API 17TR9: Subsea Umbilical Termination (SUT) Selection and Sizing Recommendations Contents API 17TR9: Subsea Umbilical Termination (SUT) Selection and Sizing Recommendations ................. 1 1 Scope ............................................................................................................................................... 3 1.1 Introduction .............................................................................................................................. 3 1.2 Document purpose .................................................................................................................. 3 1.3 Use of the Document ............................................................................................................... 3 1.4 Applicability .............................................................................................................................. 4 2 REFERENCES ................................................................................................................................. 6 3 TERMS, DEFINITIONS AND ABBREVIATIONS ............................................................................. 6 3.1 Terms and Definitions .............................................................................................................. 6 3.1.1 .................................................................................................................................................. 6 bend limiter ..................................................................................................................................... 6 (from the UMF Glossary of Terms)................................................................................................... 6 3.1.2 .................................................................................................................................................. 6 bend stiffener .................................................................................................................................. 6 (from the UMF Glossary of Terms)................................................................................................... 6 3.1.3 .................................................................................................................................................. 6 rigid length ...................................................................................................................................... 6 3.1.4 .................................................................................................................................................. 8 subsea termination interface ........................................................................................................ 8 STI .................................................................................................................................................... 8 3.1.5 .................................................................................................................................................. 8 subsea umbilical termination ........................................................................................................ 8 SUT .................................................................................................................................................. 8 3.1.6 .................................................................................................................................................. 8 umbilical Line.................................................................................................................................. 8 3.1.7 .................................................................................................................................................. 8 umbilical termination assembly .................................................................................................... 8 UTA .................................................................................................................................................. 8 3.1.8 .................................................................................................................................................. 8 UTA Yoke......................................................................................................................................... 8 3.2 Abbreviations ......................................................................................................................... 10 API American Petroleum Institute........................................................................................... 10 FBC Free Board Clearance .................................................................................................... 10 FEED Front-End Engineering Design ..................................................................................... 10 Document1, 5 July 2015 1 JIP Joint Industry Project ....................................................................................................... 10 MBR Minimum Bend Radius ................................................................................................. 10 MQC Multiple Quick Connects .............................................................................................. 10 OD Outer diameter ................................................................................................................. 10 Umbilical Manufacturers’ Federation ........................................................................... 10 UMF UMSIRE 4 5 Umbilical Termination Size Reduction [name of the JIP that created this document] 10 SDU Subsea Distribution Unit .................................................................................................. 10 SPS Subsea Production Systems............................................................................................ 10 STI Subsea Termination Interface.......................................................................................... 10 SUT Subsea Umbilical Termination ......................................................................................... 10 TR Technical Report .............................................................................................................. 10 UTA Umbilical Termination Assembly ..................................................................................... 10 VLS Vertical Lay System ......................................................................................................... 10 Drivers for UTA Size ....................................................................................................................... 11 4.1 Consequences ....................................................................................................................... 11 4.2 Forward Planning ................................................................................................................... 12 Installation Systems ....................................................................................................................... 13 5.1 Installation Methods ............................................................................................................... 13 5.2 Handling Restrictions ............................................................................................................. 14 5.3 Vessel Implications and Consequences ................................................................................ 16 6 Guidance for UTA Optimisation ...................................................................................................... 19 7 Workflow for Selection and Sizing of the UTA ............................................................................... 22 7.1 Category functionalities ......................................................................................................... 23 7.2 UTA Categorization Method .................................................................................................. 24 7.3 Selection of packing reel or carousel ..................................................................................... 25 7.4 SUT rigid length ..................................................................................................................... 26 7.5 Optimisation Assessment ...................................................................................................... 35 Appendix A: Packing of a UTA with the confines of a reel .................................................................... 36 Appendix B: Fault tree analysis (FTA) ................................................................................................... 39 Appendix C: STI and SUT length calculations ...................................................................................... 42 Appendix D: Steel tube Umbilical or Thermoplastic Umbilical with spool ............................................. 44 Appendix E: False Barrel Diameter calculations ................................................................................... 