:05:32 PM Syleisha Smythe The change control log provides a single location where any project team member can review the changes made and the current status of all of those changes. Tracking items that would be included in the change control log would include: Unique tracking # assigned on the project impact report Title (one line summary description of the change) Date Created (date the change was formalized utilizing the PIR) Cost Impact – in dollars (quantification of the cost impact of the change) Schedule Impact – in days (quantification of the schedule impact of the change) Scope Impact (quantification of the scope impact of the change) Status – indicate where the change is in the change control processes (Assess, Approval, Approved, Implemented, Complete, Rejected) Status Comments – provide more details about the status and history moving through the change control processes. http://pm-foundations.com/2011/06/16/pm-foundations%E2%80%93-the-change-control-process/ 309534581 Change Management 0 4/8/2012 9:05:17 AM David Page Anything that affects the project scope is going to affect the overall project as this would impact the resources, budget, objectives, milestones, and deliverables. Should these change requests be made by the customer then evaluations need to be made regarding budget, time, and performance. Objectives are going to have to be re-evaluated as well as cost and schedule. The PM should work to find alternatives but in the end should the customer want this scope change it would be necessary to discuss cost, schedule, and performance. Going a step further risk management would have to be involved and re-evaluated. Any change to a project large or small has an impact on the project but when scope changes that is a rather large implication on the project and really needs to be evaluated via the group meaning all stakeholders. 309565664 Scope Changes 0 Robyn Little 4/8/2012 11:01:43 AM Reasons for Scope Change Defining scope management is most easily accomplished by looking at what causes scope change. There are three general reasons that project scope changes: 1. Scope Creep The project team increases or decreases project activities or deliverables, or the size of one particular deliverable. This naturally occurs in projects, but needs to be monitored so that it does not throw the whole project off. Lola's programmer adding extra functionality to the database application is an example of scope creep. 2. Budget or Schedule Changes Scope, budget, and schedule all exist in equilibrium. It takes a certain amount of money and work to create the product. The project team would need to revisit the scope were the project schedule or budget to change because they would be unable to accomplish the same scope. If the executive director were to ask Lola to deliver the project earlier, she would have to investigate whether the scope needed to be reduced to achieve the new target date. 3. Project Change Request Scope can also change simply because someone requests it. A project team member or another stakeholder may request that a change be made to meet other priorities or because the project will not accomplish the original objectives. An example of a project change request might be if the funder requested that the database application link up with their financial package. It is a request to expand the scope. What is Scope Management? Scope management means monitoring the project to identify changes to the scope or constraints, or receiving change requests. It also includes investigating the impact that changes will have on the project and making informed decisions about how to address them. Reading the Winds of Change The scope creep was a surprise for Lola. She was surprised to find that the scope had changed. I let her, and now you, in on a little secret of project management. There are a few signs that will let you know when change is about to happen. It does not have to come as a complete surprise. Unclear scope The project overview statement should outline what the project is to deliver, and should be clear and accurate. It is similar to the blueprint for a house. If it is vague, the carpenters might show up and put the kitchen in the basement. Oops. That might not be what you had intended, but i t was not communicated clearly enough. The project manager needs to define the scope clearly so that everyone knows precisely what the project is about. The what is not aligned with the why Every project is delivered for a reason. Lola's project intends to facilitate tracking donations to the agency. Therefore, she needs to deliver a project that will achieve that objective. Delivering a database that tracks people who might donate will not achieve that objective. This is often the case with projects. The "what" is not aligned with the "why." Something does not quite fit The project scope will probably include a number of key deliverables. Lola is delivering a database, a training manual, and sessions for the users. These are all related to one another and make sense to deliver as one project. If the project scope were also to include analysing the type of programs offered by the agency, one would have to wonder whether it really fits. It doesn't, and should probably be delivered as another project. Look for activities or deliverables in your project that do not quite fit with the rest. Deliverables have not been approved by the appropriate body This is a common reason that scope changes. It is very important that deliverables be approved by anyone who has the authority to later disagree. This is especially true when work builds upon previous deliverables. One of the first things that Lola did was develop a document stating what the database would do and the information it would collect. She then had the executive director approve this document and agree to what she was doing. The project team created the database based on this document. As long as she delivers a database that accomplishes what she agreed upon with the executive director, the executive director cannot claim that she did not know what to expect. If Lola did not have the executive director approve the project scope, she could have claimed that Lola delivered a database that she did not request. http://www.charityvillage.com/cv/research/rom20.html 309580071 Scope