11.3 Perform Qualitative Risk Analysis • The process of prioritising risks by assessing and combining their probability of occurrence and the consequences of their impacts • Project performance can be improved by focussing limited resources on the high priority risks • Qualitative risk analysis is the most common, fastest and most cost effective means of establishing risk priorities and planning risk responses • It is critical to establish definitions of the levels of probability and impact so as to reduce the influence of bias Monitor • Occurs during Planning Initiation Planning Execution Close Control Adapted from PMBOK 4th Edition BSBPMG508A Manage Project Risk 11.3 Perform Qualitative Risk Analysis • Inputs to Qualitative Risk Analysis Draft Risk Register Risk Management Plan Project Scope Statement Organisational Process Assets – Risk management standards – Risk management policies and procedures – Risk categories and definitions – Standard templates – Lessons learned from previous projects – Risk databases and checklists Monitor Initiation Planning Execution Close Control Adapted from PMBOK 4th Edition BSBPMG508A Manage Project Risk 11.3 Perform Qualitative Risk Analysis • Tools and techniques for qualitative risk analysis include Risk Probability & Impact Assessment Expert Judgement BSBPMG508A Manage Project Risk Probability & Impact Matrix Risk Data Quality Assessment Risk Urgency Assessment Risk Categorisation Probability and Impact Assessment Likelihood = Probability Consequences = Impact • Qualitative Risk Analysis involves the estimation of the likelihood and consequences of each risk • Quantitative Risk Analysis involves estimating the measurable impact on project objectives, specifically – Cost, Time, Scope and Quality BSBPMG508A Manage Project Risk Basic Risk Analysis Matrix • For example Low Risk Green Business as Usual Acceptance Medium Risk Amber Heightened Action Monitor Closely Immediate Action Mitigate or Avoid High Risk Red Probable Improbable How risks are treated How closely they are monitored How quickly they must be resolved if they occur Likelihood • Determines Medium Risk High Risk Low Risk Medium Risk Minor Major Consequence Risk Management Guidelines – Companion to AS 4360:2004 BSBPMG508A Manage Project Risk Likelihood and Consequences Simple Likelihood Scale Rating Definition Scale Almost Certain Will definitely occur or will occur on an annual cycle 5 Likely Similar events have been experience several times in the past 20 years 4 Possible Will occur once every 20 years 3 Unlikely Occurs from time to time 2 Rare Occurrence is possible but highly unlikely 1 Simple Consequences Scale Rating Definition Scale Severe Most objectives cannot be met 5 Major Some important objectives cannot be met 4 Moderate Some objectives impacted but may still be met 3 Minor Minor effects that can be remedied 2 Negligible Almost no impact on objectives 1 Adapted from Risk Management Guidelines – Companion to AS 4360:2004 BSBPMG508A Manage Project Risk Risk Rating Matrix and Risk Urgency • Put your likelihood and consequence ratings together and what do you get? Rating Severe Major Moderate Minor Negligible Almost Certain Red 25 Red 20 Red 15 Amber 10 Green 5 Likely Red 20 Red 16 Amber 12 Amber 8 Green 4 Possible Red 15 Amber 12 Amber 9 Green 6 Green 3 Unlikely Amber 10 Amber 8 Green 6 Green 4 Green 2 Rare Green 5 Green 4 Green 3 Green 2 Green 1 Risk Rating = Likelihood x Consequences Risk Urgency = RED, GREEN, AMBER BSBPMG508A Manage Project Risk Risk Categorisation – Breakdown Structure Project Risk Breakdown Structure Project Management External Technical Organisational Estimating Subcontractors & Suppliers Requirements & Scope Dependencies Planning Regulatory Technology Human Resources Controlling Market/Economy Complexity Funding Communication External Customer Performance & Reliability Prioritisation Environment Quality PM Environment Adaptations and additions to the example in the PMBOK Methodology & Materials Adapted from PMBoK Guide – Fourth Edition BSBPMG508A Manage Project Risk 11.3 Perform Qualitative Risk Analysis • Outputs of this process include – Risk Register Updates – Likelihood and Impacts Prioritised List of Project Risks – Risks requiring response in near term – Risks requiring additional analysis and response planning Risks grouped by categories Root cause analysis Watch lists of low priority risks Trend analysis Monitor Initiation Planning Execution Close Control Adapted from PMBOK 4th Edition BSBPMG508A Manage Project Risk Inclusions in Risk Register During Analysis Risk ID Risk Category Risk Description Risk Owner Likelihood Impact Risk Rating Management /Mitigation Strategies Residual Likelihood Residual Impact Likelihood Risk Rating • • • • • • Combines Likelihood and Impact • Normally multiplied together • Enables overall prioritisation of risks Probability of the risk occurring Typically defined in a risk rating matrix Has both a number scale and definition Requires judgement and prediction More accurate if can leverage lessons learnt Residual Rating Status Priority Management/Mitigation Strategies Impact • • • • • • Consequences of the risk occurring Impacts on or more project objectives Includes scope, time, cost & quality Has both a number scale and definition Requires judgement and prediction More accurate if can leverage lesson learnt • • • • Avoid – remove entirely Mitigate – reduce likelihood or impact Accept – normally for LOW risks Transfer – to another party, eg contract or outsource Adapted from PMBOK 4th Edition BSBPMG508A Manage Project Risk Inclusions in Risk Register During Analysis Risk ID Risk Category Risk Description Risk Owner Likelihood Impact Risk Rating Management /Mitigation Strategies Residual Likelihood Residual Impact Residual Rating Status Priority Residual Likelihood • Probability of risk occurring after management or mitigation actions Residual Impact Status • Impact of risk occurring after management or mitigation actions • Typically RED, GREEN, AMBER Priority • Typically HIGH. MEDIUM. LOW Residual Rating • Revised risk rating • Most important for risk monitoring Adapted from PMBOK 4th Edition BSBPMG508A Manage Project Risk
© Copyright 2026 Paperzz