46 Appendix F: Responsibility Matrix (informative) .................................................................................... 48 Document1, 5 July 2015 2 1 1.1 Scope Introduction This document was generated, by means of the UMSIRE (Umbilical Termination Size Reduction) Joint Industry Project (JIP) in response to the increasing difficulties in installation of high-functionality Subsea Umbilical Terminations (SUTs), due to their increasing size. The JIP committee comprised a representative cross section of experienced industry personnel from engineering, installation and operational organisations. Whilst there are widely accepted standards for the design of a SUT and its sub-systems, none of these standards specifically address the subject of the risks of installation, and the measures required to minimise these risks. The UMSIRE deliverables are two API documents, 17TR9: Subsea Umbilical Termination (SUT) Selection and Sizing Recommendations and 17TR10: Subsea Umbilical Termination (SUT) Design Recommendations. This document is intended to be used as a reference guide by operators, UTA and umbilical specifiers, installers and FEED companies. It is also intended to be used as a reference document to enable reviews to be undertaken to ensure that installation risk has been properly considered as part of SUT design and operations reviews. This document assumes that the reader has a good level of understanding of the design, engineering and installation of UTAs. The 17TR10 can be referred for educational purpose and for additional technical information on UTAs. The intent with describing these project stages (see Figure 1) is to clarify when within the umbilical project timeline each UMSIRE document should be referenced, and the interested parties that should be involved in discussions during each stage. 1.2 Document purpose This document aims to: Highlight technical and commercial risks associated with high functionality umbilicals and umbilical terminations, especially with respect to installation. Describe the implications of decisions made early in the umbilical and SUT planning, selection and design phases Provide guidance on specifications and respective sizes of umbilical terminations. This is intended to aid the making of informed choices during the early design phase. The primary aim of this document is to be a reference guide during early field development planning stage to ensure that due considerations are given to the implications of the size of UTAs and possible consequences during installation. The guidelines for the design of UTAs are included in API 17TR10. 1.3 Use of the Document The users of these Design Recommendation TR’s are primarily intended to be operators, SUT designers and FEED companies. Umbilical system design and manufacturing roles and responsibilities are defined in Annex A. This document should be read in conjunction with API 17TR10 which aims to provide best practice technical guidance for SUT design, in order to aid in making informed choices during the design phase. Document1, 5 July 2015 3 This document has an educational purpose and is intended to be descriptive rather than prescriptive. It is important to note that none of the following sections should be read in isolation. 1.4 Applicability In recent years, the size and complexity of umbilical terminations have grown considerably, driven by increasing subsea power, communication and fluid delivery requirements, as well as the need to integrate functions normally found on manifolds. Due to some of the existing lay spreads and their long service life, the equipment has been unable to keep pace with these UTA changes. It also appears that the difficulties and increased risk implications incurred during installation of excessively large UTAs are not given the due consideration during early planning stages. Historically in some cases the design has been such that the UTA cannot be easily deployed when connected to the umbilical by conventional installation methods. This emerging trend poses severe challenges to installers and appears to be compounded by the increased functionality and higher expectations of parties in the supply chain (FEED contractors, termination designers, operators and manufacturers) This trend has led to occurrences where the SUT either cannot be installed through conventional lay equipment which results in the necessity for higher specification lay spreads and vessels and proportionately increased risk to personnel, equipment, schedule and overall project cost impact. Without full consideration of these collective impacts this trend of higher functionality and proportionately larger UTAs is expected to continue. It is acknowledged that having a separate Subsea Distribution Unit (SDU) may have an impact on the overall cost. However, the costs of the UTA / SDU alone should not be the deciding factor in increasing the UTA proportions and weight to achieve an all-encompassing single UTA. Further analysis should be undertaken throughout the lifecycle of the UTA, which may include the following: Packing, transporting and increased installation costs of the larger unit in conjunction with a risk analysis Assessment of the aforementioned factors with detailed examination of the increased risks in offshore handling, deployment and lay-down on the seabed This final UTA design approval should be made following close scrutiny of these analyses and assessments in order to balance costs against increased risk. The applicability of 17TR9 will be during all stages of UTA concept selection, design and installation. The figure below shows the applicability of both 17TR9 and 17TR10 by all the parties involved. Document1, 5 July 2015 4 Figure 1: Project stage chart The intent with describing these project stages is to clarify when within the umbilical project timeline each UMSIRE document should be referenced, and the interested parties that should be involved in discussions during each stage. Readers should be aware that integration of distribution leads to a significant increase in size of the UTA, although it is required in some cases. For the purposes of this document, it is assumed that the termination does not provide distribution. The UMSIRE JIP Following an Umbilical Manufacturers’ Federation initiative, several major umbilical installation contractors (Acergy, Saipem UK, Subsea 7 and Technip) and OTM Consulting collaborated towards the launch of a JIP for the development of two API documents. These documents address the necessity to optimize the shape, dimensions and overall weight of UTA’s. The UMSIRE JIP objective is to reduce the size of UTA’s through increased understanding of the key issues associated with their design, manufacturing and installation, resulting in the development of a recommended guideline. Document1, 5 July 2015 5 2 REFERENCES The following referenced documents are indispensable for the application of this document. For dated references, only the edition cited applies. For undated references, the latest edition of the referenced document (including any amendments) applies. API 17TR10, Subsea Umbilical Termination (SUT) Design Recommendations API Specification 17D, Specification for Design and Operation of Subsea Production Systems API Specification 17E, Specification for Subsea Umbilicals API Specification 17F, Specification for Subsea Production Control Systems 3 TERMS, DEFINITIONS AND ABBREVIATIONS 3.1 Terms and Definitions For the purposes of this document, the following terms and definitions apply. 3.1.1 bend limiter (from the UMF Glossary of Terms) A device for limiting the bend radius of the umbilical, usually by mechanical means, typically comprising a series of interlocking metal or polymeric collars designed to lock at a pre-defined radius. NOTE: This is sometimes known as “bend restrictor”. 3.1.2 bend stiffener (BSR) (from the UMF Glossary of Terms) A device for controlling bending strain in the umbilical by providing a localised increase in stiffness; usually a moulded device, sometimes reinforced depending on the required duty, applied over the umbilical. NOTE: This is sometimes referred to as a “bend strain reliever”. 3.1.3 rigid length The rigid length is the sum the combined lengths of the UTA and STI and any other component that increases the axial rigid length and cannot easily be removed or re-installed offshore. Depending on the configuration, rigid length can be calculated by three different ways, as outlined below. If the UTA is equipped with a bend stiffener, the rigid length will be the sum of length of UTA, STI and 1/3 of the length of bend stiffener, as shown in Figure 2 o Rigid length = UTA + STI + (BSR/3) If the UTA is equipped with a bend restrictor, the rigid length will be the sum of length of UTA, STI and the length of 1st interface flange (axial rigid length of bend restrictor), as shown in Figure 3 o Rigid length = UTA + STI + L If the UTA is not equipped with a bend stiffener or bend restrictor, the rigid length will be the sum of length of UTA and STI, as shown in Figure 6. (Note: It is recommended that either a bend stiffener or bend restrictor is always used) o Rigid length = UTA + STI Document1, 5 July 2015 6 Figure 2: Rigid length with a bend stiffener Figure 3: Rigid length with a bend restrictor Document1, 5 July 2015 7 Figure 4: Rigid length without bend restrictor or stiffener 3.1.4 subsea termination interface STI Mechanism that forms the transition between the umbilical and the UTA 3.1.5 subsea umbilical termination SUT Mechanism for mechanically, electrically, optically and/or hydraulically connecting an umbilical or jumper bundle to a subsea system and contains the UTA (Umbilical Termination Assembly) and STI (Subsea Termination Interface) but does not include bend restrictors or stiffeners. NOTE Figure 2 illustrates the terminology that will be adopted in the context of the UMSIRE JIP which is aligned with API’s nomenclature. 