change 0 4/8/2012 11:52:07 AM Vanansio Samson One truth of business is that scope change will happen. A riskier concept is that customers may not understand the costs associated with the scope change, and as a project manager, it is important to make certain that, the project team, customer, sponsor and stakeholder all understand the relative costs in identifying and performing scope changes in a lifecycle. The best way to change the scope is through a project scope change control process, by changing the deliverables, team, and budget. It is important to understand the following ten (10) causes of scope change: 1- Business needs 2- Business benefits 3- Proper planning was not done 4- Planning suffered a lack of stakeholder engagement 5- Scope inflation, scope creep 6- Realized risk 7- Project Resources 8- Project Funding 9- Project schedule 10- A corrective action needs to occur. Out of the ten, only one relates to evil (scope creep and scope inflation. 309656666 Change management Melissa Burr 0 4/8/2012 3:55:03 PM If a requested change will change the scope of the project then this type of change request by the customer would need to be thoroughly explained to the customer so they can make an educated decision and know all the impacts of the decision. Questions I would ask of the customer would just be to give choices of two paths to help determine which choice is best and what is most important to them (ie spending less money or extended timeline, etc) 310440858 310185028 Project scope change 0 4/9/2012 4:15:07 PM Vanansio Samson Project sometimes change mid-stream, and depending on the size and nature of the change. A project manager should let the customer know that by changing a project scope, he may need to submit a revised budget and/or timeline for a sponsor's approval before he can implement the change. 310440858 RE: Project scope change 310185028 Echo Woolf 4/9/2012 10:07:46 PM You make a good point. When a change request is submitted, the changes affects other areas of the project. Therefore, revisions do need to be submitted in order to have an understanding of how the new time frames, budget, or resources need to be monitored. Once those changes are approved, they also need to be communicated to all stakeholders. Additionally, they must be recorded in the change log so there is a point of reference. Knowing who made what changes, when the changes were made and what the changes are helps to keep the project flowing smoothly. 310377233 Managing change requests 0 4/9/2012 8:49:18 PM Tyrone Labad Effectively managing change requests would be key to achieving project goals and at the same time ensuring that the client is satisfied with the project they they have received. For doing this, there must be a proper process established right at the early stages of the project as to how change requests are going to be incorporated. Every change that is requested must be properly and thoroughly documented by the customer and then submitted to the project manager. The project manager should then analyze the extent of change needed and its impact on the project constraints and objectives. Post this there must be a decision taken whether or not the change should be implemented or not. If it is a major change that would negatively impact the project goals, the project manager must have a discussion with the customer why the change is difficult to implement, its impact and possible alternatives on what they can do. If needed, the project sponsor can be called upon as a last resort to take a call on what should be done. 310389570 Scope Change/Scope Creep 0 4/9/2012 9:03:29 PM Brandi Williams The client may want modifications made or material changes. The client may want the budget drastically reduced or contract amendments. If the customer request changes to the project's scope, the PM must assess the reasons for the change and what is needed. Questions such as: What is the added value the scope change will provide?, What are the market needs and time required to make the scope change, payback period, return on investment, and selling price?, What is the impact on the length of the product life cycle?, Is there a product liability associated with the scope change and can it impact our image? (2009, Kerzner p. 953) The possible implications of change requests could be excessive costs, poor return on investment, high risks, stiff competition, technical complexity, legal and regulatory issues, etc. These possible implications could result in the project's failure or resulting in a major loss. (2009, Kerzner p. 954) 310418014 Change Mnagement Sheila Williams 0 4/9/2012 9:37:17 PM Proposed changes in the scope: There are a variety of ways a change in the scope of a project can affect the project. Number one is cost. Generally, something big enough to result in a change in scope is often not cheap and most likely was not factored into the project's budget when it was developed. The second reason involves vendors. If you're going to need to hire the work out to vendors, resulting from the scope change, consider how much time it's going to take the vendor to do the work. 310571950 Change Requests 0 4/10/2012 9:11:18 AM Daniel Worcester I know there would be quite a few questions for the customer regarding the who, what, where, why, and how however I would want to know that the customer is fully aware of the impacts of the change that is requested. After reviewing the requested change I would want to ensure that I had enough info on the changes that I could make it fully aware to the customer the results of the change. I have seen in the past that customers have asked for changes and were not made aware of what the impacts were going to be because of the changes. Ensuring that the customer is aware of the changes will help to eliminate any misunderstandings and may alter the changes to ensure that there is no negative impacts on the project. 310602183 RE: Change Management 0 4/10/2012 10:40:38 AM Marquita Blair Modified:4/10/2012 10:45 AM Change requests can be such a tricky thing. When the proposed change affects the project's scope there has to good reason for such a change. Because change requests may modify project polices, scope, cost/budget, project schedule, quality ant etc. even the risk management plans must be re-evaluated. The decision whether to accept or reject a change would be based on a number of rules. The fundamental logic should be: Is the change unavoidable? Does the change increase the overall benefit to the organization, taking into account any impact on the costs, benefits, timescales and risks? Is the Project Team able to make such a change? Is the change best done now, or would it be more beneficial to defer it until the current work is complete? How is going to be responsible for this change, will there be shared risks? 310667648 Scope Change 0 4/10/2012 1:42:07 PM David Froning Scope change has to be monitored. The PM has to keep track of the scope change and monitor the the change requests entered by the customer. Many of these changes are able to be consumed by the project and a slight amount of scope creep is expected. Many times though the customer decides by necessity or just because change happens to make major changes to the final product that could affect the scope in a huge manner and that needs to be investigated and understood by all parties to make additions to the project scope. 310754407 Change Mgmt 0 4/10/2012 5:27:49 PM Syleisha Smythe The first question that comes to my mind is, "Should this be a separate project?". But depending on the complexity of the change being requested it may be something best handled as it's own project. For instance if the project is for a system implementation and the change being requested requires cloud computing integrations, then the complexity of the change warrants its own project, time, scope and cost allocations. 312521880,31254 310836333 Considerations for Why to Have Change Control 0 Professor Firestone 4/10/2012 7:52:37 PM All, having a formal process is essential and there are some controls that need to be in place. For example, why should the change request be reviewed by the functional department that will be impacted by the change? 312521880 RE: Considerations for Why to Have Change Control 310836333 Herbert Anderson 4/14/2012 8:50:42 PM Main reason would be the knowledge and skills address to the department. They understand the issue more then anyone else. Plus they could focus on the problem faster and with more resource; therefore that functional department should be presented the change request log. You wouldn't require a doctor to view a request log for a plumbing project. The experience needs to be set in the rigth place for the change request. 312547246 RE: Considerations for Why to Have Change Control 310836333 Albert Wells 4/14/2012 9:45:22 PM My understanding is that you want the functional department that will be impacted by the change to review the change request because thy have the greatest understanding of the rammications of a change. For instance I work in the training department. If my GM wanted to make changes to the department he would confer with my operations manager to ensure that it would not have negative impacts on the department as she has the greatest knowledge of what will and won't work, and how changes can affect our efficacy. 312470120 RE: Considerations for Why to Have Change Control 310836333 Melissa Burr 4/14/2012 6:56:21 PM The change request should be reviewed by the functional department that will be impacted because there may be impacts that are not realized by the requestor that the affected department would bring to light. It could also create tension in the work environment if the affected areas aren't consulted and make their opinions of their own department/area unimportant. 312166928 RE: Considerations for Why to Have Change Control 310836333 Robyn Little 4/13/2012 8:51:33 PM They know their workers best. They know who can fill in or who will fit best into certain areas. They would also need to adjust their schedules to accomodate and relay information to their teams. 312832289 312677281 RE: Considerations for Why to Have Change Control 310836333 Kevin Shaw 4/15/2012 10:41:20 AM The change request should be viewed by the affected functional departemnt because the change could possibly mean additionla resources being taken from tghe department or additional resources being put back into the department which will affect their budget either way. 312832289 312677281 RE: Considerations for Why to Have Change Control Sanah Fatima 4/15/2012 5:19:47 PM Modified:4/15/2012 5:20 PM Kevin, I agree with your statement. I think when we can negotiate terms and conditons with clients we should bring this up too, we should let the clients know ahead of time that if they decied change scope it would be to additional cost, and explain client how it might affect financially that why client would make sure that they are hundreed percent sure of thier original change scope. no client wants to spend more money than they have to right? our job should be to explain everything as clear as possible so there is no misundrestanding. Have you heard about the quote. "CEO don't know anything" what this means that is that he have lot of money and a big Idea. now he needs us to explain every step of the way and he learns as he goes. :) 311098789,31125 311060478 RE: Considerations for Why to Have Change Control 310836333 Leigh-Ann Joseph 4/11/2012 11:25:52 AM I agree with both Daniel and Tyrone, any and all changes should be reviewed by the functional department, including manager and team, to ensure the changes can be accommodated. As we are aware there are many parts to a projects, it is imperative that any changes be reviewed first by the team that is directly involved, and I would also advise that all other teams and stakeholders be informed, either in one of the Minor Reviews, or by way of alternate communication. It would depend on how critical a change it is and how it ultimately affects the project. 311254346 311098789 311060478 RE: Considerations for Why to Have Change Control Sheila Williams 4/11/2012 1:21:29 PM Also, the functional department is responsible for providing the labor for the project; it is imperative that they be informed of any changes that occur because they have the responsibility of determining how the project tasks will be completed. 