3.1.6 umbilical Line Functional component within the umbilical, providing hydraulic/electrical or optical service NOTE API 17E states that functional components are hoses, tubes, electric/optical fiber cables included within an umbilical which are required to fulfil the operational service needs 3.1.7 umbilical termination assembly UTA A mechanism for mechanically, electrically, optically and hydraulically, as required, connecting an umbilical or jumper bundle to a subsea system 3.1.8 UTA Yoke A frame attached to a UTA, typically at its sides, by hinged or swivelling joints and provided with a central attachment point for lifting rigging. The yoke allows the UTA to rotate during installation, e.g. in a “stab and hinge over” mode of deployment where it is lowered vertically until its hinged docking probe engages with a receptacle on the mounting base, then rotates until landed horizontally as the umbilical is laid away. Figure 5 and Figure 6 shows UTA with and without a docking probe respectively. Document1, 5 July 2015 8 Figure 5: UTA without a docking probe Figure 6: UTA with a docking probe Document1, 5 July 2015 9 3.2 Abbreviations API American Petroleum Institute FBC Free Board Clearance FEED Front-End Engineering Design JIP Joint Industry Project MBR Minimum Bend Radius MQC Multiple Quick Connects OD Outer diameter UMF Umbilical Manufacturers’ Federation UMSIRE Umbilical Termination Size Reduction [name of the JIP that created this document] SDU Subsea Distribution Unit SPS Subsea Production Systems STI Subsea Termination Interface SUT Subsea Umbilical Termination TR Technical Report UTA Umbilical Termination Assembly VLS Vertical Lay System Document1, 5 July 2015 10 4 Drivers for UTA Size The trend of increasing functionality of topside, subsea and downhole equipment over the past decade has created greater requirements for additional fluid, electrical and optical lines to be routed from the platform to the subsea equipment. This result in a greater number of functionalities required through control umbilicals and consequently the UTAs. A further consequence requiring larger umbilicals results from the lack of sufficient platform J-Tubes for umbilicals. There is competition for space between umbilicals and production risers, for which the umbilical is often seen as a lower priority on a basis that one large umbilical is more space efficient than multiple smaller umbilicals, hence larger umbilicals are envisaged to be the best option during field development planning. 4.1 Consequences The increasing size of umbilicals and UTAs due to the drivers identified above, has consequences related to the design, manufacturing and most importantly during installation of UTAs. The figure below shows the consequence of increasing size of UTAs (from category A to D, as described in section 7.2) on the overall risk and complexity of the installation operation and availability of installation vessels, which has a direct impact on the overall cost. Figure 7: Consequence of increasing size of UTAs The consequences in terms of cost, schedule and technical risks are listed below. Cost Oversize terminations often require a bespoke solution leading to “re-inventing the wheel” syndrome and additional design and engineering Packing and handling the UTA on a reel may be no longer possible A carousel equipped vessel or individual carousels may require mobilisation with additional engineering and mobilisation man-hours Handling and transportation difficulties Schedule Increase in lead time Longer fabrication and assembly Complex FAT – Factory Acceptance Tests Increase in vessel mob/demob and installation time Document1, 5 July 2015 11 Limited Installation Vessel availability Technical Risk Together with terminations, bend stiffeners and bend restrictors have grown in size and weight Lack of clear definition of acceptable level of risk resulting in over-engineering UTAs are not properly designed for lifting and over-boarding Onshore handling heavy UTAs connected to weak umbilicals increases the probability of damage to the umbilical Offshore installation of heavy UTAs connected to weak umbilicals substantially increases the probability of damage to the umbilical and substantial project schedule delays. The consequences due to increased size of umbilicals and UTAs can also be understood by an analytical method such as FTA (fault tree analysis). The Figure 18 and Figure 6 shows a FTA methodology used to highlight the main risks, associated parameters and consequences. 4.2 Forward Planning During field architecture concept definition and the design phase, consideration must be given for future expansion and limitations of the field. Consideration should be made for provision of additional future J-Tube slots for controls umbilicals. This will mitigate the competition for Umbilical J-Tube slots in the future. Careful consideration of the number of umbilical functions required (including any functions in line with the projects sparing and possible expansion requirements) and the resultant installation feasibility should be made at every stage of the SPS design. Reducing the number of umbilical functions will reduce the size of the umbilical and UTA installation. Reducing the size of the UTA is encouraged wherever practical. UTAs can be installed and recovered independently of their support frame or SDU and incur simpler interface points with which to dock and engage the UTA onto the support/SDU. Multi-bore hubs can bring all the required functions to the SDU where the full function distribution and outlet ports are incorporated within. If an additional SDU installation is required, it can: Enable a much simpler deployment of SDU and umbilical individually Alleviate complex handling Mitigate much of the installation/recovery and/or re-installation risks Document1, 5 July 2015 12 5 5.1 Installation Systems Installation Methods There are several industry standard umbilical installation methods such as; 1. Horizontal lay tensioner and over-boarding chute for low tension installation. 2. Horizontal lay tensioner with vertical over-boarding system for low/medium tension installation of umbilicals with ancillary components such as buoyancy modules, clamps, bend restrictors, etc 3. Closed Vertical Lay System for general installation of umbilicals including those with higher top tension. These systems have limitations due to UTA having to pass through the closed tensioner aperture. 4. Open Vertical Lay System for general installation of umbilicals including those with higher top tension. These systems do not have limitations due to UTA having to pass through the closed tensioner aperture. 5. Rigid Pipe Lay Systems (open or closed) used for installation of umbilicals, normally as part of rigid pipelay installation. More detailed descriptions of the above installation methods are presented in API 17TR10 Chapter 9. Figure 8 and Figure 107 show the typical operational sequence and geometric limitations of a VLS system. Figure 8: Vertical Lay Installation, first end (Source: Technip) Document1, 5 July 2015 13 Figure 9: Vertical Lay Installation, second end (Source: Technip) 5.2 Handling Restrictions The following factors should be considered during SUT design to best comply with handling constraints and requirements of the SUT and Umbilical Installers: 1 Factor UTA width and height 2 Handling points on UTA considering installation through the lay system and sea-fastening 3 Weight and centre of gravity of UTA 4 SUT total rigid length 5 UTA and umbilical structural design 6 Umbilical length & weight 7 Design of UTA bend stiffeners and UTA yokes 9 Installation of mudmats or support structures Document1, 5 July 2015 Reasons for Importance Ability for UTA to pass through tensioners and deck openings. Ability to accommodate UTA on reels and on carousels. Sea-fastening design, deck handling, lift planning and lift rigging design. Overboarding operations. Deck handling, lift planning and lift rigging design. Overboarding and landing operations. Ability to accommodate UTA on reels and on carousels. Ability to lift UTA over arch and into VLS. UTA design to withstand the loads imposed during handling and installation. UTA design to withstand the loads imposed by the umbilical during handling and installation. Ability to accommodate UTA on reels and on carousels. Ability to lift UTA over arch and into VLS. Deck handling, lift planning and lift rigging design. Overboarding and landing operations. Design of UTA docking facilities, latching arrangements and support structures. 14 9 Factor Critical installation parameters Maximum umbilical tension < allowable value Maximum umbilical compression < allowable value Umbilical MBR > allowable value Document1, 5 July 2015 Reasons for Importance Compliance with product integrity 15 5.3 Vessel Implications and Consequences The installation-related consequences of increasing UTA size include the following, and more: Consideration 1 Safety Implications 1a Danger in handling a large / heavy load at height. 1b Danger from vessel motions caused by the sea state. 2 Cost (associated with vessel capacity) 2a Reel/Carousel capacity 2b Required tensioner length / VLS capacity 2c Handling method requirements 3 Schedule 3a Vessel availability 3b Safe handling weather window 3c Geographical location Document1, 5 July 2015 Explanation and Potential Consequences The larger and heavier the UTA the higher the risk factors with regard to safety of personnel and the product(s) (UTA and umbilical). This applies onshore as well as offshore. If UTA proportions are out-with Installation Vessel crane and handling equipment capacity it may necessitate a Port Call to enable quayside crane intervention (first end lay) or 2nd vessel crane (first or second end lay). If the sea state is worse than that acceptable for safe handling of the UTA there may be delays associated with waiting for improvement or else sailing to port or sheltered water. Increasing UTA proportions size leads to increased handling complexity resulting in the need for higher specifications for installation systems (and vessels) along with additional UTA handling and deployment equipment. Influenced by UTA functionality, umbilical length, water depth, weight of umbilical, MBR and rigid length. Increasing capacity requirements can lead to restricted choice of vessel, more expensive vessel, or additional port-calls and re-mobilisations. Choice of tensioners and laying system is driven by top tension (SUT dimensions / weight, umbilical weight, water depth) and installation method. More onerous demands on VLS / Lay System capability can lead to restricted choice of vessel specification and charter costs. A need to handle a larger / heavier UTA tends to result in a need for higher rated equipment, more items of equipment, more complicated equipment - all leading to greater cost. Consequences of handling a large / heavy load at height has been described in item 1a. Increasing the UTA size tends to increase the risk of extension to schedule due to complexity in handling, intervention and installation. It is possible for a small growth in size to cause a large schedule impact. A restricted choice of vessel can lead to schedule delay owing to the reduced availability of suitable vessels. Such a restricted choice could be caused by the need for a VLS, an open tensioner VLS or a larger capacity carousel. The acceptable weather conditions for UTA and umbilical installation will be diminished and less frequent as UTA size increases or umbilical strength decreases, resulting in project schedule delays. A large UTA can result a restricted choice of vessel could result in schedule delay owing to transit time for suitable vessel to the work locations. 16 Consideration 4 Technical Risk 4a Technical Risk Reliability Explanation and Potential Consequences The technical risks associated with UTAs are likely to increase with their size, with consequent safety, reliability, cost and schedule implications. Increased functionality can have implications on long term reliability Water Depth It is considered that at larger water depths compared to shallow waters will lead to the following: o o o o the top tension will increase with a potential consequence to laying spread the crane / winches involved will have to reach deeper and possibly will require higher capacity the structure of the umbilical will potentially have to be more robust, i.e. possibly heavier and more expensive The time to deploy and install the umbilical system is likely to increase Limiting Sea state A higher limiting seastate (Hs) gives increased flexibility in terms of schedule and planning, as well as less exposure to reduced weather windows. A low limiting seastate may give constraints in installation methodology, risk of waiting on weather, risk to product during installation, etc. Type of laying system The optimum scenario is that the umbilical system can be installed with any available system (i.e over the stern, open / closed VLS, other – ref. API 17TR10 Section 9.4 for description of laying systems). In a less than optimum scenario, the umbilical system can only be installed by certain systems, e.g. open VLS if the UTA is very large etc. or for purpose built systems. The type of laying system still depends on the choice of the installer and the vessel spread availability. It should also be noted that various geometrical constraints linked with the various laying systems may influence the optimal choice of system. (Ref. Section 9 of API 17TR10) Rigid Length The total rigid length of the UTA assembly is defined section 3.1.3 with examples on figures 2, 3 and 4. A longer length of UTA is worse for handling and installation through laying systems due to geometrical constraints when interfacing and passing through these systems. Rigid lengths above a certain length may not be installable using standard methods. Reference is made to Section 6.11 of API 17TR10. A shorter length of UTA is preferable for handling and installation, also may improve the choice of alternative laying systems available. Minimum Bending Radius The limiting minimum bend radius (also referred to as allowable bending radius, varying with various stages of the operation) is less than optimal when a large radius is required, as this has a direct impact on vessel layout, lay spreads, installation methods, complexity etc. A smaller limiting radius gives increased flexibility versus handling and installation. Document1, 5 July 2015 17 SUT Weight Very heavy SUTs are less practical from handling point of view, versus vessel lay spreads, cranes and winches, safety of product and personnel. Special installation aids, installation methods and installation spreads may be required. Size of foundation structure The foundation structure (folded / open mud mats, support structure, etc) will increase the total size of the assembly and is either installed with the umbilical at launch or connected to the umbilical / UTA at the seabed. A larger UTA will require a larger size of foundation is therefore worse for handling on deck and for launching through the moon pool and through the water column. A smaller and more compact foundation structure or pre-installed design (on seabed) is more favourable in terms of handling and installation and induces less risk on the umbilical and UTA deployment. Installation Vessel Time Line The time taken from UTA definition to offshore installation can influence the choice and availability of vessels and laying systems availability. A short time to plan and execute the operation may be worse in terms of vessel availability and choice of laying systems, while a longer time period between design and UTA completion may give increased flexibility in terms of schedule and planning. Delivery method In the best case scenario, all packing systems can be utilized for transport and installation, i.e. baskets, reels or internal / external carousels etc. In the less than optimal case where the umbilical is particularly long or UTA is unreasonably large, only particular packing systems can be used e.g. an external carousel and open tensioner VLS system. Installation Complexity In a less than optimal case, the standard available laying systems are not suitable to install very large and complex UTA / umbilical systems, moon pool may not be large enough, etc. In such a case, specially engineered installation systems may be need to be designed and fabricated for use onboard the installation vessel to comply with complex handling and installation requirements – with the consequence of increased schedule and cost impact. Document1, 5 July 2015 18 6 Guidance for UTA Optimisation The size of the UTA can have enormous impact on the duration and cost for the installation of umbilical’s and its UTA’s large/ complex UTA size can cause: Bespoke, time consuming installation methods and costly onshore trials Specific requirements on installation vessel and equipment Reduced installation window due the limited acceptable environmental installation condition Limited availability of suitable installation vessels Time consuming and complex packing, transporting, mobilisation and offshore deployment As the impact of the UTA size can be significant, it is recommended to perform an optimization of the UTA size during the conceptual definition phase of the system layout. The optimization model provides the method of optimizing the size of the UTA during the concept stage of the development of a system. The model provides the opportunity to perform an optimization