311254346 311098789 RE: Considerations for Why to Have Change Control Joseph Allen 4/11/2012 7:37:50 PM I agree with you, the functional manager is typically responsible for the tasks that the change order may address. Supplying the resources to accommodate the tasks.The functional manager is also typically the expert in the area, and can not only review for resource support, but review for technical content as well. In addition, the functional manager may be supporting multiple projects within the organization and will have a good overview of what can be supported from their department as a whole. 311011418 RE: Considerations for Why to Have Change Control 310836333 Daniel Worcester 4/11/2012 8:46:42 AM Any direct impact to how a department does work should be evaluated for a variety of reasons. Some of the more important reasons include ensuring that the proposed change can be done by the department at its current level. A sure fire way to set up for failure is to assign a department a change and not realize that the department could not take on the change because of manning, skill, manufacturing, or equipment reasons. 311328861 RE: Considerations for Why to Have Change Control 310836333 Marquita Blair 4/11/2012 9:35:44 PM The change request must be reviewed by the functional department that will be impacted by the change because Functional department managers and senior corporate management are the people responsible for reviewing change request proposals and all their attached documents. Besides the fact that their department has to make sure that they can even accommodate the request with adequate enough resources. 311335857 RE: Considerations for Why to Have Change Control 310836333 Nazish Raja 4/11/2012 9:47:31 PM It is important for the functional department to be reviewed because so the project is getting completed properly so that it gives a good expression for the client. Having the project reviewed more than once gives other eyes to catch something that the other eye couldn't catch. I believe spending 10 mores minutes on the reviewing the project is better then the project coming back with bad comments etc. 311565215 RE: Considerations for Why to Have Change Control 310836333 Syleisha Smythe 4/12/2012 1:59:48 PM Modified:4/12/2012 2:28 PM Change requests should be reviewed by the functional manager impacted by the change in order to gain their insight into the logistic of enacting the change. While the change may be necessary it may not be possible currently or may require additional materials or tools to be accommodated. Only the functional manager can really speak to those points. 311721876 RE: Considerations for Why to Have Change Control 310836333 Kimberly Brewer 4/12/2012 7:42:49 PM There are a couple basic reasons the impacted team should be made aware of the new requirement and should be able to assess the requirement and give input as to whether it will work or not. They have to determine if it will fit into their current operations or if they will need to make adjustments to make it work. Also they might have some insight that other people/departments don't have that could add value to making the decision or not. 311119910 310944819 RE: Considerations for Why to Have Change Control 310836333 Tyrone Labad 4/10/2012 11:21:08 PM Given that change requests come in on an ad hoc manner, and there can be multiple change requests coming in from multiple stakeholders, it is extremely essential that each of the changes are properly tracked, analyzed, communicated and decisions taken in a proactive manner, so that these change requests do not impact meeting the project objectives. Every change request that comes in must be reviewed and analyzed by both the project manager and the functional department that would be impacted by the change, as they would be able to set expectations on how this change would impact project objectives and constraints, based upon which the decison makers can take a call on whether or not to implement the change. 311119910 310944819 RE: Considerations for Why to Have Change Control Sharon Jno-Baptiste Griffin 4/11/2012 2:24:27 PM Tyrone great post and I agree. Just to add that depending on the structure of the organization, a project manager may have little authority and thus the functional manager would be responsible in approving the changes. It is also important for the functional manager to know all changes taking place as ultimately the project manager moves on to a different project, but the functional manager remains and have to deal with the deliverables of the project. 311317212 311235726 Change Management 0 4/11/2012 7:06:42 PM Donte Whiting A change request is a formal proposal for an alteration to some product or system. In project management, a change request often arises when the client wants an addition or alteration to the agreed-upon deliverables for a project. Such a change may involve an additional feature or customization or an extension of service, among other things. Because change requests are beyond the scope of the agreement, they generally mean that the client will have to pay for the extra resources required to satisfy them. 311317212 RE: Change Management 311235726 Michael Boston 4/11/2012 9:16:54 PM There are a few different types of changes that I am familiar with. CCD (construction change directive) RFI (request for information) RFP (request for proposal). These typical start with the inquirer y about a project question or function that either leads into a alternate route of completion which may or may not lead to a cost and CCD is a directive from the owner to do a change of project scope but either way typical a RFP is sent and approved and a formal change order is issued to guarantee that the owners have approved the change order and that additional costs will be paid. 311325750 Change Management 0 4/11/2012 9:30:34 PM Kimberly Brewer The Change Management Process should outline how all changes are analyzed and made or rejected. If a customer is requesting a change to the scope of the project they must first understand the timeline, quality, resource and cost implications. If they agree to pay the cost and we have the available resources and do not have other time constraints that prevent the additional work, then I think we would probably make the change. However, if the quality of my output is going to be impacted negatively, I would fight to not make the change. If there is no negative impact to quality, I think the change might be ok. 311575011,31158 311368095 Change Control Board 0 4/11/2012 10:51:48 PM Professor Firestone Going further with this one, Folks, part of a Change Management Plan for projects is having defined a Change Control Board. The Change Control Board has three options when considering a change request. They can accept the requested change, they can reject the requested change, or they can hold the requested change over for a future project, edition, or version. If a requested change is accepted by the Change Control Board, who should be notified of the approved change request and how would this be communicated? 311589177,31159 311575011 RE: Change Control Board 311368095 Syleisha Smythe 4/12/2012 2:27:38 PM If the Change Control Board approves a change, it will need to be communicated to all project stakeholders. This should be communicated immediately upon making the decision in writing (email is fine) and then reviewed/discussed during the next upcoming project status meeting. 311598350,31166 311589177 311575011 RE: Change Control Board 4/12/2012 3:06:32 PM Echo Woolf Like Syleisha mentions, all stakeholders should be notified. Typically, there is a communication plan for the project; therefore notifying the stakeholders appropriately based on what was agreed upon in the communication plan would be the best way to handle things. Additionally, it should also be mentioned in a meeting just to clarify to there is no misunderstandings. Also the project manager and functional managers may choose to make a formal announcement to the project team as well. 311661296,31192 311598350 311589177 RE: Change Control Board 4/12/2012 3:31:52 PM David Froning You are right on board. THe Communication Plan for the project needs to be followed immediately after a change request has been accepted. This will allow for the teams to get started immediately on the changes and follow with as little as possible scope change due to the communication gaps. 311926720,31247 311661296 311598350 RE: Change Control Board 4/12/2012 5:59:13 PM Sheila Williams To comment, the CCB decides whether or not it will implement the change and the decision will be based on factors such as: the severity of the change; cost vs benefit or can it be handled in the project’s schedule. If the CCB decides that the change is to be implemented, it is communicated, via written document, to stakeholders, project manager, project team etc. t affected by that change. http://www.cse.dcu.ie/our_services/pm/managing-userrequirements.html 312472092 311926720 311661296 RE: Change Control Board Miriam Hassan 4/13/2012 8:50:52 AM As Sheila has mentioned, it is not necessary to notify all the stakeholders involved in the project regarding a change notice, but only those who are directly affected by said change, including the project manager, project team members and and trades managers (subcontractors). Identifying the seriousness of the change and how it will impact the project is also a determinant regarding who should be notified. 312472092 311926720 RE: Change Control Board Donte Whiting 4/14/2012 7:01:14 PM One caution here: often it's lots of small-scope changes that do the damage, rather than the big, obvious ones. Consider this when defining your PCR criteria. For example, your change management plan should define change request categories, such as what is major or minor: Major changes These should be documented as a PCR. Major project changes: Affect requirements or work items on the critical path, delaying significant milestones or the overall project end date by a certain time percentage or duration. Major change criteria should be defined for each project. Require additional funding (in dollars or percentage of budget). Again, the amount should be defined for each project. Minor changes These routine changes don't require a PCR. Minor changes: Don't significantly affect the plan. They don't extend the completion date of milestones or tasks with project dependencies. Have no negative financial impact. No project budget variance will occur as a result. 311500779 RE: Change Control Board 311368095 4/12/2012 11:04:17 AM Daniel Worcester The whom that needs to be informed is anyone who has a direct relation to the change. If it is a change that is going to affect the next project than I would leave it up to the supervisor's to inform there crews. As far as "how" I think it depends on the change and the nature of the project. If it is a work to be done than that needs to come over as a work request added to the path. If its how a work is going to be done it should be communicated through the chain of command and posted in the Standard Operating Procedures SOP. 311497993,31201 311419930 RE: Change Control Board 311368095 4/12/2012 6:19:18 AM Brandi Williams If the Change Control Board has been approved all stakeholders (client(s), project manager(s), functional manager(s), and team members) need to be notified. This notification needs to be formal (in writing), as well as announced to the team in-person. Some companies prefer to send email communications as their form of "in writing". There have been a few occasions where I have received "confidential" emails from management that pertain to a "change of plans" for a project's process, however, most formal change requests are noted in writing (confidential memo, hand-out, or something similar) and a meeting is held making the announcement to the functional team members. At this meeting, questions and concerns are addressed about how this change will take effect and what steps need to be made in order to implement the change. 312012151 311497993 311419930 RE: Change Control Board Joseph Allen 4/12/2012 10:56:21 AM I completely agree Brandi. All of the stakeholders in the project should be informed of any change, and the change order should be in writing with specifics on cost, scope, and and addtional time required. Each organization may have a different process in to how they communicate the change, but the process should dictate that the change is in writing and that all stakeholders including team members be informed. The team members may not receive the change from the change control board, however the project manager or some other lead in the project should communicate this change throughout the team. This communication is necessary so that all team members understand the change and how it may affect and be related to their specific tasks. 