of the UTA size considering key aspects of the system layout. The model is structured in three elements: Optimization process Key Optimization Aspects Optimization Matrix 6.1 Optimization Process Once the first draft of the system is present the optimization can be started based on the following process below in combination with the information of the earlier chapters of this document. After each of the optimization process steps the key system questions should be answered and documented within the optimization matrix. Once modifications of the UTA and/ or system have been implemented, the process shall either be continued at the same level or re-started at one of the previous levels. Document1, 5 July 2015 19 System Functional Design Requirements UTA OPTIMIZATION “System layout versus UTA size” Figure 10: UTA optimisation process 6.2 Key Optimization Aspects During the concept phase for the development project not all details about the proposed equipment are available. Due to that, the optimization process concentrates on a few key aspects. These aspects are: Field architecture, o Arrangement of drill centres and system layout o Umbilical system and umbilical function o Field environmental conditions, e.g.: seabed load-bearing capacity, tide, sea state, visibility condition o Use of SDU in conjunction with UTA UTA Functionality o Termination of the umbilical services o Distribution (e.g.: teeing of lines, electrical distribution units etc.) o Isolation, reconfiguration option (gate/ ball valves, logic caps) Line Size o Flow-assurance o Bending radius Spare philosophy o Number of spare lines/ cables o Accessibility of spare lines Level of technology New technology development Qualification (for product and/ or system) Foundation arrangement o Type of foundation structures (e.g. mudmat, suggestion pile, single or combined foundation Document1, 5 July 2015 20 o Installation method (combined or separate, permanent attached, disconnectable subsea) In early conceptual and front end engineering phases of field layout, strong consideration should be given to the number of wells to be served by a single umbilical. This directly influences the required number of functional elements in the umbilical, and ultimately is truly what governs the size of the UTA. Limiting the number of functional elements to a practical amount is a preferred method of limiting the size of a UTA, as opposed to limiting or eliminating the ability to utilize spare lines or compromising on design reliability with respect to materials of construction, minimum bend radii, and the number of welded fittings. 6.3 Optimization Matrix The optimization matrix below has been developed: to perform the optimization process systematically to gain overview and awareness which system design aspects influence the UTA size/ complexity to document the decisions/assumptions being made during FEED/ tender stage This matrix should be used during all the stages of the optimization process. For the different process steps, the matrix can be extended as needed, as this list is not exhaustive. Key Aspects Why is the UTA large/ complex? Can the size / complexity be reduced? Yes?/No? Process step: Consideration of installation aspects Process step: Evaluation of packing option Process step: : UTA Categorization Field architecture UTA Features Line Size Sparing philosophy Level of technology Foundation arrangement Field architecture UTA Features Line Size Sparing philosophy Level of technology Foundation arrangement Field architecture UTA Features Line Size Sparing philosophy Level of technology Foundation arrangement If yes, HOW? If not: WHY? Table 1: Optimization matrix Upon completion of this process, the UTA size should be optimised as much as the system allows. The matrix also provides an overview of the aspects which influences the system layout aspects, size and complexity of the UTA. During project execution, the matrix should be used to develop mitigation plans when the size and complexity can be optimised no further. This should instigate critical activities such as development work, qualification, vessel selection to address the challenging installation scenarios. Document1, 5 July 2015 21 7 Workflow for Selection and Sizing of the UTA The aim of the workflow is to guide the user through a sequence of steps, to understand the implications of the decisions made during early design phase. The workflow comprises of selection of UTA category and packing, followed by an optimisation assessment leading to optimised UTA size, design and installation. Figure 11 below shows the five sub-components of the workflow. • Category Functionalities • UTA Categorization Method • Selection of Packing Reel/ Carousel • SUT Rigid Length • Optimisation Assessment Figure 11: Workflow of the selection and sizing of the UTA Document1, 5 July 2015 22 7.1 Category functionalities Table 2 below indicates typical maximum functionalities that can be specified for each category of UTA, with the categories defined as in Figure 9 of section 7.2. UTA Functionalities Category A UTA To fit Closed Tensioner Aperture Ø Category B UTA Category C UTA Category D UTA 1.2 m 1.4 m 1.6 m >1.6 m (requires an open tensioner) MQC Plates 2 MQC plates with 7 lines each (2 up to 3/4''OD and 5 up to 1/2'' OD) 2 MQC plates with 10 lines each (4 up to 3/4''OD and 6 up to 1/2''OD) 4 MQC plates with a total of 24 lines (maximum of 4 up to 1’’OD, 8 up to ¾’’OD and 12 up to ½’’OD) >4 MQC Cables A total of 6 optical and electrical umbilical cables each terminating to a single connector, of which a maximum of 2 are fiber optics. 6 electrical umbilical cables each terminating at a single connector, and 2 fiber optic umbilical cables each split into 3 connectors 6 electrical umbilical cables each terminating at a single connector, and 2 fiber optic umbilical cables each split into 3 connectors More than 6 electrical umbilical cables each terminating at a single connector, and more than 2 fiber optic umbilical cables each split into 3 connectors Valves No No Not recommended Possible Distribution No No Possible Possible Max. UTA length (including the padeye) 3m 3m 3.5 m >3.5 m (depending on handling limitations) ROV operable Yes Yes Yes Yes Note: The UTA length may exceed theses recommended values while optimizing the all-over length of the SUT or rigid length with the length of the STI and bend limiter properties. Table 2: Functionalities of UTA categories A, B C and D Document1, 5 July 2015 23 The table below gives an indication of typical STI dimensions. UTA Category Total STI Length (mm) Max STI flange diameter (mm) Minimum interface aperture in UTA (mm) X Y Recommended Default Z Recommended Default A (steel tube) 1175 - 1400 650-710 ASME/ANSI B16.5 Class 300 – 20” 390 - 432 20” (510mm) A (thermoplastic hose)* 370* 650* ASME/ANSI B16.5 Class 300 – 20” 390* 20” (510mm) B (steel tube) 1250 - 1800 775 ASME/ANSI B16.5 Class 300 – 20” 480 - 550 20” (510mm) B (thermoplastic hose)* 420* 650* ASME/ANSI B16.5 Class 300 – 20” 390* 20” (510mm) C (steel tube) 1300 - 1900 770 - 838 ASME/ANSI B16.5 Class 300 – 20” 490 - 550 20” (510mm) C (thermoplastic hose)* 510* 650* ASME/ANSI B16.5 Class 300 – 20” 390* 20” (510mm) * Thermoplastic hose STI dimensions are examples from one umbilical designer only Table 3: Ranges of STI dimensions advised by umbilical designers The table gives an indication of typical STI dimensions where it has not been possible to integrate the STI into the main UTA body. In some cases STI may be integrated in the UTA, thereby the length of STI will be much shorter than the indicative figures in the table above. The total STI length may include the first joint in the bend restrictor interface when it is included as a machined part of the armour body. The total rigid length includes this interface as shown in Figure 3. 7.2 UTA Categorization Method This section described the methodology for UTA size categorization adopted by the UMSIRE JIP. UTAs have been classified into four categories depending on the limiting factors of installation systems. Each category of UTA has been based on the level of functionality that can be incorporated within each envelope as described in table 2 UTA Categories Four UTA categories are defined as follows: Category A: up to 1.2 m closed tensioner diameter Category B: up to 1.4 m closed tensioner diameter Category C: up to 1.6 m closed tensioner diameter Category D: >1.6 m (requires open tensioner) The categories are defined by the closed tensioner aperture as shown in the diagram below. The UTA cross-section must stay within and be free to rotate within the circle enclosed by the aperture. Figure 12 shows a 4-track tensioner, although other designs exist in the industry. Document1, 5 July 2015 24 Category Tensioner opening A ≤ 1.2m B ≤ 1.4m C ≤ 1.6m D > 1.6m Figure 12: Closed Tensioner Opening Clearance must be considered to allow the SUT to pass through the tensioner without issue. Certain items may be temporarily removed to allow the SUT to pass freely through the tensioner. The minimum radial clearance to tensioner aperture should typically be 50mm (for category A to C), depending on geometrical layout and handling constrains (ref. Figure 12). Certain items, such as protective covers, may be temporarily removed to allow the SUT to pass freely through the tensioner. 