312012151 311497993 RE: Change Control Board Brandi Williams 4/13/2012 1:16:47 PM Thanks for your comments Joseph! - I know I am super-annoyed when I find out some change related to my job functions or department from someone who works on another floor or someone totally from a different area. I feel left-out and blindsided. It is so important to inform your immediate team members before the "word hits the streets" and is exaggerated. 312664367 RE: Change Control Board 311368095 Kathryn Martinez 4/15/2012 10:00:30 AM From my line of work I have never heard of having a change control board. With all my employers they trust us to do our job, if you don't trust your people on a project then how does any work get done? We are free to make the changes necessary to get our job done. Especially in project management if you don't foresee the problems you wouldn't do get being in project management. As a project manager you are to know those issues before hand before you start a project that is what Risk Assessment is for that way it doesn't take up your time and resources and creates over cost. 311430961 Week 7 0 4/12/2012 7:20:33 AM Kathryn Martinez When the change affects the project scope if you are the project manager you make the necessary adjustments to fix the project to keep it in scope. If your customer request a change in project scope if you are the project manger you make the changes for the customer but make them aware of the consequences of the change and how it will effect their project. 311992851,31202 311718757 Change Requests 0 4/12/2012 7:38:14 PM Professor Firestone Ah, Everyone, there are many types of controls that need to be in place. For example, why should the change request be reviewed by the customer or functional department that will be impacted by the change? 312024042 311992851 RE: Change Requests 311718757 John Sebastien 4/13/2012 12:17:05 PM Modified:4/13/2012 12:18 PM These changes must be reviewed by the customer and functional department, so as to assess the value and effectiveness of those changes, as well as the impact that this change will have on the project. Also, this change/s can affect the cost estimates, activity sequences, schedule dates and resource requirements. Therefore, adjustments to the project management plan and other documents may become necessary. 312024042 311992851 RE: Change Requests Michael Boston 4/13/2012 1:53:08 PM Modified:4/13/2012 1:54 PM Yes changes need to be reviewed not only for those obvious reasons to but verify that there is not any over charges or excessive labor amounts added into the changes. 312003009 RE: Change Requests 311718757 4/13/2012 12:48:47 PM David Froning Can the functional team make the change at this point in the project? What if the customer can not accept the change due to his process? Change requests are sometimes huge because they may break something else in the process of making the change. 312189793,31223 312018926 RE: Change Requests 311718757 4/13/2012 1:37:06 PM Brandi Williams The change request needs to be reviewed by the customer or functional department because there may be an issue that requires a revision or addition to the change. Circumstances for both the customer and functional team may not be ideal for the change to take effect immediately, and may require a delay. Or, there may be other risks, for instance, the functional department may need to recruit additional staff (or let some staff go) to accommodate the change. For example, if it's a construction project and the client wants a 3-car garage instead of a 2-car garage, the functional team needs to be sure they can make that change at the current stage of the home's construction because the foundation and structure already in place may not allow for such a modification at this phase of the project. Or it may be a customdesigned wedding cake and now the client wants to change the color or tier-layer. The baker may be able to change the tier-layer, but not match the color (maybe they ran out of silver icing) and will have to check with the client if it is okay to use a different color trimming on the extra tier-layer. The client may want the colors to stay uniform with the wedding party. I can go on and on, but the point is changes can be major or minor, both they still impact the project's desired outcome. Therefore, the client and functional team must communicate openly about the change request. 312189793 312018926 RE: Change Requests 4/13/2012 9:49:57 PM Professor Firestone Great discussions/dialogues throughout the entire thread! Keep going! Everyone, knowing the entire project from 'head to toe' with regards to the major measurements is key to a project manager's being able to address requests for change. As a project manager, how would you approach being more specific with your response to a change request? 312808158 312239897 312018926 RE: Change Requests Tyrone Labad 4/14/2012 3:13:34 AM The later in the project changes come about, the more difficult it is to incorporate them, and hence the project manager must try to get the scope and requirements right as early in the project as possible. Keeping the customer involved in the project, right from the start would be key to effectively managing and implementing the project. By having very close interaction with the customer, they would be able to immediately offer any review comments that can be incorporated in the requirements. Also, as stated by Brandi above, customer should review all changes that are requested and approve them, as they would finally be responsible and hence make the decision after considering impact of change on the scope, quality, cost and schedule of the project. 312808158 312239897 RE: Change Requests Donte Whiting 4/15/2012 4:27:44 PM I agree; keeping the customer involved in the project from the start will help with managing and implementing the project. One thing that I believe to also be a good factor in sticking to the scope. Walk the project with the customer before the start of the project and point out possible road blocks and unforseen tasks. 312629777 RE: Change Requests 311718757 Frederick Rock 4/15/2012 7:41:16 AM These changes need to be review to ensure that they meet the all the requirment of the customer and that the functional department can meet the new requirments encluding quality and time lines. 312993476 RE: Change Requests 311718757 Leigh-Ann Joseph 4/15/2012 9:28:19 PM The change request should be reviewed by the customer as they are one of the key stakeholders of the project. Ultimately, they need to approve the change and the impact it will have on the outcome of the project. Hopefully, the change will result in a desired outcome with only changes in the process or subtle changes in the tasks. Sometimes, however, the changes are involve more making it even more crucial to inform the customer. The change request should be reviewed by the functional department as they will ultimately be affected by the change and will need to make informative decision. It is a good practice to inform all members of the project team of any changes to keep everyone aware of the progress of the project. 312808399,31295 312335492 An Example to Try 0 4/14/2012 12:01:51 PM Professor Firestone Would it be fair to surmise that being on top of everything in the project means all the difference in the world = project? Here is a D.A. type of situation and question. Suppose that you are actually managing a program that is composed of more than two dozen projects, world-wide and taking more than two years to complete. What would be your approach for being on top of all that is happening (and, perhaps not happening) with the program? [Have some realistic fun with this one, please.] 312808399 RE: An Example to Try 312335492 Kimberly Brewer 4/15/2012 4:28:14 PM If I'm managing the program, I have 12 project managers or at lest project managers responsible for each of the 12 projects. I would expect from each of the responsible owners a weekly status report. In addition a monthly project review meeting that would require everyone to meet and review each project. I would expect that this is a mandatory meeting and if one cannot make it, they have a back up that will be present to represent their project. I would expect a daily half our review of the most critical project items. 312952002 RE: An Example to Try 312335492 Albert Wells 4/15/2012 8:30:35 PM First I would cry, then I would dance, I then I would pass out in disbelief. Having accomplished all of this. I think I would look at the projects and the amount of risk associated with each one. High risk projects get a single PM to manage them, where as low risk projects could be doubled up. I think we would also need to take into consideration geographic location if they are world wide. Its hard to be abreast with a project on opposite sides of the world. If I had two though it would require clear rules and guidelines for communication. 312906087 312722079 RE: An Example to Try 312335492 Herbert Anderson 4/15/2012 12:50:44 PM With strong project management skills, that person wouldn't have a life to enjoy. For example with 60 hours away from home, it hard to spend time with your family. In fact I've read in our text book that, "There are severe risks that are not always evident. Some project management positions may require a sixty-hour workweek and extensive time away from home. When a project manager begins to fall in love more with the job than with his family, the result is usually lack of friends, a poor home life, and possibly divorce. During the birth of the missile and space programs, companies estimated that the divorce rate among project managers and project engineers was probably twice the national average. Accepting a project management assignment is not always compatible with raising a young family. Characteristics of the workaholic project manager include: •Every Friday he thinks that there are only two more working days until Monday. •At 5:00 p.m. he considers the working day only half over. •He has no time to rest or relax. •He always takes work home from the office. •He takes work with him on vacations. So think about two dozen project world-wide, you would become a PM robot. For some reason when I signed up for this major, I didn't think about my family, however i didn't have a son at the start of my education. I think a great PM could be anyone with skills, but a better one would be someone young with no kids or no-one to take care of, but themselves. 312906087 312722079 RE: An Example to Try Derek Cavanaugh 4/15/2012 7:26:48 PM If you are a managers of a program like this there are two things that can be thought about it and Herbert you are correct about this but not all people are like that. There are always people that have the right people below them that are able to handle more things and may not need their direct manager to be on their cases everyday or every week even. I think as a manager like this you would need to know who is managing what and what project needs more control from you. As or having a 60 hr work week top managers like this are not the only ones doing this and if you really think about it is is only really an 12 hour day and considering where in the world you are having projects then there will be many days where you may need to be at work from say 6am to 6-7 pm to make sure everything is done. When it comes to being someone that has risen from where they started to a manager that is doing something like this it is someone that is going to be use to taking work home as well as knowing how to relax the best and what may even be the fastest way for them to relax. 312954632 312387609 RE: An Example to Try 312335492 Leigh-Ann Joseph 4/14/2012 2:50:41 PM Professor Firestone, this project example is extremely large, but I am aware they fully exist. I find myself fortunate to have been working in a Project Management role over the last three years but my experience has been very local and with one to three projects at a time. Before really getting into my core courses at DeVry, I wasn't even aware that the tasks I was completing actually played a role in our overall Projects on campus. Once i realized this, I started tracking them with MS Project so I could apply them to my PMI once I graduate. I do hope to one day become this PM that you are describing, with full confidence and abilities to to take on multiple projects spanning many countries. For a PM in this role, one of the key things for success would be complete and constant communication. Although I have managed what I now know are smaller scale projects, I have been a part of a big picture for our Head office and other four campuses. The tool we use to keep in constant communication is MS Sharepoint, as well as pages on our custom website. Using these applications we are able to update and keep all five campuses, including our Head Office and Head Project Manager, abreast of all actions, tasks completed, and updates in real time. We also meet weekly with conference calls and webinars. 