7.3 Selection of packing reel or carousel Figure 14 below shows the methodology for selection of packing. The selection is based on three main criteria, if all three criteria meet the specifications, the installation using a reel will be more favourable. The total system weight refers to weight of umbilical, fluid, terminations, reel (including cradle and the partitions. The maximum rigid length check and the umbilical length check can be carried out with the help of calculations such as described in Appendix B. Document1, 5 July 2015 25 UTA Category (Table 1) Tensioner Type (Figure 7) A B C CLOSED / OPEN (350 tonne typical , 350 to 500 tonne special case only Total System Weight Check < 350 tonne D OPEN No Yes No Max rigid Length check Equation 2 Yes No Yes A to D Umbilical Length Check Equation 3 Installation Reel Vessel Carousel Figure 13: Flow chart for selection of packing reel/ carousel Equation 2 and equation 3 have been included in Appendix C. 7.4 SUT rigid length The SUT rigid length is calculated based on the UTA dimensions and the STI length. The UTA dimensions are obtained from section 7.1 and the following section describes STI length calculations. Figure 14 shows the rigid length with a bend stiffener connected with the STI. As described in section 3.1.3, the rigid length will differ in other cases depending on if the SUT is connected with either a bend stiffener or a bend restrictor, or none of them. Document1, 5 July 2015 26 Figure 14: Rigid length The maximum permissible Rigid Length should be considered for two operational cases; storage and as installed. Storage Rigid Length - The total length of the UTA taken from the end of any padeyes or hold down points plus the STI (if not incorporated into the UTA) with the Bend Restrictor or BSR not attached. This will allow a longer UTA to be stored on the reel prior to deployment. As Installed Rigid Length - The total length of the UTA taken from the end of any padeyes or hold down points plus the STI (if not incorporated into the UTA) plus the Bend Restrictor interface or 1/3 rd BSR length installed in position. This allows overboarding and deck handling requirements for the different lay methods to be reviewed with the umbilical in the installed condition. The remaining Bend Restrictors elements are attached prior to overboarding in a suitable location as determined by the installer. Further details on rigid length and STI have been provided in section 6.11.1 of API17TR10. STI Length Calculation The formulas for calculating length of STI have been included in Appendix C (STI and SUT length calculations). The formulas are intended to provide an initial sizing of the STI length based on the reel diameter, umbilical (MBR & diameter) and UTA size (L & H). Some of the important assumptions incorporated in the calculation method are as follows: The umbilical MBR should be equal or greater than the reel barrel radius The UTA is box shape (side view) and does not have large extending brackets or component’s on the top, base or front The free board clearance (FBC) is the same for both the umbilical and UTA Packing configuration as per Error! Reference source not found. Document1, 5 July 2015 27 The rigid length in Error! Reference source not found. is indicated as the sum of the length of UTA and STI, without a bend stiffener or a bend restrictor. If a bend stiffener or a bend restrictor is used, the rigid length will be different, as described in section 3.1.3. Note: It is recommended that a bend stiffener or a bend restrictor is always used. Document1, 5 July 2015 28 Document1, 5 July 2015 29 Figure 15: UTA packed within reel flanges (to allow 2nd end lay) The maximum STI length can be obtained from figure 11 or can be calculated by using the equations mentioned in Appendix B. In some cases the barrel radius can be increased by adding a suitable packing structure to increase the barrel radius. This may also be extended into both bay A and bay B, (as shown in figure 14 and in Appendix E). Figure 16: Illustration to show increased barrel radius by using packing structure (size view) Equation 4 in Appendix E contains the details of false barrel diameter calculations and the symbols used. Document1, 31 August 2015 30 Figure 17: Illustration to show increased barrel radius by using packing structure (front view) Table 4 shows the maximum STI lengths based on UTA categories, umbilical MBR and reel size. The table provides guidance for STI lengths based on MBR range between 1-4 metres. For specific project requirements the user can refer to the length equations in Appendix C. The main purpose of the table is to act as a quick reference guide for checking whether the results of preliminary evaluation of umbilical length and the UTA dimensions will fit on the desired packing (reel/ carousel). The range of MBR, reel diameter and barrel diameter in the table has been chosen on the basis of project experience, with an aim to provide an example of how such an exercise could be conducted. The recommendation to the reader of the document is that an equivalent table must be constructed for field specific requirements and range of possible umbilical and UTA dimensions. Document1, 31 August 2015 31 The table can prove to be a useful and flexible tool which can be adjusted depending on project specific conditions, drivers and requirements. The aim of the table is not to act as a comprehensive guide, but to be used as an approach for making a systematic methodology which can be effectively used on projects. The table can be expanded or modified to suit individual project requirements. Table 4 refers to technical terms such as reel, false barrel. A reel used for umbilical storage, transportation or installation has a cylindrical barrel fitted with larger diameter flanges at each end. An intermediate circular partition may be provided to divide the usable space on the reel into two compartments: one of which may be used for storing the main quantity of umbilical and the other used for containing a UTA. The partition is provided with a cross-over gate (aperture) to allow the umbilical to pass between one compartment and the other. A false barrel may be fitted to increase the effective central diameter of the reel when its use is dictated by the minimum bend radius of the umbilical being carried. The edges of the flanges are reinforced to allow the reel to rest on deck or underrollers. The barrel usually projects slightly outboard of the flanges to allow slings to be passed round it for lifting purposes. Document1, 31 August 2015 32 Rigid length (Lrigid) UTA Size Category Reel (m) Ø Rim Ø Barrel 6 2.0 3.0 7 3 4 8.6 4 5 6 9.2 4 5 6 9.8 4 5 6 11.2 4 5 6 8 11.4 5 6 8 (…..) (…..) A B C Umbilical MBR range (m) Umbilical MBR range (m) Umbilical MBR range (m) 1.0 3.37 3.37 4.4 3.37 4.4 4.4 3.37 4.4 4.4 4.4 4.4 4.4 4.4 4.4 4.4 4.4 4.4 4.4 4.4 4.4 2.5 (4.4) 3.37 3.37 (4.4) 4.4 4.4 (4.4) 4.4 4.4 (4.4) 4.4 4.4 4.4 4.4 4.4 4.4 4.0 (4.4) (4.4) 3.37 (4.4) (4.4) 3.37 1.0 3.42 3.42 3.42 4.8 4.8 3.42 4.8 4.8 3.42 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 4.8 2.5 4.0 1.0 2.5 4.0 4.01 (3.42) 3.42 5.4 4.01 (4.01) 4.01 (4.8) 4.8 3.42 (4.8) 4.8 4.8 (4.8) 4.8 4.8 4.8 4.8 4.8 4.8 5.4 5.4 4.01 5.4 5.4 5.4 5.4 5.4 5.4 4.01 5.4 5.4 5.4 (4.01) 4.01 (3.42) (4.8) (4.8) 3.42 (4.8) (4.8) 3.42 (5.4) 5.4 4.01 (5.4) 5.4 5.4 4.01 (5.4) 5.4 4.01 (5.4) (4.01) (4.01) (5.4) (5.4) 4.01 Steel tube or thermoplastic STI Steel tube or thermoplastic STI, umbilical requires false barrel Thermoplastic STI only Thermoplastic STI only, umbilical requires false barrel Insufficient space for STI & UTA or MBR Table 4: Variation of rigid length with varying reel diameter and UTA size category Note: Rigid length is calculated from the combined maximum values for STI length from table 3 & UTA length from table 2. The dimensions given in Table 4 are the maximum rigid lengths that can be used for either steel or thermoplastic umbilicals for a given UTA category and MBR. The two examples below show how the above approach can be used. The Table 4 can be used in two ways: Example 1 If the available option has restricted the maximum reel diameter to 9.2m and have a 2.5m MBR steel tube umbilical fitted with category “C” UTA:. It can be seen from the table the only option available is a thermoplastic umbilical due to the maximum rigid length of 4.01m. Document1, 31 August 2015 33 Notes: 1. A steel tube option maybe possible, however it will need to be designed within the 4.01m rigid length 2. If the barrel diameter is less than 5m, then a false barrel will be required 3. A larger diameter reel may be required to accommodate the actual umbilical length. Example 2 If the available option is to have a 2.5m MBR steel tube umbilical fitted with category “C” UTA: the first available reel diameter is 9.8m with a 5m barrel. Notes: 1) A 4m barrel could be used with a false barrel. 