312954632 312387609 RE: An Example to Try 4/15/2012 8:34:10 PM Michael Boston I agree this would be a very large project unless you look at it in a different way. Lets say this is a construction project and the general contractor has a PM that has been assigned to the project. Under the GC's PM is a list of subcontractors who each of them has its own PM assigned to manage the project. In this case it is very feasible that there would be twelve or more PMs to look over even if the project is very small in scale. I can see this in many different types of business where there are subcontractors assigned to take on portions of the project that must be managed by the main PM. 312399974 RE: An Example to Try 312335492 Marquita Blair 4/14/2012 3:30:48 PM More than likely I see this as IT type of project, I can not see this type of situation in an engineering firm for example. Being that there are more than two dozen projects, that are world wide and taking two years to complete, the best approach for me would be to appoint a project-co-captain per project. I would need constant contact with that one leader because this is too much work to leave the burden of such a large scale project on one person (the PM), he is going to have to have some help because trying to keep up with this many employees and their progress is impossible. If there was a co-captain he could directly communicate project issues to the PM, with the PM managing the project as needed through them. They should all be communicating on an Intranet type system keep all info cc'ed between functioning groups and the PM. 312700244,31285 312583492 RE: An Example to Try 312335492 Sharon Jno-Baptiste Griffin 4/14/2012 11:19:22 PM While managing multiple projects is essentially the same as managing a single project, there are two important differences. First, the scale is vastly different, as you have to do the same thing (manage a product) several times throughout a day. Secondly, you have to learn important soft skills like prioritizing, delegation and risk management – terms that take a whole new meaning when applied to multiple projects. To learn the art of managing multiple projects, one should learn the following techniques: Scheduling resources – Since you have to plan for several projects simultaneously, you need to schedule manpower and physical resources to ensure that no one project is given all the attention or neglected totally. Establish priorities – prioritizing is crucial to managing multiple projects. By assigning higher priority to value-added tasks, you can allocate your time to those specifics that yield higher and better results. Delegate – In conjunction with establishing priorities, you need to delegate all but the most important tasks. This often means trusting your team a lot more, and for this reason it is important to have people with you that you have worked with before and / or people with experience. Integrated project scheduling – With multiple projects, you have to schedule different tasks and phases of your projects in simultaneous time slots. Maybe you’re in the final stages of one project and in the development / production phase of another, while you have two projects in the planning phase. Integrating your activities to ensure that different phases of different projects can be executed in harmony at the same time. While managing multiple projects is essentially the same as managing a single project, there are two important differences. First, the scale is vastly different, as you have to do the same thing (manage a product) several times throughout a day. Secondly, you have to learn important soft skills like prioritizing, delegation and risk management – terms that take a whole new meaning when applied to multiple projects. To learn the art of managing multiple projects, one should learn the following techniques: Scheduling resources – Since you have to plan for several projects simultaneously, you need to schedule manpower and physical resources to ensure that no one project is given all the attention or neglected totally. Establish priorities – prioritizing is crucial to managing multiple projects. By assigning higher priority to value-added tasks, you can allocate your time to those specifics that yield higher and better results. Delegate – In conjunction with establishing priorities, you need to delegate all but the most important tasks. This often means trusting your team a lot more, and for this reason it is important to have people with you that you have worked with before and / or people with experience. Integrated project scheduling – With multiple projects, you have to schedule different tasks and phases of your projects in simultaneous time slots. Maybe you’re in the final stages of one project and in the development / production phase of another, while you have two projects in the planning phase. Integrating your activities to ensure that different phases of different projects can be executed in harmony at the same time. 312855866 312700244 312583492 RE: An Example to Try Sheila Williams 4/15/2012 11:49:39 AM This is great information and well said, Sharon. All I would say, is that in order to manage two dozen projects, worldwide, that is taking more than two years to complete would mean that the project manager has to have a very good tracking tool, excellent interpersonal skills, and trustworthy team members; without it, failure is just a matter of time! 312855866 312700244 RE: An Example to Try Summers Love-Morrison 4/15/2012 6:06:30 PM Sheila, I totally agree. In order to make a project of this magnitude happen, the PM must have members that have integrity and are trustworthy. Another key element is teamwork. Teamwork is needed in order to ensure the project is done accordingly and accurately. _u=7295436;_dt= 86-5E-A8-8F-F3-
© Copyright 2026 Paperzz