2) A larger diameter reel may be required to accommodate the actual umbilical length. Document1, 31 August 2015 34 7.5 Optimisation Assessment The optimisation assessment aims to guide the user through the process for optimising the process of installation of umbilical and UTA. The methodology takes into account several factors such as the environmental conditions (water depth, sea state), installation system, size and weight of the structure. The aim of this table is to provide guidance to the user for being aware of the consequences of UTA size relating to optimisation and installation operation. The table should be used to assess the implications in terms of cost, schedule and risk. Table 5: Optimisation assessment Document1, 31 August 2015 35 Appendix A: Packing of a UTA with the confines of a reel Design considerations: Packing Design When considering the packing of a UTA within the confines of a transport / installation reel, the design engineer shall assess the methods required for packing onshore and un-packing offshore with consideration to the following: Safe access to ALL rigging when onshore and offshore with zero or minimum at height working The project offshore lifting standard and certification requirements UTA, 1st and 2nd end lay, note 1st lay could be position outboard of the reel Reel Hub Drive system or under roller Working clearance between UTA and reel compartment sides Load rating / testing of the reels UTA support structure and rigging attachment points Routing and anchorage of the umbilical Positioning of bend stiffeners or limiters and anchorage, with particular attention to long term bending of bend stiffeners Design of rigging considering dynamic and rotational acceleration Clearance of the umbilical and UTA from reel rim and driving system 2nd end hold back anchorage of the UTA and umbilical or cable, with particular attention of both tension and compression of the umbilical or cable at the point of partition cross over Environmental protection of partially dis-assembled equipment Accessibility to install and use pressure & electrical monitoring equipment Reel weight distribution Radial offset weight balance of the reel for lifting and rotation Reel lifting beam / rigging offset loading Packaging of removed equipment i.e. ROV grab bars, dummy connectors etc Drawings and procedures Reel and Drive System Reels shall be sized for the total weight of the umbilical, UTA (s) and all ancillary equipment, the designer should also consider the following: Load distribution of product on the reel and lifting equipment, to ensure compliance with the reel load / test certification Un-even balance Drive system, where under rollers may extend beyond the inner edge of the reel rim Low support structures, where access may be limited due to reel support cradles Structural strength of the rigging points Not welding rigging points to critical structural members of the reel Document1, 31 August 2015 36 UTA Support Structure The UTA support structure should be designed with consideration to the following and the prevailing offshore lifting standard and certification requirements: The structure should be easy to install and ideally adaptable to allow for a UTA loading tolerance Ideally the structure should be designed and positioned to remove the need for disassembly offshore If removal is required offshore, adequate lifting points should be provided and component weights marked If the structure has to be welded in position after the UTA is positioned, adequate protection should be used to prevent damage to the UTA and umbilical Rigging Equipment All rigging equipment should be designed to prevailing offshore lifting standard and certification requirements and consideration of the following: Dynamic loading of the rigging and pad eyes Generally chain falls (chain block hoists) are the preferred lifting / lowering system offshore, this allows the deck crew to work at deck level and clear of the descending UTA Ratchet lever hoists are generally used to rig fore and aft of the UTA Once installed chain falls and ratchet lever hoists should have chain lockers attached to secure Long term effect of high grade steel rigging in an offshore environmental Umbilical Routing The routing of the umbilical should consider the following: Maintaining the MBR Preventing damage to the outer sheath or roving from chafing, axial moment or over tightening of the securing system Stored energy in umbilical or cable when released Future intervention, removal and decommissioning should be considered when considering the routing of the umbilical Bend Stiffeners Consideration shall be given to the amount of bending the bend stiffener is subjected to and the duration; typically to prevent a permanent set a bend stiffener should not be bent for more than the maximum period specified by the manufacturer. As a rule thumb the bend stiffener should not be bent more than a 1/3 of its length for packing purposes, in all cases the bend stiffener manufacturer must advise the amount of bend vs. duration. Document1, 31 August 2015 37 Monitoring Systems Monitoring systems used for shipping and or installation lay should have good access for installation of the equipment and monitoring. When used for shipping the monitoring part of the system should be positioned at ground / deck level to provide easy access on route. Document1, 31 August 2015 38 Appendix B: Fault tree analysis (FTA) FTA is one of the most widely used methods in system reliability, maintainability and safety analysis. The main drivers for using FTA are to be able to conduct a thorough examination the factors which may lead to a system failure or accident. The process identifies the causes of a failure, to identify the weakness in a system, to prioritize contributors to failure, to identify effective upgrades to a system, to quantify the failure probability and contributors, and to optimize tests and maintenances. FTA is a deductive technique where users start with a specified system failure or an accident, known as the top event of the fault tree. The immediate causal events A1, A2, … that, either alone or in combination, may lead to the top event are identified and connected to the top even through a logic gate. Next, all potential causal events Ai,1, Ai,2, … that may lead to event Ai for i = 1, 2, 3, … are identified. These events are connected to event Ai through a logic gate. This procedure is continued deductively until a suitable level of detail is reached. The events on the lowest level are called the basic events of the fault tree. The 1st FTA (Figure 18) demonstrates that “sea state” event and the undeveloped “SUT size” contribute to increase project costs. The 2nd FTA (Figure 19) develops the “SUT size” and mentions a number of contributory factors to the size of the SUT. Document1, 31 August 2015 39 FTA - project costs Operator point of view Increased project realization time Increased installation time Limited installation window Sea state Heavy / large vessels Large reels / caroussels / lifting equipment Decreased vessel availability Heavy / large vessels Increased material handling time Decreased vessel availability Manufacturing / Equipment Large reels / caroussels / lifting equipment Health & safety issues Personnel safety Large / long umbilicals Document1, & 8 October 2013 SUT 40 Repair of complex equipment damaged Supply: vessel, cranes, etc Excessive # of hours Technical risks Components costs Sea state Large reels / caroussels / lifting equipment Sea state Large / long umbilicals & SUT Increased material handling time Engineering Large / long umbilicals & SUT Large reels / caroussels / lifting equipment Large / long umbilicals & SUT Time to soucre, specify Large / long umbilicals & SUT Quantity / complexity of components Large / long umbilicals & SUT Large / long umbilicals & SUT Figure 18: FTA step one Large / long umbilicals & SUT Excessive # of functions / interfaces Over engineering Personnel experience / training Specifications lacking or not followed or excessive Lack of industry standardisation Missing field return reliability data Maximum # of functions / interface per umbilical / SUT not defined Figure 19: FTA step two The FTA methodology has been chosen to give an indication of an analytical approach that could be used to gain a better understanding of the risks and consequences of excessive size of UTAs. The choice of using FTA was driven by the following factors. FTA is specified in a number of reliability related manuals, such as US ARMY HEADQUARTERS Design for Reliability Guide (1976), each investigative method (FMEA, FTA, RBD, etc) will identify measures to be taken into account to enhance reliability, safety or other probabilistic features. FMEA analysis, for example, is well adapted to “evaluate individual component failures”. Our choice to use Fault Tree Analysis (FTA) method was motivated by the fact that “FTA is thus the appropriate analysis to carry out if a given undesired event is defined and the goal is to determine its basic causes”, NASA Fault Tree Handbook with Aerospace Applications, 2002. Hence, FTA is fit to analyze multiple causes and effects. Some important considerations for using the FTA method have been outlined below. Our approach was to remain superficial and not to dive into design and/or engineering considerations potentially overlapping with project requirements, specifications, supplier experience, design intent, etc. The FTA presented aims at demonstrating that SUT size and minimal design considerations can influence significantly project costs and timespan. Publishing the complete FTA seemed irrelevant as it would generate interest away from the objectives set forth. Serious considerations have to be taken during the design and/or engineering phases as typically 5% of the life cycle costs have been spent at those stages, but typically 85% of the life cycle costs are determined then, Reliability and Maintainability Guideline for Manufacturing Machinery and Equipment, (1999). o Life cycle costs (LCC) refer to the total cost to the customer, both sunk and anticipated, of acquisition and ownership of an item over its useful life, as defined by IAQG. It includes the cost of research, development, test & evaluation; procurement (to include production testing, deployment, support to operational test & evaluation); operations & support (to include training); customer facilities; and disposal. Life Cycle Cost is also called Total Ownership Cost (TOC). Our purpose here was to evaluate scenarios probability values but to identify major contributions to increased installation costs. Appendix C: STI and SUT length calculations Equation 1 Case A: Maximum permissible STI length = LSTI (For a UTA with a front pad eye length that equals ½ the UTA height) 𝐿𝑆𝑇𝐼 ∶= (√(𝑅𝑅 − 𝑀𝐵𝑅 − 𝐹𝐵𝐶 + ( 𝐷𝑝𝑟𝑜𝑑 2 ) − (𝐻1 − 𝑀𝐵𝑅)2 ) + (√(𝑅𝑅 − 𝐹𝐵𝐶)2 − 𝐻1 2 ) − 𝐿𝑈𝑇𝐴 2 ) Case B: Maximum permissible STI length = LSTI (For a UTA with no front pad eye or a pad eye length less than ½ the UTA height) 𝐿𝑆𝑇𝐼 ∶= (√(𝑅𝑅 − 𝑀𝐵𝑅 − 𝐹𝐵𝐶 + ( 𝐷𝑝𝑟𝑜𝑑 2 𝐻𝑈𝑇𝐴 ) − (𝐻1 − 𝑀𝐵𝑅)2 ) + (√(𝑅𝑅 − 𝐹𝐵𝐶)2 − 𝐻1 2 ) − (𝐿𝑈𝑇𝐴 + ) 2 2 ) Where: RR = reel rim radius (m) RB = reel barrel radius (m) FBC = free board clearance (m) LUTA = length of UTA including pad eye (m) HUTA = overall height of UTA (m) Dprod = diameter of product (umbilical or cable) (m) MBR = minimum bend radius of product (umbilical or cable) (m) Hrig = height of support rigging between barrel & UTA (m) H1 =distance between reel centre to UTA centreline (m) H1 ∶= R B + Hrig + ( Document1, March 2015 HUTA 2 ) 42 Umbilical or cable length calculator Total storage capacity (m) of umbilical or cable to be placed in bay (B), see figure 12 Equation 3 𝐿𝑝𝑟𝑜𝑑 ∶= (𝑘1 ∗ 𝑘2 ∗ 𝜋 ∗ (𝐷𝑏 + 𝑘2 ∗ 𝐷𝑝𝑟𝑜𝑑 )) ∗ 𝑘3 Where: Lprod = total length of product (umbilical or cable (m) Dprod = diameter of product (umbilical or cable) (m) FBC = free board clearance (m) Df = reel flange diameter (m) Db = barrel diameter (m) Wt = reel traverse width Wp = partition width (m) WUTA = maximum width of UTA (m) Wc = UTA to reel clearance (each side) (m) k1 = width fill factor (unit less) 𝑘1 ∶= 𝑟𝑜𝑢𝑛𝑑 ( (𝑊𝑡 −(𝑊𝑈𝑇𝐴 +𝑊𝑃 +𝑊𝑐 ∗2)) 𝐷𝑝𝑟𝑜𝑑 , 0) k2 = height fill factor (unit less) ( 𝑘2 ∶= 𝑟𝑜𝑢𝑛𝑑 ( (𝐷𝑓−2∗𝐹𝐵𝐶)−𝐷 ) 𝑏 ) 2 𝐷𝑝𝑟𝑜𝑑 , 0) k3 = product fill factor (%) (Typically 80%) Figure 23 shows an illustration of storage of umbilical or cable placed in a bay. Document1, March 2015 43 Appendix D: Steel tube Umbilical or Thermoplastic Umbilical with spool The details of design and installation of different types of umbilical have been described in API17E and API17I. Figure 20 and Figure 21 shows the Steel tube and the Thermoplastic Umbilical. Figure 20: Steel tube Umbilical or Thermoplastic Umbilical with spool Figure 21: Thermoplastic Umbilical The calculation of rigid length depends if a bend stiffener or a bend restrictor is connected with the STI. Figure 22 shows the rigid length when a bend stiffener is used. As described in section 3.1.3, the rigid length will differ in other cases depending on if the SUT is connected with either a bend stiffener or a bend restrictor, or none of them. Document1, March 2015 44 Figure 22: Calculation of rigid length (handling) Document1, March 2015 45 Appendix E: False Barrel Diameter calculations The false barrel build up diameter required (see Figure 14 & Figure 20) to maintain the umbilical manufacturer’s stated MBR (Equation 4) 𝐷𝐵 ∶= (𝑀𝐵𝑅 ∗ 2 − 𝐻1 ) ∗ 2 + 𝐷𝑝𝑟𝑜𝑑 DB = false barrel diameter RB = reel barrel radius (m) HUTA = overall height of UTA (m) Dprod = diameter of product (umbilical or cable) (m) MBR = minimum bend radius of product (umbilical or cable) (m) Hrig = height of support rigging between barrel & UTA (m) H1 =distance between reel centre to UTA centreline (m) H1 ∶= R B + Hrig + ( Document1, March 2015 HUTA 2 ) 46 Figure 23: Storage of umbilical or cable placed in a bay Document1, March 2015 47 Appendix F: Responsibility Matrix (informative) The responsibility matrix on next page includes the typical roles and responsibilities of multiple parties involved in the design, development, manufacture and installation of UTAs. The matrix is for informative purpose and can be used through the field planning and development phase. Document1, March 2015 48 Typical Umbilical System Design, Manufacturing and Installation Roles Activity Operator Umbilical UTA Manufacturer Manufacturer Umbilical Establishes and The Umbilical The UTA System monitors Manufacturer is Manufacturer Requirements communication presented with is presented between the umbilical the Umbilical with the and UTA System Umbilical manufacturers. configuration. System Transmits Umbilical configuration. System configuration, functional and operational requirements. Umbilical Establishes and Design Umbilical The UTA System monitors Bundle, Manufacturer Configuration communication Structural and is provided the between the umbilical Mechanical Umbilical and UTA Interfaces to the configuration. manufacturers. UTA to meet Approve the design project solution and requirements. manufacturing process. UTA Design Establishes and monitors communication between the umbilical and UTA manufacturers. Approve the design solution and manufacturing process. Takes ownership of the equipment designed and manufactured in compliance with the project technical requirements. Review the UTA design and provide feedback to operator and UTA Manufacturer. Design UTA to accommodate interfaces to the Umbilical Bundle and meet project requirements transmitted. Coordinates with the operator the acceptance activities of the equipment manufactured. Coordinates with the operator the acceptance activities of the equipment manufactured. Umbilical Bundle & UTA Assembly Process & FAT N/A N/A Umbilical Bundle & UTA SIT Establishes the Site Integration test requirements, issues the Test Specification and is responsible for coordinating all Assemble the Umbilical bundle to the UTA in accordance with the project requirements. Supports the SIT activities and can provide labour and resources. Umbilical Bundle & UTA Components Document1, March 2015 Supports the SIT activities and can provide labour and resources. UTA Installer N/A The Installer is presented with the Umbilical System configuration and properties for review and comments from Installation Perspective to ensure configuration is installable. The Installer is to be informed about design parameters and layout/ interfaces of the UTA. The Installer witnesses the acceptance activities where practicable and is made aware of any technical issues associated with the components to assess installation implications. N/A The Installer witnesses the acceptance activities where practicable and is made aware of any 49 activities. Umbilical System Assembly Post Load Out Takes ownership of the equipment designed and manufactured in compliance with the project technical requirements. Coordinates with the Oil Field Developer and acceptance activities of the equipment manufactured. N/A Installation Takes ownership of the equipment designed and manufactured in compliance with the project technical requirements and free issues where appropriate to Installer and monitors where appropriate via manufacturers installation activities in accordance with class design requirements. Will also include post installation tests. Takes ownership of the post installation activity and verification of functionality prior to systems start up. Coordinates with the Installer the acceptance activities of the equipment manufactured in accordance with Oil Field / Company requirements. Coordinates with the Installer the acceptance activities of the equipment manufactured in accordance with Oil Field / Company requirements. Supports the commissioning activity and can provide labour and resources. Supports the commissioning activity and can provide labour and resources. System Commissioning Document1, March 2015 technical issues arisen during SIT to assess installation implications and for warranty. Takes custody of the designed, manufactured and tested equipment in compliance with the Oil Field Operators project technical requirements and installs items in line with installation design criteria. Takes custody of the designed, manufactured and tested equipment in compliance with the Oil Field Operators project technical requirements and installs items in line with installation design criteria. Supports the commissioning activity. 50
© Copyright 2026 Paperzz